ID Task Mode Task Name Duration Start Finish 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
0 Residential 152 days Thu 5/11/17 Fri 12/8/17
1 Construction
General Conditions 21 days Thu 5/11/17 Thu 6/8/17
2 Finalize plans and 20 days Thu 5/11/17 Wed 6/7/17 General contractor[50%],Architect[50%],Owner[12%],Mortgage
3 develop
Sign estimate
contract and 1 day Thu 6/8/17 Thu 6/8/17 General contractor,Architect,Owner,Mortgage lender
4 notice for
Apply to proceed
Permits 0 days Thu 6/8/17 Thu 6/8/17 6/8
5 Secure foundation 0 days Thu 6/8/17 Thu 6/8/17 6/8
6 permit
Secure framing 0 days Thu 6/8/17 Thu 6/8/17 6/8
7 permit
Secure electrical 0 days Thu 6/8/17 Thu 6/8/17 6/8
8 permit
Secure plumbing 0 days Thu 6/8/17 Thu 6/8/17 6/8
9 permit
Secure HVAC 0 days Thu 6/8/17 Thu 6/8/17 6/8
10 permit
Secure 0 days Thu 6/8/17 Thu 6/8/17 6/8
11 miscellaneous
Site Work 3 days Fri 6/9/17 Tue 6/13/17
12 Clear and grub lot 1 day Fri 6/9/17 Fri 6/9/17 Site excavation contractor
13 Install temporary 1 day Mon 6/12/17 Mon 6/12/17 Electric company
14 power underground
Install service 1 day Tue 6/13/17 Tue 6/13/17 Electric contractor,Plumbing contractor
15 utilities
Foundation 42 days Wed 6/14/17 Thu 8/10/17
16 Excavate for 3 days Wed 6/14/17 Fri 6/16/17 Site excavation contractor
17 foundations
Form basement 13 days Mon 6/19/17 Wed 7/5/17 Concrete contractor
18 walls
Place concrete for 12 days Thu 7/6/17 Fri 7/21/17 Concrete contractor
19 foundations
Cure basement& walls 7 days Mon 7/24/17 Tue 8/1/17
20 for
Strip7 basement
days wall 2 days Wed 8/2/17 Thu 8/3/17 Concrete contractor
21 forms
Waterproof/insulate 2 days Fri 8/4/17 Mon 8/7/17 Concrete contractor
22 basementfoundation
Perform walls 1 day Tue 8/8/17 Tue 8/8/17 Inspector
inspection
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Mode Task Name Duration Start Finish 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
23 Backfill foundation 2 days Wed 8/9/17 Thu 8/10/17 Site excavation contractor
24 Framing 22 days Fri 8/11/17 Mon 9/11/17
25 Install 1st floor joists 2 days Fri 8/11/17 Mon 8/14/17 Framing contractor
26 Lay 1st floor decking 2 days Tue 8/15/17 Wed 8/16/17 Framing contractor
27 Frame 1st floor walls 4 days Thu 8/17/17 Tue 8/22/17 Framing contractor
28 Frame 1st floor 1 day Wed 8/23/17 Wed 8/23/17 Framing contractor
29 corners
Install 2nd floor 2 days Thu 8/24/17 Fri 8/25/17 Framing contractor
30 joists
Frame 2nd floor 2 days Mon 8/28/17 Tue 8/29/17 Framing contractor
31 decking
Frame 2nd floor 3 days Wed 8/30/17 Fri 9/1/17 Framing contractor
32 walls
Frame 2nd floor 2 days Mon 9/4/17 Tue 9/5/17 Framing contractor
33 corners
Complete roof 3 days Wed 9/6/17 Fri 9/8/17 Framing contractor
34 framing framing
Conduct 1 day Mon 9/11/17 Mon 9/11/17 Inspector
35 Dryinspection
In 22 days Mon 9/11/17 Tue 10/10/17
36 Install 1st floor 3 days Tue 9/12/17 Thu 9/14/17 Framing contractor
37 sheathing
Install 2nd floor 3 days Fri 9/15/17 Tue 9/19/17 Framing contractor
38 sheathing
Install roof decking 3 days Mon 9/11/17 Wed 9/13/17 Framing contractor
39 Install felt, flashing 3 days Wed 9/27/17 Fri 9/29/17 Roofing contractor
40 and
Hangshingles
1st floor 1 day Mon 10/2/17 Mon 10/2/17 Framing contractor
41 exterior
Install 1stdoors
floor 3 days Tue 10/3/17 Thu 10/5/17 Framing contractor
42 windows
Install 2nd floor 3 days Fri 10/6/17 Tue 10/10/17 Framing contractor
43 windows
Exterior Finishes 19 days Wed 10/11/17Mon 11/6/17
44 Complete exterior 16 days Wed Wed 11/1/17 Masonry contractor
45 brick
Complete exterior 3 days 10/11/17
Thu 11/2/17 Mon 11/6/17 Framing contractor
siding
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Mode Task Name Duration Start Finish 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
46 Utility Rough-B97Ins 21 days Thu 9/14/17 Thu 10/12/17
47 and Complete
Rough-in plumbing 5 days Wed 9/20/17 Tue 9/26/17 Plumbing contractor
48 Conduct rough-in 1 day Wed 9/27/17 Wed 9/27/17 Inspector
49 plumbing
Place inspection
concrete for 11 days Thu 9/28/17 Thu 10/12/17 Concrete contractor
50 basementelectrical
Rough-in floor 5 days Wed 9/20/17 Tue 9/26/17 Electric contractor
51 Conduct rough-in 1 day Wed 9/27/17 Wed 9/27/17 Inspector
52 electrical inspection
Rough-in HVAC 3 days Thu 9/28/17 Mon 10/2/17 Heating and AC contractor
53 Conduct rough-in 1 day Tue 10/3/17 Tue 10/3/17 Inspector
54 HVAC inspection
Rough-in 2 days Thu 9/14/17 Fri 9/15/17 Electric contractor
55 communication
Interior Finishes - 30 days Wed 10/11/17Tue 11/21/17
56 Insulation 11 days Wed 10/11/17Wed 10/25/17
57 Place wall 1 day Wed Wed Insulation contractor
58 insulation
Place wall - 1st 1 day 10/11/17
Thu 10/11/17
10/12/17 Thu 10/12/17 Insulation contractor
59 insulation
Place - 2nd
ceiling 1 day Tue 10/24/17 Tue 10/24/17 Insulation contractor
60 insulationinsulation
Conduct - 2nd 1 day Wed Wed Inspector
61 inspection
Drywall 9 days 10/25/17
Thu 10/25/17
10/12/17 Tue 10/24/17
62 Install drywall - 2 days Thu 10/12/17 Fri 10/13/17 Drywall contractor
63 1st floor walls
Install drywall - 2 days Mon Tue 10/17/17 Drywall contractor
64 1st floor overhead
Install drywall 2nd 2 days 10/16/17
Wed Thu 10/19/17 Drywall contractor
65 floor
Installwalls
drywall 2nd 2 days 10/18/17
Fri 10/20/17 Mon Drywall contractor
66 floor overhead
Tape and float 1st 1 day Wed 10/23/17
Wed Drywall contractor
67 floor drywall
Tape and float 2nd 1 day 10/18/17
Tue 10/18/17
10/24/17 Tue 10/24/17 Drywall contractor
68 floor
Paint drywall
and Wallpaper 17 days Thu 10/19/17 Fri 11/10/17
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Mode Task Name Duration Start Finish 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
69 Texture all except 1 day Thu 10/19/17 Thu 10/19/17 Painting contractor
70 entry all
Paint andexcept
kitchen 1 day Fri 10/20/17 Fri 10/20/17 Painting contractor
71 entry wallpaper
Hang and kitchen 1 day Mon Mon Painting contractor
72 entry and
Texture allkitchen
- 2nd 1 day 10/23/17
Fri 10/23/17
10/20/17 Fri 10/20/17 Painting contractor
73 floor
Paint all - 2nd 1 day Mon Mon Painting contractor
74 floor
Paint exterior 4 days 10/23/17
Tue 11/7/17 10/23/17
Fri 11/10/17 Painting contractor
75 siding & trim work
Cabinets 6 days Tue 10/24/17 Tue 10/31/17
76 Install 1st floor - 2 days Tue 10/24/17 Wed Finish carpentry contractor
77 kitchen cabinets
Install 1st floor - 1 day Thu 10/26/17 10/25/17
Thu 10/26/17 Finish carpentry contractor
78 master bath and- 1 day
Install 2nd floor Fri 10/27/17 Fri 10/27/17 Finish carpentry contractor
79 hall bath
Install andrails, 2 days
chair Mon Tue 10/31/17 Finish carpentry contractor
80 crown
Finish moldings, 6 days
Plumbing 10/30/17
Thu 10/26/17 Thu 11/2/17
81 Complete 1st floor 1 day Thu 10/26/17 Thu 10/26/17 Plumbing contractor
82 - kitchen plumbing
Complete 1st floor 2 days Fri 10/27/17 Mon Plumbing contractor
83 - master bath
Complete 2ndand 2 days 10/30/17
Tue 10/31/17 Wed 11/1/17 Plumbing contractor
84 floor - hall
Conduct bath
finish 1 day Thu 11/2/17 Thu 11/2/17 Inspector
85 plumbing
Finish Electrical 3 days Thu 11/2/17 Mon 11/6/17
86 Complete 1st floor 1 day Thu 11/2/17 Thu 11/2/17 Electric contractor
87 circuits
Complete to 2nd
service 1 day Fri 11/3/17 Fri 11/3/17 Electric contractor
88 floor circuits
Conduct finishto 1 day Mon 11/6/17 Mon 11/6/17 Inspector
89 electrical
Complete 2 days Fri 11/3/17 Mon 11/6/17 Electric contractor
90 communications
Finish HVAC 3 days Tue 11/7/17 Thu 11/9/17
91 Complete 1st floor 1 day Tue 11/7/17 Tue 11/7/17 Heating and AC contractor
- zone 1 HVAC
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Mode Task Name Duration Start Finish 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
92 Complete 2nd 1 day Wed 11/8/17 Wed 11/8/17 Heating and AC contractor
93 floor - zone
Conduct HVAC 2 1 day Thu 11/9/17 Thu 11/9/17 Inspector
94 inspection
Carpet, Tile and 8 days Fri 11/10/17 Tue 11/21/17
95 Appliances
Tile entry, kitchen 3 days Fri 11/10/17 Tue 11/14/17 Flooring contractor
96 and baths
Carpet 1st floor 2 days Wed Thu 11/16/17 Flooring contractor
97 Carpet 2nd floor 2 days 11/15/17
Fri 11/17/17 Mon Flooring contractor
98 Install appliances 1 day Tue 11/21/17 11/20/17
Tue 11/21/17 Appliance contractor
99 Landscaping and 12 days Mon Tue 11/28/17
100 Grounds Work
Pour concrete 2 days 11/13/17
Mon Tue 11/14/17 Concrete contractor
101 driveway and
Install backyard 2 days 11/13/17
Wed Thu 11/23/17 Fencing contractor
102 fence
Sod and complete 2 days 11/22/17
Fri 11/24/17 Mon Landscape contractor
103 plantings
Sod - front yard 1 day
and complete 11/27/17
Tue 11/28/17 Tue 11/28/17 Landscape contractor
104 plantings
Final - backyard 8 days
Acceptance Wed 11/29/17Fri 12/8/17
105 Complete final 1 day Wed Wed Inspector
106 inspection
Cleanup forfor 1 day 11/29/17
Thu 11/29/17
11/30/17 Thu 11/30/17 Maid service
107 occupancy
Perform final 1 day Fri 12/1/17 Fri 12/1/17 Owner
108 walk-through
Complete punch list 5 days Mon 12/4/17 Fri 12/8/17 General contractor
items

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Residential Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5