TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
10.4 Appendix -4: Emergency Contact Number 80
1. INTRODUCTION
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur, is initiated by the
Government of Malaysia. The project owner for this project is Jabatan Pengairan Dan Saliran
Malaysia. Furthermore, Perunding Azman,Ooi & Rao Sdn Bhd leads to be Consultant. To ensure
successful implementation of the works, Gaya Analisa Sdn Bhd has been appointed as a main
contractor.
To implement this project in an orderly manner and in accordance with the contractors schedule where it
involves the current traffic, the main contractor has appointed T&D Consult Sdn Bhd as the Traffic
Management Consultant and implement Traffic Management of Wilayah Persekutuan Kuala Lumpur,
Flood Mitigation Planning of Sungai Bunus.
Our call is specifically to come out with a Traffic Management concept during construction tenure prior to
commencement of work and some measure to divert traffic flow as well as providing safety
measurement between public road users and the construction personnel in construction vicinity. For this
2
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
arrangement, specified materials and equipment will include such as signage, barrier and other devices
which is to be complied by authority requirement. T&D Consult Sdn Bhd will develop and plan the traffic
diversion and providing traffic safety measurement during construction.
2. EXECUTIVE SUMMARY
The main objective of this technical proposal is to Plan, Design and Implement comprehensive Traffic
Management Scheme which consists of several sections and zones. We will ensure that the TMS
designed for Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur is
tailored to Gaya Analisa Sdn Bhd contractor construction program and method as well as compliance
to the relevant authority requirements.
1 Planning, designing, and submit Traffic Management Plan to the Local Authorities / agencies
involved (City Hall) for approval and authorization before work has done.
2 Supply and install the standard traffic safety devices.
3 Implement and oversee the approved Traffic Management Plan
3
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
A major factor emphasis in Traffic Management Plan is the safety for all road users especially
motorcyclists, in general, traffic operators and construction workers who will directly involve the
construction work as well as to the public.
3. OBJECTIVE
1 Carry out maintenance devices, installation temporary signage, lighting sources such
as 'blinkers', 'string delineator', reflective sticker to ensure safety for road users.
4
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
2 Monitoring the work carrying out efficient and effective traffic management schemes
such 'Road Diversion', 'Lane Closure and Traffic Control' in line with essential for
construction work.
3 Announcement and Information to road users, local residents, authorities regarding
work plan, traffic congestion, road closures, accident, natural disasters and
emergency that can occur on site through notification signage, media and electronic
media.
4 Provide effective management system, such as (permit to work) for ongoing work
activity.
Due to high capacity of traffic flow on the working area especially in Kuala Lumpur and
prior to the commencement of the construction works, a proper traffic management will be
carried out to divert the traffic in order to provide a sufficient safety around work area. The
Traffic Management Plan will be implemented accordingly to the construction schedule
and subjected to authority requirement.
To implement Traffic Management Plan of Flood Mitigation Planning of Sungai Bunus,
Wilayah Persekutuan Kuala Lumpur. Wilayah Persekutuan Kuala Lumpur, Construction
and Completion Of Flood Diversion and Associated Works it will be divided into two (2)
main stages as follows:
The overall stages are covering the entire construction activities that will be undertaken
during construction. Aspects of safety for road users and construction workers have been
5
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
taken into account in the preparation of the proposed Traffic Management Scheme.
During construction period, work will be performed for each closure installation of warning
signboards, barrier, blinker and string delineator.
1 STAGE 1
The construction work in first stage, the work focused on Jalan Tun Razak, Jalan
Raja Muda Abdul Aziz, Jalan Raja Uda and road Haji Salleh. The work will be
carried out in this area will use the Open Cut method. At this stage, Jalan Raja
Uda and Jalan Haji Salleh will be closed to the user to make way for the work to
be carried out. Work-job using the pipe jacking method will be carried out in areas
dealing Perkeso Towers and Menara TH Selborn across Jalan Raja Muda Avdul
Aziz. At this stage, the construction work while railing to The Orion Condominium
will also be undertaken to facilitate work in the next stage.
To ensure that the work can be carried out successfully with optimum safety in the
vicinity of the work, all safety equipment and traffic warning signboard will be
placed at the site to warn road users to be more careful when approaching the
work area.
2 STAGE 2
The situation in second stage, the construction work is still ongoing. It is more
focused on the construction of a new bridge in front of Menara TH Selborn, Jax
Box Tunneling works across AKLEH with Pipe Jacking works across Jalan Raja
Muda Abdul Aziz. The road was closed on previous stages have been opened to
the user. However, routes of Jalan Haji Sirat and Menara TH Selborn routes to
6
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
The Orion Condominium where access to Jalan Tun Razak road to be closed.
Hence, users are advised to use other alternatives to Jalan Tun Razak and refer
the signboard that had been installed.
All equipment and traffic safety warning signboard, "plastic barrier with hoarding"
will be placed on site to warn road users to be more careful when approaching the
work area.
4. PROJECT BRIEF
About Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Sungai Bunus is one of the catchment areas of 17 km. The construction and completion bonus flood
diversion in the river is one of the flood mitigation project designs, in regions kuala lumpur. It is
concentrated in the area where Jalan Tun Razak area is always faced with the problem of flash floods.
This project aims to increase the level of flood protection for a period of 20-30 years.
8
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
2. PROJECT INFORMATION
9
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
(Kementerian Sumber Asli Dan Alam Sekitar)
10
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
13
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
6.
WORK PROGRESS &TRAFFIC MANAGEMENT SCHEME (MONTH: FEBRUARY 2015)
zone 1 Ongoing works of bore pile 1 Sand Bag and geotextile installed
work. at proper placed.
(In Front Th
Selborn) 2 Provide suitable taper (plastic
barrier, hoarding and con) base
on TMP plan for road closure in
front TH Selborn building.
14
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
been closed.
15
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
2 Provide suitable taper for heavy
machine whenever enter work
area zone.
Zone 4 Ongoing works of Excavation 1 Barricade the micro pile area with
and micro pile. the warning tape.
16
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
9 Signboards installed at proper
spaces.
17
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
(In Front mechanical and electrical. 11 Advance warning and information
signboards installed at proper
TH SELBORN)
spaces.
Zone 4 Ongoing works of Excavation 3 Barricade the micro pile area with
and micro pile. the warning tape.
18
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
19
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
20
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
9 Barricade with plastic barrier in
front PERKESO.
Zone 4 Ongoing works of Excavation 4 Barricade the micro pile area with
and micro pile. the warning tape.
Quantity
No Description Unit
BQ Supply Used Service Damage Lost
21
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
B Traffic devices
22
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
10 Arrow left F nos 11 9 - - -
23 No entry W nos - - - - -
24 T-junction X nos - - - - -
25 Others nos 16 16 4 - - -
23
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
9 Speed limit 80km/h d nos
12 No entry l nos
E A-shape signboards
1 PembinaanMula nos
Pembinaantamat nos
24
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
Note:
1 Signboard legends such A, B, C, etc. are referred from specified TMP drawings.
Quantity
No Description Unit
BQ Supply Used Service Damage Lost
B Traffic devices
26
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
17 Chevron left P nos
23 No entry W nos - - - - -
24 T-junction X nos - - - - -
25 Others nos 16 16 14 - - -
12 No entry l nos
27
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
16 Right lane narrow ahead 100m p nos
E A-shape signboards
1 PembinaanMula nos
Pembinaantamat nos
Note:
1 Signboard legends such A, B, C, etc. are referred from specified TMP drawings.
28
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
Quantity
No Description Unit
BQ Supply Used Service Damage Lost
B Traffic devices
29
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
14 Robotic flagman set - - - - -
23 No entry W nos - - - - -
30
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
24 T-junction X nos - - - - -
25 Others nos 16 16 14 - - -
12 No entry l nos
E A-shape signboards
31
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
1 PembinaanMula nos
Pembinaantamat nos
Note:
1 Signboard legends such A, B, C, etc. are referred from specified TMP drawings.
1. ACCIDENT DETAILS
Damages of Traffic
Date / Time Weather Accident Details Location
Equipment etc
32
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
2. VEHICLE BREAKDOWN
Damage of
Vehicle Breakdown
Date / Time Weather Location Traffic
Details
Equipment etc.
33
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
3. ACCIDENT DETAILS
Damages of Traffic
Date / Time Weather Accident Details Location
Equipment etc
4. VEHICLE BREAKDOWN
Damage of
Vehicle Breakdown
Date / Time Weather Location Traffic
Details
Equipment etc.
34
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
No Date / Time Accident Vehicle Breakdown Remark
5. ACCIDENT DETAILS
Damages of Traffic
Date / Time Weather Accident Details Location
Equipment etc
Nil
6. VEHICLE BREAKDOWN
Damage of
Vehicle Breakdown
Date / Time Weather Location Traffic
Details
Equipment etc.
Prepared by;
9. SUMMARY
To minimize disruption to road users, the traffic controller are placed at ingress / egress of parking area.
In addition, not only maintenance but also additional devices are conducted from time to time according
to the activities on site. Necessary warning to motorist was made regarding site condition.
1 Increase the traffic controller quantity and other traffic devices such as blinker, string delineator,
etc.
2 Increase patrolling frequent in the area and careful maintenance to ensure all traffic safety
materials to be clean and proper position.
3 Water filled up into barriers and keep in nice alignment, installation at proper spaces to reduce
risk of accident and traffic congestion.
10. APPENDIX
36
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
1. APPENDIX -1: TRAFFIC MANAGEMENT PLAN
1 PPL/JPS/PAOR/GA/SGB/02
37
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
2 PPL/JPS/PAOR/GA/SGB/03
38
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
3 PPL/JPS/PAOR/GA/SGB/04
39
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
2. APPENDIX -2:
SITE ACTIVITY PHOTO OF TRAFFIC MANAGEMENT
(MONTH: FEBRUARY 2015)
40
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
41
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
42
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
43
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
44
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
45
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
46
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
47
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
48
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
49
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
50
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
51
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
52
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
53
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
54
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
55
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
56
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
57
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
58
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
59
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
60
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
61
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
62
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
63
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
64
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
65
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
66
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
67
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
68
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
69
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
70
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
71
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
72
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
73
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
74
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
75
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
76
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
77
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
78
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
79
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
80
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
81
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
82
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
83
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
10.3 APPENDIX-3:
OPERATION SCHEDULE FOREMERGENCY RESPONSE TEAM
84
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
1 APPENDIX-4:
EMERGENCY CONTACT NUMBERS
85
Traffic Management Officer, T&D Sdn Bhd, Oon Bin Mohd Nor 014-800 4991
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
2 APPENDIX-4:
TEMPORARY SIGNBOARD FOR CONSTRUCTION ACTIVITY
86
TRAFFIC MANAGEMENT MONTHLY REPORT FEBRUARY - APRIL 2015
Flood Mitigation Planning of Sungai Bunus, Wilayah Persekutuan Kuala Lumpur
Construction and Completion Of Flood Diversion and Associated Works, Wilayah Persekutuan
Kuala Lumpur
==================================================
===========================
87