You are on page 1of 6

2011 IEEE Colloquium on Humanities, Science and Engineering Research (CHUSER 2011), Dec 5-6 2011, Penang

Application of Lean Model to Reduce Waste of Time


in Construction
Case study of concreting task in Malaysia

*Ali Lajevardi, **Intan Rohani Endut and **Soleyman Paydar


*Faculty of Civil Engineering, Universiti Teknologi MARA, Shah Alam, Malaysia
**Malaysia Institute of Transportation (MITRANS), Universiti Teknologi MARA, Shah Alam, Malaysia
ali.la81@yahoo.com

Abstract This paper is a case study in order to evaluate the the use of newer project delivery systems and concepts in
result of implementing the relatively new productivity construction projects and as a result considerable elimination of
management approach lean production in local construction time-related wastage was measured [5] [6].
industry of Malaysia in order to achieve better project outcome.
Delay in project delivery is a major issue of concern for In this effort, one of the concepts which were introduced to
managers of construction projects. Traditionally the the construction industry in the recent decades is lean
management tried to put effort to decrease construction task time production system. Since the manufacturing industry has
by increasing resources to reduce duration of process activities. always been a source of new ideas and concepts for the
However the objective of lean concept is to avoid project delay by construction industry, the lean concept was introduced to
looking to the whole construction tasks rather than what is called construction industry after being successfully implemented in
activity based thinking. This research analyzes a case study of manufacturing industry [7]. What was later commonly called
concreting task by initially identifying activities that contribute to lean construction, was adopted by researchers as a new
the waste of time and then determining the amount of those approach toward construction project delivery system and
activities. aimed to better fulfill customers needs, while using the
resources at minimum [8]. The objectives of lean construction
Keywords: lean construction, time waste, construction are to generate value to the final customer (client) and
management, value creation, Malaysia construction, project delay
eventually to eliminate the factors that do not add any value
and are considered as waste [5]. Waste in construction and
I. INTRODUCTION manufacturing industry actually comes from the same old
activity based thinking in which reduction of cost and duration
Despite many management efforts, construction industry is of each activities is thought to be the optimizing factor.
facing a lot of issues regarding proper performance and However lean construction is aimed to improve the
productivity. Many of the projects fail to deliver the performance at the project level and through the whole project
preliminary objectives especially on-time project delivery. A lifecycle by managing interactions between activities and their
contributing factor to this issue is the fact that the construction dependency and variation [8].
process greatly contains activities which do not generate any
value to the final customer. Therefore these activities are II. LEAN PRODUCTION SYSTEM
considered as wastes [9]. For example in Australia up to 35%
of project total cost is wasted on reworks [1]. A 1998 research In the 1950s the manufacturing industry was introduced a
of UK department of the environment, transport and the new production philosophy by Toyota company in Japan. The
regions (DETR) among UK, Scandinavian countries and US, systems were then developed and improved by industrial
also indicates a 30% contribution of reworks and a minimum engineers in a long process of trial and error and became
contribution of 10% waste of construction materials while widely used in later decades in other industrial countries [9].
labor efficiency is only 40-60% [2]. Many successful cases were reported from application of that
Similarly, the construction industry in Malaysia is facing new production philosophy - which is known by different
the same performance problems, especially failure in on-time names such as lean production or initially Just-In-Time
project delivery, mostly due to lack of recognition of real client (JIT) production - in improvement of the productivity of
needs through proper management and a value creation system manufacturing firms [8-10]. Lean production is defined as a
[3, 4]. Therefore, the local construction industry needs better system that can reduce overall cost especially indirect cost
methods of project management to achieve better project while maintaining quality standards and reducing
outcome by reducing any activities that does not contribute to a manufacturing cycle time [11]. Or a production system that
better final delivery. Time wastage is an important factor will deliver a custom product instantly on order but maintain
directly affecting on-time delivery of a construction projects. no intermediate inventories [8].
Therefore there have been studies suggesting and evaluating

978-1-4673-0020-9/11/$26.00 2011 IEEE 345


2011 IEEE Colloquium on Humanities, Science and Engineering Research (CHUSER 2011), Dec 5-6 2011, Penang

The traditional view toward production, which used to be stability and standardized work [14].
the basis for understanding production in many disciplines,
defines production process as a process of converting an input
to an output (Fig.1). This conversion process could be divided III. METHOD
into sub-processes or activities with same characteristics. The
value of the output was associated with the cost of the inputs to This study aims to investigate application of lean model to
that process and the total process cost was minimized by reduce waste of time in construction projects of Malaysia.
reducing each sub-processs cost. On the contrary, the lean However the objective of this paper which is a part of a larger
production model (Fig.2) is a flow of raw material and/or study - is to identify and highlight the significance of time-
information that is processed, inspected, waited or moved to related wastes by using the lean model. . For this purpose, the
reach the finished product [9]. These activities are different in authors have chosen a case study method because of its ability
nature as processing is the conversion of material or to deal with a wide variety of evidence and different data
information while inspecting, moving and waiting characterize collection methods. Moreover the case study can be a preferred
the flow feature of production. method when dealing with how or why research questions that
The lean concept attracted the interest of many scholars in focus on a contemporary phenomena [15]. However, in order
the construction industry who argue that the lean principles can to conduct a case study, having a developed theory before
be implemented to the construction industry as a service collection of any data is a necessity [16-18]. In this case the
industry in order to reduce activity performance time and well modeled lean production theory is the basic theory which
projects costs. One of the reasons is that a service can be is tested with the data collected through direct observation in a
considered as a product since it is started with a customer construction site. On the other hand, the single case chosen for
demand (client) and it ends when it is delivered to them in the this research had all the conditions for testing the theory;
desired time, cost and quality through design and development therefore, studying multiple cases is not necessary in such a
(construction) process [12]. situation [15].
In a lean system, value refers to the achievement of The data was collected through five stages of different
customer requirements. Although all activities contribute to the construction tasks including four stages of in-site framing and
time and cost of production, only process activities add value to one stage of concreting. However due to the limitations of this
the final product whether it is material or information. paper, only the data from the concreting task is analyzed and
Therefore, for the improvement of the flow process, focus is presented here. A key factor which affected the boundaries of
mainly to reduce or eliminate activities that do not add any this study was the boundary of the selected project itself. At the
value (so-called nonvalue-adding activities) whilst the time of data collection, on-site activities were mainly casting of
process activities or value-adding activities have to be more pile caps and ground beams. The choice of this case study was
efficient [9]. The nonvalue-adding activities are actually initially made due to instant availability of the site and project
product flows that only tie process - or also known as data to the researchers.
conversion - activities together e.g. inspection, rework or
waiting. For example handling, rearrangement and re-moving IV. CASE STUDY
of material are nonvalue-adding activities which are more
likely to happen especially in small construction sites [13]. In The case study compromises the construction of a 1600
order to have a successful lean production system, there are square meter three story luxurious residential bungalow with
three foundations that supplement each other and must work basement. The contract sum of the project is approximately
together relatively. Continuous flow of information and level seven million Malaysian Ringgits and total construction
production is matched with customer demand. However this duration is 18 months. The construction of the building consists
continuous flow must exist in an environment of high quality of various main tasks including piling, earthworks, super
and standardized operation. For example, if the quality level is structure, masonry works, Electronic glass roof, M&E, ID, etc.
rather poor, then the stable operation will not be achieved However, at the time of data collection for this study, the main
because low quality is prone to rework. On the other hand, high task running at the site was construction of Reinforced
quality is associated with stable operation which is a result of
combination of labor, machineries, system control compounds

Figure 2. Production as a Flow Process. The shaded boxes represent


nonvalue-adding activities, in contrast to value-adding processing
activities[9].
Figure 1. The Traditional View of a Production Process [9]

346
2011 IEEE Colloquium on Humanities, Science and Engineering Research (CHUSER 2011), Dec 5-6 2011, Penang

Concrete (RC) structure elements. All reinforcements of The concrete was delivered from trucks to the casting area
structural elements were fabricated at site. Likewise, the by filling a concrete bucket which was hoisted by a mobile
traditional method of in-situ fabricated timber formwork crane. After filling the structural elements with concrete, the
system was employed to accomplish casting of structural empty bucket was hoisted back to the truck in order to refill.
elements. However the method of ready mixed concrete was The detailed hoisting process times were recorded and
used in casting of all structural elements of the building. The presented in Table 2. The table shows the number of hoists for
contractor ordered the required amount of concrete on demand each truck and the duration of each which is the duration of
and it was delivered to the site by the concrete supplier with filling and hoisting the bucket until it reached the concerting
mixer trucks. point. Since the volume of bucket was considerably smaller
than each trucks concrete volume, hoisting activity was done
By adopting the lean production model, as illustrated in several times for each batch of concrete.
Fig. 2, the construction task duration is the sum of process time
plus inspection, move and wait time. Only the process time is In order to identify activities that generate value and those
considered as a value-adding activity and the rest do not add regarded as wasted activities; the concreting task was matched
any value to the final product. Therefore the nonvalue-adding against the lean production process flow shown in Fig 2. The
activities should be ideally eliminated or minimized. However, breakdown of these value-adding and nonvalue-adding
process time is also prone to different wastes including but not activities is presented in Table 3. As can be seen in this table
limited to (1) over-production waste, (2) construction method the only value-adding activity in concreting task is actually the
waste, (3) waste from product defects, and (4) poor process time which is the time taken from the first hoist of
optimization in carrying out tasks [5]. In order to measure the concrete until the last bucket of concrete for each batch.
share of all different activities, the required sample data of However the process time in this concreting technique is also
concreting task was collected through direct observation at site. prone to process waste which can also be considered as a move
Data analyzed in this paper is the result of one day total casting time. The move time is actually the concrete hoisting time in
of 34 m3 concrete volume. This ready mixed concrete was this technique and is referred to as process wait time in this
delivered to the construction site through six concrete mixer article. The description column in Table 3 explains how time
trucks. It should be noted that since the goal in this study is to durations of value-adding and nonvalue-adding activities can
evaluate time-related wastage, it is assumed that every be determined from the raw data in Table 1 and Table 2. Table
workers productivity is the same level. Thus, the data is not 4 shows the result of these duration times for each concrete
affected with workers different level of productivity. That batch.
means all workers contribution to produce one meter cube of a
structure element is equal.
TABLE IV. DETAIL OF HOISTING DURATION TIMES

V. RESEARCH FINDINGS
Batch 1 2 3 4 5 6

Table 1 presents the collected time data of each concrete Hoist


mixer truck in detail. The Data in this table includes the H1 0:01:30 0:01:20 0:01:15 0:01:35 0:02:05 0:01:15
volume of concrete each truck delivered, arrival time to the H2 0:01:20 0:01:35 0:01:40 0:01:15 0:01:55 0:02:15
site, inspection times and finally concreting time. After the
H3 0:01:20 0:01:40 0:01:15 0:01:20 0:02:15 0:02:00
arrival of each truck to the site, inspection was done by Clerk
of Work. Inspection time recorded for concreting refers to the H4 0:01:25 0:01:20 0:01:50 0:01:25 0:02:20 0:01:40
slump test which measures the workability or wetness of the H5 0:01:20 0:01:25 0:01:35 0:01:40 0:02:40 0:02:30
concrete mix. The test was conducted for each individual H6 0:01:30 0:01:15 0:01:45 0:01:50 0:02:35 0:02:15
batches of concrete delivered to the site and casting was only
allowed if the slump was between the required workability H7 0:01:10 0:01:20 0:01:30 0:02:00 0:02:50 0:02:30
ranges. H8 0:01:15 0:01:15 0:01:40 0:02:10 0:03:00 0:01:50
H9 0:01:10 0:01:20 0:01:20 0:01:50 0:02:40 -
TABLE III. TIME RECORD FOR CONCRETING TASK (RAW FORMAT)
H10 0:01:20 0:01:25 0:01:25 0:01:50 0:02:10 -
H11 0:01:15 0:01:15 0:01:25 0:01:45 0:01:50 -
C.O.W C.O.W
Batch Concrete Arrival Concreting Concreting H12 0:01:10 0:01:30 0:01:40 0:01:40 0:02:10 -
inspection inspection
Number Volume Time start time end time
start time end time H13 0:01:25 0:01:25 0:01:35 0:01:55 0:02:20 -
H14 - 0:01:15 0:01:35 0:02:15 0:02:10 -
1 6 9:25 9:55 10:10 10:10 10:36
H15 - - 0:01:45 - 0:02:35 -
2 6 10:52 10:57 11:10 11:10 11:45
H16 - - 0:01:40 - 0:02:40 -
3 7 12:10 12:12 12:25 12:30 13:28 H17 - - 0:01:55 - 0:02:45 -
4 6 13:35 13:40 13:55 14:30 15:07 H18 - - 0:01:30 - 0:02:45 -

5 7 15:35 15:35 15:50 16:10 17:30 H19 - - 0:01:40 - 0:02:40 -


H20 - - 0:01:45 - 0:02:50 -
6 2 18:00 - - 18:03 18:30
H21 - - - - 0:02:30 -

347
2011 IEEE Colloquium on Humanities, Science and Engineering Research (CHUSER 2011), Dec 5-6 2011, Penang

Subsequently further analysis is done on the data of Table 4


TABLE III. CATEGORIZATION OF ACTIVITIES BASED ON LEAN
and the result is tabulated in Table 5. In this table total wait PRODUCTION MODEL
time of each batch is calculated by adding all wait times in that
particular batch and the total wait time for the whole task is the
Type of activity Activity Description
sum of all. Absolute process time is resulted from deducting
process wait time from process time. For example for the batch Value-adding Process time Time taken from start of each
No.1 process time is 26 minutes and process wait time which trucks concrete casting (first
is the sum of hoist times in Table 2 is 17 minutes. Therefore hoist) until end of casting
the absolute process time is 9 minutes.
Nonvalue-adding Process wait Move time hidden inside process
Since the volume of concreting is different in each batch, in time time which is calculated from
order to make a comparison between data of different delivery total hoisting durations in Table
batches of concrete, we need to have a standard data. For this 2. This move time is considered
the process waste time since it is
mean all time data are divided by the volume of concreting to happening in the middle of the
achieve a data of the same value. For example in order to process time and is a motion
calculate the standardized times for batch 1, we divide all time waste since concrete should be
data by 6. The results of data standardization are tabulated in hoisted to the place it actually is
Table 6. being used

Fig 3 demonstrates the value-adding and nonvalue-adding Nonvalue-adding Wait time (1) Time taken from finishing each
trucks casting until arrival of
activities based on data presented in Table 6. The data in this next truck on site. However for
figure is arranged in the order of total duration of tasks. The the first concrete mixing truck
data is then reorganized in Fig 4 where total duration of each this time is calculated from start
task is expressed as 100% to assist the comparison between the of site operation hour (9:00 am)
entries. till arrival of first lorry

The findings show that the absolute process time Nonvalue-adding Wait time (2) Waiting time calculated from
(concreting time) for each batch is actually a very small arrival of each lorry until start of
inspection
percentage of total time. This percentage for the batch No. 1 to
No.6 is respectively 9.4%, 23.1%, 25.3%, 12.1%, 19.8%, and Nonvalue-adding Wait time (3) Waiting time taken from end of
18.6%. As can be seen batch 3 is the most efficient comparing inspection until start of concrete
to the rest since 25.3% of the whole task duration is a value- casting
adding activity. However the rest of the time spent on each task
Nonvalue-adding Inspection time Time taken to perform concrete
does consist of different nonvalue-adding activities which slump test at site
contributes to project delay.

TABLE IV. BREAKDOWN CALCULATION OF DURATION OF EACH ACTIVITY (HOURS:MINUTES)

Batch Number Wait time 1 Wait time 2 Inspection time Wait time 3 Process time Process wait Activity
time duration

1 0:25 0:30 0:15 0:00 0:26 0:17 1:11

2 0:16 0:05 0:13 0:00 0:35 0:19 0:53

3 0:25 0:02 0:13 0:05 0:58 0:32 1:18

4 0:07 0:05 0:15 0:35 0:37 0:25 1:32

5 0:28 0:00 0:15 0:20 1:20 0:52 1:55

6 0:30 0:00 0:00 0:03 0:27 0:16 0:30

348
2011 IEEE Colloquium on Humanities, Science and Engineering Research (CHUSER 2011), Dec 5-6 2011, Penang

TABLE V. TIME CALCULATION FOR TOTAL VALUE-ADDING AND NON VALUE-ADDING ACTIVITIES (HOURS:MINUTES)

Batch Total process time Absolute Total wait time Total process wait Total inspection time Total activity
process time time duration
1 0:26 0:09 1:12 0:17 0:15 1:11

2 0:35 0:16 0:40 0:19 0:13 0:53

3 0:58 0:26 1:04 0:32 0:13 1:18

4 0:37 0:12 1:12 0:25 0:15 1:32

5 1:20 0:28 1:40 0:52 0:15 1:55

6 0:27 0:11 0:49 0:16 0:00 0:30

Total Sum 4:23 1:42 6:37 2:41 1:11 7:19

Total non-process wait time for batch 1 to 6 is 57.3%, process time is not a large portion of the total task time. As it is
30.1%, 31.1%, 47.5%, 32.8% and 54.3% respectively. shown in the last chapter, absolute process time, which is the
Inspection time for batch one to five contribute to 15.6%, only value-adding activity in a lean system, only takes up to
18.9%, 12.7%, 15.2% and 10.6% of total task time respectively 25.3% of the whole task duration at most. That means the rest
while it does not appear in batch number six. Finally the of the time spent on the task is all wasted time rising from the
process wait time (or move time), which is hoisting time of activities that do not create any value to the final project
concrete, for batches one to six hits 17.7%, 27.9%, 30.9%, delivery. Therefore the management should put all the effort to
25.2%, 36.8% and 27.1% of total task duration respectively. employ methods that minimize these nonvalue-adding
activities.
The result of the study shows that the most significant
VI. CONCLUSION
nonvalue-adding activity in concreting task is waiting time
which ranges from 30% to 57% of the whole task duration.
Although in many countries the concept of lean Educating management team in lean methods of purchasing
construction has been in practice for almost two decades, and delivery such as JIT purchasing can actually reduce the
previous surveys reveals that the majority of construction task duration almost to half without doubling up the resources.
practices in Malaysia are still managed by the traditional Likewise, inspection time which takes up to almost 19% of the
activity-based thinking [19]. Project team usually tries to avoid task duration can be totally eliminated through a better
any delays by reducing process time of different tasks. relationship among the supply chain. For example, if the
However the findings of this paper reveal that in fact the quality of the supplied concrete mix is controlled and the

TABLE VI. . STANDARDIZED TIME CALCULATION FOR TOTAL VALUE-ADDING AND NON VALUE-ADDING ACTIVITIES

Total process Absolute process Total wait time Total process wait Total inspection Total activity
Batch Volume ( m3)
time per m3 time per m3 per m3 time per m3 time per m3 duration per m3
1 6 0:04:20 0:01:30 0:12:00 0:02:50 0:02:30 0:11:50

2 6 0:05:52 0:0:40 0:06:40 0:03:10 0:02:10 0:08:50

3 7 0:08:17 0:03.43 0:09:09 0:04:35 0:1:52 0:11:09

4 6 0:06:10 0:02:00 0:12:00 0:04:10 0:2:30 0:15:20

5 7 0:11:26 0:04:00 0:14:17 0:07:26 0:02.09 0:16:26

6 2 0:13:30 0:05:30 0:24:30 0:08:00 0:00:00 0:15:00

349
2011 IEEE Colloquium on Humanities, Science and Engineering Research (CHUSER 2011), Dec 5-6 2011, Penang

However, employing such technique for smaller projects is not


cost wise in Malaysia. The rental price of a concrete pump is
considerably more than renting a crane. Same argument can be
done over using a larger concrete bucket in order to reduce
process waste time. Nevertheless, hoisting a larger bucket
requires using a larger crane. Unfortunately, according to the
project team of the case study, the price difference between the
two crane sizes does not worth the time saved from employing
a larger crane. Overcoming the process waste time can be
possible by conducting surveys among the contractors to
investigate the practicality of different casting methods. It is
also suggested that future studies compare the process time of
different cases that exercise different casting methods in order
to suggest the most efficient technique which create more value
to the final project delivery.

Figure 3. Absolute time of task cycle for concreting (per meter cube) REFERENCES
[1] Love, P.E.D., Z. Irani, and D.J. Edwards, Learning to reduce rework
inprojects: Analysis of firms organizational learning and quality
practices, in Project Management Journal, 2003: p. 13-25.
required inspections are done before it reaches the site, there is [2] Banik, G.C. Construction productivity improvement, in ASC
no need for further inspection at site. Of course, that is only Proceedings of the 35th Annual Conference. 1999. San Luis Obispo,
achievable if there is a high level of trust between project California.
consultant team and the suppliers. Hence further studies are [3] Jaapar, A., I. R. Endut, N. A. Bari, and R. I. Takim, the impact of value
highly recommended in order to investigate ways of building management implementation in Malaysia. in Journal of Sustainable
Developement, 2009. 2(2): p. 210-219.
such trust through the project supply chain. [4] Jaapar, A., The Application of Value Management in the Malaysian
While this study is one of the few studies in lean Construction Industry and Development of Prototype Value
Management Guidelines. 2006, Shah Alam, Selangor: Universiti
construction in Malaysia, it is still limited to certain extent. Teknologi MARA.
This study only covers concreting task in a Bungalow [5] Low, S.P. and S.K.L. Tan, How 'just-in-time' wastages can be
construction project. The authors believe that analyzing the quantified: case study of a private condominium project, Construction
concreting task as a sample is important since the majority of Management and Economics, 1998. 16: p. 621-635.
building projects in Malaysia are RC structured (mostly due to [6] Neo, R.B. Accounting for waste in construction, in Proceedings of the
First International Conference on Construction Project Management.
the market price). However, future studies on other 1995. Singapore: Centre for Advanced Construction Studies, Nanyang
construction tasks and other types of projects are recommended Technological University.
to identify causes of delay. On the other hand, although in case [7] Lean Construction, ed. L.F. Alarcn. 1997, Netherlands: A.A. Balkema.
of the current paper it does not really matter what type of [8] Howell, G.A. What is lean construction, in Proceedings of the
project (in term of scale) is chosen, it can be argued that the Seventh Annual Conference of the International Group for Lean
Construction. 1999. Berkeley, CA: IGLC-7.
choice of Bungalow is not suitable due to the concreting
[9] Koskela, L., Application of the New Production Philosophy to
technique. Usually in larger project especially high rise Construction. 1992, CIFE, Stanford University: Stanford, CA.
construction - the concreting is done by using a pump rather [10] Ansari, A. and B. Modarress, Just-in-time purchasing. 1990, New York:
than hoisting a concrete bucket. That naturally eliminates the The Free Press.
process waste time caused by construction method which was [11] Womack, J.P. and D.T. Jones, Lean Thinking. 1996, New York: Simon
determined between 17.7% and 36.8% of task duration earlier. & Schuster.
[12] Sayer, N.J. and B. Williams, Lean for Dummies. 2007, Indianapolis:
Wiley Publishing, Inc.
[13] Lundesjo, G., construction industry logistics benefits from
environmental concerns. Logistics & Transport Focus, 2009: p. 43-47.
[14] Martin, J.W., Lean Six Sigma for Supply Chain Management: The 10-
step Solution Process. 2007, New York: The McGraw-Hill Co.
[15] Yin, R.K., Case study research: design and methods. 2009, Thousand
Oaks: SAGE Publication, Inc.
[16] Lincoln, Y.S. and E.G. Guba, Trustworthiness and authenticity in
naturalistiv evaluation, in Naturalistic evaluation, D.D. Williams, Editor.
1985, Jossey-Bass: San Francisco. p. 73-84.
[17] Van Maanen, J., Tales of the field: On writing ethnography. 1988,
Chicago: University of Chicago Press.
[18] Corbin, J. and A. Strauss, Basics of qualitative research: Techniques and
procedures for developing grounded theory. 2007, Thousand Oaks, CA:
Sage.
[19] Lim, V. A., Lean construction: knowledge and barriers in implementing
into Malaysia construction industry. Masters thesis. 2008, Faculty of
Civil Engineering, Universiti Teknologi Malaysia.

Figure4. Relative time of task cycle for concreting

350

You might also like