stahilator
Tomasz Najder; PhD, Civ. Eng.
Stabilator AB
Stockholm/Sweden
THE STRENGTHENING WORKS IN THE WESTERN WING OF
MALBORK MIDDLE CASTLE
Summary
Problems of a structural nature connected with the Western Wing of
Malbork Castle in northern Poland have probably persisted since
the construction of the castle was completed, that is to say for
650 years. The tying of the boldly designed upper structure to its
much poorer quality foundation that had also been weakened by the
decaying process was effected in 1990 in necessity of prompt
strengthening of the structure.
The design finally chosen for this project was a concept proposed
by a Swedish company, Stabilator AB. The idea was to transfer the
weight of the Western Wall to new injected piles using a girt beam
system embracing both sides of the base of the wall in the form of
a clamp.
It was expected to achieve satisfactory pressing of the beams to
the walls by means of prestressed horizontal anchorages installed
in boreholes previously coredrilled crosswise to the wall.
These works were carried out by Stabilator AB and successfully
finished in September 1992.208
1.0 Preface
In 1992, the Swedish company Stabilator AB, a member of the
Skanska Group, carried out the first part of the foundation
strengthening works on the Western Wing of the Middle Castle in
Malbork. This was one of the most significant projects of its kind
carried out in Poland, and also one of the most meaningful assign-
ments in the company's 27-year history.
2.0 History of the castle
Construction of the castle of the Teutonic Order in Malbork
started in 1274 and continued in different stages for nearly 130
years. The entire castle complex consists of the following sec-
tions: the High Castle, the Middle Castle with the Great Refec-
tory, the Palace of the Grand Masters and the front castle lying
at the foot of the section named the Low Castle. The Middle Castle
and the Low Castle comprising stores and workshops were completed
after the building of the High Castle.
On the side where the Western Wing now stands there were formerly
defence walls with loop-holes, dating from about 1300. Up till now
the fragments of these walls have still existed - unseen due to
their being incorporated in the cellars of the wing which was
added later.
An interesting point is that the defence wall inclines to a
noticeable degree, which suggests that its original builders also
had problems with stability. The extension of the castle in
connection with the building up of its Western Wing was the reason
for the demolition of the old defence wall. The wall of the
Western Wing protruded towards the Nogat river due to its being
positioned on the original moat line.
The works connected with the Western Wing started in about 1318.
The mass of the building was situated on the edge of a natural
sandy hill which is the site of the High Castle and also today's
Middle Castle courtyard foundation. The Eastern Wall was founded
on the above-mentioned hill too, and the Western Wall at the foot
of a slope in the area of the sandbank deposited by the overflow
branch of the Nogat River.
The decision to strengthen the original foundation of the Western
Wall was based on the realisation of the importance of having the
appropriate foundations on such weak ground.sn 101 (9798
stabilator .
Results obtained from excavation pits carried out in 1990 con-
firmed conclusions that the Teutonic Knights had also made some
attempts to strengthen the ground on which the foundation stood.
For a distance of 3.0 m, which is the width of the wall base, two
rows of short oaken piles were driven at intervals of 1 m. The
piles were bound together with longitudinal beams, the entire
structure forming a kind of frame. A thousand short wooden stakes
were driven close to each other within the borders of this frame-
work. These stakes are not a kind of typical piling, but remain
the still-in-use way of sand compaction. On the foundation, topped
with wooden grillwork, large stones were placed to form a rubble
wall with the joints in its upper parts filled with lime mortar.
Higher up, the wall of bricks with lime mortar was erected to a
height of 17 m above the actual ground level. After the structure
was built some problems were bound to occur due to the fact that
the internal geometry of the structure had been changed.
According to conclusions drawn from architectural research, high
rooms with stellar vaults had previously been built on the lowest
floor, the vault resting on three columns made of stone similar to
the ones in the Great Refectory one floor above. That design was
altered by counterbracing the building skeleton with the third
wall positioned along its centre line. The height of the rooms was
divided into two, making two floors each half the original height
with barrel-type vaults this time. The rigid block of the heating
stove supplying the Great Refectory with heat was also built
there.
On the level of the first floor of the building (viewed from the
Nogat River side), which is the same as the east side courtyard
level, the biggest, most presentable room was built, extra-
ordinarily light and of bold design. The vault of this room which
is constructed in a very difficult and complicated way, with an
almost palm-shaped form, rests on only three octagonal, very
slender pillars of granite. Rows of large windows with stone
tracery decoration in the Western and Eastern Walls reflect the
Gothic-style lightness of interior decoration typical of the great
cathedrals built at that time.
This daring architecture caused permanent problems. The first
documentary evidence dates from 1565. At thet time cracks appeared
on the north wall of the Great Refectory necessitating its re-
erection. About 1860 cracks reactivated to such an extent that
special ties had to be installed, located in the attic of the
Western Wing, and in 1865 a stone counterfort had to be built at
the foot of the wall near the Kitchen. At that time the first pits
were excavated for research purposes.a0 (2703
The Western Wing survived the disaster of the Second world War,
but unfortunately in 1959 its roofs were gutted by fire. The
original rafter frame made of wooden beams was replaced by steel
lattice girders. The roof, which once rested on the internal part
of the porch topping the walls, was moved to rest on the outside
of the porch. Up to now there has been controversy as to how these
changes affect the magnitude of the expansion forces in the wall.
In consequence of the progressive degradation, various
explanations of the causes of the new cracks still forming were
put forward in the following years. The cracks continued to appear
in the walls and vaults, and there was a permanent increase in the
rate of settlement. Several concepts for the preservation of the
structure were implemented in the following years, often only in
an intermittent way and sometimes not even reaching completion.
The most often applied method was to fasten the structure with
ties to the level of the cellars, the Great Refectory and the
loft.
In the latter part of the eighties the cracks in the transversal
walls and vaults reached a width of a few centimetres. The Western
Wall fell off the remaining part of the structure, pulling down
with it some parts of the transversal walls. In effect the Great
Refectory vault remained suspended in the air and it became
necessary to underpin it immediately. The ongoing process of
settlement in the Western Wall and also the inclination of the
wall activated in 1990-1991 (fig. 1) meant that the Western Wall
was in imminent danger of collapsing.
3.0 The concept of preservation of the Western Wing
The analysis of the available archival evidence and the actual
condition of the building structure comprising the Great Refectory
made it possible to attempt the job of reconstructing the long
history of problems concerning the Western Wing. Its location on
the edge of an upland with one of the walls (the western one)
situated on weaker ground gave rise to long-lasting consequences.
The foundation was loaded with approx. 100 tons per running meter
of the weight of the wall with countertie-like acting vaults and
roof, overloading the edge of the foundation from the very start
with a peak value reaching 600 kPa. The process of disintegration
was hastened by old age in combination with the decaying of the
pile tops after lowering of the groundwater level due to the
regulation works on the Nogat River carried out at the beginning
of this century.190103 (67.03)
stabilator
The half of the building facing the water side kept on moving
slightly but steadily and detaching from the remaining part. The
Western Wall has begun to settle in a downward direction and to
incline from the vertical.
Attempts to cope with this problem by installing ties in the loft
have halted the inclining process but at the same time have caused
@ threatening bending tendency in the slim pillars between the
windows in the Great Refectory.
Earlier attempts to save the structure have for many reasons not
got to the root of the problem, i.e. strengthening of the weakened
foundation of the Western Wall. The concepts considered in 1991
had to be carefully analysed from the point of view of reality and
efficiency as well as with reference to reducing the unavoidable
state of destruction that would accompany the initial stage of the
structural strengthening works.
The tender-winning design presented the concept of applying
micropiles. It was planned to join the micropiles by pile capping
concrete beams on both sides of the Western Wall and to instal a
special kind of injected TNA system pile driven with the aid of
special drilling methods on the inside and outside of the wall.
The piles had to be driven as close to the face of the wall as
possible, which meant in practice at a distance of 60 cm at
intervals of 0.8 - 1.2 m, and to a depth of 12.0 m (see fig. 2).
A load-bearing part of the piles extended below the level of the
original foundation base, in sand layers. Later on, excavation in
sections down to 2.0 m below the actual ground level had to be
carried out, and at intervals of 1.0 m the wall had to be rebored
using the shockless method of core drilling. Bundles of pre-
stressed cables (lines) had to be pulled through the bored holes,
after which solid girt beams appropriately reinforced were cast on
both sides of the wall. After concrete hardening, the bundles of
cables were prestressed, thus pressing the beams to the wall and
functioning together to form a clamp. The placing of this clamp on
new piles transfers the load from vaults, roof and wall onto these
piles, so that the entire load is removed from the old foundation.
4.0 The execution of the works
First of all load testing of the piles was carried out. The load-
bearing part of the piles was about 6.0 m in length and the piles
were 30 cm in diameter. The load-bearing capacity was 84.0 and
89.0 tons. After reaching the working load, settlements have not
exceeded 5.0 mm. During execution of the works, three additionalstabilator
test loadings of "production piles" have been carried out and the
xesults obtained showed nearly the same load values.
Before starting the drilling works, the structure had been clamped
with prestressed ties of GWS system type on the level of the
Kitchen and the bottom edge of the Great Refectory windows.
Similar ties were placed in the northern part of the loft of the
wing. To avoid buckling of the pillars between the windows in the
Great Refectory, protective strengthening of the pillars was
performed.
Drilling works for the piling were done using pipes with diameters
of 140 mm or 168 mm and a minimum amount of drilling fluid. In
spite of very careful working procedures, it was not possible to
prevent additional settlements of an average of about 15 mm.
Drilling had to be done through fine, single-grained sand which
appeared to be very sensitive as regard the liquefaction phen-
omenon. Previous doubts concerning the application of the jet-
grouting injection system as being hazardous for the structure
turned out to be justified, as the structure would probably not
survive this system of underpinning. Some problems appeared while
drilling stone, old piles and wooden beams, but not to the extent
expected. Core drilling through the walls did not prove to be a
problem, as the walls were of continuous type, and the quality of
the mediaeval bricks and mortar was surprisingly high.
Problems in connection with piling inside the cellars were due to
the low height of the rooms, i.e. 1.4 m in the axis of drilling
and also the inevitable necessity of operating the equipment among
a "forest" of shores supporting the vault. In such conditions a
mini-drilling rig (Stabilator's "cellar mouse") was invaluable
equipment.
The sequence and progress of works as well as their intensity and
division into stages were continuously modified with the aid of a
measuring and warning computer system. This system provided conti-
nuous measurement of structure settlements, measurement of forces
in temporary steel counterforts, temporary ties and roof trusses
and also took measurements of the relative displacements of the
Western Wall towards the Eeastern one (convergence measurements).
The whole system included dial gauges installed on the cracks by
scientists from the Academy of Mining and Metallurgy of Cracow.
Accurate levelling of the Western Wall including changes in in-
clination was also carried out.19201 6703)
5.0 Final conclusion
The strengthening works were started in December 1991 by instal-
ling the temporary supports. In January 1992, load testing of the
piles was carried out. The actual underpinning works started in
March and they were timely (with a break for holidays) finalized
in September 1992.
After the termination of the works, observations of the settlement
of the building indicated that it had increased by about 1.0 mm
during the first three months. However, a precision levelling
carried out in May 1993 showed that, in comparison to measurements
from November 1992, the settlements and the horizontal movements
of the Western Wall had ceased completely (cf Fig. 1). In addi-
tion, there was no cracking whatsoever to be observed in the
plaster of Paris seals attached to the walls of the building.
During the second stage of the works, the remaining section of the
Western Wall was supported in its entire length towards the north
together with the Chickenfoot Tower and a part of the Northern
Wall of the Western Wing. These works were carried out between
October 1992 and May 1993.
In the next stages, the vaults will be renovated and the brick
walls will be strengthened. The scope of this task will require
many years of work. It seems that the most magnificent medieval
hall in Malbork Castle will be closed to visitors for a long time
to come.
However, the observations of the Western Wing so far allow for
careful optimism, as it seems as though the strengthening opera~
tions of this priceless monument have proven successful.
Malbork, June 1993aoe 1988 see ise AS93,
EN | | i
MS
o | i
' {
\ |
| vl
| | \
|
10
1
: | |
i
i
- | | | |
1 | I
| |
| pertos
0 i
Oo
a
Fig. 1 Increment of settlements at the Western Wall in the
sector of the Great Refectory, from before the start
of the strengthening works until after their
completion.~20m
BRICK WALL
PRESTRESSING LINES
TYPE VSL IN PLasTiC =
ie Ana
THE GIRT BEAM
i
i
| | CONCRETE K50
DRAIN PIPE
COREDRILL HOLE
@ 85 mm cic 1.0m
WOODEN GRILLWORK
WOODEN PILES eel
~ THE MEDIEVAL ;
i Founparton,
MICROPILE TYPE TNA
cc 120 cm; ¢ 30 cm
‘BRICK DEBRIS,
LOAM BACKFILL
(HISTORICAL LAYER)
DRILLING TUBE 6 168 mm
DEFORMED BAR TYPE GWS 6 36 mm
GROUNDWATER LEWE
Sad ~ 2WG
MICROPILE TYPE TNA
cc 85 cm; 9 40 cm
VERTICAL
RAKE 10:1
THE ZONE
OF BEARING
PILE MANTLE
|| Fig-2 =10,80
if The underpinning of the Western 1_ 7
I! \ wall - typical cross section | THE z0NE
ade