Professional Documents
Culture Documents
ASSIGNMENT GROUP
NOMBOR
NAMA
MATRIK
AZMAN BIN ROSLAN AP140431
MOHD HAIRY BIN YUSOFF AP140420
NOR NADIAH BINTI ISMAIL AP140341
NUR ADIIBAH BINTI BASIRUN AP140303
PART B
a. Identify the impact to the contractor when the project is behind schedule
and is expected to be delayed in its completion time.
viii. The Supervisors and the team doing the work arent aware or dont
understand the schedule
Management may give a copy of the updated schedule to Supervisors
but often this is the schedule for the whole project for the remaining duration
and it could be several or even hundreds of pages long. Most Supervisors are
only concerned with their section of work and what needs to be done in the
next couple of weeks. Therefore give them only their relevant sections of the
schedule for the next few weeks. In fact Ive found that, if possible, providing
a schedule in a pictorial form highlighting the important dates works well as
it can be put up on their office wall and is easily understood by their team.
Even better is to spend time explaining to the Supervisor what needs to be
achieved and explaining why certain dates are critical to the project. Its
amazing how a team who know what they have to achieve and the reasons
behind it can then deliver.
i. Be Aware
Every project has its own rhythm and flow. Using your knowledge of
project goals, priorities, and project team dynamics, you can pick up on the
warning signs of pending delays, and you will be in a better position to make
the tough decisions.
ii. Long lead items, requested by owner, have not been received
iv. New or Extra Work not included in the original scope or contract
v. Unusual or adverse weather conditions
It is also important to highlight that time extensions will be denied for the
following reasons:
v. When insufficient proof or evidence that the critical path method has suffered
irrecoverable delays caused by the contractor or their parties
The time extension when properly presented must contain the following
supporting documents:
Indicate the actions the contractor has taken to avoid or minimize other
delays
Insurances and other bonds will need to be re-issued to cover extend periods
No additional time will be granted for the same item once it has been
approved
In the case of a continuing delay, only one claim is necessary
A letter should be concise and must reference the contract clause that allows the
request, a schedule that can prove the delay reasons and the proposed recovery plan.
It shall include also the damages if any, the amount of calendar or working days
being requested and the impacted activities delayed by the changes.