You are on page 1of 35

NEPAL TELECOM

NEPAL DOORSANCHAR COMPANY LIMITED


CENTRAL OFFICE
CIVIL DEPARTMENT
BHADRAKALI PLAZA , KATHMANDU

for

Nepalganj
BANKE DISTRICT

2068/69

Kartik , 2068
1/35

NEPAL TELECOM
NEPAL DOORSANCHAR COMPANY LIMITED
EASTERN REGIONAL DIRECTORATE
CIVIL SECTION
BIRATNAGAR, MORANG
DISTRICT:- ILAM
RATES for 2071/72
Rate With 15%
S.N. Items Unit Remarks
Overhead
1. EARTHWORK
1.1 EarthWork in exc. in soft soil Cu.M. 364.83
1.2 EarthWork in exc. in- BMS Cu.M. 416.94
1.3 E/W for foun. trench (soft soil) Cu.M. 521.18
1.4 E/W for foun. trench - BMS Cu.M. 828.68
1.5 Earth fill. With water compact Cu.M. 253.00
1.6 Mud filling with transportation of mud up to 2.00
Cu.M. 480.19
Km. distance.
1.7 Stone filling at foundation Cu.M. 3,351.89
1.8 Sand fill. With compaction Cu.M. 3,045.74
1.9 Stone Dust Filling. Cu.M. 1,482.36

2. BRICK WORK
2.1 Brick soling in sand - flat Sq.M. 1,205.09
2.2 Brick soling in sand - vert Sq.M. 2,097.68
2.4 For ground floor
2.4a Brick mas.in c.m. - 1:3 Cu.M. 17,853.52
2.4b Brick mas.in c.m. - 1:4 Cu.M. 17,355.06
2.4c Brick mas.in c.m. - 1:6 Cu.M. 16,881.06
2.4d Brick mas.in mud mortar Cu.M. 14,442.87
2.5 Above ground floor
2.5a Brick mas.in c.m. - 1:3 Cu.M. 18,114.11
2.5b Brick mas.in c.m. - 1:4 Cu.M. 17,615.65
2.5c Brick mas.in c.m. - 1:6 Cu.M. 17,141.65
2.5d Brick mas.in mud mortar Cu.M. 14,703.46

3. STONE WORK
3.1 Dry Stone soling in sand Cu.M. 5,518.54
3.2 Stone mas.in c.m. - 1:4 Cu.M. 9,917.97
3.3 Stone mas.in c.m. - 1:6 Cu.M. 9,043.05
3.4 Stone mas.in c.m. - mud Cu.M. 4,407.70
3.5 Stone work for dry wall Cu.M. 4,147.82

4. CONCRETE WORK
4.1 PCC 1:5:10 general work (gravel) Cu.M. 9,846.94
4.2 PCC 1:4:8 general work (gravel) Cu.M. 10,544.19
4.3 PCC 1:3:6 general work (gravel) Cu.M. 11,415.75
4.4 PCC 1:2:4 general work (gravel) Cu.M. 12,933.75
4.5 For RCC -PCC 1:2:4 crush. Agg.-M15 Cu.M. 14,053.10
4.6 For RCC -PCC 1:1.5:3 cru. Agg. -M20 Cu.M. 15,436.74
4.7 For RCC -PCC 1:1:2 cru. Agg. -M25 Cu.M. 19,059.20

5. WOODEN WORK
5.1 Sal wood- Chaukhat Cu.M. 202,807.35
5.2 Sal wood- Beam Cu.M. 176,487.03

Prepared by:- Checked by:- Approved by:-


2/35

NEPAL DOORSANCHAR COMPANY LIMITED


EASTERN REGIONAL DIRECTORATE
CIVIL SECTION
BIRATNAGAR, MORANG
DISTRICT:- ILAM
RATES for 2071/72
Rate With 15%
S.N. Items Unit Remarks
Overhead
5.3 38mm thick Sal. Panelled shutters Sq.M. 10,977.16
5.4 " " - with 4mm glass Sq.M. 7,432.61
5.5 " " - 4mm plywood Sq.M. 6,217.49
5.6 " " - GI plain sheet 24 # Sq.M. 7,036.16
5.10 4mm glass + listy on frame Sq.M. 767.60
5.11 24 Gauge GI sheet fixing with listy Sq.M. 874.53
5.12 Wooden form work for R.C.C.+P.C.C. Sq.M. 480.07
5.13 12mm Th. Plywood partition with salwood frame Sq.M. 3,292.13
5.14 25mmth saal wooden planking works Sq.M. 7,036.32

6. PLASTERING WORK
6.1 12.5mm cement plaster - 1:3 ceil. Sq.M. 355.31
6.2 - 1:4 ceil. Sq.M. 344.55
6.3 - 1:4 On Walls Sq.M. 301.54
6.4 - 1:6 On Walls Sq.M. 277.04
6.5 20mm " " " - 1:4 Sq.M. 397.42
6.6 Flush cem.pointing1:2- brick wall Sq.M. 184.12
6.7 Flush cem.pointing1:2- stone wall Sq.M. 236.21
6.8 3 mm cement punning Sq.M. 219.25
6.9 Plain Plaster of Paris Sq.M. 316.16

7. FLOORING WORK
7.1 Brick vertical soling in (1:6) and Pointing Sq.M. 2,174.55
7.2 25mm thick Mozaic flooring Sq.M. 2,790.23
7.3-a Tile Porcelain -Glazed-Wall-NS-76 Sq.M. 2,319.02
7.3-b Tile Porcelain -Glazed-floor-NS-76 Sq.M. 2,229.86
7.4-a Marble slab flooring Sq.M. 4,628.88
7.4-b 38mm cement concrete flooring with punning Sq.M. 603.82
7.4-c 50mm cement concrete flooring with punning Sq.M. 749.17
7.4-d Granite flooring Sq.M. 5,873.88

8. ROOFING WORK
8.1 CGI sheet roof - 26 # plain Sq.M. 758.39
8.2 CGI sheet roof - 26 # coloured Sq.M. 873.24
8.3 GI sheet ridge-24 # (60 cm wide) R.Mt. 712.51
8.4 GI sheet ridge-26 # (60 cm wide) Colour R.Mt. 852.61
8.5 GI plain sheet fixing work - 24 # Sq.M. 1,126.46
8.7 False ceilling of 4mm ply.in sal wood frame Of 50
mm.*75 mm. size & Room 600 mm.*900 mm. Sq.M. 2,805.54

9. STEEL WORK
9.1 Barbed wire fencing 12 # R.Mt. 55.32
9.2 M.S. grill 3x20 (13.45Kg/sm) Sq.M. 1,956.98
9.3 M.S. grill 4.5x20 (20.17Kg/sm) Sq.M. 2,931.87
9.4 Collapsible Gate(37.66 Kg.) Sq.M. 4,651.75
9.5 Rolling Shutter(18 Gauge) Sq.M. 4,847.25
9.6 MS Angle Fixing work Kg 174.23

Prepared by:- Checked by:- Approved by:-


3/35

NEPAL DOORSANCHAR COMPANY LIMITED


EASTERN REGIONAL DIRECTORATE
CIVIL SECTION
BIRATNAGAR, MORANG
DISTRICT:- ILAM
RATES for 2071/72
Rate With 15%
S.N. Items Unit Remarks
Overhead
Making Gabin with 100*120 mm size mesh with Sq.M. 384.00
9.7 medium GI wire.
Making Gabin with 80*100 mm size mesh with
Sq.M. 360.10
9.8 medium GI wire.
9.9 Iron rod( TOR steel) for RCC dia. 8mm& below Kg 109.51

10. PAINTING WORK


10.1 2 Coat white wash in new surf. Sq.M. 27.58
10.2 2 coat snocem (cement paint) Sq.M. 119.03
10.3 Primer + 1 coat enamel painting Sq.M. 173.68
10.4 Primer + 2 coat enamel (new) Sq.M. 263.50
10.5 - aluminium Sq.M. 235.11
10.6 One coat of distemper paint Sq.M. 114.60
10.7 Two coats of distemper paint Sq.M. 163.24
10.8 One coat of Plastic Emulsion painting Sq.M. 194.38
10.9 Two coats of Plastic Emulsion painting Sq.M. 300.30
10.10 One coat of Apex painting with Primer Sq.M. 194.38
10.11 Two coats of Apex painting with Primer Sq.M. 300.30

12. WATER PROOFING WORK


12.1 38mm thick D.P.C. (1:2:4) with WPC. Sq.M. 603.66
12.2 Water proofing (P.C.C. -1:2:4, Safecrete ) Cu.M. 17,055.35
13. NETWORK RATE
13.1 Pitch cutting work Sq.M. 506.00
13.2 Site clearence of top soil Sq.M. 30.36
13.3 19mm plywood form work for RCC Sq.M. 781.93
13.4 PVC Duct pipe 110mm dia laying R.Mt. 12.53
13.5 Earth back filling with compaction Cu.M. 126.50
13.6 Disposal work at least 2.00 KM Cu.M. 335.77

15. DEMOLISHING WORK


15.1 Demolishing - cem.plaster Sq.M. 54.65
15.2 - wall in mud Cu.M. 536.36
15.3 - wall in c.m. Cu.M. 1,072.72
15.4 - PCC Cu.M. 2,116.00
15.5 - RCC Cu.M. 5,566.00

This Rate Analysis is prepared on the basis of approved Norms-


2041 (2nd Rivision) excluding VAT.

Prepared by:- Checked by:- Approved by:-


Ilam /Material Rate-1/35

RATE OF LABOURS & CONSTRUCTION MATERIALS


FOR 2071-72
DISTRICT:- ILAM
Description Unit Rate Remarks
LABOUR RATE
Skilled (carpenter, mason) M.D. 660.00 1.01
Plumber " 660.00 1.06
Helper " 440.00 1.1
Unskilled " 440.00 1.03
Painter " 660.00 1.01
Heavy Driver " 580.00 1.04.02
Driver wages per hour " 72.50
Driver Helper Per Hour " 55.00
CONSTRUCTIONAL MATERIAL RATE
Ceiling with JYP board-fixing in GI under frame- 9-
12mm th Sq.M. 1152.87 10.13.00
Bitumen washer No. 0.30 9.04.04
Bricks 1st class at Bhatta Thousand 19000.00 7.10.13
Cement white M.Ton. 27500.00 7.12.04
Cement Concrete hollo blocks-16"*6"*8" No. 48.00 7.11.02
Cement Nepali 53 grade OPC M.Ton. 15000.00 7.12.01
CGI sheet 26 # (6'x2'8") medium-plain Sq.M. 335.33 9.01.01.02
CGI sheet 26 # (6'x2'8") medium-color Sq.M. 418.55 9.01.02.02
Chheskini - 100-Aluminium No. 45.00 10.02.03.02
Chheskini - 150-Aluminium No. 75.00 10.02.03.04
Chheskini - 200-Aluminium No. 85.00 10.02.03.05
Door closer set- Standard No. 440.00 10.05.02
GI Gabin Wire(Medium-Zinc coat) Kg. 86.00 8.08.02
GI plain sheet 26# ridge 2' wide-0.37mm R.Mt. 280.48 8.05.03
GI plain sheet 24# - Plain-0.40mm Sq.M. 580.44 8.05.02
GI plain sheet 26# 2' wide Coloured-.37mm R.Mt. 382.00 9.01.03.02.03
Glass- Plain - 4mm Sq.M. 516.48 10.06.01.03
Gravel sieved (at river)-20-40 Cu.M. 3300.00 7.08.01.04
Gravel crushed (Crusher) - 10 mm Cu.M. 3100.00 7.08.01.03
Gravel crushed (crusher) - 20 mm Cu.M. 3100.00 7.08.01.03
Gravel crushed (crusher)- 40mm Cu.M. 3100.00 7.08.01.03
Gravel not sieved (at river) Cu.M. 2100.00 7.08.01.02
Gravel sieved (river) - 10 -20mm Cu.M. 3300.00 7.08.01.04
Handle Brass 6" No. 150.00 10.03.01
Hinges - 100mm-14Gauge- No. 30.00 10.01.02
Hinges - 125mm-12Gauge- No. 50.00 10.01.03
Holdfast No. 50.00 8.04.09
Iron Angle Iron -Different size-MS Kg. 130.00 8.10.02.02
Iron Black pipe -Different size-MS-2.6mmth-3.5M long No. 665.00 8.09.02.09
Iron Barbed wire 12# ( 7m/Kg ) R.Mt. 13.57 8.07.04
Iron Collapsible shutter(with fitting)37.66 Kg Sq.M. 4045.00 8.10.01.10
Iron M.S. binding wire Kg. 101.00 8.02.01.01
Iron M.S. grill with fitting Kg. 126.15 8.10.01.02
Iron rod (TMT steel)-Upto 8mm M ton 77000.00 8.01.03
Iron rod (TMT steel)-10 mm &Above M ton 77000.00 8.01.04
Iron Rolling shutter 16 gauge with fitting(30 Kg/Sq.M.) Sq.M. 4215.00 8.10.01.12

Iron gate using -14 to 16 Gauge MS sheet-MS angle


Kg 135.43 8.10.01.09
of different size-one cot primer
J - hook No. 28.33 8.03.01
Listi of Sisaun wood R.Mt. 12.04 Market
Marble chips- 6 mm Cu.M. 36256.00 11.03.03.06

Prepared by:- Checked by:- Approved by:-


Ilam /Material Rate-2/35

RATE OF LABOURS & CONSTRUCTION MATERIALS


FOR 2071-72
DISTRICT:- ILAM
Description Unit Rate Remarks
Marble Slab-16mm-Rajasthani Sq.M. 2433.50 11.01.01
Granite -16mm Sq.M. 3568.75 11.01.03
Mortice lock-Brass No. 985.00 10.04.07
Mosquito net - Indian Sq.M. ?
Mosquito Net- Chainese Sq.M. 175.00 8.08.04.03
Mud sand mixed Cu.M. 105.00 7.03.02
Nails Kg. 120.00 8.04.01
Nut bolt No. 19.00 8.03.02
Nut bolt with washer Kg. 170.00 Market
Paint Aluminium-NS-117 Litre 550.00 12.02.15
Paint-Weather cot Litre 750.00 12.02.20
Paint Barnesh Litre 400.00 12.02.24
Paint Distemper-Wasable-NS-165 Kg. 450.00 12.02.06
Paint Enamel-NS-112 Litre 550.00 12.02.14
Paint Gum Kg. 300.00 12.02.26
Paint Lime Kg. 30.00 12.02.10
Paint Oxalic acid Kg. 250.00 12.02.37
Paint Plastic Emulsion-madium-NS-161 Litre 750.00 12.02.16
Paint Primer Litre 330.00 12.02.01
Paint Red Oxide Litre 400.00 12.02.35
Paint Tarpentine Litre 150.00 12.02.33
Paint Wax polish Kg. 420.00 12.02.25
Plaster of Paris Kg. 31.00 11.03.03.08
Plywood - 3 mm commercial-NS 38 Sq.M. 210.00 10.05.01
Plywood - 4 mm commercial-NS 38 Sq.M. 269.00 10.05.02
Plywood - 6 mm commercial-NS 38 Sq.M. 322.80 10.05.03
Plywood - 12 mm commercial-NS 38 Sq.M. 495.00 10.05.04
Plywood water proof 19 mm thick Sq.M. 1100.00 10.09.05
Sand Cu.M. 1900.00 7.07.02
Sand paper No. 7.08 12.01.01
Screws No. 1.00 market
Stone Cu.M. 1525.00 7.06.01
Stone Dust Cu.M. 824.00 7.08.02.10
Tile Porcelain -Glazed-Wall-NS-76 Sq.M. 758.58 11.03.02.06
Tile Porcelain -Glazed-floor-NS-76 Sq.M. 688.10 11.13.01.06
Water proof compound Kg. 110.00 22.12
Wood Ku-Kath Cu.M. 22880.00 7.09.03
Wood Sal (Not Seasoned) Cu.M. 134090.00 7.09.05
Wood Sisaun (Not Seasoned) Cu.M. 134090.00 7.09.05

Prepared by:- Checked by:- Approved by:-


Transportaion cost-3/35
TRANSPORTATION OF CONSTRUCTION MATERIALS BY TRUCK
i) Truck rent per hour(6t/150HP) according to 450
heaby equipment Division office 450.00
ii) Fuel and lubrication cost
H.S diesel (5.5lit*unit rate) 5.5 100 550.00
Mobil (0.1 lit*unit rate) 0.1 420 42.00
Gear oil (0.03lit*unit rate) 0.03 425 12.75
Grease (0.015*unit rate ) 0.015 352 5.28
Sub Total : 610.03
TOTAL TRANSPORTATION COST per hour, i+ii =E 1060.03

MATERIAL COST AT SITE

Speed of truck , km/hr.(S) ... 40.00


Time per trip by truck = (2*distance/speed + loading & unloading time)
Loading and unloading time = 0.75
For hauling average distance 1 km, hrs 0.80
" " 2 km, hrs 0.85
" " 5 km, hrs 1.00
" " 10 km, hrs 1.25
" " 15 km, hrs 1.50
" " 20 km, hrs 1.75
" " 25 km, hrs 2.00
1. BRICKS
Time (T), hrs 1.00
Distance average, km 5.00
Load unloading coefficient, K 0.406
Capacity of truck per trip, nos. of bricks 2400.00
Transportation cost (E*T) 1060.03
For 1000 nos. of bricks (E*T/2400*1000) 441.00
Load. & unload. cost (K*unskill. labour wage/day) 74.00
Price of 1000 nos. of bricks 19000.00
Per thousand 19515.00
Per unit brick 19.52
2. STONE
Time (T), hrs 1.00
Distance average , km 5.00
Load unloading coefficient, K 0.406
Capacity of truck per trip, cu.m. 3.50
Transportation cost (E*T) 1060.03
For 1cu.m. (E*T/3.5) 302.87
Load. & unload. cost (K*unskill. labour wage/day) 51.04
Price of stone per 1 cu.m. 1525.00
Per 1 cu.m. 1878.91
3. CEMENT
Time (T), hrs 0.80
Distance average , km 1.00
Load unloading coefficient,K 0.221
Capacity of truck per trip, m.t. 6.00
Transportation cost (E*T) 848.02
For 1m.t. (E*T/6) 141.34
Loading & unloading cost (K*unskilled labour wages/day) 16.21

Prepared by:- Checked by:- Approved by:-


Transportaion cost-4/35
Price of cement per m.t. 15000.00
Per m.t. 15157.55
4. IRON ROD
Time (T), hrs 0.80
Distance average, km 1.00
Load unloading coefficient, K 0.221
Truck capacity per trip, m.t. 6.00
Transportation cost (E*T) 848.02
For 1m.t. (E*T/6) 141.34
Loading & unloading cost (K*unskilled labour wages/day) 16.21
Price of iron rod per m.t. average 77000.00
Per m.t. 77157.55
5. SAL WOOD
Time (T), hrs 0.80
Distance average, km 1.00
Load unloading coefficient, K 0.168
Truck capacity per trip, m3 7.50
Transportation cost (E*T) 848.02
For 1m3 (E*T/7.5) 113.07
Loading & unloading cost (K*unskilled labour wages/day) 9.86
Price of 1 cu.m.) 134090.00
Per m.t. 134212.93
Per cu.m. 134212.93
Density of sal (d), kg/cu.m. 800.00
6.OTHER WOOD
Time (T), hrs 0.85
Distance average, km 2.00
Load unloading coefficient, K 0.203
Truck capacity per trip, Cu.m 10.00
Transportation cost (E*T) 901.03
For 1m3 (E*T/10) 90.10
Loading & unloading cost (K*unskilled labour wages/day) 8.93
Price of 1 cu.m.) 22880.00
Per m.t. 22979.03
Per cu.m. 22979.03
Per Sq.m. 459.58
Density of other wood (d), kg/cu.m. 600.00
7. SAND
Time (T), hrs 1.00
Distance average, km 5.00
Load unloading coefficient, K 0.375
Capacity of truck per trip, cu.m. 5.38
Transportation cost (E*T) 1060.03
For 1cu.m. (E*T/5.38) 197.03
Load. & unload. cost (K*unskill. labour wage/day) 30.67
Price of 1cu.m. sand 1900.00
Per cu.m. ... ... 2127.70
Per cu.m. ... ... 2127.70
8. RIVER AGGREGATE (20mm & 40mm)
Time (T), hrs 1.00
Distance average, km 5.00
Load unloading coefficient, K 0.406

Prepared by:- Checked by:- Approved by:-


Transportaion cost-5/35
Capacity of truck per trip, cu.m. 4.69
Transportation cost (E*T) 1060.03
For 1cu.m. (E*T/4.69) 226.02
Load. & unload. cost (K*unskill. labour wage/day) 38.09
Price of 1cu.m. river aggrigate ... ... 3300.00
Per cu.m. ... ... 3564.11
Per cu.m. ... ... 3564.11
9. RIVER AGGREGATE (10mm)
Time (T), hrs 1.00
Distance average, km 5.00
Load unloading coefficient, K 0.406
Capacity of truck per trip, cu.m. 4.69
Transportation cost (E*T) 1060.03
For 1cu.m. (E*T/4.69) 226.02
Load. & unload. cost (K*unskill. labour wage/day) 38.09
Price of 1cu.m. river aggrigate 3300.00
Per cu.m. ... ... 3564.11
Per cu.m. ... ... 3564.11
10. BROKEN AGGREGATE ( 10mm)
Time (T), hrs 1.00
Distance average, km 5.00
Load unloading coefficient, K 0.375
Capacity of truck per trip, cu.m. 5.79
Transportation cost (E*T) 1060.03
For 1cu.m. (E*T/5.79) 183.08
Load. & unload. cost (K*unskill. labour wage/day) 28.50
Price of 1cu.m. broken aggregate ... ... 3100.00
Per cu.m. ... ... 3311.58
Per cu.m. ... ... 3311.58
11. BROKEN AGGREGATE ( 20mm)
Time (T), hrs 1.00
Distance average, km 5.00
Load unloading coefficient, K 0.375
Capacity of truck per trip, cu.m. 5.79
Transportation cost (E*T) 1060.03
For 1cu.m. (E*T/5.79) 183.08
Load. & unload. cost (K*unskill. labour wage/day) 28.50
Price of 1cu.m. broken aggrigate ... ... 3100.00
Per cu.m. ... ... 3311.58
Per cu.m. ... ... 3311.58
12. BROKEN AGGREGATE ( 40mm)
Time (T), hrs 1.00
Distance average, km 5.00
Load unloading coefficient, K 0.375
Capacity of truck per trip, cu.m. 5.79
Transportation cost (E*T) 1060.03
For 1cu.m. (E*T/5.79) 183.08
Load. & unload. cost (K*unskill. labour wage/day) 28.50
Price of 1cu.m. broken aggrigate ... ... 3100.00
Per cu.m. ... ... 3311.58
Per cu.m. ... ... 3311.58
13. SAND(Other querries)

Prepared by:- Checked by:- Approved by:-


Transportaion cost-6/35
Time (T), hrs 1.30
Distance average, km 11.00
Load unloading coefficient, K 0.633
Capacity of truck per trip, cu.m. 5.38
Transportation cost (E*T) 1378.04
For 1cu.m. (E*T/5.38) 256.14
Load. & unload. cost (K*unskill. labour wage/day) 278.52
Price of 1cu.m. sand 900.00
Per cu.m. ... ... 1434.66
Per cu.m. ... ... 1434.66
14. DISPOSAL (For 2 Km.)
Time (T), hrs 0.85
Distance average, km 2.00
Load unloading coefficient, K 0.254
Capacity of truck per trip, cu.m. 5.00
Transportation cost (E*T) 901.03
For 1cu.m. (E*T/5.00) 180.21
Load. & unload. cost (K*unskill. labour wage/day) 111.76
Price of 1cu.m. material. ... ... 0.00
Per cu.m. ... ... 291.97
Per cu.m. ... ... 291.97
15. Mud transportation.
Time (T), hrs 0.85
Distance average, km 2.00
Load unloading coefficient, K 0.254
Capacity of truck per trip, cu.m. 5.00
Transportation cost (E*T) 901.03
For 1cu.m. (E*T/5.00) 180.21
Load. & unload. cost (K*unskill. labour wage/day) 22.35
Price of 1cu.m. material. ... ... 105.00
Per cu.m. ... ... 307.56
Per cu.m. ... ... 307.56
16. Stone dust ransportation.
Time (T), hrs 1.00
Distance average, km 5.00
Load unloading coefficient, K 0.375
Capacity of truck per trip, cu.m. 5.00
Transportation cost (E*T) 1060.03
For 1cu.m. (E*T/5.00) 212.01
Load. & unload. cost (K*unskill. labour wage/day) 33.00
Price of 1cu.m. material. ... ... 824.00
Per cu.m. ... ... 1069.01
Per cu.m. ... ... 1069.01

Prepared by:- Checked by:- Approved by:-


Rate Analysis-1
NEPAL TELECOM
NEPAL DOORSANCHAR COMPANY LIMITED
EASTERN REGIONAL DIRECTORATE
(CIVIL SECTION)
BIRATNAGAR, MORANG

DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM


Items Descript. Unit Quantity U.Rate Amount
1. EARTHWORK
Excavation of soft clay & silty soils Unskilled m.d. 0.70 440.00 308.00
including disposal upto 10m lead Equipment
and 1.5m lift 3%of labour 9.24
Item No. per Sub-Total 317.24
1.1 1 cu.m. Contract Rate(1.15) 364.83
Norms - 2(1) page 5 Contract U.Rate cu.m. 364.83
Earthwork in excav. : soft soil per cu.m. 364.83

Excavation of hard clay and soils mixed Unskilled m.d. 0.80 440.00 352.00
with soft moorum stones (upto 30mm Equipment
size) including disposal upto 10m lead 3%of labour 10.56
and 1.5m lift
Item No. per Sub-Total 362.56
1.2 1 cu.m. Contract Rate(1.15) 416.94
Norms - 2(2) page 5 Contract U.Rate cu.m. 416.94
Earthwork in excav. : B.M.Soil per cu.m. 416.94

Excavation of soft soil, disposal upto Unskilled m.d. 1.00 440.00 440.00
10m lead and 1.5m lift Equipment
3%of labour 13.20
Item No. per Sub-Total 453.20
1.3 1 cu.m. Contract Rate(1.15) 521.18
Norms - 2(9) page 8 Contract U.Rate cu.m. 521.18
E/W excav. for found. Trench - soft soil per cu.m. 521.18

Excavation for foundation drain, pipe Unskilled m.d. 1.59 440.00 699.60
line etc.in boulder mixed soil, disposal Equipment
(upto 10m lead and 1.5m lift) 3%of labour 20.99
Item No. per Sub-Total 720.59
1.4 1 cu.m. Contract Rate(1.15) 828.68
Norms - 2(14) page 9 Contract U.Rate cu.m. 828.68
E/w in excav. for found. trench B.M.Soil per cu.m. 828.68

Filling with ordinary soil in 15 cm thick Unskilled m.d. 0.50 440.00 220.00
layer and hand compaction (haulage
distance 10m) with sprinkling water
Item No. per Sub-Total 220.00
1.5 1 cu.m. Contract Rate(1.15) 253.00
Norms - 2(25a) page 15 Contract U.Rate cu.m. 253.00
Earth filling and compaction with watering per cu.m. 253.00

Filling with ordinary soil by transportation of Unskilled m.d. 0.25 440.00 110.00
mud from 5 km distance Mud Cum. 1.00 307.56 307.56
Item No. per Sub-Total 417.56
1.6 1 cu.m. Contract Rate(1.15) 480.19
Norms - 2(25b) page 15 Contract U.Rate cu.m. 480.19
Mud filling by transportation per cu.m. 480.19

Prepared by:- Checked by:- Approved by:-


Rate Analysis-2
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
Filling by stones in the foundation and Unskilled m.d. 1.50 440.00 660.00
levelling including haulage distance Bloc stone cu.m. 1.00 1878.91 1878.91
upto 30m Bond stone cu.m. 0.20 1878.91 375.78
Item No. per Sub-Total 2914.69
1.7 1 cu.m. Contract Rate(1.15) 3351.89
Norms - 6(5) page 39 Contract U.Rate cu.m. 3351.89
Filling of dry stone at trench per cu.m. 3351.89

Filling by sand and hand compaction Unskilled m.d. 0.70 440.00 308.00
(haulage distance 10m) with sprinkling Sand cu.m. 1.10 2127.70 2340.47
water
Item No. per Sub-Total 2648.47
1.8 1 cu.m. Contract Rate(1.15) 3045.74
Norms - 2(42) page 21 Contract U.Rate cu.m. 3045.74
Filling of sand with water compaction per cu.m. 3045.74

Filling with stone dust by transportation of Unskilled m.d. 0.50 440.00 220.00
dusty from 15 km distance With compaction Stone dust Cum. 1.00 1069.01 1069.01
Item No. per Sub-Total 1289.01
1.9 1 cu.m. Contract Rate(1.15) 1482.36
Norms - 2(25b) page 15 Contract U.Rate cu.m. 1482.36
stone dust filling by transportation per cu.m. 1482.36

2. BRICK WORKS
Dry brick laying (soling) in sand skilled m.d. 0.50 660.00 330.00
a) flat unskilled m.d. 1.00 440.00 440.00
Brick nos. 420.00 19.52 8198.40
Sand cu.m. 0.71 2127.70 1510.67
Item No. per Sub-Total 10479.07
2.1 10 sq.m. Contract Rate(1.15) 12050.93
Norms - 11(15a) page 107 Contract U.Rate sq.m. 1205.09
Dry Brick flat soling. per sq.m. 1205.09

Dry brick laying (soling) in sand skilled m.d. 1.00 660.00 660.00
a) on edge (vertical) unskilled m.d. 3.25 440.00 1430.00
Brick nos. 750.00 19.52 14640.00
Sand cu.m 0.71 2127.70 1510.67
Item No. per Sub-Total 18240.67
2.2 10 sq.m. Contract Rate(1.15) 20976.77
Norms - 11(15b) page 107 Contract U.Rate sq.m. 2097.68
Dry Brick on edge soling. per sq.m. 2097.68

a. BRICK WORK IN MORTAR (for ground floor)


Chimney (bhatta) brick masonry works skilled m.d. 1.50 660.00 990.00
along with supplying bricks making unskilled m.d. 2.20 440.00 968.00
cement sand mortar and construction Brick nos. 560.00 19.52 10931.20
of brick wall including haulage distance Cement m.t. 0.13 15157.55 1970.48
upto 30m Sand cu.m 0.27 2127.70 574.48
a) 1:3 Add.unskill m.d. 0.20 440.00 88.00
At Ground floor Scaffolding 3% of add. Unskilled 2.64
Item No. per Sub-Total 15524.80
2.4a 1 cu.m. Contract Rate(1.15) 17853.52
Norms - 5(1a &1b6) page 32,33 Contract U.Rate cu.m. 17853.52
Brick work in c.m. - 1:3 per cu.m. 17853.52

Chimney (bhatta) brick masonry works skilled m.d. 1.50 660.00 990.00
along with supplying bricks making unskilled m.d. 2.20 440.00 968.00

Prepared by:- Checked by:- Approved by:-


Rate Analysis-3
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
cement sand mortar and construction Brick nos. 560.00 19.52 10931.20
of brick wall including haulage distance Cement m.t. 0.10 15157.55 1515.76
upto 30m Sand cu.m 0.28 2127.70 595.76
a) 1:4 Add.unkill m.d. 0.20 440.00 88.00
At Ground floor Scaffolding 3% of add. Unskilled 2.64
Item No. per Sub-Total 15091.36
2.4b 1 cu.m. Contract Rate(1.15) 17355.06
Norms - 5(1a &1b6) page 32,33 Contract U.Rate cu.m. 17355.06
Brick work in c.m. - 1:4 per cu.m. 17355.06

Chimney (bhatta) brick masonry works skilled m.d. 1.50 660.00 990.00
along with supplying bricks making unskilled m.d. 2.20 440.00 968.00
cement sand mortar and construction Brick nos. 560.00 19.52 10931.20
of brick wall including haulage distance Cement m.t. 0.07 15157.55 1061.03
upto 30m Sand cu.m 0.30 2127.70 638.31
a) 1:6 Add.unskill m.d. 0.20 440.00 88.00
At Ground floor Scaffolding 3% of add. Unskilled 2.64
Item No. per Sub-Total 14679.18
2.4c 1 cu.m. Contract Rate(1.15) 16881.06
Norms - 5(1a &1b6) page 32,33 Contract U.Rate cu.m. 16881.06
Brick work in c.m. - 1:6 per cu.m. 16881.06

Chimney (bhatta) brick masonry works skilled m.d. 1.00 660.00 660.00
along with supplying bricks making unskilled m.d. 1.70 440.00 748.00
mud mortar and construction of brick Brick nos. 560.00 19.52 10931.20
wall including haulage distance upto mud cu.m 0.42 307.56 129.18
30m Add.unskill m.d. 0.20 440.00 88.00
a) mud mortar Scaffolding 3% of add. Unskilled 2.64
Item No. per Sub-Total 12559.02
2.4d 1 cu.m. Contract Rate(1.15) 14442.87
Norms - 5(1a &1b6) page 32,33 Contract U.Rate cu.m. 14442.87
Brick work in mud mortar per cu.m. 14442.87
b. BRICK WORK IN MORTAR (above ground floor)
Chimney (bhatta) brick masonry works skilled m.d. 1.50 660.00 990.00
along with supplying bricks making unskilled m.d. 2.20 440.00 968.00
cement sand mortar and construction Brick nos. 560.00 19.52 10931.20
of brick wall including haulage distance Cement m.t. 0.13 15157.55 1970.48
upto 30m Sand cu.m 0.27 2127.70 574.48
a) 1:3 Add.unskill m.d. 0.70 440.00 308.00
Scaffolding 3% of add. Unskilled 9.24
Item No. per Sub-Total 15751.40
2.5a 1 cu.m. Contract Rate(1.15) 18114.11
Norms - 5(1a &1b6) page 32,33 Contract U.Rate cu.m. 18114.11
Brick work in c.m. - 1:3 per cu.m. 18114.11

Chimney (bhatta) brick masonry works skilled m.d. 1.50 660.00 990.00
along with supplying bricks making unskilled m.d. 2.20 440.00 968.00
cement sand mortar and construction Brick nos. 560.00 19.52 10931.20
of brick wall including haulage distance Cement m.t. 0.10 15157.55 1515.76
upto 30m Sand cu.m 0.28 2127.70 595.76
a) 1:4 Add.unkill m.d. 0.70 440.00 308.00
Scaffolding 3% of add. Unskilled 9.24
Item No. per Sub-Total 15317.96
2.5b 1 cu.m. Contract Rate(1.15) 17615.65
Norms - 5(1a &1b6) page 32,33 Contract U.Rate cu.m. 17615.65
Brick work in c.m. - 1:4 per cu.m. 17615.65

Chimney (bhatta) brick masonry works skilled m.d. 1.50 660.00 990.00

Prepared by:- Checked by:- Approved by:-


Rate Analysis-4
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
along with supplying bricks making unskilled m.d. 2.20 440.00 968.00
cement sand mortar and construction Brick nos. 560.00 19.52 10931.20
of brick wall including haulage distance Cement m.t. 0.07 15157.55 1061.03
upto 30m Sand cu.m 0.30 2127.70 638.31
a) 1:6 Add.unskill m.d. 0.70 440.00 308.00
Scaffolding 3% of add. Unskilled 9.24
Item No. per Sub-Total 14905.78
2.5c 1 cu.m. Contract Rate(1.15) 17141.65
Norms - 5(1a &1b6) page 32,33 Contract U.Rate cu.m. 17141.65
Brick work in c.m. - 1:6 per cu.m. 17141.65

Chimney (bhatta) brick masonry works skilled m.d. 1.00 660.00 660.00
along with supplying bricks making unskilled m.d. 1.70 440.00 748.00
mud mortar and construction of brick Brick nos. 560.00 19.52 10931.20
wall including haulage distance upto mud cu.m 0.42 307.56 129.18
30m Add.unkill m.d. 0.70 440.00 308.00
a) mud mortar Scaffolding 3% of add. Unskilled 9.24
Item No. per Sub-Total 12785.62
2.5d 1 cu.m. Contract Rate(1.15) 14703.46
Norms - 5(1a &1b6) page 32,33 Contract U.Rate cu.m. 14703.46
Brick work in mud mortar per cu.m. 14703.46

3. STONE WORKS
Dry stone laying (soling) in sand skilled m.d. 1.00 660.00 660.00
unskilled m.d. 3.50 440.00 1540.00
stone cu.m 1.10 1878.91 2066.80
Sand cu.m 0.25 2127.70 531.93
Item No. per Sub-Total 4798.73
3.1 1 cu.m. Contract Rate(1.15) 5518.54
Norms - 11(16) page 107 Contract U.Rate cu.m. 5518.54
Stone soling in sand per cu.m. 5518.54

Rubble masonry work including supply skilled m.d. 1.50 660.00 990.00
of hard stone blocks preparing cement unskilled m.d. 5.00 440.00 2200.00
sand mortar and construction of the cement m.t. 0.159 15157.55 2410.05
wall upto 5m high haulage distance Sand cu.m 0.45 2127.70 957.47
upto 10m bl.stone " 1.00 1878.91 1878.91
a) cement sand mortar 1:4 bond st. " 0.10 1878.91 187.89
Item No. per Sub-Total 8624.32
3.2 1 cu.m. Contract Rate(1.15) 9917.97
Norms - 6a(2) page 35 Contract U.Rate cu.m. 9917.97
Stone work in c.m. - 1:4 per cu.m. 9917.97

Rubble masonry work including supply skilled m.d. 1.50 660.00 990.00
of hard stone blocks preparing cement unskilled m.d. 5.00 440.00 2200.00
sand mortar and construction of the cement m.t. 0.106 15157.55 1606.70
wall upto 5m high haulage distance Sand cu.m 0.47 2127.70 1000.02
upto 10m bl.stone " 1.00 1878.91 1878.91
a) cement sand mortar 1:6 bond st. " 0.10 1878.91 187.89
Item No. per Sub-Total 7863.52
3.3 1 cu.m. Contract Rate(1.15) 9043.05
Norms - 6a(3) page 35 Contract U.Rate cu.m. 9043.05
Stone work in c.m. - 1:6 per cu.m. 9043.05

Rubble masonry work including supply skilled m.d. 1.00 660.00 660.00
of hard stone blocks preparing mud unskilled m.d. 2.22 440.00 976.80
mortar and construction of the wall bl.stone cu.m 1.00 1878.91 1878.91

Prepared by:- Checked by:- Approved by:-


Rate Analysis-5
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
upto 5m high haulage distance upto 30m bond st. " 0.10 1878.91 187.89
a) in mud mortar mud " 0.42 307.56 129.18
Item No. per Sub-Total 3832.78
3.4 1 cu.m. Contract Rate(1.15) 4407.70
Norms - 6(1) page 36 Contract U.Rate cu.m. 4407.70
Stone work in mud mortar per cu.m. 4407.70

Rubble masonry work including supply skilled m.d. 1.00 660.00 660.00
of hard stone blocks and construction unskilled m.d. 2.00 440.00 880.00
of the wall upto 5m high haulage bl.stone cu.m 1.00 1878.91 1878.91
distance upto 30 m a) dry wall bond st. " 0.10 1878.91 187.89
Item No. per Sub-Total 3606.80
3.5 1 cu.m. Contract Rate(1.15) 4147.82
Norms - 6(1) page 36 Contract U.Rate cu.m. 4147.82
Stone work - dry wall per cu.m. 4147.82

4. CONCRETE WORKS
Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00
walls (cement concrete) including supply unskilled m.d. 4.00 440.00 1760.00
of materials and haulage distance upto cement m.t. 0.13 15157.55 1970.48
30 m a) P.C.C.(1:3:6) gravel_1 cu.m. 0.65 3564.11 2316.67

Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.24 3564.11 855.39

Gravel_2 =20 mm gravel from river sand cu.m. 0.47 2127.70 1000.02
Item No. per Sub-Total 8562.56
4.1 1 cu.m. Contract Rate(1.15) 9846.94
Norms-7-2(a) page 44 Contract U.Rate cu.m. 9846.94
P.C.C. - ( 1:3:6 ) - river gravel per cu.m. 9846.94

Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00


walls (cement concrete) including supply unskilled m.d. 4.00 440.00 1760.00
of materials and haulage distance upto cement m.t. 0.17 15157.55 2576.78
30 m a) P.C.C.(1:3:6) gravel_1 cu.m. 0.65 3564.11 2316.67
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.24 3564.11 855.39
Gravel_2 =20 mm gravel from river sand cu.m. 0.47 2127.70 1000.02
Item No. per Sub-Total 9168.86
4.1 1 cu.m. Contract Rate(1.15) 10544.19
Norms-7-2(b) page 44 Contract U.Rate cu.m. 10544.19
P.C.C. - ( 1:3:6 ) - river gravel per cu.m. 10544.19

Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00


walls (cement concrete) including supply unskilled m.d. 4.00 440.00 1760.00
of materials and haulage distance upto cement m.t. 0.22 15157.55 3334.66
30 m a) P.C.C.(1:3:6) gravel_1 cu.m. 0.65 3564.11 2316.67
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.24 3564.11 855.39
Gravel_2 =20 mm gravel from river sand cu.m. 0.47 2127.70 1000.02
Item No. per Sub-Total 9926.74
4.1 1 cu.m. Contract Rate(1.15) 11415.75
Norms-7(c) page 44 Contract U.Rate cu.m. 11415.75
P.C.C. - ( 1:3:6 ) - river gravel per cu.m. 11415.75

Prepared by:- Checked by:- Approved by:-


Rate Analysis-6
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount

Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00


walls (cement concrete) including supply unskilled m.d. 4.00 440.00 1760.00
materials and haulage distance upto 30m cement m.t. 0.32 15157.55 4850.42
a) P.C.C.(1:2:4) gravel_1 cu.m. 0.52 3564.11 1853.34
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.22 3564.11 784.10
Gravel_2 =20 mm gravel from river gravel_3 cu.m. 0.11 3564.11 392.05
Gravel_3 =10 mm gravel from river sand cu.m. 0.445 2127.70 946.83
Item No. per Sub-Total 11246.74
4.2 1 cu.m. Contract Rate(1.15) 12933.75
Norms-7(d) page 44 Contract U.Rate cu.m. 12933.75
P.C.C. - 1:2:4 -General work (river gravel) per cu.m. 12933.75

Concreting works of super structure skilled m.d. 0.80 660.00 528.00


deck slabs, beams including supply unskilled m.d. 7.00 440.00 3080.00
of materials and haulage distance upto cement m.t. 0.32 15157.55 4850.42
30 m a) P.C.C. 1:2:4 gravel_1 cu.m. 0.52 3311.58 1722.02
Gravel_1 =40 mm broken ggregate gravel_2 cu.m. 0.22 3311.58 728.55
Gravel_2 =20 mm broken aggregate gravel_3 cu.m. 0.11 3311.58 364.27
Gravel_3 =10 mm broken aggregate sand cu.m. 0.445 2127.70 946.83
Item No. per Sub-Total 12220.09
4.3 1 cu.m. Contract Rate(1.15) 14053.10
Norms-7(4)a page 46 Contract U.Rate cu.m. 14053.10
PCC for RCC (1:2:4) - broken aggregate per cu.m. 14053.10

Concreting works of super structure skilled m.d. 0.80 660.00 528.00


deck slabs, beams including supply unskilled m.d. 7.00 440.00 3080.00
of materials and haulage distance upto cement m.t. 0.40 15157.55 6063.02
30 m. a) P.C.C.(1:1.5:3) gravel_1 cu.m. 0.57 3311.58 1887.60
Gravel_1 =20 mm broken aggregate gravel_2 cu.m. 0.29 3311.58 960.36
Gravel_2 =10 mm broken aggregate sand cu.m. 0.425 2127.70 904.27
Item No. per Sub-Total 13423.25
4.4 1 cu.m. Contract Rate(1.15) 15436.74
Norms-7(4)b page 46 Contract U.Rate cu.m. 15436.74
P.C.C. for RCC - (1:1.5:3) broken aggregate per cu.m. 15436.74

Concreting works of super structure skilled m.d. 0.80 660.00 528.00


deck slabs, beams including supply unskilled m.d. 7.00 440.00 3080.00
of materials and haulage distance upto cement m.t. 0.61 15157.55 9246.11
30 m. a) P.C.C.(1:1:2) gravel_1 cu.m. 0.64 3311.58 2119.41
Gravel_1 =20 mm broken aggregate gravel_2 cu.m. 0.21 3311.58 695.43
Gravel_2 =10 mm broken aggregate sand cu.m. 0.425 2127.70 904.27
Item No. per Sub-Total 16573.22
4.4 1 cu.m. Contract Rate(1.15) 19059.20
Norms-7(4)c page 46 Contract U.Rate cu.m. 19059.20
P.C.C. for RCC - (1:1:2) broken aggregate per cu.m. 19059.20

5. WOODEN WORKS
Making and fixing sal wood skilled m.d. 34.00 660.00 22440.00
chaukhat unskilled m.d. 3.40 440.00 1496.00
salwood cu.m 1.10 134212.93 147634.22
holdfast nos. 92.00 50.00 4600.00
killa " 184.00 1.00 184.00
Item No. per Sub-Total 176354.22

Prepared by:- Checked by:- Approved by:-


Rate Analysis-7
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
5.1 1 cu.m. Contract Rate(1.15) 202807.35
Norms - 10(1) page 75 Contract U.Rate cu.m. 202807.35
Sal wood work - chaukhat per cu.m. 202807.35

Making beams, rafter, purlin cross skilled m.d. 17.65 660.00 11649.00
beams from seasoned sal wood with unskilled m.d. 1.76 440.00 774.40
fitting and fixing wood cu.m 1.05 134212.93 140923.58
killa-L/S Kg. 1.00 120.00 120.00
Item No. per Sub-Total 153466.98
5.2 1 cu.m. Contract Rate(1.15) 176487.03
Norms - 10(17) page 90 Contract U.Rate cu.m. 176487.03
Sal wood work - beam, rafter etc. per cu.m. 176487.03

Making and fixing sal wood panelled skilled m.d. 10.00 660.00 6600.00
shutters using 38 mm sal wood frame unskilled m.d. 1.00 440.00 440.00
wood cu.m 0.084 134212.93 11273.89
Shutter size: hinges nos. 6.00 50.00 300.00
1.07m * 1.982 m=2.114 sq.m. bolt_1 nos. 1.00 75.00 75.00
Hinges (Kabja) - 100 mm bolt_2 nos. 1.00 85.00 85.00
bolt _1(Chheskini) - 150 mm lock nos. 1.00 985.00 985.00
bolt _2(Chheskini) - 300 mm handle nos. 2.00 150.00 300.00
lock - Mortise lock 250 mm nails-L/S Kg. 1.00 120.00 120.00
Item No. per Sub-Total 20178.89
5.3 2.114 sq.m. Contract Rate(1.15) 23205.72
Norms - 10(2) page 76 Contract U.Rate sq.m. 10977.16
Salwood frame panelled shutters (38mm thick) per sq.m. 10977.16

Making and fixing 4 mm thick glazed skilled m.d. 9.00 660.00 5940.00
shutter using sal wood shutter of the unskilled m.d. 0.90 440.00 396.00
size : 38 mm x 75 mm wood cu.m 0.049 134212.93 6576.43
glass sq.m. 1.085 516.48 560.38
hinges nos. 8.00 50.00 400.00
hinges (Kabja) - 75 mm bolts nos. 4.00 45.00 180.00
bolts (Chheskini) - 100 mm handle nos. 2.00 150.00 300.00
screws-L/S Kg. 0.50 120.00 60.00
Item No. per Sub-Total 14412.81
5.4 2.23 sq.m. Contract Rate(1.15) 16574.73
Norms - 10(4) page 78 Contract U.Rate sq.m. 7432.61
Sal frame 38mm thick 4 mm glazed shutters per sq.m. 7432.61

Making and fixing 4 mm commercial skilled m.d. 7.00 660.00 4620.00


plywood flush shutter ( plywood both unskilled m.d. 0.70 440.00 308.00
sides ) in 38 mm sal wood frame. wood cu.m 0.0346 134212.93 4643.77
Shutter size : Plywood sq.m. 4.65 269.00 1250.85
1.092*2.058 = 2.245 hinges nos 3.00 50.00 150.00
lock - Mortise lock bolts nos 2.00 45.00 90.00
hinges - 100 mm lock nos 1.00 985.00 985.00
bolts - 100 mm screws-L/S Kg. 0.75 120.00 90.00
Item No. per Sub-Total 12137.62
5.5 2.245 sq.m. Contract Rate(1.15) 13958.26
Norms - 10(7) page 80 Contract U.Rate sqm 6217.49
Sal frame 38mm thick 4mm plywood shutter per sqm 6217.49

Making and fixing 24 # G.I. plain sheet skilled m.d. 7.00 660.00 4620.00
flush shutters (GI sheer both sides) unskilled m.d. 0.70 440.00 308.00
in 38 mm sal wood frame. wood cu.m 0.0346 134212.93 4643.77
sheet sq.m. 4.65 580.44 2699.05
Shutter size : hinges nos 3.00 50.00 150.00

Prepared by:- Checked by:- Approved by:-


Rate Analysis-8
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
1.092*2.058 = 2.245 sq.m. bolts nos 2.00 45.00 90.00
hinges - 100 mm lock nos 1.00 985.00 985.00
bolts - 100 mm handle nos 1.00 150.00 150.00
lock - Mortise lock screws-L/S Kg. 0.75 120.00 90.00
Item No. per Sub-Total 13735.82
5.6 2.245 sq.m. Contract Rate(1.15) 15796.19
Norms - 10(9) page 82 Contract U.Rate sq.m. 7036.16
Sal frame 38mm th. G.I. plain sheet shutter per sq.m. 7036.16

Making and fixing 4 mm thick glass skilled m.d. 0.06 660.00 39.60
using necessary listi. unskilled m.d. 0.006 440.00 2.64
glass sq.m. 1.00 516.48 516.48
listi r.m. 4.05 12.04 48.76
nails-L/S Kg. 0.50 120.00 60.00
Item No. per Sub-Total 667.48
5.10 1 sq.m. Contract Rate(1.15) 767.60
Norms-10(11)b page 84 Contract U.Rate sq.m. 767.60
4 mm glass with listi on frames per sq.m. 767.60

Fixing of plane sheet skilled m.d. 0.06 660.00 39.60


using listi.(24 Gauge) unskilled m.d. 0.006 440.00 2.64
Sheet sq.m. 1.05 580.44 609.46
listi r.m. 4.05 12.04 48.76
nails-L/S Kg. 0.50 120.00 60.00
Item No. per Sub-Total 760.46
5.11 1 sq.m. Contract Rate(1.15) 874.53
Norms - similar to 10(12) page 85 Contract U.Rate sq.m. 874.53
24 gauge plane sheet fixing work with listy per sq.m. 874.53

Making wooden form work including supply skilled m.d. 1.72 660.00 1135.20
and selection of materials fixing, nailing unskilled m.d. 2.57 440.00 1130.80
according to drawings, placing separa- wood cu.m. 0.07 22979.03 1608.53
tors, dismantling forms and hauling killa kg 2.50 120.00 300.00
upto 30 m distance (Use of wood 7 times)
Item No. per Sub-Total 4174.53
5.12 10 sq.m. Contract Rate(1.15) 4800.71
Norms-8(2a) page 55 Contract U.Rate sq.m. 480.07
Wooden Form work for slab per sq.m. 480.07

For analysis -9.75x3.65=35.58m2


12mm th commercial plywood on both side works with 38 skilled m.d. 23.00 660.00 15180.00

salwood frame of size 0.61x0.915m unskilled m.d. 2.30 440.00 1012.00

with wooden listy on joints sal wood cu.m. 0.35 134212.93 46974.53

12mm ply Sq.m 75.00 495.00 37125.00

Listy Rm 100.00 12.04 1204.00


killa kg 3.00 120.00 360.00
Item No. per Sub-Total 101855.53
5.13 35.58 sq.m. Contract Rate(1.15) 117133.86
Norms-1(10-14b) Contract U.Rate sq.m. 3292.13
12mm th commercial plywood on both side works per sq.m. 3292.13

= analysis =10m2
For

Prepared by:- Checked by:- Approved by:-


Rate Analysis-9
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
25mmth wooden planking works skilled m.d. 6.50 660.00 4290.00
frame size-699x600mm-Frame size unskilled m.d. 0.65 440.00 286.00
wooden size-50x75mm sal wood cu.m. 0.42 134212.93 56369.43
killa kg 2.00 120.00 240.00
Item No. per Sub-Total 61185.43
5.14 10 sq.m. Contract Rate(1.15) 70363.24
Norms-1(11-21b) Contract U.Rate sq.m. 7036.32
12mm th commercial plywood on both side works per sq.m. 7036.32

6. PLASTERING WORKS
12.5 mm thick cement sand plastering skilled m.d. 15.00 660.00 9900.00
works for ceiling unskilled m.d. 20.00 440.00 8800.00
a) Cement sand ratio - 1:3 cement m.t. 0.625 15157.55 9473.47
sand cu.m 1.28 2127.70 2723.46
Item No. per Sub-Total 30896.93
6.1 100 sq.m. Contract Rate(1.15) 35531.47
Norms-12(1b) page 110 Contract U.Rate sq.m. 355.31
12.5mm cement sand (1:3) plaster in ceilling. per sq.m. 355.31

12.5 mm thick cement sand plastering skilled m.d. 15.00 660.00 9900.00
works on ceiling unskilled m.d. 20.00 440.00 8800.00
a) Cement sand ratio - 1:4 cement m.t. 0.538 15157.55 8154.76
sand cu.m 1.46 2127.70 3106.44
Item No. per Sub-Total 29961.20
6.2 100 sq.m. Contract Rate(1.15) 34455.38
Norms-12(1c) page 110 Contract U.Rate sq.m. 344.55
12.5mm cement sand (1:4) plaster in ceilling. per sq.m. 344.55

12.5 mm thick cement sand plastering skilled m.d. 12.00 660.00 7920.00
works on walls unskilled m.d. 16.00 440.00 7040.00
a) Cement sand ratio - 1:4 cement m.t. 0.538 15157.55 8154.76
sand cu.m 1.46 2127.70 3106.44
Item No. per Sub-Total 26221.20
6.3 100 sq.m. Contract Rate(1.15) 30154.38
Norms-12(1c) page 110 Contract U.Rate sq.m. 301.54
12.5mm cement sand (1:4) plaster work. per sq.m. 301.54

12.5 mm thick cement sand plastering skilled m.d. 12.00 660.00 7920.00
works unskilled m.d. 16.00 440.00 7040.00
a) Cement sand ratio - 1:6 cement m.t. 0.382 15157.55 5790.18
sand cu.m 1.57 2127.70 3340.49
Item No. per Sub-Total 24090.67
6.4 100 sq.m. Contract Rate(1.15) 27704.27
Norms-12(1d) page 110 Contract U.Rate sq.m. 277.04
12.5mm cement sand (1:6) plaster work. per sq.m. 277.04

20 mm thick cement sand plastering skilled m.d. 14.00 660.00 9240.00


works unskilled m.d. 19.00 440.00 8360.00
a) Cement sand ratio - 1:4 cement m.t. 0.810 15157.55 12277.62
sand cu.m 2.20 2127.70 4680.94
Item No. per Sub-Total 34558.56
6.5 100 sq.m. Contract Rate(1.15) 39742.34
Norms-12(4 b) page 112 Contract U.Rate sq.m. 397.42
20mm cement sand (1:4) plaster work. per sq.m. 397.42

Prepared by:- Checked by:- Approved by:-


Rate Analysis-10
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
Flush cement pointing works in cement skilled m.d. 10.50 660.00 6930.00
sand ratio 1:2 unskilled m.d. 12.00 440.00 5280.00
a) In brick masonry cement m.t. 0.21 15157.55 3183.09
sand cu.m 0.29 2127.70 617.03
Item No. per Sub-Total 16010.12
6.6 100 sq.m. Contract Rate(1.15) 18411.64
Norms-14(1a) page 121 Contract U.Rate sq.m. 184.12
Flush cement pointing 1:2 - in brick per sq.m. 184.12

Flush ruled pointing works in cement skilled m.d. 10.00 660.00 6600.00
sand ratio 1:2 unskilled m.d. 14.00 440.00 6160.00
a) In stone masonry cement m.t. 0.408 15157.55 6184.28
sand cu.m 0.75 2127.70 1595.78
Item No. per Sub-Total 20540.06
6.7 100 sq.m. Contract Rate(1.15) 23621.07
Norms-14(2b) page 122 Contract U.Rate sq.m. 236.21
Flush cement pointing 1:2 - in stone per sq.m. 236.21

3 mm thick fine cement rubbing works skilled m.d. 1.00 660.00 660.00
unskilled m.d. 1.00 440.00 440.00
cement kg 53.20 15.16 806.51
Item No. per Sub-Total 1906.51
6.8 10 sq.m. Contract Rate(1.15) 2192.49
Norms-11(20) page 109 Contract U.Rate sq.m. 219.25
3mm cement punning per sq.m. 219.25

Plain Plaster of Paris on walls and ceilings skilled m.d. 1.00 660.00 660.00
unskilled m.d. 1.00 440.00 440.00
POP kg 53.20 31.00 1649.20
Item No. per Sub-Total 2749.20
6.9 10 sq.m. Contract Rate(1.15) 3161.58
Norms-11(20) page 110 Contract U.Rate sq.m. 316.16
Plain Plaster of Paris per sq.m. 316.16

7. FLOORING WORKS
Dry brick on edge soling with cement sand skilled m.d. 1.10 660.00 726.00
(1:6) and pointing by (1:2) C/S in joints unskilled m.d. 1.80 440.00 792.00
Cement m.t. 0.121 15157.55 1834.06
Brick nos. 750.00 19.52 14640.00
Sand cu.m 0.431 2127.70 917.04
Item No. per Sub-Total 18909.10
7.1 10 sq.m. Contract Rate(1.15) 21745.47
Norms - 11(13) page 106 Contract U.Rate sq.m. 2174.55
Brick vertical soling in (1:6) and Pointing per sq.m. 2174.55

25 mm thick mosaic flooring with skilled m.d. 3.50 660.00 2310.00


19 mm thick cement plaster (1:2) base unskilled m.d. 36.00 440.00 15840.00
course and 6 mm thick marble chips cement m.t. 0.121 15157.55 1834.06
white cement (1:1) surface course sand cu.m 0.165 2127.70 351.07
including rubbing and polishing wh.cement m.t. 0.069 27500.00 1897.50
marble cu.m 0.047 36256.00 1704.03
Note:- acid kg 0.34 250.00 85.00
acid - oxalic acid mainpolish kg 0.11 420.00 46.20
stone - carborand stone tarpentine litre 0.50 150.00 75.00
stone L.S. 120.00
Item No. per Sub-Total 24262.86
7.2 10 sq.m. Contract Rate(1.15) 27902.29

Prepared by:- Checked by:- Approved by:-


Rate Analysis-11
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
Norms-11(3) page 99 Contract U.Rate sq.m. 2790.23
25mm thick Mozaic flooring per sq.m. 2790.23

Tile Porcelain -Glazed-Wall-NS-76 skilled m.d. 13.00 660.00 8580.00


mortar unskilled m.d. 4.50 440.00 1980.00
tile sq.m 11.00 758.58 8344.38
Note:- cement m.t. 0.056 15157.55 848.82
Tile Porcelain -Glazed-Wall-NS-76 sand cu.m 0.152 2127.70 323.41
wh.cement kg 3.228 27.50 88.77
Item No. per Sub-Total 20165.38
7.3 10 sq.m. Contract Rate(1.15) 23190.19
Norms-11(7) page 103 Contract U.Rate sq.m. 2319.02
Tile Porcelain -Glazed-Wall-NS-76 per sq.m. 2319.02

Tile Porcelain -Glazed-Floor-NS-76 skilled m.d. 13.00 660.00 8580.00


mortar unskilled m.d. 4.50 440.00 1980.00
tile sq.m 11.00 688.10 7569.10
Note:- cement m.t. 0.056 15157.55 848.82
Tile Porcelain -Glazed-Floor-NS-76 sand cu.m 0.152 2127.70 323.41
wh.cement kg 3.228 27.50 88.77
Item No. per Sub-Total 19390.10
7.3 10 sq.m. Contract Rate(1.15) 22298.62
Norms-11(7) page 103 Contract U.Rate sq.m. 2229.86
Tile Porcelain -Glazed-Floor-NS-76 per sq.m. 2229.86

35 mm thick marble flooring with skilled m.d. 2.00 660.00 1320.00


20 mm thick cement plaster (1:2) base unskilled m.d. 8.00 440.00 3520.00
course and 15 mm thick marble slab marble slab sq m 11.00 2433.50 26768.50
cement m.t. 0.130 15157.55 1970.48
sand cu.m 0.183 2127.70 389.37
acid kg 0.37 250.00 92.50
Note:- mainpolish kg 0.118 420.00 49.56
acid - oxalic acid tarpentine litre 0.538 150.00 80.70
stone - carborand stone stone L.S. 120.00
Machine or Labour for Polishing. unskilled m.d. 13.50 440.00 5940.00
Item No. per Sub-Total 40251.11
7.4 10 sq.m. Contract Rate(1.15) 46288.78
Norms-11(6) page 102 Contract U.Rate sq.m. 4628.88
Marble slab flooring per sq.m. 4628.88

Granite flooring -16mm skilled m.d. 13.00 660.00 8580.00


mortar unskilled m.d. 4.50 440.00 1980.00

tile sq.m 11.00 3568.75 39256.25


Note:- cement m.t. 0.056 15157.55 848.82
Granite-16mm th sand cu.m 0.152 2127.70 323.41
wh.cement kg 3.228 27.50 88.77
Item No. per Sub-Total 51077.25
7.3 10 sq.m. Contract Rate(1.15) 58738.84
Norms-11(7) page 103 Contract U.Rate sq.m. 5873.88

Granite flooring -16mm per sq.m. 5873.88

38mm Cement oncreting for flooring skilled m.d. 1.25 660.00 825.00
and cement punning all complete unskilled m.d. 2.00 440.00 880.00

Prepared by:- Checked by:- Approved by:-


Rate Analysis-12
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
cement m.t. 0.13 15157.55 1970.48
a) P.C.C.(1:2:4) gravel_1 cu.m. 0.36 3311.58 1192.17
Gravel_1 =12 mm broken aggregate gravel_2 cu.m. 0.00
sand cu.m. 0.180 2127.70 382.99
Item No. per Sub-Total 5250.64
4.4 10 sq.m. Contract Rate(1.15) 6038.24
Norms-11(1)c page 87 Contract U.Rate cu.m. 603.82
P.C.C. flooring in 1:2:4 with punning per cu.m. 603.82

50mm Cement oncreting for flooring skilled m.d. 1.25 660.00 825.00
and cement punning all complete unskilled m.d. 2.50 440.00 1100.00
cement m.t. 0.17 15157.55 2576.78
a) P.C.C.(1:2:4) gravel_1 cu.m. 0.46 3311.58 1523.33
Gravel_1 =12 mm broken aggregate gravel_2 cu.m. 0.00
sand cu.m. 0.230 2127.70 489.37
Item No. per Sub-Total 6514.48
4.4 10 sq.m. Contract Rate(1.15) 7491.65
Norms-11(1)d page 87 Contract U.Rate cu.m. 749.17
P.C.C. flooring in 1:2:4 with punning per cu.m. 749.17

8. ROOFING WORKS
26 gause C.G.I. sheet roofing works skilled m.d. 1.10 660.00 726.00
with supply of materials all complete unskilled m.d. 1.25 440.00 550.00
CGIsheet sq.m. 12.00 335.33 4023.96
nutbolt nos. 30.00 19.00 570.00
J-hook nos. 25.00 28.33 708.25
bit.washer nos. 55.00 0.30 16.50
Item No. per Sub-Total 6594.71
8.1 10 sq.m. Contract Rate(1.15) 7583.92
Norms-9(1) page 69 Contract U.Rate sq.m. 758.39
CGI sheet roofing - 26 # per sq.m. 758.39

26 gauge C.G.I. sheet roofing works skilled m.d. 1.10 660.00 726.00
with supply of materials all complete unskilled m.d. 1.25 440.00 550.00
(Colourded CGI sheet) CGIsheet sq.m. 12.00 418.55 5022.60
nutbolt nos. 30.00 19.00 570.00
J-hook nos. 25.00 28.33 708.25
bit.washer nos. 55.00 0.30 16.50
Item No. per Sub-Total 7593.35
8.2 10 sq.m. Contract Rate(1.15) 8732.35
Norms-9(1) page 69 Contract U.Rate sq.m. 873.24
CGI sheet roofing - 26 # Coloured per sq.m. 873.24

Making ridge of 24 gause G.I. plain skilled m.d. 2.00 660.00 1320.00
sheet and fitting with supply of unskilled m.d. 3.00 440.00 1320.00
materials all complete GIplain r.m. 12.00 280.48 3365.76
nutbolt nos. 10.00 19.00 190.00
Item No. per Sub-Total 6195.76
8.3 10 r.m. Contract Rate(1.15) 7125.12
Norms-9(2) page 69 Contract U.Rate Rm 712.51
CGI sheet ridge - 24 # (60cm wide) per Rm 712.51

Prepared by:- Checked by:- Approved by:-


Rate Analysis-13
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
Making ridge of 26 gause G.I. plain skilled m.d. 2.00 660.00 1320.00
sheet and fitting with supply of unskilled m.d. 3.00 440.00 1320.00
materials all complete GIplain r.m. 12.00 382.00 4584.00
nutbolt nos. 10.00 19.00 190.00
Item No. per Sub-Total 7414.00
8.4 10 r.m. Contract Rate(1.15) 8526.10
Norms-9(2) page 69 Contract U.Rate Rm 852.61
CGI sheet ridge - 26 # (60cm wide) Coloured per Rm 852.61

Plain G.I.Sheet of 24 gauge skilled m.d. 2.00 660.00 1320.00


sheet and fitting with supply of unskilled m.d. 3.00 440.00 1320.00
materials all complete GIplain sqm 12.00 580.44 6965.28
nutbolt nos. 10.00 19.00 190.00
Item No. per Sub-Total 9795.28
8.5 10 Sq.m. Contract Rate(1.15) 11264.57
Norms-9(2) page 69 Contract U.Rate sqm 1126.46
GI plane sheet work - 24 # per sqm 1126.46

Making various types of false ceiling in salwood skilled m.d. 23.00 660.00 15180.00
frame of size 50mm*75mm making room unskilled m.d. 2.30 440.00 1012.00
600*900 using 4 mm commercial plywood wood cu.m. 0.45 134212.93 60395.82
Ceiling size plywood sq.m. 37.50 269.00 10087.50
9.75 x 3.65 = 35.59 sq.m. listi, killa L.S. 150.00
Item No. per Sub-Total 86825.32
8.7 35.59 sq.m. Contract Rate(1.15) 99849.12
Norms-10(16a) page 89 Contract U.Rate sq.m. 2805.54
False Ceiling - 4mm plywood with sal frame per sq.m. 2805.54

9. STEEL WORKS
G.I. barbed wire fencing with supply skilled m.d. 1.076 660.00 710.16
of materials and fitting all complete unskilled m.d. 5.380 440.00 2367.20
barb.wire Rm 110.00 13.57 1492.70
nails-L/S Kg. 2.00 120.00 240.00
Item No. per Sub-Total 4810.06
9.1 100 m Contract Rate(1.15) 5531.57
Norms-24(6) page 240 Contract U.Rate Rm 55.32
Barbed wire 12# fencing per Rm 55.32

Supplying, making & fixing of MS Grill with paint M.S.Grill


of 3x20mm size (13.45Kg/Sq.M.) (3x20 mm) K.G. 13.45 126.15 1696.72
Fitting & welding etc K.G. 0.00 0.00 0.00
Primer L/s 5.00
Item No. per Sub-Total 1701.72
9.8 1 Sq.M. Contract Rate(1.15) 1956.98
Norms-24(1a) page 238 Contract U.Rate sqm 1956.98
MS Grill work 3x20mm per Sq.M. 1956.98

Supplying, making & fixing of MS Grill M.S.Grill


of 4.5x20mm size (20.17Kg/Sq.M.) (4.5x20 mm) K.G. 20.17 126.15 2544.45
Fit & welding etc K.G. 20.17 0.00 0.00
Primer L/s 5.00
Item No. per Sub-Total 2549.45
9.9 1 Sq.M. Contract Rate(1.15) 2931.87
Norms-24(1b) page 238 Contract U.Rate sqm 2931.87
MS Grill work 4.5x20mm per Sq.M. 2931.87

Iron Collapsable Gate Iron Gate Sq.M. 10.00 4045.00 40450.00

Prepared by:- Checked by:- Approved by:-


Rate Analysis-14
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
Per Sq.m.= 37.66 Kg. Fitting charge Sq.M. 10.00 0.00 0.00
Primer L/s 2 lit. 0.00
Item No. per Sub-Total 40450.00
9.10 10 sq.m. Contract Rate(1.15) 46517.50
Norms-24-4 Contract U.Rate sq.m. 4651.75
Iron Collapsable Gate per sq.m. 4651.75

Iron Rolling Shutter(18 Gauge) Rolling Sh. Sq.M. 10.00 4215.00 42150.00
Arround 30 Kg./Sq.m. Fitting charge Sq.M. 10.00 0.00 0.00
Primer L/s 0.00
Item No. per Sub-Total 42150.00
9.11 10 sq.m. Contract Rate(1.15) 48472.50
Norms-24-2 Contract U.Rate sq.m. 4847.25
Iron Rolling Shutter per sq.m. 4847.25

Ms angle fixing work. Ms angle Kg. 1.05 130.00 136.50


Primer L/s 5.00
Welding etc. L/S 1.00 10.00 10.00
Item No. per Sub-Total 151.50
9.13 1 Kg. Contract Rate(1.15) 174.23
Norms-24-4 Page 239 Contract U.Rate Kg. 174.23
Ms angle fixing work with primer. per Kg. 174.23

Making of gabin with 100*120 mm size mesh skilled m.d. 0.45 660.00 297.00
with Medium GI wire mesh unskilled m.d. 0.20 440.00 88.00
(2.00*1.00*1.00 m.) GI wire Kg. 34.35 86.00 2954.10
Item No. per Sub-Total 3339.10
9.14 10 Sqm. Contract Rate(1.15) 3839.97
Norms-16(4a) page 159 Contract U.Rate Sqm 384.00
Gi Gabin (100*120 mm mesh size) per Sqm 384.00

Making of gabin with 80*100 mm size mesh skilled m.d. 0.50 660.00 330.00
with Mesh wire 10 SWG,Selwage Wire-7 SWG unskilled m.d. 0.20 440.00 88.00
GI wire Kg. 28.40 86.00 2442.40
Box size (2.00*1.00*1.00 m.) Selwage wire Kg. 3.15 86.00 270.90
Item No. per Sub-Total 3131.30
9.15 10 Sqm. Contract Rate(1.15) 3601.00
Norms-16(2a) page 156 Contract U.Rate Sqm 360.10
Gi Gabin (80*100 mm mesh size) per Sqm 360.10

Cutting, bending, placing in position as skilled m.d. 12.00 660.00 7920.00


shown in the drawing & binding by GI unskilled m.d. 12.00 440.00 5280.00
wire of reinforcement steel bar for RCC iron rod<=8mm m.t. 1.05 77157.55 81015.43
works incl. haulage dist. upto 30m bind.wire kg 10.00 101.00 1010.00
Item No. per Sub-Total 95225.43
9.16 1 m.t. Contract Rate(1.15) 109509.24
Norms-7( 5) page 47 Contract U.Rate m.t. 109509.24
Iron rod( TOR steel) for RCC per kg 109.51

10. PAINTING WORKS


2 coat white washing with gum in new skilled m.d. 1.50 660.00 990.00
surface unskilled m.d. 1.10 440.00 484.00
chuna kg 22.00 30.00 660.00
gum kg 0.88 300.00 264.00
Item No. per Sub-Total 2398.00
10.1 100 sq.m. Contract Rate(1.15) 2757.70

Prepared by:- Checked by:- Approved by:-


Rate Analysis-15
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
Norms-13(1b) page 114 Contract U.Rate sq.m. 27.58
2 coat white washing work in new surface. per sq.m. 27.58

Water proof cement paint (Snowcem) skilled m.d. 5.00 660.00 3300.00
application unskilled m.d. 5.00 440.00 2200.00
a) in 2 coats Snowcem kg 48.50 100.00 4850.00
Item No. per Sub-Total 10350.00
10.2 100 sq.m. Contract Rate(1.15) 11902.50
Norms-13(4b) page 116 Contract U.Rate sq.m. 119.03
2 coats Snowcem painting per sq.m. 119.03

Prepared enamel paint application skilled m.d. 8.00 660.00 5280.00


in addition to one base or lining coat unskilled m.d. 5.00 440.00 2200.00
(primer) primer litre 8.10 330.00 2673.00
a) in 1 coats enamel litre 9.00 550.00 4950.00
Item No. per Sub-Total 15103.00
10.3 100 sq.m. Contract Rate(1.15) 17368.45
Norms-13(5b) page 117 Contract U.Rate sq.m. 173.68
1 coat primer + 1 coat enamel painting per sq.m. 173.68

Prepared enamel paint application skilled m.d. 12.00 660.00 7920.00


in addition to one base or lining coat Unskilled m.d. 8.00 440.00 3520.00
(primer) primer litre 8.10 330.00 2673.00
a) in 2 coats enamel litre 16.00 550.00 8800.00
Item No. per Sub-Total 22913.00
10.4 100 sq.m. Contract Rate(1.15) 26349.95
Norms-13(5c) page 117 Contract U.Rate sq.m. 263.50
Primer +2 coats enamel paint in New surface per sq.m. 263.50

Prepared alluminium paint application skilled m.d. 10.75 660.00 7095.00


work with one coat primer unskilled m.d. 10.75 440.00 4730.00
primer litre 8.10 330.00 2673.00
a) in 2 coats alumin.pnt litre 10.76 550.00 5918.00
kakhsi sh. nos. 4.00 7.08 28.32
Item No. per Sub-Total 20444.32
10.5 100 sq.m. Contract Rate(1.15) 23510.97
Norms-13(6) page 117 Contract U.Rate sq.m. 235.11
Primer +2 coats aluminium painting per sq.m. 235.11

One Coats of Distemper Paint skilled m.d. 4.00 660.00 2640.00


application unkilled m.d. 4.00 440.00 1760.00
Primer Lit. 8.00 330.00 2640.00
a) in 1 coats Distemper kg 6.50 450.00 2925.00
Item No. per Sub-Total 9965.00
10.6 100 sq.m. Contract Rate(1.15) 11459.75
Norms-13(3a,b) page 115 Contract U.Rate sq.m. 114.60
1 coats distemper painting per sq.m. 114.60

Two or more coats of distemper paint skilled m.d. 5.80 660.00 3828.00
application unkilled m.d. 5.80 440.00 2552.00
Primer Lit. 8.00 330.00 2640.00
a) in 2 coats Distemper kg 11.50 450.00 5175.00
Item No. per Sub-Total 14195.00
10.7 100 sq.m. Contract Rate(1.15) 16324.25
Norms-13(3a,b & c) page 115 Contract U.Rate sq.m. 163.24
2 coats distemper painting per sq.m. 163.24

One Coats of Plastic Emulsion Paint skilled m.d. 8.00 660.00 5280.00

Prepared by:- Checked by:- Approved by:-


Rate Analysis-16
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
application unkilled m.d. 5.00 440.00 2200.00
Primer Lit. 8.10 330.00 2673.00
a) in 1 coats Emulsion Lit. 9.00 750.00 6750.00
Item No. per Sub-Total 16903.00
10.8 100 sq.m. Contract Rate(1.15) 19438.45
Norms-13(5 a,b) page 117 Contract U.Rate sq.m. 194.38
1 coats Plastic Emulsion painting per sq.m. 194.38

Two or more coats of Plastic Emulsion paint skilled m.d. 12.00 660.00 7920.00
application unkilled m.d. 8.00 440.00 3520.00
Primer Lit. 8.10 330.00 2673.00
a) in 2 coats Emulsion Lit. 16.00 750.00 12000.00
Item No. per Sub-Total 26113.00
10.9 100 sq.m. Contract Rate(1.15) 30029.95
Norms-13(5 a,b & c) page 117 Contract U.Rate sq.m. 300.30
2 coats Plastic Emulsion painting per sq.m. 300.30

One Coats of Apex Paint skilled m.d. 8.00 660.00 5280.00


application unkilled m.d. 5.00 440.00 2200.00
Primer Lit. 8.10 330.00 2673.00
a) in 1 coats Apex Lit. 9.00 750.00 6750.00
Item No. per Sub-Total 16903.00
10.10 100 sq.m. Contract Rate(1.15) 19438.45
Norms-13(5 a,b) page 117 Contract U.Rate sq.m. 194.38
1 coats Apex painting with Primer per sq.m. 194.38

Two or more coats of Apex paint skilled m.d. 12.00 660.00 7920.00
application unkilled m.d. 8.00 440.00 3520.00
Primer Lit. 8.10 330.00 2673.00
a) in 2 coats Apex Lit. 16.00 750.00 12000.00
Item No. per Sub-Total 26113.00
10.11 100 sq.m. Contract Rate(1.15) 30029.95
Norms-13(5 a,b & c) page 117 Contract U.Rate sq.m. 300.30
2 coats Apex painting with Primer per sq.m. 300.30

12. WATER PROOFING WORK


38 mm thick Damp Proof Course of skilled m.d. 1.00 660.00 660.00
cement concrete of the ratio 1:2:4 unskilled m.d. 2.00 440.00 880.00
Note :- cement m.t. 0.12 15157.55 1818.91
Sieved gravel from river sand cu.m. 0.17 2127.70 361.71
gravel20 mm cu.m. 0.34 3564.11 1211.80
W.P.C. kg 2.88 110.00 316.80
Item No. per Sub-Total 5249.22
12.1 10 sq.m. Contract Rate(1.15) 6036.60
Norms-18(9) page 188 Contract U.Rate sq.m. 603.66
38mm thick D.P.C. (1:2:4) with WPC. per sq.m. 603.66

Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00


walls (cement concrete) including supply unskilled m.d. 4.00 440.00 1760.00
materials and haulage distance upto 30m cement m.t. 0.32 15157.55 4850.42
with safecrete. safecrete litre 12.80 280.00 3584.00
a) P.C.C.(1:2:4) gravel_1 cu.m. 0.52 3564.11 1853.34
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.22 3564.11 784.10
Gravel_2 =20 mm gravel from river gravel_3 cu.m. 0.11 3564.11 392.05
Gravel_3 =10 mm gravel from river sand cu.m. 0.445 2127.70 946.83
Item No. per Sub-Total 14830.74
12.2 1 cu.m. Contract Rate(1.15) 17055.35

Prepared by:- Checked by:- Approved by:-


Rate Analysis-17
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
Norms-7(d) page 44 Contract U.Rate cu.m. 17055.35
Water proofing (P.C.C. -1:2:4, Safecrete ) per cu.m. 17055.35

13. NETWORK RATES


Pitch cutting works for cable trench with Unskilled m.d. 10.00 440.00 4400.00
haulage distance 10M.
Item No. per Sub-Total 4400.00
13.1 10 Sqm. Contract Rate(1.15) 5060.00
Norms - 19 (8) Page 192 Contract U.Rate Sqm. 506.00
Pitch cutting work per Sqm. 506.00

Site clearence work Cutting of Top soil, Unskilled m.d. 0.06 440.00 26.40
levelling,and Leading of disposal.

Item No. per Sub-Total 26.40


13.2 1 sq.m. Contract Rate(1.15) 30.36
Norms - 1(8) page 4 Contract U.Rate sq.m. 30.36
Site clearence work of top surface. per sq.m. 30.36

19mm plywood form work including supply skilled m.d. 2.67 660.00 1762.20
of materials fixing, nailing according to drawing unkilled m.d. 4.00 440.00 1760.00
and dismantling of formworks. plywood sq.m 1.65 1100.00 1815.00
(Use of plywood six times) Local-wood cu.m 0.039 22979.03 896.18
Steel Prop No 0.400 665.00 266.00
nails kgs 2.50 120.00 300.00
Item No. per Sub-Total 6799.38
13.3 10 sq.m. Contract Rate(1.15) 7819.29
Norms - 51(a) -KTM Contract U.Rate sq.m. 781.93
19 mm plywood Form work. per sq.m. 781.93

laying of 6 meter long 110mm dia, PVC Plumber m.d. 1.00 520.00 520.00
Duct pipe in proper level and jiont Unskilled m.d. 8.00 350.00 2800.00
Item No. per Sub-Total 3320.00
13.4 1000 Rft Contract Rate(1.15) 3818.00
Norms as available from Network PID. Contract U.Rate R.ft. 3.82
laying of 110 mm PVC duct pipe. per Rmt. 12.53

Filling with ordinary soil in 15 cm thick layer Unskilled m.d. 0.25 440.00 110.00
with hand compaction (haulage distance 10M)

Item No. per Sub-Total 110.00


13.5 1 cu.m. Contract Rate(1.15) 126.50
Norms - 2(25b) page 15 Contract U.Rate cu.m. 126.50
Earth back filling and compaction work per cu.m. 126.50

Disposal of excess earth work from site Disposal cu.m. 1.00 291.97 291.97
at least 2.00KM far from site.

Item No. per Sub-Total 291.97


13.6 1 cu.m. Contract Rate(1.15) 335.77
As per Tranportation analysis. Contract U.Rate cu.m. 335.77
Disposal work at least 2.00KM far from site. per cu.m. 335.77

Norms of Item No.13.3 and 13.4 are available from NTC, PID Kupandol

15. DEMOLISHING WORKS

Prepared by:- Checked by:- Approved by:-


Rate Analysis-18
DISTRICT:- ILAM RATES for 2071/72 SITE:- ILAM
Items Descript. Unit Quantity U.Rate Amount
Demolishing cement or mortared plaster unskilled m.d. 0.108 440.00 47.52
and removing demolished materials upto
10 m away from the site
Item No. per Sub-Total 47.52
15.1 1 sq.m. Contract Rate(1.15) 54.65
Norms-19(5) page 191 Contract U.Rate sq.m. 54.65
Demolishing : cement plaster per sq.m. 54.65

Demolishing mud mortared masonry unskilled m.d. 1.06 440.00 466.40


wall and removing demolished mate-
rials upto 10 m away from the site
Item No. per Sub-Total 466.40
15.2 1 cu.m. Contract Rate(1.15) 536.36
Norms-19(1) page 191 Contract U.Rate cu.m. 536.36
Demolishing : wall in mud per cu.m. 536.36

Demolishing cement mortared masonry unskilled m.d. 2.12 440.00 932.80


wall and removing demolished mate-
rials upto 10 m away from the site
Item No. per Sub-Total 932.80
15.3 1 cu.m. Contract Rate(1.15) 1072.72
Norms-19(2) page 191 Contract U.Rate cu.m. 1072.72
Demolishing: wall in cement mortar per cu.m. 1072.72

Demolishing P.C.C. or mortared concrete unskilled m.d. 4.00 460.00 1840.00


and removing demolished materials upto
10 m away from the site
Item No. per Sub-Total 1840.00
15.4 1 cu.m. Contract Rate(1.15) 2116.00
Norms-19(4) page 191 Contract U.Rate cu.m. 2116.00
Demolishing : P.C.C. per cu.m. 2116.00

Demolishing R.C.C. or R.B.C. works unskilled m.d. 11.00 440.00 4840.00


and removing demolished materials upto
10 m away from the site
Item No. per Sub-Total 4840.00
15.5 1 cu.m. Contract Rate(1.15) 5566.00
Norms-19(3) page 191 Contract U.Rate cu.m. 5566.00
Demolishing : R.C.C. per cu.m. 5566.00

Prepared by:- Checked by:- Approved by:-


Rate analysis for Gabion, page 19

NEPAL TELECOM
NEPAL DOORSANCHAR COMPANY LIMITED
CENTRAL OFFICE
(CIVIL DEPARTMENT)
BHADRAKALI PLAZA
DISTRICT:- BANKE SITE:- NEPALGANJ
RATES for 2068/69
Items Description Unit Quantity U.Rate Amount

Making of hecxagonal box of 100mm*120mm mesh, 10 SWG skilled m.d. 0.45 660.00 297.00
mesh wire and 7 SWG salwage wire boxes size: 2*1*1m unskilled m.d. 1.100 440.00 484.00
GI wire Kg. 24.15 80.00 1932.00
Salvedge wire Kg. 3.15 80.00 252.00
Binding wire (11SWG) Kg. 1.15 75.00 86.25
Stone Cum 2.20 564.96 1242.91
Item No. per Sub-Total 4294.16
1.1 1 box Contract Rate(1.15) 4938.28
Norms - similar to 16(5)Ka, 16(6) ka, 16(11) Contract U.Rate Box 4938.28
Gabion box , size 2*1*1m per Box 4938.28

Making of rectangular box of 100mm*100mm mesh, 10 SWG skilled m.d. 0.70 660.00 462.00
mesh wire and 7 SWG salwage wire boxes size: 3*1.5*0.75m unskilled m.d. 1.54 440.00 677.60
GI wire Kg. 33.30 80.00 2664.00
binding wire (11SWG) Kg. 1.60 75.00 120.00
Stone Cum 3.71 564.96 2096.00
Item No. per Sub-Total 6019.60
1.2 1 Box Contract Rate(1.15) 6922.54
Norms - similar to 16(9)Ka, 16(6) Kha, 16(11) Contract U.Rate Box 6922.54
Gabion box , size 3*1.5*0.75m per Box 6922.54

Prepared by Checked by Approved by


Rate Analysis Ilam, 71-72

ANALYSIS OF RATES
FOR
DESCRIPTION OF WORKS : WOODEN FORM WORK FOR R.C.C. COMPONENETS INCLUDING
REMOVING OF FORM WORK ALL COMPLETE.
ITEM NO.
54, 8-2KA UNIT : 10 Sqm
S.NO. ITEMS QUANTITY RATE AMOUNT REMARKS
A MATERIALS
a LOCAL WOOD 0.07 m3 33,000.00 2,310.00
b NAILS 2.50 Kg 120.00 300.00

TOTAL COST OF MATERIALS : 2,610.00


B LABOURS:
a CARPENTER 1.72 Nos. 660.00 1,135.20
b COOLIE 2.57 Nos. 440.00 1,130.80

TOTAL COST OF LABOURS : 2,266.00


C SUNDRIES, TOOLS & PLANTS @ 3% OF (g):
D SUB TOTAL (A+B+C) : 4,876.00
E CONTRACTOR'S OVERHEAD @ 15% OF (D) 731.40
F TOTAL (D+E) : 5,607.40
G GOVERNMENT TAX (VAT) @ 13% OF (F) 728.96
G R A N D T O T A L (With VAT) 6,336.36
G R A N D T O T A L (Without VAT) 5,607.40
Rate per m2 with VAT 633.64
Rate per m2 without VAT 560.74

1 jfn'jf eg]{, kfgL 5g]{ / HofdLf/f sDk]s ug]{ sfd


B3 -!) dL6/ 9'jfgL ;d]t_
b/ ljZn]if0fsf] nflu ! 3= ld= lnOPsf]
k|To]s ;|f]t
b/ k|lt
;|f]t ;fwg txlsl;d kl/df0f PsfO{ /sd ;fwgsf]
PsfO{
hDdf
>lds Hofld 0.7 hjfg 440.00 308.00 308.00
jfn'jf 1.1 3=dL= 900.00 990.00
lgdf{0f ;fdu|L
kfgL 5.00 nL6/ 0.25 1.25 991.25
jf:tljs b//]6 1299.25
b/ k|lt 3=dL=sf] !% 7]s]bf/ cf]e/x]8 194.88
?= 1494.13 k}= hDdf b/ /]6 1494.13

Making and fixing sal wood panelled skilled m.d. 10.00 660.00 6,600.00

Prepared by:- Checked by:- Approved by:-


Rate Analysis Ilam, 71-72

shutters using 38 mm sal wood frame unskilled m.d. 1.00 440.00 440.00
wood cu.m 0.084
Shutter size: hinges nos. 6.00 50.00 300.00
1.07m * 1.982 m=2.114 sq.m. bolt_1 nos. 1.00 75.00 75.00
Hinges (Kabja) - 100 mm bolt_2 nos. 1.00 85.00 85.00
bolt _1(Chheskini) - 150 mm lock nos. 1.00 985.00 985.00
bolt _2(Chheskini) - 300 mm handle nos. 2.00 150.00 300.00
lock - Mortise lock 250 mm nails-L/S Kg. 1.00 120.00 120.00
Item No. per Sub-Total 8,905.00
5.3 2.114 sq.m. Contract Rate(1.15) 10,240.75
Norms - 10(2) page 76 Contract U.Rate sq.m. 4,844.25
Salwood frame panelled shutters (38mm thick) per sq.m. 4,844.25

Prepared by:- Checked by:- Approved by:-


Rate Analysis Ilam, 71-72

Prepared by:- Checked by:- Approved by:-


Rate Analysis Ilam, 71-72

Prepared by:- Checked by:- Approved by:-


ESTIMATED QUANTITIES OF MATERIALS REQUIRED PER CUBIC METRE OF COMPACTED MORTAR OR CONCRETE

NOMINAL MIX WATER CEMENT


WATERRATIO CEMENT SAND CRUSHE
CEMEN F.A. C.A. PER BY BY (CUM) D
T 50KG WEIGHT NUMBE STONES
BAG OF (KG) R OF (CUM)
CEMEN BAGS
1 1 - 0.25 12.5 1015 20.3 0.71 -
1 1.5 0.28 14 815 16.3 0.855 -
1 2 - 0.3 15 687 13.74 0.963 -
1 2.5 - 0.35 17.5 585 11.7 1.023
1 3 - 0.4 20 505 10.1 1.06 -
1 4 - 0.53 26.5 395 7.9 1.106 -
1 6 - 0.7 35 285 5.7 1.197 -
1 8 - 0.9 45 220 4.4 1.232 -
1 1 2 0.3 15 560 11.2 0.392 0.784
1 2 2 0.42 21 430 8.6 0.602 0.602
1 1.5 3 0.42 21 395 7.9 0.414 0.828
1 1.66 3.33 0.48 24 363 7.26 0.419 0.838
1 2 3 0.5 25 385 7.7 0.539 0.808
1 2 3.5 0.53 26.5 330 6.6 0.462 0.808
1 2 4 0.55 27.5 310 6.2 0.434 0.868
1 2.5 3.5 0.57 28.5 305 6.1 0.534 0.748
1 2.5 4 0.6 30 285 5.7 0.499 0.798
1 3 4 0.65 32.5 265 5.3 0.556 0.742
1 2.5 5 0.65 32.5 255 5.1 0.446 0.892
1 3 5 0.69 34.5 240 4.8 0.504 0.84
1 3 6 0.75 37.5 215 4.3 0.452 0.904
1 4 8 0.95 47.5 165 3.3 0.462 0.924

Notes:

1. F.A.= Fine Aggregates, C.A.= Coarse Aggregates

2. The table is based on assumption that the voids in sand and crushed stone are 40 and 45 percent respectively.

3. Air content of 1 percent has been assumed.

4. For gravel aggregates decrease cement by 5 percent, increase sand by 2 percent and coarse aggregate in proportion to fine aggregate in mix

4. No allowance has been made in the table for bulking of sand and wastage./>
0.3
3.333333

ortion to fine aggregate in mix.

You might also like