Professional Documents
Culture Documents
Balu E. George
Department of Civil Engineering, IIT Madras Chennai 600036, India
balueliasgeorge@yahoo.co.in
Hari G.
Department of Civil Engineering Saintgits College of Engineering, Kerala 686011, India
hari.g@saintgits.org
ABSTRACT: This paper presents a numerical investigation conducted on bored cast in situ piles and under reamed piles
in cohesive soil to understand and compare the failure pattern under axial loads. Conventional bored cast in situ piles of
two different shaft diameters, single under reamed pile and double under reamed pile were subjected to vertical loading.
The geometry of the under reamed piles were chosen in accordance with the Indian code (IS 2911) specification. Finite
Element Analysis was conducted using commercially available Plaxis 3D 2013, assuming Mohr-Coulomb failure for soil.
The failure mode and ultimate load in compression and tension were examined in cohesive soil. It was observed that the
load carrying capacity increased by 119% in tensile load and 102% in compressive loads for single under reamed piles,
whereas the corresponding values for double under reamed piles were 204% and 180%. Difference in failure pattern
observed for different geometries considered for numerical analysis are also touched upon. The study suggests that under
reamed piles is an effective option in cohesive soil if the ground is stable enough to stand on its own during formation of
cavity.
KEYWORDS: Under-reamed piles, cohesive soil, Plaxis 3D
1
The Sixth International Geotechnical Symposium6IGSChennai2015
Chennai, India, January 21-23, 2015
Notation Description Meshing was further refined around the pile. Interface
elements were modelled with the reduction factor taken
Uniform shaft of 300mm diameter,
P0.3 equal to the adhesion factor between concrete and the
without any bulb
clay. Wehnert and Vermeer 2004 [5] commented that
Uniform shaft of 500mm diameter, the results of a calculation without interface elements
P0.5
without any bulb are highly mesh dependant. When interface elements
Shaft of 300mm diameter with a were used, the mesh dependency was found to be
P0.8S single bulb of 800mm diameter at 4m negligible, especially for shaft resistance.
depth
Shaft of 300m diameter with two Phases of analysis
bulbs of 800m diameter each at The analysis is divided into four phases. In the initial
P0.8D
1.25Du spacing, with bottom bulb at phase, generation of initial stress using k0 procedure is
4m depth adopted as default step. In the next phase (Phase 1), the
soil in the pile cluster was deactivated to simulate
excavation to create pile cavity. The cavity was
NUMERICAL ANALYSIS reactivated with pile material in the following Phase
(Phase 2 ) thereby simulating the process of concreting
Finite Element Analysis was carried out using
PLAXIS 3D 2013 version. The extend of soil mass of cavity. Interface elements were subsequently
activated. In the last phase (Phase 3), the axial
chosen was such that the influence zone falls well
within the boundary. After a few trial runs, it was found compressive loading was simulated on top of the pile
volume as prescribed displacement. To compare the
The Sixth International Geotechnical Symposium6IGSChennai2015
Chennai, India, January 21-23, 2015
load carrying capacity, each pile was given a prescribed length, where pile-soil interface friction is not
displacement of 10% Ds downwards where Ds equal to mobilized.
30mm. From the practical field point of view, such
settlement failure criteria are more logical than shear CONCLUSION
failure (Bowles J.E). However, it was found that the The results of numerical analysis using Plaxis 3D are
piles failed by general shear failure much before presented in this paper to examine the load carrying
reaching the settlement corresponding to the popular capacity and failure patterns associated with four
theories. Hence the L1-L2 criterion is considered here. different geometries of bored cast in situ piles under
The results of Plaxis 3D analysis are explained in axial loading in soft clay. Following conclusions may
following session. be drawn from the study
TEST RESULTS AND OBSERVATIONS Comparing the piles used for the study, it is found that
the load carrying capacity of 0.5m diameter pile is
Fig 3 shows the load-settlement plot in axial
76% greater in compression and 85% greater in tension
compressive loading of P0.3,P0.5, P0.8S and P0.8D
than a 0.3m diameter pile. But the volume of concrete
considered in the present numerical study. It is worth
used is 177.7% extra.
noting that the conventional piles, prismatic in cross
section invariably exhibits plunging failure under axial Load carrying capacity in compression is increased
compression, whereas the under reamed piles on the 102% when a single bulb of diameter 2.6D is provided
other hand follows a pattern comparable to general at bottom. The corresponding increase in tension is
shear failure. 119%.
The increase is load carrying capacity of double under
Fig 3: Load Vs Settlement in axial compression reamed pile is 180% in compression and 204% in
tension at an increase in volume of concrete by 77%.
Feasibility
The observations leads to the conclusion that double
Fig. 4: Load Vs Settlement in axial tension under reamed pile is a highly cost-effective proposition
in terms of material input, in agreement to the
observations made by Kurian and Srilakshmi [3].
Soil Failure Mechanism However, proper care should be taken to ensure cavity
stability during construction. For the same reason, they
It is worth having a good understanding of the soil are not advisable in soil with sandy strata and clay of
behaviour surrounding the piles, which is helpful to loose consistency which are incapable of self standing
reveal the soil-pile interaction mechanism during during the time gap between employing the under
axial loading. By evaluating the deformed pattern of reaming tool for bulb cutting and the subsequent
bored cast in situ piles, it can be understood that the concreting. However, in stiff cohesive soil, under
zone of influence in uplift is predominantly in the reamed piles are recommended over conventional piles
immediate vicinity of the pile shaft. The soil mass as suggested by observations from figure 5. It was also
involved in failure of double under reamed pile is observed that the under reamed cavity did not show
concentrated within the space between the bulbs. any chance of caving in during Phase 1. Had it been of
The soil to soil friction or cohesion formed on the larger diameter in a softer soil, chances are high that
hypothetical cylindrical surface between the centers the cavity becomes unstable upon deactivation of the
of the bulbs mobilizes full undrained shear strength soil cluster in a soft clay medium. Another observation
( =1) unlike the conventional pile-soil interface worth noticing is that the suggestion by IS 2911 in
(Figure 5). This phenomenon is partly responsible regard of keeping bulb spacing as 1.25Du to 1.5Du is
for the increase in the bearing resistance in axial found to be effective in mobilizing the cylindrical
loading. friction action for the range of undrained shear strength
considered in the present study.
3
The Sixth International Geotechnical Symposium6IGSChennai2015
Chennai, India, January 21-23, 2015
(b)
Fig. 6: Deformation contour of double under reamed pile
in (a) Compression and (b) Tension
REFERENCE
1. Bowles J E., Foundation Analysis and Design,
McGraw-Hill New York.,1988
2. IS:2911 (Part III) - 1980: Indian Standard Code
of Practice for Design and Construction of Pile
Foundations. Underreamed Piles (First
Revision), Bureau of Indian Standards, New
Delhi, with Amendment No.1 - Jan. 1983,
Amendment No.2 - Sept.1984, Amendment No. 3
- July, 1987.
3. Kurian, N.P. and Srilakshmi, G. (2001). "
(a) Studies on geometrical features of under reamed
piles by finite element method," Proceedings of
the Indian Geotechnical Conference, Indore, 1,
135-138.
4. Sladen, J. A. (1992). The adhesion factor:
applications and limitations.Canadian
Geotechnical Journal, 29(2), 322-326.
5. Wehnert, M. and Vermeer, P. A.
(2004)Numerical analysis of load test on bored
piles, Indian institute of geotechnical
engineering, University of Stuttgart, Germany,
Numog 9th, 2004