Daily Report

Oven Management Team Monday, Sept'


COKE Plant Contents
S/L G/L Operator Total
Total 1 2 10 13
Member
Vacancy 0 0 0 0
Today 1 2 10 13
* Inspection & problem checking at oven battery area
- #1 & #2 Battery Main Facility and Utility
- TEX and Lamp installation was finished at oven management room EL+8240
- Mechanical, Electrical, Refractory
- Fire hydrant key hand over with Mr Bambang (PT.Citra), total: 8 EA (4 set)
* Safety Training at Headquarter auditorium
- Content : Watching animation video about actual work accident
Aditya
S/L - Instructor : Mr. Acep Permana
Purna N
- Time : 10.00 ~ 11.00 am.
* Reporting and communication both superior and subordinate.
- Supervision daily report
* Field study, accompanying Mr Dani (New Foreman) at Oven Battery Area
* Controlling and monitoring operator.
* There is a problem at control valve flange amonia liquor with stick damper, because it crash
other (S/P no. #48, #51, #57, #59, #66)
* VP and TBM meeting before work (Safety Slogan Iron Making & Hyoksin)
- Giving job Desc' to the operator's
- Temperature checking cross wall
- COP Facility (Lubrication & Specification) and CPCT Facility, Oven Management (Erection pro
Sidik * Guide the new foreman to study about COB and the process
G/L Setiawan * Checking progress status in the oven top #2 Battery (Piping, S/P & Gooseneck)
* Invitation to training safety hazards in HQ (Electric, Gas, Rotary machine, Height)
* Guide operator to check temperature cross wall
* Monitoring operators to do them job with well
* Cleaning day with all expansion team at oven top #2 Battery
.Status of construction progress
Equipment Major progress status
* Installation pipe for HP amonia liquor in the s/p (Continue)
* Installation cable for thermocouple in GC Main (Continue)
* Installation pipe in bleeder connect to LP amonia Liquor line (Continue)
* Installation fresh water pipe to the GC Main near s/p no #66 (Complete)
* Tight flange bolting fresh water supply at the G.C Main near s/p no #73 (Comp't)
* Joint pipe by welding in the amonia liqour line near offtake main no #4 (Comp't)
* Installation globe valve to the fresh water line in G.C Main (s/p no #64) (Comp't)
Oven Top * Preparing to install pipe for COG gas in the offtake main no. #3 (Complete)
(Selva) * Installation steam pipe (Continue)
* Connecting pipe for sealing water in lid S/P ( continue )
#2
* Connecting cable of thermocouple in s/p : 42/42 ea ( complete )
Batt'
* Centering measured between axis point (Continue)
* Stick damper crash with valve amonia liqour high pressure
no. #48, #51, #57, #59, #66 ( issue )
* Installation pipe for Nitrogen line in GC Main ( continue )
* Installation pipe for LP ammonia liqour in GC MAIN ( continue )
# Pusher Side
Oven * Adjuting all Spring at Buckstay No. 45, 44, 43
Door
(Rusjaya) # Coke Side
* Adjusting all Spring at Buckstay No. 45, 44, 43
* Repairing of pipe lubrication system in travel drive has been finished (Charging car)
* Installation of pipe lubrication system in door extractor in progress (Pusher Car)
* installation of pipe lubrication system in door cleaner in progress (Pusher Car)
* Repairing of pipe lubrication system in door extractor in progress (Transfer car)
Oil, greasing * Installation of hdraulic system in coke pan has been finished
and lubrication
* Pipe line for lubrication system on pusher car, charging car, and transfer car
checking
(Arman)
Oil, greasing Daily Report
and lubrication
Oven Management Team Monday, Sept'
checking
COKE Plant
(Arman) Contents

* 2nd Floor
- Finishing of concrete brick in area reversing winch #2 battery (continue)
- Installation of conduit pipe for electric cable in reversing winch #1 battery
* 3th Floor
- Installation of tex (jayaboard) (Finish)
* 6th Floor
- Installation of pressure (WISE) EN837-1
- Installation of transmitter
Model: EJA 530A, supply: 10.5-30, output: 4-20 mA DC, mwp: 20 bar
- Installation of conduif pipe for electric cable
Coal Tower
- Installation of panel AIRCHOC
(Dicky)
* 7th Floor
- Installation of pipe duct connection for hood system (continue)
- Installation of pipe duct support (continue)
- Installation of manual damper and automatic damper (cylinder) to pipe duct
Specifications automatic damper: DN 300 mm, Temp: 300, No: 12118
Cylinder merk: AIRTAC, model: SC63x250-TC (continue)
- Installation of pull cord (KIEPE), type: HEN
- Installation of belt sway switch (KIEPE), type: HES017
- Centering grid coupling (continue)
- Connection electric cable for reversing conveyor local control panel CBC-03
# PECS
- Repair Concrete for hydraulic coupling (no progress)
# Quenching Tower
- Moving Machine Cleaning area quenching
- Installation Lamp in quenching tower : 8/16 ea (continue)
- Installation Cover Fresh water pool (continue)
- Testing Spray in quenching tower
PECS, Q/T & S/P - Q/T checking, there are problems in drains toward settling pond
(Ahmad) - Q/T checking, there are problems leakage in fresh water valve
- Welding support fresh water pipe
# Settling Pond
- Installation filter box : 7/12 ea (continue)
- Testing fresh water and vertical pump)
- Changing Selenoid valve: 2ea

# Surge bin
- Test operating BC-111
# Crusher
- Continue installing wall at crusher building floor 4

CP - Grinding cooling water pipe after welding


(Faizal, - Welding pipe dedusting unit from floor 3 to BF02
Arisandi) # Blending bin
- Lifting pipe dedusting unit for connection from top blending bin to BF03
- Welding support beam for pipe dedusting unit at top blending bin
- Prepare for connecting pipe dedusting unit at top blending bin bulding
- Connecting pipe dedusting unit at tripper car
#WHARF #YARD
*SPESIFICATION *Finishing drainase stacker and reacleam
1.COLUMN PLATES:Finish,lock plate-27 not installed*Wellding procces gallery C-162
2.SIDE PLATE WEAR PLATE1:Finish *Transfer tower 162 installation chute
Daily Report
Oven Management Team Monday, Sept'
COKE Plant Contents
3.SIDE PLATE WE R PLATE2: Finish #BUNKER
4.MIDLE PLATE WEAR PLATE1:Finish *installation chute Transfer tower 161
5.MIDLE SIDE WEAR PLATE2:Finish *Finishing procces,Grinding and wellding
6.ANGLE WEAR PLATE1:Finish *installation cabel line area
7.MIDLE SIDE WEAR PLATE3:Finish *C-171 No project and ceramic liners no p
CT 8.MIDLE SIDE WEAR PLATE4:Finish *Welding H- Beam construction project
(Chandra) 9:ANGLE WEAR PLATE2:Finish *Finishing Concrete area Vibrating Feede
10.NOSE:Material-7Pcs
11.WALL PLATES:Finish
12.BOTTOM PLATES:FINISH
13.BELOW PLATES:Finish
14.HORIZONTAL PLATES:Finish
15.NOSE PLATES:Material-20Pcs
16.STARTING WEAR PLATES RIGHT:Repair project
17.STARTING WEAR PLATES LEFT:No project
18.TOP END WEAR PLATES:Finish
Monday, Sept' 23rd 2013

Remark

cause it crashed each

nt (Erection progress)

ng car)

r)
Monday, Sept' 23rd 2013

and reacleamer area

ation chute
Monday, Sept' 23rd 2013

tower 161
and wellding (1st)

mic liners no project (2nd)


tion project
brating Feeder (3rd)
Daily Report
Oven Management Team Tuesday, Sept'
COKE Plant Contents
S/L G/L Operator Total
Total 1 2 10 13
Member
Vacancy 0 0 0 0
Today 1 2 10 13
* Inspection & problem checking at oven battery area
- #1 & #2 Battery Main Facility and Utility
- Mechanical, Electrical, Refractory
- There was a lot of rubbish inside the G/C main sealing sealing rope, it was not
good, so we have already cleaned inside it (complete, 42 EA)
* Commisioning & Heating-Up Meeting
- time : 10.00 ~ 10.45 am
- Participant : 1.PW : Mr.Nikolai & Mr.Thierry
2.PTKP : Mr.Kim Jong In, Aditya, Agasa
3.IPCR : Mr. Lee Dong Hee
- Content : 1. Today we start spring adjustment because expansion has already begin to
2. Piano wire <--> Buckstay measurement must be done by IPCR.
3. There is wrong measurement done between axis battery to end buckstay
Aditya 4. Dry sealing process (#2 batt) start from tomorrow.
S/L
Purna N 5. We have to clean oven chamber due to silica dry sealing remains by air b
6. Wooden space installation between H/W to Buckstay must be checked by
7. Mirror plate bolt tighting must be done by GM
- Time : 11.00 ~ 11.20
- Participant : 1.IPCR : Mr Lee Dong Hee & Mr. Ahn Yoeng Ho
2.PTKP: Aditya, Sidik,Dani
3. TTP : Mr Yusdi, Yasin
- Content : 1. PT.TTS will support refractory work (maintenance activities) in COP.
2. Organization Chart will be given to PTKP later.
* Reporting
- Measuring fence installationboth
and communication superior and
of quenching car subordinate.
driving Track (Autocad Drawing)

- Supervision daily report


- Review about CPCT line (C-Line and K-Line)
* Controlling and monitoring foreman and operator.
* VP and TBM meeting before work (Safety Slogan Iron Making & Hyoksin)
- Giving job Desc' to the operator's
- Temperature checking cross wall
- COP Facility (Lubrication & Specification) and CPCT Facility, Oven Management (Erection pro
* Guide the new foreman to study about COB and the process
Sidik * Guide operator to check temperature at P/S & C/S oven door #1 Battery
G/L Setiawan * Meeting with TTP company, IPCR, and KP about Oven Maintenance
* Checking progress status in the oven top #2 Battery (Piping, S/P, Bleeder & Gooseneck)
* Meeting with PT. Nuri about paging installation
* Guide operator to check temperature cross wall
* Monitoring operators to do them job with well
* Cleaning day with all expansion team at oven top #1 Battery and sealing stand pipe area
.Status of construction progress
Equipment Major progress status
* Installation pipe for HP amonia liquor in the s/p (Continue)
* Installation cable for thermocouple in GC Main (Continue)
* Installation pipe in bleeder connect to LP amonia Liquor line (Continue)
* Cleaning area oven top
* Installation support for cable thermocouple ( continue )
* Installation COG pipe in bleeder ( continue )
* Mortar dry sealing in charging hole chamber no # 84
Oven Top * Installation pipe for LP ammonia liqour in bleeder ( continue )
(Selva) * Installation steam pipe (Continue)
* Connecting pipe for sealing water in lid S/P ( complete )
#2
* Installation steam pipe in bleeder no # 3 and # 4 (Continue)
Batt'
* Centering measured between axis point (Continue)
* Installation pipe for LP ammonia liqour in GC MAIN near s/p no. # 49 and #54
Oven Top
(Selva)

#2 Daily Report
Batt'
Oven Management Team Tuesday, Sept'
COKE Plant Contents
* Installation pipe for Nitrogen line in GC Main ( continue )
* Installation pipe for LP ammonia liqour in GC MAIN ( continue )
* Temperature checking cross wall : 6wall
# Pusher Side
Oven * Measuring Buckstay level
Door # Coke Side
(Rusjaya) * Installed steel for centering Tranfer Car

* Installation of pipe lubrication system in door extractor in progress (Pusher Car #1)
* installation of pipe lubrication system in door cleaner in progress (Pusher Car #1)
* Pipe line for lubrication system on pusher car, charging car, and transfer car (Continue)
Oil, greasing * Installation of panel pressure valve in travel drive (charging car #1)
and lubrication * Ram beam test (Pusher car #2)
checking
(Arman)

* 1st Floor
- Installation of hand rail
* 2nd Floor
- Finishing of concrete brick in area reversing winch battery #2 (finish)
- Installation of conduif pipe for electric cable in reversing winch battery #1
- Connection of electric cable in panel 342JB001, 341JB002, and 341JB003
* 6th Floor
- Connection of electric cable in pressure, transmitter, and valbia valve
* 7th Floor
- Installation of pipe duct connection for hood system (continue)
Coal Tower
- Installation of pipe duct support (continue)
(Dicky)
- Installation of manual damper and automatic damper (cylinder) to pipe duct
Specifications automatic damper: DN 300 mm, Temp: 300, No: 12118
Cylinder merk: AIRTAC, model: SC63x250-TC (continue)
- Centering grid coupling (continue)
- Installation of chute switch (VEGAVIB 63)
Specifications: temp: -50...+150C, length: 250mm, pressure: -1...+16 bar
- Installation of valve for air
- Installation of line conduif pipe for electric cable
- Testing of conveyor C-124 and C-125

# PECS
- Repair Concrete for hydraulic coupling (no progress)
# Quenching Tower
- Install Lamp in stairs : 2ea
- Install Lamp in Quenching tower : 8ea
PECS, Q/T & S/P
- Repair Valve, because valve leakage
(Ahmad)
- Remove Scaffolding
- Remove Buffle Flap
- Installation Cover Fresh water pool
# Settling Pond
- Remove filter box : 0/12 ea
# Surge bin
- Repair speed switch
#Crusher
- Removing deflector unit of chute C-111 crusher
CP - Installing cage bag filter at dedusting unit no. 02
(Faizal,
Arisandi) # Blending bin
Daily Report
CP Management Team
Oven Tuesday, Sept'
(Faizal,
COKE Plant
Arisandi) Contents
- Closing end pipe dedusting unit for chute C-111
- Installation cover dedusitng unit pipe top hopper
- Connecting pipe dedusting unit at chute C-113
- Installation cover dedusting unit pipe top hopper blending no. 8,9,10,11,12,13,14
#WHARF
*SPECIFICATION
16.STARTING WEAR PLATES RIGHT:Repair concrete and installation starting wear
plate.total material:3Pcs
18.TOP END WEAR PLATES:Repair concrete.total material:1Pcs
#YARD
*Fhinishing concrete left position
CT *Continue concrete project right position
(Chandra) *Instalation of cable stacker and reakleamer area
*Transfer tower 162 of instalation gallery area Transfer tower 162.
#BUNKER
*Installation skirt board in area Transfer tower 161,Bolthing M:24
*Bolting Chute connecting castafel,bolhing M:24
*Fhinishing area Vibrating feeder
*Bolthing skirt board of inlet chute k171
*Welding of H-beam,gallery area Vibrating feeder and Finishing Concrete project
Tuesday, Sept' 24th 2013

Remark

ready begin today.(#1 batt)

o end buckstay.

mains by air blowing.


be checked by IPCR

s) in COP.

nt (Erection progress)

ooseneck)

d pipe area
Tuesday, Sept' 24th 2013

ar #1)

Continue)
Tuesday, Sept' 24th 2013
Daily Report
Oven Management Team Tuesday, Sept'
COKE Plant Contents
S/L G/L Operator Total
Total 1 2 10 13
Member
Vacancy 0 0 0 0
Today 1 2 10 13
* Inspection & problem checking at oven battery area
- #1 & #2 Battery Main Facility and Utility
- Mechanical, Electrical, Refractory
- There was a lot of rubbish inside the G/C main sealing sealing rope, it was not
good, so we have already cleaned inside it (complete, 42 EA)
* Commisioning & Heating-Up Meeting
- time : 10.00 ~ 10.45 am
- Participant : 1.PW : Mr.Nikolai & Mr.Thierry
2.PTKP : Mr.Kim Jong In, Aditya, Agasa
3.IPCR : Mr. Lee Dong Hee
- Content : 1. Today we start spring adjustment because expansion has already begin to
2. Piano wire <--> Buckstay measurement must be done by IPCR.
3. There is wrong measurement done between axis battery to end buckstay
Aditya 4. Dry sealing process (#2 batt) start from tomorrow.
S/L
Purna N 5. We have to clean oven chamber due to silica dry sealing remains by air b
6. Wooden space installation between H/W to Buckstay must be checked by
7. Mirror plate bolt tighting must be done by GM
- Time : 11.00 ~ 11.20
- Participant : 1.IPCR : Mr Lee Dong Hee & Mr. Ahn Yoeng Ho
2.PTKP: Aditya, Sidik,Dani
3. TTP : Mr Yusdi, Yasin
- Content : 1. PT.TTS will support refractory work (maintenance activities) in COP.
2. Organization Chart will be given to PTKP later.
* Reporting
- Measuring fence installationboth
and communication superior and
of quenching car subordinate.
driving Track (Autocad Drawing)

- Supervision daily report


- Review about CPCT line (C-Line and K-Line)
* Controlling and monitoring foreman and operator.
* VP and TBM meeting before work (Safety Slogan Iron Making & Hyoksin)
- Giving job Desc' to the operator's
- Temperature checking cross wall
- COP Facility (Lubrication & Specification) and CPCT Facility, Oven Management (Erection pro
* Guide the new foreman to study about COB and the process
Sidik * Guide operator to check temperature at P/S & C/S oven door #1 Battery
G/L Setiawan * Meeting with TTP company, IPCR, and KP about Oven Maintenance
* Checking progress status in the oven top #2 Battery (Piping, S/P, Bleeder & Gooseneck)
* Meeting with PT. Nuri about paging installation
* Guide operator to check temperature cross wall
* Monitoring operators to do them job with well
* Cleaning day with all expansion team at oven top #1 Battery and sealing stand pipe area
.Status of construction progress
Equipment Major progress status
* Installation flow metre for GC MAIN near bleeder no. #3 ( continue )
* PWHT pipe Ammonia Pump ( continue ) picture
* Installation support for control valve steam line near bleeder ( complete )
* Installation steam pipe in bleeder # 4 ( Complete )
* Connecting air instrument pipe with pneumatic pannel ( complete )
* Installation COG pipe in bleeder ( complete )
Oven Top
* Mortar dry sealing in charging hole chamber no. #43- #48
(Selva)
* Give grease in opened damper gooseneck ( complete )
* Installation steam pipe (Complete)
* Installation steam pipe in bleeder no # 3 and # 4 ( Complete )
* Installation pipe for Nitrogen line in GC Main ( complete )
* Installation pipe for LP ammonia liqour in GC MAIN ( complete )
* Tighten bolting between goosneck and GC MAIN : 42/42ea ( complete )
Daily Report
Oven Management Team Tuesday, Sept'
COKE Plant Contents
* Give Silicone at hole of fire host cable ( continue ) picture
* Installation bolting on bottom S/P : 42/42 ea ( complete )
* Installation silling rope and silicone between goosneck and GC MAIN : 42/42ea ( complete )
* Installation Ammonia LP pipe supply ( continue )
#2
* Installation fresh water pipe supply ( continue )
Batt'
* Repaired piston of pneumatic damper goose neck ( continue )
* Cleaning inside GC MAIN area ( complete )
* Adjusting gap between elbow S/P and gooseneck ( continue )
* Install pipa yang buat pembuangan sealing water in lid S/P ( complete )
* Install pipe line for pressure indicator at GC MAIN ( continue )
* Cleaning Area Oven Top
* Repaired Instrument air pipe because leakage.
# Pusher side
* Adjusting Spring at Oven Door No. 53 - 63
* Tighten Bolting at Oven Door No. 57 - 60

Oven # Coke Side


Door
(Rusjaya) * N - A

Oil, greasing
and lubrication
checking
(Arman)

Coal Tower
(Dicky)

PECS, Q/T & S/P


(Ahmad)
Daily Report
Oven Management Team Tuesday, Sept'
COKE Plant Contents

PECS, Q/T & S/P


(Ahmad)

CP
(Faizal,
Arisandi)

CT
(Chandra)
Tuesday, Sept' 24th 2013

Remark

ready begin today.(#1 batt)

o end buckstay.

mains by air blowing.


be checked by IPCR

s) in COP.

nt (Erection progress)

ooseneck)

d pipe area
Tuesday, Sept' 24th 2013

a ( complete )
Tuesday, Sept' 24th 2013
Daily Report
Oven Management Team Tuesday, Sept'
COKE Plant Contents
S/L G/L Operator Total
Total 1 2 10 13
Member
Vacancy 0 0 0 0
Today 1 2 10 13
* Inspection & problem checking at oven battery area
- #1 & #2 Battery Main Facility and Utility
- Mechanical, Electrical, Refractory
- There was a lot of rubbish inside the G/C main sealing sealing rope, it was not
good, so we have already cleaned inside it (complete, 42 EA)
* Commisioning & Heating-Up Meeting
- time : 10.00 ~ 10.45 am
- Participant : 1.PW : Mr.Nikolai & Mr.Thierry
2.PTKP : Mr.Kim Jong In, Aditya, Agasa
3.IPCR : Mr. Lee Dong Hee
- Content : 1. Today we start spring adjustment because expansion has already begin to
2. Piano wire <--> Buckstay measurement must be done by IPCR.
3. There is wrong measurement done between axis battery to end buckstay
Aditya 4. Dry sealing process (#2 batt) start from tomorrow.
S/L
Purna N 5. We have to clean oven chamber due to silica dry sealing remains by air b
6. Wooden space installation between H/W to Buckstay must be checked by
7. Mirror plate bolt tighting must be done by GM
- Time : 11.00 ~ 11.20
- Participant : 1.IPCR : Mr Lee Dong Hee & Mr. Ahn Yoeng Ho
2.PTKP: Aditya, Sidik,Dani
3. TTP : Mr Yusdi, Yasin
- Content : 1. PT.TTS will support refractory work (maintenance activities) in COP.
2. Organization Chart will be given to PTKP later.
* Reporting
- Measuring fence installationboth
and communication superior and
of quenching car subordinate.
driving Track (Autocad Drawing)

- Supervision daily report


- Review about CPCT line (C-Line and K-Line)
* Controlling and monitoring foreman and operator.
* VP and TBM meeting before work (Safety Slogan Iron Making & Hyoksin)
- Giving job Desc' to the operator's
- Temperature checking cross wall
- COP Facility (Lubrication & Specification) and CPCT Facility, Oven Management (Erection pro
* Guide the new foreman to study about COB and the process
Sidik * Guide operator to check temperature at P/S & C/S oven door #1 Battery
G/L Setiawan * Meeting with TTP company, IPCR, and KP about Oven Maintenance
* Checking progress status in the oven top #2 Battery (Piping, S/P, Bleeder & Gooseneck)
* Meeting with PT. Nuri about paging installation
* Guide operator to check temperature cross wall
* Monitoring operators to do them job with well
* Cleaning day with all expansion team at oven top #1 Battery and sealing stand pipe area
.Status of construction progress
Equipment Major progress status
* Installation flow metre for GC MAIN near bleeder no. #3 ( complete )
* PWHT pipe Ammonia Pump ( continue )
* Installation pipe for venting in GC MAIN
Oven Top
* Installation cover for cable ladder ( continue )
(Selva)
* Installation venting valve for steam ( continue )
* Painting pipe Ammonia ( continue )
* Installation CCTV in pipe rack ( continue )
* Give Silicone at hole of fire host cable ( complete )
* Installation bolting on bottom S/P : 33/42 ea ( continue )
* Installation Ammonia LP pipe supply ( continue )
* Installation fresh water pipe supply ( continue )
* Repaired piston of pneumatic damper goose neck ( complete )
* Adjusting gap between elbow S/P and gooseneck ( complete )

#2
Daily Report
Oven Management Team Tuesday, Sept'
COKE Plant Contents
* Install pipe line for pressure indicator at GC MAIN ( complete )
#2 * Cleaning Area Oven Top
Batt' * Gate valve in off take main unsafety ( issue ) picture
* Flexible hose for pneumatik damper gooseneck no #84 leakage ( issue ) picture
* Numbering for oven chamber in charging car rail no 70 ( not good ) picture
# Pusher side
* Tighten Bolting at Oven Door No. 61, 62
* Cleaning at Oven Door and pusher side area

# Coke Side
Oven * Numbering at steel For Centering Transfer Car
Door
(Rusjaya)

Oil, greasing
and lubrication
checking
(Arman)

Coal Tower
(Dicky)

PECS, Q/T & S/P


(Ahmad)
PECS, Q/T & S/P
(Ahmad)
Daily Report
Oven Management Team Tuesday, Sept'
COKE Plant Contents

CP
(Faizal,
Arisandi)

CT
(Chandra)
Tuesday, Sept' 24th 2013

Remark

ready begin today.(#1 batt)

o end buckstay.

mains by air blowing.


be checked by IPCR

s) in COP.

nt (Erection progress)

ooseneck)

d pipe area
Tuesday, Sept' 24th 2013
Tuesday, Sept' 24th 2013
Daily Report
Oven Management Team
COKE Plant Contents
S/L G/L Operator
Total 1 2 10
Member
Vacancy 0 0 0
Today 1 2 10

Aditya
S/L
Purna N

Sidik
G/L Setiawan

.Status of construction progress


Equipment Major progress status
* Flexible hose nozle disconnecting to fume duct COG no: 12,18,28
* Install oriffice MG no : 1 ( on progress )
* Tightening AIB & GIB bolts to the pipe & bolts oriffice no : 1-22 (on progress)
* Shut off cock not yet install bolt no : 41
Equipment * Cleaning condensat COG no : 1 - 10 finish # battery 1
Batery 1
( Taufik )
at
10:00 - 11:15
am
Daily Report
Oven Management Team
COKE Plant Contents
Tue, Nov' 12th 2013

Total Remark
13
0
13

status

o : 1-22 (on progress)


Tue, Nov' 12th 2013