Professional Documents
Culture Documents
Masters Mechanical
PO #: (Letter of Intent)
Delta #: 63630
Order Date: 9/24/2009
Drawing(s)
o DT-C-79-852 t75 Assembly
Material of Construction
Sound Data
Installation, Operation & Maintenance Manual
Tower Sell Sheet
Warranty
Misc Data Sheets and/or drawings
o B78001 Three Phase Wiring
o B79501 Blower Hood
o Immersion Heater Package Data Sheet and wiring diagram
o B78007 Fan Thermostat Installation Instructions
o Vibration Cut Off Switch Data Sheet
o Outlet Strainer Data Sheet
o B78004 High Sump Level Swich
o Control Panel Data Sheet
Average Properties of the Materials of Construction
Mechanical Properties:
Polyethylene (Shell Material) Test Method Properties
1. Tensile Strength (@ 20m./min.) ASTM D 638 2600-3000
2. Stiffness Modulus ASTM D 747 56-70 X 103 psi
3. Tensile Impact Strength ASTM D 1822 90-130 ft. lb. /in.2
4. Elongation (@ 20in./min.) ASTM D 638 150-350%
5. Vicat Softening Point ASTM D 1525 230/238F
6. Deflection Temperature at 66psi ASTM D 648 172F
7. Brittleness Temperature ASTM D 746 -94F
Permanence Tests:
Test Method Polyethylene PVC
1. Outdoor Weathering ASTM D 1435-65T Complete Protection Excellent
2. Accelerated Weathering ASTM E 42 Very Resistant Very Resistant
3. Normal Exposure to Sunlight Complete Protection Complete Protection
4. Accelerated Exposure to Sunlight FADEOMETER Complete Protection Complete Protection
Chemical Properties:
Test Method Polyethylene PVC
1. Weak Acids ASTM D 543 Very Resistant No Effect
2. Strong Acids ASTM D 543 None to Slight None to Slight
3. Weak Alkali ASTM D 543 Very Resistant No Effect
4. Strong Alkali ASTM D 543 Very Resistant No Effect
5. Salts ASTM D 543 Resistant No Effect
6. Sea Salts ASTM D 543 Resistant No Effect
Data developed in accordance with Cooling Technology Institute ATC-128 for Small Towers
* Calculated A-Weighted Sound Pressure Level (dB reference 0.0002 microbar)
** Calculated A-Weighted Total Sound Power Level (dB reference one picowatt)
Rev. 0
Sound data shown is for a standard single cell unit; installed in ideal conditions. 10/4/06
Data does not account for any environmental conditions of the specific installation site, which can greatly affect the final installed sound levels. JBH
Delta Cooling Towers, Inc.
Important: Deltas cooling towers have been designed to provide trouble-free service over an extended period of time. To obtain
the design performance, it is necessary that the cooling tower be installed, operated and maintained as prescribed in
these instructions.
Only persons possessing the skill and experience described herein should attempt to install this equipment. Prior to
installation, these instructions should be read carefully by the person who is to install the cooling tower to be certain
that its installation, operation and maintenance are thoroughly understood.
Questions regarding the installation, operation or maintenance of this equipment should be directed to Delta Cooling
Towers, Inc., Rockaway, New Jersey, (Telephone: 973/586-2201).
Step-by-step instructions contained in this brochure are based on normal installation conditions only. Abnormal or
unusual combinations of field conditions should be brought to the attention of Delta Cooling Towers or its
representative prior to installation of the equipment. The information contained herein is subject to change without
notice in the interest of product improvement.
Rev. 02-17-04
Delta Cooling Towers, Inc.
1
Installation of Your Pioneer Cooling Tower
structure that blocks prevailing winds, install Secure the safety slings completely around
Safety Procedures the cooling tower so the top discharge is and under the cooling tower. Provide
slightly higher than the structure. Locate padding to protect the edges of the
CAUTION: blower at the farthest point from the polyethylene shell at points of sling contact.
Observe safety procedures during structure, facing the direction of the The slings should be secured in a girdle
installation and whenever construction is prevailing winds. fashion for a double secure point of lift.
under way. Slings should be brought up snug around
Gravity drain to an indoor storage the tower before lifting onto the building.
Always disconnect & lock out main Sump requires proper head differential and
power supply before working on motors and pipe design considerations. Allowance must NOTE: Do not use guy wire U-bolts for
other electrical equipment. be given based on flow, pipe size, piping hoisting.
layout and distance cooling tower is located
Stand clear of rotating equipment from the indoor storage sump. (See chart
during start-up. page 3) Blower Assembly
The blower assembly should be hoisted
Before start-up replace all guards Should it be necessary to locate the separately onto the building, prior to the
removed during installation, that protect cooling tower near walls, within enclosures, removal of the shipping skid, in the same
pinch areas of V-belts, sheaves and other or indoors, choose a location that will not manner as the cooling tower.
rotating equipment. restrict airflow. Do not install the cooling
tower in a well or below the level of an Note: Do not use blower support frame for
Avoid contact with open flame or heat obstruction that might impede air discharge, hoisting.
source that could cause combustion. cause short circuit of air flow, or result in
recirculation of the discharge air back into Any questions regarding hoisting for roof
Observe recommended safety precautions the blowers. mounted installations should be directed to
whenever construction involving welding, a Delta.
cutting torch, a blowtorch or any other such Do not locate the cooling tower near
equipment is under way within the heat-generating equipment, exhaust vents
immediate area. or pipes which could interfere with the
Cooling Tower Installation
temperature of inlet air and raise the
Delta cooling towers have been designed to
ambient wet-bulb temperature to the
provide maximum performance, long life
How to Prevent Reverse cooling tower.
and trouble-free service. To assure optimum
Siphoning: performance, the following
Reverse siphoning is a back flow of non- Do not install a canopy or roof of any
recommendations should be followed as
potable, recirculating water into a potable kind over the cooling tower that would
closely as possible.
water system which can occur through the deflect discharge air back down around the
make-up float valve assembly located in the cooling tower and cause recirculation of the
discharge air back into the blowers. Positioning the Tower
water reservoir of a cooling tower.
The cooling tower should be installed on a
Should the valve malfunction, blockage
continuous firm, smooth and level concrete,
of the overflow or outlet lines would cause a
steel or wood foundation.
high water level in the reservoir, causing
the make-up water pressure to drop below Hoisting
Note: The tower must be anchored to the
atmospheric pressure creating a vacuum at
foundation with guy wires using the four
the make-up inlet. Cooling Tower
U-bolts provided at the top of the cooling
To prevent reverse siphoning, install a For roof mounted installations, it is
tower shell. Hand tightening of guy wires is
check valve in the water make-up supply recommended that a hoist using two or
sufficient. Do not over-tension.
line to the cooling tower. more safety slings and spreader bars, as
shown in the illustration, be used-to lift the
Spacing for piping and service access should
NOTE: Do not cap the overflow connection. cooling tower onto the building.
be considered when positioning the cooling
tower. Also to insure an adequate positive
suction head, the pump should be located
Location of the Pioneer below the bottom of the cooling tower
sump.
Cooling Tower
Proper location of the cooling tower is
essential to its satisfactory operation. The
following are recommendations for Indoor installation
selecting a cooling tower location. Consult Typically, cooling towers are placed outside,
the factory or our representatives for either on the roof or adjacent to a building.
additional assistance in selecting equipment If the situation dictates indoor installation,
and equipment locations. make sure there is ample fresh air available
around the blower inlets of the tower.
Select an open site having an Restricted amounts of fresh air will lead to
unobstructed air supply and free air poor tower performance. It is also
motion. necessary to attach a duct to the tower
discharge to convey the hot, humid air to
If the site is adjacent to a wall or other the outside. All ducting should be
independently supported and be kept as
short and straight as possible. The duct size
must not be smaller than the inlet and
discharge openings. Blowers may require
adjustment to accommodate ducting for Gravity Drain Long distance horizontal pipe runs, as well
indoor installation. Consult the factory for as excessive turns, may cause pressure
Outlet Size Selection Chart
the recommended motor and drive selection losses that prevent free gravity flow through
Outlet Size (inches)
when duct exterior static pressure (ESP) is the outlet sizes shown. Consult Delta for
2 3 4 6
1/8 W.C. or greater. It is recommended further information.
that the inlet and discharge ducting be
Head Feet GPM
screened to prevent foreign objects from
entering. Should prevailing winds blow into 0.5 20 50 75 165 Electric Immersion Heater
a horizontal discharge, it is recommended
1 25 65 95 215 Cooling towers ordered with anti-freeze
that a suitable windbreak be installed
several feet away. 2 35 90 135 305 systems are shipped with a protective seat
3 40 110 165 370 secured under the immersion heater
element that is to remain in place during
4 47 125 190 430 operation to protect the polyethylene shell
Cold Weather Protection 5 53 140 215 475 from direct contact with the heater element.
The cooling tower may require protection
against freezing at light heat loads when the
6 57 155 235 525
Note: This protective seat is not a shipping
wet-bulb temperature is under 32F, or 7 62 165 250 565 brace and must not be removed.
during shutdown when the temperature 8 66 180 270 600
drops below 32F.
9 70 190 285 645
The following methods are
recommended for use with Delta cooling 10 74 200 300 675
towers for protection during cold weather 12 81 220 325 715
conditions. Recommended equipment is 15 90 245 365 825
optional and may be ordered from the
factory. Consult the factory for further
information on which equipment to choose Notes: The above gpm flow rates, for the
for your specific application. outlet sizes shown, are calculated for cold
water gravity drain through piping designed
for direct and short horizontal runs before
Separate Indoor Sump dropping vertically to the indoor sump tank,
This method is a virtually foolproof anti-
See illustration on page 6.
freeze protection system with the added
advantage of minimum maintenance. The
indoor sump tank should be large enough to
fill the entire recirculation system without
danger of pump cavitation. As a general
rule, the tank should be sized to hold three
times the rate of circulation in gallons per
minute (gpm).
The tank should be provided with
properly sized overflow, makeup, drain and
suction connections. When a separate sump
tank is ordered with a cooling tower, the
water makeup valve assembly and the
overflow and drain connections are installed
in the indoor sump only. A bottom outlet
can be provided for gravity drain to indoor
sump tank installations.
When a sump tank is used, the cooling
tower should be located high enough above
it to allow free cold water gravity drain, as
the chart below outlines.
3
Thermostatic On-Off Control Note: Never block overflow connection. When threading pipe to the bulkhead
A thermostatically controlled blower for on- Water should be allowed to flow freely fittings, do not allow fittings to turn.
off operation should be considered as an without obstruction. See how to prevent Turning can loosen the locknut or squeeze
energy-saving feature during winter reverse siphoning page 2. the gasket out of position and may cause
operation. The thermostatic control can be leaks. PVC bulkhead fittings should be
field set to insure automatic blower shut- The outlet connections for pump tightened with a chain wrench so that the
down when cold water drops below design suction applications are provided with a gaskets sit property between the cooling
temperature, as well as blower start-up vortex breaker. tower shell and the fitting. Do not over
when cold water rises to design tighten. A bulkhead fitting that is too tight
temperature. A thermostatic control Note: For gravity flow applications, a vortex or too loose can cause the gasket to crimp
provides excellent cooling tower anti-freeze breaker is not required or provided. A vent or squeeze away from the locknut, causing
protection while reducing operating costs pipe or bleed valve should be installed at leaks around these connections.
through out cold weather operation. the highest elbow of the piping system,
to prevent air locks and insure free flow of
PVC Distribution system water. Air locks can cause gravity flow Duct To Blower Housing
To prevent damage to the PVC distribution restriction resulting in excessive water
system during cold weather shut-down, accumulation and eventual overflow of the Installation
cooling tower. To install the cooling tower air duct to
install an automatic or manual drain line
the blower housing, place the lip of the duct
from the hot water inlet piping as close to
The outlet, makeup and overflow over the lip of the blower housing as shown.
the cooling tower inlet as possible. Locate
connections are notched at the outer ridge With seven screws supplied, fasten duct to
this drain line to allow the water to drain
and should be held in position with the housing using two screws on each side and
either to waste or to an indoor storage tank.
notch at 12 oclock. This is to insure proper three on the bottom.
This precaution will prevent water from
being trapped and possibly freezing inside position of the vortex breaker, float valve,
assembly and overflow extension which are On models DT-10 through DT-25, install the
the distribution system.
internal and not visible from the exterior of duct sides outside the blower housing.
Piping the cooling tower.
On all other models, install the duct sides
When the cooling tower is located outdoors, inside the blower housing.
adequate measures including the use of The inlet fitting of models DT-10
heat tracing tape and insulation should be through DT-40 is notched in the same
manner as described above to insure proper Install bottom of the duct to outside of the
considered to protect outdoor water lines blower housing on all models.
from freezing. spray nozzle position.
PVC bulkhead connections must be Seal off air leaks around the duct with
held steady and in their factory-installed duct tape.
Piping and Tower positions when the connecting piping is
Connections being installed. Note: the blower support frame must be
Piping should be adequately sized bolted to the foundation. The assembly is
according to accepted standard practices. furnished with pre-drilled bolt holes.
Refer to cooling tower drawings for size and Shimming may be required for perfect fit.
types of cooling tower connections
furnished as standard. Damage to painted surface of blower
housing during installation must be repaired
On multiple tower installations, pipe immediately to prevent corrosion.
sizing should balance pressure drops to
provide equal inlet pressures. Equalizing
fittings can be provided in cooling tower
sumps and are available as an option from
the factory. Each unit should be valved
separately to allow for flow balance or
isolation from service.
V-belt Alignment and The following belt tensioning procedure is belt midway between the sheaves as shown
recommended: in the illustration.
Tensioning
Check that the driver and driven
Proper belt tension is the most
sheaves are in alignment by placing a Note: Excessive belt tension can shorten
important factor in the successful operation
straight edge across the sheaves at four belt and bearing life. Loose belts or
of a V-belt drive. The belt tension should be
contact points as shown. If realignment is misaligned sheaves can cause unseating
checked frequently during the first 24 hours
required, loosen the motor sheave bushing and breakage of belts. Replacement of
of operation and then periodically on a
screws and align the sheaves. multiple belt systems should be made in
maintenance schedule. Loose belts cause
matched sets.
slippage which reduces air flow and can
To tension the belts, adjust the motor
adversely affect belt life and cooling tower
base so that the belt will deflect about
performance.
when moderate pressure is applied to the
Initial Start-Up
Clean accumulated debris from inside
shell bottom.
5
The standard make-up valve assembly Check spray pattern from nozzle(s) to the heat transfer media. Excessive high
is shipped as shown with the plastic float be sure there is no clogging, Remove drift spray pressure may also cause wet decking
ball against the tower side to prevent eliminators for nozzle inspection, then fatigue and damage. The nozzles furnished
damage. To set the ball for proper return to proper position. with standard cooling towers are sized for 3
operation, loosen the thumb screw on the gpm/ton, requiring 10 psi inlet pressure for
fulcrum arm and rotate until a 10 operating Start fan motor and check amperage models
level is obtained (measured from the tower and voltage against motor nameplate data. DT-50 though DT-100, and 7 psi inlet
bottom vertically upward to the midpoint of pressure for models DT- 10 through DT- 40.
the float ball). It is recommended that a After 24 hours of operation, check belt This standard may vary when the design
shut-off valve be installed in the make-up tension and adjust if necessary. See page 5. flow is less or greater than 3 gpm/ ton.
line. See how to prevent reverse siphoning Alternate orifice nozzles will be provided in
page 2. order to maintain the proper inlet pressure
requirement. Correct flow rates and inlet
Operating Design pressures should be determined prior to
Condition Checklist completion of system installation.
For proper operation and maximum
efficiency of the cooling tower, the following Blower motors must be properly
operating design conditions are essential: wired for counter-clockwise (ccw) rotation
of the blower wheel as viewed from the
The flow rate of the cooling tower sheave side of the blower assembly.
must be as close to the design gpm as Reversed leads will cause incorrect rotation
possible. The distribution system, including and inhibit required air distribution.
spray nozzles, are provided for the design
flow condition. Under-pumping or over- Note: The blower must always operate with
pumping will cause the cooling tower to water circulating through the cooling tower
perform inefficiently. to prevent motor overload.
Water Treatment To determine the appropriate water A bleed line can be connected in any
The Delta cooling tower shell and internal treatment practices for your particular part of the system with routing to the
components are fabricated of corrosion- application, it is suggested that you contact sewer. Normally, it is most desirable to
resistant plastics and are resistant to water a water treatment firm for their make this connection in the hot water line
treatment chemicals including common recommendation. A list of water treatment at the cooling tower. A petcock type valve,
fungicides and bactericides. firms is available for your reference. installed in the bleed line for proper control
Follow appropriate water treatment is recommended. The required amount of
practices as required and take frequent It is not necessarily complete nor do we bleed-off water must be substituted with
sample tests to avoid possible water recommend a specific firm. The list will be properly controlled amounts of make-up
contamination. We also recommend water mailed to you on request. water.
treatment maintenance as a measure of Bleed off is also important to water quality.
protection for the environment in the Evaporation of the recirculated water does
vicinity of any cooling tower or evaporative not remove the dissolved solids that are
condenser equipment. present in the water. Without bleed off, the
continual buildup of these solids will impair
the proper functioning of the piping and
other equipment in the system.
6
Remove the wet decking from the For Pioneer Models T-50 through
Disassembly and Cleaning cooling tower shell using the plastic hand T-100
straps attached for lifting. The wet decking
For Pioneer Models DT-10 has a smaller diameter than the drift Same procedure as above except:
through DT-40 eliminator and will lift easily out of the shell
once the distribution spray system is These models are designed so the drift
Remove the drift eliminator from the removed. eliminator can be easily lifted up and away
cooling tower. It is flexible enough to push from the cooling tower shell. The spray
the outer perimeter toward the center and When the internal components are tree sections of the water distribution
lift over the top lip of the cooling tower removed the empty shell can be cleaned system are threaded to a coupling and
shell. Begin at one point and work carefully and inspected, It is recommended that the unscrew easily. Hold and turn the entire
around the entire circumference of the drift water distribution laterals and nozzles be riser below the lateral and nozzles, then
eliminator. cleaned and flushed before reassembly. carefully remove the whole assembly.
Models DT-30 and DT-40 are designed To reassemble components, reverse The wet decking can now be easily
without a top lip so the drift eliminator can the above procedure. removed using the plastic hand straps
be easily lifted up and away from the shell. Before installing the drift eliminator, attached for lifting.
pump water through the distribution system
Remove the water distribution spray to be sure there is a good spray pattern and
system from inside the cooling tower. The proper water distribution over the wet
spray system is installed across the top of decking surface.
the tower directly under the drift eliminator.
Disconnect locknuts at each end of system
and remove piping by elongating top of
tower shell slightly.
Drift Eliminator
Distribution Spray
System
Wet Decking
Blower Housing
Tower Shell
7
Preventative Maintenance
Checklist
Pioneer
Recommended
Replacement Parts
When ordering, include model number and
To avoid costly cooling tower downtime, the serial number of the cooling tower as it
following replacement parts should be appears on the tower nameplate.
carried in inventory at the installation site:
V-belts Under normal conditions, shipment of
Blower bearings factory replacement parts is made within
Make-up float, or complete make-up one day after the order is received. Spare
valve assembly pumps and pump parts s well as control
Blower shaft panel components, such as fuses and
Blower motor heaters for magnetic starters, are also
Or, a complete blower assembly available.
including bearings, shaft, sheaves, V-
belts and motor.
8
PIONEER
D E LTA Forced Draft, Counter Flow Design
Cooling Towers, Inc.
10 - 100 Ton Single Modules
STANDARD FEATURES:
Pioneer cooling towers
Seamless Engineered Plastic (HPDE) Shell
Corrosion Proof Construction
are forced draft counter flow
Forward Curved Centrifugal Blower with Totally Enclosed Motor.
design cooling towers with Factory Assembled for Simple Installation
15 Year Shell Warranty
single module capacities from 10
PVC Water Distribution System with Non-clog Large Orifice
to 100 cooling tons. These Removable Nozzles
High Efficiency PVC Fill
towers are a unitary seamless
Made in the USA
engineered plastic design that
Compare the value Delta Cooling Towers offer against the
Delta has been manufacturing value of other comparable units. You will find the benefits
we can provide are unique and superior:
since 1971 and have been the Cost Reduction - save water costs and sewer taxes. A Delta
cooling tower pays for itself by recirculating water.
standard for long-term trouble-
Non-Corrosive Materials of Construction - impervious to
free operation. chemicals, acids, and salts.
Cost Less to Maintain - will not rust, chip, or ever require
painting for extraordinary tower life.
Unique Design - provides unlimited flexibility of modular
operation, future upgrade capablity, and location convenience.
One-Piece Construction - strong and long lasting. Shell is
backed by a 15 year warranty.
Cost Less to Install - light weight construction reduces rigging
and structural roof support requirements. Maintenance costs
and water treatment chemicals cost are significantly lowered.
OPTIONS AVAILABLE:
Mounting Platforms
Two Speed Motors
Thermostatic On/Off Fan Control Package
Anti Freeze Basin Heaters
Pump(s)
Sump Level Switches
Stainless Steel Basket Strainers
Control Panels
Storage Tanks
CORROSION- DRIFT
PROOF SHELL ELIMINATOR
HDPE Plastic PVC drift eliminator
Construction can not prevents water droplets
corrode and is from leaving the tower.
backed by 15 Year
Warranty.
6
www.indeeco.com 800-243-8162
Pipe Thread Heaters
2" Pipe Thread Heaters
Water Water
304 SS Sheath, 304 SS Fitting 50 W/Sq. In. Copper Sheath, Brass Fitting 50 W/Sq. In.
Stock Without Thermostat, NEMA 4 Terminal Box Stock Without Thermostat, NEMA 4 Terminal Box
Availability Availability
Number Number
B 1 Phase 3 Phase B 1 Phase 3 Phase
of KW Catalog of KW Catalog
Dimensions Dimensions
Elements Number Elements Number
120V
240V
208V
480V
240V
480V
208V
120V
240V
208V
480V
240V
480V
208V
(Inches) (Inches)
10
www.indeeco.com 800-243-8162
Control Panels
Cooling Tower Control Panels
INDEECO offers a pre-engineered, UL Listed/CSA Approved Sensor Probe Specifications:
package for freeze protecting cooling tower basins. Sensor Probe: INDEECO probe assembly incorporating
both temperature and liquid level sensors. Probe is made
The complete package includes:
out of 316 stainless steel to minimize corrosion. Probe can
Electric Immersion Heater(s)
be installed vertically or horizontally.
Control Panel with Solid-State Printed Circuit Board
Maximum Pressure Rating for Sensor Probe: 15 psi
Sensor Probe with Cord
Cord: 12-foot outdoor rated cord with PVC hub connector
Wiring Diagram
for installation through tower basin wall. Options include
Installation and Operating Instructions
different cord lengths or cord suitable for total immersion.
INDEECO offers the following options:
Disconnect Switch Cooling Tower Control Panel Specifications:
Fuses Solid-State Control: Pre-set 45 F ON/OFF temperature
Circuit Breaker control with 5 F switching differential and built-in low
water cutoff. Circuit board LEDs provide visual indication
of heater-on and liquid level status.
Ambient Temperature Range: -40 F to 150 F
Fail Safe: Output relay is de-energized if the input sensor
is either open or short-circuited. This prevents heater burn-
out problems.
NEMA 4X enclosure with pre-mounted electrical hubs for
conduit connections.
Single probe to sense both water temperature and water
level. Sensor probe supplied with 12-foot outdoor rated
cord pre-connected to control panel. Probe also supplied
with PVC hub connector for attachments through cooling
INDEECO Heater Control Panels offer these advantages: tower basin wall.
Solid-State Control Nameplate showing maximum KW and amp ratings at
Outmoded bulb and capil- system volts/phase.
lary control has been System Wiring Diagram.
replaced with new patented Installation and Operating Instructions.
solid-state technology Rated for maximum of 40 amps or 50 amps with disconnect
which combines tempera- switch when specified.
ture control with low water Suitable for multiple heaters per basin (maximum of 2 on
level protection in a single 40 amp panel).
solid-state device. Disconnect switch with door interlock and operator handle,
which can be padlocked in the OFF position.
NEMA 4X Enclosure Dimensions: 8" x 10" x 6" for 40 amp size
All controls are factory 10" x 12" x 7" for 50 amp size
wired inside a rugged 14" x 16" x 8" for two circuits
NEMA 4X enclosure Control panels rated greater than 50 amps are supplied
designed for wet, outdoor with two circuits and offered either with built-in fusing or
use. Pre-engineered a circuit breaker for each circuit.
designs up to 96 amps are
available with stock and
built-to-order listings.
Lower Cost
Installation time and cost
are reduced by replacing
individually mounted tem-
perature and liquid level
control devices with one
pre-engineered and assem-
bled control package
that requires only one
probe to sense both water
temperature and level.
41
www.indeeco.com 800-243-8162
Limited Warranty
Industrial Engineering and Equipment Company (INDEECO) Remedy: The part or product in question should be returned,
products are warranted against defects in workmanship, freight prepaid, to:
material, design, labeling and packaging. No other warranty, INDEECO
expressed or implied, written or oral, applies. No person 425 Hanley Industrial Court
other than an officer or the general manager of INDEECO is St. Louis, Missouri 63144
authorized to give any other warranty or assume any liability. Attention: Return Goods Manager
Warranty Period: This warranty is effective for eighteen
months from the date of shipment of the product from If after receipt of the product and the claim, INDEECO finds
INDEECOs factory, or for twelve months from the date the to its reasonable satisfaction that the product is defective in
product is first placed in service, whichever period lapses workmanship, material, design, labeling or packaging, the
first. product will be repaired or replaced or the purchase price
refunded at INDEECOs option. There will be no charge to the
Conditions of Warranty: INDEECO products must be installed, purchaser for parts or labor. Removal and reinstallation of
operated and maintained in accordance with INDEECOs the product, and shipment of the product to INDEECO for
instructions. INDEECO is not liable for damage or unsatisfac- repair or inspection shall be at the purchasers risk and
tory performance of the product resulting from accident, expense.
negligence, alteration, unauthorized repair, improper applica-
tion or installation of the product, improper specifications or THE REPAIR, REPLACEMENT OR REFUND PROVIDED FOR IN
corrosion. INDEECO IS NOT LIABLE FOR ANY INCIDENTAL OR THIS LIMITED WARRANTY IS THE EXCLUSIVE REMEDY OF THE
CONSEQUENTIAL DAMAGES. Claims against carriers for dam- PURCHASER. THIS WARRANTY IS EXPRESSLY IN LIEU OF ANY
age in transit must be filed by the purchaser with the carrier. OTHER WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING
ANY WARRANTY OF MERCHANTABILITY OR FITNESS FOR A
PARTICULAR PURPOSE. THERE ARE NO WARRANTIES WHICH
EXTEND BEYOND THE TERMS OF THIS LIMITED WARRANTY.
48
www.indeeco.com 800-243-8162
Delta Cooling Towers, Inc.
41 Pine Street
Rockaway, NJ 07866
PH: 973.586.2201
Fax: 973.586.2243
www.deltacooling.com
Email: sales@deltacooling.com
The vibration cut-out switch option is utilized when excessive vibration of the rotating machinery is
undesirable. Excessive vibration can be caused by worn or failed bearings, misalignment and/or wheel
unbalance.
This device helps prevent further potential damage by shutting the motor off. It is wired in series with the
motor starter coil and has dry contact rating of 10 ampere capacity at 120 VAC.
Delta provides the vibration cut-out switch installed on the blower when ordered as a component of a new
cooling tower or on a replacement blower assembly.
Pioneer
FDDS 8
3/94 Rev 2
Delta Cooling Towers, Inc.
41 Pine Street
Rockaway, NJ 07866
PH: 973.586.2201
Fax: 973.586.2243
www.deltacooling.com
Email: sales@deltacooling.com
This option is desirable to prevent debris which may have entered the cooling tower sump from getting into the
pump, or the rest of the cooling water system. This option is recommended to minimize particle size which could
foul chillers, heat exchanger, compressors, or the cooling tower nozzles.
A vortex breaker pipe, which is provided as standard on pump suction applications, is included to maximize the
inlet area and prevent cavitations. The strainer is made from a vortex breaker pipe surrounded by 3/16" #2 PVC
coated mesh screen.
Finer mesh screens can be overlaid to minimize particle size. Consult Delta for add prices and availability.
Pioneer
FDDS 9
3/94 Rev. 1
Prewired Control Panels
Product Information
NOTE:
For dependable, compact, Standard control panels are
electrical control of cooling provided:
1. With electrical components selected from
tower water recirculation various manufactures of Deltas choice.
systems. In most cases, however, the control panel
can be provided with a specific
manufacturers components other than
Deltas standard, at additional charge.
Consult the factory.
Includes: 2. 208V or 230V or 460V or 575V 3ph/60hz
cycle operation.
NEMA 3R water tight enclosure
3. Can be provided with optional fused
Single speed motor starter disconnect and pump motor starters for
an additional charge.
110V transformer with fuses
4. NEMA 4X stainless steel or fiberglass
Fan operating lights enclosures availabe.
Fan on/off selector switches 5. Can be provided with digital temperature
controller or VFD package.
Terminal Strips