Additional activities for each tank As commeted by MODES & SATA

Sl. No. Sector Activities Sub Activities Remarks


1. Chain block Fixing
2.Cutting in pieces (10 pieces minimum)
Beam Removal (4 No)
1 Roof 3.Removal from inside of the tank to the top of tank Painted area will get damage
Under pump house
4. Removal from top of the tank to the ground level
5.Grinding on columns plate has cut with beams
1.Grinding for paint removal
2 Roof Welding on the columns gap 2.Welding Painted area will get damage
3. Weld visual
Sharp edges removal of bracket
3 Roof 1.Grinding to remove sharp edges of the bracket plate (240Nos) Painted area will get damage
plate
1.Cutting of hooks
4 Roof Hooks Removal 2.Glousing to minimize the grinding required Painted area will get damage
3.Flush grinding
1. Plate cutting
5 Shell Connecting plate removal 2.Glousing to minimize the thicknes Painted area will get damage
3.Flush grinding
1. welding of ladder base with the plate connected with bottom plate
6 Bottom Ladder
2.Grinding & Weld visual
1.Column guide support cutting
2.Flush grinding
7 Bottom Columns base welding
3.Welding of column base plate with bearing plate (8MM welding)
4.Grinding and weld visual