SITEWEEKLYMEETING,PTCEMINDOGEMILANGANDFUTAIENGINEERING
Followingtopicswere/agreedduringtheweeklyprogressmeetingwithFutaifortheCiwandanCementGrindingProjecton
th
17 ofApril2013
Attendees:
PTCemindoGemilang FUTAIEngineering
1. AriefNoerH. 6. WansonS. 1. JenHsienChang 6. YohnHarmen
2. E.Widodo 7. ArzanM 2. MarkShih 7.
3. AndriH 8. 3. JohnsonChang 8.
4. FauzanTarmizi 9. 4. Safrico(DFN) 9.
5. DedeS. 10. 5. Zulkarnen(DFN) 10.
PurposeOfMeeting/Agenda:
Subject
Agenda:
7. PackingHouse
1. Progress
8. MainOffice
2. CementSilo#1,#2,#3
9. QualityIssue
3. ClinkerStorage
10 SafetyIssue
4. AdditiveStorage
11 ElectricalWork
5. MillHouse
12 GeneralIssue
6. ProportionsBuilding
No. STATUS/COMMENTS
1. Progress:forConstructiononly
PLANNED ACTUAL DEVIATION REMARK
LASTWEEK: 51.32 39.18 12.14 Progressindexstillnot
THISWEEK: 5.1 1.43 3.67 statedbyFuTai
OVERALL: 56.42 40.61 15.81
LastWeekHighlight:
Pouringconcretefoundationcementsilo#2isdone
InProgressInstallsteelrebaronClinkerStorage
StartdeeperexcavationatMillhouse
Provideaccessroadtocoverallarea,stillinprogress
PlanningNextweek:
Duetoprogressdeviationbecomebiggerandbigger,CGaskFuTaitomakecorrectiveplan&
actiontoachieve&maintainprogressachieved,suchas;
o Increasemanpower,additionalheavyequipment,
Page1of5
o Considertoinvolvedanysubcontractorifnecessary
o Providealldrawingsrequiredforallarea
o Dothejobinparallelforallareatoachievemuchprogress
Nextweekprogressplanachieve:4.9%ortotallyapprox.45%
2. CementSilo.
TinTaiwilldeliver2unitstheslipformmaterialsnextweek.
Targetstartpouringconcreteforbottomwallsilo#1on25April13andwillbefinishedon
1May13
DFNwillcontinuetheconcreteworkforcolumninsidesilo#1,#2,#3,plannedfinishon24
April
Orientationmarkingmustbemadeforinspectionreference,target19April13,byDFN(Mr.Zul)
EmbeddedpartswillbesuppliedlocallybyDFN,FuTaishallmakesurealldocumentrequiredas
perfabricationproceduremustbeprovided
Scaffoldingmustbeusedforworkingabove2melevation
3. ClinkerSilo.
Formwork&installsteelrebarhasstartedforfoundation,progress60%andwillcontinuenext
week.Targetpouringconcreteon26April13
Progressstillundercontrol
4. AdditiveStorage.
Theprogressstillnotgoodasnottoomuchactivity
DFNwilladdmanpower;15workertocoveradditivearea,andFuTaihasaddedwaterpump.
FTEwillstartformwork&installrebarplannedthisweek;pilecapCT5(20ea)finishon24April
13
5. MillHouse.
ProgressplannedlastweekisnotachievedduetotheexcavationsoilstillnotremovedbyFuTai
DFNaskFuTaitoprepareaccessroadfrom2sideofgrindingmilltoeasyaccess&speedupthe
work
DFNwillcontinuedeeperexcavation&foundationwork,targetnextweek;LC&installrebarfor
4area,
6. ProportionsBuilding.
Noactivitysincelastweeks,duetofoundationdwgsstillnotavailable.FuTaijustconfirmedthat
foundationisnowavailablereadytostart.
Plannednextweek:purchasesteelbar,startfabricationsteelbar
7. PackingHouse.
Noactivitysincelast4weeks,duetofoundationdwgsstillnotavailable.FuTaijustconfirmed
thatfoundationisnowavailablereadytostart.
Plannednextweek;purchasesteelrebar,cuttingpiles
8. MainOffice.
Noactivitysincelast4weeks,duetothefoundationdwgswasnotavailable.FuTaijust
confirmedthatfoundationisnowavailablereadytostart.
Plannednextweek:purchasesteelbar,startfabricationsteelbar
9. QualityIssue.
CGhasissuedNCRno002&003,FuTaiwillcloseditwithinthisweek.
FTEsiteshallsubmittoCGsitePDAtestreportlistforallarea,target18April13
Tensiletestforrebaralreadydoneforseveraltestpiece,FuTaishallsubmittensilereportand
receivingmaterialsinspectionreporttoCGon18April13.
Page2of5
Materialstestremainaredia.29mm(basedonmaterialsreceived),willbetestedon22April13.
10. SafetyIssue.
FTEMUSTprovidelightingtocoverallareastartingfromentrygatethroughallaccessroadatjob
site.Lightingmustbeinstalled&lightonnextweekatleastonentrygate,accessroadtosite
workshopareaandinfrontoffsiteoffice.
JobSafetyAnalysisforalljobsshallbesocializedtoallsubcontractor
11. Electical.
Groundingrodoncementsiloareahasplantedandcontinueforwiringconnection.
FTEshallinspect&makesuregroundingrodquality,aspercontractitshallbecopperrod.
12. GeneralIssue.
FTEMUSTsubmitconstructionschedulecompletedwithprogressindex&Scurveassoonas
possible,soprogressachievementcanbemeasured.FTEwillsubmit18April2013afternoon.
FTEwillsubmitdetailweeklyscheduleon18April13.
CurrentlytotalmanpowerDFNare140worker,DFNwillincrease55personsnextweek,totally
willbe200workernextweek.
Photos:
AdditiveStorage:
ClinkerSilo:
Page3of5
CementSilo:
MillHouse:
PorportionBin:
Page4of5
PackingHouse:
MainOffice:
Page5of5