S10 Pgina 1

Presupuesto
Presupuesto 0491002 "CREACION DEL PUENTE CARROZABLE WITU JAWIRA EN EL CENTRO POBLADO NINANTAYA DISTRITO MOHO
PROV. DE MOHO - PUNO"
Subpresupuesto 001 PUENTE UNA VIA 25M
Cliente MUNICIPALIDAD PROVINCIAL DE MOHO Costo al 30/07/2012
Lugar PUNO - MOHO - MOHO

Item Descripcin Und. Metrado Precio S/. Parcial S/.

01 OBRAS PRELIMINARES 22,370.00


01.01 CAMPAMENTO DE OBRA GLB 1.00 15,000.00 15,000.00
01.02 TRAZO Y REPLANTEO m2 450.00 8.60 3,870.00
01.03 CARTEL DE OBRA DE 5M X 3M GLB 1.00 3,500.00 3,500.00
02 MOVIMIENTO DE TIERRAS 295,582.10
02.01 EXCAVACION EN MATERIAL SUELTO m3 103.66 9.44 978.55
02.02 EXCAVACION EN TERRENO SATURADO m3 282.53 13.17 3,720.92
02.03 ELIMINACION MATERIAL EXCEDENTE m3 463.42 10.37 4,805.67
02.04 DESVIO DEL RIO m3 960.00 5.69 5,462.40
02.05 ENROCADO DE PROTECCION DE PILARES Y ESTRIBOS m3 360.00 119.66 43,077.60
02.06 ENROCADO DE PROTECCION DIQUES DE PROTECCION m3 600.00 119.66 71,796.00
02.07 CONFORMACION DE TERRAPLEN CON MATERIAL DE RELLENO m3 1,637.97 46.72 76,525.96
02.08 BOMBEO DE AGUA PARA CIMENTACION hm 500.00 178.43 89,215.00
03 CONCRETO SIMPLE 133,095.48
03.01 ELEVACION Y CIMIENTOS DE ESTRIBOS 133,095.48
03.01.01 CONCRETO EN FALSA ZAPATA F'C=140KG/CM2+30%P.G. m3 29.49 412.31 12,159.02
03.01.02 CONCRETO F'C=175 KG/CM2+30% P.G m3 249.10 430.60 107,262.46
03.01.03 ENCOFRADO Y DESENCOFRADO PARA ELEVACIONES- ESTRIBOS m2 299.54 45.65 13,674.00
04 CONCRETO ARMADO 176,229.02
04.01 VIGAS PRINCIPALES 115,499.24
04.01.01 CONCRETO f'c=280kg/cm2 m3 60.00 720.12 43,207.20
04.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 194.80 57.15 11,132.82
04.01.03 ACERO FY=4200 KG/CM2 VIGAS PRINCIPALES kg 13,012.60 4.70 61,159.22
04.02 VIGAS DIAFRAGMA 8,096.13
04.02.01 CONCRETO f'c=280kg/cm2 m3 4.60 720.12 3,312.55
04.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 31.60 57.15 1,805.94
04.02.03 ACERO FY=4200 KG/CM2 VIGA DIAFRAGMA kg 633.54 4.70 2,977.64
04.03 LOSAS 42,004.55
04.03.01 CONCRETO f'c=280kg/cm2 m3 28.25 720.12 20,343.39
04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN LOSA m2 133.84 57.15 7,648.96
04.03.03 ACERO FY=4200 KG/CM2 LOSA kg 2,981.32 4.70 14,012.20
04.04 VEREDAS Y SARDINELES 10,629.10
04.04.01 CONCRETO f'c=280kg/cm2 m3 6.00 720.12 4,320.72
04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA VEREDAS Y SARDINELES m2 30.48 39.35 1,199.39
04.04.03 ACERO FY=4200 KG/CM2 VEREDA Y SARDINEL kg 1,087.02 4.70 5,108.99
05 REVOQUES ENLUCIDOS Y MOLDURAS 2,829.00
05.01 TARRAJEO DE VEREDA COLUMNETA SARDINEL m2 50.00 56.58 2,829.00
06 PINTURA 561.69
06.01 PINTURA ANTICORROSIVA EN BARANDAS m2 35.20 10.44 367.49
06.02 PINTURA ESMALTE EN SARDINEL m2 20.00 9.71 194.20
07 VARIOS 82,501.11
07.01 APOYO DE NEOPRENO und 8.00 339.32 2,714.56
07.02 JUNTAS ASFALTICAS m 8.60 6.05 52.03
07.03 TUBERIA PVC SAP 2" PARA DRENAJE m 13.60 21.28 289.41
07.04 TUBERIA DE F G DE 3" PARA BARANDA m 140.80 484.87 68,269.70
07.05 PLACA RECORDATORIA und 1.00 500.00 500.00
07.06 APOYO FIJO ACERO kg 158.92 4.25 675.41
07.07 COMPESACION SOCIAL EN AREAS DE CANTERA GLB 1.00 10,000.00 10,000.00
08 FLETE 55,000.00
08.01 MOVILIZACION Y DESMOVILIZACION MAQUINARIA GLB 1.00 30,000.00 30,000.00
08.02 TRANSPORTE DE MATERIALES DE CONSTRUCCION GLB 1.00 25,000.00 25,000.00

Fecha : 17/05/2017 2:42:20p. m.


S10 Pgina 2

Presupuesto
Presupuesto 0491002 "CREACION DEL PUENTE CARROZABLE WITU JAWIRA EN EL CENTRO POBLADO NINANTAYA DISTRITO MOHO
PROV. DE MOHO - PUNO"
Subpresupuesto 001 PUENTE UNA VIA 25M
Cliente MUNICIPALIDAD PROVINCIAL DE MOHO Costo al 30/07/2012
Lugar PUNO - MOHO - MOHO

Item Descripcin Und. Metrado Precio S/. Parcial S/.

09 PRUEBAS DE CALIDAD DE CONCRETO 1,350.00


09.01 PRUEBAS DE CALIDAD DEL CONCRETO und 45.00 30.00 1,350.00

Costo Directo 769,518.40

GASTOS GENERALES (15%) 115,427.76

SUPERVISION (7.5%) 57,713.88

EXPEDIENTE TECNICO (3.5%) 26,933.14

GASTOS DE LIQUIDACION (1.00&) 7,695.18

UTILIDAD (10.00%) 76,951.84


============

SUB TOTAL 1,054,240.20

IGV (18.00%) 189,763.24


============

TOTAL PRESUPUESTO 1,244,003.44

SON : UN MILLON DOSCIENTOS CUARENTICUATRO MIL TRES Y 44/100 NUEVOS SOLES