TECHNICAL POLICY BOARD

GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE


INSTALLATION

0035/ND

Once downloaded this document becomes UNCONTROLLED.


Please check the website below for the current version.

22 Jun 13 0 DR Technical Policy Board


Date Revision Prepared by Authorised by

www.gl-nobledenton.com
GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

PREFACE

This document has been drawn with care to address what are considered to be the primary issues in relation to the
contents based on the experience of the GL Noble Denton Group of Companies (the Group). This should not,
however, be taken to mean that this document deals comprehensively with all of the issues which will need to be
addressed or even, where a particular matter is addressed, that this document sets out a definitive view for all
situations. In using this document, it should be treated as giving guidelines for sound and prudent practice, but
guidelines must be reviewed in each particular case by the responsible organisation in each project to ensure that
the particular circumstances of that project are addressed in a way which is adequate and appropriate to ensure that
the overall guidance given is sound and comprehensive.
Reasonable precaution has been taken in the preparation of this document to seek to ensure that the content is
correct and error free. However, no company in the Group
shall be liable for any loss or damage incurred resulting from the use of the information contained herein or
shall voluntarily assume a responsibility in tort to any party or
shall owe a duty of care to any party other than to its contracting customer entity (subject always to the terms
of contract between such Group company and subcontracting customer entity).

This document must be read in its entirety and is subject to any assumptions and qualifications expressed therein as
well as in any other relevant communications by the Group in connection with it. Elements of this document contain
detailed technical data which is intended for analysis only by persons possessing requisite expertise in its subject
matter.

2013 Noble Denton Group Limited. The content of this document is the copyright of Noble Denton Group Limited.
All rights reserved. Any reproduction in other material must have written permission. Extracts may be reproduced
provided that their origin is clearly referenced.

0035/ND Rev 0 Page 2 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

CONTENTS
SECTION PAGE NO.
1 SUMMARY 5
2 INTRODUCTION 6
2.1 Scope 6
2.2 Other GL Noble Denton Guideline Documents 6
2.3 Exclusions 7
3 DEFINITIONS & ABBREVIATIONS 8
4 THE APPROVAL PROCESS 14
4.1 GL Noble Denton Approval 14
4.2 Scope of Work Leading to an Approval 14
4.3 End of MWS Scope of Work 15
4.4 Limitation of Approval 15
5 GENERAL 16
5.1 Coordination 16
5.2 Tolerances & Criteria 18
5.3 Vulnerable Items or Areas 18
5.4 Planned Moorings 19
5.5 Site & Route Survey Requirements 19
5.6 Health Safety & Environment 19
5.7 Organisation & Communication 19
5.8 Procedures and Manuals 20
5.9 Weight Control 20
5.10 Weather-Restricted Operations & Weather Forecasts 20
5.11 Scour Protection 21
6 VESSELS 22
6.1 Background 22
6.2 Moorings 22
6.3 DP Vessels 22
6.4 Jack-Ups Unrestricted Operations 22
6.5 Jack-Ups Weather-Restricted Operations 23
6.6 Crane Vessels (Seagoing) 23
6.7 Inshore Crane Vessels and Barges 23
6.8 Grounded Installation Vessels and Barges 24
6.9 Transportation Ships, Tugs & Barges 24
6.10 Cable Laying Barges 24
6.11 Cable Laying Vessels 24
6.12 Other Vessels 24
7 LOAD-OUT 25
7.1 Lifted, Skidded and Trailer Load-Outs 25
7.2 Float-Over 25
7.3 Cable Load-Out 25
8 MARINE TRANSPORTATION 28
8.1 Transportation of Components on Vessels or Barges 28
8.2 Transportation of Complete Rotor 28
8.3 Transportation of Tall Vertical Cargoes 28
8.4 Concrete Gravity Structures & Other Wet Towages 29
8.5 Cables 29
9 INSTALLATION 30
9.1 General 30
9.2 Monopiles and Transition Pieces 30
9.3 Piling Templates 30
9.4 Suction Bucket Foundations 31

0035/ND Rev 0 Page 3 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

9.5 J-tubes and I-Tubes 31


9.6 Turbine Installation 31
9.7 Towers 31
9.8 Nacelles 32
9.9 Blades 32
9.10 Complete Rotor Installation 32
9.11 Lifting operations and Lifting Tools 32
9.12 Innovative Installation Methods 33
10 CABLE INSTALLATION 34
10.1 Background 34
10.2 Major Challenges /Considerations for All Cables 34
10.3 Specific Challenges /Considerations for Export Cables 36
10.4 Specific Challenges /Considerations for Array Cables 36
10.5 Cable Route Survey and Positioning 36
10.6 Procedures 37
10.7 Project Installation Manuals 38
10.8 Cable Protection 39
10.9 Plough Operations 41
10.10 Vessel Movement and Cable Pay-out 41
10.11 Pull-in and Transfer to Structures 42
10.12 Cable Laying Mooring 43
10.13 Pull-Ahead Anchor & Winch 43
10.14 Carousels and Fixed Cable Tanks 44
10.15 Lifting Cables 44
10.16 Catenary Management 44
10.17 Cable Radius Control System 45
10.18 Lay Chute and Lay Sheave 45
10.19 Temporary Abandon Procedure 46
10.20 Array Cables 46
10.21 Export Cables 46
10.22 Export Cable Landfall 47
10.23 Cable and Pipe-Line Crossings 47
10.24 Cable Jointing and Repair 48
REFERENCES 50
APPENDIX A - INITIAL INFORMATION REQUIRED FOR APPROVAL 51

TABLES
Table 4-1 Typically Required Surveys 15
Table 5-1 Relative Advantages of Different Installation Vessels & Positioning Systems 17

FIGURES
Figure 5-1 Simplified Required Early Interaction Flow-Chart 16

0035/ND Rev 0 Page 4 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

1 SUMMARY
1.1 These guidelines have been developed for the installation of offshore wind farms of various types.
They mainly refer to other GL Noble Denton guidelines developed for similar operations, but giving
alternatives which may apply to offshore wind farm installations.

1.2 They are intended to show clients the requirements for obtaining approval by GL Noble Denton. This
approval may be needed where an operation is the subject of an insurance warranty, or where an
independent third party review is required.

1.3 A description of the Marine Warranty approval process is given together with practical advice on
current best practice in offshore wind farm installation.

0035/ND Rev 0 Page 5 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

2 INTRODUCTION
2.1 SCOPE
2.1.1 This document provides guidance for installation of offshore wind farms, in particular:
Foundations including monopiles, steel jackets, gravity bases, suction bases, floating bases
including spars, TLPs and semisubmersibles.
Turbines and other equipment on pre-installed foundations.
Offshore substations, transformer, control and other platforms, including those on jack-up
platforms.
Array and Export cable laying, protection and installation onto foundations and offshore
substations.

2.1.2 In particular it identifies factors that need to be addressed as wind farm installation moves into deeper
water and more exposed locations.
2.1.3 The guidelines and calculation methods set out in this document represent the views of GL Noble
Denton and are considered to be in accordance with offshore wind farm industry good practice.
Operators should also consider national and local regulations, which may be more stringent.

2.2 OTHER GL NOBLE DENTON GUIDELINE DOCUMENTS


2.2.1 This document refers to, and should be read in conjunction with other GL Noble Denton Guideline
documents, particularly:
0001/ND General Guidelines for Marine Projects, Ref. [1]. In particular this covers
a. The approval process for marine warranty
b. Health Safety and Environment
c. Organisation, planning and documentation
d. Metocean criteria (design and operating) and forecasts
e. Weight Control
f. Structural Strength
g. Building /construction basins
h. Tow-out from dry-dock /building basin
i. Temporary ballasting & compressed air systems
j. Use of Dynamic Positioning (DP) vessels

0009/ND Guidelines for Elevated Operations of Jack-Ups, Ref. [2]


0013/ND Guidelines for Load-Outs, Ref. [3]
0015/ND Guidelines for Concrete Gravity Structure Construction & Installation, Ref. [4]
0016/ND Seabed and Sub-seabed Data Required for Approvals of Mobile Offshore Units
(MOU), Ref. [5]
0021/ND Guidelines for the Approval of Towing Vessels, Ref. [6]
0027/ND Guidelines for Marine Lifting & Lowering Operations, Ref. [7]
0028/ND Guidelines for Steel Jacket Transportation & Installation, Ref. [8]
0030/ND Guidelines for Marine Transportations, Ref. [9]
0031/ND Guidelines for Float-over Installations /Removals, Ref. [10]
0032/ND Guidelines for Moorings Ref. [11].

0035/ND Rev 0 Page 6 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

2.2.2 Electronic versions of GL Noble Denton Guidelines are available on:


http://www.gl-nobledenton.com/en/rules_guidelines.php
Care should be taken when referring to any GL Noble Denton Guideline document that the latest
revision is being consulted.
2.2.3 Designers and installers of innovative designs or installation methods are recommended to discuss the
procedures and design with the relevant GL Noble Denton office at an early stage of the project to
ensure that it will be approvable without changes.
2.2.4 Please contact the Technical Policy Board Secretary at TPB@nobledenton.com with any queries or
feedback.

2.3 EXCLUSIONS
2.3.1 Diving operations are not generally subject to a Marine Warranty and so are normally excluded,
except in so far as they may cause delays to weather-sensitive operations. In particular delays may be
caused by waiting for slack tide to allow divers to work safely. Where possible, weather sensitive
operations should be planned to be achieved without the use of divers.
2.3.2 Grouting operations are normally covered by the Certifying Authority rather than the Marine Warranty
Surveyor (MWS). Agreement will need to be made with the client at an early stage to define the
boundaries between the involvements of the Certifying Authority and the MWS. However the timing of
grouting operations that could delay a monopile or piled jacket being able to resist a 10 year seasonal
storm is of concern to the MWS. In particular any damage to grout seals before grouting will be a
concern (see Section 5.3.2 d) as it could delay grouting.
2.3.3 Structural strength and operability of completed installed structures and equipment are covered by
the Certifying Authority rather than the MWS. The MWS is only concerned with the strength during
installation, including transportation and load-out. GL Noble Denton will accept a statement from the
Certifying Authority that the structure can safely withstand the required accelerations and loads for the
load-out, transportation and installation provided that the load paths /allowable local forces for
seafastening, lifting or load-out forces are given. Alternatively the relevant calculations may be
reviewed by GL Noble Denton.
2.3.4 Un-exploded ordnance UXO disposal is not generally subject to a Marine Warranty and is normally
excluded. However it is recommended that it will be managed in accordance with the requirements of
Risk Management Framework provided in CIRIA C681, K Stone, et al. (2009), or Unexploded
Ordnance (UXO) - A Guide for the Construction Industry, or similar.

0035/ND Rev 0 Page 7 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

3 DEFINITIONS & ABBREVIATIONS


Referenced definitions are underlined.
Term or Acronym Definition
ALARP / As Low As A philosophy used in Risk Assessment to find acceptable risk levels.
Reasonably
Practicable
AMS Anchor Management System.
Approval The act, by the designated GL Noble Denton representative, of issuing a
Certificate of Approval.
Array Cable(s) Generic term collectively used for Inter Turbine Cables and Collector
Cables.
Barge A non-propelled vessel commonly used to carry cargo or equipment. (For
the purposes of this document, the term Barge can be considered to
include Pontoon, Ship or Vessel where appropriate).
BAS / A survey to assess the expected burial depths on a cable route using
Burial Assessment purpose built sledges equipment with bottom penetrating sonar equipment
Survey. or by towing a miniature plough.
Bend restrictor A device with several interlocking elements that lock when a design radius
is achieved.
Bird Caging A phenomenon whereby armour wires locally rearrange with an increase
and/or decrease in pitch circle diameter as a result of accumulated axial
and radial stresses in the armour layer(s).
BPI / A process to optimise cable burial depth requirements based on a risk
Burial Protection assessment of threats to the cable and the soil strengths in the location of
Index each risk.
Cable Burial A submarine power cable is trenched into the seabed and covered with soil
providing complete burial of a cable (see Cable Trenching below)
Cable Trenching A submarine cable is lowered beneath the mean seabed level into an open
cut trench. The trench is left open and any subsequent cover of the cable
is by natural reinstatement of the seabed.
Cats-paw An extreme type of loop thrown into cables where a combination of low
tension and residual torsion forms a twisted loop. Commonly seen at
repair Final Splice locations where the Final Splice is lowered too quickly.
Certificate of A formal document issued by GL Noble Denton stating that, in its
Approval judgement and opinion, all reasonable checks, preparations and
precautions have been taken to keep risks within acceptable limits, and an
operation may proceed.
Cable Grips Cable Grips are used to pull or support cables and pipes. They work on
the principle of the harder the pull, the tighter the grip.
Chinese Fingers Also known as pulling socks, are used to pull or support cables and pipes.
They work on the principle of the harder the pull, the tighter the grip.
CLB Cable Lay Barge
CLV Cable Laying Vessel. Main cable installation vessel.

0035/ND Rev 0 Page 8 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

Term or Acronym Definition


CLV (SE) Cable Laying Vessel (Shore End).
Collector Cables Submarine power cables that collect power from strings of Array Cables
and deliver that power to an offshore substation.
Competent person Someone who has sufficient training and experience or knowledge and
other qualities that allow them to assist you properly. The level of
competence required will depend on the complexity of the situation and the
particular help required.
Crane vessel The vessel, ship or barge on which lifting equipment is mounted. For the
purposes of this document it is considered to include: crane barge, crane
ship, derrick barge, floating shear-leg, heavy lift vessel, semi-submersible
crane vessel (SSCV) and jack-up crane vessel.
CSA / Normally presented as the CSA of a single conductor in a submarine power
Cross Sectional Area cable x 3. For example a submarine power cable with 3x600mm2 in its
designation would be a cable with three conductors each of 600mm2.
DP Dynamic Positioning or Dynamically Positioned
Export Cable(s) Submarine power cables connecting the offshore wind farm to a landfall
connection point and hence the onshore distribution network.
FAT Factory Acceptance Tests
Final Splice The location where a second joint is inserted into a cable system during a
repair and includes the excess slack in the cable where the two ends of the
final splice come to the surface.
FMEA or Failure Modes and Effects Analysis or
FMECA Failure Modes, Effects and Criticality Analysis
GBS Gravity Base Structure (foundation)
GL Noble Denton The legal entity trading under the GL Noble Denton name which is
contracted to carry out the scope of work and issues a Certificate of
Approval, or provides advice, recommendations or designs as a
consultancy service.
Grommet A single length of unit rope laid up 6 times over a core, as shown in IMCA,
Ref. [17], to form an endless loop
HDD Horizontal Directional Drilling
HVAC High Voltage Alternating Current
HVDC High Voltage Direct Current
HPR Hydro-acoustic Positioning Reference. A through water acoustic link
between a vessel and a seabed beacon. Used to locate and track vehicles
in the water column and can be used as a DP reference.
IACS International Association of Classification Societies
ICPC / A trade body representing and lobbying on behalf of subsea cable owners.
International Cable For historical reasons membership is predominately telecom companies.
Protection
Committee
ITP / A plan in which all test, witness and hold points for all aspects of a cable
Inspection Test Plan installation are listed.

0035/ND Rev 0 Page 9 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

Term or Acronym Definition


IVB Independent Verification Body. The wind farm certification agency.
I-tube. A vertical tube fitted to offshore structures to install submarine cables
between the seabed and the structure topsides.
Installation Analysis. An analysis of the impact the installation methods will have on the cables to
be installed. Focusses on the cable tension for each stage of an
installation and should include an analysis of the seabed stability of the
cable for surface laid sections especially when the cable will be laid in a
curve or around an alter course.
Insurance Warranty A clause in the insurance policy for a particular venture, requiring the
approval of a marine operation by a specified independent survey house.
Inter Turbine Cables Submarine power cables connecting two turbines.
J-tube A J shaped tube fitted to offshore structures to install submarine cables
between the seabed and the structure topsides.
LCE / An industry term commonly used to refer collectively to cable lay
Linear Cable Engine tensioners.
Lift point The connection between the rigging and the structure to be lifted. May
include padear, padeye or trunnion
Load-out The transfer of a major assembly or a module from land onto a barge e.g.
by horizontal movement or by lifting
MBR / Minimum The minimum allowable radius of a bend in a cable (to prevent damage)
Bending Radius
MP / Common tubular structure used as foundation for offshore wind turbine
Monopile generator.
MPI / Magnetic A Non-Destructive Testing (NDT) process for detecting surface and slightly
Particle Inspection subsurface discontinuities in ferroelectric materials such as iron.
MWS Marine Warranty Surveyor (see Section 4.1 of 0001/ND, Ref. [1]).
Nacelle The part of the wind turbine on top of the tower, where the hub, gearbox,
generator and control systems are located.
Net weight The calculated or weighed weight of a structure, with no contingency or
weighing allowance
NTE weight / sometimes used in projects to define the maximum possible weight of a
Not To Exceed particular structure.
weight
NDT / Non Ultrasonic scanning, magnetic particle inspection, eddy current inspection
Destructive Testing or radiographic imaging or similar. May include visual inspection.
Operation Duration The planned duration of the operation excluding a contingency period
from the Point of No Return to a condition when the operations /structures
can safely withstand a seasonal design storm (also termed safe to safe
duration).
Operation, Any activity, including load-out, transportation, offload or installation, which
marine operation is subject to the potential hazards of weather, tides, marine equipment and
the marine environment,

0035/ND Rev 0 Page 10 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

Term or Acronym Definition


Operational The Operation Duration, including a contingency period.
reference period
OWF Offshore Wind Farm
Padear A lift point consisting of a central member, which may be of tubular or flat
plate form, with horizontal trunnions round which a sling or grommet may
be passed
Padeye A lift point consisting essentially of a plate, reinforced by cheek plates if
necessary, with a hole through which a shackle may be connected
PLIB / The use of a WROV to survey the installed cables. WROVs are often used
Post Lay Inspection with a cable burial module in order that an attempt can be made to
Burial. increase the burial depth in areas where the burial depth is non-
conforming.
PLGR / The use of grapnels to clear linear debris that might have fallen onto the
Pre Lay Grapnel Run cable route after RC operations. Normally done immediately before cable
lay and burial operations.
PNR / The last point in time, or a geographical point along a route, at which an
Point of No Return operation could be aborted and returned to a safe condition.
Pull Back Method A J-tube pull-in operation where the pull-in winch is mounted on the
installation vessel and the end of the pull-in wire connected to the cable
runs from the vessel to the J-tube bottom end up and over a sheave and
back to the installation vessel pull-in winch.
Quadrant A structure, usually with rollers, to limit the MBR as the cable travels over
or though it and changes direction, typically during loading or laying during
second end J tube pull in operations.
RC / The use of grapnels and other methods to clear debris from the planned
Route Clearance. cable routes. Normally done well in advance of cable operations to allow
adequate time to remove debris.
Rigging The slings, shackles and other devices including spreaders used to
connect the structure to be lifted to the crane
Rigging weight The total weight of rigging, including slings, shackles and spreaders,
including contingency.
Rotor Configuration consisting of the complete set of blades, connected to the
hub.
RPL / A tabularised list of the co-ordinates defining the route along which a
Route Planning List. submarine cable is to be installed and the planned installation slack. A
post installation RPL will record the as-built cable route co-ordinates,
installed slack and burial depths.
Seafastenings The system used to attach a structure to a barge or vessel for
transportation
Scour pit The result of scour around a pile, leg etc. See Ref. [21].
SE / The section of submarine cable installed between the landfall connection
Shore End point and the offshore set up position of the CLV or CLB.

0035/ND Rev 0 Page 11 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

Term or Acronym Definition


SIMOPS / Operations usually involving various parties and vessels requiring co-
Simultaneous ordination and definitions of responsibilities.
Operations
Slack Management A generalized term used by the submarine cable installation industry to
refer to the control of cable pay-out out against a pre-defined installation
plan.
Spreader beam or A spreader beam or bar is a structure designed to resist the compression
bar forces induced by angled slings, by altering the line of action of the force on
a lift point into a vertical plane. The structure shall also resist bending
moments due to geometry and tolerances.
Spud A large metal post which penetrates the seabed under its own weight and
is used to prevent lateral movement of a barge. A dredge barge will
typically have two spuds in guides near its stern.
Structure The object to be lifted
Survey Attendance and inspection by a GL Noble Denton representative.
Other surveys which may be required for a marine operation, including
suitability, dimensional, structural, navigational and Class surveys.
Surveyor The GL Noble Denton representative carrying out a survey.
An employee of a contractor or Classification Society performing, for
instance, a suitability, dimensional, structural, navigational or Class survey.
SWL / SWL is a de-rated value of WLL, following an assessment by a competent
Safe Working Load person of the maximum static load the item can sustain under the
conditions in which the item is being used.
Tensioner A winch used for handling submarine power cables to pay out and pick up
or to provide hold back tension in the cable during installation operations.
TD / Seabed location at which a submarine cable touches down on the seabed
Touch Down during installation.
Tower The tubular element from the top of the flange on the foundation to the
bottom of the flange below the nacelle, generally built up of several
sections.
TP / A tubular structure on top of a monopile to provide a horizontal foundation
Transition Piece for the tower.
Trunnion A lift point consisting of a horizontal tubular cantilever, round which a sling
or grommet may be passed. An upending trunnion is used to rotate a
structure from horizontal to vertical, or vice versa, and the trunnion forms a
bearing round which the sling, grommet or another structure will rotate.
UNCLOS United Nations Law of the Sea
UXO Unexploded Ordnance
Vessel A marine craft designed for the purpose of transportation by sea or
construction activities offshore. See Barge

0035/ND Rev 0 Page 12 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

Term or Acronym Definition


Weather restricted A marine operation which can be completed within the limits of an
operation operational reference period with a favourable weather forecast (generally
less than 72 hours), taking contingencies into account.
The design environmental condition need not reflect the statistical
extremes for the area and season.
A suitable factor should be applied between the operational weather limits
and the design weather conditions (see Section 7.3.3 of 0001/ND, Ref. [1]).
Weather unrestricted An operation with an operational reference period greater than the reliable
operation limits of a favourable weather forecast (generally less than 72 hours).
The design weather conditions must reflect the statistical extremes for the
area and season.
The design weather is typically a 10 year seasonal storm, but subject to
Section 7.2.2 of 0001/ND, Ref. [1].
WLL / The maximum force which a product is authorized to sustain in general
Working Load Limit service when the rigging and connection arrangements are in accordance
with the design. See SWL.
WTG Wind Turbine Generator
WROV Work class Remotely Operated Vehicle.
XLPE / Cross Linked A type of AC cable conductor insulation commonly used on submarine
Polyethylene power cables.

0035/ND Rev 0 Page 13 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

4 THE APPROVAL PROCESS


4.1 GL NOBLE DENTON APPROVAL
4.1.1 See Section 4 of 0001/ND General Guidelines for Marine Projects, Ref. [1] for more details.
4.1.2 See Section 4.6 of 0001/ND, Ref. [1], for details of the approval of repetitive operations.

4.2 SCOPE OF WORK LEADING TO AN APPROVAL


4.2.1 The scope of work of each phase of installation, apart from cable installation, is covered in the relevant
guidelines described in Section 2.2.
4.2.2 The scope of work for cable installation will depend on the insurance warranty but may typically cover:
a. Attendance at Factory Acceptance Tests (FAT) at the factory.
b. Approval of land transport to the loading port.
c. Approval of load-out onto a transport vessel, CLV or CLB and any subsequent inter-vessel
transfer. This may include continuous attendance witnessing the load-out.
d. Approval of transport of cables to offshore site.
e. Approval of cable route and method(s) of protecting the cable along the route.
f. Approval of cable installation including trenching, burial or other protection and terminations at
either end.
g. Review and appproval of the Installation Manual, Installation Procedures, Task Plans, HAZID,
HAZOP and Contingency Procedures.
h. Review of Installation Analysis, vessel motion analysis and other relevant analyses to ensure all
criteria stated in the Installation Manual and other installation procedural documents are
supported by valid calculations.
i. Approval of CLV, CLB and CLV (SE) cable installation equipment on them.
j. Approval of attending tugs and other construction support vessels.
k. Approval of submarine cable Installation Analysis.
l. Approval of CLV, CLB and/or CLV(SE) limiting sea states for each stage of the cable installation
operationApproval of weather-restricted operations.
m. Issuance of Certificates of Approval for towing/transport and installation of cables on a cable by
cable basis. Issuance of Statements of Acceptablity for operations that no longer require GL
Noble Denton attendance, includes setting of conditions that must be followed for the
Statements of Acceptablity to remain valid..

4.2.3 In order to issue Certificates of Approval, GL Noble Denton will typically require to consider, as
applicable, the following topics:
a. Operating manuals, including procedures and contingency procedures.
b. The management structure for multi-contracting projects for the operations, and Management of
Change procedures.
c. Site zone control, including Simultaneous Marine Operations (SIMOPS).
d. Design criteria and geotechnical, bathymetric and environmental /meterological data.
e. Risk assessments, HAZOP /HAZID studies involving all parties.
f. Operation-specific requirements described later in these guidelines.
g. Vessels suitability and certification.
h. Suitability of all jack-up operating locations (including soils, obstructions, survival air gap, and
suvivability of the jack-up in the design environmental conditions).

0035/ND Rev 0 Page 14 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

i. Procedures, calculations and equipment certification for:


All significant (as determined by the insurance warranty) load-outs
All significant towages or transportations
All significant lifts and installation operations
Cable laying and termination at either end.

4.2.4 Surveys carried out as part of GL Noble Dentons scope of work typically include those in the following
Table.
Table 4-1 Typically Required Surveys
Survey Time Place

Sighting of inspection/test. Certificates for slings Before departure of GL ND / client's office or


and shackles structure from shore fabrication yard
Survey of barge /transport vessel Before load-out
Survey of towing vessel(s) Before tow As available
Suitability survey of installation vessel and
installation /handling tools. This will include Before start of
witnessing function tests of new or adapted marine operations
handling /lifting tools
Survey of load-out site and equipment, and
Before load-out
issue of Certificate of Approval
Sighting of inspection /test certificates or release
notes for lift points and attachments Fabrication yard
Before departure of
Inspection of rigging laydown, seafastening, tow /transport
securing of all items, tow /transport preparations,
and issue of Certificate of Approval
Jack-up Crane vessel mooring and/or jack-up for
installation activities Before start of
marine operations
Installation vessel in-field DP trials At lift site
Inspection of preparations for lift, and issue of Immediately before
Certificate of Approval cutting seafastening

4.2.5 The survey frequency for repetitive operations is specified in Section 4.6 of General Guidelines
0001/ND, Ref. [1].

4.3 END OF MWS SCOPE OF WORK


4.3.1 The end of the scope of work is typically when the installation (or stage of installation) can safely
withstand a design storm. Agreement should be reached at an early stage of the project as exactly
when this is. It will depend on the warranty wording and agreement with the client and Certifying
Authority (see Section 2.3.3).

4.4 LIMITATION OF APPROVAL


4.4.1 See Section 4.5 of General Guidelines 0001/ND, Ref. [1].

0035/ND Rev 0 Page 15 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

5 GENERAL
5.1 COORDINATION
5.1.1 The owner or operator of a wind farm has a duty to provide In-field Management to co-ordinate the
operations of vessels and helicopters in the field and communications between them. In general there
will be many more vessels working in a wind farm during construction than in an oil or gas field of
comparable value.
5.1.2 The following figure shows the main interaction between parties that is required at an early stage of the
installation project to ensure success.

In-field Management (including communications / control, common


procedures & emergency procedures --see Section 5.1.3)

Turbine manufacturers MWS involvement (see


/designers involvement Section 5.2.4)

Installation /transportation Interaction between


contractors involvement contractors (SIMOPS)

Agree installation & maintenance vessels / methods Agree installation tolerances, vulnerable
- selection & availability (see Section 5.1.4) items & criteria (see Sections 5.2 and 5.3)
Figure 5-1 Simplified Required Early Interaction Flow-Chart

5.1.3 In-Field Management. This will include:


a. Scheduling contractors, vessels and helicopters to avoid congestion /collisions.
b. Co-ordinating communication and control between all parties to reduce conflicts and risks.
c. Managing common logistic arrangements and scheduling for key operations, especially
SIMOPS,
d. Providing a framework for developing and enforcing common procedures, including emergency
procedures, which define the responsibilities at all times.
e. Ensuring that adequate mooring systems can be laid to avoid damaging cables or subsea
structures, or interfering with other operations. This may involve installing prelaid pile anchors if
the anchor holding is poor or there are too many power or control cables on the seabed.
f. If jack-ups are used, ensuring that footprints and cable routes will not prevent other jack-ups
operating subsequently
g. Ensuring that all positional, bathymetric, soil and current surveys are performed using the same
datum and coordinate system, are of sufficient accuracy and that the results are disseminated
to all relevant parties as required. See Section 5.5.
h. Identifying particularly vulnerable items or areas that are at risk from operations by other
parties. See Section 5.3.
5.1.4 Vessels. Working alongside offshore structures for installation and maintenance may involve use of
many different types of vessel during the life of the structure, including:
Jack-up barges or ships which leave footprints into which subsequent jack-ups (especially with
different leg spacing) may slide, causing leg damage, or stand on cables that are laid in the
incorrect locations. The planning for installation and maintenance must allow for the use of
different jack-ups during the life of the wind farm.
Moored vessels with anchors that can drag and cut cables on the seabed.

0035/ND Rev 0 Page 16 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

DP vessels with the potential to lose position after a DP failure and hit the structure.
Vessels bringing repair and maintenance personnel, often with sophisticated transfer systems.
The main advantages and disadvantages of these different types are given in the following Table 5-1.
Table 5-1 Relative Advantages of Different Installation Vessels & Positioning Systems
Vessel /system Advantages Disadvantages
Jack-up Provides a relatively stable 1. Needs good weather (typically <1 to 2 m sig wave height) to
(of adequate operating platform above jack-up or down to move to a new location.
design) the waves (reducing crane 2. Normally needs moorings or DP to move onto location (tugs
see Note 1 hook movements).
may sometimes be used alone if locational accuracy is not
Can stay on location during required and there are no collision risks or strong currents)
storms. 3. Footprints from previous jack-ups may cause severe
(For some short operations structural problems due to legs sliding into them (especially if
in good weather, the jack- of different leg geometry.
up may not jack-up out of 4. Jack-ups may not be suitable with some seabeds (e.g. very
the water to save time but soft or rocky). Legs may be vulnerable to scour & punch-
use its legs to stay on
through. Adequate leg length required to maintain safe air
location).
gap in storms.
5. Limited number of jack-ups presently available with adequate
design especially for deeper exposed locations.
6. Cables on seabed (especially if not located accurately) may
restrict operating positions
Floating vessel Generally cheaper to 1. Vessel motions limit crane and other operations.
(not DP) operate than jack-ups or 2. Need moorings to stay on location (see below).
Mooring system DP vessels 1. Anchors may drag causing loss of position leading to collision,
Do not leave footprints or or cable /subsea structure damage.
tread on /damage cables 2. In some locations some anchor cables will require be
(apart from with anchors) slackened to avoid damage to structures between vessel and
anchor. Care needed when re-tensioned.
3. Mooring systems need redundancy.
4. Moorings must be laid to avoid damaging cables.
5. Generally moorings will not be designed to survive a storm so
the vessel needs to initially move away from a structure when
weather deteriorates and then out of the field if it gets worse.
DP (for vessel or Faster to mobilise or 1. Risk of run-off or drift-off after DP failure or if environmental
jack-up) demobilise and more conditions occur beyond the DP System capacity. (For jack-
flexible than if moored. ups this is for the approach only, reducing the time at risk).
DP vessels can operate in
deeper water than jack-ups
Sheerlegs Often have high lifting 1. As for floating vessels (moored or DP)
capacities 2. Less adaptable as cannot slew lifted objects
3. Usually designed for inshore or coastal use (small waves)
4. Class limitations may prevent use offshore.
Grounded (May be required in 1. Must avoid any prelaid cables unless well protected.
vessels /barges shallow water for cable 2. Generally requires a good weather window or sheltered water.
landfall) 3. Cohesive soils may hold the hull down when trying to refloat.
Note 1: Jack-ups that are not designed for ongoing seasonal operations for that location may need to cut and
run for a safe location before the weather exceeds that required for safely jacking down into the water.

0035/ND Rev 0 Page 17 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

5.2 TOLERANCES & CRITERIA


5.2.1 The selection of many installation tolerances and criteria will be an economic trade-off between
reducing the cost of manufacture and reducing the costs of delays waiting for good weather in
consequence. Manufacturers often prefer tighter installation tolerances which require better weather
criteria for installation. It is generally beneficial to select the transportation /installation contractors
before such tolerances and criteria are fixed as they may significantly affect the installation methods,
risks and costs.
5.2.2 Such tolerances may include:
a. Position and orientation of monopiles, pile templates, jackets and other structures.
b. Pile or structure verticality.
c. Clearances between piles inside pile sleeves, including allowances for weld beads and grout
keys.

5.2.3 Such criteria may include:


a. Wind speeds (at specified heights and gust durations) for critical lifts.
b. Any restrictions on current speeds or wave heights (and how they will be measured) for specific
operations. These could include stabbing piles or jackets into templates.
c. Degree of acceptable damage to grout keys during piling.
d. Any restrictions on helicopter or vessel movements within the field in bad visibility or other
adverse conditions.
e. Any restrictions on transfer of people and equipment onto fixed or floating installations by
various means.
f. Requirements for disposal of any dredged materials, drilling cuttings or soil plugs removed from
piles (to comply with national or international laws or conventions, and to avoid problems with
other contractors).
g. Piling operations sound effects on sea life.

5.2.4 GL Noble Denton will also have an input to such selection in so far as the tolerances and criteria must
not be so severe that there is a possibility that the equipment may never be able to be installed without
taking unacceptable risks. If installation environmental criteria are set too high then there is also a
higher probability of damage.

5.3 VULNERABLE ITEMS OR AREAS


5.3.1 Due to the many parties and vessels working in close proximity it is necessary that each party
understands what items are particularly vulnerable to actions by others. These items need to be
identified at an early stage so that they can be considered in the relevant risk assessments. The list of
vulnerable items needs to be updated and promulgated as required during the life of the wind farm.
5.3.2 Typical vulnerable items or areas may include:
a. J-tube entry holes being covered with soil or debris
b. Changes in seabed level (from scour, dredging, jack-up footprints, drill cuttings etc) varying the
natural frequency of foundations.
c. Scour can also affect jack-up foundations, cables, anchors etc. Scour model tests may be
required in areas with high current speeds and soft or sandy seabeds.
d. Damage to grout seals and back-up seals.
e. External fittings (including anodes, J-tubes) being damaged by dropped objects, vessel collision
or mooring lines.
f. Operations of divers (vulnerable to propellers and propeller wash, noise and blast, bubble
curtains, cables and dropped or lowered objects).

0035/ND Rev 0 Page 18 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

5.4 PLANNED MOORINGS


5.4.1 Geotechnical and bathymetric surveys should determine at an early design stage if the seabed will
provide good anchor holding and may determine the type of anchors that will be needed. If anchor
holding is poor (leading to a high probability of dragging anchors damaging cables) then prelaid or
piled anchors may be very cost effective. Allowable anchor locations should be agreed at the same
time as the cable routes.

5.5 SITE & ROUTE SURVEY REQUIREMENTS


5.5.1 As well as ensuring that all positional, bathymetric, soil and current surveys are performed using the
same datum and coordinate systems, various requirements to ensure sufficient accuracy like the
frequency of survey equipment calibration (for salinity, temperature etc) must be agreed. There should
be an agreed procedure for ensuring that all survey results are disseminated to all relevant parties as
required.
5.5.2 The as built locations of structures, cables and subsea equipment must be recorded accurately on
charts using a common survey datum used by all parties. These charts must be kept updated,
including all jack-up footprints as soon as they are made and issued to all vessels operating in the
field. No anchoring zones must be well marked.
5.5.3 In advance of the final detailed design being carried out for the foundations, the seabed material, and
geophysical and geotechnical surveys of the sub-bottom profile should have been carried out, as well
as magnetometer surveys for ferrous objects. The Cone Penetrometer Test results and other
appropriate survey details for each foundation location should be issued, or made available, to jack-up
vessel operators. This will allow them to carry out site-specific assessments in accordance with
ISO 19905-1, Ref. [20], and to assess the possibility of scouring around jack-legs and spud-cans.
5.5.4 Additional requirements for the cable route surveys are given in Section 10.5.

5.6 HEALTH SAFETY & ENVIRONMENT


5.6.1 Section 5 of 0001/ND, Ref. [1], describes the requirements for most offshore construction /installation
projects.
5.6.2 For marine operations that are planned to carried out in close proximity to fixed or moored installations,
appropriate risk assessments and vessel audits shall be carried out prior to issue of a Certificate of
Approval.
5.6.3 Risk assessments, HAZOP / HAZID studies shall be carried out in the presence of the client, GL Noble
Denton and the contractors operational personnel. These studies shall be completed at an early stage
so that the findings can be incorporated into the operational procedures.

5.7 ORGANISATION & COMMUNICATION


5.7.1 Section 6.2 of 0001/ND, Ref. [1], gives suggestions for the type of organisation and communications
that is usual for efficient offshore projects.
5.7.2 Sufficient management and resources shall be provided and documented to carry out the operations
efficiently and safely.
5.7.3 Where the installation operations are carried out using a multi-contracting strategy, the organisation
and management of these marine operations shall be defined by organisation charts with reporting
lines and definition of roles and responsibilities of key personnel.

0035/ND Rev 0 Page 19 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

5.8 PROCEDURES AND MANUALS


5.8.1 The management structure for each operation, including reporting and communication systems, and
links to safety and emergency services shall be shown. They should include:
a. The anticipated timing and duration of each operation, including contingencies.
b. The limiting wave states, wind speeds and currents, and where applicable any visibility/day-
light, temperature and precipitation limits, as well as the site-specific equipment or methodology
prescribed for measuring each limit-state.
c. The arrangements for control, manoeuvring and mooring of barges and/or other craft alongside
installation vessels.
d. Effects on and from any other simultaneous operations (SIMOPs see IMCA Ref. [18]).
e. Contingency and emergency plans.
f. Requirements from the relevant GL Noble Denton guidelines for each individual phase.

5.9 WEIGHT CONTROL


5.9.1 The requirements in Section 8 of 0001/ND General Guidelines for Marine Projects, Ref. [1], will apply.
5.9.2 Additionally for lifting, the weight contingency factors of Section 5.2 of 0027/ND Guidelines for Marine
Lifting & Lowering Operations, Ref. [7] will apply.
5.9.3 The manufacturer shall supply a weight statement with tolerance and CoG envelope for all weight-
sensitive items.
5.9.4 When a large number of virtually identical items are built with very good quality control, reduced weight
contingency factors may be agreed with GL Noble Denton based on the standard deviation from
weighing of initial items, with random subsequent weighing used to confirm consistency of
manufacture.
5.9.5 Weighing of each item may not be required if the quality control and predictions of final weights in initial
weighings are shown to be good enough and a reduced requirement for weighing may then be agreed
with GL Noble Denton.

5.10 WEATHER-RESTRICTED OPERATIONS & WEATHER FORECASTS


5.10.1 See Section 7 of 0001/ND General Guidelines for Marine Projects, Ref. [1] for more details.
5.10.2 For areas with high tidal currents there may be additional restrictions on operations due to the need to
wait for slack (or slacker) tides for current-sensitive operations such as:
Moving jack-ups on or off location
Stabbing piles or installing jackets, substructures or equipment on the seabed
Bringing cargo barges alongside installation vessels.
Diving operations.

5.10.3 When high currents are combined with shallow water then additional current forces will be caused by
blockage effects. These shallower conditions also lead to increased seabed turbulence due to wave
action, and additional contingency measures may be necessary to make allowances for accelerated
scouring around jack-legs and spud-cans.
5.10.4 However suitable moorings, stabbing guides and other aids may help to reduce the sensitivity to
currents and decrease downtime waiting for slack tide.
5.10.5 A weather forecast of at least 48 hours duration, from an approved source, predicting that conditions
will be within the prescribed limits, shall be received prior to the start of any weather-sensitive
operation, and at not more than 12 hourly intervals (but preferably 6 hourly and on issuance of a bad
weather warning) thereafter, until the operation is deemed complete, i.e. with all equipment and
vessels in a safe condition even if the weather deteriorates.

0035/ND Rev 0 Page 20 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

5.10.6 Weather forecasts for wind speed should specify the height (to be agreed in advance) and wind
speeds measured on site should be corrected to that height for direct comparison. The swell height,
direction, and period should also be included, as well as the probability of precipitation, fog and
lightning within the next 24 hours. The time of sunrise and sunset, and the phase of the moon may be
advantageous though these will normally be found in nautical almanacs.
5.10.7 In field monitoring of waves (height, direction and period) should be considered to enhance the
forecast for each specific lift operation.
5.10.8 For subsea lifts in areas where it is known that high currents exist in the water column, in-field
monitoring of currents (speed and direction) should be considered to enhance the regular forecasts.
The monitoring of sub-sea currents with acoustic Doppler or similar systems should be considered
when the operational limits of ROVs, and drag on piles during stabbing can lead to operational delays.
5.10.9 Current and wave monitoring may also be used to reduce contractual disputes when operating in a
specific current speed or wave height is a contractual requirement. However contractual requirements
must not be allowed to over-ride safety or to increase risk.

5.11 SCOUR PROTECTION


5.11.1 See Sections 5.5.3 & 5.10.3 for information that will help in prediction of scour. Dynamics of scour
pits and scour protection, Ref [21] gives the results of research into scour on early UK offshore wind
farms.
5.11.2 If scour is a possible problem then procedures or contingency procedures shall be prepared and anti-
scour materials stockpiled and deployment equipment prepared for mobilisation.
5.11.3 Scour around jack-up legs may also make them more vulnerable to punch-through.
5.11.4 Care should be taken when laying scour protection to ensure that bad weather and/or high currents
during the installation phase do not cause damage to the lower layers.
5.11.5 Cables will generally be trenched or otherwise protected in scour-prone areas. However additional
precautions may be required close to J-tubes or I-tubes at monopiles or platforms, especially
immediately after laying.

0035/ND Rev 0 Page 21 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

6 VESSELS
6.1 BACKGROUND
6.1.1 Many existing wind farms are in shallow sheltered waters. This has allowed use of coastal and inshore
vessels that are not designed or classed for operating in exposed waters. In turn, this has often
required vessels to remain within a limited distance from a port of shelter and for jack-ups to jack down
and seek shelter on a bad weather forecast. This approach exposes the operations to a high risk of
accidents from unforecast bad weather and being caught on a lee shore.
6.1.2 The risk is further increased if the national administration and/or class restrictions require the unit to
remain within a certain distance from land (which may be a lee shore) but where there is no safe port
or sheltered jacking location. However some national administrations and classification societies may
be prepared to agree specific direct routes in advance which are shorter and entail less risk but exceed
the normally required distance from shore.
6.1.3 Installation in deeper and more exposed locations requires a different approach, such as is used in the
oil and gas industries, in which vessels typically have to be designed to survive in 50 to 100 year
design storms without seeking shelter. Although the initial costs are higher, the greatly increased
productivity and decreased risk make this approach much more attractive financially.

6.2 MOORINGS
6.2.1 Almost all installation vessels, unless operating on DP, will require suitable moorings to keep them on
station when working alongside a structure, or when preparing to jack-up or jack-down.
6.2.2 These moorings should be designed to the requirements of 0032/ND, Ref. [11], using the agreed
design criteria corresponding to the proposed operating criteria modified by the relevant Metocean
Reduction Factors described in Section 7.3 of 0001/ND, Ref. [1].

6.3 DP VESSELS
6.3.1 A vessel with a minimum DP Class 2 will generally be required though a few operations, e.g. rock-
dumping and cable-laying when not close to high value structures, may use DP Class 1 if the
consequences of any DP failure are low. Further requirements are in Section 13 of 0001/ND, Ref. [1].
6.3.2 Jack-ups with DP shall have procedures to determine at what stages during installation or departure
from a location they will operate in DP mode. As a general rule (subject to the risk assessment for the
specific operation) jack-ups need to be on manual control once the seabed develops a certain level of
lateral resistance during installation, and at all stages during departure. See also Section 13.7 of
0001/ND, Ref. [1].

6.4 JACK-UPS UNRESTRICTED OPERATIONS


6.4.1 Jack-ups that are designed and classed for elevated operations in conditions in excess of those at the
installation site (either all year or for particular months) shall, as a minimum, comply with the
requirements of BWEA /RenewableUK Guidelines for Jack-Ups, Ref.[12].
6.4.2 The jack-up may operate at a lower air gap than required for survival in a design storm as long as it is
able to jack-up to a safe air gap for a design storm before bad weather. If a breakdown prevents
jacking up then the crew may need to be evacuated.

0035/ND Rev 0 Page 22 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

6.5 JACK-UPS WEATHER-RESTRICTED OPERATIONS


6.5.1 Jack-ups that cannot comply with Section 6.4 above for a specific location and season shall comply
with the requirements for Weather-Restricted Operations in Section 5.3 of BWEA Guidelines for
Jack-Ups, Ref. [12]. This is summarised as:
a. Agree procedure documents which include limiting criteria for relevant decision points and
identify suitable alternative jack-up locations between the site and safe ports. These criteria
shall take into consideration the Metocean Reduction Factors described in Section 7.3 of
0001/ND, Ref. [1].
b. The jack-up is only to leave a safe location to go to the installation site on receipt of a confident
good weather forecast to cover the time (including a contingency for delays) from departure to
return to a safe location.
c. The jack-up is to leave the installation site unless there is a confident good weather forecast to
cover the remaining time on site and to return to a safe port or to elevate to a safe air gap at a
suitable stand-by location, including a contingency for delays.
d. If the jack-up cannot reach a safe port or location before meeting bad weather (above the laden
jacking limits of the jack-up, typically about 1 to 1.5 m significant wave height), then it should
jack-up to survival air gap at a suitable shallow water location and evacuate the crew if
necessary.

6.5.2 The procedures and criteria described in Section 6.5.1 above shall be the subject of a risk assessment
in which GL Noble Denton participates and agrees that the risks are acceptable.
6.5.3 Jack-ups may also operate when moored afloat, or partly elevated, to save time jacking up and down
and preloading. These operations will require good weather and need to follow the Weather-Restricted
Operations requirements of Section 7.3 of 0001/ND, Ref. [1].

6.6 CRANE VESSELS (SEAGOING)


6.6.1 Any seagoing crane ship operating in an area for which it is classed should be able to survive in bad
weather unless it is carrying vulnerable cargo. However any lifting and mooring operation needs to be
done in good weather and these design and operating criteria need to be agreed with GL Noble
Denton taking Metocean Reduction Factors into account.
6.6.2 Carrying a suspended load on a crane hook in transit offshore is not generally considered good
practice, unless it is for very short distances in calm weather. In bad weather the load may be very
difficult to control, stability is reduced and the crane may be overloaded. Approval of such operations
will require agreement from the Classification Society and a risk assessment in which GL Noble
Denton participates and agrees that the risks are acceptable.

6.7 INSHORE CRANE VESSELS AND BARGES


6.7.1 Inshore crane vessels and barges shall only be used if allowed by their class notation and:
a. GL Noble Denton has agreed procedure documents which include limiting criteria for relevant
decision points and identifies safe ports or locations. These criteria shall take into consideration
the Metocean Reduction Factors described in Section 7.3 of 0001/ND, Ref. [1].
b. The vessel is only to leave a safe port or location to go to the installation site on receipt of a
confident good weather forecast to cover the period from departure to safe return, including a
contingency for delays.
c. The vessel to leave the installation site unless there is a confident good weather forecast to
cover the remaining time on site and to reach a safe port or location, including a contingency for
delays.

0035/ND Rev 0 Page 23 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

6.8 GROUNDED INSTALLATION VESSELS AND BARGES


6.8.1 Some vessels working in shallow water may need to be grounded at low water or over one or more
tidal cycles. This may only be approved provided that:
a. The vessels classification society allows such operations.
b. The seabed is such that the barge will not be damaged and it will not hold the barge down when
attempting to refloat.
c. There is a method (e.g. moorings or spuds) for holding the vessel on location when grounding
and floating off in the design conditions agreed with GL Noble Denton at the design stage
without damaging any cables or other structures or equipment..
d. A confident good weather forecast is obtained before grounding to cover the period (including a
suitable allowance for delays) until float-off without exceeding the design conditions in c. above
modified by the Metocean Reduction Factor.

6.9 TRANSPORTATION SHIPS, TUGS & BARGES


6.9.1 The requirements of 0030/ND Guidelines for Marine Transportations, Ref. [9], apply for all tows and
transportations. For short voyages the relaxations in Sections 6.3 and 6.4 of 0030/ND may apply.
6.9.2 If towing vessels are currently registered in the GL Noble Denton Towing Vessel Approval Scheme
(TVAS) see 0021/ND, Ref. [6], then suitability surveys will not be required, though a check will be
required before a Certificate of Approval is issued.

6.10 CABLE LAYING BARGES


6.10.1 Moored CLBs are standard industry equipment for installing submarine power cables in relatively
shallow waters in close proximity to land. Moored CLBs are equipped with four or more mooring
winches and one pull-ahead winch. They are usually flat top pontoons with a cable laying spread
added.

6.11 CABLE LAYING VESSELS


6.11.1 Cable ships are generally purpose built (or converted permanently) and typically use DP rather than
moorings. They can generally lay faster than barges and in deeper waters as they are not so restricted
by the time taken to adjust moorings.

6.12 OTHER VESSELS


6.12.1 Crew transfer or accommodation vessels with proprietary crew access arrangements.
6.12.2 Escort and standby vessels may be needed in some areas to warn off other vessels, especially during
sensitive operations or transports.
6.12.3 Bubble curtain deployment and energising vessels may be needed if regulations on piling noise
pollution apply (see Section 13.3 of 0028/ND, Ref [8]).

0035/ND Rev 0 Page 24 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

7 LOAD-OUT
7.1 LIFTED, SKIDDED AND TRAILER LOAD-OUTS
7.1.1 Lifted, skidded and trailer load-outs are covered in 0013/ND, Ref. [3]. However the following special
cases may apply.
a. Special consideration will be given to purpose-built lifting appliances for blades. The lifting tool
Certificate should specify the maximum load and any limits regarding the overall dimensions of
the lifted item and any environmental limitations (e.g. maximum wind speed).
b. In the event of structural modifications to an item of lifting equipment it shall be re-approved by
an IACS member before further use.
c. Bolts used for removable lifting lugs shall generally be used one time only. In special cases
re-use may be accepted as described in Section B5 in Appendix B of 0001/ND, Ref. [1], but
only if initial pretensioning does not exceed 60% of the bolt yield strength and the loads during
lifting have not exceeded the maximum design values. For re-use of bolts, a detailed inspection
plan with regular NDT including rejection criteria and exchange intervals should be submitted
for review by GL Noble Denton. As a minimum, bolts should be visually inspected after each lift
and with MPI (Magnetic Particle Inspection) after every 3 lifts unless fatigue calculations
accepted by GL Noble Denton show that less frequent inspections are acceptable.
d. Re-useable lifting lugs shall be tested in accordance with Section 8.6 of 0027/ND, Ref. [7].

7.2 FLOAT-OVER
7.2.1 Float-over load-outs are covered in 0031/ND, Ref. [10]. However pre-ballasting floating structures
must be avoided unless adequate local structural checks show that loads produced by the ballast do
not exceed the capacity of the structure.

7.3 CABLE LOAD-OUT


7.3.1 Before start of load-out the cable ends must be sealed against water ingress in accordance with the
cable manufacturers procedures.
7.3.2 Before shipping, drummed cable ends must be sealed and the cable protected from external damage
by use of wooden planks, or similar, securely fitted between the drum flanges.
7.3.3 Electrical and optical tests are normally done after cables are loaded into carousels or cable tanks only
when the responsibility for the cable transfers from one party to another, for example when the cable
manufacturer and the cable installation contractor are different companies.
7.3.4 Otherwise post load-out tests are a discretionary requirement and the client will choose whether or not
to specify full or partial post load-out electrical and optical tests.
7.3.5 However if there is an incident during cable loading then tests should be done to establish whether or
not the cable suffered damage. The scope of the tests can be agreed at the time of an incident and
will depend on the type of incident.
7.3.6 Depending on the post load-out test scope it might be necessary for both ends of the loaded cable to
be accessible for testing. The test protocol should be taken into account in the transport or lay vessel
tanking plans and loading procedures.
7.3.7 Post load-out test results should be compared with the FAT results and abnormallities investigated.
7.3.8 In high fibre count cables it is acceptable to test an agreed percentage of the fibre optics unless there
is an incident during load-out that might have damaged the cable.
7.3.9 When post load-out testing is finished, end seals and pull-in arrangements must be properly fitted to
the cable ends by competent technicians in accordance with the manufacturers procedures.
7.3.10 Pre-installed cable pull-in heads with integrated end seals can be fitted at the manufacturers premises
on drum-loaded cables and approriate certificates must be supplied. Drum-loaded cables are normaly
only tested at FAT stage, after loading onto drums, and tested again after the cable has been installed
offshore.

0035/ND Rev 0 Page 25 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

7.3.11 Pull-in heads or cable grips must be of adequate strength (i.e. stronger than the cables) for the transfer
operation.
7.3.12 Typically pull-in head designs will be type-tested, removing the need to load test and certify every pull-
in head.
7.3.13 Loaded drums should be inspected for signs of physical damage on arrival at the delivery location. If a
drum is damaged then the cable in the damaged area should be inspected and, if deemed necessary,
the cable should be tested.
7.3.14 Cable types. Submarine power cables can be torsion balanced or non-torsion balanced. Torsion
balanced cables can only be stored in carousels or on drums. Non-torsion balanced cable can be
stored in cable tanks.
7.3.15 Submarine power cable armour layup can be S lay, Z lay or SZ lay which is a combination of the
two. Cables might need to be coiled in a specific direction depending on the type and direction of
armour layup. Loading procedures shall specify the coiling direction.
7.3.16 Submarine power cables can be constructed as wet, dry or semi-dry cables. Wet cables allow water to
enter the body of the cable as far as the conductor outer sheath which is sealed against water ingress.
Dry cables have a water-blocking sheath normally under the armour wire bedding layer. The water-
blocking sheath prevents water from entering the body of the cable. Each conductor in a dry cable will
have a swellable tape sheath encasing the conductor which swells in contact with water and keeps the
conductor XLPE (Cross Linked Polyethylene) insulation dry. Some dry cables have a lead water-
blocking sheath under the armour bedding. Typically HVAC cables are constructed as dry cables.
Some manufactureres build semi-dry HVAC cables.
7.3.17 The cable pathway from the cable factory storage location to the quayside cable loading tower must
be inspected for non-conforming bends (less than the cable MBR), loose /stiff rollers, sections where
the cable can jump off the cable pathway and sections that are out of sight. Preferably the complete
cable pathway will be monitored by CCTV during cable loading.
7.3.18 Non-conforming bends, excessive side wall pressure and shear forces are a cause for concern and
can damage the cable metallic laminate and metallic sheaths and allow moisture ingress which can
reduce cable insulation life.
7.3.19 Loading procedures must define a clear and concise chain of command and communications protocol
and must include a command and communication interface between the onshore load-out team and
CLV / CLB team.
7.3.20 Load-out must be preceded by a pre-load meeting at which the task, chain of command, control station
command priorities, radio and communication protocols, emergency procedures and source of back up
communications faciities must be communicated to all personnel involved in supervising the load and
personel operating loading machinery and winches.
7.3.21 Responsibility for managing the load-out catenary between onshore and the CLV or transport vessel
must be clearly defined.
7.3.22 If necessary a watch shall be maintained to ensure that the wash from passing vessels cannot
endanger the cable loading operation.
7.3.23 All loading equipment controls, sensors and monitoring devices shall have in date calibration
certificates.
7.3.24 Swivels must be used at the cable ends and between segments to enable residual torsion to leave the
cable.
7.3.25 Cable loaded into a cable tank or a carousel must be tightly packed together to minimise gaps.
Wooden paddles should be used to lever the incoming cable into place. Gaps should be packed out
with wood or plastic to prevent movement at sea and to prevent overlying cable being forced into gaps
between cables in underlying layers.
7.3.26 Vertical carousels. Submarine power cables loaded onto vertical carousels must be wound onto the
carousel under tension to prevent the cable falling down the carousel. The calculations to justify the
back tension required to prevent the cable falling down the already loaded cable should be submitted
for GL Noble Denton review.

0035/ND Rev 0 Page 26 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

7.3.27 Damage. All parts of the load-out operation must be observed. Any damage to the cable outer
serving must be made good. Any signs of bird-caging armour wires, kinks and buckling in the cable
and a tendency for the cable to try to form loops in the catenary between the load-out gantry and the
CLV load-out chute are causes for concern and should be investigated.

0035/ND Rev 0 Page 27 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

8 MARINE TRANSPORTATION
8.1 TRANSPORTATION OF COMPONENTS ON VESSELS OR BARGES
8.1.1 The requirements of 0030/ND Guidelines for Marine Transportations, Ref. [9], apply for all tows and
transportations. For short voyages the relaxations in Sections 6.3 and 6.4 of 0030/ND may apply.
8.1.2 Seafastening of blades and other fragile components will normally need special care to avoid damage
from welding or locating guides. Where friction is required to resist some or all of the seafastening
forces then the coefficients of friction shall be shown to be adequate in both the wet and dry states.
8.1.3 If towing vessels are currently registered in the GL Noble Denton Towing Vessel Approval Scheme
(TVAS) see 0021/ND, Ref. [6], then suitability surveys will not be required, though a check will be
required before a Certificate of Approval is issued.
8.1.4 The requirements of Appendix B of 0001/ND, Ref. [1], will apply for bolted connections used for
seafastening.
8.1.5 Minimum clearance between cargo items to be lifted is given in Section 9.2 and 9.3 of 0027/ND,
Ref. [7].

8.2 TRANSPORTATION OF COMPLETE ROTOR


8.2.1 Rotors with diameters of well over 100 meters may be transported horizontally (rotor axis vertical) on
vessels or barges of only about 30 to 40 m beam. However the blades will generally be very
vulnerable to wave slam, especially when the vessel rolls and/or pitches into a wave.
8.2.2 A successful transportation will rely on:
a. The rotor being designed to safely withstand the accelerations (from 0030/ND, Ref. [9]) during
transport.
b. Reducing to negligible the probablility of wave slam on the blades by securing them well above
the still water level.
c. Selecting vessels that can be ballasted to reduce the motions in likely wind and wave
combinations.
d. Doing motion response calculations to optimise the loading and ballasting arrangments so as to
minimise the probablity of wave slam on the blades in likely wind and wave combinations.
e. Weather routing the transport to avoid any weather that could cause wave slam on the blades.
(This may not always be practicable for some seasons and longer routes between suitable
shelter ports).
f. Developing procedures to avoid blade collision damage when coming alongside loading quays,
entering ports of shelter (as part of the weather routing) and coming alongside the offshore
lifting vessel. These procedures must include advance liaison with any suitable shelter ports (to
agree the conditions under which the transport may enter, e.g. problems when meeting other
vessels in the approach channel, clearances at harbour entrance and mooring at a quay).
Escort vessels may also be required to reduce the probability of collision with other shipping,
especially at night.
g. The rotor will normally be upended (so that the rotor axis is horizontal for installation) before
coming alongside the installation vessel.

8.2.3 In some respects a transportation with the rotor in a vertical plane (as installed) may be easier,
especially if fully assembled on a tower. However the required accelerations may be higher though
wave slam and collision problems should be reduced

8.3 TRANSPORTATION OF TALL VERTICAL CARGOES


8.3.1 Seafastening of the TP flanges on barges or ships is often critical for many projects. The design of the
bolted connection should be gap free to avoid self-loosening of the bolts. All gaps due to
imperfections should be filled in with shim plates but not more than 2 shim plates should be used at a
time. Pretension bolts in seafastenings shall be used only once due to fatigue during transportations.

0035/ND Rev 0 Page 28 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

8.3.2 Seafastenings must be designed to allow safe removal offshore without endangering the cargo or
personnel. See also Section 9.2.1 b.
8.3.3 Clearance (air draught) under any bridges or power cables must be considered. The safe distance
from live power lines shall be allowed for. The power line catenary will change if power is shut off.

8.4 CONCRETE GRAVITY STRUCTURES & OTHER WET TOWAGES


8.4.1 Larger Concrete Gravity Structures will generally be built in a dry-dock, with construction often
completed afloat. The requirements for float-out, towage and installation will generally be covered by
0015/ND Guidelines for Concrete Gravity Structure Construction & Installation, Ref. [4].
8.4.2 Smaller gravity structures may be built on barges and floated off or lifted off by crane or sheerlegs.
They may also be lowered to the seabed by purpose-built installation units. Where these are not
covered by existing GL Noble Denton guidelines, suitable criteria can be developed by GL Noble
Denton at an early design stage.
8.4.3 Other wet towages (floating on their own buoyancy) may be launched from a slipway using standard
ship launch procedures which will depend mainly on the location and slope of the launchways.
8.4.4 It will often be impracticable to provide 1 compartment damage stability for floating piles, transition
pieces and suction anchors with temporary bulkheads. In this case a formal documented risk
assessment, with participation from GL Noble Denton, will be required to determine the major causes
of flooding and to reduce the probability to ALARP (As Low As Reasonably Practicable) as described
in Section 10.7.3 of 0030/ND, Ref. [9]
8.4.5 Procedures shall be established for reconnecting a towline to a towed object in the event of a failure of
any part of the towline, pennants or connections.

8.5 CABLES
8.5.1 A fundamental requirement during transport of submarine power cables is protection of the
mechanical, electrical and optical properties of the cable achieved by careful and proper loading into
cable tanks or rotating carousels.
8.5.2 Crush loads imparted by overlying cable must within limits set by the cable manufacturer.
8.5.3 Calculations confirming crush loads are within set limits shall be developed and shall include the
effects of vessel motions which should not be less than the design storm conditions in Section 6 of
0030/ND, Ref. [9].
8.5.4 Cable tank design calculations shall be checked to ensure the cable tank structure can withstand
racking loads imparted by the cable stack into the cable tank structure. The conditions used for the
calculations should not be less than the design storm conditions in Section 6 of 0030/ND, Ref. [9].
8.5.5 Carousel and cable tank seafastening and grillage calculations shall be checked for approval by
GL Noble Denton. The conditions used for the calculations should not be less than the design storm
conditions in Section 6 of 0030/ND, Ref [9].
8.5.6 The requirements for loading and stowing cable on transport vessels are the same as for a CLV /CLB
as described in Section 7.3.
8.5.7 Trans-spooling operations between the transport vessel, CLVs or CLBs shall always be carried out in
sheltered waters where both vessels can be safely moored with the minimum relative movement
between the vessels.
8.5.8 The requirements for trans-spooling cables between transport vessels and CLVs are the same as for
loading cables onto a CLV at the cable manufacturers facility. Special care and attention should be
given to managing the cable catenary between the two vessels especially if there is relative movement
between the two vessels. Mooring lines should be checked on a regular basis and the checking period
should be in accordance with the prevailing environmental conditions and passing marine traffic.
Mooring line checks and adjustment shall be recorded in the cable loading log (in addition to the vessel
bridge log).

0035/ND Rev 0 Page 29 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

9 INSTALLATION
9.1 GENERAL
9.1.1 Installation of components on wind farms are generally covered as follows:
a. Concrete or steel gravity platforms, foundations or complete integrated platforms by 0015/ND,
Ref. [4], and 0028/ND, Ref. [8].
b. Monopiles and jackets by 0028/ND, Ref. [8], including piling and un-piled (storm safe) stability.
c. Lifted turbines, transition pieces, decks and modules (including substations, control stations,
transformers, HVDC converter platforms, etc) by 0027/ND, Ref. [7]
d. Decks floated over jackets or gravity bases by 0031/ND, Ref. [10]
e. Jack-up platforms (construction and containing Wind Farm permanent equipment) by 0009/ND,
Ref. [2], 016/ND, Ref. [4] and BWEA Guidelines for Jack-Ups, Ref.[12].
f. Cables in Section 10 of this document.
However special cases for offshore wind farms are covered in the following sections. Where special
considerations apply, the requirements need to be agreed In advance with GL Noble Denton.

9.2 MONOPILES AND TRANSITION PIECES


9.2.1 Special considerations may apply for
a. Position and orientation tolerances (See Section 5.2).
b. Release of seafastenings which will normally require a specific procedure, especially for tall
objects transported vertically.
c. Sea bed soil condition and scour protection requirements.
d. Levelling arrangements for the transition pieces.
e. Grippers, handling & upending equipment.
f. On-bottom stability of the unpiled Monopile in the pile gripper.
g. Stability of the TP on the MP prior to grouting (see Section 7.2.2 of 0001/ND, Ref. [1], for the
environmental criteria).
h. If drilling is required for installing piles then:
1. Disposal of cuttings (see Section 5.2.3)
2. Contingency plans & equipment (e.g. fishing tools) for a broken drill string.

9.3 PILING TEMPLATES


9.3.1 Piling templates are often used to help locate piles before driving and to ensure that piles are driven
vertically or at the right inclination.
9.3.2 They are normally placed on the seabed but may be attached to the side of a jack-up, with the facility
to be lowered or raised and may use the jack-up legs as a positioning guide.
9.3.3 If transported attached to a jack-up then the template and its attachment must be able to withstand the
design accelerations from Sections 7 and 8 of 0030/ND Ref. [9]. Its effect on trim and stability must
also be checked.
9.3.4 Special transit procedures may need to be developed to reduce the risk of collisions or grounding if the
attached template increases the combined draught or beam, especially if not visible above water.
9.3.5 The template will need to be capable of being levelled if there is a sloping or uneven seabed. Mud
mats may also be needed for a soft seabed.
9.3.6 When templates are liable to settle in clay or silt, provision should be made for jetting or other means
to overcome adhesion during subsequent extraction.

0035/ND Rev 0 Page 30 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

9.4 SUCTION BUCKET FOUNDATIONS


9.4.1 The requirement for any seabed preparation before installation shall be determined at any early stage.
9.4.2 Equipment and procedures shall be provided to ensure that:
a. the foundations can be safely lowered to the seabed and located within tolerances
b. there is no piping through the soil between outside and inside, or between individual
compartments, if any, during installation
c. that any out of verticality can be corrected to within the required tolerances (possibly using
crane assistance)
d. there is sufficient redundancy to allow installation to continue after flooding of any compartment
or breakdown of any item of equipment. If there is insufficent compartmentation to allow this
then a risk assessment must show that therre are sufficient safegaurds in place that the risk of
such flooding is acceptable to GL Noble Denton

9.5 J-TUBES AND I-TUBES


9.5.1 J-tubes and I-tubes provide an installation guide and long term protection to submarine cables installed
onto offshore structures. Typically the hang-off mounting flange will be welded to the top of the J-tube
/I-tube.
9.5.2 J-tubes guide the cable from or near seabed level usually via a bellmouth into a bend conforming with
the cable MBR and vertically to an upper level of either the foundation, substation or other structure.
9.5.3 Internal J-tubes are normally sealed where they pass through the foundation wall to prevent water
exchange between the sea and the inside of the monopile.
9.5.4 I-tubes are vertical tubes with an opening facing down toward the seabed. I-tube pull-ins can be
problematical if the correct installation tension is not maintained throughout the pull-in operation and
over tension during pull-in operations can damage cable if the cable is pulled over the lip of the open
I-tube.
9.5.5 J-tube and I-tube internal diameters should be sufficiently large to minimise friction induced tension in
the cable during pull-in operations and shall be smooth with no snagging points that can snag pull-in
rigging.
9.5.6 Installing cables through J-tubes and I-tubes is covered in Section 10.11

9.6 TURBINE INSTALLATION


9.6.1 Fully erected turbines have already been installed from floating craft and there will soon be jack-ups
designed to do this.
9.6.2 Existing guidelines should apply unless novel installation techniques are proposed.

9.7 TOWERS
9.7.1 Installation of towers is generally carried out by a crane vessel using conventional lifting methods,
often with a custom-designed lift-beam arrangement.
9.7.2 Towers can be installed in sections. If installation of the tower is planned in sections then these
sections are connected together, often using bolts, before de-rigging the upper tower section.
9.7.3 Installation requirements for towers are covered in 0027/ND, Ref. [7]. However the following special
cases may apply:
Access for de-rigging
Partial bolting
Lifting points certification for multiple use (loadout, installation, maintenance, decommissioning)
Verification that there will be no ovalisation due to local seafastening forces in higher seastates
Transport frames
Requirements and criteria for upending from the horizontal to vertical mode.

0035/ND Rev 0 Page 31 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

9.8 NACELLES
9.8.1 Installation of nacelles is carried by conventional lifting techniques often with spreader beams
connected to grommets and trunnions. Installation requirements is covered in 0027/ND, Ref. [7].
However the following special considerations may apply:
Lift points
Access for de-rigging
Partial bolting

9.9 BLADES
9.9.1 Installations of blades have generally been carried out with the hub in the horizontal position.
Historically, the bunny-ears method has been commonplace, in which there is a single blade installed
offshore with the blade inserted into the hub in the vertical direction
9.9.2 Blade handling tools are used in order to ensure a correct orientation for the integration of the blade to
the hub and to permit safe rigging up and de-rigging. Blades are then bolted to the hub.
9.9.3 Installation requirements for blades is covered in 0027/ND, Ref. [7]. However the following special
considerations may apply:
Infra-red release systems which must be shown to be reliable in releasing and, more
importantly, not liable to early release from any cause.
Limiting criteria. See Section 5.2
Boom tip motions, See Section 11.4.2 of 0028/ND, Ref. [8]
Partial bolting

9.9.4 If the design of the blades is so confidential that the client, manufacturer or designer is unwilling to
submit transport or handling calculations to GL Noble Denton then the approach in Section 9.6.3 of
0001/ND, Ref. [1], may be taken.

9.10 COMPLETE ROTOR INSTALLATION


9.10.1 Installations of completely assembled rotors (blades and hub) are carried out with the rotor axis
horizontal. If the rotor is transported horizontally (rotor axis vertical as described in Section 8.2), the
rotor is normally upended on board the vessel using a bespoke lifting device before coming alongside
the installation vessel.
9.10.2 Installation requirements for complete rotors is covered in 0027/ND, Ref. [7]. However the following
special considerations may apply:
Upending and lifting devices
Partial bolting
Horizontal and vertical movement during positioning
High windage area effect on dynamical loads

9.11 LIFTING OPERATIONS AND LIFTING TOOLS


9.11.1 Lifting operations and Lifting Tools are covered in 0027/ND, Ref. [7]. However the following special
considerations may apply to wind farms:
a. Blade lifting tools (usually proprietary designs)
b. Wire slings and grommets
c. Fibre Slings (Dyneema, Aramid or HDPE)
d. Certification
e. Inspection / recertification
f. Discard criteria

0035/ND Rev 0 Page 32 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

9.12 INNOVATIVE INSTALLATION METHODS


9.12.1 Requirements for new methods of installation of any equipment should be agreed with the relevant
GL Noble Denton office in advance, preferably at an early design stage when is more economical to
comply with any recommendations.

0035/ND Rev 0 Page 33 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

10 CABLE INSTALLATION
10.1 BACKGROUND
10.1.1 A successful offshore wind farm cable laying operation will normally be preceded by:
a. Desk Top Study
b. Environmental Impact Assessment
c. Liaison with third party stakeholders such as fishing industry representatives and other marine
users
d. Seabed route surveys
e. Burial Protection Index study
f. Route development and cable engineering
g. Cable protection selection
h. Out of service cables identified
i. In service cables identified and cable crossing agreements established with cable owners in
which the crossing construction method is agreed
j. Assessment of the physical risks to the cable
k. Selection of suitable installation resources
l. Installation Analysis including J-tube /I-tube pull-in, laying around curves and when cable will
be surfaced laid but not immediately buried
m. Interface management plan
n. Other items covered in Section 10.6.1, as applicable.

10.2 MAJOR CHALLENGES /CONSIDERATIONS FOR ALL CABLES


10.2.1 Minimum Bend Radius (MBR). The minimum bend radius shall be protected at all times. Suitable
measures should be taken to protect the MBR, particularly during high-risk operations such as pull-in,
overboarding and laydown operations. Protection can be ensured with the use of quadrants, bend
restrictors or rollers, etc. See Section 10.17.
10.2.2 Turn-overs. The cable supply contract must state the maximum number of times a cable can be
turned over and the contract maximum turn-overs must exceed the planned operational turn-overs.
10.2.3 Lead sheathing. Some submarine power cable designs use lead sheathing as a water-block. Lead
sheathing can be prone to micro cracking cause by excessive bend reversals. Micro cracking reduces
the lead sheathing water-blocking properties. The installation procedures must take account of this
and aim to reduce bend reversals during installation of lead-sheathed submarine power cables which
must always be less than the design limit.
10.2.4 Compression Forces. Submarine power cables have maximum allowed compression forces that
must not be exceeded during handling and installation operations. The maximum allowed
compression force must be provided by the cable manufacturer and must be presented as load per
unit length of cable. Cable handling machinery such as LCEs (Linear Cable Engines - tracked and
wheeled types) exert compression forces on cables (see Section 10.10.3).
10.2.5 CSA (Cross Section Areas) have increased to accommodate offshore wind farm generating capacities.
Handling of ever larger cables requires new techniques and skills to lay the cable properly and safely.
When cable sizes push installation technologies it becomes increasingly important that the installation
methodologies are considered at the cable selection /design stage.
10.2.6 Direction of lay is an important consideration and will be driven by a number of factors such as cable
congestion around an offshore substation, location of installation joints and prevailing marine
environment conditions.
10.2.7 Varying ground conditions may require different cable burial technologies to achieve acceptable
levels of protection against identified threats throughout the length of the cable route. This may be a

0035/ND Rev 0 Page 34 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

bigger problem for export cable routes due to their longer length resulting in a greater variation of
ground conditions along their routes.
10.2.8 Jack up vessel operations. Jack up legs can be a major threat to cables if they are placed on or
near a cable. Jack up legs placed on a cable will damage the cable as will ground-heave from a jack
up leg placed too close to a cable (cable protection should not be relied on as protection from jack up
legs). Leg penetration and ground-heave studies should be done to ensure there is sufficient space
between jack up legs and cable positions.
10.2.9 External aggression leading to higher risk of damage. The increased risk of damage by anchors and
fishing gear will influence the BPI and subsequent installation costs. In particular export cable routes
will increasingly cross shipping lanes, anchorages and areas where bottom trawling is done,
presenting increased challenges when designing export cable routes and installing cables.
10.2.10 Burial. Achieving required burial in difficult ground conditions.
10.2.11 Lay barge mooring capability in marginal laying conditions, cross currents, variable anchor holding
ground conditions and shallow water.
10.2.12 Laying around curves. Cables must be laid around obstacles and approaches to offshore structures
require laying around curves to line up with J-tube orientations. This may be a bigger problem for
export cable routes due to major seabed obstacles at landfall areas.
10.2.13 Bend restrictor and protection at J-tube approaches. J-tube bell mouths can be raised above the
seabed. The cable MBR must be protected in the free span between the J-tube bell mouth and the
cable touch down point. The free span must be protected from ocean current induced vibration which,
over time, can damage cable armour wires and can also reduce the electrical life of a cable. Cables
must be protected against dropped objects at the approach to offshore structures. Scour pits might
need to be crossed. All of these require bend restrictors and cable protection to be attached to the
cable, usually on board the installation vessel before the cable is installed into the J-tube.
10.2.14 J-tube /I-tube pull-in. Protection of cable MBR; potentially high tension due to friction of pulling cable
across the seabed into a J-tube; subsea handling and timely release of pull-in quadrant; cable
protection /bell-mouth interface; scour pits; control of pull-in tension and MBR monitoring, observation
and surveying of pull-in (visibility & tides) and correct engagement into the J-tube /I-tube of cable
protection systems.
10.2.15 J-tube pull-in limiting sea state. A number of factors need to be considered to establish Array and
Export Cable pull-in operational limiting sea states and other limiting conditions. These include:
a. offshore structure access /egress for cable pull-in personnel
b. vessel motions and impact on crane operations for transferring pull-in aids and other equipment
to offshore structures
c. Cable tension caused by CLV / CLB accelerations.

10.2.16 Laying away from the J-tube / I-tube. Tension due to ploughing/trenching pull-off forces; cable
protection/bell-mouth interface; scour pits. Control and observation of pull-in tension and MBR
monitoring, observation and surveying of pull-in.
10.2.17 Installation of cable protection. Selection, installation monitoring and correct engagement into the J-
tube/I-tube of suitable cable protection systems at the J-tube /I-tube seabed interface.
10.2.18 Congested cable routes. Wherever possible submarine power cables should be installed with
sufficient space between cables to allow future repair operations to be carried out.
10.2.19 Crossings. Cable or pipeline crossings normally require a constructed crossing (mattresses, rock
dumping, polyurethane products or small concrete bridges). The design and installation must be
approved by the owners of the product being crossed. Wherever possible crossing points should keep
the heading of the two products as close to 90 degrees as possible. Typically plough burial will not be
allowed within 500m of the crossed product; therefore other means of protecting cables in this
no-plough zone must be provided.
10.2.20 Installing cables in bundles. Cables are sometimes installed in bundles (HVDC circuits for
example). Bundled cables are more difficult to handle than single cables and careful consideration

0035/ND Rev 0 Page 35 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

must be given to the burial technology to ensure the cables are not damage by the burial /trenching
tool.
10.2.21 DP or mooring system failures may lead to excessive tension or slack in the cable during cable
laying operations. For moored barges the Mooring Analysis shall include line failure modes and an
excursion analysis considering failure of each mooring line. The outcome of the Mooring Analysis will
contribute to setting the limiting sea states and/or the number of attending tugs required.

10.3 SPECIFIC CHALLENGES /CONSIDERATIONS FOR EXPORT CABLES


10.3.1 Installation durations often exceed reliable weather forecast durations. Therefore it is difficult to set
time limited weather windows.
10.3.2 Cable route lengths often result in installation joints in export cables. Installation joints take up to
seven days to install, exceeding reliable weather forecast durations.
10.3.3 Route development and cable engineering at the landfall site are critical to ensure cables are
secure for the life time of the project. Landfalls often have complex seabed physical environments
where the influence of waves breaking in the surf zone can cause a poorly installed cable to fail within
months of installation. Cable repairs in the surf zone cost substantially more than a repair undertaken
at sea. Repairs done in the surf zone are more likely to fail again as protecting a cable repair in the
surf zone can be very difficult.
10.3.4 Grounding of export cable laying barges for landfall installation. At some landfall sites the water
depths prevent CLBs from getting close enough to the landfall to remain afloat during a landfall pull-in
operation.
10.3.5 Landfall sites with sea defence systems. Normally consent conditions prevent sea defences from
being breached by open cut trenches and must be crossed by HDD ducts. Ducts result in increased
cable pull-in tensions and must be designed to accommodate the export cable maximum tensions and
the cable design must accommodate the expected pull-in tensions.
10.3.6 Landfall sites with extensive shallow water will require a bespoke solution adapted to the
challenges of each landfall. A range of methods have been adopted including very shallow draft
vessels and tracked vehicles with cable drums mounted on the vehicle. The combination of HDD and
ducts and extensive shallow water adds a high level of construction risk.
10.3.7 Laying cables close to or over existing cables and pipelines. Export cable routes can cross the
routes of existing telecommunication cables, power cables and pipelines. Crossings typically require a
constructed crossing point to maintain vertical separation between cables or between cables and
pipelines. See Section 10.23.
10.3.8 Constructed crossing points must be designed to ensure the construction materials and methods do
not cause scour to undermine the protection materials and potentially cause the crossing materials to
put weight onto the crossing export cables and/or the crossed submarine plant.

10.4 SPECIFIC CHALLENGES /CONSIDERATIONS FOR ARRAY CABLES


10.4.1 Cable installation time. Array cables are typically installed end to end in around 36 hours. However
the installation program should be based on the actual expected installation time for each cable.
10.4.2 Weather windows. Array Cable installations typically have different limiting sea states for crew
access and egress to foundations and offshore substations, J-tube pull-in operations and Array Cable
installation.
10.4.3 Proximity to other structures increases the risk of collision and damage to and from the CLB
mooring lines and anchors. This applies particularly during pull-in operations.

10.5 CABLE ROUTE SURVEY AND POSITIONING


10.5.1 Survey grid. A survey should be performed covering the grid of proposed cable routes. The seabed
survey shall be specified to determine seabed bathymetry, topographical features, surface soil
conditions (soil type, presence of boulders etc), surface objects and UXO. Ordinarily this will be
performed in the years preceding the construction phase. This survey should be repeated in the
months prior to cable-laying to ensure no change in the suitability of routes. All surveys shall be

0035/ND Rev 0 Page 36 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

performed to the same geographical datum and should be tied into existing known points and levels. A
BAS (Burial Assessment Survey) is recommended for export cable routes where the ground conditions
will typically vary along the export cable route.
10.5.2 Jack-up footprints Areas with existing jack-up footprints should be identified and new footprints
should be accurately plotted when jack-ups are deployed.
10.5.3 Plough routes should be based on surveys and should avoid wrecks, substantial obstacles, UXO
(with a defined exclusion zone), environmental sensitive areas (e.g. Sabellaria worm habitats), and
difficult soil conditions. Small objects may be removed, but should be avoided if practicable.
10.5.4 Route clearance & UXO. Cable routes should be surveyed for potential UXO prior to choosing cable
routes. Suspected UXO should be investigated or avoided. A grapnel run should be performed prior
to cable laying, to ensure a clear cable route.
10.5.5 Exclusion zones should be adhered to when laying cable to consider future repair operations, and the
possibility of using anchored vessels or grapnel assisted cable recovery. Current guidance suggests
250m exclusion from other cables, UXO, wrecks etc. Site specific assessments should be made to
determine exclusion distances.
10.5.6 Wherever cables are to be installed close to an existing telecom cable consideration should be given to
the additional required clearances for the telecom cable. Telecom cable repair procedures often
require more space around the telecom cable in order that the repair vessel can deploy grapnels to
locate, snag and recover the telecom cable. ICPC Guidelines, Refs. [14] to [16] should be referred to.
10.5.7 Cable route selection should also take account of the telecom cable owners right to repair and
maintain their cables as granted by UNCLOS (United Nations Law of the Sea).
10.5.8 A detailed bathymetry of the site resulting from a recent underwater survey should be available when
assessing minimum clearances within the seabed contour, and survey inaccuracies should be
accounted for.
10.5.9 Normally, two independent on-board positioning monitoring systems (PMSs) shall be utilized for
operational monitoring and control purposes. Both systems shall be in operation at any time, each
serving as the back-up for the other. Each should be fed by an independent power source.
10.5.10 Where underwater accuracy is important, at least one PMS shall be an underwater, hydro-acoustic
reference system.
10.5.11 As-laid surveys. As-laid information must be compiled to enter the as-built documentation. Post-lay
surveys may be required to determine burial levels and accurate locations for post-lay burial measures.
If this is not required, due to recorded successful burial levels, monitoring of vessel location may be
sufficiently accurate for as-built records. Required accuracy of location will be project specific.

10.6 PROCEDURES
10.6.1 An Installation Manual with Procedures, Story Boards, Task Plans and other supporting documents
should be produced to cover the following as appropriate to the specific cable installation operations,
incorporating solutions to the various problems identified in Sections 10.2 to 10.4:
a. General
1. Measures taken to ensure the protection of cables MBR. See Section 10.17
2. UXO Survey. See Section 10.5.4
3. ITP (Inspection Test Plan)

b. Cable Route Development and Cable Engineering


1. Cable Route Survey. See Section 10.5
2. Route Development and Cable Engineering. See Section 10.3.3 for landfall site
3. RPL (Route Planning List). See Section 10.10.8
4. BPI (Burial Protection Index) Study to establish burial depths that will provide protection
against the identified risks in the given soil conditions. See Section 10.8.

c. Route Clearance to remove old cables and large debris from the cable routes

0035/ND Rev 0 Page 37 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

d. Pre Lay Grapnel Run (PLGR) to remove linear debris immediately before the cable installation
operation from the cable routes

e. Cable Transport
1. Cable Loading. See Section 7.3
2. Cable Transport. See Section 8.5
3. Cable Trans-spooling. See Section 8.5.7 onwards

f. Cable Laying
1. Cable End Sealing. See Section 7.3.1 onwards
2. Offshore Structure Topside Pull-in Preparation
3. CLV and/or CLB Suitability Analysis
4. CLV and/or CLB Vessel Motions Analysis
5. Cable Installation Analysis
6. Slack and Catenary Management. See Section 10.16
7. J / I-Tube Pull-in. See Section 10.11.
8. Cable Protection at J / I-TubeCable trenching and/or burial. See Section 10.8.
9. Cable and/or Pipeline Crossing Protection. See Section 10.23
10. Cable Emergency Abandonment and Recovery. See Section 10.19.
11. Cable Jointing or Repair. See Section 10.24.
12. PLIB (Post Lay Inspection Burial), often with a WROV to rectify any areas with
inadequate burial.

g. Landfall Preparation and Shore End Cable Installation (see Section 10.22)
1. HDD and Duct Installation
2. Landfall Site Preparation
3. Open Cut Trenching
4. Direct Shore End Installation
5. Pre-installed Shore End Installation
6. Cable Protection Landfall to Main CLV

h. Marine Logistics
1. Anchor Handling
2. DP Trials. See Section 13.5 of 0001/ND, Ref. [1].
3. DP Manoeuvring and Close Proximity work
4. Crew Transfer and Access / Egress
5. Pull-in Aids Transfer

i. Risk & Continency Planning. See Section 5.4 of 0001/ND, Ref. [1].
1. HIRA, HAZID and HAZOPS
2. Operational Activity and Contingency Planning
3. SIMOPS
4. Risk Management Plan

10.7 PROJECT INSTALLATION MANUALS


10.7.1 Procedures shall include close proximity operations, laying cable around curves and laying cable
along straight sections of cable routes whilst in DP mode (if applicable). Installation Manuals shall

0035/ND Rev 0 Page 38 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

include story boards showing each step required by the installation vessel to complete all cable
installations including:
a. Vessel position for each operation, mooring, anchor handling, stability, WTG /Substation setup,
lay-away, laying, overboarding, burial, deburial, pull-in, cable protection systems).
b. Step-by-step written instructions for the more complex processes during cable installation (i.e.
pull-in /lay away /laydown /recovery /overboarding). These shall be used to explain the
methodology engineered for the operation and for the site teams to follow.
c. Limiting weather criteria, control and monitoring measures used to ensure cable integrity,
surveys,
d. Calculations, contingency plans, hold/stop points, equipment descriptions and electrical testing
programmes as appropriate.
e. Use of divers and ROVs

10.7.2 Live anchors may be used to manoeuvre a CLB in close proximity to offshore structures and to
maintain the CLB position along the planned cable route. Live anchor operations shall be carefully
planned and a Live Anchor Handling Procedure shall be written by the installation contractor and
approved by GL Noble Denton. The Anchor Handling Procedure must include Anchor Position
Drawings showing the planned positions of anchors for all phases of live anchor operations.
10.7.3 TD position when laying in curves must take account of the tendency for tension in cables during lay
operations to pull the TD point closer to the installation vessel track line. Curves laid in surface-laid
submarine power cables must be planned carefully and must be supported by Installation Analysis and
Seabed Stability Analysis.
10.7.4 Operating weather. Computational analysis and modelling can be undertaken to assess the ability of
a vessel to maintain position and heading during high risk cable handling operation and to evaluate the
weather criteria for operability of the moored vessel and suitability of its moorings in a site.
10.7.5 Risk Assessments including HAZOPs etc. These should be attended by all appropriate project staff
including the Contractor, GL Noble Denton, project H&S staff, and others as required to cover all
project interfaces
10.7.6 ROV operations. ROVs are often used to monitor subsea activities, perform subsea work (such as
attaching/detaching wires, lifting anchors etc.). Such work is often limited by visibility and currents.
ROV dependant activities should therefore consider recent weather (rough weather reduces visibility),
tidal schedules and predicted tidal current speeds. If visibility is an issue for ROVs, it is recommended
to also use sonar surveying instruments to identify objects and cables during operations. ROV test
dives should be performed to test conditions prior to activities involving cable handling. A clear and
descriptive commentary/narrative should be submitted alongside any surveying video /screenshots to
ensure the viewer understands and can interpret what is being presented.
10.7.7 Messenger lines. Messenger lines, shackles and other rigging should be fully certified and graded for
predicted loads. The site specific tidal and weather conditions should also be considered when
specifying such rigging. Pre-installation of messenger wires prior to pull-in should consider as-left
conditions and the risk of entanglement /damage.

10.8 CABLE PROTECTION


10.8.1 All cables will require protection to some extent from scour, anchors, trawl equipment, ocean current
induced vibration and dropped or sinking objects. This can be achieved through a number of
techniques. Burial of cables can be carried by a number of machines or by divers. For post laying
protection, accurate geophysical survey data is required to identify the cable location accurately which
is intended for protection. In some cases it may be necessary to apply a tone to cables so they can be
located in case of partial backfill or natural burial.
10.8.2 Cable Protection Systems. Cable protection systems are generally employed at the interface
between the seabed and foundation, or where cable burial is not possible. Cable protection systems
should be designed to protect the MBR, protect against abrasion, and minimise dynamic movement
which could cause fatigue damage. Due account should also be taken of scour predictions. Key
considerations for protection systems are installation methodology, friction with seabed during pull-in,

0035/ND Rev 0 Page 39 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

the interface with the bell-mouth, and protection of the cable during pull-in /lay-away as well as over
the course of the cable life-time.
10.8.3 Cable Burial. Cable burial targets are informed by site specific risk assessments of potential damage
to the cable (inputs such as types of fishing activity). Achieved burial levels should be recorded for as-
built documentation and assessment of conformity. Post-lay measures may be required to achieve
target burial depth (such as rock-dumping, mattress laying or jetting). Proof of achieved depth of burial
can be important to any project for presentation to the necessary stakeholders. This can be provided
by video and sonar surveying equipment attached to the devices carrying out the work or immediately
after burial to identify the depth of burial prior to backfill.
10.8.4 Burial depth The intended depth of burial will be specified for the site and based on a number of site
specific parameters such as regulatory requirements, other marine users & their activities,
geotechnical & seabed conditions onsite and tidal conditions of the site. It is most likely that the
seabed and geotechnical conditions for the site will determine which burial methods are most suitable
and feasible. The correct burial depth will ensure cables are protected from other marine users and
also are not exposed by mobile seabed features such as sand waves.
10.8.5 Burial Typically jetting tools do not bury cables, most jetting tools do not reinstate the seabed over
the cable so that the cable is not buried. Jetting tools fluidise the seabed leaving an open trench into
which the cable will fall. The cable is subsequently buried by natural re-instatement of the seabed.
10.8.6 Ploughing ploughs are towed or self-powered devices that cut a slot into the seabed. The cable
passes through the plough body and exits at the bottom of the slot. The soil is then placed over the
cable to provide immediate full depth burial. Towed ploughs require high bollard pull vessels to
overcome the seabed cutting forces while self-powered ones will normally require power from the
surface via an umbilical.
10.8.7 Trenching is the process whereby a trench is opened and a cable is placed in the trench, back fill is
by natural processes over time.
10.8.8 Post Lay Jetting Protection can be provided by lowering cables below the mean seabed level using
high pressure jetting tools operated by ROVs or divers. It is important the pressures and forces being
applied to any cable are acceptable or within the allowable limits for the cable to withstand. As
previously mentioned, cables may be partially buried and to find and track a cable a tone may need to
be applied.
10.8.9 As-laid Jetting It is becoming increasingly common to lower cables into the seabed using tracked
jetting vehicles operating a few meters behind the cable TD point.
10.8.10 Mechanical Trenching equipment, using rock wheels or chain cutters, can be used to open trenches
in hard ground conditions. Mechanical trenching tools normally open cut a trench and the cable is post
trench laid into the trench when the trenching machine has completed its work. Post lay mechanical
trenching machines provide protection to the cable from the mechanical cutting device.
10.8.11 Rock Dumping If the required burial depth is not achieved during installation, subsequent rock
dumping can provide the necessary protection he characteristics of the material being placed and the
design of the rock berm will be specific to the site and the protection required. Rock is placed by rock
dumping specific vessels which have sophisticated survey equipment to ensure rock is placed directly
on the intended area.
10.8.12 Mattresses and/or rock dumping can be used to provide protection to cables especially in areas
where cables are most exposed, i.e. close to bell-mouth and WTG/substation foundations. Mattresses
are placed by cranes using necessary lift beams to ensure placement directly over the intended area.
10.8.13 Articulated Pipe (also known as split pipe) is a type of cable protection that protects against high
impact forces and chafing where cables pass over exposed bedrock. The pipe is fitting around a cable
in two halves and clamped together with two bolts at each end. The pipe ends form a ball and socket
joint between pipe sections allowing the pipes to form a bend wherever required. Due to the weight of
the pipe sections (spheroidal cast iron) and the necessity to use divers to fit to cables, articulated pipes
are normally only used over rocks or in high currents at shore ends and over shallower water rocks.

0035/ND Rev 0 Page 40 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

10.8.14 Survey Following cable protection operations, confirmation of the operations success is required.
Survey of cable route, burial depth, depth below seabed, sonar images of protection can all provide the
necessary confirmation of what is achieved.

10.9 PLOUGH OPERATIONS


10.9.1 If ploughing is used to bury the cable during laying then ploughing trials are recommended to ensure
that the selected plough types and sizes are suitable and to show that the support vessel can provide
sufficient bollard pull or power supply to penetrate the seabed to the required burial depth across the
site.
10.9.2 Towed ploughs have limited steering which must be considered when developing cable routes with
curves and alter course points.
10.9.3 Ploughs should carry HPR acoustic beacons to monitor plough seabed position and to plot the cable
as-laid cable co-ordinates.
10.9.4 Ploughs can be towed or supported by DP vessels operating either in auto-track or manual mode or
by moored barges using a pull-ahead winch with sufficient pull. Consideration must be given to the
impact of a DP runaway happening during plough operations.
10.9.5 Towed ploughs require high bollard pulls which can require more power from the DP vessel main
propulsion than during normal DP operations. Consideration must be given to the impact this might
have on the ability of the DP vessel to support plough operations with wind, wave and current on the
vessel beam.
10.9.6 Plough burial depths of 3m are often required. In some seabed types bollard pulls or traction forces in
excess of 150 tonnes will be required.

10.10 VESSEL MOVEMENT AND CABLE PAY-OUT


10.10.1 The installation vessels suitability and limiting criteria should be checked at an early stage in the
project lifecycle.
10.10.2 Tension Monitoring During laydown, cable recovery, pull-in and pay-out operations the loads
exerted on cables must be constantly monitored to ensure forces exerted on the cable do not exceed
forces and loads specified by the manufacturer. The tensile limit specified by the manufacturer should
not be exceeded during installation. Load cells shall be used to monitor and record tension levels
throughout installation. This monitoring can be carried by instruments such as tension meters or load
cells.
10.10.3 Compression Forces Exerted by Cable Handling Machinery. The maximum compression force the
cable handling machinery can exert must be set and calibrated at a load point that ensures the
maximum allowable compression force cannot be exceeded. GL Noble Denton must:
a. be provided with a written statement from the cable manufacturer confirming the maximum
allowable compression force,
b. witness calibration of the cable handling machinery compression force setting, measurement
and display functions and
c. witness setting of the maximum compression force.

10.10.4 CLV /CLB movements when laying cable must comply with pre-defined plans recorded in the
Installation Manual and the Installation Procedures.
10.10.5 When planning cable-lay operations for curves and alter courses, consideration must be given to the
vessel track required to lay the required curve and/or alter course.
10.10.6 TD position by WROV monitoring is recommended when surface-laying submarine power cables
around curves and/or altering course.
10.10.7 TD monitoring is also recommended in locations where a cable must be laid within a defined corridor
or when cable length tolerances are tight.
10.10.8 A Route Planning List (RPL) shall be provided. The RPL shall include the cable route co-ordinates,
planned burial or trenching depths and slack cable required along the cable route.

0035/ND Rev 0 Page 41 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

10.10.9 Well planned and managed cable installation operations deploy continuous Slack Management and
Catenary Management techniques to provide real time monitoring and input to vessel position and
speed decisions and to maintain the correct cable pay out speed and tension. These topics are
addressed in greater detail in Section 10.16 (Catenary Management).
10.10.10 A CLV / CLB should never be allowed to drop back onto the cable catenary unless the operation is
planned and the LCE can recover cable from the seabed at least at the same speed as the CLV / CLB
drops back onto the cable. This type of movement, when unplanned and therefore uncontrolled, will
reduce TD tension and will increase the risk of loops being thrown in the cable.
10.10.11 If the CLV / CLB does drop back over the cable and the movement is unplanned then the cable must
be inspected at the seabed to ensure no loops have been thrown before the CLV / CLB moves off to
re-establish the catenary and commence laying cable. If there is doubt over the condition of the cable
then the cable should be tested before laying operations are re-commenced.
10.10.12 If an uncontrolled drop back occurs when plough burying cable the cable must be inspected for loops
before re-commencing plough operations. If a loop enters a plough the loop will be closed by the
plough body to such an extent that the conductors, sheaving and fibre optics will fail and the plough
might be damaged.
10.10.13 Contingency plans must address action required in event of a DP malfunction and must include the
actions required by the cable installation equipment operators.

10.11 PULL-IN AND TRANSFER TO STRUCTURES


10.11.1 Planning. CLV / CLBs typically approach close enough to offshore structures to transfer pull-in aids
using the CLV / CLB crane. The Installation Manual and the Installation Procedure must show careful
planning of close proximity operations and must include contingency plans to be implemented in the
event that the CLV / CLB vessel moves out of control toward or away from a structure.
10.11.2 J-tube/I-tube pull-in winch locations. There are two types of J-tube /I-tube pull-in methods:
1. Pull-in winches mounted on the WTG or the offshore substation
2. Pull-in winches mounted on the CLV / CLB with a sheave arrangement mounted on the WTG or
the offshore substation (pull back method).
In both cases the pull-in winch must have a render setting so that excess tension in the pull-in rigging
caused by CLV movements does not over tension the pull-in rigging. Design calculations must be
provided for GL Noble Denton review for all components in the pull-in rigging system. Wherever pull-in
aids attach to an offshore structure, the suitability of the structure to support the pull-in aids shall be
confirmed by the structure designer.

10.11.3 Second end pull-in operations. There are two methods commonly adopted to implement second
end J-tube /I-tube pull-in operations:
1. A bight of cable is lowered toward the seabed using a quadrant. When the quadrant is close to
the seabed as defined in the Installation Procedures, the quadrant is tipped and the bight of
cable placed on the seabed. This method requires careful co-ordination between control
stations to prevent a loop being thrown in the cable. The J-tube bell mouth lead angles must be
capable of accepting the vertical off-lead angle required without jeopardising the cable MBR.
2. The cable end is laid on the seabed in an omega loop in close proximity to the J-tube and
pulled into the J-tube. This requires a seabed survey covering the whole of the lay down area
to ensure there are no snagging points against which the cable could snag. The pull-in tensions
using this method are influenced by seabed friction and soil build up where the omega loop is
dragged across the seabed during pull-in and must be accounted for in the Installation Analysis.
The J-tube bell mouth off-lead angles must be capable of accepting the anticipated horizontal
lead angle without jeopardizing the cable MBR.

10.11.4 Messenger wires are normally pre-installed into J-tubes /I-tubes before foundations go offshore and a
system that allows rapid messenger replacement offshore should be considered. Messenger wires
and fittings will normally be a marine grade stainless steel.

0035/ND Rev 0 Page 42 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

10.11.5 Messenger wires occasionally fail due to corrosion and/or chafing over edges. The messenger wire
design should take account of these failure modes and ensure the risk of messenger wire failure is
minimised.
10.11.6 It is advisable that J-tubes /I-tubes are marked top and bottom to ensure the right messenger wire is
connected to the pull-in winch wire.

10.12 CABLE LAYING MOORING


10.12.1 Mooring Analysis. Limiting environmental conditions as stated by the vessel owner must be verified
by a mooring analysis to confirm the ability of the mooring system to hold and manoeuvre the CLB at
the stated limiting conditions.
10.12.2 A Mooring Analysis must be done by competent persons and reviewed by GL Noble Denton and used
as an input to the setting of the barge limiting conditions. Criteria for moorings are in 0032/ND, Ref.
[11]. The Mooring Analysis shall include mooring line failure conditions and shall present the expected
barge excursion in case of each mooring line failure mode.
10.12.3 Mooring system and pull-ahead anchors shall be selected to provide the required holding capability at
the limiting operating conditions in the ground conditions expected at any part of a cable route.
10.12.4 Limiting conditions should be established by analysis for single mooring line failure cases for each
mooring line. The number, type and power of the AHT(s) should be used when considering the limiting
conditions GL Noble Denton might require for the CLB mooring operations. Excursion distances and
excursions speed of the CLB for the single mooring line failure modes must be included in the Mooring
Analysis.
10.12.5 Contingency Plans shall mitigate potential impact on the cable in the case of a mooring line failure. GL
Noble Denton shall assess the risks to the cable in event of a mooring line failure and set the operating
limitations.
10.12.6 Close proximity operations. CLBs must set anchors with the CLB as far from other assets as the
mooring system will safely allow.
10.12.7 CLBs must test each anchor on deployment at an agreed mooring line tension for an agreed period of
time before moving in for close proximity operations. GL Noble Denton shall agree the required test
tension and duration and this shall be recorded in the CoA if required and will be a pre-condition to
start close proximity operations.
10.12.8 A mooring control system and equipment FMEA must be done by competent persons and reviewed
and approved by GL Noble Denton.
10.12.9 Mooring system spare parts holding must be reviewed and spares sighted. The spares holdings must
take account of the FMEA findings.
10.12.10 Mooring winches shall be controlled from a mooring control station. The mooring control station shall
be equipped with an open communications system to all relevant control points and shall have
monitors with feeds from the survey suite and the AMS (Anchor Management System).
10.12.11 Mooring winches shall have line out recorders and tension monitors with read outs at the mooring
control station. Mooring winches shall be monitored by CCTV with screens installed at the mooring
control station.
10.12.12 Mooring and anchor handling operations shall be monitored and controlled with an AMS continuously
logging anchor positions. The CLB control station and the AHT navigation bridge shall be equipped
with screens showing anchor positions. The AMS shall be capable of showing when an anchor has
slipped from its deployed position.
10.12.13 The CLB survey display and the AMS shall be integrated to provide real time position displays of the
CLB barge, the anchor locations and installed cables including third party cables.

10.13 PULL-AHEAD ANCHOR & WINCH


10.13.1 Pull-ahead winches and anchors provide the force to move a CLB along the cable route. Pull-ahead
winch and anchor capacity must be sufficient to move the CLB ahead within the limiting environmental
conditions. When supporting plough operations the pull-ahead winch and anchor system must have

0035/ND Rev 0 Page 43 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

the capacity to overcome the plough resistance and the tension required to overcome the limiting
environmental conditions.
10.13.2 Pull-ahead winch, rope and anchor must have valid certification. Winches must be well maintained
with especial attention paid to the condition of the fairlead, winch wire and its end connections and
fittings.
10.13.3 The pull-ahead winch wire must be of adequate length and strength for the planned anchor
placements. There must always be sufficient turns of mooring wire on the winch barrel when the pull-
ahead anchor is run out to its maximum planned extent.

10.14 CAROUSELS AND FIXED CABLE TANKS


10.14.1.1 Submarine power cables are stowed in rotating carousels or fixed cable tanks. Both types will have
centre cones to protect the cable MBR.
10.14.2 Carousels (either vertical or horizontal) rotate to load and discharge cable. The carousel grillages and
sea fastening must be approved by GL Noble Denton.
10.14.3 Fixed cable tanks do not rotate to load and discharge cable. Fixed cable tanks have rotating cable
arms to position the cable over the touch down point in the cable tank.
10.14.4 In vertical carousels the cable is wrapped around the centre cone of the rotating carousel and the
loading arm moves vertically up and down the height of the centre cone to position the cable. They are
loaded and unloaded with the cable under tension. The cable coils can slip down if there is insufficient
tension in the cable.
10.14.5 In horizontal carousels the cable is placed on the floor of the rotating carousel and the loading arm
moves horizontally across the width of the carousel.
10.14.6 Cable tank floors must be smooth with no steps that could damage cable when the cable tank is fully
loaded. It is common to line cable tank floors with ply wood sheets to protect the cable against
irregularities in the cable tank floor.
10.14.7 Drums are sometimes used to transport and install shorter length cables. Special handling equipment
is required to lay cable from a drum. Drum-loaded cables are usually delivered cut to the length
required for a single cable segment. It is common to pre install a combined pull-in head and end seal
arrangement before the loaded drum is delivered.
10.14.8 Drum-loaded cable lengths must be carefully calculated during the route development stage and
precisely measured to ensure sufficient cable is loaded onto each drum.

10.15 LIFTING CABLES


10.15.1 See 0027/ND, Ref. [7], for all lifting equipment and operations.

10.16 CATENARY MANAGEMENT


10.16.1 The catenary is the cable suspension formed between the lay chute and TD at the seabed. Effective
Catenary Planning and Management reduce the risk of cable damage during installation.
10.16.2 Poorly planned and implemented Catenary Management can lead to:
a. Excessive cable tension:
o During pull-in operations can:
threaten the cable MBR at J-tube/I-tube entrances.
cause cable damage near the pull-in head or pull-in stocking.
o Can prevent cable from dropping into the trench.
o Can cause excessively long suspensions to form between the J-tube/I-tube entry points
and the seabed.
o Can pull cable off route when laying in curves.
o Can prevent cable from being pulled to the surface for a repair operation.
o During ploughing, can result in excessive tension through the plough body and in the
ground after the plough has buried the cable.

0035/ND Rev 0 Page 44 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

o Can leave the cable in suspension over undulating seabed.

b. Excessive cable slack


o During J-tube/I-tube pull-in operations can:
Cause loops to be thrown in the cable especially at the second end when a
quadrant is deployed to lower the cable to the seabed.
Cause cables to be laid in no cable zones.
Make trenching operations difficult or impossible if the excessive slack cable
results in curves that cannot be followed by a burial vehicle.
o Can result in excessive cable ahead of the plough, resulting in the plough running over
the cable.

10.16.3 The installation contractor shall provide a Catenary Management Plan for acceptance. The Catenary
Management Plan must be supported by an Installation Analysis. The Catenary Management Plan
must include the lay back distances and top tensions required to maintain a safe seabed tension at all
water depths when laying cable in straight lines and in curves.
10.16.4 When laying cables from a DP vessel care should be given to catenary management in conditions
where the DP reference system becomes unreliable and/or a DP dropout might occur. A momentary
drop out of the DP reference signal can result in the CLV dropping astern enough for a loop to form in
the cable.

10.17 CABLE RADIUS CONTROL SYSTEM


10.17.1 Submarine power cables have a range of allowable MBRs for different cable handling situations. For
example the following would typically have different MBR for the same cable:
a. coiling into a carousel or a fixed cable tank
b. loading cable under tension onto a drum or a vertical carousel
c. whilst laying cable.

10.17.2 The cable MBR must be protected at all times during all cable handling operations. Protection of the
MBR must be provided by the design of the cable storage areas, cable coiling arms, cable highways,
cable handling quadrants, J-tube curves, cable tensioners, over boarding chutes/sheaves, Catenary
Management Procedures, cable trenching and cable burial tools and WTG and offshore substation
cable pathways.
10.17.3 If cable passes over rollers whilst under tension then the distance between the rollers must be
approved by the cable manufacture to ensure that micro bending will not occur over rollers that are too
far apart.

10.18 LAY CHUTE AND LAY SHEAVE


10.18.1 Cable passes overboard via a Lay Chute or a Lay Sheave. A Lay Chute is a fixed plate shaped to
protect the cable MBR. A Lay Sheave is a sheave of at least the same radius as the cable MBR.
10.18.2 Lay Chutes and Lay Sheaves must have whiskers to protect the cable MBR in cases where the cable
lead angle is not in line with the Lay Chute or Lay Sheave plan view centre line. Whiskers must
accommodate the maximum lead angle expected during cable installation operations for example
when a CLV might need to weather vane or crab along a cable route to overcome the influence of
wind, waves and current.
10.18.3 Whisker lead angles must take account of the impact of cross currents on the cable lead angle.
10.18.4 If the CLV stands by with cable deployed over the Lay Chute or the Lay Sheave then the cable must
be picked up or paid out a few metres at set periods of time to prevent cable damage where the cable
is stationary on the Lay Chute or Lay Sheave freshening the nip.

0035/ND Rev 0 Page 45 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

10.19 TEMPORARY ABANDON PROCEDURE


10.19.1 There shall be a temporary abandonment procedure (giving weather and/or motion criteria for
initiation). The abandonment procedure shall include a procedure to restart the installation operations.
The abandonment procedure must include and forecast periods and conditions for initiating the
abandonment procedure. For moored barges the forecast period might need to include the time to
transit to sheltered waters.

10.20 ARRAY CABLES


10.20.1 MBR Inter-array cable MBR are ordinarily in the range of 1 1.5 m. Measures should be taken to
monitor and protect the MBR throughout installation activities. Measurement of the MBR is not
ordinarily practicable, and can only be ensured to any level of accuracy with cable handling tools (such
as a quadrant, shoe-in tool, bend restricting cable protection). Where MBR is most at risk, bend
restriction methods such as quadrants should be used. If this is not possible, careful monitoring of the
cable bend geometry should be ensured.
10.20.2 Instances in which the MBR are most at risk include (but are not limited to) entry /exit to I /J-tubes, lay-
away, over-boarding and touchdown, use of a quadrant, support of over-length on TP during pull-in,
handling on deck.
10.20.3 Cable protection and bend restrictor fitting to Array Cables. Cable protection and bend restrictors
must be fitted at the correct location on the cable and following the manufacturers installation
instructions to ensure the interface with the J-tube /I-tube engages properly. Careful measurements
and calculations are required to establish the position at which bend restrictors and cable protection
are to be attached to an Array Cable. The calculations must be verified by an approved and proven
QA/QC check process on-board the installation vessel.
10.20.4 The attached position of the bend restrictor and cable protection onto the cable must be confirmed and
recorded before the Array Cable pull-in operation commences. GL Noble Denton shall witness an
agreed number of calculations, bend restrictor and cable protection fittings and deployments of
first-end pull-in operations.
10.20.5 Ploughed or free laid. Cable ploughing is usually performed where possible simultaneous lay and
burial being an efficient method. Cable plough equipment should be specified for the target burial,
taking consideration of soil conditions, topography and variability across the site.
10.20.6 1st end Installation is performed using a messenger wire installed inside the J-tube/I-tube and
connected to the cable end. Pull-in operations shall ensure protection of MBR and tension limits.
Particular care should be taken at touchdown to avoid jeopardizing the cable MBR, and at the bell-
mouth to avoid snagging. Careful consideration should also be given to the engagement of cable
protection systems with the bell-mouth, and how this allows movement and protection of the cable.
10.20.7 2nd end laydown. A bight (curved length of slack cable) may be laid on the seabed or a second end
deployment quadrant might be used in order to facilitate pull-in using a messenger wire. The length at
which the cable is cut shall allow for the design position of the cable, the final catenary from seabed
into foundation based on water depth, the required over-pull for cable termination, potential scour pit
development. Calculations shall be submitted by the contractor to show due consideration of these
factors. A pre-defined number of calculations shall be witnessed offshore by GL Noble Denton. The
cable must be lowered to the seabed in a controlled method, normally by taking up the tension in the
messenger wire from the TP.

10.21 EXPORT CABLES


10.21.1 MBR For all operations which involve the handling of export cables such as offloading,
trans-spooling, laydown, overboarding and abandonment, measures shall be undertaken to ensure the
protection of the cable MBR. Such measures can include the use of quadrants, cable highways
onboard the vessel, tension meters and bend restrictors. The use of such equipment should be
outlined in the procedural documentation for each operation including:
a. Ploughed or free laid
b. 2nd end laydown at substation

0035/ND Rev 0 Page 46 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

c. Back tension
d. Grounding lay barges
e. Floating installation
f. Positioning
g. Tides
h. Surveys of grounded areas.

10.22 EXPORT CABLE LANDFALL


10.22.1 Cable landfall - direct. If a CLV / CLB can approach close to the landfall position, cable can be
floated ashore using a pulling wire from the landfall with floats attached to the cable. Detailed marine
planning is required to ensure the main CLV / CLB can set up close enough to the landfall position for
the duration of the landfall operation. Care must be taken in cross currents which can cause excessive
tension in the cable leading to loss of control of the pull-in operation.
10.22.2 It is common to float the CLV in on a rising tide until the CLV is close enough to the landfall for a direct
pull-in operation. The CLV is allowed to bottom out during low water phases of the tidal cycle. Careful
planning is required to ensure the seabed is flat with no obstructions that might in anyway cause
damage to the CLV hull. Adequate pre-set mooring must be provided. Often anchors must be placed
on land due to the close proximity to land of the CLV set up position.
10.22.3 The work must be carefully planned and timed to ensure the vessel does not become trapped by falling
tides. A pull-ahead anchor should be deployed offshore of the CLV and a stand-by AHT (Anchor
Handling Tug) should be on site to assist the CLV if it needs to pull off the set-up position in an
emergency. It would be normal for an operation where the CLV needs to bottom out for the CLV to
approach the landfall site with minimum cable on-board. That means to lay cable from the offshore
structure toward the landfall. Consideration should be given to seabed suction forces when re-floating
the CLV.
10.22.4 Cable landfall pre-installed. A small low draft vessel can be used to pre-install a separate shore
end cable when the main CLV / CLB cannot approach close enough for a direct landfall operation.
There are two methods for implementing a pre-installed shore end installation:
1. A shore end cable is laid by a CLV(SE) between the landfall and a position where the main CLV
/ CLB can set up for jointing operations or,
2. The cable is turned-over from the main CLV / CLB onto a CLV(SE). The CLV(SE) lays the
cable toward the landfall location. This method presents complications at the landfall end as
the cable will need to be turned-over a second time to bring the landfall cable end to the top of
the cable tank.

10.22.5 Selecting landfall sites. Good landfall sites are rare. They allow the CLV / CLB to approach to within
a few hundred metres of land and float the cable ashore or, in some locations, pull the cable ashore
without floats into an open cut trench or through a short HDD duct.
10.22.6 Wind farm export cables are more often installed at sites requiring challenging and complex civil
engineering solutions than would be required at ideal landfall sites.
10.22.7 Sea defences and environmentally sensitive foreshore areas must often be crossed using HDD ducts.
The physical nature of some landfall sites requires HDD lengths at the extreme end of what is currently
possible.

10.23 CABLE AND PIPE-LINE CROSSINGS


10.23.1 Detailed planning is required to ensure a safe crossing for both the crossing and the crossed
submarine plant (pipeline or cable). The crossing point construction must ensure the crossed
submarine plant is safe from physical or other interference that could be caused by the crossing export
cable(s). This could include prevention of physical contact, prevention of galvanic action and electrical
interference with the crossed submarine plant.
10.23.2 The crossing design must allow for future maintenance of the crossed submarine plant and the export
cable. The crossing angle should be as near to 90 degrees as is possible. Typically owners of the

0035/ND Rev 0 Page 47 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

crossed submarine plant will require that plough operations cease 500m before and restart 500m after
the crossing point location. Jetting is normally allowed within the agreed no-plough zone.
10.23.3 Crossings are often constructed using concrete mattresses and/or rock dumping to provide separation
between the submarine plant and to provide stability and protection to the crossing export cable(s).
The export cable can also be encased in a cable protection product although this is a decision for the
cable owner. Construction methods, crossing angles and operational zone dimensions will need to be
agreed between the respective submarine plant owners and recorded in a formal Crossing Agreement.
10.23.4 When export cables are to be installed close to other submarine plant then due consideration should
be given to maintenance requirements of each of the respective items of submarine plant. For
submarine cables it is typical to allow at least three times the water depth clearance to ensure that a
repair operation can be done. Clearance from pipelines will need to be agreed with the pipeline owner.

10.24 CABLE JOINTING AND REPAIR


10.24.1 Array and export cable post-installation faults are rare and most faults to date have occurred as a
result of incidents during installation. Wind farm cable repairs will either be by complete replacement
of a cable or repair by cutting out the damaged /faulty cable and inserting a new section of cable.
Replacement is most likely to be used for array cables whereas inserting a new segment will most
likely apply to export cables.
10.24.2 Repair Vessels must provide a stable working platform, have fine control when manoeuvring and be
capable of holding station over the repair location for the time required to insert a joint into a cable.
10.24.3 Repair vessels must be configured for two ends of a cable to be handled both in the water and on the
vessel.
10.24.4 An enclosed jointing space is required with sufficient length and space for the ends of a cable to be
bought together so a joint can be inserted into the cable.
10.24.5 Repair joints must be qualified and type tested in accordance with CIGRE, Ref. [13].
10.24.6 Jointing personnel must be qualified jointers and jointers qualifications must be submitted for GL Noble
Denton approval.
10.24.7 It is recommended that repair joint kits are opened in a clean environment onshore and all parts are
checked against the repair joint contents list and a dummy assembly of the joint should be done to
prove the procedures are correct. The shelf life of compounds and/or resins should be checked and
shown to be valid.
10.24.8 Submarine power cable repair operations involve a number of complex manoeuvres that must be
carefully planned and procedures written. The selected repair vessel must be capable of supporting all
phases of a cable repair operation.
10.24.9 A typical cable repair will include
a. locating the cable at the fault location,
b. recovering the cable to the surface, cutting the cable and attaching a buoy to one end,
c. deploying the buoyed off end to the seabed, recovering cable until into good cable,
d. jointing sea cable onto spare cable on the repair vessel,
e. laying cable to buoyed off cable end, recovering buoy and buoyed off cable end,
f. jointing the spare cable to the sea cable and deploying the Final Splice to the seabed.

10.24.10 If cable tension prevents the cable from being lifted to the surface the cable will need to be cut on the
seabed. If the cable is not a water-blocked design then there is a risk of flooding the cable.
Submarine power cables are either wet, dry or semi-dry designs and each has different levels of
tolerance to water ingress. The cable manufacturer should be consulted if the repair strategy involves
cutting the cable on the seabed.
10.24.11 The cable end should be secured to the seabed to prevent movement due to ocean currents. Typically
this is achieved by attaching chain, steel reinforced ground rope and a clump weight to the cable end.
If a buoy is used to aid location and recovery of the ground tackle the buoy should have sufficient

0035/ND Rev 0 Page 48 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

buoyancy to remain at the surface in all anticipated current conditions. The rope, wire or chain
attaching buoys to the clump weight should have sufficient strength to ensure it does not fail.
10.24.12 The cable end(s) will need to be stoppered to secure points on the repair vessel. The stopper type
must be approved by the cable supplier. The stopper deck attachment point must be in line with the
cable line to prevent the stopper from exerting non-conforming forces on the cable.
10.24.13 The first joint will be deployed over the lay chute or sheave in line with the spare cable to be laid out to
the Final Splice location. The repair joint load mechanical properties should be confirmed as adequate
for the repair chute/sheave diameter and cable tension during deployment. Extreme tensions can be
generated in the cable where it enters the joint housing as the joint tips over the repair chute / sheave.
Consideration should be given to using a spreader beam and crane to deploy the joint over the repair
chute / sheave.
10.24.14 An Installation Analysis is required for the time the repair joint is in the water column until the joint is on
the seabed. If there is insufficient cable tension as the joint approaches the seabed the cable MBR will
be jeopardised.
10.24.15 At the Final Splice location the end of the good cable must be recovered to the repair vessel until there
is sufficient overlap with the spare cable laid from the first repair joint location for the cable ends to be
taken into the jointing facility and the joint to be made.
10.24.16 The cable catenaries formed during the Final Splice jointing operation must have sufficient tension to
ensure the cable MBR is not jeopardise at the seabed TD point but not so much tension that the repair
vessel imparts load in the cables.
10.24.17 Final Splice operations insert an additional cable length of approximately 3 times the water depth into a
cable system.
10.24.18 Final Splice deployment is a cable- hazardous operation during which a combination of cable slack and
residual torsion in the cable can cause loops, catpaws and standing sections of cable.
10.24.19 During Final Splice deployment the joint and cable must be supported using a spreader beam. The
repair vessel must be manoeuvred away from the cable line as the Final Splice is lowered to the
seabed. The joint lowering speed and the repair vessel speed must be co-ordinated to ensure the
Final Splice is laid down on the seabed without jeopardizing the cable MBR, without throwing loops or
leaving sections of the cable standing proud of the seabed.
10.24.20 Deployment rigging must be removed from the cable to ensure the rigging does not become entangled
with cable jetting equipment.
10.24.21 The repair vessel must have sufficient manoeuvring and position keeping capability to undertake the
manoeuvres required to support the operations described herein.
10.24.22 The whole of the repair section should be trench into the seabed. The Final Splice layout should be
surveyed using an inspection ROV and any loops, standing loops and/or cats-paws should be
recorded and if necessary an alternative protection to jetting should be developed.
10.24.23 The repaired cable should be tested and the cable repair vessel should remain on site until the tests
are complete and the cable repair is shown to be acceptable.
10.24.24 The damaged and/or faulty cable should be kept and taken ashore for investigation into the cause of
the failure. If the cause is an inherent defect then the costs to repair might be recoverable as a
warranty claim against the cable manufacturer.

0035/ND Rev 0 Page 49 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

REFERENCES

[1] GL Noble Denton 0001/ND General Guidelines for Marine Projects


[2] GL Noble Denton 0009/ND Guidelines for Elevated Operations for Jack-Ups
[3] GL Noble Denton 0013/ND Guidelines for Load-Outs
[4] GL Noble Denton 0015/ND Guidelines for Concrete Gravity Structure Construction & Installation
[5] GL Noble Denton 0016/ND Seabed and Sub-seabed Data Required for Approvals of Mobile Offshore Units
(MOU)
[6] GL Noble Denton 0021/ND Guidelines for the Approval of Towing Vessels
[7] GL Noble Denton 0027/ND Guidelines for Marine Lifting & Lowering Operations
[8] GL Noble Denton 0028/ND Guidelines for Steel Jacket Transportation & Installation
[9] GL Noble Denton 0030/ND Guidelines for Marine Transportations
[10] GL Noble Denton 0031/ND Guidelines for Float-Over Installations /Removals
[11] GL Noble Denton 0032/ND Guidelines for Moorings
[12] BWEA Guidelines for the Selection and Operation of Jack-ups in the Marine Renewable Energy Industry,
June 2009 (Note that BWEA is now RenewableUK and updates will be in this new name)
[13] CIGRE, Recommendations for Mechanical Tests on Submarine Cables published in Electra No 171 April 1997
[14] ICPC (International Cable Protection Committee ) Recommendation No 2 - Recommended Route and
Reporting Criteria for Cables in Proximity to Others
[15] ICPC Recommendation No 3 - Criteria to be Applied to Proposed Crossings Between Submarine
Telecommunications Cables and Pipelines/Power Cables
[16] ICPC Recommendation No 13 - Proximity of Wind Farm Developments & Submarine Cables
[17] IMCA M 179 Guidance on the Use of Cable Laid Slings and Grommets - August 2005.
[18] IMCA M 203 Guidance on Simultaneous Operations (SIMOPS)
[19] ISO 7531:1987 - Wire Rope slings for General Purposes - Characteristics and Specifications.
[20] ISO 19905-1 - Petroleum and natural gas industries -- Site-specific assessment of mobile offshore units --
Part 1: Jack-ups
[21] (UK) Department of Energy and Climate Change - Dynamics of scour pits and scour protection Synthesis
report and recommendations Final Report 2008
http://mhk.pnnl.gov/wiki/images/9/91/Dynamics_of_Scour_Pits_and_Scour_Protection.pdf

All GL Noble Denton Guidelines can be downloaded from


http://www.gl-nobledenton.com/en/rules_guidelines.php.

0035/ND Rev 0 Page 50 of 51


GUIDELINES FOR OFFSHORE WIND FARM INFRASTRUCTURE INSTALLATION

APPENDIX A - INITIAL INFORMATION REQUIRED FOR APPROVAL


A.1 GENERAL INFORMATION REQUIRED
A.1.1 Where approval is required, the following shall be submitted to GL Noble Denton for information and/or
review, consisting of:
a. The project management structure, including contractors and subcontractors as in Section 6 of
0001/ND, Ref. [1].
b. Proposed project drawing and document register including risk assessments and marine manuals
/procedures
c. Proposed timetable of events.

A.2 STRENGTH, MOTION RESPONSE & STABILITY (ALL PHASES)


A.2.1 Information to cover the topics in Sections 7 to 9.
A.2.2 Information on weight control of weight-sensitive items as in Section 8 of 0001/ND, Ref. [1].

A.3 CONSTRUCTION IN DRY-DOCK OR BASIN (IF APPLICABLE)


A.3.1 Information to cover the topics in Section 10 of 0001/ND, Ref. [1].

A.4 MOORINGS FOR CONSTRUCTION AFLOAT (IF APPLICABLE)


A.4.1 See Appendix A of 0032/ND, Ref. [11]

A.5 FLOAT-OUT & TOW TO INSHORE CONSTRUCTION SITE (IF APPLICABLE)


A.5.1 Information to cover the topics in Section 11 of 0001/ND, Ref. [1].

A.6 CONSTRUCTION / OUTFITTING AFLOAT (IF APPLICABLE)


A.6.1 Information to cover the topics in Section 9 of 0015/ND, Ref. [4].

A.7 HEAVY LIFTS (IF APPLICABLE)


A.7.1 See Appendix A of 0027/ND, Ref. [7]

A.8 TEMPORARY BALLASTING AND COMPRESSED AIR SYSTEMS (IF


APPLICABLE)
A.8.1 Information to cover the topics in Section 12 of 0001/ND, Ref. [1].

A.9 DECK MATING (IF APPLICABLE)


A.9.1 See Appendix A of 0031/ND, Ref. [10].

A.10 TOW /TRANSPORTATION TO INSTALLATION SITE


A.10.1 See Appendix A of 0030/ND, Ref. [9].

A.11 INSTALLATION
A.11.1 Information to cover the topics in Section 9.

A.12 CABLE INSTALLATION


A.12.1 Information to cover the topics in Section10.

0035/ND Rev 0 Page 51 of 51