You are on page 1of 21

APPLICATION NOTE

An In-Depth Examination of an Energy


Summary
Efficiency Technology
Thermal energy storage (TES) systems
shift cooling energy use to non-peak
times. They chill storage media such as
water, ice, or a phase-change material
Thermal Energy during periods of low cooling demand
for use later to meet air-conditioning
Storage Strategies loads. Operating strategies are gener-
ally classified as either full storage or
partial storage, referring to the amount
for Commercial of cooling load transferred from on-peak
to off-peak.
HVAC Systems TES systems are applicable in most
commercial and industrial facilities, but
certain criteria must be met for eco-
nomic feasibility. A system can be ap-
propriate when maximum cooling load is
significantly higher than average load.
High demand charges, and a significant
differential between on-peak and off-
peak rates, also help make TES sys-
tems economic. They may also be ap-
Summary ............................................. 1 propriate where more chiller capacity is
needed for an existing system, or where
How This Technology back-up or redundant cooling capacity
Saves Energy ...................................... 2 is desirable.

Types of Demand and Energy Besides shifting load, TES systems may
Efficiency Measures ........................... 3 also reduce energy consumption, de-
pending on site-specific design, notably
Applicability ........................................ 7
where chillers can be operated at full
Field Observations to Assess load during the night. Also, pumping
Feasibility ............................................ 7 energy and fan energy can be reduced
by lowering the temperature of the wa-
Cost and Service Life ....................... 11 ter, and therefore the air temperature,
affecting the quantity of air circulation
Laws, Codes, and Regulations........ 13 required.
Definitions of Key Terms ................. 13
Capital costs tend to be higher than a
References to More Information...... 14 conventional direct-cooling system, but
other economic factors can reduce such
Major Manufacturers ........................ 14 costs. In new construction, ductwork

Copyright May 1997, Pacific Gas and Electric Company, all rights reserved. Revised 4/25/97
could be smaller, allowing more usable does require the chiller to work harder
space. Or a TES system may enable to cool the system down to the required
reduction in electrical capacity, reducing lower temperatures (for ice storage);
the cost of electrical service for a new or and energy is needed to pump fluids in
expanding facility. and out of storage.

But a number of design options can


How This Technology make TES systems more energy-
efficient than nonstorage systems. Stor-
Saves Energy age systems let chillers operate at full
load all night , versus operating at full or
In a TES system, a storage medium is part load during the day.
chilled during periods of low cooling
demand, and the stored cooling is used Depending on the system configuration,
later to meet air-conditioning load or the chiller may be smaller than would be
process cooling loads. required for direct cooling, allowing
smaller auxiliaries such as cooling-
The system consists of a storage me- tower fans, condenser water pumps, or
dium in a tank, a packaged chiller or condenser fans. Pumping energy can
built-up refrigeration system, and inter- be reduced by increasing the chilled
connecting piping, pumps, and controls. water temperature range; fan energy
The storage medium is generally water, can be cut with colder air distribution.
ice, or a phase-change1 material Storage systems can also make in-
(sometimes called a eutectic salt); it is creased use of heat recovery and wa-
typically chilled to lower temperatures terside economizer strategies.
than would be required for direct cooling
to keep the storage tank size within
economic limits. Figure 1 illustrates the
basic operation of a system that uses Discharging
chilled water.

Load shifting is typically the main rea- Building Load


son to install a TES system. Cool stor- Distribution
age systems can significantly cut oper- Pump Warm
ating costs by cooling with cheaper off- Storage
peak energy, and reducing or eliminat-
ing on-peak demand charges. Cool

These systems have a reputation for


consuming more energy than nonstor- Primary Pump
age systems. This has often been true Chiller
where demand reduction was the pri- Charging
mary design objective. Cool storage
1
Bold italicized words are defined in the section Figure 1: Thermal Energy Storage
title Definition of Key Terms. System with Stratified Chilled Water
Storage (Source: ASHRAE)*


PG&E Energy Efficiency Information Thermal Energy Storage Page 2
Tank volume is affected by the separa-
Types of Demand and tion maintained between the stored cold
Energy Efficiency Measures water and the warm return water. Natu-
ral stratification has emerged as the
preferred approach, because of its low
TES systems can be characterized by
cost and superior performance. Colder
storage medium and storage technol-
water remains at the bottom and
ogy. Storage media include chilled wa-
warmer, lighter water remains at the top.
ter, ice, and phase-change materials,
Specially designed diffusers transfer
which differ in their operating charac-
water into and out of a storage tank at a
teristics and physical requirements for
low velocity to minimize mixing.
storing energy. Storage technologies
include chilled water tanks, ice systems, The figure of merit (FOM) is a measure
and phase-change materials. of a tanks ability to maintain such sepa-
ration; it indicates the effective percent-
Chilled Water Storage age of the total volume that will be
available to provide usable cooling.
These systems use the sensible heat
Well-designed stratified tanks typically
capacity of water (1 Btu per pound per
have FOMs of 85 to 95 percent.
degree Fahrenheit) to store cooling.
Tank volume depends on the tempera- The practical minimum storage volume
ture difference between the water sup- for chilled water is approximately 10.7
plied from storage and the water re- cubic feet per ton-hour at a 20F tem-
turning from the load, and the degree of perature difference.
separation between warm and cold wa-
ter in the storage tank. Where most Chilled Water System Example
conventional nonstorage HVAC systems Application
operate on temperature differentials of
10 to 12F, chilled water systems gen- Needing an additional 3,750 tons of
erally need a differential of at least 16F peak cooling capacity for a 250,000-
to keep the storage tank size reason- square-foot addition to its Dallas head-
able. A difference of 20F is the practi- quarters, Texas Instruments chose a
cal maximum for most building cooling chilled water thermal storage system:
applications, although a few systems Adding chiller capacity would have cost
exceed 30F. about $10 million, while the TES system
cost about $7 millionand a $200/kW
Chilled water is generally stored at 39F utility rebate reduced this to about $5.75
to 42F, temperatures directly compati- million. The new system also has cut
ble with most conventional water chillers operating costs about $1.5 million per
and distribution systems. Return tem- year and allowed postponement of an
peratures of 58 to 60F or higher are expansion of the facilitys high-voltage
desirable to maximize the tank tem- substation.
perature difference and minimize tank
volume. The TES system uses a 5.2-million-
gallon, thermally stratified chilled water
storage tank, built under a parking lot.


PG&E Energy Efficiency Information Thermal Energy Storage Page 3
This pre-stressed, cylindrical concrete
reservoir, 140 feet in diameter and 45
feet in height, has a design discharge
rate of 7,500 tonsdelivering 40F wa- Building Ice Harvester
Load Chiller
ter at 12,000 gallons per minute (gpm)
which returns to the tank at 55F.

This system shifts 5.1 MW (35 percent)


of existing electric chiller load to off-
peak hoursabout 8.5 percent of total
facility demand. Five existing chillers Chilled Ice-water
with total capacity of 6,500 tons now Ice / Water
Water Pump
Mixture
remain off during the day. Mechanical Pump
cooling systems now operate more effi-
ciently because they are more fully
Figure 2: Ice Harvesting
loaded (0.85 kW/ton versus the previ- (Source: ASHRAE)*
ous 0.95 kW/ton) and produce 13 per-
cent more annual ton-hours of cooling.
a higher temperature rise at the load, up
Ice Storage to 25F. The following technologies are
used:
Ice thermal storage uses the latent heat
of fusion of water (144 Btu per pound). Ice harvesting. Ice is formed on an
Storage volume is generally in the evaporator surface and periodically re-
range of 2.4 to 3.3 cubic feet per ton- leased into a tank partially filled with
hour, depending on the specific ice- water. Cold water is pumped from the
storage technology. tank to meet the cooling load. Return
water is then pumped over ice in the
Thermal energy is stored in ice at 32F, tank. Refer to Figure 2.
the freezing point of water. The equip-
ment must provide charging fluid at External melt ice-on-coil. Ice is
temperatures of 15 to 26F, below the formed on submerged pipes or tubes
normal operating range of conventional through which a refrigerant or secon-
cooling equipment for air-conditioning. dary fluid is circulated. Storage is dis-
Depending on the storage technology, charged by circulating the water that
special ice-making equipment is used or surrounds the pipes, melting the ice
standard chillers are selected for low- from the outside.
temperature duty. The heat transfer fluid
may be the refrigerant itself or a secon- Internal melt ice-on-coil. Ice is
dary coolant such as glycol with water formed on submerged pipes or tubes,
or some other antifreeze solution. as in the external melt system. Cooling
is discharged by circulating warm cool-
The low temperature of ice can also
ant through the pipes, melting the ice
provide lower temperature air for cool-
from the inside.
ing. The lower-temperature chilled water
supply available from ice storage allows


PG&E Energy Efficiency Information Thermal Energy Storage Page 4
Encapsulated ice. Water inside selected temperatures. Most common is
submerged plastic containers freezes a mixture that stores 41 Btu per pound
and thaws as cold or warm coolant is at its melting/freezing point of 47F.
circulated through the tank holding the This material is encapsulated in rectan-
containers. gular plastic containers, which are
stacked in a storage tank through which
Ice slurry. Water in a water/glycol water is circulated. The net storage vol-
solution is frozen into a slurry like the ume of such a system is approximately
ice in a Sno-Cone and pumped to a six cubic feet per ton-hour.
storage tank. Slurries can be pumped
from the tank to heat exchangers or di- The 47F phase-change point of this
rectly to cooling coils, resulting in high material allows the use of standard
energy transport rates. chilling equipment. Discharge tempera-
tures are higher than the supply tem-
The most common commercial technol- peratures of most conventional cooling
ogy today is internal melt ice-on-coil. systems, so operating strategies may be
External melt and ice-harvesting sys- limited.
tems are more common in industrial ap-
plications, and can also be applied in Phase-change materials are also avail-
commercial buildings. Encapsulated ice able for lowering the storage tempera-
systems are also suitable for many tures of ice systems. Additives on the
commercial applications. market reduce freezing temperatures to
28 and 12F in ice storage tanks; they
Ice Storage Example Application reduce the latent heat capacity of water,
as well as lower the freezing point. The
The Seafirst Building in Bellevue, material is highly corrosive, so care
Washington uses an ice storage system must be used in applying it.
and cold air distribution with smaller-
than-typical ducting. An Electric Power Operating and Control
Research Institute comparison showed Strategies
that this increased gross construction
costs but reduced construction cost per TES operating strategies are generally
square foot by about $4, because re- classified as either full storage or par-
duced floor-to-floor heights allowed 21 tial storage, referring to the amount of
stories within a height that would nor- cooling load transferred from on-peak
mally accommodate only 20thus periods. Strategies for operation at less
adding 13,000 square feet of rentable than design loads include chiller priority
space. Smaller mechanical rooms and storage priority control.
added another 4,000 square feet. This
provides about $340,000 per year of The period during which a system must
additional income. reduce electric demand is generally
called on-peak, often but not neces-
Phase-Change Material Storage sarily synonymous with on-peak hours
defined by the electric utility. In some
Phase-change materials, or eutectic facilities the period may actually be
salts, are available to melt and freeze at shorter than the utility on-peak period.


PG&E Energy Efficiency Information Thermal Energy Storage Page 5
Load
Peak electric demand from cooling also Chiller On
may not occur simultaneously with the Chiller Charging Storage
peak facility demand. Chiller Meets Load Directly
Storage Meets Load

Cool storage systems are usually sized


to generate enough cooling in 24 hours
to meet all the loads occurring during

Tons
that period, but some applications use
longer cycles.

Full Storage
24-hour Period
Full-storage, or load-shifting (shown in
Figure 3), shifts the entire on-peak
Figure 4: Partial-storage Load-
cooling load to off-peak hours and usu- Leveling Operating Strategy
ally operates at full capacity to charge (Source: ASHRAE)*
storage during all non-peak hours. On-
meets the rest. Such operating strate-
Load
Chiller On gies can be further subdivided into load-
Chiller Charging Storage leveling and demand-limiting, Figures 4
Chiller Meets Load Directly
Storage Meets Load
and 5.

In a load-leveling system, the chiller


typically runs at full capacity for 24
hours on the design day. When the load
Tons

is less than the chiller output, the ex-


cess charges storage. When the load
exceeds chiller capacity, the additional
requirement is discharged from storage.
24-hour Period
Load
Chiller On
Figure 3: Full Storage Operating Chiller Charging Storage
Strategy (Source: ASHRAE)* Chiller Meets Load Directly
Storage Meets Load

peak, all cooling loads are met from


storage, and the chiller does not run. A
full-storage system requires relatively
Tons

Reduced On-peak
large chiller and storage capacities and Demand
is most attractive where on-peak de-
mand charges are high or the on-peak
period is short.
24-hour Period
Partial Storage
Figure 5: Partial-storage Demand-
With this strategy chiller capacity is less
Limiting Operating Strategy
than design load. The chiller meets part (Source: ASHRAE)*
of the on-peak cooling load and storage


PG&E Energy Efficiency Information Thermal Energy Storage Page 6
This approach minimizes required
chiller and storage capacities and is Applicability
particularly attractive where peak cool-
ing load is much higher than average Thermal energy storage can be used in
load. In many systems, cooling loads virtually any building; the merits are
during off-design periods are small compelling in the right situations. The
enough that partial-storage systems main issues are the type of storage
may be operated as full-storage sys- system and the amount of cooling load
tems. This can increase savings but to be shifted. Before embarking on a
care must be taken to not deplete stor- cool storage project, however, one
age before the on-peak period is over. should consider the field observation
guidelines below. In addition, alternative
A demand-limiting partial-storage sys- approaches should be considered for
tem operates the chiller at reduced ca- each project.
pacity on-peak. The chiller may be con-
trolled to limit the facility demand at the
billing meter. This strategy falls between Field Observations to
load shifting and load leveling. Demand
savings and equipment costs are higher Assess Feasibility
than for load-leveling, and lower than
for load-shifting. Here too care must be This section discusses observations
taken not to deplete storage before the and checks that can ensure a TES sys-
end of the on-peak period. tem is appropriate and is installed and
working properly.
Additional variations on the full- and
partial-storage strategies are possible Related to Applicability
by scheduling the operation of multiple
chillers. The many successful TES systems op-
erating today demonstrate that the
Partial-storage systems use one of two technology can provide significant
control strategies to divide the load benefits. However, many cool storage
between chiller and storage. A chiller- systems have failed to perform as pre-
priority strategy uses the chiller to di- dicted because they did not meet the
rectly meet as much of the load as pos- criteria for applicability cited below.
sible. Cooling is supplied from storage
only when load exceeds chiller capacity. Cool storage systems are most suitable
Storage-priority meets as much of the where any of the following criteria apply:
load as possible from stored cooling,
using the chiller only when daily load The maximum cooling load of the
exceeds total stored cooling capacity. facility is significantly higher than the
Some systems use combinations of average load. The higher the ratio of
these strategies. For example, chiller peak load to average load, the greater
priority during off-peak daytime hours, the potential.
and storage priority during on-peak
hours.


PG&E Energy Efficiency Information Thermal Energy Storage Page 7
The electric utility rate structure The maximum cooling load of the
includes high demand charges, facility is very close to the average
ratchet charges, or a high differential load. A TES system would offer little
between on- and off-peak energy rates. opportunity to downsize chilling equip-
The economics are particularly attrac- ment.
tive where the cost of on-peak demand
and energy is high. On-peak demand charges are low
and there is little or no difference be-
An existing cooling system is be- tween the costs of on- and off-peak en-
ing expanded. The cost of adding cool ergy. There is little economic value for
storage capacity can be much less than customers to shift cooling to off-peak
the cost of adding new chillers. periods.

An existing tank suitable for cool The space available for storage is
storage use is available. In some ret- limited, there is no space available, the
rofits, particularly in industrial applica- cost of making the space available is
tions, using existing tanks can reduce high, or the value of the space for some
the cost of installing cool storage. other use is high.

Electric power available at the site The cooling load is too small to
is limited. Where expensive trans- justify the expense of a storage sys-
formers or switchgear would otherwise tem. Typically, a peak load of 100 tons
have to be added, the reduction in or more has been necessary for cool
electric demand through the use of cool storage to be feasible.
storage can mean significant savings.
The design team lacks experience
Backup or redundant cooling ca- or funding to conduct a thorough de-
pacity is desirable. Cool storage can sign process. The design team should
provide short-term backup or reserve be capable of TES design, which differs
cooling capacity for computer rooms from standard HVAC system design. If
and other critical applications. this is not the case, or if funding for de-
sign fees is limited, the chances for a
Cold air distribution can be used, successful system are reduced.
is necessary, or would be beneficial.
Cool storage technologies using ice Performance testing of a new thermal
permit economical use of lower- storage plant is particularly important.
temperature supply water and air. Engi- Each system should be tested for
neers can downsize pumps, piping, air charge capacity, discharge capacity,
handlers, and ductwork, and realize and scheduling and control sequences.
substantial reductions in first cost.
The charge capacity test verifies that
If one or more of the following are true, the system can fully charge storage
TES may not be an appropriate tech- within the available time. The discharge
nology: capacity test verifies its ability to pro-
vide the required cooling, at or below


PG&E Energy Efficiency Information Thermal Energy Storage Page 8
the maximum usable supply tempera- tentially at higher efficiency. And opera-
ture, for each hour over the design load tion is generally at night when lower
profile. Of primary concern is that stored ambient temperatures make for cooler
thermal energy is used at a rate con- condenser temperatures, reducing en-
sistent with the design. Especially in ergy use.
chilled water systems, if oversized
pumps circulate water at higher than However, TES systems do not always
design flow rates, a smaller supply- save energy. A retrofit using ice storage
return temperature difference will re- that fails to take advantage of the colder
duce the capacity of the storage system. water available from the ice system may
consume more energy than a direct
A test of scheduling and control se- cooling system. Yet this system can
quences confirms the proper operation make economic senseconsuming
of valves, resetting of setpoints, and more off-peak, lower cost energy at
starting and stopping of equipment, ac- night can still significantly reduce ex-
cording to scheduled operating modes. pensive electrical demand and expen-
sive on-peak electricity use.
A TES system operates differently from
a nonstorage system, in that the inven- Related to Implementation Cost
tory of stored cooling must be properly
managed. Operators of TES systems Most TES systems cost more up front
must receive training in basic concepts and (if cost-effective) pay off through
as well as the intended operating se- reduced electricity bills. But carefully
quences and specific operating proce- designed systems neednt cost more
dures for their systems. As operators or much morethan conventional
gain experience they can improve sys- HVAC systems.
tem performance and minimize operat-
ing costs by refining the design operat- Sometimes cool storage systems can
ing strategies and control setpoints. cost less and save energy. The Texas
Instruments case study discussed ear-
Related to Energy Savings lier describes one of three chilled-water
storage installations in Dallas that have
In new construction, TES systems can reduced energy consumption by more
reduce overall energy consumption than 10 percent compared to nonstor-
even though there may be increased age alternatives. The TI installation also
use in the chiller: distribution of colder reduced capital costs millions of dollars
chilled water can allow use of smaller by deferring the need for added chiller
pumps and less fan horsepower to cir- capacity. Other factors that may help
culate a smaller quantity of air through reduce cost of implementation include:
the cooling coils.
Smaller air flows will provide ade-
In retrofits it also is possible to reduce quate cooling in new construction or
energy consumption but generally less major retrofits, especially for ice stor-
so than in new construction. Here en- age. This can decrease the duct di-
ergy savings result from chillers oper- ameter, reducing not only the cost of the
ating at full load nearly all the time, po-


PG&E Energy Efficiency Information Thermal Energy Storage Page 9
ductwork, fans, and pumps but also the Standard Savings Calculation
installation labor cost.
The following equation can be used in
Smaller ducts may increase rent- estimating demand savings from TES
able space in new construction. systems. While energy consumption
may increase or decrease, the change
System sizing is critical. For ex- generally has only a minor impact on
ample, a careful assessment of the project economics. The time period
number of hours that peak load must be when the energy is consumed has a
met with stored cooling could show that significant impact; i.e. on-peak demand
a considerably smaller storage system reduction or displacing expensive on-
may only minimally affect demand re- peak energy with less expensive off-
duction. peak energy use. In general, system
economics depend heavily on the de-
Estimation of Energy Savings mand savings and/or on-peak/off-peak
rate differential. Demand savings must
Demand costs are the main considera- be calculated for each month of chiller
tion in determining the economics of a operation.
TES system. Energy savings may be
achieved, particularly in new construc- kWsavings = # tonsshifted
tion or major renovation projects, but (kW/ton)chiller performance
typically are a small percentage of op-
erating cost savings. In fact, energy Energy shifted to off-peak is more diffi-
consumption may increase and still al- cult to calculate without monitored field
low for an economically viable project. data or a calibrated, hourly computer
simulation. A rough estimate can be
To determine economic feasibility, accu- calculated as follows:
rate cooling load data from the existing
chiller plant is always best. If data are kWhshifted = # tonsshifted
not available, not considered reliable or (kW/ton)chiller performance
incomplete, or if only a short time period on-peak hours
of data has been collected, an hourly load shape factor
computer simulation model must be de-
veloped by a reputable energy analysis The load shape factor is a needed mul-
professional. Available data, even for tiplier because peak cooling load typi-
only a short period, can be used to help cally is not constant. This factor, used in
calibrate the simulated building model the above equation, is for the on-peak
and improve its accuracy. period only (the time when cooling load
will be shifted) and for the peak cooling
Back-of-the-envelope calculations can load for that day. Typical load shape
give a rough estimate of possible sav- factors are in the range of 60 to 90 per-
ings but must not be used for the final cent for a variety of building types and
economic analysis, or chiller or storage climates. Annual energy shifted is the
tank sizing. sum of daily energy shifted. At this
point, an estimate can be made using


PG&E Energy Efficiency Information Thermal Energy Storage Page 10
an average cooling load for each month a specific application can be obtained
and the number of cooling days in the from contractors or vendors.
month, then summing the monthly to-
tals. Costs for chilled water tanks are based
on volume, so the cost per ton-hour de-
pends on the chilled water temperature
Cost and Service Life range. Unit storage costs decrease as
tank size increases. The cost of chillers
or refrigeration equipment must be con-
Factors That Influence Service sidered along with the cost of storage
Life and First Cost capacity. Chilled water and phase-
change material storage are compatible
with typical conventional HVAC tem-
Typically, a TES system increases costs peratures, and can often be added to
compared to those for a direct cooling existing systems with no chiller modifi-
system. But a much larger picture needs cations. For ice-harvesting systems, low
to be looked at. Additional issues in- storage cost is offset by a relatively high
clude: cost for the ice-making equipment.
Floor Height: In new construction, Typical Service Life
can low-temperature air distribution
which uses smaller, less expensive In addition to all equipment in a tradi-
ductworkreduce floor-to-floor height? tional cooling system, a TES system
has a storage tank, pumps, piping and
Electrical Capacity: Can using possibly an interface heat exchanger.
TES reduce the capacity and therefore The service life of each component
the cost of the electrical service to a (except the actual storage tank) has
new project, or avoid increasing the been estimated and can be found in
service in the case of a building expan- Reference 1. All TES-specific compo-
sion? nents are rated at a 20-year minimum
service life. Storage tanks, generally
Useable Space: Can using TES, concrete or steel, also have service
with an underground storage tank, such lives of at least 20 years.
as under a parking lot, free up space in
an existing chiller plant or reduce the Operation and Maintenance
size of a new structure? Requirements
Costs given in Table 1 are general Factors that tend to increase mainte-
guidelines for initial economic evalua- nance costs for cool storage systems
tions of storage systems. They include compared to nonstorage systems in-
the cost of storage tanks and any re- clude:
quired internal diffusers, headers, or
heat transfer surface. Costs will vary Annual tests to ensure solutions
depending on the size of the project and contain proper coolant concentration,
site-specific considerations, among levels of corrosion inhibitors, and other
other things. Accurate cost estimates for


PG&E Energy Efficiency Information Thermal Energy Storage Page 11
Chilled Ice External Internal Encapsulated Phase-change
Water Harvester Melt Ice Melt Ice Ice Material
Pre-packaged or
Low-temperature Low-temperature Low-temperature
built-up ice-
Chiller Cost Standard water coolant or built-up secondary secondary Standard water
making
refrigeration plant coolant coolant
equipment
Chiller Costa
$/ton 200-300, 1,100-1,500 per 200-300,
200-500 200-500 200-500
or use existing ice-making ton or use existing

$/kW 57-85 313-427 57-142 57-142 57-142 57-85


Tank Volume
ft/ton-hr 11-21 3.0-3.3 2.8 2.4-2.8 2.4-2.8 6.0
Storage Installed
Costb $/ton-hr 30-100 20-30 50-70 50-70 50-70 100-150
$/kWh 8.50-28 5.70-8.50 14-20 14-20 14-20 48-43
Charging Temperature (oF) 39-42 15-24 15-25 22-26 22-26 40-42
Chiller Charging
Efficiency kW/ton 0.60-0.70 0.95-1.3 0.85-1.4 0.85-1.2 0.85-1.2 0.60-0.70
COP 5.9-5.0 3.7-2.7 4.1-2.5 4.1-2.9 4.1-2.9 5.9-5.0
Discharge 1-4 above
Temperaturec (oF) charging 34-36 34-36 34-38 34-38 48-50
temperature
Secondary Secondary
Discharge Fluid Water Water Water Water
coolant coolant
Open or closed
Tank Interface Open tank Open tank Open tank Closed system Open tank
system
Use existing High High Modular tanks
Tank shape Use existing
Strengths chillers; fire instantaneous instantaneous good for small or
flexible chillers
protection duty discharge rates discharge rates large installations
Separate charge
Storage capacity Requires
and discharge
increases with clearance above
Comments circuits. Charge
larger temperature tank for ice
with coolant or
range. maker.
liquid refrigerant.
Notes:
a: Costs are for chiller or refrigeration plant only, and do not include installation. All costs, except ice harvesters, are per nominal ton.
Derating for actual operating conditions may be required.
b: Costs are for storage only, and include tank, internal diffusers, headers, and heat transfer surface.
c: Typical minimum temperatures, with appropriate sizing of storage capacity. Higher temperature can be obtained from each medium.

Table 1: Comparative Costs and Performance of Cool Storage Systems (Source: ASHRAE )*

additives for ice storage systems using Added maintenance for cool stor-
glycol or other secondary coolants. age system components, such as addi-
Some glycol manufacturers provide free tional pumps, heat exchangers, and
laboratory analysis of samples. There control valves.
may also be an expense associated
with replacing glycol lost during mainte- Factors that tend to decrease mainte-
nance procedures and through leaks. nance costs for cool storage systems
include:
Increased water treatment ex-
pense in chilled water storage and Smaller components, such as chill-
some ice storage systems, which con- ers, pumps, and cooling towers, for typi-
tain large volumes of chilled water in the cal systems.
tanks.


PG&E Energy Efficiency Information Thermal Energy Storage Page 12
Glycol or other secondary cool- Demand Charge: A tariff added to
ants in the system provide coil freeze a customers electric bill that increases
protection, and eliminate the need to in proportion to maximum kilowatts
drain the cooling system in the winter, used.
or to use special controls to prevent coil
freeze-ups. DX (direct expansion): Refers to a
heat exchanger that contains the refrig-
Cooling loads can be met from erant inside its tubing rather than water,
storage while some equipment is taken antifreeze, or other fluid. Heat from the
out of service for maintenance in some surroundings is directly absorbed into
storage systems. the refrigerant, which is pumped by
the compressor.

Laws, Codes, and Figure of Merit (FOM): A measure


of a storage tanks ability to maintain
Regulations separation between warm and cool wa-
ter.
All equipment and components used for
a TES system should conform with the Full Storage: Refers to a TES sys-
same laws, codes, and regulations re- tem that stores sufficient cooling to meet
quired for traditional cooling systems. an entire peak day cooling capacity, al-
Large tanks may pose a problem. Zon- lowing chillers to be off during the on-
ing requirements, particularly height re- peak period.
strictions, should be checked early. If
height is an issue, it is possible to com- Off-Peak: A time period, defined by
pletely or partially bury it. It is also pos- the utility, when the cost of providing
sible that a levee will be required power is relatively low, because the
around the tank in case of a rupture. system demand for power is low. The
off-peak period is often characterized by
If a fire-protection storage tank is re- lower costs to the customer for energy
quired on site, as it would be at some costs, and either no or low demand
manufacturing facilities, it may be pos- charges.
sible to use this tank to store chilled
water for the cooling system. If this is On-Peak: A time period, defined by
available, it should be carefully checked the utility, when the cost of providing
to ensure code compliance. power is high because the system de-
mand for power is high. The on-peak
period is typically characterized by
Definitions of Key Terms higher costs to the customer for energy
and/or demand charges.
Condenser: The container in a
cooling system where gas changes Partial Storage: Refers to a TES
phase to liquid, releasing heat to the system that contains sufficient cool
surroundings. storage to meet part of the cooling load
of a facility. Such systems are used in


PG&E Energy Efficiency Information Thermal Energy Storage Page 13
conjunction with a chiller system to pro- 4. E Source, State of the Art Technol-
vide required cooling capacity. ogy Atlas: Commercial Space Cool-
ing and Air Handling, Chapter 11,
Phase Change: As a substance 1995.
changes between its solid, liquid, and
gaseous forms, it is said to change 5. International Thermal Storage Advi-
phase. During transitions in phase sory Council (ITSAC), 3769 Eagle
freezing, melting, condensing, boiling Street, San Diego, CA 92103, Tel:
the material releases or absorbs large (619) 295-6267.
amounts of thermal energy without
changing temperature. The energy as-
sociated with this is called latent heat. A Major Manufacturers
material that can store thermal energy
as latent heat is called a phase-change Chicago Bridge & Iron Co.
material. 1501 N. Division Street
Plainfield, IL 60544-8929
Sensible Heat: Heat that can be Tel (815) 439-6000
perceived by the human senses, as op- Fax (815) 439-6010
posed to latent heat (see phase change E-mail: www.chicago-bridge.com
definition).
San Luis Tank & Piping Co.
825 26th Street
References to More Paso Robles, CA 93447
Information Tel (805) 238-0888
Fax (805) 238-5123
1. American Society of Heating Refrig-
Cryogel
eration, and Air-Conditioning Engi-
P.O. Box 910525
neers, ASHRAE Handbook HVAC
San Diego, CA 92191
Applications, June 1995.
Tel (619) 792-9003
2. American Society of Heating Refrig- Fax (619) 792-2743
eration, and Air-Conditioning Engi- E-mail: tes@cryogel.com
neers, Design Guide for Cool
Thermal Storage, 1994. For more information on companies who
make TES components see Reference
4 above. In addition, you may contact
3. Electric Power Research Institute the International Thermal Storage Advi-
(EPRI) HVAC & R Center (formerly sory Council (Reference 5) or the EPRI
the Thermal Storage Air Condition- HVAC & R Center (Reference 3).
ing Center), University of Wisconsin,
150 East Gilman Street, Suite 2200,
Madison, WI 537093, Tel: (800) 858-
3774, Fax: (608) 262-6209.
*Reprinted with permission. Copyright, 1994 by
ASHRAE. All rights reserved.


PG&E Energy Efficiency Information Thermal Energy Storage Page 14
November 6, 2009
GP #8
Cut the Tip off the ENERGYberg:
Thermal Ice Storage and the LEEDv3 Green Building Rating System

Peak Electrical Utility Peak Electrical Load Flattened


Load Profile using Thermal Ice Storage

Green Piece #8 specifically addresses Thermal Ice Storage and its LEED credit opportunities. In
addition to energy cost savings credits in Energy and Atmosphere, there are categories in Water Efficiency and
Indoor Environmental Quality for schools that may have the potential to earn additional credits.
Take the initiative and go for those hard to obtain credits that push the LEED rating from Gold to
Platinum! Ice thermal storage provides an energy efficient cooling system that is economically responsible to the
end-user and diminishes the demand on the utilitys electrical infrastructure. The benefits of ice storage include:

Reduced greenhouse gas emissions and source fuel required to generate electricity.

Lower energy costs made possible by shifting power usage to night time when rates are lower.

Smaller chillers required for partial ice storage systems-resulting in lower refrigerant charge on site.

Quiet building operation with a full ice storage system-towers and chillers turned off during the day.

Zero water consumption when Thermal Ice Storage is combined with air-cooled chillers.

1
Water Efficiency
Credit Title LEED LEED LEED EVAPCO Product
Category NC for Core & Contribution
Schools Shell

WE Credit 4 Process Water Use NA 1 Point NA EVAPCO Thermal Ice


Reduction Storage with Extra-Pak Ice
Coils and Air Cooled
Chillers.1

Energy & Atmosphere


EA Credit 1 Optimize Energy 1-19 Points 1-19 Points 3-21 Points EVAPCO Thermal Ice
Performance Storage with Extra-Pak Ice
Coils help earn credits in
this category by reducing
energy costs ice is made
during off-peak power rates.2

EA Credit 4 Enhanced Refrigerant 2 Points 1 Point 2 Points Partial ice storage systems
Management utilize 40% smaller chillers
compared to conventional
chilled water plants,
therefore holding a smaller
refrigerant charge.3

Indoor Environmental Quality-Schools Only


IEQ Prerequisite 3 Minimum Acoustical N/A Required N/A Design a full storage system
Performance to provide chilled water
during school hours and
special events, allowing the
school to turn off their
chillers and cooling towers.4

IEQ Credit 9 Enhanced Acoustical N/A 1 Point N/A Design a full storage system
Performance to provide chilled water
during school hours and
special events, allowing the
school to turn off their
chillers and cooling towers.4

Innovation in Design
ID Credit 1 Innovation in Design 1-5 Points 1-4 Points 1-5 Points Thermal Ice Storage
reduces carbon emissions,
peak demand and the need
for new power plants.5

2
Foot Notes:
1. EVAPCO Thermal Ice Storage Systems that utilize air cooled chillers to build ice will reduce
water and energy used for air conditioning schools. If the design consultant prefers to use air-
cooled chillers, Thermal Ice Storage will provide the end-user, not only with significant water
savings, but with incremental energy savings when compared to a conventional system design
with air cooled chillers. Energy is saved by operating the chiller at night to build ice when dry
bulb temperatures are typically 20F to 30F lower than during the day.

2. The primary benefit of thermal storage is its ability to substantially reduce total operating costs,
particularly for systems using electricity as the primary energy source. Thermal storage systems reduce
the demand for expensive on-peak electric power, substituting less expensive nighttime power to do the
same job. ASHRAE Handbook-2008 HVAC Systems and Equipment

To receive Energy & Atmosphere points in the Optimize Energy Performance credit category,
LEED guidelines specify increasing percentages of energy cost savings in the proposed building
design when compared to a baseline building. For an Optimize Energy credit, the HVAC system
design must show a 12% energy cost savings for new buildings and an 8% energy cost savings for
existing buildings, using the performance rating method in Appendix G of ASHRAE Standard
90.1-2007. This energy cost savings calculation must be supported using a computer simulation
model such as E-Quest, DOE-2, Visual DOE-4 or DOE Energy Plus.

For example, Figure 1 below is a current rate graph (September 2009) for Southern California
Edison (SCE) using the Real Time Pricing (RTP-2) schedule for customers with a demand greater
than 500kW. On days defined as Very Hot Summer Weekday (91F to 94 F day time
temperature), the average cost of electricity is 42.4 cents/kWh. However, on those same days
the average night time cost of electricity is 5.6 cents/kWh. a 7.5 to 1 energy cost
differential!

Data for Graph Courtesy of Southern California Edison

Figure 1- Typical Rate Structure Beneficial to Thermal Ice Storage

3
2 continued)
Thermal ice storage reduces peak electrical cost therefore reducing the overall electric cost for
the entire building. This electrical cost saving is recognized by the USGBC and the LEED rating
system. Energy and Atmosphere Credit 1 has up to 21 points available for energy cost saving
strategies based on the energy cost budget method as defined by ASHRAE 90.1.

Energy and Atmosphere, Optimize Energy Performance Credit 1

Figure 2

There are other tangible material cost and energy saving benefits of a Thermal
Ice Storage system. For example, an ice storage system design using chilled water
at 36F and an 18F delta t compared to a standard chiller system with a 45F
chilled water temperature and 10F delta t, will have smaller pumps, piping, air
handling cooling coils and ductwork!

4
3. Ice storage systems may be sized for full or partial storage. A partial storage system is
defined as A cool storage sizing strategy in which only a portion of the on-peak cooling
load is met from thermal storage, with the rest being met by operating the chilling
equipment. (ASHRAE-2008 HVAC Systems and Equipment Chapter 50 Thermal
Storage).

A partial storage system will typically require a chiller that is 10-40% smaller in size than
a conventional chilled water system. Smaller chillers equate to lower refrigerant
charges, resulting in less impact to the environment from potential leakage during the
operating span of the equipment.

4. In another LEED for Schools strategy, using a full storage ice system sized for
complete on-peak cooling capacity would allow a school to run silent during the day or
special off hour event by melting ice without turning on noisy chillers and condenser
cooling equipment. The only components of the chilled water cooling plant that would
operate during the day are the small chilled water pumps.

Ice storage will enable HVAC system designers to use lower temperature air and water
to size smaller air handlers with reduced HP fan motors and slower duct velocities
resulting in lower sound levels, a requirement of IEQ Prerequisite 3 and IEQ Credit 9
shown below:

IEQ Prerequisite 3

Achieve a maximum background noise level from heating, ventilating and air
conditioning (HVAC) systems in classrooms and other core learning spaces of 45 dBA.

IEQ Credit 9:

Reduce background noise level to 40 dBA or less from heating, ventilating and air
conditioning (HVAC) systems in classrooms and other core learning spaces.

5. Thermal ice storage systems have received positive recognition and LEED points from
the USGBC for its ability to reduce green house gas emissions as a result of lower
energy use at the power plant. It has been well documented that power plants run
more efficiently and electricity is easier to distribute to the grid at night due to lower
ambient temperatures.

In order to receive the LEED Innovation Point, according to the USGBCs latest
Credit Interpretation Request dated 2/23/2005, the ice storage system must be sized to
shift 5% of the total building energy use. In addition, the designer must prove that there
is a reduction in air emissions compared to a standard chilled water system.

5
There are two studies available that quantify air emission reductions by shifting electrical
demand to off peak: one by the California Energy Commission (CEC) completed in
February 1996 (P500-95-005) and a Florida Light and Power (FPL) Study presented at
the 2008 ASHRAE Summer Meeting in Salt Lake City (Seminar 69).

The CEC study evaluated the two largest electricity suppliers in California: Pacific Gas &
Electric (PG&E) and Southern California Edison (SCE). The fuel source energy savings
depends on air conditioning usage patterns, the design and operating strategy for the
thermal storage system-Full or Partial and the source of the electricity supplied (i.e.
Hydro, Coal, Natural Gas or Nuclear).

In the study, Thermal Energy Storage systems in the regions served by PG&E and SCE
shifted 40-80% of the annual kWhs of electricity used for A/C from Day to Night.
The result was an 8 to 43% reduction in source fuel use. Since the fuel source was
reduced, it also has the added benefit of reducing greenhouses gas emissions.

In the FPL study, it was shown in their evaluation of its power and Thermal Energy
Storage (ice and chilled water) plants in their portfolio, that by shifting power to off
peak, it reduced CO2 output by .43 lbs per kWh shifted, based on 500 tons per peak
day per average installation

FPL was able to achieve this level of carbon reduction because Thermal Ice Storage
allowed them to shift from Oil and Gas fired power plants (34% efficient) to more
efficient Combined Cycle plants using natural gas (50% efficient).

The benefits to the environment and energy costs are significant with Thermal Ice
Storage. Incorporate Thermal Ice Storage ice into the chilled water plant design on your
next LEED project.

EVAPCO will present the benefits of ice storage at GreenBuild 2009 in Phoenix. Our Thermal
Ice Storage systems are designed for commercial HVAC, industrial cooling and district energy
projects using our Extra-Pak Ice Coils for internal or external melt applications.

EVAPCO Thermal Ice Storage Installation

6
To learn more about EVAPCOs Thermal Ice Storage systems go to
http://www.evapco.com/ice-video.asp to view the Thermal Ice Storage video and to download
our Bulletin 401F-Ice Coils. For information on how to incorporate Thermal Ice Storage into
your new or existing system design contact me at EVAPCO or send an e-mail to
ice@evapco.com.

Keep it Green!

Daryn S. Cline

Senior Manager,
Environmental Technologies

References:
1) Source: ASHRAE Handbook-HVAC Systems and Equipment-2008 Chapter 50 Thermal Storage
2) Source: Department of Energy E-Quest software-free energy evaluation download at: http://www.doe2.com/
3) Source: ANSI/ASHRAE 90.1-2007, Energy Standard for Buildings Except Low-Rise Residential Buildings
4) Source: USGBCs LEEDv3 http://www.usgbc.org/DisplayPage.aspx?CMSPageID=1970
5) Source: Southern California Edison RTP-2 Rate Structure
6) Source: Source Energy & Environmental Impacts of Thermal Energy Storage, California Energy Commission (CEC),
P500-95-005, Feb 1996.
7) Source: FPL Study 2008 ASHRAE Summer Meeting in Salt Lake City, UT, Seminar 69.
8) For large scale District Energy applications of Thermal Ice Storage, consult these documents published by the USGBC

District Energy and LEED NC/Schools: http://www.usgbc.org/ShowFile.aspx?DocumentID=4176

Guidance on Combined Heat and Power: http://www.usgbc.org/ShowFile.aspx?DocumentID=1354

LEED NC Guide for Multiple Buildings: http://www.usgbc.org/ShowFile.aspx?DocumentID=1097

You might also like