Item Details Status Responsible


No. Person
a. Target Accomplishment for the To presided by Planning every Monday, 2:00 HFFestijo
Week p.m. in PWTP2 office conference room 1

b. Work Inspection Request To prepared by Operation


No WIR, no work RUIquina RCBC, Pipes
THartmann Excavation, Installation,
Pouring and others
NRReyes Sheet Piling, Pile Hacking
Trevi Bored Piling

c. Drawing To separate per building GLCaete


To print in A1 with drawing rack
To send advance copy of Control Room to
NRReyes, Surveyor, Trevi

d. Chipping of Box Culvert To finished tonight Jan. 6, 2017 if chisels MMDeocareza


delivered

e. RCBC Completion RUIquina


Clearance 25 mm on both sides THartmann
NRReyes
Outflow Target Mar. 12, 2017
Inflow Target Mar. 22, 2017
Removal of Temporary Target Mar. 29, 2017
Drain Pipe
f. Veteran Survey Engineer To request RINunog or RGElaydo WRGozun

g. Error in Elevation To be charged against ATCabanilla ZSDelaCruz


2 to 3 cm of Installed
Ground Beam on BAF

60 cm Concrete Sheet
Pile at Esporlas

h. Bored Piling Works 9 workable area


Trevi will charge Frey-Fil for delay
Mobilize Mar. 20, 2017 on their other
project

i. Removal of Diversionary Pipe Target Mar. 22, 2017

j. Lifting on PNR Area To proceed, just dont touch the rail road or THartmann
9:00 p.m. after the train passed
No operator at night shift EEDiaz
Page | 1
Minutes of Meeting Planning Reference No.
PWTP2-WM-MMP-0001
Date : March 6, 2017 2:00 p.m.
Venue : Putatan Site Office

k. Sequence of Panel Filing Informed CSDeJesus HFFestijo

l. Leaning on Concrete Sheet Pile Corrected RBDeolosReye


To collect in billing next week s

m. Retaining Wall and Box Culvert To submit Mar. 6, 2017 ECManansala


Design

n. Sludge Structural Design As good as approved ECManansala

o. Pouring requests to be For proper dissemination of information and for All site
submitted to batching plant record purposes on the consumption of engineers/ QC
prior to delivery of concrete. materials
Meeting adjourned 4:00 p.m.