You are on page 1of 17

Dashboard Campus based Instruction Non-Specific Programs

2016-17 Semester 1 S1-16_ETZC413 General EC1 - Quiz 1

Started on Friday, 2 September 2016, 9:27 PM


State Finished
Completed on Friday, 2 September 2016, 11:00 PM
Time taken 1 hour 33 mins
Marks 25.00/25.00
Grade 5.00 out of 5.00 (100%)

Question 1
1. Early price advantage can be get in the market due to __________.
Correct

Mark 1.00 out of


1.00 Select one:

Quality of product

All of the above

Rapid development of product

Early launching of the product

Your answer is correct.


The correct answer is:
Early launching of the product
Question 2 __________ type of design deals with improving the appeal of a
Correct product to the human senses, especially its visual appeal.

Mark 1.00 out of


Select one:
1.00
Redesign
Industrial design
Original design
Adaptive design

Your answer is correct.


The correct answer is: Industrial design

Question 3
1. Design team adapts a known solution to satisfy a different need to
Correct produce a novel application is called __________ design.
Mark 1.00 out of
1.00

Select one:
Variant design
Redesign
Original design
Adaptive design

Your answer is correct.


The correct answer is: Adaptive design
Question 4
1. Creativity, Complexity, Choice and __________ are the four Cs of
Correct design.
Mark 1.00 out of
1.00

Select one:
Care
Control
Compromise
None of the above

Your answer is correct.


The correct answer is: Compromise

Question 5
1. The ________________ is a document that contains all of the facts
Correct related to the outcome of the product development.
Mark 1.00 out of
1.00

Select one:

Benchmarking

Reverse engineering

Product development specification

Quality Function Deployment

Your answer is correct.


The correct answer is:
Product development specification
Question 6
1. A highly innovative design is called as ___________.
Correct

Mark 1.00 out of


1.00 Select one:
Original design
Adaptive design
Redesign
Variant design

Your answer is correct.


The correct answer is: Original design

Question 7
1. ______________ of the product development where knowledge of
Correct the product and its capabilities has reached an increasing number of
Mark 1.00 out of customers and sales growth accelerates.
1.00

Select one:

Growth stage

All of the above

Decline stage

Maturity stage

Your answer is correct.


The correct answer is:
Growth stage
Question 8
1. Phase 3 of stage gate development process indicates ___________.
Correct

Mark 1.00 out of


1.00 Select one:

Detail Design

All of the above

Concept Development

Planning before approval

Your answer is correct.


The correct answer is:
Detail Design

Question 9
1. Computer controlled Universal Testing Machine (UTM) can be
Correct developed by using __________ type of product development
Mark 1.00 out of model.
1.00

Select one:

Spiral product development model

Stage gate development model

Hybrid product development model

None of the above

Your answer is correct.


The correct answer is:
Hybrid product development model
Question 10
1. The ____________ engineering characteristics from the House of
Correct Quality are either constraints or design variables whose values can
Mark 1.00 out of be used as decision-making criteria for evaluating candidate
1.00 designs.

Select one:

All rankings

None of the above

Highest-ranking

Lowest ranking

Your answer is correct.


The correct answer is:
Highest-ranking
Question 11
1. __________ of the product development is widely accepted and
Correct sales are stable and are growing at the same rate as the economy as
Mark 1.00 out of a whole.
1.00

Select one:

All of the above

Growth stage

Decline stage

Maturity stage

Your answer is correct.


The correct answer is:
Maturity stage
Question 12
1. A __________is a type of diagram that represents an algorithm,
Correct workflow or process, showing the steps as boxes of various kinds,
Mark 1.00 out of and their order by connecting them with arrows.
1.00

Select one:

Flowchart

All of the above

Gantt chart

Pareto Chart

Your answer is correct.


The correct answer is:
Flowchart
Question 13 Write the sequence of Kolbs model.
Correct
Select one:
Mark 1.00 out of
1.00
Reflective observation, Abstract hypothesis and
conceptualization, Concrete experience, Active experimentation

Concrete experience, Reflective observation, Active


experimentation, Abstract hypothesis and conceptualization

Abstract hypothesis and conceptualization, Active


experimentation, Concrete experience, Reflective observation

Concrete experience, Reflective observation, Abstract


hypothesis and conceptualization, Active experimentation

Your answer is correct.


The correct answer is:
Concrete experience, Reflective observation, Abstract hypothesis
and conceptualization, Active experimentation
Question 14
1. In the ___________the project links are stronger than the functional
Correct links.
Mark 1.00 out of
1.00

Select one:

Project Organization

Lightweight project organization

Heavyweight matrix organization

Functional Organization

Your answer is correct.


The correct answer is:
Heavyweight matrix organization
Question 15
1. _________________helps to identify the engineering
Correct characteristics that are the most important to fulfilling the essential
Mark 1.00 out of customer requirement.
1.00

Select one:

Reverse engineering

Benchmarking

Product development specification

House of Quality

Your answer is correct.


The correct answer is:
House of Quality
Question 16
1. _______________ is a tool used to divide a project into
Correct manageable segments to ensure that the complete scope of work is
Mark 1.00 out of understood.
1.00

Select one:
How-how diagram

Flow chart

Gantt chart

Cause and effect diagram

Your answer is correct.


The correct answer is:
Gantt chart

Question 17
1. The ____________ technique is suitable to highlight the most
Correct important among a (typically large) set of factors.
Mark 1.00 out of
1.00

Select one:

Pareto Chart

Gantt chart

Critical path method

Cause and effect diagram

Your answer is correct.


The correct answer is:
Pareto Chart
Question 18
1. _________________is a planning and team problem-solving tool
Correct that has been adopted by a wide variety of companies as the tool of
Mark 1.00 out of choice for focusing a design teams attention on satisfying customer
1.00 needs throughout the product development process.

Select one:

Reverse engineering

Product development specification

Quality Function Deployment

Benchmarking

Your answer is correct.


The correct answer is: Quality Function Deployment

Question 19
1. The _______________ is a person trained in group dynamics who
Correct assists the leader and the team in achieving its objectives.
Mark 1.00 out of
1.00

Select one:

Team leader

Team facilitator

Team sponsor

Team member

Your answer is correct.


The correct answer is:
Team facilitator
Question 20
1. Phase 1 of stage gate development process indicates ___________.
Correct

Mark 1.00 out of


1.00 Select one:

Planning before approval

All of the above

Detail Design

Concept Development

Your answer is correct.


The correct answer is:
Concept Development

Question 21
1. In the ___________the functional links are stronger than the project
Correct links.
Mark 1.00 out of
1.00

Select one:

Functional Organization

Heavyweight matrix organization

Lightweight project organization

Project Organization

Your answer is correct.


The correct answer is:
Lightweight project organization
Question 22
1. A ___________ is a collection of laws and rules that assists a
Correct government agency in meeting its obligation to protect the general
Mark 1.00 out of welfare by preventing damage to property or injury or loss of life to
1.00 persons.

Select one:

Patent

Standard

Code

Copy right

Your answer is correct.


The correct answer is:
Code
Question 23
1. Cross-functional teams is the main feature of _____________.
Correct

Mark 1.00 out of


1.00 Select one:

Lightweight project organization

Heavyweight matrix organization

Concurrent engineering

Functional Organization

Your answer is correct.


The correct answer is:
Concurrent engineering

Question 24
1. ________________is a process for measuring a companys
Correct operations against the best practices of companies both inside and
Mark 1.00 out of outside of their industry.
1.00

Select one:

Benchmarking

Reverse engineering

Product development

All of the above

Your answer is correct.


The correct answer is:
Benchmarking
Question 25
1. The ______________ is a graphical network diagram that focuses
Correct on identifying the potential bottlenecks in a project.
Mark 1.00 out of
1.00

Select one:

Gantt chart

Cause and effect diagram

Flow chart

Critical path method

Your answer is correct.


The correct answer is: Critical path method

You might also like