You are on page 1of 3

Innovative Connections

By Bree Renz

ConXtechs systemized approach to steel construction streamlines and transforms


traditional design and construction processes.

C
Terrance Reimer

onXtech is a systemized ap- concrete, or steel-framed methods. The SMRSF joint assembly is com-
proach to steel construction Simmons originally selected concrete prised of four inner and four outer col-
that encompasses a suite for his concept but found that formwork lar plates. Each of the inner collar plates
of standardized structural costs and lack of architectural exibility is machined to include a male dovetail
components, including bolt- made steel a more practical solution. and is welded to each face of the HSS 8x8
less base plates, an exterior wall panel By January 2001, Simmons had de- column at oor to oor increments. Each
system, a stair system, a rooftop davit veloped several new concepts for a steel outer collar plate is machined to include
system, and a concrete oor system. moment space frame using a self-align- a female dovetail slot contoured to the in-
ConXCAD, a parametric modeling ing, gravity stabilized joint that required verse shape of the male projection on the
software suite, allows architects to easily no eld welding. He collaborated with inner collar plate. The outer collar plate
adjust structural grid dimensions, even Walid Naja, S.E., to further develop and is mitered and drilled along the exterior
late in the design process. rene the Simmons Moment Resisting edges to receive diagonal bolts. Outer
Founder Robert J. Simmons had long Space Frame (SMRSF), a bolted collar collar plates are robotically welded to the
envisioned a concept that would stream- system for interconnecting columns and ends of the 12 wide-ange beams.
line traditional building processes. He beams. Field assembly is simple: drop one
wanted to create a building system that Structural analysis by Constantine beam/outer collar plate assembly over
would enable mass customization of high Shuhaibar, Ph.D., led to the use of the the male projection on the inner collar
quality, mid- to high-rise residential build- RBS (Reduced Beam Section) concept as plate assemblies on each of the four faces
ings and that would be faster and more an energy dissipating component to en- of the HSS 88 column. Once the beam/
cost effective than conventional wood, sure the SMRSF qualied as a special mo- outer collar plate assemblies have been
ment frame under the latest FEMA and located on each face of the column, high
AISC provisions. strength bolts are inserted into the di-
When it became clear a building com- agonal holes in the adjoining outer collar
prised of all SMRSF joints would be cost plates and pre-tensioned to form a rigid
prohibitive, Walid suggested using a moment collar assembly that surrounds
gravity connection for the perimeter of the column.
the structure, Simmons said. Simmons The ConX gravity connection is plasma
designed a simple drop and click self- cut with a simple ange cope and hook in
aligning gravity stabilized connection the web of the beam that drops into a re-
that could be utilized around a buildings ceptacle piece on the HSS 44 column and
perimeter, known as the ConX Gravity is later bolted. Similar to the SMRSF full
Joint. moment resisting connection, the grav-
ity connection is self-aligning and gravity
Structural Frame stabilized.
ConXtech reduces the structural frame ConXtechs interlocking joints drasti-
to a few common components: HSS 88 cally reduce erection time, site generated
and HSS 44 columns, 12 wide-ange waste, and overall risk because all compo-
The Simmons Moment Resisting Space Frame beams, and two jointsthe SMRSF full nents are fabricated in a highly automated
connection is integral to the ConXtech structur- moment joint and the ConX Gravity factory environment. In the eld, iron
al framing system. (US patent No. 6,837,016. Joint. workers simply drop and click beams
Other patents pending.)

August 2005 Modern Steel Construction


to columns, wall panels to the building
exterior, and stair system assemblies into
place. The connections are bolted only af-
ter the oors are in place.

Seismic Advantages
In high seismic zones, the ConXtech
system allows for much taller buildings
than could be constructed in wood and
can have substantial design, time, and
cost advantages over concrete or conven-
tional steel.

Terrance Reimer
The SMRSF joint has been subject to ex-
tensive in-house testing, as well as 17 full-
scale tests conducted at the University
of Arizonas seismic testing laboratory. It
Day 1 of erection of Building 1 at Santana Row (see sidebar). ConXtechs interlocking joints
has also been scrutinized by engineering drastically reduce erection time.
experts through peer reviews required by
the cities of San Francisco, San Jose, and dance with the 2002 AISC Seismic Provi- blies are manufactured at the companys
Palo Alto. sions, said Raymond Kitasoe, P.E., ConX- facility in Hayward, CA. Key to manu-
The panel determined that the SMRSF techs vice president of engineering. We facturing is ConXCAD software, which
frame system qualied as an alternative to were extremely fortunate to have world integrates the design and manufacturing
the Steel Special Moment Resisting frame class experts peer review the system and process by immediately reecting dimen-
system contained in the 1997 Uniform serve as a seismic advisory committee. sional modications on the architects
Building Code and also is pre-qualied for desktop in the manufacturing output
use as a fully restrained, Special Moment Manufacturing the System without the need for manual data re-entry
Resistant Framing connection in accor- All ConXtech components and assem- or updating shop drawings. ConXCAD

ConXtech Debuts: Santana Row


In August 2002, the residential core of the Row began in late April 2004. The struc- original plans. Using the ConXtech system,
nearly complete mixed-use development tures were completed by November 2004. A the Santana Row buildings were complet-
Santana Row, in San Jose, CA, was devastat- total of seven wood-framed buildings were ed under budget and over a year ahead of
ed by a 13 alarm re. The highly anticipated replaced by only three steel-framed build- schedule.
project was just weeks from celebrating the ings with four residential levels above the ConXtechs steel frame system was
grand opening of its high-end retail compo- original four parking levels. quickly erected at Santana Row directly
nent. Five acres of wood-framed, three-story With steel, the fuel-load was drastically above a bustling outdoor dining and shop-
townhouse style apartmentsatop four lev- reduced on the podium, appeasing the San ping area. Because construction with the
els of retail and parking went up in ames Jose Fire Department. Steel also made it system generates little noise, site generated
in a matter of hours. possible to build fewer structures higher, waste, or disruption, the system provided
Robert J. Simmons concrete rm had leaving ample space for a clubhouse and an advantage over conventional methods in
initially placed all of the structural concrete at swimming pool that were not part of the the demanding urban environment.
the Santana Row site on a design-build basis.
As plans to rebuild what had been destroyed
by re progressed, Simmons was tapped to
explore the feasibility of replacing the wood
structures that had burned with the edgling
steel-framed ConXtech system.
We were not quite ready to go prime
time with the system at that point, Sim-
mons said. In fact, we hadnt even gured
out exactly how or where we were going to
manufacture.
Simmons accelerated plans for his manu-
facturing facility. It was a leap of faith on
Courtesy MBH Architects

both the owners part, as well as our own,


he said.
Within three months of getting the green
light, ConXtech was operational and produc-
ing its rst ConX components.
Assembly of structural steel at Santana

August 2005 Modern Steel Construction


imports AutoCAD-based architectural on a suite of manufactured assemblies
les and converts that data to manufac- which are sequentially delivered to the
turing code. In fact, the last three ConX- building site for integration into the
tech buildings erected were effectively building. Components include;
manufactured and assembled without ConXoorComprised of a corru-
any shop, fabrication, or erection draw- gated metal deck and concrete ll,
ings. this oor has similar characteristics as
Precision manufacturing is an abso- oors in a typical concrete building.
lute requirement. Precise t up assures ConXwallPanels which form the
plumb and level buildings. To accom- wall and substrate for the exterior
plish this, ConXtech requires precision envelope of the building, as well as
down to 0.006 in its steel milling, ma- the edge stop for the concrete on the
chining, cutting, and robotic welding metal deck.
cells. Go/no-go xturing is also used ConXstairA factory-manufactured
to check tolerances as the components exit stair system that employs a drop-
make their way through the manufac- in, self-seating gravity connection al-
turing process. With go/no-go xtur- lowing permanent stairs to be erected
ing, as a steel component makes its to the roof of the structure within the
way through the factory from process rst few days of erection.
to process, it will not physically t into ConXdavitAn integrated, re-seal-
the next xture unless it is precisely in able davit receptacle integrated into
tolerance. This ensures that all compo- the top of columns at the perimeter of
nents t as designed when they are as- a building. This receptacle provides
sembled in the eld. a secure and solid base mount for a
Wide-ange beams are cut to specic portable, lightweight davit (outrig-
lengths on a Ficep automated drill/saw ger) that can be used in lieu of scaf-
line. The line also plasma cuts holes for folding during construction. It can
plumbing, HVAC, and electrical and also be used for window washing and
stamps each individual component exterior maintenance over the life of
with a unique address previously gen- the building.
erated and assigned by ConXCAD. The According to the company, the
machine code that controls the CNC system has shown a substantial sav-
machining comes directly from ConX- ings over conventional steel construc-
CAD. tionbetween 25% and 30%. ConXtech
Robotic welding is essential to the performed a cost comparison against
economic viability of the system. ConX- conventional systems that included di-
techs state-of-the-art robotic technol- rect construction costs (materials, labor,
ogy features power sources from The etc.), as well as costs for the additional
Lincoln Electric Company mated with elements ConX offers but that are not
FANUC six-axis robots for welding typically included in traditional steel
the beams and collar pieces together. buildings. The comparison also includ-
Compared to previous semiautomatic ed soft cost savings such as insurance,
welding operations, robotic gas metal construction time, and related carrying
arc welding (GMAW) offers faster trav- costs.
el speeds, higher deposition rates, and ConXtech recently nished its fth
superior-quality nished welds. structure. Although the ConXtech sys-
Semi-automatically welding one col- tem is privately owned, the companys
lar piece to a beam can take 40 minutes. goal is to broadly deploy it by enabling
With two ends to each beam, welding other fabricators, engineers, and erec-
time per beam equals one hour and 20 tors to build with the SMRSF and ConX
minutes. The fully automated systems components. Currently, SMRSF and the
two robotic arms are able to weld col- ConXtech system have not been licensed
lar pieces to both ends of a beam (com- to others, but the company is working
prised of 24 of multi-pass full pen- with several potential licensees.
etration welds and 64 of llet welds)
simultaneously in only ve minutes Bree Renz is President of Breeze Productions
and 30 seconds. in Woodside, CA.

ConX Components
In addition to the ConXframe com-
posed of columns, beams, and connec-
tors, the ConXtech solution is based

August 2005 Modern Steel Construction

You might also like