Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
UG-02 Bangalore Metro Rail Project (East-West Corridor, UG-02) 174 01-Oct-09 30-Jan-13 30-Jan-13, UG-02 Ban

UG-02.01 Start of Project 0 01-Oct-09 01-Oct-09 01-Oct-09, UG-02.01 Start of Project


A1000 Start of Project 0 01-Oct-09 Start of Project
UG-02.02 Key Dates 162 23-Dec-09 30-Jan-13 30-Jan-13, UG-02.02 K
KD01 Preliminary Design Submission 0 23-Dec-09* Preliminary Design Submission
KD02 Submission of Technical Details on Tunnel Ventilation System for BMR/UG-1 Contractor to carry out SES Analysis 0 23-Dec-09* Submission of Technical Details on Tunnel Ventilation System for BMR/UG-1 Contractor to carry out SES Analysis
KD04 Design Co-ordination Submission 0 10-Mar-10* Design Co-ordination Submission
KD05 Submission of Definitive Design 0 31-Mar-10* Submission of Definitive Design
KD07-01 Completion of Basement Rooms to permit access for Power Supply & Traction System Contractor (All Stations except ... 0 18-Jan-12* Completion of Basement Rooms to permit access for Power
KD07-02 Completion of Basement Rooms to permit access for Power Supply & Traction System Contractor (City Railway Station) 0 27-Jun-12* Completion of Basement Rooms to permit a
KD08A-01 Completion of Eqpt Rooms including Cable Ducts from RSS / TSS for Designated Contractor Access (All Stations exce... 0 18-Jan-12* Completion of Eqpt Rooms including Cable Ducts from RSS
KD08A-02 Completion of Equipment Rooms including Cable Ducts from RSS / TSS for Designated Contractor Access (City Railw... 0 27-Jun-12* Completion of Equipment Rooms including C
KD08B-01 Completion of Station Concourse Paid / Free Areas for Designated Contractor Access-AFC (All Stations except CRStn) 0 18-Jan-12* Completion of Station Concourse Paid / Free Areas for Des
KD08B-02 Completion of Station Concourse Paid / Free Areas for Designated Contractor Access-AFC (City Railway Station) 0 27-Jun-12* Completion of Station Concourse Paid / Free
KD08C-01 Completion of Station Basic Structure for Designated Contractor Access-Lifts & Escalators (All Stations except CRStn) 0 18-Jan-12* Completion of Station Basic Structure for Designated Contra
KD08C-02 Completion of Station Basic Structure for Designated Contractor Access-Lifts & Escalators (City Railway Station) 0 27-Jun-12* Completion of Station Basic Structure for De
KD09 Completion of Trackway Basic Structure for Designated Contractor Access 0 27-Jun-12* Completion of Trackway Basic Structure for
KD10 Completion of BMR/UG-2 Works including E&M Works to permit Permanent Power on to Station / Tunnels 0 31-Oct-12* Completion of BMR/UG-2 Work
KD11 Completion of BMR/UG-2 Works E&M Works to permit Integrated Testing & Comissioning, and Handover of Railway E... 0 28-Nov-12* Completion of BMR/UG-2 Wo
KD12 Completion of the Works 0 30-Jan-13* Completion of the Work
KD20 Completion of all Key Dates 0 30-Jan-13* Completion of all Key D
UG-02.03 Works Area Access Dates 58 22-Dec-11 30-Jan-13 30-Jan-13, UG-02.03 W
WAAD01 Access of 5000 m plan area at Majestic for Trackwork Contractor 35 31-May-12 30-Jan-13 Access of 5000 m plan
WAAD02-A Access of 60 m plan area at Central College / Vidhana Soudha / Cricket Stadium for Signalling Telecom Contractor 54 19-Jan-12 30-Jan-13 Access of 60 m plan ar
WAAD02-B Access of 60 m plan area at City Railway for Signalling Telecom Contractor 31 28-Jun-12 30-Jan-13 Access of 60 m plan ar
WAAD03-A Access of 60 m plan area at Central College / Vidhana Soudha / Cricket Stadium for Power Supply Contractor 58 22-Dec-11 30-Jan-13 Access of 60 m plan ar
WAAD03-B Access of 60 m plan area at City Railway for Power Supply Contractor 35 31-May-12 30-Jan-13 Access of 60 m plan ar
WAAD04-A Access of 60 m plan area at Central College / Vidhana Soudha / Cricket Stadium for Lifts & Escalators Contractor 58 22-Dec-11 30-Jan-13 Access of 60 m plan ar
WAAD04-B Access of 60 m plan area at City Railway for Lifts & Escalators Contractor 35 31-May-12 30-Jan-13 Access of 60 m plan ar
WAAD05-A Access of 60 m plan area at Central College / Vidhana Soudha / Cricket Stadium for AFC Contractor 58 22-Dec-11 30-Jan-13 Access of 60 m plan ar
WAAD05-B Access of 60 m plan area at City Railway for AFC Contractor 35 31-May-12 30-Jan-13 Access of 60 m plan ar
UG-02.04 Mobilization & Preliminary Activities 62 01-Oct-09 08-Dec-10 08-Dec-10, UG-02.04 Mobilization & Preliminary Activities
A1180 Procurement, Manufacture & Mobilization of Tunnel Boring Machine (TBM-01) 52 01-Oct-09 29-Sep-10 Procurement, Manufacture & Mobilization of Tunnel Boring Machine (TBM-01)
A1180A Procurement, Manufacture & Mobilization of Tunnel Boring Machine (TBM-02) 62 01-Oct-09 08-Dec-10 Procurement, Manufacture & Mobilization of Tunnel Boring Machine (TBM-02)
A1190 Procurement & Mobilization of Soldier Pile / Anchor / Rock Dowel Work / Earthwork / Gantry Crane / NATM Tunnel Wor... 14 01-Oct-09 06-Jan-10 Procurement & Mobilization of Soldier Pile / Anchor / Rock Dowel Work / Earthwork / Gantry Crane / NATM Tunnel Work Eqpt
A1200 Procurement, Mobilization, Installation & Commissioning of Batching Plant 26 01-Oct-09 31-Mar-10 Procurement, Mobilization, Installation & Commissioning of Batching Plant
A1210 Set-up of Site Office / Field Laboratory 12 01-Oct-09 23-Dec-09 Set-up of Site Office / Field Laboratory
A1220 Establishment of Segment Pre-casting Yard 32 01-Oct-09 12-May-10 Establishment of Segment Pre-casting Yard
A1220A Adjacent Building Condition Survey 12 24-Dec-09 17-Mar-10 Adjacent Building Condition Survey
A1220A10 Installation of Adjacent Building / Ground Settlement Monitoring Instruments 10 18-Mar-10 26-May-10 Installation of Adjacent Building / Ground Settlement Monitoring Instruments
A1230 Completion of Mobilization & Preliminary Activities 0 08-Dec-10 Completion of Mobilization & Preliminary Activities
UG-02.05 Design Work 26 01-Oct-09 31-Mar-10 31-Mar-10, UG-02.05 Design Work

UG-02.05.01 Stations 26 01-Oct-09 31-Mar-10 31-Mar-10, UG-02.05.01 Stations


A1240 Preliminary Design 12 01-Oct-09 23-Dec-09 Preliminary Design
A1250 Design Co-ordination Submission 23 01-Oct-09 10-Mar-10 Design Co-ordination Submission
A1260 Definitive Design 26 01-Oct-09 31-Mar-10 Definitive Design
A1270 Completion of Design for Stations 0 31-Mar-10* Completion of Design for Stations
UG-02.05.02 Cut & Cover 26 01-Oct-09 31-Mar-10 31-Mar-10, UG-02.05.02 Cut & Cover
A1280 Preliminary Design 12 01-Oct-09 23-Dec-09 Preliminary Design

Actual Work Critical Remaining Work Summary Page 1 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!
Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
A1290 Design Co-ordination Submission 23 01-Oct-09 10-Mar-10 Design Co-ordination Submission
A1300 Definitive Design 26 01-Oct-09 31-Mar-10 Definitive Design
A1310 Completion of Design for Cut & Cover 0 31-Mar-10* Completion of Design for Cut & Cover
UG-02.05.03 Tunnel-TBM 26 01-Oct-09 31-Mar-10 31-Mar-10, UG-02.05.03 Tunnel-TBM
A1320 Preliminary Design 12 01-Oct-09 23-Dec-09 Preliminary Design
A1330 Design Co-ordination Submission 23 01-Oct-09 10-Mar-10 Design Co-ordination Submission
A1340 Definitive Design 26 01-Oct-09 31-Mar-10 Definitive Design
A1350 Completion of Design for Tunnel-TBM 0 31-Mar-10* Completion of Design for Tunnel-TBM
UG-02.05.04 Tunnel-NATM 26 01-Oct-09 31-Mar-10 31-Mar-10, UG-02.05.04 Tunnel-NATM
A1360 Preliminary Design 12 01-Oct-09 23-Dec-09 Preliminary Design
A1370 Design Co-ordination Submission 23 01-Oct-09 10-Mar-10 Design Co-ordination Submission
A1380 Definitive Design 26 01-Oct-09 31-Mar-10 Definitive Design
A1390 Completion of Design for Tunnel-NATM 0 31-Mar-10* Completion of Design for Tunnel-NATM
UG-02.05.05 Ramp 26 01-Oct-09 31-Mar-10 31-Mar-10, UG-02.05.05 Ramp
A1400 Preliminary Design 12 01-Oct-09 23-Dec-09 Preliminary Design
A1410 Design Co-ordination Submission 23 01-Oct-09 10-Mar-10 Design Co-ordination Submission
A1420 Definitive Design 26 01-Oct-09 31-Mar-10 Definitive Design
A1430 Completion of Design for Ramp 0 31-Mar-10* Completion of Design for Ramp
UG-02.05.06 E&M Work 26 01-Oct-09 31-Mar-10 31-Mar-10, UG-02.05.06 E&M Work
A1440 Preliminary Design 12 01-Oct-09 23-Dec-09 Preliminary Design
A1440A Technical Details on Tunnel Ventilation System 12 01-Oct-09 23-Dec-09 Technical Details on Tunnel Ventilation System
A1450 Design Co-ordination Submission 23 01-Oct-09 10-Mar-10 Design Co-ordination Submission
A1460 Definitive Design 26 01-Oct-09 31-Mar-10 Definitive Design
A1470 Completion of Design for E&M Works 0 31-Mar-10* Completion of Design for E&M Works
UG-02.05.07 Completion of Design Work 0 31-Mar-10 31-Mar-10 31-Mar-10, UG-02.05.07 Completion of Design Work
A1480 Completion of Design Work 0 31-Mar-10* Completion of Design Work
UG-02.06 Construction Work 172 01-Oct-09 16-Jan-13 16-Jan-13, UG-02.06 Co

UG-02.06.01 West Ramp (Ch. Km: 6+350.000 ~ 6+525.000), L=175.000 m, Cut (D=7.00 m) & Fill (D=5.50 m) 82 21-Jan-10 17-Aug-11 17-Aug-11, UG-02.06.01 West Ramp (Ch. Km: 6+350.000 ~ 6+525.000),
A1490 Traffic Diversion / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion / Utility Diversion
A1500 Soldier Pile with Lagging 12 01-Apr-10 23-Jun-10 Soldier Pile with Lagging
A1510 Excavation & De-watering 5 24-Jun-10 28-Jul-10 Excavation & De-watering
A1520 RCC Structural Work (Base Slab / Wall / Top Slab) 32 29-Jul-10 09-Mar-11 RCC Structural Work (Base Slab / Wall / Top Slab)
A1520A Trackway Concrete 12 10-Mar-11 01-Jun-11 Trackway Concrete
A1530 Backfill 6 10-Mar-11 20-Apr-11 Backfill
A1540 Permanent Road Diversion 10 21-Apr-11 29-Jun-11 Permanent Road Diversion
A1540A Traffic Diversion 1 30-Jun-11 06-Jul-11 Traffic Diversion
A1550 Misc Works 6 07-Jul-11 17-Aug-11 Misc Works
A1560 Completion of West Ramp 0 17-Aug-11 Completion of West Ramp
UG-02.06.02 Cut & Cover-01 (Ch. Km: 6+525.000 ~ 6+630.880), L=105.880 m, D=11.30 m 80 21-Jan-10 03-Aug-11 03-Aug-11, UG-02.06.02 Cut & Cover-01 (Ch. Km: 6+525.000 ~ 6+630.880
A1570 Traffic Diversion / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion / Utility Diversion
A1580 Soldier Pile with Lagging 7 24-Jun-10 11-Aug-10 Soldier Pile with Lagging
A1590 Excavation, De-watering & Decking 8 12-Aug-10 06-Oct-10 Excavation, De-watering & Decking
A1600 RCC Structural Work (Base Slab / Wall / Top Slab) 24 07-Oct-10 23-Mar-11 RCC Structural Work (Base Slab / Wall / Top Slab)
A1600A Trackway Concrete 7 24-Mar-11 11-May-11 Trackway Concrete
A1600A10 Tunnel Ventilation 2 12-May-11 25-May-11 Tunnel Ventilation
A1600A20 Traffic Diversion 1 24-Mar-11 30-Mar-11 Traffic Diversion
A1600A30 Decking Removal 1 31-Mar-11 06-Apr-11 Decking Removal
A1610 Backfill 6 07-Apr-11 18-May-11 Backfill
A1610A Road Restoration 6 19-May-11 29-Jun-11 Road Restoration
A1610A10 Traffic Diversion 1 30-Jun-11 06-Jul-11 Traffic Diversion

Actual Work Critical Remaining Work Summary Page 2 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!
Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
A1620 Misc Works 4 07-Jul-11 03-Aug-11 Misc Works
A1630 Completion of Cut & Cover-01 0 03-Aug-11 Completion of Cut & Cover-01
UG-02.06.03 City Railway Station (Ch. Km: 6+630.880 ~ 6+872.880), L=242.000 m, D=13.00 m) 172 01-Oct-09 16-Jan-13 16-Jan-13, UG-02.06.03
UG-02.06.03.01 Area-A 117 01-Oct-09 28-Dec-11 28-Dec-11, UG-02.06.03.01 Area-A
A1640 Handing Over of Area-A 0 01-Oct-09 Handing Over of Area-A
A1650 Traffic Diversion / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion / Utility Diversion
A1660 Soldier Pile with Lagging on Northern & Southern Side 10 12-Aug-10 20-Oct-10 Soldier Pile with Lagging on Northern & Southern Side
A1670 Excavation (including Open Cut on Southern Side) & De-watering 9 16-Sep-10 17-Nov-10 Excavation (including Open Cut on Southern Side) & De-watering
A1680 RCC Structural Work for Base Slab 4 11-Nov-10 08-Dec-10 RCC Structural Work for Base Slab
A1690 RCC Structural Work for Side Walls of Basement-02 (Platform Level) 3 02-Dec-10 22-Dec-10 RCC Structural Work for Side Walls of Basement-02 (Platform Level)
A1700 RCC Structural Work for Platform 6 24-Mar-11 04-May-11 RCC Structural Work for Platform
A1710 RCC Structural Work for Concourse Level Slab 6 23-Dec-10 02-Feb-11 RCC Structural Work for Concourse Level Slab
A1720 Construction of Equipment Rooms at Platform Level (Power Supply & Traction) 3 27-Jan-11 16-Feb-11 Construction of Equipment Rooms at Platform Level (Power Supply & Traction)
A1720AConstruction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS) 3 27-Jan-11 16-Feb-11 Construction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS)
A1720A10
Construction of Other Rooms at Platform Level 3 27-Jan-11 16-Feb-11 Construction of Other Rooms at Platform Level
A1730 RCC Structural Work for Side Walls of Basement-01 (Concourse Level) 3 27-Jan-11 16-Feb-11 RCC Structural Work for Side Walls of Basement-01 (Concourse Level)
A1740 RCC Structural Work for Top Slab 6 17-Feb-11 30-Mar-11 RCC Structural Work for Top Slab
A1750 Construction of Equipment Rooms at Concourse Level (Power Supply & Traction) 3 24-Mar-11 13-Apr-11 Construction of Equipment Rooms at Concourse Level (Power Supply & Traction)
A1750AConstruction of Equipment Rooms at Concourse Level (Cable Ducts from RSS / TSS) 3 24-Mar-11 13-Apr-11 Construction of Equipment Rooms at Concourse Level (Cable Ducts from RSS / TSS)
A1750A10
Construction of Other Rooms at Concourse Level 3 24-Mar-11 13-Apr-11 Construction of Other Rooms at Concourse Level
A1750BBackfill of Station Area 3 31-Mar-11 20-Apr-11 Backfill of Station Area
A1760 Construction of Entry / Exit Structures 4 21-Apr-11 18-May-11 Construction of Entry / Exit Structures
A1760AConstruction of Vent Shafts, Fireman Access, Emergency Egress Stairs, and Ancillary Building 4 21-Apr-11 18-May-11 Construction of Vent Shafts, Fireman Access, Emergency Egress Stairs, and Ancilla
A1770 Finishing Work 32 19-May-11 28-Dec-11 Finishing Work
A1810 Completion of Area-A 0 28-Dec-11 Completion of Area-A
UG-02.06.03.02 Area-B 123 15-Jul-10 21-Nov-12 21-Nov-12, UG-02.06.03.02 A
00 Handing Over of Area-B 0 15-Jul-10 Handing Over of Area-B
01 Traffic Diversion / Utility Diversion 6 15-Jul-10 25-Aug-10 Traffic Diversion / Utility Diversion
02 TBM (01B & 02B) Receiving Chamber - East End 26 26-Aug-10 23-Feb-11 TBM (01B & 02B) Receiving Chamber - East End
03 Soldier Pile with Lagging on Northern & Southern Side 7 26-Aug-10 13-Oct-10 Soldier Pile with Lagging on Northern & Southern Side
04 Excavation (including Open Cut on Southern Side) & De-watering 6 30-Sep-10 10-Nov-10 Excavation (including Open Cut on Southern Side) & De-watering
05 RCC Structural Work for Base Slab 5 04-Nov-10 08-Dec-10 RCC Structural Work for Base Slab
06 RCC Structural Work for Side Walls of Basement-02 (Platform Level) 5 09-Dec-10 12-Jan-11 RCC Structural Work for Side Walls of Basement-02 (Platform Level)
07 RCC Structural Work for Platform 6 04-Aug-11 14-Sep-11 RCC Structural Work for Platform
08 RCC Structural Work for Concourse Level Slab 6 13-Jan-11 23-Feb-11 RCC Structural Work for Concourse Level Slab
09 Construction of Equipment Rooms at Platform Level (Power Supply & Traction) 12 24-Feb-11 18-May-11 Construction of Equipment Rooms at Platform Level (Power Supply & Traction)
10 Construction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS) 12 24-Feb-11 18-May-11 Construction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS)
11 Construction of Other Rooms at Platform Level 12 24-Feb-11 18-May-11 Construction of Other Rooms at Platform Level
12 RCC Structural Work for Side Walls of Basement-01 (Concourse Level) 5 19-May-11 22-Jun-11 RCC Structural Work for Side Walls of Basement-01 (Concourse Level)
13 RCC Structural Work for Top Slab 6 23-Jun-11 03-Aug-11 RCC Structural Work for Top Slab
14 Construction of Equipment Rooms at Concourse Level (Power Supply & Traction) 12 04-Aug-11 26-Oct-11 Construction of Equipment Rooms at Concourse Level (Power Supp
15 Construction of Equipment Rooms at Concourse Level (Cable Ducts from RSS / TSS) 12 04-Aug-11 26-Oct-11 Construction of Equipment Rooms at Concourse Level (Cable Ducts
16 Construction of Other Rooms at Concourse Level 12 04-Aug-11 26-Oct-11 Construction of Other Rooms at Concourse Level
16A Completion of Works in TBM (01B & 02B) Receiving Chamber - East End 12 12-Apr-12 04-Jul-12 Completion of Works in TBM (01B & 02B) R
16A10 Traffic Diversion 1 04-Aug-11 10-Aug-11 Traffic Diversion
16A20 Decking Removal 1 11-Aug-11 17-Aug-11 Decking Removal
17 Backfill Station Area & Restoration of Cross Road (Decking Area) 6 05-Jul-12 15-Aug-12 Backfill Station Area & Restoration of C
18 Traffic Diversion 1 16-Aug-12 22-Aug-12 Traffic Diversion
19 Construction of Entry / Exit Structures 12 16-Aug-12 07-Nov-12 Construction of Entry / Exit Stru
20 Construction of Vent Shafts, Fireman Access, Emergency Egress Stairs, and Ancillary Building 12 16-Aug-12 07-Nov-12 Construction of Vent Shafts, Fir
21 Finishing Work 21 28-Jun-12 21-Nov-12 Finishing Work

Actual Work Critical Remaining Work Summary Page 3 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!
Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
22 Completion of Area-B 0 21-Nov-12 Completion of Area-B
UG-02.06.03.03 Common Works 70 15-Sep-11 16-Jan-13 16-Jan-13, UG-02.06.03
A1775 Trackway Concrete 9 15-Sep-11 16-Nov-11 Trackway Concrete
A1780 E&M Work (Permanent Power) 52 27-Oct-11 24-Oct-12 E&M Work (Permanent Power)
A1780BE&M Work 52 27-Oct-11 24-Oct-12 E&M Work
A1780CTesting of E&M Works 4 25-Oct-12 21-Nov-12 Testing of E&M Works
A1800 Misc Works 8 22-Nov-12 16-Jan-13 Misc Works
A1910 Completion of Common Works 0 16-Jan-13 Completion of Common
UG-02.06.03.04 Completion of City Railway Station 0 16-Jan-13 16-Jan-13 16-Jan-13, UG-02.06.03
A3350 Completion of City Railway Station 0 16-Jan-13 Completion of City Railw
UG-02.06.04 TBM (Ch. Km: 6+872.880 ~ 7+100.000), L=227.120 m 40 07-Jul-11 11-Apr-12 11-Apr-12, UG-02.06.04 TBM (Ch. Km: 6+872.880
UG-02.06.04.01 TBM-01B (East Bound Tunnel; From Cut & Cover-02 towards City Railway Station) 30 07-Jul-11 01-Feb-12 01-Feb-12, UG-02.06.04.01 TBM-01B (East Bound Tunne
A1820 TBM Assembly, Commissioning & Systems Check 8 07-Jul-11 31-Aug-11 TBM Assembly, Commissioning & Systems Check
A1830 Launch & Initial Drive 4 01-Sep-11 28-Sep-11 Launch & Initial Drive
A1840 Main Drive / Complete Main Drive 6 29-Sep-11 09-Nov-11 Main Drive / Complete Main Drive
A1850 Recover Shield & Back-up 4 10-Nov-11 07-Dec-11 Recover Shield & Back-up
A1860 Misc Works (including Invert Concrete / Walkway) 7 08-Dec-11 25-Jan-12 Misc Works (including Invert Concrete / Walkway)
A1860ATunnel Ventilation 1 26-Jan-12 01-Feb-12 Tunnel Ventilation
A1870 Completion of TBM-01B 0 01-Feb-12 Completion of TBM-01B
UG-02.06.04.02 TBM-02B (West Bound Tunnel; From Cut & Cover-02 towards City Railway Station) 30 15-Sep-11 11-Apr-12 11-Apr-12, UG-02.06.04.02 TBM-02B (West Bound
A1880 TBM Assembly, Commissioning & Systems Check 8 15-Sep-11 09-Nov-11 TBM Assembly, Commissioning & Systems Check
A1890 Launch & Initial Drive 4 10-Nov-11 07-Dec-11 Launch & Initial Drive
A1900 Main Drive / Complete Main Drive 6 08-Dec-11 18-Jan-12 Main Drive / Complete Main Drive
A1920 Recover Shield & Back-up 4 19-Jan-12 15-Feb-12 Recover Shield & Back-up
A1930 Misc Works (including Invert Concrete / Walkway) 7 16-Feb-12 04-Apr-12 Misc Works (including Invert Concrete / Walkway)
A1930ATunnel Ventilation 1 05-Apr-12 11-Apr-12 Tunnel Ventilation
A1940 Completion of TBM-02B 0 11-Apr-12 Completion of TBM-02B
UG-02.06.05 Cut & Cover-02 (Ch. Km: 7+100.000 ~ 7+270.000), L=170.000 m; East Side of Majestic Station 101 21-Jan-10 28-Dec-11 28-Dec-11, UG-02.06.05 Cut & Cover-02 (Ch. Km: 7+100.000
A1950 Traffic Diversion / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion / Utility Diversion
A1960 TBM (01B & 02B) Launching Chamber - West End 26 04-Mar-10 01-Sep-10 TBM (01B & 02B) Launching Chamber - West End
A1970 Soldier Pile with Lagging 11 21-Oct-10 05-Jan-11 Soldier Pile with Lagging
A1980 Excavation, De-watering & Decking 8 06-Jan-11 02-Mar-11 Excavation, De-watering & Decking
A1990 RCC Structural Work (Base Slab / Wall / Top Slab) 24 03-Mar-11 17-Aug-11 RCC Structural Work (Base Slab / Wall / Top Slab)
A1990A Trackway Concrete 11 18-Aug-11 02-Nov-11 Trackway Concrete
A1990A10 Tunnel Ventilation 2 03-Nov-11 16-Nov-11 Tunnel Ventilation
A1990A20 Traffic Diversion 1 18-Aug-11 24-Aug-11 Traffic Diversion
A1990A30 Decking Removal 1 25-Aug-11 31-Aug-11 Decking Removal
A2000 Backfill 6 01-Sep-11 12-Oct-11 Backfill
A2000A Road Restoration 6 13-Oct-11 23-Nov-11 Road Restoration
A2000B Traffic Diversion 1 24-Nov-11 30-Nov-11 Traffic Diversion
A2010 Misc Works 4 01-Dec-11 28-Dec-11 Misc Works
A2020 Completion of Cut & Cover-02 0 28-Dec-11 Completion of Cut & Cover-02
UG-02.06.06 TBM (Ch. Km: 7+691.460 ~ 8+645.760), L=954.300 m 85 30-Sep-10 16-May-12 16-May-12, UG-02.06.06 TBM (Ch. Km: 7+691.
UG-02.06.06.01 TBM-01A (East Bound Tunnel; From Central College Station towards Majestic Station) 64 30-Sep-10 21-Dec-11 21-Dec-11, UG-02.06.06.01 TBM-01A (East Bound Tunnel; Fr
A2030 TBM Assembly, Commissioning & Systems Check 10 30-Sep-10 08-Dec-10 TBM Assembly, Commissioning & Systems Check
A2040 Launch & Initial Drive 4 09-Dec-10 05-Jan-11 Launch & Initial Drive
A2050 Main Drive / Complete Main Drive 23 06-Jan-11 15-Jun-11 Main Drive / Complete Main Drive
A2060 Recover Shield & Back-up 3 16-Jun-11 06-Jul-11 Recover Shield & Back-up
A2070 Misc Works (including Invert Concrete / Walkway) 20 07-Jul-11 23-Nov-11 Misc Works (including Invert Concrete / Walkway)
A2070ATunnel Ventilation 4 24-Nov-11 21-Dec-11 Tunnel Ventilation
A2080 Completion of TBM-01A 0 21-Dec-11 Completion of TBM-01A

Actual Work Critical Remaining Work Summary Page 4 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!
Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
UG-02.06.06.02 TBM-02A (West Bound Tunnel; From Central College Station towards Majestic Station) 64 09-Dec-10 29-Feb-12 29-Feb-12, UG-02.06.06.02 TBM-02A (West Bound Tu
A2090 TBM Assembly, Commissioning & Systems Check 10 09-Dec-10 16-Feb-11 TBM Assembly, Commissioning & Systems Check
A2100 Launch & Initial Drive 4 17-Feb-11 16-Mar-11 Launch & Initial Drive
A2110 Main Drive / Complete Main Drive 23 17-Mar-11 24-Aug-11 Main Drive / Complete Main Drive
A2120 Recover Shield & Back-up 3 25-Aug-11 14-Sep-11 Recover Shield & Back-up
A2130 Misc Works (including Invert Concrete / Walkway) 20 15-Sep-11 01-Feb-12 Misc Works (including Invert Concrete / Walkway)
A2130ATunnel Ventilation 4 02-Feb-12 29-Feb-12 Tunnel Ventilation
A2140 Completion of TBM-02A 0 29-Feb-12 Completion of TBM-02A
UG-02.06.06.03 Cross-Passage with Sump Pit (Ch. Km: 7+999.060) 38 25-Aug-11 16-May-12 16-May-12, UG-02.06.06.03 Cross-Passage wit
001 Traffic Diversion / Utility Diversion 4 25-Aug-11 21-Sep-11 Traffic Diversion / Utility Diversion
002 Installation of Dewatering System 2 22-Sep-11 05-Oct-11 Installation of Dewatering System
003 Temporary Support inside both Tunnels 4 06-Oct-11 02-Nov-11 Temporary Support inside both Tunnels
004 RC Ring Beam 2 06-Oct-11 19-Oct-11 RC Ring Beam
005 Shaft Sinking 6 03-Nov-11 14-Dec-11 Shaft Sinking
006 Excavation of Cross-Passage & Sump Pit 8 15-Dec-11 08-Feb-12 Excavation of Cross-Passage & Sump Pit
007 RC Work for Cross-Passage & Sump Pit 8 09-Feb-12 04-Apr-12 RC Work for Cross-Passage & Sump Pit
008 Dismantling of Temporary Supports in Tunnels 2 05-Apr-12 18-Apr-12 Dismantling of Temporary Supports in Tunnels
009 Backfilling of Shaft & Re-instatement 4 05-Apr-12 02-May-12 Backfilling of Shaft & Re-instatement
010 Misc Works 2 03-May-12 16-May-12 Misc Works
011 Completion of Cross-Passage with Sump Pit (Ch. Km: 7+999.060) 0 16-May-12 Completion of Cross-Passage with Sump Pit (Ch
UG-02.06.06.04 Cross-Passage without Sump Pit (Ch. Km: 8+243.060) 30 22-Sep-11 18-Apr-12 18-Apr-12, UG-02.06.06.04 Cross-Passage withou
012 Traffic Diversion / Utility Diversion 4 22-Sep-11 19-Oct-11 Traffic Diversion / Utility Diversion
013 Installation of Dewatering System 2 20-Oct-11 02-Nov-11 Installation of Dewatering System
014 Temporary Support inside both Tunnels 4 03-Nov-11 30-Nov-11 Temporary Support inside both Tunnels
015 RC Ring Beam 2 03-Nov-11 16-Nov-11 RC Ring Beam
016 Shaft Sinking 6 01-Dec-11 11-Jan-12 Shaft Sinking
017 Excavation of Cross-Passage 4 12-Jan-12 08-Feb-12 Excavation of Cross-Passage
018 RC Work for Cross-Passage 4 09-Feb-12 07-Mar-12 RC Work for Cross-Passage
019 Dismantling of Temporary Supports in Tunnels 2 08-Mar-12 21-Mar-12 Dismantling of Temporary Supports in Tunnels
020 Backfilling of Shaft & Re-instatement 4 08-Mar-12 04-Apr-12 Backfilling of Shaft & Re-instatement
021 Misc Works 2 05-Apr-12 18-Apr-12 Misc Works
022 Completion of Cross-Passage without Sump Pit (Ch. Km: 8+243.060) 0 18-Apr-12 Completion of Cross-Passage without Sump Pit (C
UG-02.06.07 Central College Station (Ch. Km: 8+645.760 ~ 8+917.760), L=272.000 m, D=17.90 m 147 21-Jan-10 14-Nov-12 14-Nov-12, UG-02.06.07 Cent
A2240 Traffic Diversion Phase-I / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion Phase-I / Utility Diversion
A2240A Traffic Diversion Phase-II 1 27-Oct-11 02-Nov-11 Traffic Diversion Phase-II
A2250 TBM (01A & 02A) Launching Chamber - West End 26 04-Mar-10 01-Sep-10 TBM (01A & 02A) Launching Chamber - West End
A2250A NATM (01 & 02) Launching Chamber - East End 26 04-Mar-10 01-Sep-10 NATM (01 & 02) Launching Chamber - East End
A2260 Soldier Pile with Lagging on Northern & Southern Side 16 06-Jan-11 27-Apr-11 Soldier Pile with Lagging on Northern & Southern Side
A2270 Excavation (including Open Cut on Southern Side), De-watering & Decking 15 10-Feb-11 25-May-11 Excavation (including Open Cut on Southern Side), De-watering & Decking
A2280 RCC Structural Work for Base Slab 6 05-May-11 15-Jun-11 RCC Structural Work for Base Slab
A2290 RCC Structural Work for Side Walls of Basement-02 (Platform Level) 5 26-May-11 29-Jun-11 RCC Structural Work for Side Walls of Basement-02 (Platform Level)
A2300 RCC Structural Work for Platform 9 15-Sep-11 16-Nov-11 RCC Structural Work for Platform
A2310 RCC Structural Work for Concourse Level Slab 9 16-Jun-11 17-Aug-11 RCC Structural Work for Concourse Level Slab
A2320 Construction of Equipment Rooms at Platform Level (Power Supply & Traction) 5 21-Jul-11 24-Aug-11 Construction of Equipment Rooms at Platform Level (Power Supply & Trac
A2320A Construction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS) 5 21-Jul-11 24-Aug-11 Construction of Equipment Rooms at Platform Level (Cable Ducts from RS
A2320A10 Construction of Other Rooms at Platform Level 5 21-Jul-11 24-Aug-11 Construction of Other Rooms at Platform Level
A2330 RCC Structural Work for Side Walls of Basement-01 (Concourse Level) 5 21-Jul-11 24-Aug-11 RCC Structural Work for Side Walls of Basement-01 (Concourse Level)
A2340 RCC Structural Work for Top Slab 9 11-Aug-11 12-Oct-11 RCC Structural Work for Top Slab
A2340A Construction of Equipment Rooms at Concourse Level (Power Supply & Traction) 5 15-Sep-11 19-Oct-11 Construction of Equipment Rooms at Concourse Level (Power Supp
A2340A10 Construction of Equipment Rooms at Concourse Level (Cable Ducts from RSS / TSS) 5 15-Sep-11 19-Oct-11 Construction of Equipment Rooms at Concourse Level (Cable Ducts
A2340A20 Construction of Other Rooms at Concourse Level 5 15-Sep-11 19-Oct-11 Construction of Other Rooms at Concourse Level

Actual Work Critical Remaining Work Summary Page 5 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!
Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
A2340A30 Completion of Wroks in TBM (01A & 02A) Launching Chamber - West End 12 01-Mar-12 23-May-12 Completion of Wroks in TBM (01A & 02A) Laun
A2340A40 Completion of Wroks in NATM (01 & 02) Launching Chamber - East End 12 12-Apr-12 04-Jul-12 Completion of Wroks in NATM (01 & 02) La
A2340B Backfill Station Area 4 14-Jun-12 11-Jul-12 Backfill Station Area
A2340B10 Road Restoration 6 12-Jul-12 22-Aug-12 Road Restoration
A2340B20 Traffic Diversion Phase-III 1 23-Aug-12 29-Aug-12 Traffic Diversion Phase-III
A2360 Construction of Entry / Exit Structures - 01 12 18-Aug-11 09-Nov-11 Construction of Entry / Exit Structures - 01
A23600A Construction of Entry / Exit Structures - 02 (Underground) 10 18-Aug-11 26-Oct-11 Construction of Entry / Exit Structures - 02 (Underground)
A23600A0 Construction of Entry / Exit Structures - 02 (Above ground) 2 30-Aug-12 12-Sep-12 Construction of Entry / Exit Structure
A23600A10Construction of Entry / Exit Structures - 03 (Underground) 10 18-Aug-11 26-Oct-11 Construction of Entry / Exit Structures - 03 (Underground)
A23600A10A
Construction of Entry / Exit Structures - 03 (Above ground) 2 27-Oct-11 09-Nov-11 Construction of Entry / Exit Structures - 03 (Above ground)
A23600A20Construction of Entry / Exit Structures - 04 12 18-Aug-11 09-Nov-11 Construction of Entry / Exit Structures - 04
A2360A Construction of VS/VE Shaft, TVS Shaft, Fireman Access (Near E/E Structure - 01) 12 18-Aug-11 09-Nov-11 Construction of VS/VE Shaft, TVS Shaft, Fireman Access (Near E/
A2360A010Construction of VS/VE Shaft, TVS Shaft (Near E/E Structure - 03; Underground) 10 18-Aug-11 26-Oct-11 Construction of VS/VE Shaft, TVS Shaft (Near E/E Structure - 03; U
A2360A020Construction of VS/VE Shaft, TVS Shaft (Near E/E Structure - 03; Above ground) 2 27-Oct-11 09-Nov-11 Construction of VS/VE Shaft, TVS Shaft (Near E/E Structure - 03; A
A2360A030Construction of Ancillary Building (Near E/E Structure - 03; Underground) 12 18-Aug-11 09-Nov-11 Construction of Ancillary Building (Near E/E Structure - 03; Underg
A2360A040Construction of Ancillary Building (Near E/E Structure - 03; Above ground) 8 10-Nov-11 04-Jan-12 Construction of Ancillary Building (Near E/E Structure - 03; Ab
A2360A10 Trackway Concrete 10 17-Nov-11 25-Jan-12 Trackway Concrete
A2370 Finishing / Misc Work 52 18-Aug-11 15-Aug-12 Finishing / Misc Work
A2380 E&M Work (Permanent Power) 52 20-Oct-11 17-Oct-12 E&M Work (Permanent Power)
A2380A E&M Work 52 20-Oct-11 17-Oct-12 E&M Work
A2380B Testing of E&M Works 4 18-Oct-12 14-Nov-12 Testing of E&M Works
A2410 Completion of Central College Station 0 14-Nov-12 Completion of Central College
UG-02.06.08 NATM (Ch. Km: 8+917.760 ~ 9+644.890), L=727.130 m 91 02-Sep-10 30-May-12 30-May-12, UG-02.06.08 NATM (Ch. Km: 8+91
UG-02.06.08.01 NATM-01 (East Bound Tunnel; From Central College Station towards Vidhana Soudha Station) 83 02-Sep-10 04-Apr-12 04-Apr-12, UG-02.06.08.01 NATM-01 (East Bound
A2420 Main Drive (including Excavation, Installation of Water-proofing Membrane, & RCC Inner Lining) 52 02-Sep-10 31-Aug-11 Main Drive (including Excavation, Installation of Water-proofing Membran
A2470 Invert Concrete & Walkway 24 01-Sep-11 15-Feb-12 Invert Concrete & Walkway
A2470ATunnel Ventilation 3 16-Feb-12 07-Mar-12 Tunnel Ventilation
A2480 Misc Works 4 08-Mar-12 04-Apr-12 Misc Works
A2490 Completion of NATM-01 0 04-Apr-12 Completion of NATM-01
UG-02.06.08.02 NATM-02 (West Bound Tunnel; From Central College Station towards Vidhana Soudha Station) 83 09-Sep-10 11-Apr-12 11-Apr-12, UG-02.06.08.02 NATM-02 (West Bound
A3360 Main Drive (including Excavation, Installation of Water-proofing Membrane, & RCC Inner Lining) 52 09-Sep-10 07-Sep-11 Main Drive (including Excavation, Installation of Water-proofing Membran
A3370 Invert Concrete & Walkway 24 08-Sep-11 22-Feb-12 Invert Concrete & Walkway
A3370ATunnel Ventilation 3 23-Feb-12 14-Mar-12 Tunnel Ventilation
A3380 Misc Works 4 15-Mar-12 11-Apr-12 Misc Works
A3380ACompletion of NATM-02 0 11-Apr-12 Completion of NATM-02
UG-02.06.08.03 Cross-Passage with Sump Pit (Ch. Km: 9+300.000) 38 08-Sep-11 30-May-12 30-May-12, UG-02.06.08.03 Cross-Passage w
023 Traffic Diversion / Utility Diversion 4 08-Sep-11 05-Oct-11 Traffic Diversion / Utility Diversion
024 Installation of Dewatering System 2 06-Oct-11 19-Oct-11 Installation of Dewatering System
025 Temporary Support inside both Tunnels 4 20-Oct-11 16-Nov-11 Temporary Support inside both Tunnels
026 RC Ring Beam 2 20-Oct-11 02-Nov-11 RC Ring Beam
027 Shaft Sinking 6 17-Nov-11 28-Dec-11 Shaft Sinking
028 Excavation of Cross-Passage & Sump Pit 8 29-Dec-11 22-Feb-12 Excavation of Cross-Passage & Sump Pit
029 RC Work for Cross-Passage & Sump Pit 8 23-Feb-12 18-Apr-12 RC Work for Cross-Passage & Sump Pit
030 Dismantling of Temporary Supports in Tunnels 2 19-Apr-12 02-May-12 Dismantling of Temporary Supports in Tunnels
031 Backfilling of Shaft & Re-instatement 4 19-Apr-12 16-May-12 Backfilling of Shaft & Re-instatement
032 Misc Works 2 17-May-12 30-May-12 Misc Works
033 Completion of Cross-Passage with Sump Pit (Ch. Km: 9+300.000) 0 30-May-12 Completion of Cross-Passage with Sump Pit (C
UG-02.06.09 Vidhana Soudha Station (Ch. Km: 9+644.890 ~ 9+916.890), L=272.000, D=17.40 m 143 21-Jan-10 17-Oct-12 17-Oct-12, UG-02.06.09 Vidhana
A2630 Traffic Diversion Phase - I / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion Phase - I / Utility Diversion
A2630A NATM (01 & 02) Receiving Chamber - West End 26 15-Sep-11 15-Mar-12 NATM (01 & 02) Receiving Chamber - West End
A2630B NATM (03 & 04) Receiving Chamber - East End 26 15-Sep-11 15-Mar-12 NATM (03 & 04) Receiving Chamber - East End

Actual Work Critical Remaining Work Summary Page 6 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!
Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
A2640 Soldier Pile with Lagging on Northern & Southern End 16 04-Mar-10 23-Jun-10 Soldier Pile with Lagging on Northern & Southern End
A2650 Excavation (including Open Cut on Eastern & Western Side) & De-watering 15 08-Apr-10 21-Jul-10 Excavation (including Open Cut on Eastern & Western Side) & De-watering
A2660 RCC Structural Work for Base Slab 6 01-Jul-10 11-Aug-10 RCC Structural Work for Base Slab
A2670 RCC Structural Work for Side Walls of Basement-02 (Platform Level) 5 22-Jul-10 25-Aug-10 RCC Structural Work for Side Walls of Basement-02 (Platform Level)
A2680 RCC Structural Work for Platform 9 11-Nov-10 12-Jan-11 RCC Structural Work for Platform
A2690 RCC Structural Work for Concourse Level Slab 9 12-Aug-10 13-Oct-10 RCC Structural Work for Concourse Level Slab
A2700A Construction of Equipment Rooms at Platform Level (Power Supply & Traction) 5 16-Sep-10 20-Oct-10 Construction of Equipment Rooms at Platform Level (Power Supply & Traction)
A2700A10 Construction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS) 5 16-Sep-10 20-Oct-10 Construction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS)
A2700A20 Construction of Other Rooms at Platform Level 5 16-Sep-10 20-Oct-10 Construction of Other Rooms at Platform Level
A2710 RCC Structural Work for Side Walls of Basement-01 (Concourse Level) 5 16-Sep-10 20-Oct-10 RCC Structural Work for Side Walls of Basement-01 (Concourse Level)
A2720A RCC Structural Work for Top Slab 9 07-Oct-10 08-Dec-10 RCC Structural Work for Top Slab
A2720A10 Construction of Equipment Rooms at Concourse Level (Power Supply & Traction) 5 11-Nov-10 15-Dec-10 Construction of Equipment Rooms at Concourse Level (Power Supply & Traction)
A2720A20 Construction of Equipment Rooms at Concourse Level (Cable Ducts from RSS / TSS) 5 11-Nov-10 15-Dec-10 Construction of Equipment Rooms at Concourse Level (Cable Ducts from RSS / TSS)
A2720A30 Construction of Other Rooms at Concourse Level 5 11-Nov-10 15-Dec-10 Construction of Other Rooms at Concourse Level
A2720A40 Completion of Works in NATM (01 & 02) Receiving Chamber 12 12-Apr-12 04-Jul-12 Completion of Works in NATM (01 & 02) Re
A2720A50 Completion of Works in NATM (03 & 04) Receiving Chamber 12 12-Apr-12 04-Jul-12 Completion of Works in NATM (03 & 04) Re
A2720A60 Traffic Diversion Phase - II 2 05-Jul-12 18-Jul-12 Traffic Diversion Phase - II
A2720A70 Decking Removal 2 19-Jul-12 01-Aug-12 Decking Removal
A2720B Backfill Station Area 4 02-Aug-12 29-Aug-12 Backfill Station Area
A2720B10 Road Restoration 4 30-Aug-12 26-Sep-12 Road Restoration
A2720B20 Traffic Diversion Phase - III (Final) 1 27-Sep-12 03-Oct-12 Traffic Diversion Phase - III (Final)
A2740A Construction of Entry / Exit Structures - 01 12 14-Oct-10 05-Jan-11 Construction of Entry / Exit Structures - 01
A2740A01 Construction of Entry / Exit Structures - 02 (Underground) 10 14-Oct-10 22-Dec-10 Construction of Entry / Exit Structures - 02 (Underground)
A2740A02 Construction of Entry / Exit Structures - 02 (Above ground) 2 04-Oct-12 17-Oct-12 Construction of Entry / Exit Struct
A2740A03 Construction of Entry / Exit Structures - 03 (Underground) 10 14-Oct-10 22-Dec-10 Construction of Entry / Exit Structures - 03 (Underground)
A2740A04 Construction of Entry / Exit Structures - 03 (Above ground) 2 04-Oct-12 17-Oct-12 Construction of Entry / Exit Struct
A2740A05 Construction of Entry / Exit Structures - 04 12 14-Oct-10 05-Jan-11 Construction of Entry / Exit Structures - 04
A2740A10 Construction of VS/VE Shaft, TVS Shaft, Fireman Access (Near E/E Structure - 01) 12 14-Oct-10 05-Jan-11 Construction of VS/VE Shaft, TVS Shaft, Fireman Access (Near E/E Structure - 01)
A2740A11 Construction of VS/VE Shaft, TVS Shaft (Near E/E Structure - 03) 12 14-Oct-10 05-Jan-11 Construction of VS/VE Shaft, TVS Shaft (Near E/E Structure - 03)
A2740A12 Construction of Ancillary Building (Near E/E Structure - 03) 20 14-Oct-10 02-Mar-11 Construction of Ancillary Building (Near E/E Structure - 03)
A2740A20 Trackway Concrete 10 13-Jan-11 23-Mar-11 Trackway Concrete
A2750 Finishing / Misc Work 52 14-Oct-10 12-Oct-11 Finishing / Misc Work
A2760A E&M Work (Permanent Power) 52 16-Dec-10 14-Dec-11 E&M Work (Permanent Power)
A2760A10 E&M Work 52 16-Dec-10 14-Dec-11 E&M Work
A2760A20 Testing of E&M Works 4 15-Dec-11 11-Jan-12 Testing of E&M Works
A2790 Completion of Vidhana Soudha Station 0 17-Oct-12 Completion of Vidhana Soudha S
UG-02.06.10 NATM (Ch. Km: 9+916.890 ~ 10+395.800), L=478.910 m 58 03-Mar-11 11-Apr-12 11-Apr-12, UG-02.06.10 NATM (Ch. Km: 9+916.89
UG-02.06.10.01 NATM-03 (East Bound Tunnel; From Cricket Stadium Station towards Vidhana Soudha Station) 57 03-Mar-11 04-Apr-12 04-Apr-12, UG-02.06.10.01 NATM-03 (East Bound
A3390 Main Drive (including Excavation, Installation of Water-proofing Membrane, & RCC Inner Lining) 35 03-Mar-11 02-Nov-11 Main Drive (including Excavation, Installation of Water-proofing Me
A3400 Invert Concrete & Walkway 16 03-Nov-11 22-Feb-12 Invert Concrete & Walkway
A3400ATunnel Ventilation 2 23-Feb-12 07-Mar-12 Tunnel Ventilation
A3410 Misc Works 4 08-Mar-12 04-Apr-12 Misc Works
A3410ACompletion of NATM-03 0 04-Apr-12 Completion of NATM-03
UG-02.06.10.02 NATM-04 (West Bound Tunnel; From Cricket Stadium Station towards Vidhana Soudha Station) 57 10-Mar-11 11-Apr-12 11-Apr-12, UG-02.06.10.02 NATM-04 (West Bound
A3420 Main Drive (including Excavation, Installation of Water-proofing Membrane, & RCC Inner Lining) 35 10-Mar-11 09-Nov-11 Main Drive (including Excavation, Installation of Water-proofing Me
A3430 Invert Concrete & Walkway 16 10-Nov-11 29-Feb-12 Invert Concrete & Walkway
A3430ATunnel Ventilation 2 01-Mar-12 14-Mar-12 Tunnel Ventilation
A3440 Misc Works 4 15-Mar-12 11-Apr-12 Misc Works
A3440ACompletion of NATM-04 0 11-Apr-12 Completion of NATM-04
UG-02.06.11 Cricket Stadium Station (Ch. Km: 10+395.800 ~ 10+667.800), L=272.000 m, D=15.40 m 134 21-Jan-10 15-Aug-12 15-Aug-12, UG-02.06.11 Cricket Stadiu
A2960 Traffic Diversion Phase - I / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion Phase - I / Utility Diversion

Actual Work Critical Remaining Work Summary Page 7 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!
Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
A296001 Soldier Pile with Lagging & Decking: Phase - I 4 24-Jun-10 21-Jul-10 Soldier Pile with Lagging & Decking: Phase - I
A29600A Traffic Diversion Phase - II 1 22-Jul-10 28-Jul-10 Traffic Diversion Phase - II
A29600A01Soldier Pile with Lagging & Decking: Phase - II 4 29-Jul-10 25-Aug-10 Soldier Pile with Lagging & Decking: Phase - II
A29600A10Traffic Diversion Phase - III 1 26-Aug-10 01-Sep-10 Traffic Diversion Phase - III
A2960A NATM (03 & 04) Launching Chamber - West End 26 02-Sep-10 02-Mar-11 NATM (03 & 04) Launching Chamber - West End
A2970 Soldier Pile with Lagging on Northern & Southern Side 16 02-Sep-10 22-Dec-10 Soldier Pile with Lagging on Northern & Southern Side
A2980 Excavation (including Open Cut on Northern & Southern Side) & De-watering 15 07-Oct-10 19-Jan-11 Excavation (including Open Cut on Northern & Southern Side) & De-watering
A2990 RCC Structural Work for Base Slab 6 30-Dec-10 09-Feb-11 RCC Structural Work for Base Slab
A3000 RCC Structural Work for Side Walls of Basement-02 (Platform Level) 5 20-Jan-11 23-Feb-11 RCC Structural Work for Side Walls of Basement-02 (Platform Level)
A3010 RCC Structural Work for Platform 9 16-Jun-11 17-Aug-11 RCC Structural Work for Platform
A3020 RCC Structural Work for Concourse Level Slab 9 10-Feb-11 13-Apr-11 RCC Structural Work for Concourse Level Slab
A3030A Construction of Equipment Rooms at Platform Level (Power Supply & Traction) 5 17-Mar-11 20-Apr-11 Construction of Equipment Rooms at Platform Level (Power Supply & Traction)
A3030A10 Construction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS) 5 17-Mar-11 20-Apr-11 Construction of Equipment Rooms at Platform Level (Cable Ducts from RSS / TSS)
A3030A20 Construction of Other Rooms at Platform Level 5 17-Mar-11 20-Apr-11 Construction of Other Rooms at Platform Level
A3040 RCC Structural Work for Side Walls of Basement-01 5 21-Apr-11 25-May-11 RCC Structural Work for Side Walls of Basement-01
A3050 RCC Structural Work for Top Slab 9 12-May-11 13-Jul-11 RCC Structural Work for Top Slab
A3060A Construction of Equipment Rooms at Concourse Level (Power Supply & Traction) 5 16-Jun-11 20-Jul-11 Construction of Equipment Rooms at Concourse Level (Power Supply & Trac
A3060A10 Construction of Equipment Rooms at Concourse Level (Cable Ducts from RSS / TSS) 5 16-Jun-11 20-Jul-11 Construction of Equipment Rooms at Concourse Level (Cable Ducts from RS
A3060A20 Construction of Other Rooms at Concourse Level 5 16-Jun-11 20-Jul-11 Construction of Other Rooms at Concourse Level
A3070A Construction of Entry / Exit Structures 12 14-Jul-11 05-Oct-11 Construction of Entry / Exit Structures
A3070A10 Construction of VS/VE Shaft, Tunnel Vent Shafts, Fireman Access 12 14-Jul-11 05-Oct-11 Construction of VS/VE Shaft, Tunnel Vent Shafts, Fireman Access
A3070A11 Construction of Ancillary Building 20 14-Jul-11 30-Nov-11 Construction of Ancillary Building
A3070A20 Completion of Works in NATM (03 & 04) Launching Chamber 12 12-Apr-12 04-Jul-12 Completion of Works in NATM (03 & 04) La
A3070A30 Trackway Concrete 10 18-Aug-11 26-Oct-11 Trackway Concrete
A3070A40 Traffic Diversion 2 14-Jul-11 27-Jul-11 Traffic Diversion
A3070A50 Decking Removal 2 28-Jul-11 10-Aug-11 Decking Removal
A3070A60 Backfill Station Area 4 14-Jun-12 11-Jul-12 Backfill Station Area
A3070A70 Road Restoration 4 12-Jul-12 08-Aug-12 Road Restoration
A3070A80 Traffic Diversion 1 09-Aug-12 15-Aug-12 Traffic Diversion
A3080 Finishing / Misc Work 52 04-Aug-11 01-Aug-12 Finishing / Misc Work
A3090A E&M Work (Permanent Power) 52 21-Jul-11 18-Jul-12 E&M Work (Permanent Power)
A3090A10 E&M Work 52 21-Jul-11 18-Jul-12 E&M Work
A3090A20 Testing of E&M Works 4 19-Jul-12 15-Aug-12 Testing of E&M Works
A3120 Completion of Cricket Stadium Station 0 15-Aug-12 Completion of Cricket Stadium Station
UG-02.06.12 Cut & Cover-03 (Ch. Km: 10+667.800 ~ 10+925.000), L=257.200 m, D=13.10 m 87 21-Jan-10 21-Sep-11 21-Sep-11, UG-02.06.12 Cut & Cover-03 (Ch. Km: 10+667.800 ~ 10+9
A3130 Traffic Diversion / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion / Utility Diversion
A3140 Soldier Pile with Lagging 17 01-Apr-10 28-Jul-10 Soldier Pile with Lagging
A3150 Excavation, De-watering & Decking 10 29-Jul-10 06-Oct-10 Excavation, De-watering & Decking
A3160 RCC Structural Work (Base Slab / Wall / Top Slab) 21 07-Oct-10 02-Mar-11 RCC Structural Work (Base Slab / Wall / Top Slab)
A3160A Trackway Concrete 17 03-Mar-11 29-Jun-11 Trackway Concrete
A3160A10 Tunnel Ventilation 3 30-Jun-11 20-Jul-11 Tunnel Ventilation
A3160A20 Traffic Diversion 1 03-Mar-11 09-Mar-11 Traffic Diversion
A3160A30 Decking Removal 1 10-Mar-11 16-Mar-11 Decking Removal
A3170 Backfill 9 17-Mar-11 18-May-11 Backfill
A3170A Road Restoration 6 19-May-11 29-Jun-11 Road Restoration
A3170A10 Traffic Diversion 1 30-Jun-11 06-Jul-11 Traffic Diversion
A3180 Misc Works 9 21-Jul-11 21-Sep-11 Misc Works
A3190 Completion of Cut & Cover-03 0 21-Sep-11 Completion of Cut & Cover-03
UG-02.06.13 East Ramp (Ch. Km: 10+925.000 ~ 11+218.315), L=293.320 m, Cut (D=6.70 m) & Fill (D=6.80 m) 103 21-Jan-10 11-Jan-12 11-Jan-12, UG-02.06.13 East Ramp (Ch. Km: 10+925.000 ~
A3200 Traffic Diversion / Utility Diversion 6 21-Jan-10 03-Mar-10 Traffic Diversion / Utility Diversion
A3210 Soldier Pile with Lagging 19 29-Jul-10 08-Dec-10 Soldier Pile with Lagging

Actual Work Critical Remaining Work Summary Page 8 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!
Bangalore Metro Rail Project

East-West Corridor (UG-02)


Activity ID Activity Name Original Start Finish 2010 2011 2012 2013
Duration
S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
A3220 Excavation & De-watering 5 09-Dec-10 12-Jan-11 Excavation & De-watering
A3230 RCC Structural Work (Base Slab / Wall / Top Slab) 22 13-Jan-11 15-Jun-11 RCC Structural Work (Base Slab / Wall / Top Slab)
A3230A Trackway 19 16-Jun-11 26-Oct-11 Trackway
A3240 Backfill 18 16-Jun-11 19-Oct-11 Backfill
A3260 Misc Works 11 27-Oct-11 11-Jan-12 Misc Works
A3270 Completion of East Ramp 0 11-Jan-12 Completion of East Ramp
UG-02.06.14 Completion of Construction Work 0 16-Jan-13 16-Jan-13 16-Jan-13, UG-02.06.14
A3300 Completion of Construction Work 0 16-Jan-13 Completion of Construct
UG-02.07 Integrated Testing & Commissioning 4 22-Nov-12 19-Dec-12 19-Dec-12, UG-02.07 Integ
A3330 Integrated Testing & Commissioning 4 22-Nov-12 19-Dec-12 Integrated Testing & Comm
A3340 Completion of Integrated Testing & Commissioning 0 19-Dec-12 Completion of Integrated Te
UG-02.08 End of Project 0 30-Jan-13 30-Jan-13 30-Jan-13, UG-02.08 E
A3310 End of Project 0 30-Jan-13* End of Project

Actual Work Critical Remaining Work Summary Page 9 of 9 TASK filter: All Activities

Remaining Work Milestone


pdfMachine Primavera Systems, Inc.
A pdf writer that produces quality PDF files with ease!
Produce quality PDF files in seconds and preserve the integrity of your original documents. Compatible across
nearly all Windows platforms, simply open the document you want to convert, click print, select the
Broadgun pdfMachine printer and thats it! Get yours now!

You might also like