EXCAVATIONWORK
Page No 1 of
MEDANTAHOSPITALPROJECT 5
METHOD STATEMENT
FOR
EXCAVATION WORK
CLIENT : MEDANTA
PMC: CUSHMAN & WAKEFIELD INDIA PVT. LTD.
CONTRACTOR :SPCPL
1. Purpose:
The purpose of the procedure is to provide details of safe operating system of
excavation operation for building work foundation, using excavator , construction plant
METHODSTATEMENTFOR
EXCAVATIONWORK
Page No 2 of
MEDANTAHOSPITALPROJECT 5
& manpower to ensured that excavation operation are carried out safe manner .This
procedure will help to ensured a safe & healthy work environment at site at all time.
2. Scope:
4. Reference Code:
5.MachineriesUsed:
Excavation work will be undertaken by Earth Excavator, JCB &
Dumpers. (Manually where & when require).
6.Preinformation:
Ground conditions
underground structures or water courses / Table; and
The location of existing services.
7.ManpowerDeployedforPilingWork.:
i)Supervisor 01 No.
ii) Excavator Operator 02 No.
iii) Dumper Driver-06 nos
8.Procedure:
a) SurveyWork:
1.PrelevelthatisEGLneedstobefinalizedandEGLlevelSheetneddstosignedby
C/W.
2.ExcavationLayoutneedstofinalizedandcheckedbyC/W.
METHODSTATEMENTFOR
EXCAVATIONWORK
Page No 3 of
MEDANTAHOSPITALPROJECT 5
b)DetailProcedure:
Work will be started from the Phase-1 that is from grid by1 and
proceeds towards the grid 26 as per drawing. But before excavation of
Phase 2 we required to keep in mind that phase 2 is pile zone. Before
excavation of this zone the piling work and the maturity time needs to
over. Required slope to be maintained for excavation & the excavated
areas will be protected by hard barricading for safety purpose &
temporary shoring (Barricading) to retain the slide earth (as per below
fig.). After major excavation by Excavator, dressing will be done
manually. At the time of excavation all levels and excavation areas will
be checked by our Engineer and surveyor as per drawing jointly with
C/W. Minimum 600 working Space is required for fixing of
reinforcement & Shuttering.
9.Disposal:
The excavated top soil is sold to the nursery as per green building
norms. Balance earth we shall stock as per instruction of the owner.
10.Dewatering:
All the water that may accumulate in excavations during the progress of
work from rains, subsoil water, springs or any other cause shall be
pumped-out completely by submergible or dewatering pump towards the
outside drain or sump. The basement raft shall be kept dry during
excavation and before the commencement of Brick flat soling and PCC.
G: Safety Requirement: