METHODSTATEMENTFOR

EXCAVATIONWORK
Page No 1 of
MEDANTAHOSPITALPROJECT 5


METHOD STATEMENT
FOR
EXCAVATION WORK

CLIENT : MEDANTA
PMC: CUSHMAN & WAKEFIELD INDIA PVT. LTD.
CONTRACTOR :SPCPL

METHOD STATEMENT NO.: SPCPL/MEDANTA/MS/01/PILE

Re Date Description Prepared Checked By Approved Approved By


v By By (C&W) Client
no
0 22.04. METHOD S Saha A Garg
2017 STATEMENT
FOR
EXCAVATION
WORK

1. Purpose:
The purpose of the procedure is to provide details of safe operating system of
excavation operation for building work foundation, using excavator , construction plant
METHODSTATEMENTFOR
EXCAVATIONWORK
Page No 2 of
MEDANTAHOSPITALPROJECT 5

& manpower to ensured that excavation operation are carried out safe manner .This
procedure will help to ensured a safe & healthy work environment at site at all time.

2. Scope:

In BOQ: 82000 cum


Phase- 1 21000 cum
Phase- 2 29000cum
Phase- 3 24000 cum
Misc - 8000 Cum
3.Role & Responsibility:
The Construction Manager and the Execution Engineer shall be responsible for the
Overall implementation of this method statement.

4. Reference Code:

.1 IS: 2911 (Part 1, Section 2) 2010


.2 IS 456 2000
.3 IS 1786 2008
.4 IS 2720 (Part 5) -1985
.5 Project Specification / Schedule of Rates (SOR)

5.MachineriesUsed:
Excavation work will be undertaken by Earth Excavator, JCB &
Dumpers. (Manually where & when require).

6.Preinformation:
Ground conditions
underground structures or water courses / Table; and
The location of existing services.

This information should be used to during the planning and preparation


for excavation work.

7.ManpowerDeployedforPilingWork.:
i)Supervisor 01 No.
ii) Excavator Operator 02 No.
iii) Dumper Driver-06 nos

8.Procedure:
a) SurveyWork:
1.PrelevelthatisEGLneedstobefinalizedandEGLlevelSheetneddstosignedby
C/W.
2.ExcavationLayoutneedstofinalizedandcheckedbyC/W.
METHODSTATEMENTFOR
EXCAVATIONWORK
Page No 3 of
MEDANTAHOSPITALPROJECT 5

b)DetailProcedure:
Work will be started from the Phase-1 that is from grid by1 and
proceeds towards the grid 26 as per drawing. But before excavation of
Phase 2 we required to keep in mind that phase 2 is pile zone. Before
excavation of this zone the piling work and the maturity time needs to
over. Required slope to be maintained for excavation & the excavated
areas will be protected by hard barricading for safety purpose &
temporary shoring (Barricading) to retain the slide earth (as per below
fig.). After major excavation by Excavator, dressing will be done
manually. At the time of excavation all levels and excavation areas will
be checked by our Engineer and surveyor as per drawing jointly with
C/W. Minimum 600 working Space is required for fixing of
reinforcement & Shuttering.

9.Disposal:
The excavated top soil is sold to the nursery as per green building
norms. Balance earth we shall stock as per instruction of the owner.

10.Dewatering:
All the water that may accumulate in excavations during the progress of
work from rains, subsoil water, springs or any other cause shall be
pumped-out completely by submergible or dewatering pump towards the
outside drain or sump. The basement raft shall be kept dry during
excavation and before the commencement of Brick flat soling and PCC.

11.Health Safety & Environment:


Care shall be taken not to dump the excavated material near the
excavation area and follow the safety norms.
Barricading shall be provided around excavated area and signal light
shall be provided at night hours.
Excavated material shall not be dumped alongside the pit excavated.
Excavated earth shall be disposed - off to designated locations as
mentioned in contract.
Some quantity of excavated earth shall be retained for backfilling if
specified so.
METHODSTATEMENTFOR
EXCAVATIONWORK
Page No 4 of
MEDANTAHOSPITALPROJECT 5

Excavation pit shall be kept free from water by suitable means of


dewatering as and when required.
In case of mechanized excavator with excavators, work shall be
continued till about 150mm above final level. Leveling and dressing shall
be done manually with light compaction.
Educate the workmen through pep-talk meeting.
All persons engaged in job shall wear PPE and the equipments deployed
will be checked by HSE Officer
B. Equipment/ Machineries Safety:-
All equipment should be properly maintained and equipped with
manufacturer-recommended safety devices. Disabling or removing
safety devices is dangerous and should be avoided. All unsafe or
inoperable equipment should be marked as such to prevent further use
of the equipment. All workers should be trained and tested by the
manager or superintendent before operating any equipment. Knowledge
of the hazards associated with specific equipment is the first line of
defence against injury.

G: Safety Requirement:

Equipments & List of Indicate


Tools Equipments, Tools & Tackles Fitness Test & Certification
[Submit Test Needed/TPT
Certificate
before start
Excavator,Dumper/Tripper Checked By P & M Dept. of SPCPL.
of work
wherever
applicable]
Water Pump, Compactor Machines Checked By safety and P & M
Dept. Of SPCPL.

Non- acceptable Control Measures to be ensured against Hazards/Risks


Hazards/Risks
[Attach HIRA] Engineering Administrative PPE
Controls Controls
1. Fall from Height1. Stability of soil to be checked 1. Put sign board and Full body
before erection.
2. Fall of materials alert worker. harness,
3. Struck 2. All materials should be
by 2.Take rest for avoid Safety Helmet,
Falling/ Movinginspected before use. fatigue & sunstroke. fall arrester,
Object 3. Under ground cable or service 3. Work should be Safety
lines should be checked before carried out with goggles, Hand
proper supervision. Gloves, safety
4. Caught In start of work. 4. Trained worker & shoes/gum
Between 4. Maintained Safe procedure for
materials handling. operator should be boot and
5. Slip/Trips deployed. reflective
5. Barricade & Fencing to be
6. Poor access jacket as
ensured at working area.
control required as per
6. Proper illumination should be safety norms.
7. Poor
provided.
housekeeping
METHODSTATEMENTFOR
EXCAVATIONWORK
Page No 5 of
MEDANTAHOSPITALPROJECT 5

8. Improper 7. Proper housekeeping &


illumination suitable approach/access should
9. Fire /explosion be ensured.
10. Improper
guarding
arrangement of
rotating parts
11. under ground
cable/ service
line.
Hazardous
Substances
[Attach MSDS if
required]
Emergency Refer To HSE PLAN
Plan/Procedures

On-site Medical Aid Off-site Medical Aid


Name & contact Ph no-
of First Aider To be decided. Sri Ram Hospital 7781880022
Location of First-Aid centre.
First Aid Box

Roles, Responsibility , Authority & Contact No.


Key Personnel
Mr. Subrata Parui Project In charge
Involved in work
Execution Mr. Binod Pandey Construction
Manager
To be decided Sr. Supervisor
Mr.Bijit Sinha Quality In
Change
To be decided Safely In charge
Assessment on Type Specify Specify
Competency & Qualification/E Medical
Medical Fitness xperience Fitness
[Certificate to be Certification Certification
submitted before needed Needed
start of work)
Fabricator Yes General Health
Gas Cutter & welder, check-up.
Khalasi Gang,
Operator Yes General Health
check-up
Skilled & Semi-skilled worker NA General Health
check-up.
Any other specialist