Professional Documents
Culture Documents
Project
C. I. TARRAGONA
INDEX
1. INTRODUCTION ...................................................................................................... 3
3. CAPACITY ............................................................................................................... 56
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 3 of
Improvements 2022020
1. INTRODUCTION
The purpose of this document is to provide bidders information to realize a Conceptual and
Basic Design to improve DAF performance and biological sludge separation within Waste
Water Treatment Plant of Repsol Petrleo Refinery at Tarragona (Spain). The Plant will be
able to process 300 m3/h of wastewater with a service factor of 365 days per year.
The Waste Water Treatment Plant is designed to treat wastewater coming from Refinery,
two Ethylene Plants and Spent Caustic Treatment Plant in Repsol Petrleo Tarragona Site.
2.2. SCOPE
Project Boundaries Con formato: Fuente: Negrita
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 4 of
Improvements 2022020
a1. DAF
b2. Biological Sludge Separation
The project will have the following phases: Con formato: Espacio Despus: 0 pto
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 5 of
Improvements 2022020
3. CAPACITY
The average wastewater treated wastewater flowrate is 250 m3/h and the design capacity for
the new Cclarifierd will be 300 m3/h.
In order to improve maintenance of the equipments, new Clarifier has to be defined taking
account that current Clarifier or new Clarifier could be out of service. Therefore, the
following cases have to be considered:
Case A: After current Clarifier
Case B: After current Biological Bed:
The sludge recirculation is 210 m3/h (Current pump flow) and the service factor of
24 h/day.
Other options proposed by bidders will be evaluate. Con formato: Sangra: Izquierda: 1
cm
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 6 of
Improvements 2022020
4. WASTEWATER SPECIFICATIONS
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 7 of
Improvements 2022020
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 8 of
Improvements 2022020
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 9 of
Improvements 2022020
5. EFFLUENTS
Other gaseous effluents (at least CO2, SO2, SO3, NOx, and particles) should be reported.
Other effluents (liquid, used catalysts, etc.) and their disposal or treatment, if any, will be
specified by Bidder.
6. DESIGN CRITERIA
STREAM P T TO / FROM
(kg/cm2g) (C)
Feed:
Wastewater to DAF From Flocculation/coagulation
atm 35
Basin
Wastewater to Biological From Biological Bed
atm* 35
Sludge Separation
Products:
Treated Wastewater atm* 35 To final retention basin
Biological Sludge - - To Biological Bed and Purge
* If a new biological sludge separator is required evaluate the need of pumping
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 10 of
Improvements 2022020
8. PLOT PLAN
The new facility will be located close to the existing Biological Bed.
ET-B-452-A-42092-H ET-B-452-A-42092-H
0-0.pdf 0-0 rev1.pdf
After awarding the Basic Engineering Package, as soon as possible (no later than two weeks)
a meeting at Tarragona Refinery will be mandatory to check that the proposed area is
adequate to install new equipment.
9. DOCUMENTATION
Wastewater Temperature:
Temperature
wastewater feedstoo
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 11 of
Improvements 2022020
APPENDIX 1
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 12 of
Improvements 2022020
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 13 of
Improvements 2022020
This water reaches 452 unit through a 16 " line. The 16 line discharges into a settling
solids channels (called simple separators that remove solids) and afterwards flows to the
final basin (retention basin).
1.3 Stormwater:
The clean rainwater are those that are collected in not contaminated areas, such as streets
and buildings of the industrial site, the racks passing pipes, unit gravel areas and tank
bunds.
The rainwater comes through two channels (south and north) to rainwater basin. The
rainwater basin has three outlets: by overflow into the river, from the bottom exit of the
rainwater basin through the final basin (retention basin), and into head basin storage (U-456
basins) in case of water treatment required.
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 14 of
Improvements 2022020
The maximum design capacity of the treatment plant was 300 m3/h.
3 WWTP Systems
3.1 Preatment
Pretreatment of the WWTP consists of a primary de-oiling system (API's) and a secondary
de-oiling (CPIs) currently out of service.
Oil separation takes place in gravimetric tanks of the VOC Abatement Plant (457 unit).
After VOCs removal, the wastewater is sent to the 452 unit via a 10 line. In 452 unit
entrance, there is an automatic valve FV-002 whose mission is to protect the treatment
system. In the case of higher flows to 300 m3/h this valve closes and the water from the U-
457 will overflow into the U-456 basin.
At the entrance of the unit 452, 452-G-17/17-A pump water to the flocculation system.
In DAF unit, the folcs formed during the flocculation reaction are extracted in the surface
and the solids are decanted and send it to Float pits. The water overflows to chemical
oxidation basin.
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 15 of
Improvements 2022020
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 16 of
Improvements 2022020
escape from WWTP are retained. In case of contamination of any input current,
hydrocarbons remain on the surface and it will be close the outfall to the sea.
In the retention the entrance and the exit channel basin are located at the same side. The
basin is divided in two parts to ensure the resident time required. The rainwater, the waste
water treated coming from the clarifier, the cooling water and water coming from the
security basin enter into the entrance channel.
The chemical oxidation basin overflows to the retention basin.
The main equipment design data of the unit wastewater treatment are listed below:
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 17 of
Improvements 2022020
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 18 of
Improvements 2022020
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx
PROJECT. DAF Performance and Biological Sludge Separation Page 19 of
Improvements 2022020
Once the sludge is thickened, it is pumped (452-G-3-A / 4 and G-25) to TRADEBE plant.
Thickened biological sludge is sent to the suction pumps 452-G-3/4-A. The water produced
in the thickener overflow to the biological reactor II.
The centrifuged sludge raft is out of service. This can act as a sludge storage raft before
shipment to the plant TRADEBE. The raft can receive sludge from 452-G-3/3-A and 452-
G-4/4-A and can pump sludge to TRADEBE (452-G-25).
Annex I PO1 Process Design Basis DAF and biological Sludge Separation rev 3PO1 Process Design Basis DAF and biological
Sludge Separation rev 1.docx