Professional Documents
Culture Documents
Introduction
Why is Production Planning Important?
The goal of production planning is to support the manufacturing process by determining the
resources and sequence of operations required to build a product. During the production planning
process, a company generates the detailed production schedule required to build a product. The
production schedule must be tightly linked with a detailed materials plan to ensure the raw
materials are available when needed. The planning process also communicates required
materials to the purchasing department.
Ensuring machines and materials are available for production when needed
Maximizing throughput and utilization of factory resources
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
How is a Production Planning Integrated with Supply Chain Planning?
Production planning is one component of the supply chain planning process. Supply chain
planning is an integrated process that allows companies to plan and integrate the supply chain
functions of procurement, manufacturing, and fulfillment.
Demand, supply, production, and fulfillment planning operate as interdependent supply chain
planning functions. The goal is to integrate these processes so that all the plans are synchronized
with one another. Plans generated during one process are used by one or more of the other
processes. In other words, planners need to know:
Specifically, a materials planner may wonder, "What if my suppliers can't deliver to our requested
quantities and timing?" There are many ways to resolve this issue. One viable option is to delay
the production of some of the items until materials are available, and inform fulfillment planning
about the delay in meeting customer requirements. Another option may be to work with
Procurement to determine if the finished goods could be sourced from another vendor.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Objectives
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Introduction to Production Planning
Overview
Once a company has developed demand and supply plans, it must plan how to manufacture the
product. Production planning (sometimes referred to as factory planning) includes two
components:
Production Schedule - Determine the resources required (labor and machines) and the
sequence (time frame) of the manufacturing operations. In some cases, the production
schedule specifies the start times for the different items; it is occasionally referred to as
the start plan.
Materials Plan - Identify the materials needed (raw materials or sub-components) to
meet manufacturing requirements, along with the time and factory floor location where
the material will be needed. This differs in the level of detail from the materials plan
generated during supply planning.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Planning Constraints
Production planning is limited by capacity and materials constraints. For example, a machine can
produce a maximum number of items per hour, or is scheduled to run a set number of times per
week. This differs from supply planning in the level of detail. An example of a supply planning
constraint is the daily production capacity of one line, while an example of a production planning
constraint is the production capacity for one station on the entire manufacturing line. The
production capacity may be stated as either the number of items processed per time unit, or the
processing time required per item.
Similarly, there could be materials constraints that affect production. The materials plan
generated during supply planning considers only key components, while the materials plan
generated during production planning considers all materials required for manufacturing the
products.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Components of Production Planning
Production Scheduling
Materials Planning
Important Note
Many companies conduct production scheduling simultaneously with materials planning. For
simplicity, however, we have explicitly differentiated between production scheduling and materials
planning. Furthermore, depending on the industry, a company could implement one or both
processes.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Planning in Different Industries
Planning emphasis on the different production planning components can vary by industry. For
example, capacity constraints are very important in the semiconductor industry, while materials
planning is very important in the computer industry.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Planning in Different Industries - Semiconductor
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Planning in Different Industries - Computer
In contrast to the semiconductor industry, the computer industry is not capacity constrained at all,
i.e., there is sufficient capacity to meet all customer demand. However, the profit margins for
computer manufacturers are thin, and customers demand customized configurations. Thus,
ensuring that sufficient material is available (without incurring excessive inventory costs) is very
important in this industry. Challenges in the computer industry include:
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Planning in Different Industries - Automotive
The automotive industry is an example in which production scheduling and materials planning are
both very important. Each car requires several thousand parts; therefore, material coordination is
extremely important. At the same time, manufacturers must ensure that assembly lines are
balanced and assembly stations are not over or under-utilized (idle). Some challenges of the
automotive industry are:
Production Flexibility
Every car traveling down an assembly line is different from the preceding or succeeding car.
Despite this, the assembly line must remain in balance to ensure minimal disruptions to
production.
Maintaining Inventory
Due to the large number of parts, manufacturers cannot afford to keep a high inventory of each
part. They must therefore minimize their inventory for parts and ensure availability.
Both production scheduling and materials planning are thus critical in the automotive industry.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Topic Summary
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Scheduling
A Manufacturing Facility
Consider a simple factory that is capable of manufacturing three products, Products A, B, and C.
The factory has four machines, Machines M1, M2, M3, and M4. Furthermore, many different raw
materials (RM1, RM2, RM3, and RM4) are required for manufacturing the products. Click on
Product A, Product B, and Product C to view the routes through the manufacturing facility.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Introduction to Production Scheduling
The master production schedule (MPS) created during supply planning defines what must be
produced in the factory to meet customer demand. The MPS now needs to be converted into a
production schedule that is used to drive manufacturing on the factory floor. The production
schedule will determine the resources required and the sequence in which operations will be
performed on each resource to manufacture the product. The production scheduling process
strives to respect the capacity constraints of each resource and reflect cycle times. This is
inherently a very complex process because planners generate the schedule while considering
dozens of business rules and constraints.
In many cases, a company will have many different products to manufacture and could do so in a
variety of ways. For effective production scheduling, a company must implement key capabilities,
including the ability to:
Production schedulers use the production schedule to drive production through the factory shop
floor. They will usually receive a report that specifies the sequence and start times for each item
to be manufactured during a given day or shift. They may also use specialized software to
evaluate multiple scenarios before making a final decision on the production schedule for the day.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Scheduling Stakeholders and Business Issues
We have established the outputs from and the capabilities required for production scheduling.
During production scheduling, companies strive to:
Maximize throughput
The MPS process during supply planning considers high-level capacity constraints and creates a
daily schedule for production scheduling to follow. The goal of the production scheduling process
is to ensure that manufacturers can produce maximum product using available resources.
Minimize lateness
Orders scheduled in the factory have a due date, i.e., a date prior to which they must be
completed. In many cases, sufficient capacity and/or materials are not available to meet all due
dates. During the detailed scheduling process, manufacturers strive to minimize late orders.
Minimize earliness
Orders scheduled in the factory have a due date, i.e., a date prior to which they must be
completed. In many cases, sufficient capacity and/or materials are not available to meet all due
dates on the exact date specified, and items may be manufactured ahead of that date. Early
completion means incurring undesirable inventory-carrying costs. During the detailed scheduling
process, manufacturers strive to minimize early orders.
Manufacturing uses the output from the production scheduling process to ensure that machines,
labor, and materials are available when required. Fulfillment may use the production schedule as
an input to determine when transportation is needed to move the product from the factory to the
distribution centers and/or customers. Customer service may use the production plan to
determine whether orders will be met on time or late.
Production scheduling is typically performed for one to seven days, and updated daily. Some
advanced companies update their schedules more frequently, e.g., a high-volume discrete
manufacturer has a four-hour scheduling horizon.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Key Inputs, Outputs, and Considerations
Business objectives
Customer prioritization
Supply prioritization
Alternate production routes
The figure illustrates the key inputs and outputs for production scheduling.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Key Outputs - Production Schedule
The production schedule specifies what items are started on which resources at what times. The
schedule considers capacity constraints and manufacturing cycle times while trying to ensure
maximum utilization of resources and maximum throughput of product.
Example
Consider the example of a cookie manufacturer that bakes two types of cookieschocolate chip
(CC) and peanut butter (PB).
The CC cookies are baked at 275 degrees F for one hour, and the PB cookies are baked
at 350 degrees F for one hour.
The company only has one oven in which to bake these cookies.
If the oven is already set at 275 degrees, it requires another 15 minutes for it to heat up
to 350 degrees, whereas if it has been set at 350 degrees, it takes 45 minutes for it to
cool down to 275 degrees (both of these times are analogous to changeover times).
Due to the capacity constraints of the oven, the company can bake a maximum of 15 CC
cookies or 10 PB cookies at one time.
The baker (and hence the oven) works from 7 a.m. to 3:30 p.m.
According to the Cookie Delivery Schedule, the company needs to produce 30 CC
cookies and 50 PB cookies.
Identify the factory resources required - an oven is the only resource that is required.
Understand the manufacturing process/routes - in this case, the process and the
route is very simple. Put the cookies in the oven at the appropriate temperature and bake
for the required time period.
Define the raw materials required to make the cookies - the dough for each type of
cookie is premixed.
Identify the constraints - the constraint for baking cookies is that only one oven is
available from 7 a.m. to 3:30 p.m., and the set-up time to change the temperature from
275 degrees to 350 degrees is 15 minutes, while the set-up time to change the
temperature from 350 degrees to 275 degrees is 45 minutes. The company can bake a
maximum of 15 CC cookies or 10 PB cookies at one time.
Determine when the items are demanded - the schedule of demand for the cookies is
identified in the problem description.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Key Outputs - Production Schedule - continued
There are many ways to go about determining a feasible production schedule. One approach is
trial and errortry a sequence of activities and determine if the resulting sequence satisfies all
the constraints. If it does, you have a solution. If it does not, you then must modify some aspect of
the sequence, and try again until you reach a feasible solution.
Determine which of the following sequences provides a feasible production schedule. Be sure to
consider the Cookie Delivery Schedule and Capacity Constraints. Click the button below to
review the schedule and constraints.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Key Concepts - Production Scheduling Algorithms
Generating a production schedule is extremely difficult, especially in cases where the goods must
be processed on multiple machines and can have multiple routes through the manufacturing
facility. Commonly used methods for solving such scheduling problems include:
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Inputs for Production Scheduling
There are several inputs required for production scheduling. The most common and important
inputs are classified into three typesdemand inputs, supply inputs, and static inputs (inputs that
seldom change).
Demand Inputs
Customer Orders
Orders placed by customers and given top priority for scheduling to ensure that due
dates are met.
Manufacturing Orders
Generated during distribution planning and master production scheduling, and used as
the key input for developing the production schedule.
Stock Orders
Requests to increase inventory (demand) at certain locations. Stock orders are not
customer specific, but placed according to inventory location (e.g., distribution centers)
and are not tied to any specific customers.
Supply Inputs
On-hand Inventory
Inventory of materials currently available; this information is used to determine the net
material requirements.
Scheduled Receipts
Inventory of materials that has been shipped and is en route to the appropriate location;
this information is used to determine the net material requirements.
Static Inputs
Run Rates
The rate at which resources manufacture goods, e.g., a machine may be capable of
manufacturing 30 units of Product A per hour, or 20 units of Product B per hour. Its run
rate would then be 30 units per hour for Product A, and 20 units per hour for Product B.
Cycle Times
The time it takes to manufacture an item.
Set-up Times
Some resources may require an initial set-up time before they can become operational
for production. Set-up time is usually defined in units of time, e.g., 30 minutes or two
hours.
Transfer Times
The amount of time required to move product from one factory resource to another. As
product is moved from one resource to another, there may a time lag between the time
the product is finished being processed by one resource and started on the next
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
resource.
Capacities
The manufacturing capacity of a resource.
Batch Sizes
The number of items that can be simultaneously processed on a resource. There are
numerous resources that can produce many units of a product at the same time. A
conventional oven able to bake several cookies simultaneously is one such example
(e.g., 15 chocolate chip cookies or 10 peanut butter cookies per oven batch).
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Additional Considerations
In developing production schedules, companies may account for additional considerations, such
as:
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Organizational Implications
Currently, many organizations create production schedules manually, e.g., by using spreadsheets,
pegboards, and/or whiteboards. Consequently, they cannot consider all the possible inputs and
constraints. To use and benefit from the production scheduling process, companies must
implement scheduling software that, in turn, leads to fundamental changes in the process,
including:
Centralized Decisions - Often there is a central schedule coordinator who works with
schedulers from each manufacturing line or factory to coordinate all production schedules
and ensure that the business objectives of the organization are met.
Team-based Decisions - Decisions made by the schedulers are team-based, preventing
individual schedulers from making isolated decisions.
Coordinated Decision Support - The schedule coordinator, who provides coordinated
decision support to all schedulers, now coordinates any changes and decisions that must
be made in the production schedules.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Organizational Implications - continued
Such changes to the production scheduling process also lead to several organizational changes
within the company:
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Production Scheduling Example
We will now consider a complex example by taking into account work in progress (WIP) and
alternate routes.
Example
Product B has only one routeprocess on Machine 3 for 30 minutes and then on
Machine 2 for 30 minutes
Product A has two routes; the primary route is to process on Machine 1 for two hours,
and then on Machine 2 for 90 minutes; the alternate route is to process on machine 3 for
three hours, and then on Machine 2 for one hour
We will assume that there are no materials constraints, set-up times, or changeover
times
The figure shows the routes
The factory is required to complete five units of Product B today, and four units of Product A
today. The only available WIP today is one unit of Product B that has completed processing on
Machine 3. The machines are available during the hours of 8 a.m. and 4 p.m. The company's
goals are to maximize resource utilization and product throughput.
Solution Approach
Determine the materials required - The problem states that there are no materials
constraints, but in this case there is one WIP unit of Product B.
Identify the resources required - Machines 1, 2, and 3.
Understand the manufacturing process/routes - In this case, there is a different route
for each product; there is also an alternate route for Product A.
Identify the constraints - The constraints for the machines are the times they are
available (8 a.m. to 4 p.m.).
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Determine when the items are demanded - The schedule of demand for the products is
to complete five units of Product B today, and four units of Product A today.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Production Scheduling Example - continued
There are many ways to go about solving this problem. Select the Sample Solution button to
reveal one feasible solution.
Sample Solution
A sample production schedule for each machine and product is shown in the tables (note that we
have used A1, A2, etc., to differentiate between each unit of the product).
Select the Sample Solution Considerations button to reveal how this solution addresses capacity
and materials constraints and achieves production scheduling objectives.
Although the problem appears to be relatively simple, the solution procedure is very complex; it
may take several minutes, or sometimes hours, for specialized software to generate a good
solution for the typical company that has several products and resources. For this example, note
the following:
Only four units of Product B are manufactured on Machine 3 because one unit was
already a WIP and was netted out to determine the net requirements for the day.
Schedulers consider cycle time for each machine and unit in developing the schedule.
The capacity constraints are satisfied for each resource.
One unit of Product A is manufactured on the alternate route because not enough
capacity is available on the primary route.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
The goal of maximizing factory utilization is met because all the resources are fully
utilized and are not idle at any time.
The goal of maximizing product throughput is met because after completing the required
number of units for Product A, some additional units of Product A are manufactured, and
they will serve as WIP for the subsequent days.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Topic Summary
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Materials Planning
Overview
The materials planning process ensures materials are available at the right time and in the right
factory location to manufacture product. The production schedule is synchronized with the
materials plan and defines the time that each operation on a product is performed, which in turn
defines what materials are needed for operations. The materials plan used during production
planning is therefore more detailed than the materials plan generated during supply planning
(which only defines the day/week on which materials are needed). In contrast, the materials plan
generated during production planning will define the exact time at which the materials are needed
on any given day. Furthermore, the materials plan generated during supply planning considers
only key materials and components, while the materials plan generated during production
planning considers all the required materials.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Introduction to Materials Planning
The detailed production plan sets forth the time at which product production starts and stops on
each resource. As the product moves from one resource to another, it requires additional
materials. The materials plan lists exactly what material is required for the product at each of the
resources. Many companies conduct materials planning simultaneously with production
scheduling.
The key output of this process is a material requirements plan, which is used to pull materials
from suppliers. The materials plan is thus execution-oriented, just like the production schedule,
and serves to:
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Materials Planning - Planning Horizon and Key Capabilities
The materials planning horizon generally depends on the lead-time of materialslonger lead-
time items require a longer planning horizon. A typical company may create their requirements in
daily buckets for two weeks, then weekly buckets for six weeks, and monthly buckets for the
remainder. We will discuss how a company generates requirements for the daily buckets, on
which manufacturers determine what materials to pull from their suppliers. Most organizations
plan for materials based on their daily needs, but some advanced supply chain planning
companies may do so more often.
For effective materials planning, companies must develop key capabilities, including the ability to:
Manage by exception
No planner can possibly manage each part when there are so many parts included in a plan.
Thus, planners manage by exceptionan exception message is created if the supply for a part
does not meet the requirements. The materials planner will then intervene and resolve the
exception.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Materials Planning - Stakeholders and Business Issues
Procurement is the business function that interacts most closely with materials planning, using
the output from materials planning to purchase materials. They may use the long-term materials
plan to negotiate contracts and terms with suppliers, e.g., establish blanket purchase orders, and
then use the detailed materials plan to pull materials against the blanket purchase orders.
Some of the key business issues that companies attempt to address during materials planning
include the ability to:
Minimize backorders. If material is not available when needed, the company may have
to backorder the product, and consequently not meet current demand. A goal of materials
planning is to ensure materials are available to minimize backorders.
Minimize inventory. While a company can always ensure that sufficient material is
available for production by carrying a large inventory, they incur the associated costs of
doing so. Thus, companies try to carry as little inventory as possible while still meeting
requirements.
Minimize ordering costs. Every time a company places an order for materials, it incurs
some ordering costs (e.g., paperwork and order processing costs). To minimize ordering
costs, a company will strive to place fewer orders, i.e., orders for larger quantities. Thus,
companies constantly grapple with the tradeoff between ordering costs and inventory
costs.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Key Inputs, Outputs, and Considerations
The bill of materials (BOM) explosion is a key concept related to the materials planning process.
Part Substitution
Part Effectivities
o Date Effectivity
o Use-up effectivety
Advanced BOM
o Planning BOM
o As-build BOM
Customer Prioritization
Supply Prioritization
The figure illustrates the key inputs and outputs for materials planning.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Key Concept - Bill of Materials Explosion
A key concept related to the materials planning process is the bill of materials (BOM) explosion.
Let's look at how a BOM explosion is done.
A company manufactures cookies. Each pack of cookies requires lb of chocolate chips, 2 lbs of
flour, and cup of sugar. Each pound of chocolate chips requires lb of vanilla and lb of
chocolate. Thus, the exploded BOM for a pack of cookies is:
lb of chocolate chips
2 lbs of flour
cup of sugar
lb of vanilla and lb of chocolate (required per pound of chocolate chips)
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Key Outputs - Materials Plan
The materials plan will specify what materials are needed on what days for the factory to
manufacture the required product. This requires a complete BOM explosion, as well as
knowledge of current inventory, expected receipts, and expected demand. Some suppliers
require manufacturers to place orders in minimum quantities (e.g., 100) and also in multiples of
lot sizes (e.g., if a lot size is 50, the order sizes are in multiples of 5050, 100, 150, 200, etc.).
Planners also use these quantities as inputs when developing the materials plan.
Example
The demand for the cookies for each of the next four days is 50, 60, 100, and 80 respectively. By
exploding the BOM, we can determine the quantity needed of each material per day to
manufacture the cookies. This example focuses only on expected demand, and does not
consider beginning inventory or expected receipts.
Materials Plan
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Key Outputs - Materials Plan - continued
Materials plans must take into consideration beginning inventory levels and expected receipts, as
well as expected demand. Consider the case of a yogurt manufacturer that is planning its
materials for days three and four (today is day one).
For simplicity, assume that they are only planning materials for six-ounce containers, and
that supplier lead-time is two days (so they must place an order today to receive it in time
for day three).
Also, the supplier specifies a minimum quantity of 75 and lot sizes of 75.
On day three, there are 10 containers in inventory, with expected demand of 205. Based on this
expected demand and existing inventory, the company needs 195 additional containers (i.e., net
material requirements) on day three (as shown below).
Because of the lot size restrictions, they cannot order 195 exactly but must order in multiples of
75 (75, 150, 225, etc.). Click on the Materials Plan button to view the adjusted materials plan and
related purchase order recommendations.
Materials Plan
Minimum Quantity 75
Lot Size 75
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Inputs for Materials Planning
There are several inputs for materials planning that can be classified into three typesdemand
inputs, supply inputs, and static inputs (inputs that seldom change).
Demand Inputs
Customer Orders
Customer orders are given top scheduling priority to ensure that due dates are met.
Production Schedule
Daily manufacturing requirements are used to determine the total material requirements.
Demand Plan
Long-term material requirements are derived from the long-range demand plan.
Supply Inputs
On-hand Inventory
Currently available inventory of materials. This information is used to determine the net
material requirements.
Supplier Inventory
Inventory of materials currently available at the suppliers.
Scheduled Receipts
Inventory of materials that has already been shipped and is en route to the appropriate
locations. This information is used to determine the net material requirements.
WIP
Work that has already started and is partially completed. The WIP may be used during the
calculation of net material requirements.
Purchase Orders
Orders placed so that materials will arrive in time for production.
Static Inputs
Items
Goods planned for production that have bills of materials associated with them.
BOM
Detailed bill of material that is used to explode finished goods requirements into detailed
material requirements.
Supplier Lead-times
The time between placing an order with a supplier and receiving it so that it is available for
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
manufacturing.
Minimum Quantities
The minimum quantity in which an order must be placed with a supplier.
Lot Sizes
Multiples in which orders must be placed with suppliers, e.g., if lot size is 75, then the orders
must be in multiples of 75 (75, 150, 225, 300, etc.).
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Additional Considerations
In developing materials plans, companies may also take into account additional considerations,
such as:
Part Substitution
Use of an alternate part, or substitute part, when a primary part is not available.
Part Effectivities
A company may choose to terminate the usage of one part and use a different part instead; they
can accomplish this in various ways, including:
Date Effectivity - After a predetermined date, the original part is replaced with a different
part. For example, if the date effectivity of component A is May 16, then component A will
no longer be used after May 16 (even if the company still has existing inventory of
component A).
Use-up Effectivity - The original part is replaced with a different part after all the current
inventory of the original part is used up. For example, if component A is affected by use-
up effectivity, when the entire current inventory for component A is used up, it will no
longer be used and will be replaced by a different part.
Advanced BOM
There may be many different types of bills of material that could be used for different purposes:
Planning BOM - A company uses such BOMs during long-range planning. Planning
BOMs usually do not specify each part that is required to build an item, but are limited to
parts (materials) that need to be planned early, e.g., parts with long lead-times.
As-build BOM - The most detailed level of the BOM; the As-build BOM lists in great
detail every part that is required to manufacture an item, including routing information.
Customer Prioritization
Some customers are more important than others, and companies go to great lengths to satisfy
this customer base, and meet delivery dates, by developing production schedules that
accomplish this even if it means slippage in delivery dates to some other customers.
Supply Prioritization
A company may have multiple sources of supply for certain raw materials, or sub-assemblies and
components, and they will typically specify the primary source and a secondary source of supply
for each of these items. They will use secondary sources only if the primary source is unable to
meet requirements.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Organizational Implications
Use of the materials planning process usually involves implementation of supply chain planning
software. This leads to several organization changes within the company:
Centralized Planning
Use of an integrated materials planning process usually means that there is one planner who
plans the material requirements globally and communicates those to the suppliers as well as
within the organization. Previously, there may have been several planners/buyers who were each
responsible for materials planning for a product, region, or division. Centralized planning changes
that balance of power and shifts it to the centralized planner. This could also lead to
organizational realignment.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Materials Planning Example
We will now consider a complex materials planning example by taking into account substitute
parts and date effectivities.
Demand
12-May 13-May 14-May 15-May 16-May 17-May
Number of motorcycles 100 80 80 85 130
The manufacturer uses one gear assembly (GA1) per motorcycle. However, their supplier has
developed a modification for GA1 in which a new assembly (GA2) will replace GA1 effective May
15. The supplier has suggested a lot size of 25 for GA2 (so orders have to be in multiples of 25
25, 50, 75, 100, etc.). The lot size for GA1 is 35. The motorcycle manufacturer has decided to
carry a safety stock of 15 GA2 to account for possible manufacturing mishaps (on their supplier's
part). The order lead-time is one day for GA1 and two days for GA2.
The manufacturer needs to create a feasible materials plan for GA1 and GA2 from May 12
through May 17.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Materials Planning Example - continued
The following is a feasible materials plan for GA1 and GA2 for May 12 through May 17. Due to
the date effectivity on GA1, it will be replaced by GA2 on May 15. GA1 is no longer used after
May 14 even though there are five units still in inventory.
Order 105 70
Expected Receipts 105 70
Ending Inventory 15 5
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Materials Planning Example - continued
The motorcycle manufacturer also uses fuel injectors (F1); the order lead-time for F1 is one day.
The primary supplier for fuel injectors has the F1 Capacity as shown in the table.
F1 Capacity
Fortunately, there is an alternate part available for F1 (named F2) from the same supplier. If F1 is
unavailable, then F2 can be substituted for F1 (as reflected in the F2 Capacity table).
F2 Capacity
The manufacturer needs to create a material plan for F1 and F2 from May 12 through May 17.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Materials Planning Example - continued
Considering the availability of F1 and substitute part F2, this solution highlights the materials plan
for F1 and F2 from May 12 through May 17.
F1 Capacity 85 85 85 85 85
F2 Capacity 15 15 15 15 15
F1 Beginning of Inventory 0 0 5 15 15
Order 85 85 85 85 85
Expected Receipts 85 85 85 85 85
Expected Inventory 0 5 15 15
F2 Beginning Inventory 0 0 0 0 15
Order 15 0 15 15
Expected Receipts 15 0 15 15
Ending Inventory 0 0 15 0
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Topic Summary
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Metrics for Production Planning
Overview
Companies monitor the "health" of their supply planning processes using a variety of metrics,
including:
An organization that implements and uses an effective production planning process can provide
capabilities that, together with effective procurement, manufacturing, and fulfillment functions,
increase shareholder value.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Planning Process Control
The goal of supply chain planning is for individuals within organizations to trust and use the
process-generated plans to minimize the number of manual changes to those plans. This ensures
that an organization can maximize the value of their investment in supply chain initiatives.
Thus, companies use the number of manual overrides as a crucial metric to monitor whether
they have sufficient control of the planning processes. This metric measures the number of
occurrences in which plans have been manually revised, and identifies the level of intervention in
the planning process.
A high level of intervention may indicate that there are process, organizational, or training issues
that need to be resolved.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Planning Effectiveness Oriented Metrics
Companies engage in production planning processes to improve their supply chain effectiveness,
and they can track a variety of effectiveness-oriented metrics, including:
Schedule Adherence
The percentage of time a company adheres to the established schedule during the week (i.e.,
producing the correct items in the right quantity on the day scheduled). Changing production to a
different day (later in week) might result in lost sales since product may not be available when
customers want it. Companies seek to maximize their ability to complete all production in the
correct volumes at the correct times, within the specified week.
Capacity Utilization
The percentage of a factory's capacity utilized during a period. Low capacity utilization suggests
that the company has excess capacity to meet customer requirements, while high capacity
utilization suggests that the company may occasionally not have sufficient capacity to meet
customer requirements. This is reported as a percent of total available capacity.
Inventory Turns
The number of times that inventory turns over during the year. An organizational objective is to
maximize the frequency of inventory turns per year to promote the release of working capital to
the business.
Number of Stock-outs
The number of times a company is out of stock on items ordered by customers. Companies seek
to minimize this number because it correlates to customer service level measurement.
Order Lead-time
The average time it takes a company to deliver an order once the order has been received. This
enables organizations to measure "lead-time to customer delivery" performance against their own
targets as well as other industry benchmarks. Companies seek to minimize the number of days it
takes to deliver the requested quantities to customers once the order has been placed.
Furthermore, customers may have pre-scheduled delivery days that will impact the order delivery
date. Some customers also place orders weeks in advance, which may further distort this metric.
Delivery in Full
The percentage of all orders for which the quantity and lines ordered have been delivered in full,
on first delivery, as a proportion of total orders. This shows how often an order is 100 percent
right upon delivery, and how often a company "misses" (even if the miss is one unit per order).
Companies seek to maximize the proportion of orders that are delivered completely to order
quantity. The percentage of orders delivered in full decreases when product is not available to fill
customer orders or when product is not delivered as per the customer orders.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Production Planning Influences on Shareholder Value
Companies seek to ensure product availability and high service levels for their customers, while
simultaneously maintaining low inventory levels. Production planning processes seek to ensure
machines and materials are available for production when needed. Furthermore, production
planning processes are used to maximize asset utilization and throughput. This eventually leads
to an increased number of inventory turns and reduced inventory-carrying costs. To maintain low
inventory levels, companies strive to manufacture product as close to the dates needed without
using any manufacturing overtime and without expediting materials from suppliers.
More accurate production schedules and timely materials availability also leads to increased
product availability for customers. This increases service levels to the customers. In addition, it
results in lower costs to fulfill customer orders because fewer customer orders need to be
expedited, and most orders can be shipped accurately and completely. Furthermore, less
expediting also leads to reduced manufacturing and distribution overtime, as well as reduced
FTEs in the supply chain management function.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Topic Summary
Companies monitor the "health" of their supply chains using a wide variety of metrics. Two such
metrics are metrics to ensure process is followed and metrics to measure supply chain planning
effectiveness. Companies achieve benefits from improved production planning, including
increased schedule adherence, increased capacity utilization, increased number of inventory
turns, reductions in order lead-time, and an increase in orders delivered in full. These benefits
ultimately translate into increased shareholder value.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Production Planning Case Study
A cookie manufacturer makes many different types of cookies. It has several bakeries across the
world, but uses some common raw materials for making the cookies, e.g., flour, oats, butter,
chocolate chips, peanut butter, etc. For illustrative purposes, we will look at the production
schedule for one of its bakeries. The bakery bakes two types of cookieschocolate chip and
peanut butter. The chocolate chip cookies are baked at 275 degrees F for one hour, and the
peanut butter cookies are baked at 350 degrees F for one hour. The bakery only has one oven for
baking cookies. If the oven is already set at 275 degrees, it requires another 15 minutes to heat
up to 350 degrees, whereas if it is at 350 degrees, it takes 45 minutes for it to cool down to 275
degrees (both of these times are analogous to changeover times).
The bakery is constrained by the following: The "due time" for each of type of cookie is
different as shown in the cookie delivery
A maximum of 1,500 chocolate chip schedule below.
cookies can be baked at one time
A maximum of 1,000 peanut butter Quality Due Time
cookies can be baked at one time Chocolate Chip 1,000 10 a.m.
1,000 12 noon
The baker (and hence the oven)
1,000 2 p.m.
only works from 7 a.m. to 3:30 p.m.
Peanut Butter 2,000 11 a.m.
The company needs to produce 3,000 4 p.m.
3,000 chocolate chip cookies (CC)
and 5,000 peanut butter (PB)
cookies
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Production Planning Case Study - continued
There are many ways to go about determining a feasible production schedule. One approach is
trial and errortry a sequence of activities and determine if the resulting sequence satisfies all
the constraints. If it does, you have a solution. If it does not, you then must modify some aspect of
the sequence, and try again until you reach a feasible solution.
Determine which of the following sequences provides a feasible production schedule. Be sure to
consider the Cookie Delivery Schedule and Capacity Constraints. Click the button below to
review the schedule and constraints.
Quality Due Time Only one oven is available from 7 a.m. to 3:30 p.m. The
Chocolate Chip 1,000 10 a.m. set-up time to change the temperature from 275 degrees
to 350 degrees is 15 minutes, while the set-up time to
1,000 12 noon
change the temperature from 350 degrees to 275 degrees
1,000 2 p.m. is 45 minutes. The company can bake a maximum of
Peanut Butter 2,000 11 a.m. 1,500 CC cookies or 1,000 PB cookies at one time.
3,000 4 p.m.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Production Planning Case Study - continued
While there are many materials required for baking the cookies, we will concentrate on flour only.
For each cookie, one gram of flour is required. Thus, the bakery needs 8,000 grams of flour for
the day (to produce a total of 8,000 cookies).
The planner runs the requirements for all the bakeries across the world (assume the company
has bakeries in Asia, Australia, Europe, and North America), and determines the total flour
requirements by region for the next five days. The planner then communicates the requirements
to all the suppliers in each region, as well as internally within the organization.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Production Planning Case Study - continued
Change in Forecast
During the day, the planner receives an update on the forecast and notes that the demand for
cookies has increased substantially in Asia from day five onwards (for day 5, the requirements
have changed from 7,000 kg of flour to 10,000 kg of flour). By quickly determining the additional
quantities needed in Asia, the planner updates the material requirements and communicates
them internally, as well as to the supplier.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Production Planning Case Study - continued
Unfortunately, Procurement informs the planner that the supplier has just informed them of a
labor strike in the mill, and will not be able to commit to the additional quantities that are required.
Procurement has contracted with a secondary supplier who will supply the required quantities but
at a slightly higher price. Procurement also informs the planner of the delivery schedule of the
material.
The planner updates this information and generates a revised production schedule for the
bakeries in Asia.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
A Production Planning Case Study - continued
To further hinder production, the planner is told that one of the ovens in a bakery in Australia has
broken down and will require at least 24 hours to be repaired. The planner quickly updates this
information and generates a new production schedule for the Australian bakery. Unfortunately,
the bakery does not have sufficient capacity to meet the requirements. However, one of the Asian
bakeries has excess capacity available. The planner then shifts some of the production to the
Asian bakery (while ensuring that enough materials will be available) and generates a revised
production schedule for the affected bakeries.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.
Conclusion
Module Summary
Companies plan how to manufacture product during the production planning process. Production
planning is comprised of the production schedule and the materials plan, and is limited by
constraints, including capacity and materials constraints.
The materials plan developed during materials planning is a detailed schedule that defines the
exact time at which materials are needed on any given day. Planners consider supplier
constraints, along with part substitutions, part effectivities, and customer and supply prioritizations.
The goal is to minimize backorders, inventory, and ordering costs during materials planning.
Copyright (c) 2004 Accenture. All rights reserved. You may only use and print one copy of this document for private study
in connection with your personal, non-commercial use of a Supply Chain Academy course validly licensed from
Accenture. This document, may not be photocopied, distributed, or otherwise duplicated, repackaged or modified in any
way.
Note: interactive elements such as activities, quizzes and assessment tests are not available in printed form.