CONSTRUCTION SCHEDULE

JOTUN OFFICE RENOVATION

ID Task Name Duration Start Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16
12/20 1/3 1/17 1/31 2/14 2/28 3/13 3/27 4/10
1 JOTUN OFFICE 86 days Mon 86 days
1/11 4/15
1/11/16
2 SHOP DRAWING, MATERIAL SUBMISSION 17 days Mon 17 days
1/11 1/27
AND APPROVAL 1/11/16
3 Shop drawing submission 10 days Mon 1/11/16 10 days
1/11 1/20

4 Shop drawing approval by PM/Designer 7 days Thu 1/21/16


1/21 1/27

5 Material submission 14 days Mon 1/11/16


1/11 1/24

6 Material approval by PM/Designer 10 days Sat 1/16/16


1/16 1/25

7 LONG LEAD ITEMS PROCUREMENT 83 days Thu 1/14/16 83 days


1/14 4/15

8 Movable partition 21 days Tue 1/26/16


1/26 2/25

9 Raise floor 21 days Tue 1/26/16


1/26 2/25

10 Tiles & Carpet 21 days Tue 1/26/16


1/26 2/25

11 CONSTRUCTION PROGRESS 83 days Thu 1/14/16 83 days


1/14 4/15

12 PREPARATION WORK 4 days Thu 1/14/16 4 days


1/14 1/17

13 Site hand-over 1 day Thu 1/14/16


1/14 1/14

14 Registration of worker 2 days Thu 1/14/16


1/14 1/15

15 Site protection 2 days Sat 1/16/16


1/16 1/17

16 Mobilization 2 days Sat 1/16/16


1/16 1/17

17 MAIN WORKS 79 days Mon 79 days


1/18 4/15
1/18/16
18 Demolition ( ceiling, floor tiles, glass 12 days Mon 1/18/16
walls ...) 1/18 1/29

19 Floor screeding 10 days Sat 1/30/16


1/30 2/18

20 Set-out 2 days Fri 2/19/16


2/19 2/20

21 Brick wall & plastering 10 days Sun 2/21/16


2/21 3/1

22 Floor water- proofing WC and testing 8 days Wed 3/2/16


3/2 3/9

23 Partition 24 days Sun 2/21/16


2/21 3/15

24 Conceal Ceilling 22 days Mon 2/29/16


2/29 3/21

25 T-bar ceiling 10 days Wed 3/9/16


3/9 3/18

26 Painting work 22 days Wed 3/2/16


3/2 3/23

27 Movable partition 14 days Wed 3/9/16


3/9 3/22

28 Floor, wall tile installation work 21 days Thu 3/10/16


3/10 3/30

29 Carpet floor installation work 5 days Thu 3/24/16


3/24 3/28

30 Doors & fit furniture manufacturing 21 days Sun 2/28/16


2/28 3/19

31 Door installation 10 days Sun 3/20/16


3/20 3/29

Project: 20131002 ABI PROJECT SCH Task Split Milestone Summary Project Summary External Tasks External Milestone Progress Deadline
Date: Wed 1/13/16

Page 1
CONSTRUCTION SCHEDULE
JOTUN OFFICE RENOVATION

ID Task Name Duration Start Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16
12/20 1/3 1/17 1/31 2/14 2/28 3/13 3/27 4/10
32 Glass installation 13 days Sun 3/20/16
3/20 4/1

33 Furniture & Fitment 12 days Sun 3/20/16


3/20 3/31

34 Loose furniture installation 7 days Fri 4/1/16


4/1 4/7

35 Logo, white board, skirting 7 days Fri 4/1/16


4/1 4/7

36 M&E WORK 47 days Sun 2/21/16

37 Electrical & Tel, data system 35 days Sun 2/21/16


2/21 3/26

38 ACMV / Aircon 35 days Sun 2/21/16


2/21 3/26

39 Fire Protection 35 days Sun 2/21/16


2/21 3/26

40 Pumbing 35 days Sun 2/21/16


2/21 3/26

41 Fix lighting installation 7 days Sun 3/27/16


3/27 4/2

42 Camera installation 3 days Tue 4/5/16


4/5 4/7

43 GENERAL CLEANING 3 days Fri 4/8/16


4/8 4/10

44 TESTING AND COMMISSIONING 3 days Fri 4/8/16


4/8 4/10

45 1st Site inspection 1 day Mon 4/11/16


4/11 4/11

46 Defects rectificationn 3 days Tue 4/12/16


4/12 4/14

47 Project Hand-over 1 day Fri 4/15/16


4/15 4/15