Professional Documents
Culture Documents
BETWEEN
2othApril 2006
TN OK) EXPRESSWAYS LIMITED
INDEX
B KARUR BYPASS
I
11
I
29
ii Pier 30 52
SUPER STRUCTURE
1
-- -
ii-Design
- - Melhodrrlgy
.. 67 - 74
r--
1 1
b Mix.
111
I
113
I
d Section Pro
.- -
I
1 177 179- -
e Coordination
I I I
E MISCELLANEOUS 1
I
-._
DETIALS OF PROPOSED FLYOVER AT KARUR ROTARY
INCLUDING APPROACHES FROM KM 297+787 TO KM 298+761
IN THE STATE OF TAMIL NADU
.y
MAY 2005
I
Project Title:
1 DESIGN CALCULATION FOR FLYOVER AT KARUR ROTATRY AT
I CHAINAGE 298+300 ON NH-7 IN THE STATE OF
TAMILNADU (INDIA)
I
I L
Client;
NATIONAL HIGHWAYS AUTHORITY OF INDIA
(GOVERNMENT OF INDIA)
r 1
. ..
Avenge height upto mffit l e d = 6m
Height of C m h b i t = 0.8 m
Ctepthof dcckshb = 0m
a p t h o f S y w r ~ = 2.2 m
wghtafC6dsupermwtvc 7.5 m
w
P -
From IRC: 6-2000 CI-212.3
79.75 bCg/m2
F~dklal = 9.73 KN per b i n g
fmm IRC: 6-2000CI-212.4
Lnt.mlWindfwaonLkLood= 300 Kg. Pa running m
Furna = 6.7 KIN prr bmriq
. -.
So, M W i n d f a K l fw = t9.28 KN prr brLp \ J~;;',,.<
~EARINGD~IGN25OU/Horirontol~Lorrd
'7'
TJ
dl.. - 005
v;<; c ..
AS per previous Code flRC:&2MH3)
Nonnal Cam Sekmlc Came Wind Case Dnign Forceo
BEARINGDESZGN250~Swnmaryof Load
4.1 D u r b o T ~ rise
m
- 50C
O.oOool17 / %
25 m
1n'L0a7
7.31 rnm
4.3 Rotetion
h
Maximum Dssd lord moment
- -
MadmumLivsmmambnt
Modulus of Elmwty L
Baarkrgbimcnrian&PllopsrHcr
Length I = mm
h d t h b= mm 9hp
Si& cover c = mm
f nttmnal layer hi = mm
Steel thk. t,= mm Yd= C
v
Vertical Load (KN] btwl toad (KN) . I-LtKN)
Y, b'ma h n y H ,mm
1982.2 724.6 46.0 53.1 J0.24
-
-4
. i: 1.4 Rotatbmon W n g
a (radian)
, a H (dm)
A buetoDadLoad,SIbL 0.00303 0.06000
bllL to PPCJtress 0.00000 0.00000
Due to Live Load 0.00108 0.0000
Rotationdue t o Installation I m c c ~0.00000 6.06600
1 . 6 P ~ ~ & P r r * l l . d b l s S t r s u I n ~ ~ ~
Length of Pedestal (Across Bridge Axis) = 860 mm dK
Breadth of Pedestal (Along Bridge Axis) = 675 mtn OK
1L
-4 A1= 5808w Id
A2 =
AUA2=
198924 nwt'
2
.--
-. -
.
6.0 Desim of Reinforced Elastomeric &wino as wr IRC:83 Part IIl-1987
6.1 k i n a Dimension
=
Length I, 560 mm Eff. length (I.)= 548 mm
B d t h b. = 375 mm Eff. b d t h (b.). 363 mm
Side cover c = 6 mm Eff. areu (A& 198924 sqmm
1nterml lap- hi = 10 mm Shape Factor(S,)= 10.92
Outer lap- h, = 5 mm Shore Hardness = 60
Steel thk. t,= 4 mm Shear Modulus(b)= 1.0 N/sqmm
No.of Steel plate n = 6 nos
Total Elastomer. (h)- 60 mm
Total Height of Bearing (t)= 84 mm
t,,=[2*t0 + (n-l)*ti + n"t.1
C
/.
6.3 Mowmatt o f k i n a
,A (in mm) A~,J(in mm)
Movement due to Temperature 7.31 0.0
Movement due to Shrinkage + C r u p of concrete 2.38 0.0
Movement due to Prestress 0.00 0.0
Total L#lgitudiwl MovMwnt 9.69 0.0
I r-
-
1.1 Load Data
Axial Force (P)
Moment (M)
-
1.2 Material Data
. - Grade of Concrete
Grade of steel ("m" for Mild Steel & "t" for HYSD)
Load Case (N=Normal, W = Wind, S = Seismic)
Permissible mid wmpressive stress in concrete (a,)
Permissible bending tensile stress in concrete ( a 3
Permissible bending compressive stress in concrete (acb)
Permissible tensile stress in steel (a,3
Modular Ratio
-
13 Geometric data
Clear cover (d")
Effdive cover (d'=d"441/2)
Diameter of column (d)
Bar Diameter (I))
n
Number of bars
-. Reinforcement area (&,)
Reinforcement %
-
1.4 Properties of uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calculated direct compressive stress (a,&)
Calculated bending compressive stress (rr,b,d)
Interaction formula :
a,.d l o
, + add / a,, r 1.O
Resultant compressive stress in concrete (
a
,,
)
Mipa the ~ectlonas cracked section
-
1.5 Proverties of cracked section
Neutral axis depth (n)
Distance of centroid of cracked section from centre of circle
n
Cross-sectional area of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net m t r i c i t y
Effective moment of inettia of d e d section
Calculated distance of neutral axis below CG* @,I)
-
1.6 Check for stress
Compressive stress in c o n m e (a&)
60.95 kglm2 (Safe)
-511.03 kg/cm2 (Safe)
Tensile stress in steel (~a)
Flyover at Karur Design of Abutment for flyover
-
1.1 Load Data
Axial Force (P)
Moment (M)
Material Data
Grade of Concrete
Grade of steel ("m" for Mild Steel & '"t"for HYSD)
Load Case (N =Normal, W = Wind, S = Seismic)
Permissible axial compressive stress in concrete (a,)
Permissible bending tensile stress in concrete (a,3
Permissible bending compressive stress in concrete (a*)
Permissible tensile stress in steel (a,,)
Modular Ratio
-
1.3 Geometric data
Clear cover (d')
Effective cover (d=d"+4/2)
Diameter of column (d)
h
Bar Diameter (4)
Number of bars
Reinforcement area (&
Reinforcement %
1.4 Pro~ertiesof uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calculated direct compressive stress (a,,&)
Calculated bending compressive stress ( u ~ , ~ )
Interaction formula :
iJ,,d / a, + a*,csl/ a* I1.o
Resultant compressive stress in concrete (a,,,,) -27.572 kg/cm2
-
1.5 Properties of cracked section
Neufral axis depth (n)
h Distance of centroid of cracked section h m centre of circle
Cross-sectional area of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
Effective moment of inetria of cracked section
Calculated distance of neutral axis below CGd (yell)
Stress at neutral axis
-
1.6 Check for stress
87.69 kg/cm2 (Safe)
Compressive s t m s in concrete (ack)
Tensile stress in steel (a,d -1128.14 kglcm2 (Safe)
Abut-Reinforcement-Wind
Flyover at Karur Design of Abutment for flyover
-
1.1 Load Data
Axial Force (P)
Moment (M)
-
1.2 Material Data
Grade of Concrete
Grade of steel ("m"for Mild Steel & "t" for HYSD)
Load Case (N =Normal, W = Wind, S = Seismic)
Permissible axial compressive stress in wncrete (a,)
Permissible bending tensile stress in concrete (a,)
Permissible bending compressive sbess in concrete (a,)
Permissible tensile stress in steel (a,)
Modular Ratio
-
1.3 Geometric data
Clear cover (d")
Effective cover (d'=dv++I2)
Diameter of column (d)
Bar Diameter (4)
h
Number of bars
.- - Reinforcement area (As,)
Reinforcement %
-
1.4 Pro~ertiesof uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calculated direct compressive stress (amml)
Calculated bending compressive stress ( Q , ~ , ~ ~ )
Interaction formula :
a,& / a, + a*,, / a,, I1.0
Resultant compressive stress in concrete (s,,)
Design the section as cracked section
-
1.5 Proverties of cracked section
Neutral axis depth (n) 67.19 crn
n Distance of centroid of cracked section from centre of circle 60.65 cm
Cross-sectional area of cracked section 9264.94 cm2
Moment of inertia of cracked section about its own centroid 2908557.75 cm4
Effective area of cracked section 10944 cm2
Eccentricity of load from the centroid of the effective section 51.35 cm
Net eccentricity 62.77 cm
Effective moment of inetria of cracked section 15712559.37 cm4
Calculated distance of neutral axis below CGfi(y,l) 22.87 cm
Stress at neutral axis 0.01
-
1.6 Check for stress
Compressive stress in wncrete (a,k) 111.14kglcm2 (safe)
Tensile stress in steel (qbt) -1899.13 kg/rm2 (Safe)
Abut-Reinforcement-Seismic LASA
Flyover at Karur Design of Abutment for flyover
-
1.1 Load Data
Axial Force (P)
Moment (M)
Material Data
Grade of Concrete
Grade of steel ("m" for Mild Steel & "t" for HYSD)
Load Case (N = Normal, W = Wind, S = Seismic)
Permissible axial compressive stress in concrete (a,)
Permissible bending tensile stress in concrete (ad
Permissible bending compressive stress in concrete (a*)
Permissible tensile stress in steel (a,,)
Modular Ratio 10
-
1.3 Geometric data
Clear cover (dm)
Effective cover (d'=d"+@)
Diameter of column (d)
Bar Diameter (4)
n Number of bars
Reinforcement area ( 4 3
Reinforcement %
-
1.4 Pro~ertiesof uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calculated direct compressive stress
Calculated bending compressive stre~s(a&,&
Interaction formula :
,,,a a +
I, I a* 5 I .O
Resultant compressive stress in concrete (
a
,,
)
Design the section as cracked section
-
1.5 Pro~ertiesof cracked section
Neutral axis depth (n)
A Distance of centroid of m k e d section from centre of circle
Cross-sectional area of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
Effective moment of inetria of cracked section
Calculated distance of neutral axis below CGa (yd)
Stress at neutral axis
-
1.6 Check for stress
42.94 kglcmZ (Safe)
Compressive stress in concrete (a&)
Tensile stress in steel (a,*) -326.94 kg/rm2 (Safe)
-
1.1 Load Data
Axial Force (P)
Moment (M)
-
1.2 Material Data
Grade of Concrete
Grade of steel ("m" for Mild Steel & "t" for HYSD)
Load Case (N =Normal, W = Wind, S = Seismic)
Permissible axial compressive stress in wncrete (a,)
Permissible bending tensile stress in wncrete (0,)
Permissible bending compressive stress in concrete (acb) 133.33 kg/cm2
Permissible tensile stress in steel (an) 2666.60 kg/cm2
Modular Ratio 10
-
1.3 Geometric data
Clear cover ( d )
Effative cover (d'=d"+4~2)
Diameter of column (d)
Bar Diameter (4)
n Number of bars
-. Reinforcement area (A,J
Reinforcement %
-
1.4 Proverties of uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calculated direct compressive stress (a,.d)
Calculated bending compressive stress (a&,&)
Interaction formula :
-
1.5 Properties of cracked section
Neutral axis depth (n)
* Distance of centroid of cracked section from centre of circle
Cross-sectional asea of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
Effective moment of inetria of cracked section
Calculated distance of neutral axis below CGdFbmI)
Stress at neutral axis 0.00
-
1.6 Check for stress
Compressive stress in wncrete (a,,) (Safe)
Tensile stress in steel (a,d (Safe)
Abut-Reinforcement-Wind
Flyover at Ksrur Design of Abutment for flyover
-
1.1 LoadDab
Axial Force (P)
Moment (M)
-
1.2 Material Data
M30
Grade of Concrete
Grade of steel ("m" for Mild Steel & "t" for HYSD) t (One Span Dislodged
Load Case (N =Normal, W = Wind, S = Seismic) s Condition)
Permissible axial compressive stress in wncrete (a,) 112.50 kdcm2
Permissible bending tensile stress in concrete (ad 10.05 ks/Crn2
Permissible bending compressive stress in concrete (a*) 150.00 kdcm2
Permissible tensile stress in steel (a,J 3000.00 kg/cm2
Modular R h o 10
-
1.3 Geometric data
Clear wver (d")
Effective cover (d'=d"+~$L?)
Diameter of column (d)
Bar Diameter (4)
n Number of bars
Reinforcement area (A,)
Reinforcement %
-
1.4 Pro~ertiesof uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calculated direct compressive strffs (a,,d)
Calculated bending compressive stress (a*.d)
Interaction formula :
, +,,n
u , , ~I a < 1.0
1aCb
Resultant compressive stress in concrete (aRd)
Design the section as uncracked section
-
1.5 Pro~ertiesof cracked section
Neutral axis depth (n)
Distanoe of centroid of cracked section from centre of circle
n
Cross-sectional area of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
Effective moment of inetria of cracked section
Calculated distance of neutral axis below CGd (yd)
Stress at neutral axis 0.00
-
1.6 Check for stress
26.52 kg/rm2 (Safe)
Compressive stress in concrete (rick)
Tensile stress in steel ( a d -68.01 kg/cm2 (Safe)
LASA
Wi of Abutment for Flyover
REACTION W E TO DL
. . . .
i
.---.-,'5 1 ...,.......0 ....
! , , . , , ,
,
..Mi.5 ,.~_i
--
i..-.-.?5........... ..........................
1 I . O......................
6n=.5 ......
"j
. 15 C
' 2 1 0 :
j._"".39 ......,.-.-"... .--y-.--
,--... c_ ?7&4-.1
i4.!~2]D.12!5 x-j
i 51
l.....
j 2 0 213:YIj_j
TdLnanmmnt = 188 437
Totd SlDL madim on abutment 52.976 Tonne
DesQn DL +SHK for abutment = 241.413
Flyover at Karur Design of Abutment for Flyover
.-
Constants:-
Density of concrete -
- 2.5 T/m3
W i g h t of w r i n g c ~ e t -
- 9.2 T/m2
Grade of Concrete (~ubsfru~ture) =M 30 MPa.
Grade of Concrete (superstructure) =M 40 MPa.
-
Dia of abutment 2000 mm
Dia of abutment - 2000 mm
Total straight Height of abutment -- 9012 mm
-
From Bed Block/ abutment Cae
Area inelevation - 0.5 x 9.75 + 5.875 x 0.75
= 9.28125 m Z
.: Total Volume = 9.28125 x 2.4
-- 22.275 m3
n .: Dead Load = 22.275 x 2.50
-4
Ootions For desIaninu abutment
I Max DL+LL on one snan+LWL+Beanm.
2 Max DL+LL on one soan+LWL+wind+Bearinq.
3 Max DL+LL on one wan+LWL+EQ+Bearina.
4 DL ofone w a n
5 DL of one wan+wind
6 DL of one wan+EQ
Brakin0 eRec( ' load on 1 span'
Braking Load 20.0 T
Height 10.7
F =FhL? + Vr.Ltc
Cenlifuual force:
The centrifugal force shaN be delrmined from the following equation (IRC-6:2000, clause-215)
C - - W v2
127 R
Where C = Centrifugal force
- W =
I
--
Loadin tons
0.0
Design
t
speed of vehicles
v
- 58.0 KMPH
R = Radius of curvature in meters
- w.0 m
C - 0.0 t
C e n t M ~ ~he l e = 0.00 t Distributed on Two abutments
per abutment
Eccentricrty of Centrifugal f0rce - Deck top Level +7.20 - Pile cap top level
- 13.56 m
Transv Eccentricrty
n Live Load Eccenblcitv Trans. ecc Load Moment
Tm
One Train of Class 70R 1.78 77.53 738.0
One Train of Class A 3.075 33.31 102.4 Tm
Two Trains of Class A 1.325 66.62 88.3 Tm
This ecc is opposite to the FP em.
live Load Eccentn'cltv Lona. ecc Loed Moment Load on longer Span only
One Train of Class 70R 0.00 77.53 0.0 Tm
One Train of Class A 0.00 33.31 0.0 Tm
Two Trains of Class A 0.00 66.62 0.0 Tm
Check for wind load (IRC 6: cl. 2f2.3) (Wind is taken on longer span for ~implicity)
Herght of deck from mid abutment 4.34 m
Height of deck abutment base 7.31 m
C . Exposed area of deck and railings
a) - 2600 ht x 25000 length
= 32 5 m2
avg ht above bed level 7.3 m
mm pressure = 2.40 KN/m2 (IRC 6: c1.212.3)
fom = 78 T
Moment at 57.0 Tm
a ,/'.
., -
b 7
,". <\
1.
+
- 4
1-21
fl---T4,'b,
;
?j - -.
A r'
I *
of RCC ~
~bt-Design/De~ign b ~ q ' ~ \ - .
,
Flyover at Karur Design of Abutment for Flyover
abubnent Shaff
- 8672 x 2000 = 17.344
avg ht above bed level
min pressure =
Total Wnd Force
hbment at abutment base
F&
- 5.6 1
Mom& 81 b?tB= 41 # Trn
1 span laid
MaxmW wind m n h . (wflh 4
~ e 5 ,1
-g st mid ht of a b m f g9.38 Tm 0.00
Desgn Moment 8f a b u t m f base 7OB.M Tm 53.09 tm
s m t Force
= (O.Q(] (Seismic Zone 111)
Wind farce
D L + t L ecc In Transverse Dim 218 9
Se~srnlcForces (Hor-long)
axial Mtr Mlong
Total Loads 434.8 218.9 192.6
I
DL.~ L 5cc
L ~nTransvetse Dim. i 218.9
Sersm~c(Hor-long) 1 20 6 - 1 1936
ax~al Mtr Mlong
Total Loads 389.0 218.9 386.i
4 DLof One S m n
Check for dress i n abutment
6 DL vf O m Smn *wfnd
I I
anal - Mtr. Mlong
Total Loads 326 4 ' 107.s , 47.5
'. \
ESSI In abutment
I I 1 Loaa I ecc I Moment
gbutment Dead ~ o a d ] 124 9 1 ;r I 09
Super ~ t r k u r e ~ o a d 2131 5 20 9
~tve Load I C 0 00 00 -
Bearangt +Bmk~ng 00 10 7 D0
1;hnd force [ I
DC+LL e m ~nTransverse Dm. 80.9
Sets-) I 18 5 111.8
axial M!T Mlong
Total Loads 326.4 80.9 132 7
A w , ~ w O m . I g nd RCC Abutment
Flyover at Karur Design of Pier for flyover
3000 1
L
- - .......--.-.-.- i.....----.-*.,,,,,........
- 3875 Y
diemeter
A) Ds&n d Cgnbhver Pombn in ffm T r a n s w D m .
C/S ama of Bed B k h / rn = 3.391 m2 (Transverse Vhw)
Cantilevered Length = 3.875171
= 3.391 x 2.40
- 8.14 m 3
Volume
Net Volune = 8.14 m 3 -
Dead load = 8.14 x 2.50 = 26.34 T
C.Gof Loed = 1.66 m
rectm~ triang part
D.Load Moment at face of abubnenf
As 1 = 8.0425 m 2
No of bars Reqd: =127.856 = $6 Nos
8.0425
Spacing of Bars = 240 -- 15.0 Crns
fr
SOpravide 32 mm dia bars . 150 mm c/c spacing
. . -.,.
Ast Provided 12868.0 mm2 - - - - - . ..
'
,\
7,
-
.4,_
I-
., - - 026
LASA
Design Of Abutment Cap
Tobl s b u = 88.83 + 13.91 = 11277' T
--, r = Y
Bxd
v m&*almrrrr#rmrscliwr
d m HRscfivsdrpndmmsC* 1023.93 mm
B =BW&dalrb
. .I = 112.8 x 10006 = 0.46 Nrnwn2
2400 x 1023.93
-
b = Ma0 mm
d = 1024 mm
P 0.62 K
f, = 30.00 -'
rc = 031 FUmrn2
rmex = 2.2 IrUmrn2
= V/M = 0.459 > 0.31 Mmn2
= 0.459 < 2.2 ~lk~wn' SAFE
Vsbal = V-c%W 36.6 T Slnar-RW.
= U ~ C X A ~ X ~
v8t
Aswmhg 4 12 dirdimqpo
A sv 3 452.16 mmd
U E r 200 hum2
Mar DL+U On o n span
..
r
YY*. UT' 21w.36 kNm
&=*l- 444730 W h
IC
C a h n face to storti*) of sbppirg In X dirfction
C o h n face t o Hart,*) of slopping In Y direchon ck&fu-bm+sh
-
kl presnre IK
Avg Effective Cover = 0095 m MI" Pressure K
A v q e Effective depth d = 1.505 m c h k ln XX d*r&
6ros WingPrcroln = 376 k~lm' L31c Way ShMr
&DSS Baring F w s w e : M+ DO kN/mZ Rndlrgmcunem )K
)K
<reelalong W d ~ r u t
I
Direction of Tmff LC
-.
v. w,m&w
II= w . 1w
-
.
HY' wd*i@ =
n' z 1.226 rn (Depth ef -lad X3x4) ,.:v/bld'=
b= I 131 m (Eff bapm of section at X3X4) bZ
Flyover at Karur Design of Pier for flyover
-
1.1 Load Data
Axial Force (P)
Moment (M)
Material Data
Grade of Concrete
Grade of steel ("mufor Mild Steel & "t" for HYSD)
Load Case (N = Normal, W = Wind, S = Seismic)
Permissible axial compressive stress in concrete (a,)
Permissible bending tensile stress in concrete (ad
Permissible bendig compressive stress in concrete (u*)
Permissible tensile stress in steel (0,J
Modular Ratio
-
13 Geometric data
Clear cover (d")
Effective mver (d'=d"+41/2)
Diameter of column (d)
Bar Diameter (+)
n Number of bars
% Reinforcement area (&J
Reinforcement %
-
1.4 Proverties of uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calculated direct compressive stress (om,&
Calculated bending compressive stress (ecb.ul)
Interaction formula :
em,d/ua+OCb,d/cTC,, 5 1.0
Resultant compressive stress in concrete (a,&)
Desipn the section as cracked section
-
1.5 Prowrties of cracked section
Neutral axis depth (n)
Distance of centroid of cracked section from centre of circle
n Cross-sectional area of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
Effective moment of inetria of cracked section
Calculated distance of n e w axis below CGa (y4)
Stress at neutral axis
LASA
Flyover at Karur Design of Pier for flyover
-
1.1 Load Data
Axial Force (P)
Moment (M)
-
1.2 Material Data
Grade of Concrete
Grade of steel ("m"for Mild Steel & "t" for HYSD)
Load Case (N = Normal. W = Wind, S = Seismic)
Permissible axial compressive stress in concrete (a,)
Permissible bending tensile stress in concrete (a,)
Permissible bending compressive stress in concrete (a*) 133.33 k9/m2
Permissible tensile stress in steel (a,3 2666.60 k#m2
Modular Ratio 10
-
1.3 Geometric data
Clear cover (8)
Effective cover (d'=d"W)
Diameter of column (d)
Bar Diameter (4)
Number of bars
Reinforcement area (A,J
Reinforcement %
-
1.4 Pro~ertiesof uncracked section
Cross-sectional area of uncracked section
Moment of inertia of unmked section
Calculated direct compressive stress (u,,d)
Calculated bending compressive stress (ah,d) 57.577 kg/cm2
Interaction formula :
u,,,Ia,+a~,,/q,~ 1.0
Resultant compressive stress in concrete ( c ~ , , ~ )
Design the section as cracked section
h. -
1.5 Properties of cracked section
Neutral axis depth (n)
Distance of centroid of cracked section from centre of circle
n Cross-sectional area of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
Effective moment of inetria of cracked section
Calculated distance of neuhd axis below CGd b,)
Stress at neutral axis
-
1.6 Check for stress
11851 k g h 2 (Safe)
Compressive stress in concrete (acb)
Tensile stress in steel (IT& -1400.54 kg/cm2 (Safe)
LASA
Flyover at Karur Design of Pier for flyover
-
1.2 Material Data
Grade of Concrete
Grade of steel ("m" for Mild Steel & "t" for HYSD)
Load Case (N =Normal, W = Wind, S = Seismic)
Permissible axial compressive stress in concrete (G,)
Permissible bending tensile stress in concrete (0,)
Permissible bending compressive stress in concrete (acb)
Permissible tensile stress in steel ( a 3
Modular Ratio
-
1.3 Geometric data
Clear cover (d")
Effective cover (d'=dW+/2)
Diameter of column (d)
Bar Diameter (4)
n Number of bars
r,
Reinforcement area (A,,)
Reinforcement %
-
1.4 Prowerties of uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calcdated direct compressive stress (G,,,~)
Calculated bending compressive stress (a&,&)
Interaction formula :
a,,dIa,+a,b,4/a,b 5 1.0
4
-, -
1.5 Pro~ertiesof cracked section
Neutral axis depth (n)
Distance of centroid of cracked section from centre of circle
n Cross-sectional m of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
Effective moment of inetria of cracked section
Calculated distance of neutral axis below CGd (yd)
Stress at neutral axis
-
1.6 Check for stress
132.23 kglcm2 (Safe)
Compressive stress in concrete (a&)
Tensile stress in steel (crSb) -1815.20 kglcm2 (Safe)
LASA
Flyover at Karur Design of Pier for flyover
-
1.1 Load Data
Axial Force (P)
Moment @I)
-
1.2 Material Data
Grade of Con& M30
Grade of steel ("m" for Mild Steel & "t"for HYSD) t (One Span Dislodged
Load Case (N= Normal, W = Wind, S = Seismic) n Condition)
Permissible axial compressive stress in concrete (a,) 75.00 kdcm2
Permissible bending tensile stress in concrete (o,) 6.70 kg/cm2
Permissible bending compressive stress in concrete (qb) 100.00 kg/cm2
Permissible tensile stress in steel (a,J 2000.00 kg/cm2
Modular Ratio 10
-
1.3 Geometric data
Clear cover (d")
EfFective cover (d'=d''w2)
Diameter of column (d)
Bar Diameter (4)
.n Number of bars
Reinforcement area (A,d
Reinforcement %
-
1.4 Proverties of uncracked section
Cross-sectional area of unmcked section
Moment of inertia of uncracked section
Calculated direct compressive stress (a,,,)
Calculated bending compressive stress (o~~,,~)
Interaction formula :
a w , d / a , + u ~ , d / u ~ 51.0
Resultant compressive stress in concrete (aqd)
Design the section as cracked section
L .
1.5 Pro~ertiesof cracked section
7
7
1.6 Checkforstress
Compressive stress in concrete (a&) 90.44 kg/cm2 (Safe)
Tensile stress in steel (u,d -1395.71 kg/cm2 (Safe)
LASA
Flyover at Karur Design of Pier for flyover
-
1.1 Load Data
Axial Force (P)
Moment (M)
-
1.2 Material Data
Grade of Concrete
Grade of steel ("m" for Mild Steel & "t" for HYSD) t (One Span Dislodged
Load Case (N= Normal, W = Wind, S = Seismic) w Condition)
Permissible axial compressive stress in concrete (a,) 100.00 kg/cm2
Permissible bending tensile stress in concrete (a,) 8.93 kg/cm2
Permissible bending compressive stress in concrete (a*) 133.33 kg/cm2
Permissible tensile stress in steel (a,,) 2666.60 kg/cm2
Modular Ratio 10
-
1.3 Geometric data
Clear cover (d")
Effective cover (d'=d1'+/2)
Diameter of column (d)
Bar Diameter (4)
Number of bars
Reinforcement area (4,)
Reinforcement %
-
1.4 Proverties of uncracked section
Cross-sectional area of uncracked section
Moment of inertia of uncracked section
Calculated direct compressive stress (rr,,&)
Calculated bending compressive stress (ad,3
Interaction formula :
%,,I/ 0, + Scb,,~ / acb 1-0
Resultant compmsive stress in concrete (a,,,,)
Desien the section as cracked section
-
1.5 Promrties of cracked section
Neutral axis depth (n)
Distance of centroid of cracked section fmm centre of circle
h Cross-sectional area of cracked section
Moment of inertia of cracked section about its own centroid
Eff'ective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
Effective moment of inetria of cracked section
Calculated distance of neutral axis below CG# (y,,)
Stress at neutral axis
-
1.6 Check for stress
62.92 kg/cm2 (Safe)
Compressive stress in concrete (a,d
Tensile stress in steel (a,d -740.86 kglcm2 (Safe)
LASA
Flyover at Karur Design of Pier for flyover
-
1.1 Load Data
Axial Force (P)
Moment (M)
-
1.2 Material Data
.- * Grade of Concrete
Grade of steel ("m"for Mild Steel & "t" for HYSD) t (One Span Dislodged
Load Case (N =Normal, W =Wind, S = Seismic) s Condition)
Permissible axial compressive stress in concrete (0,) 1 12.50 kg/cm2
Permissible bending tensile stress in concrete (0,) 10.05 kglcm2
Permissible bending compressive stress in concrete (crcb)
Permissible tensile stress in steel (ad
Modular Ratio 10
-
1.3 Geometric data
Clear cover (d")
Effective wver (a=-d"++12)
Diameter of column (d)
Bar Diameter (4)
+4 Number of bars
* Reinforcement area (&J
Reinforcement %
-
1.4 Properties of uncracked section
Cross-sectional area of uncracked section
Moment of inertia of unuacked section
Calculated direct compressive stress (aw,&
Calculated bending compressive stress (a*,d)
Interaction formula :
am,d/ o", + G * , ~1 a* s 1.o
Resultant compressive stress in concrete ( D , ~ )
W i n the section as cracked section
-
1.5 Properties of cracked section
Neutral axis depth (n)
Distance of centroid of cracked section from centre of circle
fi Cross-sectional area of cracked section
Moment of inertia of cracked section about its own centroid
Effective area of cracked section
Eccentricity of load from the centroid of the effective section
Net eccentricity
EKective moment of inetria of cracked section
Calculated distanceof neutral axis below CGd (yo,)
Stress at neutral axis
-
1.6 Check for stress
Compressive stress in concrete (o,~) 9138 kg/cm2 (Safe)
Tensile stress in steel (qb3 -1418.97 kg/cm2 (Safe)
Parmeters
Lsft Sidc Span (C/Cof Exp. Gap) " m e m
Mi Side Span (t/C of Exp. Gap)
-. Irf) Sde Dirt. Be-n Exp 6ap 8 Bearing
zsw m
m
Right Slde Dist. &tween Exp 6ap 6 Bearing - m
Left Sidr Span (WC of k i n g ) - Zrsu m
R i i Side Span (C/Cof Beanng) - 22 81? m
The line sketch for the spans and the pier is shown below.
Tht ~ p p ShPH
n tmomm&te the full train of live had.
-
The braking force is calculated as per Cl:214.2 of IRC:6 2000.
H e m Breking bnce = 20 O
h of the first train load.
Flyover at Karur Design of Pier for flyover
The span is of enough length to acwmmodate the full train of Live Load.
i 1.m
The ruution at C is given by R1
- 395.84 kn m-
9 Bmkina Force
-
The braking force is calculated as per Cb214.2 of 1RC:6 2000.
The span is of enough length to accommodab the full train of Live Load.
LASA
PIER-DESIGW MOM
Flyovsr at Karur Deaign of Pibr for Wwr
To fmd the maximum R d w we place the train of loads in such a way that
Maximum Reaction
R1 = 490~(22.8-(2.66+0.67-1.1))1(2.8)Im
RI + R2 - 917.6 kn
Longitudinal Moment (RZ-Rl)* l .l - 36.8 Lorn
Flyover at Karur W i n of Pier for Wver
Maximum Reaction
RI - 282 x ( 22.8 - ( 1.44 +3.38 - 1.1 ) f 1 (22.8) kn
Total Reaction is R l +
R1+ R2 = 235.99 + 220.47 kn
For Class A 2 Lane the loads & the moments shall get doubled of that of Class A 1 Lane.
R 1 + R2 = 2 x 456.46
Design of P ifor ffyolrsr
RACTtON DUE TO DL
15
.......... , , . . . . .c. . . . . . . ' ." ,.' 3. S. . .
-.........2.5-....................................................................
L C . , 21595 ;
2
1 8.. :.
--..---..-- 2 a !LP?.sP.-j
i,..- .......
3 m
R . .
: .-..,-.--
.
Z .
i a...--..L-..?;l:W .-.- i
j
!
...-. 41 ....-... A- .-.-,.. 2 .-".* i--.... 0......-..i 215.96
'
.C
.I ...... ..-.I
i
i S L2 t -.-.-.- 0 i 215.333
Total D l re&ion = 376.874
Total SIDL rasdion on Par = 105.952 Tonne
- -
PIER-DESIGNIINPUT-DATA LASA
Flyover at Karur Design of Pier for flyover
C --
h
A)
From Pedesf2ils (if anY)
Volume of 1 Pedestal = 0.7 x 0.83 % 0.25
= 0.14525 m 3
No: of Pedesfal = 3 x 2 - 6 Nos
.: Total Volume = 0.14525 x 6 = 0.8715 m3
.: Total Load = 0.8715 x 2.50 = 2.1788 T
.: Total Volume
.: Total Load
-
FM Bed Block / Piel CQ
- 0.5 x
Area inelevation
.: Total Volume
.: Dead Loed
mans Fw desfminuPier
1 m x D L + L L on o m smn*L CVL+&&nQ -
2 Max ClL+LL on one snav+LWL+wfnd+B~rim.
3 /ray l;)L*U on 010 s p ~ n + L W L + E Q + B ~ a n n q
4 ~~ofonesrxln
5 DL of one sm+wind
6 DL of one w n + E Q
Bdina dbc?
Braking Lo&
vr.Ltc
-- 6.00 tonnes
F =FN2 + Vr.Ltc
PIER-DESIGNIDesign of Pier
Flyover at Karur Design of Pier for flyover
Cenfrifuqral force:
The centrifugal force shall be detrmined h m the following equation (IRC-6:2000, clause-215)
C - - W v2
127 R
Where C = Centrifugal force
W - Load in tons
- 91.8 t
v - Design speed of vehicles
- 0.0 KMPH
R - Radius of curvature in meters
- SM.b m
C - 0.00 t
CentMugalf~me = 0.00 t Distributed on Two pian
per pier
Check for wind load (IRC 6: el. 212.3) (Wind is taken on longer span for simplicrty)
Height of deck from mid pier 4.50 m
Height of deck pier base 7.30 m
8) Exposed area of deck and railings
- 2600 htx 25000 length
- 65 m2
avg ht above bed level -
, ,>
-- 7.3 m
min pmssure = . ., 1 , . 2.40 KMm2 (IRC 6: c1.212.3)
fom =
-.
- .
,-*
-7
'.,
15.6 T
Momemat~ ' r - 6 e s e,,
#.
,'j
', ~.,
-
'--.
-7
113.9 Tm
\-:, , J ,,: ;: 1
I .;1 ' .J>> :<
.
. ., '
%
. -..;,:,:--
.. ..
u.../-:.
/+- .-;
-, hp(' - --
-.----
i -.
1 LaSA
of Pier
pl~~-CjESlGNlOe~ign t
Flyover at Karur Design of Pier for flyover
Pier Shan
-
- 8990 x 2000 = 17.98
avg ht above bed level 4.5 m
mm pressure = 2.40 KWm2 (IRC 6: c1.212.3)
Total Wind F o m 4.32 T
Moment at pier base 19.4 Tm
.- L
..
Factor = 0.06
Bearina Level = 505.1793 m
seismic times at pile cap level
- -
LASA
PIER-DESIGNIDesign of Pier
Design of Pier for flyover
4 DLof OneSwn
- Check for sbesa In Pler
I I Load em Moment
Phr Dexl Load 1334 00 00 Design Axlal load
Super StructureLoad 201 5 245 7 Design Moment (tr)
Design Moment (long)
C . Z - - "' . I , 1.1
5 DL of One S ~ a n
+wind
C k k for rtress in Pler
8 DL of One S ~ a +EQ
n
Check for atmcs In Pler
LASA
Flyover at Karur Design of Pier for flyover
A
I A - . - .
0.00 Tm
--
LASA
Design of Pier for flyover
LL Supstr Rwn
1 750, Tdal Applied load 39.81 + 134 = 174 f
Proportion of applred loads 174.1 x ,900 = 188 8
830
. - . .I
i 2000
2650
-
I CL OF PIER DL of Canti!eeverbeyond deff
6.3 +
0.00 T
1978 T
Shear due to Torsion
3.4
PIER-DESIGNIPier Cap
Design of Piir for byavn
Flyover at KINr
[h*
, ,- . .
of Open Foundation 1 sc*mkrorr.m
0 F d a t i m Dimension
-.arn
B(y)=
Bc=
I.w rn
;,:,7? m
r P i u Lead L k t ~
P =
k =4 -
b -k -
( a t Top of Fodoiion)
-23 kN
3212.13 kNm
-1.a kNm
Hr- 0 kN
Y - 481.8!J1 k N
A* Effcct~wbw
A v q l c EffeCt~u&pth d :
- 0 095 m
I755 rn Ck.tkkXXIln
OI
6rwr b ~ q R L a u n =
Gross @enr~ng Ressure - 382.213 W m f
573.32 M m 2 PcfibirqnOmnr
sealrbngwl
Motrrklr Lkcd tkckhvy*
6r.L uf bnntr ; 13- flq Shw
A * v a g r Cherburdcn Pressure:
+ 63.0 W/m2
;y
C.8 2m
-Rrcnre
PIA : 1701 kN/m2 pl = P/r\ - M d Z r . &/z= M8 k~/m'
MdZr: 35 4 k ~ / m ' p2 = PIA MTIZ,. ML/& = 130.6 kN/mZ
PIER-DESIGNKJpan Fwndabon
h?- fm:
M*rwW.l)(l#
Pt
R= I5U.7 Ma'
Pa' wo w m '
U=I 2m v
USA
Design of Pbr lw Wa
d = t-&-bV8 : 3038 m
R= 1.481 N/m2
d*: ( M I R ~ =' ~ 11m nun
Eff cew= 105 mm OY
1745 mm
hvhm
1
~:
(p3*fln/2=
h= 1345m
283.4 W m I
,,,,, +..------------.- kt-
A2 =
Vol =[A1 .
(pX3. pX4)%/2 ;
A2 + s q r t ( A l A Z ) W =
260.2 kN/m
365.4 kN
v'. 365.4 k N
M= 242.2 lcNrn
0'. 1.279 m @cpm d racrirn at v3V4)
d= 1.184 m (Eff bcpth o f sertiand Y3Y41
bl = 5.510 m
b2=
tm 8 = 0.356
LCW o ~ I ~ ~ / ~ ~ ( A I + z * ~ ~ ~ A I A ~ ~ ~ A =Z ] / { A ~ ~ A ~ A Z ~ A ~ )
v' = 3 2 5 5 685752 kN (Vol of pr. Oiagrrm)
M= 4870 597063 kNm
-
R=
A. = 15521 mmz
d-= (M!R~Y= 1041 rnnr
Eff cow3 85 m n OK Bar d~o= 1 0 mm
in W d~mctim =
do in X* direcfii =
LC'=
g
A m=
.
sc' =
2yec' + LC/] =
Min A w ;
PIER-DESIGN- Feu-
Design of superstructure
The end cross girder Is design as a continuous deep beam for bearing replacement condin, oont[nuous over knife supports at
the Jack locations. The center line of the jack location are taken to be 650mm from the the center line of bearing. The reaction
of main girder due to (DL + SIDL) are applM as bad at the girder locatlon as shown below. The value of KFY Is adjusted In
such a wav that the reactiis in su~wrtsA.0.C.D.E and F are same.
Effective Span
Smaller of the following
(i) c/c distance bebveen support
(ii) 1.15 times the clear span
I -
- 2.990 m
D -- 1.7 m
110 -
- 1.759 > 2.5 (for continuous beam)
Hence as per Clause 29.1 of IS 456 - 2000 the component shall not be design as deep beam.
Lever Ann jd =
,-3-
1.3 &/w/ation of R e r h m e n t
rn
Rein-t
1.3.1PaslPasltive
Reinforcement required
Provided Ast
- -
LASA
ff utawl&uR-
Y
Minimum Side Face reinforoement rquhed = 0.12/100 * 400 * 1700 * 0.6
-- 489.60 mm2
Reinforoement pmvidd - 2306 m2
[Rd:DesgrofmxGlrderkskadeet]
OK
L4.
m .
-
Provided spadng
11,= V, .s/05.d
2.0 Design of End Cross Girder as Bracket [Ref. "Concrete Bridge Practice: Analysis, Design
and Economics" By Dr. V.K. Raina]
a, -- 0.650 m
Effective depth d' - 1.6025 m
a, 1 d' - 0.406 m
<1
The cantilever portion of the beam shall be design as bracket
n
v, - 2223 mm'
= 0.85 f, p
- 415 NlmmL
fsy
F
- 1.4 [for Convete placed monolithiallyaaoss interface]
&=Maxof
(0(4 + A3 - 2849 mm'
(ill (2/3*& + A3 - 2104 ltIm'
(iii) (0.04 f,' / )f, *dl b -- 1730 mm'
Hence A, required
-4
A,,=Maxof
L -
T-7 (i) 0.5*&
(ii) 1/3*&
Provide 14 m. lO+ + 6 m. 16 4
-4 -- ~ 0 mm'
6
OK
So, provide 7 nos. of 10 mm db bars an both faces equally spaoed.
Provided A,
Design of Supemtructure
Effective Span
Smaller of the following
(i) c/c distance between support
(ii) 1.15 times the clear span
I - 2.990 m
D - 1.7 m
I/D -- 1.759 > 2.5 (for continuous beam)
-
Hence as per Clause 29.1 of I S 456 2000 the component shall not be design as deep beam.
Lever Arm jd =
1
Reinfo~ementrequired
Provided Ast
X -END-GIRDER/DeepBeam
d
jd
i
,
Required Ast = M / (a, * jd)
Minimum Mnfarcement required =
wnforcementrequired
-*no.-
x 4
Mlnimum Slde Face reinforcement required = 0.12/100*400*1700*0.6
- 489.60 mm2
Reinforoement pravided -- 2306 mm2
[Ref:~dEr~dX~asbadretl
OK
l.4--
T ~ =Max.pemriSSlbleshear
-- 1.7 N/mm2
OK
fc= Permissfbleshear stress of amek -- 0.298 ~/mm'
- 0.222
Henae Shear rebif. Required
Provided spacing
A, = V, .s/q.d
2.0 Design of End Cross Girder as Bracket [Ref. "Concrete Bridge Practice: Analysis, Design
and Economics" By Dr. V.K. Raina]
a,
- 0.650 m
Effective depth d' - 1.6025 m
a, 1 d' - 0.406 m
<1
n The cantilever portion of the beam shall be design as bracket
fw
- 415 WmmL
P
-- 1.4 [for Concrete placed rnodithically acroa interface]
- -
LASA
&=Max&
(1) (4 + P3
(ii) (2/3*& + 4)
(iii) (0.04 f,' / f,) *dmb
8 nos. 20 $
- 6446 mm'
OK
A,,=Maxob
n (i) 0.5*Af
w (ii) 1/3*&
Provide 14 m. 10 0 + 6 nos. 16 4
- 2306 nun'
-4
OK
So, provide 7 nos. of 10 mm dia bars on both faces equally spaoed.
CFbovefJt ?@fur Design of Superstructure
Effective Span
Smaller of the following
(i) C/C distance between support
(ii) 1.15 times the clear span
I - 3.000 m
D -
- 1.7 rn
I/D
- - 1.765 < 2.5 (for continuous beam)
Hence as per Clause 29.1 of I S 456 - 2000 the component shall be design as deep beam.
Required Ast = M / a* * Z
h
Minimum Reinforcement required = 0.2/100 * 300 * 1700 = 1020 mm2
X-INT-GIRDER/Design LASA
FCyoverJt mrur Qtary Design of Srcperssiucture
Distribution of Reinforcement
The distribution reinforcement over the support of a deep beam is placed in two zones
ZQna
It is the zone of depth "0.2 * D" ,adjacent to the tension face,and contains a proportion of the
tensile steel given by
0.5 * ( I / D - 0.5 ) - 0.63
zm!cu
It is the zone measuring "0.3 D" on either side of the mid depth of the beam, which shall contain the
remainder of the tension steel evenly distributed.
Provide 6 nos 10 I$ + lm 16 4
on each face
%
r ,
= Max. pennisslble shear - 1.7 N/mmL
OK
'Tc= PennissiMesheardnssofamrete - O.ZS9 N/mZ
LLnr arm =LA = h / 4 . ( A l ~ P q r t ( A l A 2 ~ 3 A 2 ) / { A I * q r t ( A l A 2 ~ A 2 ) 2)
v': 2 6 4 6 . 6 W 161
M= ~ 7 9 8 . n 4 w 4kNm
4. =
L - 8.1 m
14291 mm'
Bar d l 6 a mrn
Spcclrrg = mm
A, pmvidcd; rnmz OK
4. Min; mmz
Prov~dcT20 @ lXNnm Alng W d~rectim
[almd-.I*-W
Ovcrhorg;
Al: (p3*p4pu2=
h: 1.545 m
202.2 W l m
--t
--;
I +
hr
1
p3 r 151.3 pz= m9
i+T
A2 = (pX3 + pX4).LIP =
Vol :[A1 + A2 + qflAIAZ)~h/3 =
183.3 W/m
297.7 kN
lnw cm = L A . = h / 4 * ( A l r T ~ A I A 2 ~ 3 A 2 ) I ( A l * r p ~ A l A Z p A 2= )
pY3= 141.9
0.760m
B.l l m
+
pY4 = 4 S
b'= 297.7 k N
M= 226.2 M -
V=U' m/dgta@= 242.5 W
u(F--
0' ; 1.226 m (D@ af sectla at V3Y4) t, = vlbld' = D.M3 ~/rnm'
n b:
bl =
1.131 m (Eff brpth of sectionat VW4)
5.010 m
r,= 0225 Wmr' Ow
-,
u K-
tong= 0.276
r* -&
Dwhwg=
A1 : (p3 p4YV2 =
h= 3.05 m
r r t l ~ YlWr
818.9 W m
l
& p3T-{; .-
pVl = 1327
-.---
4-
+
A2 = ($43 * p X 4 Y U 2 = b68.1 M m pY2 I 3...3
Vol of p.da:[Al A2 qrt(AlAt)rh/3 = 2263.9 kN LI.1
M:
z
~ W V ( A l + r ~ A W ~ 3 ~ I ( A l ~ A I A= 2 ) . A ~
2263 887466 kN (Vol d pr. Dugrat)
3335 542667 kNm kOc*TO b
Thhs section o t the tooting a t Sez X W will be rrapczo163I It5 morncm ot
ruishmcc cm k mku!utrdby corsiderlngu t to be a rcctangk of effective
- 1.473 m
23 n --+-
width 8'.
A,
pwridd:
M~nz
tilo
1 4 ~m2
3
W
m
14726 mm2
a
Provide R 0 8 lYkun c/c Along XX d~rrctim
& . & , m - ~ , , ~
Doin XX d i d i o n = 1.434 m
do an XX direction = 1.339 m
LC'. 3.535 m
sc' : 3 . 1 ~ m5
4= ~ [ d
LC'].: 14420 m
A- = 19.573 m2
Do inYY d i m i o n :
4 m XX direction =
LC' :
ec'.
b. ~[sc'+Lc']:
Arm =
Min A m = 19.673 m2
1.0 INTRODUCTION
The 25.OM PSC T-Girder with cast-in-situ deck slab have been adopted for three
Flyovers Chainages (298+300) at NH-7 Clane Proposed carriageway with 3x25.0m span
arrangement having 3nos. Post-Tensioned PSC Girders @ 3.0m c/c The proposed span
arrangement has been provided as per smooth flow of traffic .
No, of Spans
Span length (clc of exp. joints)
Span length (clc of bearing)
Total Length
2.2 GEOMETRY
Carriageway Width
Overall width
Width of Crash Barrier
Width of safety kerb
SUPERSTRUCTURE
FOUNDATION
Foundation
2.5 MATERIAL
0.40 forPSC
EMBANKMENT
DESIGN PHILOSOPHY FOR DESIGN OF FLYOVER PSC-T GIRDER SUPERSTRUCTURE
The Reinforced earth wall has been provided behind the abutment, Therefore no active earth
pressure acting on abutment
The design of various components of the Flyover, in general are based on provisions of
IRCIIS Codes. Wherever IRC code is silent, reference is made to other Indianllnternational
codes and standards. The list of IRC Codes (latest revisions) given below will serve as a
guide for the design of structures.
IRC: 5-1998 Standard Specifications and Code of Practice for Road Bridges,
Section I- General Features of Design.
IRC: 6-2000 Standard Specifications and Code of Practice for Road Bridges,
Section-ll - Loads and Stresses.
IRC: 21-2000 Standard Specifcatins and Code of Practice for Road Bridges,
Section-Ill - Cement Concrete.
IRC: 18-2000 Design Criteria for Prestressed Concrete Road Bridges ( Post
Tensioned Concrete ).
IRC: 782000 Design Criteria for Foundation & substructure for Road Bridges.
4. LOADING
Unit weight for Dead loads calculation shall be considered by adopting unit weights as per IRC:6-
2000.
m
4.2 Super Imposed Dead toad (SIDL)
Wearing coat
For calculation of load due to wearing, thickness of wearing coat 65mm has been taken.
Safety kerb
750 mm width of safety kerb and 250mm depth has taken for calculation of load due to safety
kerb.
Crash barrier
For calculation of weight of Crash barrier the cross sectional area af 0.361~12 has been
considered. /=-?:,-,,.-
)LC v-,
- I
1 i: . fi, I I
,-, 2 .'L , --- 4
p ,., " I
t,\w- ;,:*,/ - -
\I.-
DESlGN PHILOSOPHY FOR DESIGN OF FLYOVER PSC-T GIRDER SUPERSTRUCTURE
4.3 Live Load (LL)
1 lane of Class 70R Wheel in combination with single lane of Class-A conforming to IRC 6-2000
has been considered in analysis and design for three lane carriageway.
Poisson's Ratio = 0.2 and Modulus of Elasticity is taken as per Table 9 of IRC: 21-2000.
n As per IRC :6 - 2000 Project Corridor fall in Seismic zone Ill. For calculation of force due to
seismic the following parameters has been taken.
The force generated by Centrifugal action of moving vehicle caculated as. per IRC :6 -
2000.
STRUCTURAL ANALYSIS
DESIGN PHILOSOPHY FOR DESIGN OF FLYOER PSGT GIRDER SUPERSTRUCTURE
5.1 Method of Analysis for Longitudinal Girders
The analysis of the T - Girder for longitudinal flexure shall be carried out using grillage model on
STAAD Pro on the following basis:
o For the design of the longitudinal Sections, moments and shear force shall be determined
at an interval of every Ll8 and at d' effective from support.
o Members along the longitudinal Direction shall be along the longitudinal beam and at the
ends.
Transverse members of the grillage other than the cross - diaphragm shall be modelled
as slab elements.
a The end cross diaphragm also designed for the jack up condition.
The effective flange width calculation for determination of sectional properties for the longitudinal
and cross diaphragm shall be done in accordance with IRC: 21 2000
Value of friction and webble coefficent ( p and k ) for pre stressing strands shall be
considered as v = 0.20 and k = 0.0030 (Refer Table -5 of IRC: 18-2000)
Relaxation loss shall be computed considering reluxation loss of 2.5% at 0.7 UTS
and 0% at 0.5 UTS for intermediate values, linear interpolation shall be done. (Refer
Table 4 A of IRC: 18-2000)
DESIGN PHILOSOPHY FOR DESIGN OF FLYOVER PSGT GIRDER SUPERSTRUCTURE
Ultimate resistance of T-Girder in flexure shall be checked against yielding of steel
and against crushing of concrete as per cl -13 of IRC : 18-2000.
Section cracked or uncracked in flexure has been decided on the basis of whether
the maximum ultimate capacity in shear is governed by the cracked or uncracked
capacity. Where uncracked capacity governs the relief due to prestressed force shall
be added to the shear capacity of the section obtained based on CL 14.1.5 of IRC :
18-2000.
The stress shall be checked for 20% higher time dependent losses like creep,
shrinkage, relaxation etc. as per CL 7.2.4 if IRC : 18-2000.
Duct diameter ( internal ) is considered as 90 mm. Clear cover protecting cable from
the nearest concrete surface is kept as 75 mm as per IRC : 18 - 2000.
Prestress Stage I Cables after 14 days, after a concrete has attained a strength of
35 Mpa..
Erect staging and shuttering for RC top slab supported from bottom bulb of girders.
Stress Stage 1I cables after 42days of Girder casting, after concrete has attained a
strength of 40 Mpa.
The end cross diaphragm shall be designed for the jack up position for replacement of
bearings.
DESIGN PHILOSOPHY FOR DESGN OF FLYOVER PSGT GIRDER SUPERSTRUCTURE
7.2 Steel and Concrete cover
HYSD bars (Grade Fe 415) conforming to IS :I786 shall be provided. For pre stressing
19T13 cables conforming toCL 2 of IS : 14268 ( low reluxation strands ) with bright
metal seathing shall be used.
Drainage spouts shall be placed not greater than 6m center to centre. Down take pipes
will be provided to dispose the water below soffit of the super structure.
Strip seal type of expansion joint is proposed for PSC T-Girder type superstructure.
This note pertains to the design of Sub-structure i.e. Pier, Pier Cap, Abutment Cap 4 Stem,
Dirt wall and Foundation (Pile).
For the design of Pier the vurious forces that are considered are as follows:
For the design of Pier Cap it is checked f o r Corbel and Cantilever and accordigly designed
in an In-house Excel Worksheet.
The design of Abutment Cap 6 Stem, Dirt wall has also been designed in an In-house Excel
Worksheet.
For the design of pile Foundation, the load a t the top of pile Cap has been computed and
then by using In-house excel worksheet design has been done.
Flyover at Karur Design of superstructure
CABLE PROFILE :
Outer Girder
A Total of 3 cables of type 19K13 ( 19 strands of 12.7 rnrn nominal dia each ) and proposed as
1 Dummy cable are shown in attached cable profile.
-
In cable 2 and 3 all 19 strands are placed and stressed to a jacking force of 0.75 UTS.
In cable 1, 12 strands are placed and only 10 strands stressed to a jacking force of 0.75 UTS. In case of
emergency remaining cables can be stressed to 0.75 UTS, thus satisfying the requirement of 4% cables
for emergency as stipulated oin CL 22 of IRC 18.
Radius of circular curves at bends is maintained greeter than 10.6m thus satisfying the clause 20
of IRC 18. Which states that R should be >= 1.5+700'13( dia )I1000 = 10.6m. The minimum spacing of
cables is maintained 180 mrn, hence clear cover is more than diameter of duct.
1 I Cable no :
Ilclem 1 Unit 2 1 3
I Coordinate at x 3 =
skirtof &=
m
Jmm
]
1
I
8.2
120
1
1
1
4
-120 *
S l m 6. H.IICOW
I coordineteat
start of CU~W
&=
Lx
m
1 mm 1
9.4
180 1
5.2
-180 SW>6.-Ou
I
---A+-
--
I-Z~~~I~G'G
- -- -- : 3
--
cam-no*
-0-
, ---d
Flyover at Karur Design of superstructure
LOAOIN6S
d' away f m
U8 1 V4 3U8 V2
slpp#t 1 -
2m 2.B5m 5.7~1 8.- , 11.4m
4. A r m of H~ghTens~leSteel (mm2)
------ A5 4737.6 4737.6 4737.6 4737.6 4737.6
5. UWmote Stmqth by p l d af
11963 12257 13309 136M 13792
stad (KN.m) wd+A
6. Wldth (effectwe) of web (m) b 0.65 0.3 0.3 0.3 0.3
7. Flange W ~ d t hof Tee (m)
6. Th~cknessof Fhnge of Tee beom
Bf
t
2.806 2.806 2 806 --
2 806
0 25
2.806
0.25
9. Vlt~motrStrength by CNshlng
-of C o n c h (KN.m)
(btL 36798 27594 30696 31767 32143
10. OLs~gnUlt. Strcngth (KN.m) % 11963 12257 13309 13648 13792
11. STATUS OK OK OK OK OK
LASA
Flyover at Karur Design of superstructure
Total S t a p 2 I I I
C6 o f Tendons from bottom 1 0.4651
Flyover at Karur Design of superstructure
SHEAR A T DIFFERENT S C I l O N
PedestrianLL(KN) 0 0-
0 0 0
Carriageway U (KN) 349 310 235 235 155
-6-
(KN)
0.67"b.d.(f 1Z+0.8f~f+loS -
1631.9
--
1834.8
2204.1
1399.4 813.6 818.9
872.3 818.7
Flyover at Karur Design of superstructure
FRICTION-INNER-FINAWu LASA
PGBI
Design d s u p e ~ d u m
(")NoMlrnrVlsd:
Yd (m] = Vrrtieal Ordimte of thbk frmsoffit of dcck
0 (dq) = h b t i v e arrgk of &viatiin in radian from jacking ud
P. = Forcc at the critical r r c t i o after
~ transfer (i,e after slip ot anchorage) (KN)
Flyover at Karur Design of superstructure
Component (*)
I Cable No. / 1 I 2
Nodal Points of the Cable
I 3 F 4 1 5
3
I Component (*)
I Cable No.
1 I 2
Nodal Points of the Cable
I 3 1 4 I 5
h
Flyover at Karur Design of superstructure
FRICTION-INNER-FINAUPZ
Flyover at Karur Design of superstructure
LASA
Flyover at Karur Design of superstructure
C ) Notations Used :
Zx (m) = Cumulative Length of Cable from jacking end in metres
18 (rad) = Cumulative angle of deviation in radian from jacking end
Po = Force a t Jacking end before transfer (KN)
P,= Force a t the nodal points before transfer (KN)
E. Elongation
- Calculation -
Grip Lenqth 0.6 rn
Nodal Points of the Cable
Component (*) Cable No.
-
---
1 2 3 4 5
Px 0.00 0.00 0.00 0.00 0.00
B. M a i l s of Prestressing Cables
C
El, Rise in mbh ut mL Jacking end E3, E f f c c t i Cover
~ t o 6bk
2. Risz in cdk a t tk end of c u d portion
1 Lb
C
ffan o f Cabk
a;:
~ b wmon.
n PI
I?.Clr43CI
CI s 3
Flyover at Karur Design Of Superstructure
The following calculations pertain to the design of single span PSC Post Tensioned T-
Beam with Cast in situ Solid slab. The span arrangement is as shown in the attached
sketch.
The proposed arrangement of PSC girders has been shown in the following pages.
The beams are supported on bearings and the prestressing is canied out. Then the Deck
slab and cross girders are cast. The spans for the beams on bearings is 22.80 m .
The Dead load of beam and slab are taken to be acting on the individual section and
fi the SIDL and live load are taken to be acting on the composite section. The distribution
of the same is calculated by grillage analysis, using STAAD-Pro.
The bending moment and shear forces are calculated at different sections and the beam
is checked for stresses at different stage of casting and prestressing. The stresses for
temperature are taken with 50% Live Load.
Girder Section is also checked for shear based on the ultimate theory and also for
ultimate moments, as per recommendations of IRC-18.
2 Prestress Stage I Cables after 14 days, after a concrete has attained a strength of 30 Mpa.
-?
4 Erect staging and shuttering for RC top slab supported from bottom bulb of girders.
6 Stress Stage I1 cables after 42days of Girder casting, after concrete has attained
a strength of 40 Mpa
,
' -' :\
7 Cast the crash barrier on either side.
- -
Cg$
LASA
Flyover at Karur Design of Superstructure
SUMMARY OF UCmA EXTREME FIBRE STRESS (Considering 20% Extra time Dependent Loss)
4
--A-
stage Top of Slab Top d girder Bottom Allowable Stre#e
max +ve max -ve max +ve max-ve max +va max-ve T6mpwsvStag
After 1st stage p f e s h ? ~ -3.57 -101.52 1206.35 680.43 Cornp 2C
Before 2nd stage prestress 3.71 -81.50 1134.77 644.41 Tension 1
I- unit 1 2 3 4 s
-
CG ofseCtlan hm M V x n
In- of section
Top section Modulus
Flyover at Kawr Design of Superstructure
Item Unit 1 2 3 4 5
Chairwe of Section from left support rn 2.m ZBSO 5.780 AfSb 11-
-
LASA
Flyover at Karur Design of Superstructure
4 5
From 14 to 42 day
due to GR I Tendons
I
Top ~ / m *
Bottom ~ l m '
2.38
644.41
-57.89
1085.35
-81.50
1134.77
-33.59
1115.55
3.71
1071.17
Itan -Unftr 1 Z 3 4 5
~DetaihdStapeXlp~npatter42day
lIDof T~ndonsof lQT13
P r ~ n mrce g (P21
CG of Tcndons from Bottdm
-
,
i Ecccntnctty of Tendons
Prestre~s~nq F a c m Uop)
r ~ e s due
s to Elon of Gr Itendons due to Gr lI tendons-
2.42 3.81 4.00 4.00
I
-12.17 -13.63 -13.83 -13.83
Item Unit 1 2 3 4 5
StressduetoC+S+R
.
Top ~ / m ' 1.36 1.20 0.86 0.42 0.17
EbtWn ~ / m ' -0.43 0.41 -0.23 0.02 0.35
m ,---
LASA
Flyover at Karur Design of Superstructure
p-lng Faetor
Gr. I 'np 6.27 4.41 -0.n 4.w -0.54
Gr. IBottom 1.# 2.42 3.17 3.21 3.21
Gr. I1 Top 0 .+I 0.27 0.02 4.25 -0.38
Gr. I1 Ronm 0.63 1.49 2.02 2.511 2.85
Gr. m Too 0.00 0.00 0.Dl 0.00 0.00
I
Gr. UI bttom 0.00 0.00 0.00 0.00 0.M
osa
LASA
,Check for loss due to E l m c Sllortcninq
Gr t 0.00 0.0
Gr n 0.w oa
Grm 0.OD 0.0
PratP!dng FBcta I
Sr. I T w 4 . 7 -0.91 -0.9 4-54
Gr. 1 Bomm I .R4 2.92 3.17 3.21 3.21
Gr. I1 Tr)p 0.44 0.27 0.02 -0.25 -0.38
Gr. TI BoKm 0.63 1.49 2.02 2.58 2 85
t r , 1II Top 4 . -0.60 -0.68 4.68 -0.68
3
Gr. m Wttom .48~ 2.58 3.48 3.49 3.44
Flyover at Karur Design of Superstructure
Item Unit 1 2 3 4 5
SbesresduetoC+S+R
Top ~ l r n ~ 0.00 0.00 0.00 0.00 0.00
Bottom M
T rn2 0.00 0.00 0.00 I
'51ress befwe shR of Bearlm
TwdaedtSrsb 7fd -11.51) -1.437 -32.89 41.84 4.93
Tap ofC;lrder ~ / m ' 234.21 E6.57 352.95 411,83 ' 489.56
&onim flm' 504.22 94942.39 898.59 857.35 813.45
hess at CG of Tendon I ~/rn' 134.56 836.10 R51.05 825.92 7w94
s CG of Tendon I1
S ~ e s at ~/m' 372.35 5#.56 M1.31 751.'32 7R.42
Stress at CG ufTendon In ~/m' 504.22 942.39 89B.59 857.36 813.45
Averqe S M at CG of Tendon GRI ~/m? 7R1.45 -
Average SbesE at CG of Tendon GRII ~/m? 635.17
Average 5tff54 Bt CG d Tendon GRm ~[mj H39.29
Relaxation F a m Gr III
0.m
C M k f o r s a x a t h n l o ~ of
r Gr IlI
= c I . W O ' ~ ~ - ( ~ . ~ - ~ ( O . Q O ~ ( O ~l~~.OO+~E~*~~~~~.DQ .3Z)~*~O. .~ W~ 1 * 1 ~ 2
Check For Creep LWE. of Gr III Cables
=J&[037-0.0003R7)'0'0.00 tH753*195~'l.2*839BYlMM 0.M
0.m
Relaxat~onLoss of Gr. ll CWw
- d Chprk for CrwP Loss af Gr I 1 Bbk
=jl? D00387-0 W0387)"0.526315789473684*(1.M1187a1t95WOW)'1.2*636.16 0.00
-
LASA
Flyover at Karur Design of Superstructure
1tem Unit 1 2 3 4 5
,Ulainage of Section from left support rn ZOBO 28S4l UOO LS- IMOQ
PPlamtlon F e Gr E
0.m
Relamth Lea af Er. ICables
=o ~ o ~ ~ ~ ~ o . ~ ~ ~ ~ . ~ D ~ I z . D o o D o s ~ ~ ~ ~ ~ J * ~ ~
Chwk !or C r e w L a @F Gr I Cahles
=to ~ G W - 0a m j ~ 7 ) = 2 . ~ 1 ~ ~ o n 6 3 i m o . w 1 ~ m ~ i ~ ~
0.m
-1.~18~.4~1,
oma ant due to sift of Bearinas ~ r n 0.m I 0.00 0.m o,oo 0.m s
r,, !
Stress due to Sh~ftof Beanngs
TOP TI^^ 0.00 0.00 0.00 0.00 0.00
~otfom TI^^ 0.00 om 0.00 0.00 o.00
L o s s s s from 42 to 42 day
,Creep Loss of Gr. UI Tendons I T ' 0.m 1 0.00 0.00 I 0.00 0.00
Shrinkage Loss of Gr. III Tendons T I 000 0.00 0.00 0.00 0.00
=(O 0001810.000181)*0*0.0018753*19500000*1.2
Relaxation Loss of Gr. III Tendons I T 0.00 1 0.00 0.00 0.00 , 0.00
r
'Swessesdueto~+s+ R
I
LASA
Flyover at Karur Design of Superstructure
Item Unit 1 2 3 4 1 s
Chainage of Sedion hwt left support m 2.000 2S5fk 5.70Q a550 lUOO
0.m
ChedcfwdarellanbssofGrIll
=0.~*[1~0.7-{(83B.5~[D*3.09.03)~}~2LZ.~100*~D.75*349.03)*Q.MID*~2
Checx for Creep Lo55 of Gr IT1 C a b l ~
-=:0.000387-0W ~ H 7 ~ 1 ' 0 * 0 . 0 0 t 8 7 5 3 ~ 1 9 ~ * l . 2 * 8 3 8 . ~ 1 7 / 1 O W
Rclmatfwr Factor Cr II
0.00
= O R 5 -0.71- 0 0.110 1
Relavaron Lo= d Gr. !ICa
m
RelmaMtn Factor Gr I
-
-0.752 - 0.74 0.1616 0 s -
Rela*anon Loss af tr. I Cabler
bOS0
C t w i fw C m a Loss of Gr 1 r_ab(es
I
SIDL applisd at 42th day Trn 21.70 77.10 6R.m 68-70 84.30
Srress d m to 51rtL
Top ~lm' 19.84 25.46 57.03 64.54 79.20
~/m' -33.95 -53.68 -121134 -136.M -166.98
LASA
Design of Superstructure
Flyover at Karur
*
Item Unit 1 2 3 4 5
-stressdue to C+S+R
Top ~/m' 12.27 20.66 28.61 31.72 31.84
Battom ~/m' -89.63 -153.36 -175.63 -188.97 -188.98
-
Sbes during Wee at infinity
Top of Deck Slab ~/m' 20.74 27.64 51.71 52.96 64.10
Top of Girder T/m2 247.93 272.33 392.00 486.33 542.86
Bottom T/rn2 381.18 737.67 610.44 541.93 470.02
P . ~ l W ~ oFaaor
n for Gr m =
=2 + ( 1- 0.000-O.QOD) 3.0m
Rclawat~antors or 5r Ln Cables at mid !pm
.=3,rsoo*(l+o,r-(o.m/(o.m=
~ ~ . ~ ~ ~ I ~ I o ~ z P ~ ~ ~ I ~ E ~ o L ~ o . ~ s * ~ ~ ~ . o ~ ~ ~ . ~ I - ~
Check for Gmp Ill Ghlcs
Lor;s of t r
L~(13.0#3B7)'0.WIMl*0.~1 8 7 5 3 ' 1 9 ~ * l . Z m R B . 9 1 r / I W o 0,W
R~~ Factor fur Gr II =
= 2 + ( 1- D.7404.000-0.110) 2.SO
Relamtlan Lnss or Gr. II Cables at mid span
= 7 I50*11-k0.740W f ( 0 . S 2 6 3 1 5 7 8 9 ~ 7 3 ~ 4 ~ . O 3 ~ ) ~ 2 ) 1 2 2 ~ 1 0 0 * ~ O O ~ , O 3 ~ ~ . R W 1 S 7 829 4 7 3 t i & 4 N 1
Check for Cree~L m s of Gr !I Cables
l . 3 0
1-
1Rdmatim Factor Tw Gr I =
2414.74 lo:16 t e ;Q- aorw
Relaxatrnn Loss of C;r. I C.a h k.at mid %mr!
2.048
1
- -
LASA
Flyover at Karur Design of Superstructure
-
-Stress at sRJiee w t h thW Lwd t';agsiw)
Top of Owk 9ab T / d 92.06 113.13 161.62 M5.53 207.55
TopolGirder ~ / m ' 296.23 326.19 461.24 582.45 633.23
5 2 4 167.55
Stren at Service with Live Load (Sagging) includhq h w e d a t l c effects and rRfferentialsettlement
,A Top of Oedt Stab ~ f m ' 92,W 113.13 161.62 205.53 207.55
Top of Girder 7]m' 196.23 326.19 461.24 5R2.45 633.23
i
Bottom T]m' 259.11 59.41 378.68 22024 167.55
Smsr at service with differential shrinkage and difkrerrtial veep effect (with Live Load)
Top of Deck Slab ~ / m ' 30.59 66.19 114.68 158.- 160.61
TopofGirder T/rn2 470.15 514.68 649.74 ff0.94 821.73
at service with differential shrinkage and diirentiai creep effect (without Uve Load)
I Top of Deck Slab ~ / m '
TopOTGmr T/m2
&Xb.m TI^'
-40.73
421.85
284.45
$;: 1 4.77
510.49 (
6.02
674.83
655.92 I 528.69 I 460.18
17.16
73131
3B8.27
<
~ u n d a r ~ L k l r w d [ ~ ) w f t h T e h m R ~
v b 50% bvr L M ~(sag] + DfferenIjal shrlnkqpe and creep
5hc5f at ~ ~ e r wn-h ,
M Top of m.k Slab Tim -5.07 23.45 59-73 82.30 m.88
TopofGlrder Tim' 44600 487.?S 615.12 722.8Q 776.54
E&mm f/m' 233.41 555.79 412.81 29933 237.04 -
-
m due m ~enm[~tselmgen s ~ r e a e s ) -
TwofD~kgab ~lm' 102.31 4flZ.V 4R2.57 W2.57 482.9
Too of Glrder ~ { m ' -30.22 -6.72 -6.72 -6.72 -6.72
~attwn ~ / dm.n 59,21 59.24 9.24 59.~4 t
Sln?ssatStlvbewlth509bUlleLoad(sg)+Temp~
Topd Dedr Slab T/& 97.24 506.02 542.30 564s 571.46
T o p o f h h T/& 415.79 481.03 608.40 716.17 769.82
Iktbm, TI& W.18 625.03 472.05 358.57 m
.28
...-
--.I-
I
L 4
-
.UI
.
I-
I *-I I 'L
I , r
.
I. r
I, ,r r
..t
"
" I
I'
I
...
.1 I
. L <
" L 4
" I
. I
..
- 2
I I,
I I,
3 11
II I
.
I U I
11 11 1
1 1 1 1
..,.
1 I,
D I,
m ,
I .I
I . ,
I I,
-
I
I
D li
1 3,
1 31
II
I,
,I,,
..
I
I
*
I,
.
.. ..
11 11
I I,
M U .
C I,
tl r
..
m 8 ,
..I 4 ,
I a,
n a:
- .. .....
q ,r
1 I, I
Y I,
I 0.
1 m,
1
.
1
..
1 I,
II "
U .
..
.) I?
II . SU ,
I S
..
I , I
n 3,
I I,
1 I,
7,
n tl
t,
*
n vI.
I I
7 . k
n r
.
....,
7 . L s7
m c 3
a,
" I
..I
L ,
.
I ,
" I
I,
I I
W lb
1 ',
I9 ,t ,
T
Flyover at Karur Design of superstructure
PSC BEAM AND RC SLAB STRUCTURE OF SIMPLY SUPPORTED SPAN( 1 X 25.00 m);
(OUTER GIRDER)
Item Unit 1 2 3 4 5
MEMBER NO
Chainage of Section from left support rn 2.000 2.850 5.700 8.5500 11.400
LASA
Flyover at Karur Design of superstructure
- -
-
Dead Load 2nd stage
Moments I Tm 50.31 1 62.43 1 110.76 137.03 148.06
Shear 1 T 20.76 1 19.63 1 11.89 6.54 0.00
Shift of Rearing
I
-
Moments Tm 0.00 I 0.0 00 0.00
Shear T 0.00 I 0.0 00 0.00
LASA. . . -
I"? b
Flyover at Karur Design of superstructure
-
Momcnrs
Shear
Trn
T
!
Differential Wlemcnt
Moments 0.00 0.00 0.00
I
Free body moment - 0
Moment Due to Continuity effect Tm 0 0 0 1 0 I 0
Moment Due to Continuity effect Tm 0 0 0 0 0
4 .": 8
- +
u ,: 0
LASA
Flyover at Karur Design of Superstructure
Stress Check for outer girder (with 20 O h extra long term losses)
d Basic Design Data
fbfrom (i)
fbfrom (ii)
Hence Not OK
H e n e allowable stress behind anchorage has been suitably increased by
reinforcement. CEB-FIRmdel mde has been used t o calculate the increase in
bearing stress.
END-ANCH
Flyover at Karur
Where,
u = perimeter of hoop = pi*(0.3 + 0.016)
s = hoop spacing
4 = Cross sectional area of hoop reinforcement
,f = design strength of hoop = 0.87 * 415
= 320 * 320
A, = Area of concrete within hoop reinforcement
= pi/4 * 0.3"2
fd = 0.8 * f,j / 1.5
,,M = Maximum moment in hoop reinforcement zone
Hence OK
OK
This reinfomment shall be provided in a zone 0.F Yo =
2Yo = 400 mm 40mmhom-
Therefore revised spacing of the spiral shall be 50 mm L r
r.- c
END-ANCH
Flyover at K m Design of Superstructure
Shift of Bearing
Super Imposed Dead Load
Live Load
Hyperstatic
Differentialkk Settlement
Effective width of transformed section
Depth of Deck slab
Depth of Girder
Distance of C.G. of bottom fiber
M.O.I. of the composite section
Type of reinforcement
Width of top flange of the girder
Minimum reinforcement
(i) 0.15 O h of the contact area
(ii)130 mm2
1' "
Y W
I
--
SHEAR-CONNECTOR LASA
---- /-
Provision of Untensioned Reinforcement in Beams
fhwkk 22 nos. 10 4
UNTENTIONED-REINF
Design of Superstructure
INTRODUCTION
The following calculations pertain to the design of single span PSC Post Tensioned T-
Beam with Cast in situ Solid slab. The span arrangement is as shown in the attached
sketch.
The ptoposed arrangement of PSC girders has been shown in the following pages.
---
The beams are supported on bearings and the prestressing is carried out. Then the Deck
slab and cross girders are cast. The spans for the beams on bearings is 22.8 m .
The Dead load of beam and slab are taken to be acting on the individual seetion and the
SIDL and live load are taken to be acting on the composite section. The distribution of
the same is cdculated by grillage analysis, using STAAD-Pro.
.*
T
The bending moment and shear forces are calculated at different sections and the beam
is checked for stresses at different stage of casting and prestressing. The stresses for
temperature are taken with 50% Live Load.
Girder Section is also checked for shear based on the ultimate theory and also for
ultimate moments, as per recommendations of IRC- 18.
LASA
PROPOSED SEOUENCE OF CONSTRUCTION AND PRESTRESSING
2 Stress Cables first stage after a concrete has attained a strength of 35 Mpa.
4 Erect staging and shuttering for RC top slab supported from bottom bulb of girders.
6 Stress Cables second stage after a deck slab has attained a strength of 35 Mpa.
' -2ndstagepresess
Before Etressing of Gr. III cables
93.53
427.32
-164.41
118.22
1653.31
1125.49
961.22
797.05 -Shpc
-wStagem 427.32 118.22 1125.49 797.05 Nomal Case
Befwe ShR of Bearing 427.32 118.22 1125.49 797.05 4ab C m p 1155
After shiR of Bearing 427.32 110.22 1125.49 797.05 Girder CMlp 1320
Before SIDL 427.38 118.22 1122.84 796.03 Tension 0
Sbes at servim 473.66 136.86 798.94 611.98
After considering hype- 473.66 136.86 798.94 611.98 Temperature Case
!i% atsservice (with U sag) 629.96 196.38 545.98 142.56 SbbGornp 1328
!itresi with LL (sag) + d i i shr 823.58 376.12 462.12 58.70 Girder CMnp 1518
!~FSS with diff shr wfo U 667.28 316.59 715.08 512.09 Tension 0
Stress at service (everything but temp) without LL 667.28 316.59 715.08 512.09
!3Es with 50%LL(sag)+temp It$e 165.77 .42.65 950.04 707.68
S k s with 50ahLL+temp fall 1233.92 688.53 977.41 661.93
s
1
-
ZUO
I1 2
2.OSO
3
L7m
4
E.5!m 11-
,
rota1Lorr In Reaea i T 95.85 1 97.47 101.85 107.16 107.~5
Ff$nwut lCprur Design of Superslruclure
1
-k d Ssction p r o m [IndMdual Bsrm Section)
' r
Area of ttre section m7 1.2616 0.8088 0.8088 0.8aE8
Qepthdthesectlon rn 1,8500 1.R500 1.8500 1.85QQ l.fl5M3
CG of sechan lrwn bottom rn 0.9643 0.968 0.9468 0.9468 0.968
I
Inerba of sc?ction m4 0.3823 0.3183 0.3183 0.3183 0.3183
TW Sect)on Mod* m' 0,4323 0 3521 0.3524 0.3514 0 3574
~ o t t ~ection
~n ~odu~m my 0.3~70 0.3362 0.3362 0.3362 0.3362
(Details d W o n p ~ e r t (Comudta
y Sedan) (14 day old slab)
ma of the section vm
'
1.5980 1.5980 t.5W
7.1000 Z.1MXI 2.1000 2.11#)0
1.S980
2.1000 1
Depth of the seMan
CGctfsffhonkumWttOm m 1.3533 1.45% 1 . 4 1.49% 1+4W6
Inartia of W o n m4 0.88211 0.7447 0.7447 0.7447 0.7447
f ap Se~tlonModulus Ill' 1.i624 1.1539 1.1!3;3s 1.1539 1.1539
W t o m Sectl~nModulus m' 0.6524 0.5;19.0.5114 0,5119 0.5119-
Item Unit 1 2 3 4 5
-
Chainage of Section from left support m 2250 l!A!XJ 5.700 8550 2 f . a .
-
No uf Tendom of 1QTl3 2.DO 2.00 2,M) 2.00 2.00
R e i t ~ s i n gFarce ( P I ) T 431.36 435,66 446.29 459.64 457.37
Ct of Tendms fmm BottDm m 0.3173 0.2867 0.1578 0.1400 0.1486
EmntTldly of Tendom m 0.6471 0.661?1 0.7WD 0.8M3 n.H059
pmtm!W Factw Fop) - 0 . ~ ~ 2-0.t136s -1.0325 - 1 . ~ ~ 2 9 -1.0579
,Pres@esstrq Factm (BotMml 2.4225 3.2000 3.5836 3.6365 3.6365
I
Strrss a m E I M c Shorten~noloss I
~/m' -162.33 -69.67 -100.94 -55.12 -17.51
Top
Ekytbm ~/m' 870.85 1145.65 1205.35 1191.b3 1145.94
I
SIRS at CG of Tendon GR I ~ / r n ~ 693.67 957.28 1093.94 1096.82 1057.89
~ v stress
g for each segment T/m2 782.61 968.44 1028.42 1007.99 0.00
Segment length m 0.60 2.85 2.85 2.85 -11.40
lenqth m 9.15
[~verageStress at CG of Tendon GRI 1 ~/m' 1 946.86 (
Avg shes for each segment ~ / r n ~ 465.86 670.43 852.56 963.02 0.00
Segment lensth m 0.60 2.85 2.85 2.85 -11.40
lenqth m 9.15
Awraqe !3ess at CG of Tendon GRlI 1 r/m2 1 737.97
PSC -STRESS-OUTER/pscbeam
af~eratlYpmr Design of Superstmdure
Item Unit 1 2 3 4 5
Item Unit 1 2 3 4 5
I
Shes5 affer d e m e or sbutWrh0 load
Top of Deck Slab ~fm' -11.90 -18.M -31.13 -38 9B 41.60
TopofGlrder f/m' 318.35 351.70 396.41 424.88 927.05
- Battwn ~/m' 801.06 1077.77 1095.83 1125.25 1137.20
Flyover at Xpmr Design of Superstmcture
- Item Unit 1 2 3 4 5
Stresses due to C + S + R
Top Tim2 0.39 0.43 0.98 1.52 1.88
I
Bottom T/rn2 4.00 -6.09 -8.13 -10.26 -11.72
~beforesbasimofGRmcaMtsat42dqr . , -
Top of Deck Slab T/m -11.51 -1763 -30.15 -37.46 -39.71
Top nfG!rd~r T/mZ 118.22 351.35 3%30 427.00 427.32
Botmm ~ { m ' 797.05 107 1.68 1067.70 1115.00 1125.49
~ k l p t a t b nFactw fm Fr. I 1 I
= .W16- 0.74 = I0.162
Relaxation Loxs of Gr. 1 C s b b at mid span
= O . :62'( l-[O.f-(160.453!(0.84LLlDR63 1RS9349.03~~~/0,2~*2,S~100*[OOTS~M99Q3~*I148421
10526315789*l.2
Check for Crwp L a a of (;r T I Cabler
*I=:O.NKl387-0.'JF113P7)': '0.00 18753' 1 9 ~ * 1 3 f 9 B t C 4 9 / 1 ~ 0.W
-np Fa*
1:r. I T?D 4.39 -0.3 -0.50 -0.51 -0.51
Gr. I Bottom 2.08 2.91 3.16 , 9.19 3.19
Gf. TI Ton 0.0s 0.08 -0.15 -0.39 -0.51
Gr. ll Rattom 1.23 1.85 2.38 2.91 3.19
~ r m. Top 0.GP 0.M 0.00 0.00 O.Cl0
Gr. Dl Botmm 0.00 0.00 0.00 0.W 0.00
Stress due to E l w of Gr KI
Top ~/m' 0.00 0.00 0.00 0.00
Bottom Tlm' , 0.00 0.00 0.00 0.00
S m d u e t o EimdGr t
TOP Tim2 0.00 0.00 0.00 0.00 0.00
Bottom ~/m' 0.00 0.00 0.00 0.00 0.00
rt r3
2
- - EJ J
LASA
Item Unlt 1 2 3 4 5
I
Chainaoe of SectIan from leftsupport m 225Q 2850 L7W lSS0 IZ-
Item Unit 1 2 3 4 5
,Chainage of Section from left support m 2250 2850 5.7m 8550 11AMJ
Stresses due to C + S + R
TOP, TI^' 0.00 0.00 0.00 0.00 0.00
Bottom ~lm' 0.00 0.00 0.00 0LKl 0.00 -
o.m
Check far d a m n loss 07 3 III
t
=0.000=(1-(0.7-I[0.00/(0'349.03))X0.2-25/100*(0.~349.03)=0,D0001-13
C h c k far Crrpp L
a of 6r [II Cables
=~U.000387-0.OM3A7)*OoOO001S~53*19~l.twlO58.912/1WO 0.0
d - O . m
Wauatlwr buf Gr. U
r C w p Loss of Gr 11 Cahtm
C h ~ for
=:n ~3B7-0.0003$7)'0.Wt.? 1 i 0 $ 2 6 3 1 5 7 8 9 * 0 . ~ 1 8 ~ v 1 9 ~ * 1 . 2 ' B f 2 . 40.00
1
- - 125
LASA
Fryover at Qncs Design of Superstmcfure
-
Ihm Unit i 1 3 ' 4 5
Rebmtion Factor Gr I
0.m
I Cables
Retirri3tlOn LOSSofGI.
=o.c7rro-(l<o.7-((-o.DO)R-349.03~)1m2*2+5/lwIO.fS*349.03)*2=~.2
Check for CRIJ LC% of Gr I C a w s
=(Q.W[1387-D.OOC307)'Zf0.OC119753'19~*l+Z'L982.W9/1W[, 0.00
'
' ~ o m e n due
t to Shift OF Bcarinqs Trn 0.W 0.00 0.Cm ' 0.M ' 0-W
5tress rlw :3 5919a; 3earrnps
Tap Tjm' 0.W 0. W 0.W 0.00 0.M)
T,I~~\.W 0.w w
0. 0.00 0.00
Stresesdue toC + S + R
Top of Deck Slab ~/m' 0.14 0.15 0.27 0.38 0.43
Top of Girder f/m2 0.00 -0.05 0.00 0.04 0.06
morn ~1t-n' -1.03 -1.55 -2.01 -2.46 -2.65 _
-
shes before mc
Top of Deck Slab ~1t-n' -11.37 -17.48 -29.88 -37.08 -39.29
Top of Girder T/mZ 118.22 351.30 396.30 425.04 427.38
- - Battom T/m2 796.03 1070.U 1085.69 11U.54 1122.84
4 e;.
B F.2 'el
PSCJTRESS-OUTEWpsc beam LASA - -
~fyuuerat mrur Design of Superstnrchrre
Unit 1 2 3 4 5
,Chainageof Section from left support rn 2JSQ ZllMI 5.706 8550 iiAOO
Factor Gr E
)~dalgtion l I
0.000
Check for relamtlon Im of Gr It1
=0.OGVk(1-(0.7-(~1056.95/(0~~9.a3)3)/0,2*25f
lW[0.759349.03P0.W'1.2
meek 'or Creep Loss of Gr 111Labier
=!o.aW3B7.0.00r?387jgO*OOO01S7S38195~ 0.00
Rdambn Factw Gr 11
-
= 0.05 . 0.74 0 0.110 -
Relamtion L u i s of Gr. I1 C a b k
=O.1:G*;l-[O.t~O.WJ(O.W21 l0~fi31n89'H9.a3))l/a.2)82.5f1~~D.~349.031*O.84211OR~t~'1.2
Cnecb. tor Creep Loss of Gr [I G h l s
, = [D.000387-3.000387]*nnB.rZL 1 0 1 i Z 6 3 1 ~ 0 . M 1 1 B f S 3 * 1 9 5 ~ * 1 . 2 n B 5 0 . 0.W
~
Relaxation Factor Gr I
- -
=O.S52 0.74 0.1616 0 = - 0.050
Relaxanon Loss of Gr IC a b k
=o ~5a.r r-ro.7-c(-a OO~]?*349.03))~0.2c2.SJ100*~ODfS~349r03?*2~l.2
Check for Crew Loss of Gr I Cable
=lo 000387-0m 3 t ~ 7 ~ = ~ = 0 . 0 0 1 ~ 7 n * i19 s 3m * m . 2 ~ a00
RDL_app!icd 8 t 42th day Tm 131.80 - 39.70 61.40 8D90 80.50
<trt-% duP Po SiOL
Top T/& 26.90 34.41 53.21 70.11 59.76
t3dtm-n ~/m' 48.74 -77.55 -119.94 -158.03 -157.25
-
LASA
Item Unit 1 2 3 4 5
-
Chainage of Section from left s u ~ & rn 2.259 2850 5.700 LSW 1lMO
-
5 Rdaxaawl Factw fw Gr ll =
= 2 +. I - 0.749-0.000-0.110
kelaxabm Larr oi Gr JI Cab!; at mid w n
2.150
10526315789*1-2
=2.150*[1-(0 ?-(0.00/(0.842110526315789*349.03~~~0,2~~2.5~100~(O.7PY19~O3~+Q.W2~
' C ~ W for Crracp LoY, d Gr Il Cab:-
= ~0.130~387)'5).84~11~52631~~f~~0,M118753*19~~~1.2~617.~~~~1~~ 8.W .
,
Relaxation Factor for Gr I =
- -
= 2+1-0.74 - 0.1616 0 0.0561 ZbS11
Reiax;itmn Loss of Gr. I Cables at mid span
=~.cls~~1-co.~-trco.oo.o,.o~~.0~~~-~~~.03~~~~0~~~~.~1i~*~o.m~03~-~=i.~
Chec.: tcrr CreeD Lms of Fr I Cables
=(0.OD0387)'D.84211~57631RB9'0.00LB~~195~13L689.524~1DD[] 23.42
,. -
LASA
Fbmer at 'I@mr Design of Superstructure
Item
m 2
.a
1 2
2.850
3
5.700
4
8.550
5
11.40~
I
'
Moment Due to Liie b a d ISaaainnl Tm 102.8 1285 2223 271.9 2W.4
Stresses due to Live Load (Sagging)
Top of Deck Slab T/m2 89.48 , 112.23 192.65 235.64 255.14
Top of Girder ~ / m 59.52
~ 68.75 118.02 144.36 156.30
Worn Tim2 -162.17 -252.96 434.23 -531.12 -575.07-
-
Stress at service with Live Load (Sagging)
Top of Deck Slab ~/rn~ 124.45 148.80 246.85 305.98 325.48
Top of Girder T/m2 196.38 434.75 546.37 614.53 629.96
Bottom TjrnZ 449.81 , 545.98 309.34 182.00 _ 14L56
5lrea at %w wtth Llve b a d [Saqplm) inctuding hypemtic fie& and dlMntral mlement
Top ofDeck Slab ~ / m ' 174.45 148.80 246.85 305.98 325.48
Top of Gh'def T/rn2 196.38 434.75 96.37 614.53 629.96
Battom ~ / m ' 449.81 545.98 3W.34 182.00 142.56
Stress at servlce with differential !jhrlnkage and dMererVtbl creep Me13(wRh Uva b a d )
Topof Deck Slab ~ / m ? 70.02 107.96 ' 206.01 265.13 284.64
T m of Girder ~ / r n ' 376.12 618.37 739.94 808.15 823.58
BDttom f{m7 349 92 462.11 225.49 98.14 58.70
/Stress at s m c e with dtfferenbal shrinkage and d m l creep effect (without Livp Load)
Top of Deck Slab T/m2 -19.46 1 -4.27 !
13.36 29.50 29.50
Top of Qrdw ~ / m ' 316.59 1 559.62 ( 621.97 663.80 667.28
m m r~d 512.09 1 715.08 1 659.72 629.26 633.78
~ u n d a r ~ ~ ~ ( ~ ~ * r t t h T ~ R b c I
Grress a\ k r v l c e wtl- 50% uve Load (saq, + Dlffxenhal ShrlnkW? and creep 1
Top ot Wk Stab Ttm 25.28 51.85 109.68 147.32 1!5T.W
Top uf Gtnler ~lrn"446.36 5Q3.04 CIR0.40 73597 745.43
morn ~ / m ' 431.01 588.60 442.60 363.70 34624
thalnaqe d Sectton fmm left svppaR m 2250 2.850 5.m LS5U 1Lm
sbensatScniaewRh50%LkLord(sag)+Temp~
Topol&& SLab ~ / m * 15.02 -17526 -117.43 -79.79 -70.04
Tapd Clrder T/& 42.65 14.33 101.32 156.31 165.77
T/m2 815.42 950.04 &M.OI RSJ4 707.68
-
Bottwn 230.92 39B.81 380.81 3%3.@1
+ T r n fa-
Top of- Sbb T/m2 82.60 275.05 332.88 370.52 380.27
Top of- Tld m.53 1082.48 1169.47 1224.46 1233.92
Tim2 661.93 977.41 83141 7S251 735.05 - -
iao
V 4 D W A R A - SURAT SECTION OF NH-B
45 1.79E-04
48 1.78E-04
47 1.78E-04
48 1.77E-04
49 1.7E-04
50 1.76E-04
51 1.75E-04
52 1.75E-04
53 1.74E-04
54 1.73E-04
55 1.73E-04
56 1.72E-04
VADODARA - SURAT SECTION OF W - 8
-- k
Creep strain per 1Ompa
n 3 24.62
3.4 40.00 9.40E-04
4 43.47 9.02E-04
50.00 8.30E-04
5 54.46 7.81E-04
60.00 7.20504
6 61.87 6.99E-04
7 67.31 6.40E-04
70.00 6.10E-04
8 71.52 5.95E-04
9 74.91 5.61E-04
75.00 5.60E-04
10 77.72 5.33E-04
80.00 5.10E-04
11 80.10 5.09E-04
12 82.15 4.95E-04
13 83.95 4.82E-04
14 85.54 4.71E-04
15 86.96 4.61E-04
16 88.24 4.52E-04
LASA - - ?,?2
W.
-
VADODARA SURAf SECTION OF NH-8
LASA
-
133
VADODARA - SURAT SECnON OF NH-8 of-
~bcwerat Wrur Design of Superstructure
-
MEMBER NO ------
11.400 8.590
Chninage of Section From 1cR support m 2.250 1.R50 5.70fl
LASA
Fbover at ?@fur Design of Superstructure
9
Moments Tm 57.44 70.45 117.80 [ 146.62 159.03
Shear T 20.88 18.39 11.89-[ 6.13 0.00
h -
Shear T 24.70 23.20 14.86 7.73 0.00
7
Shift of lkaring - -
Moments ------
Tm 0.00 0.00 0.00 0.00
, Shear T 0.M fl.m 0.00 , 0.00 --
SlDL
LASA
F&mer at Karur Design of Superstructure
Moments Tm
Shear T 1
Differential settlement
Moments Tm .--- 0.00 0.00 0.00 0.W 0.00
I Shear . T 0.00 o.no OBO 0.00 0.00
LASA
---
SbsChedcfwoutergirder (wtth 20 % e x h long tam ksses)
Type d cables
Area of 1 strand
AreaofoneczlMe
wdtrendorrs*hIststage
a o a Q ~ . s $ c s s e hr2ndstage
d
no of tendons stresed in 3rd stage
Jacking Force
No of Secbiom to be checked
P=-=m fom per Cable ('Jm
~fiovtratQtuf Design of Supmlrrldrac
ItnerasreFactOrstor~
In
Elastic Shortening Iws
Rebwtlonk ( Refer Clause 7.2.4, IRC18 )
Shrin- loss ( Refer Cbuse 7.2.4, IRC18 )
I .L ( R e Clause 7.2.4, IRC18 )
,- Creeploas
F a c t m 4 b r ~ ~ k r r
14th day
42th day
42th day
42th day
42th day
Infinity
-
Fador*--
14th day
42th day
4mday
4
- .r
r
42th day
42thday
CABLE PROFILE :
Outer Girder
A Total of 3 cables of type 19K13 ( 19 strands of 12.7 mm nominal dia each ) and proposed as
1 Dummy cable are shown in attached cable profile.
In cable 2 and 3 all 19 strands are placed and stressed to a jacking force of 0.75 UTS.
In cable 1 only 19 strands are placed and only 17 strands stressed to a jacking force of 0.75 UTS. In case of
emergency remaining cables can be stressed to 0.75 UTS, thus satisfying the requirement of 4% cables
for emergency as stipulated oin CL 22 of IRC 18.
Radius of circular curves at bends is maintainedgreater than 10.6m thus satisfying the clause 20
of IRC 18.Which states that R should be >= I.5+70OS13(dia )I1000 = 10.6m. The minimum spacing of
cables is maintained 180 mm, hence clear cover is more than diameter of duct.
1 36b0.320
0 200 (
, ~.Q*20&0 140 ' LUqo 1 ~ ~ 0 . 1 4 0
- - -0-1
--9 -14.000 -12.000 -10.000 -8.m 4.000 4.000 -2.000 0.m 1
m I Cable Profile ( Vertical )
- -
'
.t"l.'
- -- I
a>,'
1 .
Cablen- no_: 3
.
-
--- 1
- 4
>'
Cable--no '4
I-
Fhuuer at lyllmr Design ofsupemtructure
A
b) Faihm by crushing of concrete =)
(br0..
176Cb*dbhfd+2/3*0.8*(&-b)*(db- t / 2 ) * ~ dr
f
comp. Edge to the c.g of tendon (m) db 1.680 1.680 1.834 1.921 1.960
db = D - Y ~
3. Ultimate Tensile Strength o f steel
f~ 1670 1670 1670 1670 1670
(Mpa)
4. Area of High Tensile Steel (mm2) AS 1 5329.8 5329.8 5329.8 5329.8 5329.8
5. Ultimate Strength by yield o f I
13458 13458 14695 15390 15701
Steel (KN.m)
1 - 7
-
0.65
-
(&I+),
0.3
-
0.3
-
0.3
-
0.3
7. Flange Width of Tee (m) Bf 3.157 3.157 3.157 3.157 3.157
9
8. Thickness of Flange of Tee b a t n -
3
---- - t 0.25 0.25 0.25 0.25 0.25
of Concrete [KN.m)
w+)=
35165 33707 29655 33154 36674
lo. Design Ult. Strength (KN.m) & 134% 13458 14695 15390 15701
- -- - - -
OK OK OK
] B I OK OK *
. -
LASA
F5over at Karur Design of Superstructure
Section
Stage of
sns+mssing(
Cable No.
No. o f
C a b l e s
y, (m)
I 1 0 (drg)
P,.cosO
( K M
P , . u r s ~ . Y~
w.ml
P,.sinB
KNlI
1/8th
SPAN
SECTION
I 1 CG of Tendons from bottom I I 0.2867 I
Total Stage 2
C6 of Tendons from bottom
-7 5629.3
0.8284
1349,7
_ I -
SPAN 5.26E-06 0.826 6.795 0.0 0.0 0.0
SECTfON Toto/ Stap 1 3462.9 7tM.1 484.1
CG of Tendons from bottom 0.1578
I 1~ 6 o Tendons
f from bottom 1 I 0.1400 I
FIUC T W O UTERIP3
Design of Sqm!rurbrre
C)No)atlonrUrd:
Yd (m) = Vertical Ordimte o f CaML frwn soff it of dcck
(dsg) = Cwnuhtive angk of deviation in radian from jackity end
Pa = Force at tk critical sect- after tmnsfer (i,e aft= slip at anchomge) (KN)
Design of Superstructure
LASA
Design of Superstructure
1 2 3 4 5
ZX (4 0.000 9.466 9.526 10.726 11.726
Z8 (rad) 0.00000 0.00000 0.11859 0.11859 0.11859
Z= ( exp )-(Q+kr*) 0 1.00000 0.95739 0.92916 0.92405 0.91981
P, P, * Z (KN) 0.01 - 0.01 0.01 0.01 0.01
P', 1 0.92 0.92 0.92 0.92
n
I
117
- -r $ r
LASA
Design of Superstructure
. -
LASA
F&ruer at Wrur Design of Superstructure
I~Iongation(mm) ( I 83.4
LASA
@over at l@mr Design of Superslructure
h
Total loss in Prestress (KN) 958.5 74 7 10181.5 !C716 10785
I
I
8. Check for Ultimate Shear Capacity & Provision of Shear Reinforcement ..I
I W ~ b n d' away
fnrm
1
V8
I I !
U2 Remarks
s
shear ~ o r c e s
a) Effect~veWldth, b (m)
] hmrt
'1. Ultimate Shear Capacity of Section uncrcrckcd in Flucum (CI. 14.1.2. IRC:18-2000)
[ 0.59 0.415 0.24 0 24 0.24
I
1
b) Overall Depth, d (m) 21I 2.1 2.1 2.1 2.1
C)Max~mumPrlnc~palTens~leStress, f+ 1.52 Ref. CI 14.1.2, IRC:18
1.52 1.52 1.52 1.52
= 0.24(fck)05 (Mpa)
d) Hor~zontalComponent of prestress
(KN) - 4979.4
2.43
5011.3
3.14
- 5097.4
3.19 3.26
- 5215.1
FRICTION O U T W V U
@overat Kgtur Design of Superssrructure
I) Design Shear Capacity. Ve (KN) 2M0.4 1742.8 1056.6 631.4 319.4 Lesser of V, dc V,,
LASA
Fijmerot Xgmr *ram Design of PSC T-Glrdcr Supersbvctnre
3.0 CALCULATIONS O f BM and SF far SHUTITRING LOAD CINNER and OUTER GIRDER1
F@werat ICprur (Rpta?y Design of PSC T-Girder Superstmctum
2.0 CALCUlAnONS OF DEAD LOAD BM &SF for Ovrm S;rRDER
=(1.2616-0.B0gs)*25 . -
2.1 Wt. due to exba widening (uni)
rrc DL #--ax- - 2)
1.0 MkbiUd t&k Sbb =3*0.25*25 -
2.0 Weight of Inner XGirder =(3-1)*(1.85-0.25)*0.3*25 -
=(3-1)*(1.85-0.25)*0.4*25 =
3.0 WeigM of End X-Girder
LASA
F l j m at Kamr %?a? Design of PSC T-C;iderSupersimcture
1.2 ClaLCULAnONS OF BENDING MOMENT AND SHEAR FORCE FOR INNER GIRDER
1.2.1 pL Staae 1Loadinq
ME~xirnurn
Load C shear Force
SlDL 45.4
FPLL 0
70R(W ) Outer side 219
70R(W ) at Centre 156
n
, Summary of Bending Moments (KNm) in End cross Girder
M
Load t shw -
SlDL 17.712
FPLL 0
70R(W ) at Centre
SUM-BM-SF-LONG-GIRDkrgirder LASA
Design of Superstructure
-
Inner L Girder at the Span
Member no:-IKnGSP
I
0.225 beff = 1015 + b, = 4.860 m [ CI. 305.15.2 IRC 21 ]
WC Spacing of L-girder = 3.000 m
IrnA;$ *>5.
0.2s
Deck Slab
Modulus of Elasticity of Girder -
-
=
36050 MPa
33721.7MPa
T-SEC-PROP/Long-Inner USA
Design of Superslruciure
-
Inner L Girder at the Support
Member no:-INTLGSU
1
4.560 m [U.305.15.2 IRC 21 ]
C/C Spacing of L-girder = 3.000 m
0.65
T-SEC-PROP/Long-lnne LASA
SALEM - U R U R SECTION OF NH-7 Design of Sup-R)
i! A
(Outer Ql* )
3
u3
b
FL.4Y VIEW
J
Wearinp Coat Load
Wearing coat thickness =
Density of W.C =
Load intensity =
For outer girder
Eff width for outer girder =
Loadl m run for outer glmr =
For inner girder
Eff mdth for ouler girder = 3m
Loadl m run for inner girer = 6.6 KNlm
Crash barrier Load
Area of crash barrier = 0.39 m2
Load /m run = 9.36 KNlm
LASA
SALEM - KARUR SECTION OF NH-7 Design c# S u p w s b v m
LASA
-
SALEM KARUR SECTION OF NH-7
Ffjvwa t Kamr Qtary Design of Superstructure
-
Outer L Girder at the Span
Member no:-ENOLGSP
h
* *f 3.375 rn
0.65
-
Outer L Girder at the Support
Member no:-ENMGSU
4 3 m m
&
- - -
Composite M a n
Glrder Only
z
C
----
.
--
2.05082
1.26156
2.77535 4.3682
1.21657
0.271
1.2896 0.2a
4.63875
1.55605
CA uv Lny' XI, ~(I,+A~'I
LASA
Design of Superstructure
Area
Distance of q from bottom fibre (y)
Moment of inertia of end intermediate girder (It)
End Crass Girder
Member no: -EN- 67 TO 69 117 TO 119
Area
Distance of cg from bottom fibre (y)
Moment of inertia of end intermediate girder (It)
Slab at Exp Joint
Member no: -SLAB1 71 TO 74 127 TO 130
0.6900 m
Area
Distance of cg from bottom fibre (y)
Moment of inertia (13
Torsional moment of inertia (I,)
( 0.720 m ,
L
' " +z-t=-.-. 0.29 A
Area
Distance of cg from bottom fibre (y)
Moment of inertia (I,)
Torsional moment of inertia (I,)
Cantilever Slab (End of End Cross Girder)
Member no:-SLAB3 75 78 123 126
Area
Distance of cg from bottom fibre (y)
Moment of inertia (13
Torsional moment of inertia (IJ
i Slab in b%tw-n Cross Girder
Member no: -SLAW 83 TO 86 95 TO 98 103 TO 106 115 TO 118
Area
Distance of cg from bottom fibre (y)
Moment of inertia (13
Torsional moment of inertia (I,)
3.000 m
- %,
Area
- I $
.--_.-.-.-.-. -.--
A 0.2w
Member no:-SLAB6 15 18 43 $6
3.375 rn
._._.________
Area
__-.
"" "
Distance of cg from bottom fibre (y)
Moment of inertia (13
Torsional moment of inertia (I,)
I -
r c nnP rfl A n/Inner Girder
A
Design of Superslnclrrre
Restrained
--
2 0.100 1479.9
3
4 777.0 0.650 776.97 J -1 423.31
i
2274.45 1 634.21 1
1.2 STRESSES AT SUPPORT SECTION
I - .. - - - - -
Stresses 1
I
I
I i ( 1
Assuming due Sfress due
Y to re'ease
segment /
Height e Moment End
Restrained 1 to release Final Stress
of Moment
Lnrpa
1
LASA
J
Design ofSupemtrucrure
I
2.1 STRESSES AT SPAN SECTION
I Stresses
I
Stress Force to release Final Stress
I Restrained
rce
m K N / ~ ~K N / ~ ~
0.307 -481.17 104.63 -2672.1
,-
. I Stresses
Segment
-I
Height Stress
I
b Force Y
from top
I
e Moment
1
1
Assuming
End
Restrained
Stress due '
I
'
Of Axial
Force
Stress due
to release Final Stress
of Moment
I m KN/m2 m KN A- m m KNm K N / K N / ~~ ~
-392 1.9 3.000 -1567.82 0.088-. 0.797
-259.0 -
- - 1 .OOOo.00 0.250 0.636 0.00
0.225 -259.O 'Jxlo -
-25.49 0.314 0.571 -14.57 -258.99
-- 1454.72
- - 4 7 -0:025 32.4 0.650
-- - -0.26-- 0.467 0.419 -0.1 1 -- 32.37 1454.72
5 - 0.200 -296.0 0.650 -1 9.24 1 533 -0.648 12.46 .-- -295.99
-.
-244 1.91
1454.72 1
I 454.72-1 2747.55
I
I
LASA
,4
Design of Supemtructure
.,
Section of Girder at Section of Girder atFSuppwl
I ' r
I
,
\'
. ' 5\ i
- -
-
1, /
'\*' 8
h.
.I
I **
Design of Superstructure
I Stresses
Assuming Stress due
-
.
-I6585 76
1 479.95
--- 88757 - -31 47.49
37.88 1 1.800 ? -0.897 ] -33.97 776.97 -3147.49 , 5984.94 i 3614.4
.2545.69 ] [ 2012.05
! ="+
1.2 STRESSES AT SUPPORT SECTION
1
- 1
1
Stresses
1
1 Assuming
1
due Stress due
to re'ease
" ;*"I
Height Stress b to release Final Stress
1
'OrCe
Segment Reszd of
,
m KN/~' m KN K N ~ K N / ~ , -
1 -.-
0.150 6585.8 3.375-2041.63 0.059 0.827 - 1 1687.46 1 6585.76 -- -2017.83 -4670.48
---- -102.6
0.100 1479.9 3 3 7 5 39-1[7196 275.66 1479.95 -2017.83 -3352.18 -3890.1
2
3 0.150 1
1
888.0 1 .OOO 66.60 - 0.300 &: 3951 887.97 -201 7.83
4 0.150 777.0 0.650 , 37.88 0.437 0.448 16.98 776.97 -2017.83 I 5084.96 3844.1 ,
1 2545.69 1 2019.1 1
LASA
'I:
Design of Superstructure
I
2.1 STRESSES AT SPAN SECTION
1
I Height 1 Stress I Assuming
End
St"Ss
Stresses
1
due Stress due 1
to re'ease to release Final Stress
Segment
m 1 XNrn
1
Segment
1 Height e Moment
Assuming
to release
Of
Stress due
to release Final Stress
of Moment
m KN m
3.375 -1763.79 1 0.088 ' 0.797 -1406.1 1 -392 1.86 1610.06 2884.99 --
R Kg I -259.0
-259.0
1::
,
-25.49 1 0.314
, - 0.00
I -14.57
-258.99
-258.99 I
1610.06
1610.06
2070.66
-
LASA
%-
CABLE COOROINATES
LASA
USA
CABLE COORDINAES
USA
416 Laning of Karur-Madurai Sect~onof NH-7
Consultancy Services for Feasibility study and Preparat~onof DPR
Clause
-
SECTION 2800 REPAIR OF STRUCTURES
2809 DISMANTLING OF CONCRETE WEARING COAT
(i) The concrete wearing coat as well as the bituminous overlay shall be
removed from the existing bridges.
Renumber the sub para (i), (ii), (iii) as (ii), (iii) & (iv)
Dismantlcd macerial shall not he stacked on the deck nor shall i t be thrown below
the bridge. 11 shall be neatly piled at points designated try the Engineer with all
lifts and lead upto 1IK)Om. Materials. which can hc used or auctioned, shall he
stored in near piles at locations desimated hy the Engineer wit11all lifis and lead
upto 2000m.
2813 Rate
The contract unit rate for dismantling the wearing coat shall include the cost of all
materials, labour, tools and plant, traffic management, signage, safety precautions
<-cT.>,
.- -
.#.\
,f\
Clause
and other incidental expenses including removal of existing expansion joints for
the satisfactory completion of the work as per these specifications.
Dismantled material shall not be stacked on the deck nor shall it be thrown below
the bridge. It shall be neatly piled at points designated by the Engineer with all
lifts and lead upto 1000m. Materials, which can be used or auctioned, shall be
stored in neat piles at locations designated by the Engineer with all lifts and lead
upto 2000m.
Water shall be sprayed to reduce the dust while the dismantling work is in
progress. Dismantling work shall not be camed out at night, during storms or
heavy rain.
Goggles and gas masks shall be worn at the time of dismantling. Leather gloves
shall be worn by the workers. Screens made of G.I. sheets shall be placed
wherever necessary to prevent the disintegrated pieces from flying.
The depth of cutting ofthe existing deck slab shall be as shown in the drawings.
Dismantling shall be done in accordance with Standard Specification section
200.
Clause
2814.4 Dismantling of existing wing wall for construction of adjacent one lane
bridge - a) StonelBrick masonry, b) Concrete
The contract unit rate for the various items of dismantling shall be paid in full for
carrying out the required operations including full compensation for all labour,
materials, tools, equipment, safeguards and incidentals necessary to complete the
work. These will also include excavation and backfilling where necessary to the
required compaction and for handling, salvaging, piling and disposing of the
dismantled materials within all lifts and up to a lead of 1000m
In order to have a cross slope of 1/60 in all existing bridges whether the cross-
section is retained or widened, profile corrective course of Semi-Dense
Bituminous Concrete (SDBC) shall be laid over the stmctural deck slab after the
top has been exposed by removing the existing wearing coat (refer to clause
2809). The existing wearing coat will be basically of PCC with or without surface
reinforcement, but can also have top bituminous overlay, which had been
provided subsequently as a leveling course.
The profile corrective course of SDBC of variable thickness has to be laid over
the existing carriageway. For T girder bridges, which are not being widened, the
maximum thickness of profile corrective course will be at the existing Centre
Line. For slab bridges, which are being widened, the maximum thickness of
profile corrective course will be at the kerb toward the central verge because of
unidirectional camber.
416 Laning of Karur-Madurai Section of NH-7
Consultancy Services for Feasibility study and Preparation of DPR
Clause
Slab bridges are being widened with slab extensions. The top of extended slab
will have a cross slope of 1/60 and no profile corrective course will be required
for the widenedtextended portion of the slab bridge.
A tack coat confirming to standard specification clause 503 shall be applied over
the exposed surface of deck slab before the application of SDBC. In addition,
tack coat has to be provided on new concrete surface of widened portion.
The Mastic Asphalt (MORTH specification clause no. 515) shall be overlaid as
the other component of wearing coat on the bituminous concrete.
The profile corrective course (PCC) shall be measured in cubic metres, as running
continuously through. The tack coat shall not be measured. The work of wearing
coat shall be measured in square metres.
Rate
The contract unit rate for profile corrective course shall include the cost of tack
coat and shall also cover cost of all materials, labour, tools, plant and equipment
required for mixing, transporting and placing in position, vibrating and
compacting and finishing as per this section or as directed by the Engineer,
including all incidental expenses, sampling and testing, quality assurance and
supervision.
For repair of kerb, raillrailing post etc., cement sand mortar (1:3) shall be applied.
Missing reinforcement if any shall be compensated before application of mortar.
Damaged rails of the railing shall be replaced by rails of same size and
reinforcement as given in MORTH drawings. Both the above operations shall be
done as per relevant provisions of MORTH specification clause 2703.3 &
2703.4
Rate
The contract unit rate shall include the cost of all labour, materials, tools and
plant, scaffolding and all incidental expenses, sampling and testing and
supervision as described in these specifications.
- . .,. - .
I..
,. .. ,
.. ., I<-.-i
. . . I
. ..-d
' '1
,
, I : /
Technical Specificnr~nna . . ' % : Rehabnitation of Exlsting Bridges
416 Laning of Karur-Madurai Section of NH-7
Consultancy Services for Feasibility study and Preparation of DPR
Clause
For all existing bridges that are being widened and changed to uni-directional
camber drainage spouts shall be provided as shown in the drawings.
The work of new drainage spout shall be executed in accordance with Standard
Specification Section 2700 Clause 2705
Rate
The contract unit rate for each drainage spout shall include the cost of all labour,
material, tools and plant required for completing the work as per the
specifications. It shall also include the cost of closure of existing drainage spouts
and providing flow drainpipes with all fixtures up to the point of ground drains
wherever shown on the drawings.
The work shall be done aAer the wearing coat is removed. The grating shall be
dismantled and the existing spouts shall be removed carefully with minimum
damage to surrounding concrete.
The pocket formed shall be sufficiently large to ensure good flow and compaction
of concrete in the hole. The area around the spout covered by the grating shall be
provided with PMC sluny.
The specifications for polymer modified cementitious topping & mortar shall be
as per of Special Specifications A-3 (1.7)
Rate
The rate for such closing shalI be deemed to have been included in the cost of
new drainage spouts provided in the widened portion.
Clause
c) Extension of existing drainage spouts
For bridges that are not being widened, the existing drainage spouts are to be
retained with minor repairs. The work shall be carried out as shown in the
drawing. The concrete surrounding the spout in the sofflt of the slab shall be
chipped out. An extension collar of specified size shall be attached to the existing
pipe as shown in the drawing. The chipped out area shall then be filled with 1:4
cement sand mortar over which a lOmm thck layer of PMC repair mortar shall
be applied.
Rate
The contract unit rate for each drainage spout shall include the cost of all labour,
material, tools and plant required for completing the work as per these
Specifications. It shall also include the cost of providing flow drainpipes in girder
bridges with all fixtures up to the point of ground drains wherever shown on the
drawings.
Honey combed, spalled concrete should be cleaned and cleared (plaster removed)
before the start of repair operation. If necessary, should be cleaned vigorously
with wire brush.
Measurement for application of PMC mortar for specified thickness shall be per
square metre of surface area of application.
Rate
The contract unit rate for application of PMC mortar for specified thickness
including cement mortar 1:4 wherever required, shall include cost of all materials,
labour, tools and plant, placing in position, testing and other incidental expenses
including surface preparation for the satisfactory completion of the work as per
these specifications and as shown in the drawings.
h
Techn~calSpec~fical~ons Rehab~btatlonof Ex~st~ng
Brldges
Contract Package NS 80
.) ,
416 Laning of Kmr-Madurai Section af NH-7
Consultancy Servicesf o r Feasibility study and Preparation of DPR
Clause
Measurement for Payment
Wide crack: Measurement for sealing of cracks and injection shall be made by
weight of cement consumed in kg for cement grouting.
For provision of nipples required for grouting, the payment shall be for number of
nipples inserted.
Rate
Fine crack:The contract unit rate for application of PMC mortar for specified
thickness shall include cost of all materials, labour, tools and plant, placing in
position, testing and other incidental expenses including surface preparation for
the satisfactory completion of the work as per these specifications and as shown
in the drawings.
Wide crack: The contract unit rate for sealing of cracks and injection of cement
grout shall include cost of all materials, labour, tools and plant, placing in
position, testing, curing and other incidental expenses for the satisfactory
completion of the work as per these specifications.
The work shall be executed in accordance with Special Specification A-3 (1.3)
Measurements for reshaping of soffit of girder with PMC and Cement Plaster
(1:4) shall be square metre of surface area of application.
Rate
The conlract unit raze for application of PMC mortar for specified thickness shall
include cost OF all materials, lahour, tools and plant. placing in position, testing
and other incidental expenses including surface preparation for the salisfactory
completion of'the work as per these specifications and as shown in the drawines.
. --
. ,.
. .
(.
, ,.
.--- .,' '
.
.
\;.
.-,, I
-- . I:;
, ' 8
Technical Specifications I\, . , Rehnh~lil:>!~nn
o f F;r;~a~ng
Br!dtcs
."1.'1 7
Contract Package NS 80 ' :-., ,.' ,/,: . .
- -
L-
416 Laning of Kanu-Madurai Section of NH-7
Consultancy Sewlces for Feasibility audy and Preparation of DPR
Clause
2821 SEALING OF WIDE CRACKS AT JUNCTION OF WING WALL AND
ABUTMENT WITH BRICK BATS AND FINISHING WITH 1:3 CEMENT
MORTAR
Rate
The contract unit rate for sealing of gap, cracks and injection of cement grout
shall include cost of all material including the gap filling material, labour, tools
and plant, placing in position, testing, curing and other incidental expenses for the
satisfactory completion of the work as per these specifications.
The work is to repair spalls or loss of cover in abutment, pier substructure and
gaps. This shall be executed in accordance with standard Specilication Section
2807 and special Specification A 3 (1.6 (a) & (b)) and 1.7
Rate
The contract unit rate for guniting shall cover cost of all materids. I a b t ~ rtooIs.
,
plant. placing in position. testing. curing and surface preparation and other
incidental expenses for thc satisfactory completion of work as per specification. It
shall also include the cost of the provision of steel weld mesh as per specification.
The work shall include providing and inserting nipples with approved fixing
compound after drilling holes, and after operation, cutting and removing nipples
and sealing the holes.
Measurement for Payment for making provision of nipples required for grouting
shall be for number of nipples inserted.
"'
8
. .
-.,. ..-,
Rehabilitation of Existing Bridge
-r,.L,;.-l C-ificaIifinr
.L .
,
':
,
:?'
. .
.
Contnct Packap NS 80
- -
4/6 Laning of Karur-Madurai Section of NH-7
Consultancy Senrims for Feasibility study and Preparation of DPR
Clause
Rate
The rate will include cost of cement nipples, admixture fixing compound, all
material and labour in drilling fvring and cutting after the job and removal and
sealing the holes including the cost of drilling equipment, cost of drill, bits and
spares wastage etc.
Approach slabs are to be provided for the new widened camageway of bridges.
In addition, approach slabs, which are cracked or otherwise damaged, shall be
recast.
Rate
The contract unit rate for approach slab shall include the cost of all labour,
material, tools and plant and other cost necessary for completion of the work as
per these Specifications. The rate for base shall include cost of all labour,
material, tools and plant required, including preparation of surface and
consolidation complete in all respects
Expanded metal sheet of size 75 mm x 200 rnm, 3.25 nun wide and 3.15 mm
thick @ 2.141 kg1sq.m shall be provided over the steel plate placed at the
expansion joint and welded.
Rate
The contract unit rate shall include provision, placing in position of the sheet as
per drawing and specifications, and welding also.
Clause
SPECIAL SPECIFICATIONS
Apart from these, the bridges are to be provided with uni-directional camber, crash
barriers in lieu of railing and new expansion joints specially when the slab bridges are
widened.
For various types of defects, the repair methodology, its procedure and the material
specification and the specification and procedure for providing new expansion joint,
crash bamer and wearing coat are outlined in the succeeding Para.
1 . FINE CRACKS
There can be fine visible cracks in bridges. If the cracks are 0.5mrn wide or less, these
cracks are to be repaired with PMC mortar. The location of the cracks can be seen
during repair and widening works. In order to avoid increase in corrosion,
rectification of the cracks by cutting grooves in the concrete and sealing the grooves
with PMC repair mortar after cleaning and applying PMC sluny on the freshly cut
surfaces at all locations is recommended.
Procedure
The size of the groove, which should be cut along the whole length of visible cracks,
shall be 20 x 1Omrn. Depth of the groove is lOmm while the width of the groove is
20mm, which however, should be symmetrically placed along the crack. In case
reinforcement is met within a depth of 6- the depth should be limited to the depth
of the reinforcement from the surface. It is preferable to cut the groove
pergendicularly to the surface but a deviation of 15 degrees in either direction may be
permitted.
After cutting the groove it shall be cleaned properly to ensure a dust free clean
surface and a coating of PMC sluny be applied over the freshly cut surfaces.
The PMC repair mortar shall be used to fill the 20 x lOmm groove while the slurry
coating is still wet, after a lapse of 30 minutes from the time of application of the
slurry, the PMC repair mortar shall be applied and compacted to ensure complete
filling of the groove. The filling up of the groove shall be finished flush with the
existing concrete surface. After the finishing operation, the filled up groove should
be properly covered with impermeable sheet whose edges are to be sealed by taping.
Curing of the finished surface will be the same as that stated for curing of PMC repair
mortar (See C1.1.7). Care should be taken to cut the groove with sharp edge
instrument to avoid damage to the structure.
9
-',
Tcchn~c~l I-. ,
Spet~ficat~c~m ; I / Rehabtliiat~onof Ex~stingBridges
4/61 Laning of Karur-Madurai Sect~onof NH-7
Consultancy Services for Feasibility study and Preparation of DPR
Clause
Material Specrfication
Wide cracks having width more than 0.5 rnm have been found in some of the bridge
components. Moreover, these wide cracks are also found in MasonryIPCC
substructure, such as wing walls, abutments and piers. While locating them and to
repair specially the wing walls, it is to be decided whether the old wing wall will be
functional after widening, if so they need to be repaired.
The basic repair methodology consists of injection of cement grout in the wide cracks
after most of the visible gaps have been sealed by applying sealing mortars. The
repair should be in conformation with clause 2806 of MORTH specification.
However, the general procedure is briefly described.
Procedure
The wide gaps should be chased so that grooves are formed which may be 10 x 5 m m
in size. After cleaning the surface with wire brush and compressed air, 15mm dia
nipples are to be fixed in 150 - 200mm deep holes with suitable sealing material.
The nipples should have maximum spacing 500 - 600mm. The chased groove also
should be filled up with suitable sealing material. Neat cement along with soluble
glass (Sodium Nitrate) forms excellent quick setting sealing compounds.
Material Specrfcation
In case of voids in the girder soffits are identified, the repair technique shall be as
folloats. T h e repair shall be done by law permeability polymer modified cement
repair mortar. The thickness ofthe PMC repair mortar shall be limited to 15 mm. For
repairing voids more than I 5 mm. the lowcr!inner layer should be filled with cement-
sand mortar F :4 prior to application of PMC repair mortar.
Portions of the soffits of the girders to be repaired are to be chipped off, so that the
film forming the external soffit surface are removed exposing the reinforcement. All
loose concrete sticking with !he reinforcement shall be removed using appropriate
tools and equipment.
Depending on the depth of voids, cement sand mortar 1:4 is to be applied, before the
application of PMC mortar 15mm thick so that the soffit of the girder is in a straight
line i.e., the soffit should not have protrusion or depressions.
All concrete film in the soffit of girders and weak concrete sticking to the
reinforcement w i l ? b # p a y e d by using appropriate tools and equipment. Where the
I
Contract Package NS 80
416 Laning of Karur-Madurai Section of NH-7
Consultancy S e ~ c e sfor Feasibility study and Preparat~onof DPR
Clause
reinforcement bars are exposed, the brealung shall continue so as to expose half the
diameter prior to &her treatment.
Reinforcemenl Preparation
a) Where exposed reinforcement is sound and does not show any signs of heavy
corrosion or pitting other than typical rusting, it shall be mechanically
cleaned to remove rust and loose mill scale.
Reinforcement Priming
Within one hour of preparing and cleaning, the reinforcement shall be coated with a
primer. The primer shall be PMC sluny using Tapecrete P1.51 as polymer latex or
approved equivalent polymer latex.
The primer shall be brush applied on to the cleaned reinforcement ensuring that the
full surface area is in accordance with the manufacturer's recommendation.
Before commencing to apply PMC repair mortar or the inner cement sand mortar, the
prepared concrete substrata shall be thoroughly soaked with clean water. Free surface
water shall be removed before priming. The primer shall be PMC slurry using MIS
CICO Technologies Ltd.'s Tapecrete P 151 polymer Iatex or approved equivalent.
The priming agent shall be well worked into the irregularities according to the
manufacturer's recommendations.
The repair material should be applied before the priming agent sets. The area coated
as one time must be restricted to allow for this provision and any area, which
becomes set shall be recoated as per manufacturer's instruction.
The repair mortar shall be high build polymer modified cementitious repair mortar.
The PMC repair mortar shall be of appropriate general specification for use in vertical
and overhead application.
The total thickness of mortar shall be applied in one layer not exceeding 15mm
without sagging or slumping. The material shall be applied in accordance with the
manufacturer's recommendations.
The mixing shall be carried out using forces action mixes or with slow speed drive
mixer (400 - 500 rpm) fitted with a spiral paddle. In no circumstances shall water be
used in the PMC repair mortar mix. Re-mixing and re-tampering shall not be
permitted.
The material shall be applied by gloved hand or trowel to the prepared and primed
surface of the s u b s t y l y ~ eand be well worked inside paying particular attention to
Clause
paclung behind and between the reinforcement. In order to make up the total height
of the girder up to the original soffit level, the balance portion of the girder depth
shall be made up with 1:4 cement sand plaster. Refer to Para 1.7.1 for specifications
of PMC mortar i.e., special specification 1.7
For some bridges, spalling and honeycombing have been observed specially near the
drainage waterspout. The basic repair for this defect is to provide a 5 to 8 mrn thick
PMC repair mortar layer after removing the loose concrete, plaster etc. The peripheral
edge may be cut upto lOmm deep and the material removed to give a proper
demarcation line. If such spalling or honeycombing is observed in the cantilevered
portion of deck of girder bridges, a drip course covered with PMC repair mortar may
be provided to stop the back flow of rainwater.
Procedure
A drip course 10 x 12 rnrn size is to be formed at the outer edge of the soffit of the
cantilevered deck slab. PMC repair mortar Smm thick shall be applied on the drip
course. Refer to Para 1.7 for details of specification of PMC materials.
This type of distress has been observed in couple of bridges. The large spalling might
have been initiated due to honeycombing, a bad construction defect. In many cases,
inadequate length of drainage spout has been responsible for wetting the locality with
drained rainwater and in addition due to the growth of vegetation. This happens
particularly in pier caps.
The repair technique suggested is the application of Cement Sand mortar 1:4, before
the application of PMC mortar 15mm thick so that the soffit is in a straight line.
Procedurefor Repair
All concrete film in the soffit and weak concrete sticking to the reinforcement shall be
removed by using appropriate tools and equipment. Where the reinforcement bars are
exposed, the breaking shall continue so as to expose half the diameter prior to fkther
treatment. PMC sluny shall be applied over the prepared surface. Afier application of
PMC slurry, the repair shall be carried out as per section 1.3
. 8
,
,'
-
I -
=!
Techniul Sgcr!ficxinn?
Contad Packape NS RO
.1
----- -
\yO
1s PC.'-+
Rehabtlttat~onof Ex~stingBridges
A * , )r
416 Laning of Kmr-Madurai Section of NH-7
Consultancy Services for Feasibility study and Preparation of DPR
Clause
1.6 PIER AND ABUTMENT SUBSTRUCTURE AFFECTED BY WEATHERING
AND LOSS OF POINTINGlPLASTER
Generally, there are no cases where these defects have been identified. However,
during the construction period, if the defects are noticed, the following methodology
shall be used for repairing the same.
Bmic Principles
The purpose of guniting of the bridge is to increase its life from general weathering
and for counteracting weathering effects also. There are distinct weathering signs in
the old masonry/cement concrete substructure portion.
The guniting thickness for vertical faces of substructure should be at least 40mm and
should be strengthened by providing a steel weld mesh 50 x 50 x 10 gauge all along
vertical faces of substructure.
Procedure
The steel wire mesh has to be placed in position keeping the mesh within 10 - 15rnm
from the surface, which will be curved for the cutwater portion. Suitable fixing pins
are to be inserted between the masonry mortar joint so that the mesh can be kept in
proper position. The inserts can even be spaced quite apart but ensuring that the weld
mesh is not disturbed during guniting, which is also termed as shotcreting.
Depending on the expertise of the guniting personnel, the thickness of 40rnm may be
built in one layer but it must be ensured that no void is created behind the gunite built
up thickness. The presence of void can be found by hollow hammering sound after
the gunite has attained strength say after 3 days.
Material Specification
For loss of pointingfplaster cement mortar 1:3 will be used on exposed surface after
removal of old plaster/pointing and preparation of surface thereof.
- ..
Clause
1.7 SPECIFICATION FOR MATERIALS AND MIX FORMULATIONS FOR
PMC MATERIAL SYSTEM
The acrylic polymer latex to be used for system shall be TAPECRETE P 151
manufactured by MIS CICO Technologies Ltd. Equivalent products of M/s FOSROC
and M/s SIKA are also acceptable.
The polymer latex, which is to be used, should consist of water based acrylic and
copolymer dispersion and special purpose chemicals. (TAPECRETE Pl5l of MIS
FRC Composites (I) Pvt. Ltd. or any approved equivalent may be used for this
+
purpose). The polymer solid contents shall be 30 1 percent. The particles shall be
nearly spherical shape with a diameter of 0.35 -+ 0.05 micrometer. The manufacturer
shall certify to the above requirements about solid content and grain size. In order to
keep control over the quality, the manufacturer shall provide infrared absorption
spectrum analysis for the materials (polymer latex) to be supplied to them.
Portland Cement conforming to IS: 8112 shall be used for production of polymer
modified cement repair mortar and polymer modified cementitious coating system,
which is to be used as a bonding medium with concrete substrate.
Tapecrete P151, an acrylic polymer latex shall be used as the polymer for modifying
and improving the properties of cement. The same product is to be used for various
purposes such as in a sluny form with cement to form a bonding/priming medium and
with sand to firm PMC repair mortar. However, no additional water is to be added to
PMC slurry or PMC repair mortar as the water which is present in the latex is
sufficient for cement hydration and for this reason the latex cement ratio remains
constant for all applications.
The sand, which is to be used for constituting the PMC repair mortar, should be Silica
sand as the basic material, which is categorized in two groups:
The grading of the above groups should follow the limits provided below: -
1 L n
/<
Techn~calSpec~ficat~ons /.- Rehablhtat~onof Exlst~ngBr~dges
12, - 15
Contract Pukage NS 80
I .
, . ,
'
,
. \'.
4.
' .- ..-.
1
'9;
416 Laning of Karur-Madural Section of NH-7
fm Fcsrblllty nu+ and Prepm~iono r DPR
Canmlmcy WICPX
Clause
In the event of using local sand, the sand to be used must satisfy the limits of
deleterious materials and the requirements of soundness as given in Clause. 3.2.1 and
3.6 of IS: 383 respectively. Confirmatory tests shall be conducted by the contractor
and sample kept for comparison by the Public Works Department.
For repair of spallings, where the depth of spalling exceeds 15mm cement-sand
mortar 1:4layer have been recommended after the application of PMC repair mortar,
15rnm thick.
The amount of water will depend on the environment condition and is therefore
variable.
In case where two layers of cement-sand mortar are to be used, the second layer shall
be provided after a lapse of 24 hours from the time of application of the first layer.
Conventional practice or surface preparation for good bonding shall be adopted for all
layers.
Conventional curing of the cement sand mortar layer by application of water spray
should be followed for at least 2 days.
Miu Formafions
PMC SLURRY
Component Parts by Weight
Cement 100
Tapecrete P 151 or equivalent 50
Clause
Curing of PMC Work
This specification describes the curing procedures to be followed for various PMC
systems.
The curing procedures outlined apply to normal weather conditions. Take precautions
to avoid drying. PMC work should be carried out a temperature below 35C.
Under unusual weather conditions e.g. high humidity andlor high wind velocity or
imposed constraints special curing procedures shall be followed. Approval, therefore,
shall be obtained from the Engineer-in-charge.
As PMC work proceeds, precautions shall be taken to prevent rapid drying of the
PMC repair mortar and PMC filler. This is usually accomplished by covering the
filled surfaces with an impermeable sheet shortly after the work has been done. The
edges of the impermeable sheet should be suitably taped.
The sheet shall be kept in place until further work is camed on over the filler or in the
case where the filler will be exposed to heavy abuse, the sheet shall be kept in place
for 24 hours.
No foot traffic or further work shall be allowed over the filler until 12 hours from the
time of the completion of the work.
All the areas repaired using cementitious materials specified above shall be fully
cured in accordance with good practice for PMC application as given under general
specifications for PMC material systems.
For the first day the repaired concrete patch shall be protected from harsh
environment by laying a polythene sheet over it taping down the edges.
Following moist curing, the coating shall be allowed to air dry for at least 3 days prior
to the application of finishing coat.
-
J
[- +*-
' -1
' ., ' *. -
Techn~calS p e c ~ d c a t ~ o ~
Contract Package NS 80
\..*dTy
17
Rehabd~tatlonof Ex~st~ng
Bridges
4!6 Laning of Karur-Mahmi Smmn of UH-7
Consultancy %tv~ccs far Feasilrilny sully an!] Preprailan a1 3PR
Clause
The gunite is a mixture of cement, sand and water. It comprises 100 pacts by weight
of cement, 300 parts by weight quartz sand, 35-50 parts by weight water and 2 parts
by weight approved quick setting compound. In general, dry mix shotcrete shall be
used.
Ordinary Portland cement conforming to IS: 269 shall be used for guniting.
Sand for guniting shall comply with the requirements stipulated in IS: 383. In general,
sand should neither be too coarse to increase the rebound nor too fine to increase the
slump. Sand should preferably have a moisture content between 3 and 6%.
The grading of sand shall lie within the limits given below:
IS Sieve Designation OO
/ Passing the Sieve
4.75 mm 95 - 100
2.36mm 65 - 90
1.18mrn 45 - 75
600 microns 30 - 50
300 microns 10-22
150 microns 2 -8
For thick sections it may be advantageous to incorporate coarse aggregate in the mix
provided adequate guniting equipment is available. Coarse sgwgate, when used
shall conform to grading given in Table 1 of IS 9012. The percentage of coarse
aggregate may normally be kept as 20 to 40% of the total a g e g a t e and the mix shall
be suitably designed. Waterlcement ratio for guniting shall fall within the range 0.35
to 0.50 by mass, wet enough to reduce the rebound. Drying shrinkage may be
between 0.06% and 0.1%. The quick setting compound shall be added at the nozzle
with water just before guniting.
The cement and sand shall be batched and mixed and conveyed through a hosepipe
with the help of compressed air. A separate line shall bring the water under pressure.
The cement, sand water mix shall be passed through and intimately mixed in a special
manifold and then projected at high velocity to the surface being repaired. The
density of gunite shall not be less than 2000 kglcum. The strength of gunite shall not
be less than 25 Mpa. For effective guniting the nozzle shall be kept 60 to 150 cm
away from the surface, preferably normal to that surface. While enclosing
reinforcement bars during repairs the nozzle shall be held closer at a slight angle and
the mix shall be wetter than the normal.
Test panels simulating actual field conditions shall be fabricated for conducting pre-
ct.mHructi~ntesting. The procedure for testing the cubes or cylinders taken from the
panels stipulated in clause 6 of IS: 9012 shall be followed. It should be ensured from
tests that a strength of about 30 MPa at 28 days is available for the moaar/concrete
mix.
The defective concrete shall be cut out to the full depth till sound concrete surface is
reached. Under no circumstances should the thickness of concrete to be removed be
less than clear cover to the main reinforcement. No square shoulders shall be left at
the perimeter of the cut-off portion and all edges shall be tapered. Thereafter, all
loose and foreign materids *houid be removed and the surface be sand-blasted to
- - ,'
< -
\
\
<
1 % .
1,
\.<
/'
,
+
- __-,
4/6 Laning of Karur-Madurai Seclion of MI-7
Consultancy Services for Feasibility study and Preparation of DPR
Clause
make it rough to receive shotcrete after applying a coat of bonding epoxy as per
recommendation of the manufacturer @ 1.0 kg per 1.5 sqm of surface area.
The exposed reinforcement shall be thoroughly cleaned free of rust etc. by wire
brushing. Wherever the reinforcements have been corroded the same shall be
removed ad replaced by additional reinforcement. Before application of gunite a
coat of neat cement slurry should be applied on the surface of the reinforcement.
Sufficient clearance shall be provided around the reinforcement to permit encasement
with sound gunite. Care shall be taken to avoid sand pockets behind the
reinforcements.
The stipulations given in IS: 9012 regarding applications of gunite should be followed
so as to keep the rebound to the minimum. The quality of guniting and workmanship
shall be such that the percentage of rebound mentioned in IS: 9012 can be adhered to.
In no circumstances shall the rebound material be reused in the work. It would be
desirable that green gunite is moistened as curing requirement for at least 7 days.
Guniting work shall not be done during windy or rainy conditions.