Model letters for use by the Contractor

Letter to the Employer c.c. Engineer


ML 20.4b

Sub-Clause 20.4 Obtaining Dispute Adjudication Boards Decision


(Give reference number and title of dispute)
DAB Decision Dated ( )

We received the decision of the DAB in respect of the above dispute on (date).

We are dissatisfied with the decision of the DAB and give notice that we intend to
refer the dispute to arbitration in accordance with the provisions of Sub-Clause
20.6 of the General Conditions of Contract.

Yours etc.

A Contractors Guide to the FIDIC Conditions of Contract, First Edition. Michael D.


Robinson.