Professional Documents
Culture Documents
W. Allen Marr
Construction of civil engineering Table 1. Reasons for monitoring constructing it in stages. Placed all at
facilities must deal with many performance once, the embankment would cause a
unknowns and limited data. This is foundation failure. Placing the embank-
especially true for those projects in 1. Enabling use of the ment in stages with time between each
urban areas that involve construction observational method. stage allows the soft soil to strengthen
on or in soil and rock. We are working 2. Indicate impending failure. by consolidation between each stage.
in materials with properties that can 3. Reveal unknowns. Instruments to measure movements
change instantly and significantly from and pore water pressures could be used
4. Assess contractors means
one point to the next. These changes to determine when enough consolida-
and methods.
may result from the actions of nature tion of the clay has occurred that the
in laying down the earth, from prior 5. Minimize damage to adjacent next stage of fill can be safely added.
activities of man on the site, or from structures. A delicate balance may be sought be-
actions of the contractor as he works 6. Devise remedial measures to tween adding the next stage as quickly
with the site. Further complications fix problems. as possible to minimize construction
may come from uncertainties in time but not so quickly that a stability
7. Improve performance.
the loads that the new facility must failure is created.
withstand during construction and 8. Advance state-of-knowledge.
operation. These uncertainties combine 9. Document performance for Indicate Impending Failure
to produce substantial uncertainty assessing damages. Geotechnical facilities can fail with
about how the completed facility will 10. Inform stakeholders. catastrophic consequences to life and
perform throughout its life. property. Such failures may be the
11. Satisfy regulators. result of excessive loads, design errors,
Compounding the importance of
these uncertain conditions are the po- 12. Reduce litigation. construction deficiencies, unknown
tentially large consequences of unex- 13. Show that everything is ok. or different conditions, deterioration,
pected performance by the facility. Un- operational errors or intentional action.
expected performance may adversely Geotechnical monitoring has been
impact the project, neighbouring struc- Enabling use of the Observa- widely used to detect the onset of
tures and utilities, and people. Unex- tional Method failure in dams, slopes, embankments
pected performance may delay the Monitoring provides us with and excavations. Such monitoring may
project, increase its cost, and lead to quantitative information on actual have different purposes. It may be to
lengthy and expensive litigations. performance. We compare the measured issue a warning to evacuate people and
Table 1 summarizes the principle performance with the predicted or move equipment. It may be to initiate
technical reasons for recommending a expected performance. Differences action to forestall the failure. It may
geotechnical monitoring program for a indicate the effects of uncertainties provide feedback when causing an
project. Each of these is discussed be- in our design. We need to evaluate intentional failure, such as for a mining
low in the context of todays practice of those differences to determine what operation or a field test.
geotechnical engineering. In general, a they indicate for future performance.
common feature of these technical rea- If the anticipated future performance Reveal Unknowns
sons is that monitoring programs save is unacceptable, we look for changes, Geotechnical engineers constantly
money. modifications, and remediation work with unknowns. Sometimes these
This article is based on Marr (2007), that can be made to alter the future unknowns can cause a catastrophic
and is published in GIN with permis- performance. This process, defined failure that destroys the entire project,
sion from ASCE. as the Observational Method, was takes lives, or ruins careers. Other times
brilliantly described by Dr. Peck in his they cause delays, which increasingly
Rankine Lecture (Peck, 1969). lead to expensive claims for differing
For example, an embankment might site conditions.
be placed over a soft soil stratum by The foundations of the geotechnical
34 Geotechnical News December 2009
GEOTECHNICAL INSTRUMENTATION NEWS
discipline were built on the use of field adjacent structures are not damaged by instrumentation was used as part of
measurements to reveal unknowns dur- the work. Geotechnical instrumenta- a research effort to improve our state
ing construction and head off disaster. tion to measure vertical and horizontal of knowledge. Much of this was paid
In fact, it can be argued that the driv- movement outside the support system for by governmental agencies with a
ing force that led to the development is used to determine whether the con- mission to improve practice. The result
of most of the instrumentation we use tractor meets this requirement. In doing has been a substantial improvement
today was a need to measure something this, we save the costs to fix the actual in our understanding of how various
to reveal unknowns. damages. In addition, we may avoid or foundation systems, excavation
Use of procedures which reveal un- greatly reduce the costs that come from methods and ground improvement
known conditions as early as possible inflated claims and protracted litigation processes work and dont work.
and engage remedial work as soon as resulting from the alleged damages.
possible leads to lowest project cost. A Such savings can be of great signifi- Document Performance for
good geotechnical monitoring program cance, especially in urban areas. Assessing Damages
is vital to this approach. The alterna- Claims for damages by third parties
tive of delay, denial, and blame almost Devise Remedial Methods to represent one of the substantial risks
always costs more. Additional costs Fix Problems encountered in geotechnical projects.
come from the expenses incurred to Things sometimes go wrong in Some claims may include charges for
determine who pays the added cost. geotechnical construction that must damages unrelated to the construction.
be fixed. Finding the best fix requires Others may be inflated, such as a
Assess Contractors Means and understanding what went wrong. Data claim for major loss when only minor
Methods from geotechnical monitoring can help architectural damage has occurred.
The outcome of some geotechnical engineers to determine what caused the Data from geotechnical monitoring
projects depends on the means problem. Then a remedial action can can help establish the validity of such
and methods of the contractor, and be devised that addresses the specific claims. For example, if the instrumen-
geotechnical monitoring is used to cause rather than masks the symptoms. tation shows that an adjacent building
determine whether the contractors has not moved during construction, it
means and methods meet the specified Improve Performance becomes more difficult for the owner
performance requirements. Modern concepts of business to claim that cracks in the building re-
Project requirements may be in the management stress continual sulted from the construction activity.
form of a performance specification improvement and the need for
where the contractor is required to pro- measurements to gauge success. A Inform Stakeholders
vide the design and complete the con- common saw in business practice is Construction in developed areas may
struction. Maintaining the stability of that which is measured improves, affect numerous parties, all of whom
the bottom of a deep excavation against while things not measured eventually seek a role in controlling the adverse
uplift is one example. The specifica- fail. The mere process of measuring impacts of the project. People tend
tions might require that the contractor performance coupled with normal to fear construction impacts and
maintain a minimum factor of safety human behavior leads to improved anticipate the worst outcomes. Data
against bottom heave due to uplift of performance. from geotechnical monitoring can
at least 1.1. Piezometers installed to The underground construction in- provide solid evidence of the true
measure pore water pressures beneath dustry is searching for ways to improve construction impacts. It can provide
the excavation would indicate whether their operations to produce facilities powerful responses to the questions
the contractor is meeting this important that perform better and cost less. Like and fears of stakeholders.
requirement. other business processes, improvement
can only be assessed by measurement. Satisfy Regulators
Minimize Damage to Adjacent Geotechnical monitoring programs can Some facilities must be instrumented
Structures play a central role in providing these to meet the requirements of specific
Geotechnical construction may affect measurements. regulations, usually to help protect
adjacent property with undesirable public safety or the environment.
results. Expensive repairs, bad relations Advance State-of-Knowledge
and protracted litigation can result. Many of the advances in the theories Reduce Litigation
Movement of the ground outside a of geotechnical engineering have Data from geotechnical monitoring can
supported excavation is one example. their roots in data from geotechnical be a powerful deterrent to litigation.
The specifications might require the monitoring on full-scale projects. Contractors may claim differing site
contractor to provide an excavation The data give us insight into how conditions. Abutters may claim for
support system that limits horizontal things are performing and about damages caused by construction.
and vertical movements outside the ex- causal relationships. Historically, a Owners may claim poor performance
cavation to a specified amount, so that significant amount of geotechnical of the completed facility. Where
subsurface conditions are involved, In this use, data from a geotechnical asce.org as follows: Publications.
data from a good geotechnical monitoring program helps maintain the Research Databases. ASCE Online
monitoring program may provide various parties confidence in the per- Research Library. Search Marr,
powerful evidence to help reach a fair formance of the work and frees them Scroll to Why Monitor Perfor-
resolution of such claims. to focus on other issues. Increasingly, mance?.
owners desire performance monitor- Peck R.B. (1969). Advantages and
Show that Everything is OK ing systems that are comprehensive Limitations of the Observational
Increasingly we use geotechnical and robust but with instant reporting as Method in Applied Soil Mechan-
monitoring programs to demonstrate simple as a green light to indicate that ics. Gotechnique, 19, No. 2, 171-
the actual performance is within the everything is in an acceptable state. 187.
bounds anticipated by the designers.
The presumption is there will be no References W. Allen Marr, President and CEO,
surprises or unexpected consequences Marr W.A. (2007). Why Monitor Per- Geocomp Corporation,
to cost and schedule, and that formance? Theme Lecture, Am. 1145 Massachusetts Avenue,
unexpected behaviour can be identified Soc. Civ. Engrs. Symp. on Field Boxborough, MA 10719,
early enough to maintain control of the Measurements in Geomechanics Tel. (978) 635-0012,
project cost and schedule. (FMGM), Boston. Search www. email: wam@geocomp.com