Professional Documents
Culture Documents
Switchgear ELK3
Content
Content
1 Important Notes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.1 Supplier and manufacturer address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.2 Contact address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.3 Validity of this revision instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.4 Purpose of this revision instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.5 Safety note . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.6 Copyright . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2 Component description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Template: Inhalt 2
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
List of Figures
List of Figures
Template: Figur 3
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
List of Tables
List of Tables
Template: Tabelle 4
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
1 Important Notes
1.6 Copyright
We reserve all rights concerning this document and the components described therein.
It must not be reproduced or disclosed to third parties and the contents must not be
made use of neither in part nor in whole without our prior written permission.
E ABB Switzerland Ltd, Division High Voltage Products
Template: CR 5
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Componentdescription
2 Component description
In Fig.1 the individual elements of the fastacting earthing switch ELKEB3 are shown.
Detailed information regarding the installation, the function and the technical data of
the fastacting earthing switch ELKEB3 are to be found in the documents Operating
Instructions SF6Gas Insulated Switchgear ELK3" and Project Specific Data".
4
3
7
5
6
Template: Description_EB3 6
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Gas compartments
During overhaul work, gas compartments must be opened and entered. For this, the
Operating Instructions SF6Gas Insulated Switchgear ELK3", chapter Working on
gas compartments and partition insulators" and the document 1HC0028459 Manual
Handling Sulphur Hexafluoride SF6" have to be executed.
Before reassembling the affected components, the regulations in the Operating In
structions SF6Gas Insulated Switchgear ELK3", chapter Working on gas compart
ments and partition insulators" and the document 1HC0028459 Manual Handling Sul
phur Hexafluoride SF6" have to be followed. With improper treatment, reliable operation
of the installation is not assured.
Trouble shooting in accordance with check list These instructions are given in section 3.3
(only in case of error).
Template: Repair_Revision_EB3 7
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
In the following table the possible causes for potential problems with the fastacting
earthing switch ELKEB3 are listed. In order to restrict the fault location and the cause
of error, this list should be reviewed thoroughly prior to completing the revision works.
Template: Repair_Revision_EB3 8
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
1 2 3 4 5 8 9 10 11 12 13 14
Fig.3: Handcrank
Template: Repair_Revision_EB3 9
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Moving contact
Fixed contact
3.4.5 Loctite
Screws are usually secured and sealed using Loctite in the socket. Whenever Loctite
is mandatory during reassembly it is mentioned in the corresponding figure. The follow
ing Loctite has to be used:
Template: Repair_Revision_EB3 10
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Procedure:
Putting out of operation of the GISinstallation section, which contains the built in
fastacting earthing switch ELKEB3, adhering to all security measurements (see
chapter Maintenance, Inspection and Overhaul" in Operating Instructions SF6
Gas Insulated Switchgear ELK3)
The fastacting earthing switch ELKEB3 should be in the "O" (open) switch posi
tion
Unplug all external cable connections of the fastacting earthing switch ELKEB3
and fastacting earthing switch operating mechanism ELKDB3, adhering to all se
curity measurements (see chapter Maintenance, Inspection and Overhaul" in Op
erating Instructions SF6Gas Insulated Switchgear ELK3)
In accordance with the operating Instructions SF6Gas Insulated Switchgear
ELK3, chapter Working on gas compartments and partition insulators" and the
document 1HC0028459 Manual Handling Sulphur Hexafluoride SF6", remove
gas (evacuate) to overhaul the earthing switch ELKEM3 and ventilate with air.
Template: Repair_Revision_EB3 11
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Fastacting Fastacting
earthing switch earthing switch
Insulator
Fastacting earthing fixed
contact
Screw M10
Template: ChangeParts_EB3 12
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Pin wrench
Flange
Template: ChangeParts_EB3 13
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Template: ChangeParts_EB3 14
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
If the auxiliary switch or/and the heating element would be changed, refer to sec
Information tion 4.5.
Template: ChangeParts_EB3 15
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Guide segment
Template: ChangeParts_EB3 16
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Tubular contact
Reversing lever
Tubular contact
Sliding piece
Operating shaft
Template: ChangeParts_EB3 17
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Template: ChangeParts_EB3 18
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Long slot
Cable
Wiring conduit
Template: ChangeParts_EB3 19
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Reversing lever
Tubular contact
Sliding piece
Operating shaft
Template: ChangeParts_EB3 20
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Template: ChangeParts_EB3 21
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Template: ChangeParts_EB3 22
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Screws
Terminals
Cables of heating
supply voltage
Template: ChangeParts_EB3 23
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Template: ChangeParts_EB3 24
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Tubular contact
Template: ChangeParts_EB3 25
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
90
Position
Template: ChangeParts_EB3 26
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Screws
Terminals
Cables of heating
supply voltage
Template: ChangeParts_EB3 27
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Template: ChangeParts_EB3 28
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Heating element
Clamp
Screw
Template: ChangeParts_EB3 29
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Heating element
Clamp
Screw
Template: ChangeParts_EB3 30
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Pin wrench
Flange
Enclosure
Template: ChangeParts_EB3 31
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Fastacting Fastacting
earthing switch earthing switch
Insulator
Fastacting earthing fixed
contact
Screw M10
Template: ChangeParts_EB3 32
Manual: 1HC0037777 E01 / AC05
Revision Instructions SF6Gas Insulated Switchgear ELK3
Bring fastacting earthing switch ELKEB3 in position O" open and remove hand
crank
Mount earth connection
Attach earth connection
Fasten screws 4xM10 (42 Nm, Loctite)
Fasten cap nuts 4xM10 (42 Nm, Loctite)
The remounting of the fastacting earthing switch ELKEB3 is now finished. The mount
ing process of the operating mechanism ELKDB3 is described in revision instructions
1HC0037774.
Template: ChangeParts_EB3 33
Manual: 1HC0037777 E01 / AC05