You are on page 1of 17

Task Name Start Date End Date Duration Start Date in Number Form 42576.

Date in Number Form 42576.00 Use this number for the Minimum Bound of the Horizontal Axis to set the beginning of the chart.

Task One 7/25/2016 7/30/2016 5


7/25/16 7/30/16 8/4/16 8/9/16 8/14/16 8/19/16 8/24/16 8/29/16 9/3/16
Task Two 7/27/2016 8/1/2016 5
Task One

Task Three 7/27/2016 8/4/2016 8 Ta s k Two

Task Four 7/27/2016 8/6/2016 10 Tas k Three

Task Five 8/1/2016 8/9/2016 8 Ta s k Four

Task Six 8/1/2016 8/5/2016 4 Tas k Fi ve

Task Seven 8/3/2016 8/10/2016 7 Ta sk Si x

Tas k Seven
Task Eight 8/5/2016 8/12/2016 7
Task Eight
Task Nine 8/6/2016 8/9/2016 3
Task Ni ne
Task Ten 8/6/2016 8/10/2016 4
Ta sk Ten
Task Eleven 8/7/2016 8/13/2016 6
Tas k El even
Task Twelve 8/10/2016 8/16/2016 6
Tas k Twel ve
Task Thirteen 8/14/2016 8/19/2016 5
Task Thi rte en

Task Fourteen 8/15/2016 8/23/2016 8 Ta sk Fourteen

Task Fifteen 8/16/2016 8/26/2016 10 Ta s k Fi fte en

Task Sixteen 8/17/2016 8/28/2016 11 Tas k Si xteen

Task Seventeen 8/18/2016 8/29/2016 11 Tas k Sevente en

Key: Calculated Cell Manual Entry Cell

These cells will be automatically calculated based on These cells require manual input so the calculated
the inputs on other cells. cells have data to work with.
Duration
Task Name Start Date End Date (Days)

Task One 7/25/2016 7/30/2016 5

Task Two 7/27/2016 8/1/2016 5

Task Three 7/27/2016 8/4/2016 8

Task Four 7/29/2016 8/6/2016 8

Task Five 8/1/2016 8/9/2016 8

Task Six 8/1/2016 8/5/2016 4

Task Seven 8/3/2016 8/10/2016 7

Task Eight 8/5/2016 8/12/2016 7

Task Nine 8/3/2016 8/9/2016 6

Task Ten 8/6/2016 8/10/2016 4

Task Eleven 8/7/2016 8/13/2016 6

Task Twelve 8/10/2016 8/16/2016 6

Task Thirteen 8/14/2016 8/19/2016 5

Task Fourteen 8/15/2016 8/23/2016 8

Task Fifteen 8/16/2016 8/26/2016 10

Task Sixteen 8/17/2016 8/28/2016 11

Task Seventeen 8/18/2016 8/29/2016 11


Days Complete Days Percent Start Date in Number Form 42576.00
Remaining Complete

2.50 2.50 50%


7/25/16 7/30/16 8/4/16
3.75 1.25 75% Tas k One

2.00 6.00 25% Ta s k Two

8.00 0.00 100% Ta sk Three

6.00 2.00 75% Ta sk Four

1.40 2.60 35% Ta sk Five

Ta sk Six
1.75 5.25 25%
Ta sk Seven
4.90 2.10 70%
Ta s k Ei ght
0.90 5.10 15%
Ta s k Ni ne
2.40 1.60 60%
Ta s k Ten
3.90 2.10 65%
Ta sk Eleven
1.50 4.50 25%
Tas k Twel ve
1.50 3.50 30% Ta sk Thirteen

4.00 4.00 50% Ta sk Fourteen

4.00 6.00 40% Tas k Fi fteen

3.85 7.15 35% Tas k Si xteen

1.65 9.35 15% Ta sk Seventeen


Ta sk Seventeen

Key: Calculated

These cells will be automatical


inputs on other cells.
Use this number for the Minimum Bound of the Horizontal Axis to set the beginning of the chart.

8/4/16 8/9/16 8/14/16 8/19/16 8/24/16 8/29/16 9/3/16


Calculated Cell Manual Entry Cell

e cells will be automatically calculated based on the These cells require manual input so the
s on other cells. calculated cells have data to work with.
ing of the chart.

8/29/16 9/3/16
Duration
Task Name Start Date End Date (Days)

Task One 7/25/2016 7/30/2016 5

Task Two 7/27/2016 8/1/2016 5

Task Three 7/27/2016 8/4/2016 8

Task Four 7/29/2016 8/6/2016 8

Task Five 8/1/2016 8/9/2016 8

Task Six 8/1/2016 8/5/2016 4

Task Seven 8/3/2016 8/10/2016 7

Task Eight 8/5/2016 8/12/2016 7

Task Nine 8/3/2016 8/9/2016 6

Task Ten 8/6/2016 8/10/2016 4

Task Eleven 8/7/2016 8/13/2016 6

Task Twelve 8/10/2016 8/16/2016 6

Task Thirteen 8/14/2016 8/19/2016 5

Task Fourteen 8/15/2016 8/23/2016 8

Task Fifteen 8/16/2016 8/26/2016 10

Task Sixteen 8/17/2016 8/28/2016 11

Task Seventeen 8/18/2016 8/29/2016 11


Days Complete Days Percent Start Date in Number Form 42576.00
Remaining Complete

2.50 2.50 50%


7/25/16 7/30/16 8/4/16
3.75 1.25 75% Ta sk One

2.00 6.00 25% Tas k Two

8.00 0.00 100% Ta sk Thre e

6.00 2.00 75% Tas k Four

1.40 2.60 35% Ta s k Fi ve

Ta s k Si x
1.75 5.25 25%
Ta sk Seve n
4.90 2.10 70%
Ta s k Eight
0.90 5.10 15%
Ta s k Ni ne
2.40 1.60 60%
Tas k Ten
3.90 2.10 65%
Ta s k El even
1.50 4.50 25%
Ta sk Twel ve
1.50 3.50 30% Ta sk Thi rteen

4.00 4.00 50% Ta sk Fourteen

4.00 6.00 40% Ta sk Fifteen

3.85 7.15 35% Ta sk Si xteen

1.65 9.35 15% Ta s k Seventeen


Ta s k Seventeen

Key: Calculate

These cells will be automatical


inputs on other cells.
Use this number for the Minimum Bound of the Horizontal Axis to set the beginning of the chart.

8/4/16 8/9/16 8/14/16 8/19/16 8/24/16 8/29/16 9/3/16


Calculated Cell Manual Entry Cell

e cells will be automatically calculated based on the These cells require manual input so the
s on other cells. calculated cells have data to work with.
ing of the chart.

8/29/16 9/3/16

You might also like