You are on page 1of 16

THE ARUP JOURNAL

SHABANI SPECIAL ISSUE 1981


THEARUP
Vol. 16 Shabani special issue 1981
Published by
O v e A r u p Partnership
13 Fitzroy Street. London W1 P 6 B Q

JOURNAL Editor: Peter Hoggett


Art Editor: Desmond Wyeth F S I A D
Assistant Editor: David Brown

Front c o v e r : Underground w o r k i n g s s h o t holes being prepared ( P h o t o : B o b D a v e y )


B a c k c o v e r : C o n i c a l tower. Great Z i m b a b w e

Design of a system ( F i g s . 3 , 4 and 5 ) and the treatment


plant. In the feed system, the ore is taken
the structural concept and g i v e s rise to a n e w
form of treatment plant.

new asbestos mill in from the w e t ore stockpiles ( F i g . 6 ) and is


crushed, screened, dried and fed into the
Prior to the commencement of design of the
King Mill, it w a s assumed that the building
Shabani, Zimbabwe dry ore stockpile. From these stockpiles,
the ore is carried on conveyor belts to the
w o u l d f o l l o w tradition and have a steel frame
w i t h reinforced concrete infill floors. A r u p s
top of the treatment plant. It then gravitates w e r e commissioned to carry out the structural
Introduction d o w n through a series of screens w h e r e the design. Together with A A M , they decided to
fibre is separated from the rock and is use a solid flat slab concrete solution. T h i s
S h a b a n i and Mashaba M i n e s ( P r i v a t e ) Ltd.
carried in a current of air to c y c l o n e s , w h e r e decision w a s based mainly on e c o n o m i c c o n -
have recently completed the construction
it is deposited. T h e rock residue is treated in siderations and it has other advantages. All
of one of the w o r l d ' s biggest and most
fibreizers and screened again to separate necessary skills and materials for the c o n -
modern asbestos mills in S h a b a n i , Z i m b a b w e ,
out the shorter fibres. struction of concrete structures are available
at a cost in e x c e s s of Z $ 1 0 0 m . ( F i g . 1 ) .
The monthly milling capacity of the n e w mill After a s u c c e s s i o n of similar processes, the throughout Z i m b a b w e , w h i l e the majority
is designed to be 2 0 0 , 0 0 0 tonnes of ore. rock, by n o w a fine s a n d , is sent to a discard of steelwork for large structures requires
Shabani has the largest reserves of asbestos dump. The separated fibre in the c y c l o n e is the expenditure of foreign currency for supply
fibre in Southern Africa. T h e deposit occurs cleaned to remove dust and grit, graded by and erection. T h e comfort and safety of the
near the base of a lenticular ultrabasic sill length, and opened to the required degree. workers within the plant is of major c o n c e r n ,
14.5km long and 2.4 to 4 . 8 k m w i d e , w h i c h It is then blended to specification and bagged and an all-concrete structure provides fewer
intrudes early P r e - C a m b r i a n gneisses. T h e ready for shipment. crevices for dust and is easier to w a s h d o w n .
quality is good and the length of fibre is up to Delays in supplies of structural steelwork
T h e process design for the removal of the
3 0 m m in places. are a l w a y s a serious disadvantage.
asbestos fibre from the ore is an art based on
T h e design and construction w a s controlled years of experimentation and experience. A possible disadvantage of a concrete
by African Associated M i n e s ( P r i v a t e ) Ltd., Testing of prototype items of plant w a s solution is in reduced flexibility for c h a n g e
Secretaries and Consulting Engineers to carried out throughout the design period. T h e once the structure is complete. This problem
S h a b a n i and M a s h a b a M i n e s (Private) Ltd. final structural design and production of w a s s o l v e d , in effect, by overdesigning by
Ove Arup and Partners provided an 'arms reinforcing s c h e d u l e s goes from the f o u n - an agreed margin to allow for c h a n g e s . From
and legs' service to A A M by supplying the dations upwards, i.e. in the opposite direction the experience gained on the M a s h a b a
engineering skills that w e r e lacking in their to the mechanical design. A s the various Project as well as from other similar j o b s ,
o w n organization. In broad terms A A M designs w e r e developed simultaneously, a the concrete solution w a s further developed
carried out the design of the plant and the structural system w h i c h could accept c h a n g e s at S h a b a n i to provide not only the structural
mechanical equipment w h i l e Arups handled w a s required. T h e electrical design developed frame, but also in places, a part of the plant.
the civil, structural and electrical aspects. alongside the mechanical and had to be able
In order to be s u c c e s s f u l , the total plant,
Programming and cost control were handled to accept additional loads as the process
including the construction, operation and
jointly. Fig. 2 s h o w s diagramatically the w a s refined.
maintenance, had to be c o n c e i v e d as a w h o l e .
breakdown of w o r k into the various disci- Environmental conditions within the plant,
Historical development
plines. T h i s paper briefly describes A r u p s ' comfort and safety of staff, maintenance
work, w h i c h w a s completed at a cost of A similar mill, at King Mine, roughly t w o
costs, including those for d o w n time, and
approximately Z $ 4 3 m . thirds the size of the one at S h a b a n i , w a s
availability of skilled labour, were among the
built at M a s h a b a , 4 0 k m a w a y , 1 0 years
The process features considered during the design. T h e
earlier by the s a m e group. The design of the
text d r a w s attention to certain of these
The extraction of asbestos fibre from ore is a King Mine treatment plant w a s based on a
aspects.
lengthy a n d complicated process w h i c h vertical f l o w of materials through the
varies between different ore bodies. At reduction process rather than the horizontal Civil design
S h a b a n i , the ore is mined at various levels f l o w previously adopted by this group. T h i s T h e civil engineering w o r k s w h i c h w e r e
d o w n to a depth of about 5 7 0 m . concept proved s u c c e s s f u l and w a s repeated broken d o w n into a number of contracts
2 T h e mill has t w o basic s e c t i o n s ; the feed at S h a b a n i . It obviously radically c h a n g e s included upgrading existing services a n d
lit: V:

Fig.1
General v i e w of completed project

Fig. 2
B r e a k d o w n of work into various disciplines

Fig.3
Feed system : dryer building
s h o w i n g top of vertical dryer

Fig.4
Feed system : w e t pick-up building
s h o w i n g Q - d e c k dryer

Fig. 5
Feed system : screening plant
typical floor

Fig.6
Site surfacing and feed system :
wet ore stockpile
providing n e w facilities. T h i s work w a s
carried out in the period Au g u st 1 9 7 6 to
J u n e 1 9 8 0 at a total cost of around Z $ 4 m .
Of this, Z $ 2 m . w e r e part of the main project
w h i l e Z $ 2 m . w e r e for projects off-site.
Off-site housing
T h e decision to establish the n e w asbestos
mill at S h a b a n i gave rise to an immediate
requirement for additional housing on the
site. Traditionally the mine has provided
housing for all its w o r k e r s . T h e short-term
need w a s to provide housing to replace that
lost on the mill site and for the influx of
construction workers required to complete
the project, w i t h a longer term requirement
for the additional mine workers necessary to
cope w i t h the increased production. T h e
housing required w a s in three grades, w i t h
requirements of 6 0 high cost units, 2 0 0
medium cost units and 4 0 0 l o w cost units.
T h e l o w cost and some of the high cost units
w e r e located in an infill pattern in existing
t o w n s h i p s on the mine, w i t h the other units
in n e w t o w n s h i p areas.
O v e Arup and Partners carried out the
planning for the housing and the civil
engineering design for water and s e w e r a g e 7A 8T
reticulations, roads, stormwater drainage and Fig. 7
electrical reticulations. All housing units had Area of completed high cost housing
individual c o n n e c t i o n s to water supply,
s e w e r a g e reticulation and electricity, thereby
breaking a w a y from the tradition on the mine
for c o m m u n a l facilities for l o w - c o s t housing.
Street lighting w a s provided in all housing
areas. T h e services design maximized the
use of locally available material with asbestos
e5>
cement piping being used extensively for
water and s e w e r a g e reticulations and locally
available gravel for road construction. F i g . 7 Fig.8
s h o w s an area of completed high cost S e w a g e pumping station
housing.

D i v e r s i o n of s e r v i c e s both potable and industrial water. T h e delivery main to the treatment w o r k s , had
industrial water is recovered from the under- been included in our brief for the housing
T h e site c h o s e n for the n e w mill w a s an area
ground w o r k i n g s and is used in the process services. The next phase for w h i c h w e w e r e
previously used for low density housing and
and for garden watering. All water used on appointed w a s the design of the necessary
included, on the eastern boundary, the
the mine is supplied free of charge to the upgrading of the system serving the southern
national road from S h a b a n i to B u c h w a . All
mine personnel, and the per capita c o n s u m p - part of the mine. This consisted of four pump
the houses in the area w e r e to be demolished
tions are therefore enormous. Our report stations and approximately 4 k m of pumping
but certain services, serving areas outside
envisaged a rationalization of the main water main, and 4 k m of gravity s e w e r s .
the limits of the mill site, ran through the area.
reticulation to cater for the projected increase The pumping stations w e r e all designed as
Before bulk earthworks could c o m m e n c e ,
in population and the raising of living standards identical underground structures w i t h s u b -
all these through services had to be diverted
of the lower paid workers. The philosophy of mersible pumps. A l l o w a n c e w a s made in the
and the national road moved beyond the
bulk water storage on the mine w a s also design for increasing the number of p u m p s
confines of the site. T h e planning of the mill
examined and reported on. and duplicating the delivery mains w h e n
complex w a s in its early stages at this time
A s a result of this report w e w e r e c o m m i s - required, so that ultimately the system w o u l d
and conservative estimates had to be made
sioned to implement the first part of the cope with the f l o w s anticipated in 1 9 9 5 . Fig. 8
of the likely extent of the mill site.
recommendations w h i c h consisted of as h o w s a typical pump station w i t h inlet w o r k s
T h e diversion of the B u c h w a road comprised
1 2 , 0 0 0 m storage reservoir and 2.5km of
1
for grit removal.
a length of approximately 8 0 0 m over some
supply pipeline. T h e reservoir, of reinforced
difficult terrain. T h e c r o s s - s e c t i o n of the road T h e mill s i t e
concrete, w a s constructed on a hill over-
w a s the Government standard for this c l a s s
looking the n e w mill site and positioned to T h e civil engineering on the mill site w a s
of road of 7 m of surface on a 10m base
a l l o w for the construction of t w o future carried out in four stages. T h e first of these
course. Geometric standards laid d o w n by
reservoirs of similar size, as the demand w a s the bulk earthworks. Prior to c o n s t r u c -
the Government for national roads w e r e
required. The pipeline, w h i c h w a s 4 5 0 m m tion, the site consisted of fairly rough, tree
complied w i t h , in spite of the fact that at the
diameter asbestos cement, supplied water to covered terrain with a m a x i m u m fall across it
present, it is a gravel road on a very poor
the reservoir from the main pump station at of the order of 1 2m and a natural water course
alignment, approximately 2km from S h a b a n i .
w h i c h the Ngezi water supply w a s received. through the centre. B e c a u s e the planning of
T h e main pipe services crossing the mill site
the feed system w o u l d not be completed
consisted of a s e w a g e pumping main,
Sewerage reticulation until some time after the c o m m e n c e m e n t of
potable and industrial water supply mains
Simultaneously with the appointment to construction of the treatment plant it w a s
and a return s e w a g e effluent main. P l a n s
investigate the overall water reticulation of necessary to provide an earthwork solution
had already c o m m e n c e d for an upgrading
the mine, w e w e r e appointed to produce a that allowed flexibility in the planning. It w a s
of all these services and the immediate need
similar report for the overall s e w e r a g e therefore decided to provide a cut and fill
w a s therefore a short-term temporary diver-
reticulation. T h e terrain of S h a b a n i is made platform over the entire site. T h i s platform w a s
sion around the site. T h e four pipelines w e r e
up of numerous small hills with housing generally graded to falls of 1 :100 to permit
laid adjacent to each other in a single trench
areas generally located in the valleys between. drainage of the surface. T h e water course w a s
with minimal cover around the western and
Very limited use can therefore be made of diverted around the southern extremity of the
northern boundaries of the site.
gravity s e w e r a g e . A complex of s e w e r a g e mill site.
Water supply pumping stations existed over the mine with A s the planning of the mill complex became
The water supply to S h a b a n i c a m e from the several of these obviously overloaded. Our more finalized it w a s possible to design the
Lundi River. At the time of the start of the mill report recommended the rationalization and s e c o n d stage of the civil w o r k s . T h i s consisted
project, w o r k w a s already under w a y on the upgrading of the pumped s e w e r a g e system of the s e w e r a g e reticulation for the site, and
design and construction of a new dam on the as a phased development. T h e upgrading and roads and stormwater drainage over the
Ngezi River to supply S h a b a n i with water. re-siting of one of the pump stations serving northern portion.
In v i e w of this, w e w e r e asked to investigate the l o w - c o s t housing areas had already been T h e third stage took the stormwater drainage
the water reticulation on the mine, and to required as a result of the extension of the l o w - a step further and provided temporary drainage
report on it. T h e entire mine complex is cost housing, and this, together with a in the areas not finalized. T h i s w a s carried out
4 supplied with a dual reticulation supplying secondary pump station pumping into it and a priorto the 1 9 7 8 rainy s e a s o n .
Fig.9
S e c o n d a r y drain to
south of treatment
plant building

Fig.10
M a i n drain
through mill site

Fig.11
S p i l l w a y from
mill site

Fig.12
Site surfacing

The fourth stage w a s the completion of the Structural design fell within the coffer topping and could
stormwater drainage, finalization of the site T h e total civil and structural engineering therefore be ignored in the d e s i g n .
levelling, the roads, the surfacing of the site, w o r k s on the mill site were completed for a In each flow line there are three service ducts
the completion of the s e w e r a g e reticulation cost of Z $ 2 7 . 3 m . T h e treatment plant repre- ( b o x c o l u m n s ) w h i c h act as air plenums
and the intersection of the main a c c e s s road sents 5 8 % of the civil contract, the remaining connecting the fan c h a m b e r s to the various
to the site w i t h the Shabani to B u c h w a road. buildings 3 4 % , w h i l e the bulk e a r t h w o r k s , main floors. T h e box c o l u m n s also act a s
diversion of existing services, site roads, vertical shafts to enclose electrical cables,
The stormwater drainage consists principally
stormwater drainage, etc., make up the stairs and other services. O p e n i n g s are pro-
of open concrete lined drains ( F i g . 9 ) , piped
remaining 8%. vided in the sides to a l l o w a c c e s s w h e r e
or culverted. Underground stormwater drain-
Building work on the treatment plant building required. T h e main floor to floor height is 6 m .
age w a s avoided wherever possible, as the
milling process produces large quantities of c o m m e n c e d in October 1 9 7 7 and w a s c o m - B e t w e e n the first and s e c o n d floors and for
fibrous dust w h i c h , during S h a b a n i ' s long pleted in December 1 9 7 9 , w h i l e the feed 12 floors thereafter, hung floors are used for
dry season, c o u l d easily block invisible storm- system w a s completed in May 1 9 8 0 . T h e total working platforms to the machinery on the
water drainage routes. T w o main drains ran civil/structural work force peaked at 2 , 6 5 0 main floors. All floors, including the hung
through the site, one at the southern extremity in February 1 9 7 9 . floors, will be w a s h e d d o w n w h i l e the plant
carrying the water from the diverted water is in operation and therefore openings are
course as w e l l as water from the southern T r e a t m e n t plant provided with upstand surrounds except the
portion of the site. T h e other main drain T h e main structural design effort w a s directed w a s h d o w n outlets. A s c a n be seen in F i g . 1 3 ,
through the centre of the site picked up a t o w a r d the treatment plant. T h i s building the hung floors cover only portions of the
small catchment outside the site and also rises 1 0 0 . 6 m above the ground, and has a complete floor area. M a n y of the items of plant
drained the majority of the site ( F i g . 1 0 ) . A t t h e double basement to a depth of 5.5m. T h e on one main floor are c o n n e c t e d to the plant
western end of the site, w h e r e the central total floor area is 1 3 8 , 0 0 0 m . T h e first main
2
on the floor above or below by s c r e w c o n v e y -
drain discharged, the bulk earthworks contract nine floors are 1 0 0 . 5 x 7 6 . 5 m , stepped back ors or c h u t e s . T h e openings required in the
had raised the finished level some 8 m above at the ninth level up to the 16th floor. T h e hung floors are more n u m e r o u s and often
natural ground level. T h i s required a s p i l l w a y upper main floors are 1 0 0 . 5 33.0m. Fig. 13 larger than in the main floors and w o u l d have
structure to take peak flow of approximately s h o w s a section through the treatment plant. made s p a n n i n g between the main vertical
1 1 m / s e c . prior to passing it under the main
3

A typical main floor, w h i c h c o n s i s t s of four supports difficult w i t h a reasonable depth of


mine hall road ( F i g . 1 1 ) . f l o w lines, a service bay and a perimeter slab. For this reason additional supports from
c o n v e y o r corridor, is s h o w n in F i g . 17. the main floors w e r e a d d e d . Hanging rather
The main a c c e s s road into the site carries the than propping the intermediate floors w a s
Most of the plant is carried on the main floors.
finished product from the mill to the rail head decided upon to allow m a x i m u m w o r k i n g
T h e column grid w a s selected to impose
for d e s p a t c h . T h i s w a s the only formal road space above and around the plant on the
minimum restraints on the plant layout and
on the site, and w a s a 7 m surfaced road on a main floors ( F i g s . 1 4 , 1 5 a n d 1 6 ) .
at the same time, together w i t h the box
10m base. T h e client's requirements for the
c o l u m n s , provide a linear surface on w h i c h In order to maintain the rhythm of the c o n -
remainder of the site w e r e that v e h i c l e s should
to attach crane rails, conveyor gantries and struction programme simple standard elements
be able to drive a n y w h e r e w i t h o u t being
so on. C o l u m n sizes w e r e constant for the were used to a m a x i m u m , although in some
impeded by stormwater drainage or other
surfaces. T h i s required that secondary drains entire building. Major floor openings, i.e. larger c a s e s this w a s extravagant in terms of
on the site s h o u l d be s h a l l o w dish' drains, than 1.2m square, w e r e decided before the materials. W h e r e it w a s no longer possible to
permitting v e h i c l e s to cross. T h e entire 2 5 h a slab w a s cast, w h i l e many minor openings use or justify the use of standard elements,
site w a s therefore topped w i t h a compacted w e r e added after the reinforcing had been conventional building t e c h n i q u e s w e r e u s e d .
gravel layer sealed w i t h a single seal surface designed and detailed. Where possible, these
T h e main non-typical section of the treatment
dressing. Within this, identifiable heavy were added before the concrete w a s cast, but
plant is the dust filter area, situated at the top
traffic routes w e r e demarcated, with double in some cases w e r e punched through the of the l o w portion. T h i s area h o u s e s 10 fans,
seal surfacing in these areas. Figs. 6 and 12 coffer topping afterwards. Approximately t w o of w h i c h are on standby. T h e remaining
s h o w some of the surfaced area with d i s h ' 8 0 % of the openings, other than major eight provide 5 7 , 0 0 0 m of air a minute for the
3

drains. openings c o m m o n to all typical main floors. plant. T h e air c h a m b e r s operate at a negative 5
Fig.13
S e c t i o n through treatment plant

Fig.14
Treatment p l a n t : seventh
floor w i t h equipment installed

Fig.15
Treatment p l a n t : typical main
a n d intermediate hung floor

3
w i t h equipment installed

Fig.16
Treatment p l a n t : main floor
w i t h c y c l o n e s projecting through
h u n g floor as above
13A 14T 15T
pressure of 3 7 5 m m of water gauge. T o save 2 . 8 5 m square panels with soft board joints Main floors
foreign currency the w a l l s of the chambers are between panels T h e s e are of 1.5m square coffer construction
cast in situ concrete and the dust hoppers are ( 3 ) 1 0 0 0 gauge polythene sheeting with w i t h an overall depth of 0.5m ( F i g . 1 8 ) . T h e y
precast concrete. T h e construction of the double welt folds are designed for a superimposed load of
filter area and the high portion of the treat- 1 5 . 6 k N / m ( m a i n floor live load 6 . 0 k N / m ,
2 2

( 4 ) 2 m m thick waterproofing membrane of


ment plant building proceeded simultaneously. hung floor live load + dead load 9 . 6 k N / m ) . 2

butyl rubber sheeting with z i g - z a g edges


No expansion joints are provided in the treat- T h e y w e r e also designed to have props
glued together on site
ment plant building except at roof levels, and removed after s e v e n d a y s and to carry a
then not for those areas over the filter ( 5 ) 2 5 m m thick polyurethane insulation
subsequent floor after 14 days. T h e design
chambers. T h e roofs over the filter chambers bonded to concrete
a l l o w s for additional openings up to 1.2m
are insulated to reduce thermal movement. (6) Surface of concrete or screed. square to be added any time through the
Additional reinforcement w a s added to cater In less critical areas waterproofing consists of coffer topping. Cable routes were provided
for thermal and shrinkage strains. t w o layers of mastic asphalt layed on Kraft within the coffer depth in specified locations
The main reason for no joints w a s to avoid bituminous paper and covered w i t h flat both to protect the c a b l e s and to minimize
having to cater for movements in s u c h asbestos/cement roofing tiles. space requirements. Additional shear r e i n -
mechanical equipment as s c r e w c o n v e y o r s , A minimum of 1 in 8 0 falls w a s achieved forcement w a s provided locally in the coffer
chutes, crane rails and so on. either by tilting the slab, or by laying a screed ribs. ( F i g . 1 9 ) .
to fall. Hung floors
Waterproofing of the filter c h a m b e r s w a s
particularly critical, as any water or air leakage T h e six standard building elements used for These are 2 0 0 m m solid slabs. Support points
w o u l d interfere with the process. Working the treatment plant building are itemized for the hung slabs w e r e confined to the inter-
d o w n w a r d s from the top the waterproofing below. These w e r e developed in close section of ribs in the main slab, but the c h o i c e
medium w a s built as follows : collaboration with the civil contractor w h o s e of intersections depended on the plant layout.
practical experience w a s i n v a l u a b l e . M o c k - u p s Often they were irregularly placed, not at the
( 1 ) 4 5 0 x 4 5 0 X 4 0 m m thick precast concrete
of all the standard elements were made before optimum structural s p a c i n g . T h e s e slabs
slabs with 2 5 m m open joints between slabs
the construction of the treatment plant were designed using yield line technique.
(2) 75mm sand/concrete cover slab in commenced. (Figs.20and21).

Fig.17
F l o w line F l o w line i Service B a y
F l o w line F l o w line
'4 T y p i c a l main floor plan
of the treatment plant

Fig.18
12 Treatment p l a n t : B line w a l l
(south side of building)

y 3<H px^ - i 83G


( P h o t o : R o b a l S t u d i o s ( P v t . ) Ltd.)

Fig.19
*3 i 3 -JP4= " 2 1
Coffer rib w i t h additional
is a a la a 14-t 2
shear reinforcement
T7 P 5 15 F i g . 20
8 I 6 Treatment plant building : fourth and
7 fourth intermediate hung f l o o r s s h o w i n g
' C line c o l u m n and B - C box c o l u m n s
( P h o t o : R o b a l Studios ( P v t . ) Ltd.)

F i g . 21
16
Treatment plant building : sixth floor
a n d sixth intermediate floor s h o w i n g
17 openings for c y c l o n e s in intermediate floor
I I
( P h o t o : Robal S t u d i o s ( P v t . ) Ltd.)
I I
I
19
I I

Key
Plant openings 1. Bucket elevators 1 1 . S u p p l y air plenum
typical to 2. Electrical cable duct 12. Crane w a l l to w o r k s h o p
all main 3. S u p p l y air plenum 1 3. Material hoist
floors 4. Return air plenum 14. Passenger elevator
Plant openings 5. Stairs and main elevators 1 5 . Main stairs
peculiar to a 6. Return air plenum 16. Material hoist
particular 7. S u p p l y air plenum 17. Small materials hoist
floor (71 on 8. Electrical cable duct 18. T o w e r crane openings
example s h o w n ) 9. Electrical cable duct (temporary)
Conveyor 10. Return air plenum 1 9. Spiral stairs
Corridor

17A 18T 19T 20 A 21T

elllJ
* 7
H a n g e r t o p section
cast into concrete

a) Stepl

Hangertop section
remains after props
b) Step 2 have been removed

Fig. 22
Perspective v i e w of hanger design

Hangers
T h e design of the hangers removed them as a
restraint on the construction critical path as
they did not interfere w i t h the propping of a
slab or of the subsequent slab. T h e hangers
are e n c a s e d in concrete for protection.
Fig. 2 2 s h o w s the hanger design and Figs.
2 3 a , b a n d c s h o w the s e q u e n c e of c o n -
structing the main and hung floors.

Box c o l u m n s
T h e s e have 2 5 0 m m w a l l s . Structurally their
function is to provide vertical supports and
lateral stability. T h e internal w a l l s and floors
were cast after the outside shell.
Columns Hanger lower
One standard size of 0 . 7 5 X 1.5m w a s used section bolted
for all c o l u m n s . Their bending stiffness relative into place
to the slab permitted a reduction in the overall
design moment of the slabs.
Precast cladding units (Fig. 24)
T h e total area of cladding is 3 0 , 0 6 2 m . 2

Precast concrete, structural steel supporting


a s b e s t o s / c e m e n t sheets a n d glass reinforced
cement panels were among the alternatives c)
considered. T h e cladding needed to be sturdy
and durable as replacement or repairs w o u l d
be costly and difficult. T h e precast concrete
solution turned out to be the cheapest and F i g . 23
the one w h i c h best suited the client's require- S e q u e n c e of
ments. T h e typical panels are 6.5 X 1.5m in constructing the
size w i t h a mass of 1 4 8 0 k g ( F i g . 2 5 ) . T w o main and h u n g
w i n d o w s per panel are provided to give a floors
human scale to the units.
T h e vertical joints between panels are o p e n -
drained w i t h a baffle strip and an air seal. T h e
setback in the building between the ground
and the first floor simplified the waterproofing
detail at the ground floor and provided a
covered w a l k w a y around the building.
B r i c k w o r k w a s used between the ground and
the underside of the first floor. A precast F i g . 24
solution used up to the underside of the first Precast cladding units
floor on King Mill treatment plant project (Photo:
proved costly, because the numerous o p e n - Ove Arup & Partners
ings at this level resulted in a number of Zimbabwe)
8 non-typical panels.
Construction
T h e use of standard elements made possible
a fast rate of construction on the site. A
500mm minimum programme of 19 d a y s per floor w a s
achieved, w i t h an average of 26 d a y s per
floor. T h e m a x i m u m concrete pours w e r e in
e x c e s s of 4 0 0 m per day ( F i g . 2 6 ) .
3

Four tower cranes, each capable of lifting


2 , 5 0 0 k g at full reach were used on the
treatment plant. Concrete w a s supplied from
t w o mixers on the east and w e s t of the
building. Their m a x i m u m delivery rate w a s
1 5 m / h o u r e a c h . Concrete w a s moved into
3

position either in s k i p s or by pumping. T h e


m a x i m u m output of the pump w a s rated at
5 0 m / h o u r , but this w a s never achieved as it
3

exceeded the rate of the mixer. Pumped


concrete w a s used for the entire height of the
building. Concrete slumps were 3 5 - 4 5 m m
and 8 5 - 1 0 0 m m for conventionally placed and
pumped concrete respectively. In the solid
c o l u m n s only conventionally placed concrete
w a s used. E l s e w h e r e both types of concrete
were used interchangeably.
5.5m T h e main slabs w e r e formed w i t h fibre glass
moulds and steel pans supported on tubular
steel props, at 1.5m centres each w a y ( F i g .
2 7 ) . T h e support system a l l o w e d for the
removal of the coffer mould, leaving props
in place at the intersection of the ribs. For
typical areas reinforcing w a s made up into
cages before being lifted onto the deck, and
then joined together using splice bars. T h e
amount of steel fixing done in place w a s kept
to a practical minimum.

T h e 2 0 0 m m hung slabs were formed using


steel pans, carried on beams, supported by
steel props s p a c e d on a 1.5m x 3 . 0 m grid.

F i g . 25
T y p i c a l precast panel

F i g . 26
General v i e w of treatment plant
building, packed fibre store
and mechanical equipment store
( P h o t o : Robal Studios ( P v t . ) Ltd.)

**K
l >

)
i


I3E
a c c u r a c y of the building. External reference
beacons w e r e used to establish internal
control b e a c o n s at ground level. T h e s e four
corner points w e r e then transferred u p w a r d s
w i t h a precision optical plumb to provide a
replica of control for construction w o r k on
each floor.
Specific construction lines were then e s t a b -
lished at e a c h construction level by theodolite
observations and offset measurements from
this control grid. From these, reinforcing and
shuttering w e r e erected and c h e c k e d before
concrete w a s poured. Ideally these secondary
construction lines should have been set out
and adjusted proportionately between the
main framework before construction w o r k
c o m m e n c e d . H o w e v e r , as it w a s not practical
to complete one floor before proceeding to
the next, setting out work had to be carried
out piecemeal, usually from one corner of the
building.
The points and lines established in this manner
on upper floors were c h e c k e d from time to
time by direct observation and measurement
to external b e a c o n s . B y and large the monitor-
ing of construction w o r k w a s carried out
using a combination of triangulation, precise
traversing a n d levelling from outside control
beacons or n e w stations established in
convenient positions. A system w a s devised
F i g . 27 to continually c h e c k a l l - 1 6 5 c o l u m n s and
Treatment p l a n t : s e c o n d floor coffers in position and steel being fixed points of structural significance and process
(Photo : Robal Studios ( P v t . ) Ltd.) the results by computer. A program w a s
developed to calculate the grid co-ordinates
Again it w a s impossible to remove the pans the slab module in the vertical direction and of each corner of all the c o l u m n s , top and
w h i l e leaving the props in place. Welded wire openings in the w a l l s occurred almost bottom, on e a c h floor from a series of
mesh w a s used for top and bottom reinforcing a n y w h e r e . T h i s complicated the design and adjusted traverses along each line of measure-
over the entire slab. C u t - o u t s for openings the detailing, thus c a u s i n g delays in the ments, north/south and e a s t / w e s t , closed on
were made on site and additional reinforcing construction. Had this restraint been fully the outside main grid control lines. T h i s data
added at supports and around openings. appreciated at the outset it may have been w a s used to determine the positions of each
possible to provide structural c o l u m n s in the c o l u m n at e a c h floor level in turn, relative to
T h e hollow c o l u m n s and all other w a l l s were adjoining c o l u m n s in a horizontal plane and
corners with large non-structural infill panels
formed w i t h gang forms. Where possible, to the same c o l u m n at a level immediately
w h i c h could have been added later.
prefabricated reinforcing panels w e r e used. above and below the particular level c o n -
T h e w a l l s were poured continuously over the Solid c o l u m n s were cast using steel box cerned.
5.5m height in approximately 2.0m lifts. T h e shutters. T h e reinforcing c a g e s were pre-
fabricated. A survey w a s carried out on the effects of
internal w a l l s and slabs were cast afterwards.
c h a n g e s of temperature on the structure, both
R e v i e w i n g the design and construction of the T h e precast concrete cladding units were cast during construction and to the completed
treatment plant in retrospect, one structural in a yard adjacent to the site. They were lifted building. T h e results of this survey w e r e
element that could obviously have been better onto the buildings at night using the tower n e g a t i v e ; if there w a s a temperature effect
designed w a s the box c o l u m n s , especially as cranes. it could not have exceeded the k n o w n
they were on the critical path. Unfortunately A qualified surveyor w a s attached to the a c c u r a c y of the survey work of 4 m m
the mechanical designers could not maintain resident engineer's team to monitor the standard deviation.

F i g . 28
Histogram s h o w i n g difference between surveyed and design positions of the centre of gravity of c o l u m n s

120

110

100

90

80

s 7


cr
60
LL

50

40

30

20

10

0 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40

Differences between surveyed and design positions of the centre of gravity of c o l u m n s ( m m )


From the results obtained s h o w n in F i g . 28 (3) Pit sand The following s y s t e m s were considered for
for the difference between surveyed and T w o sources of pit s a n d were used. T h e s e the fundamental control of the p l a n t :
design positions of the centres of gravity of were 2km from the site on the S h a b i River and (a) Computer based equipment.
the c o l u m n s , it c a n be seen that 1.6% of the 2 5 k m from site on the Nyaratedzi River. (i) Programmable logic
results are greater than 2 5 m m and 5 % are A n on-site concrete team w a s established to controllers (PLC)
greater than 2 0 m m . T h e results for the control the design and placing of the concrete. (ii) Micro processing units (MPU)
difference between surveyed and design All aggregates complied w i t h the requirements ( b ) Solid state logic (SSL)
positions of c o l u m n corners w e r e similar of the Central African Standard CASA34:
with 1.7% of the results greater than 2 5 m m ( c ) E l e c t r o - m e c h a n i c a l relays
1969. logics (EMRL)
and 4 . 7 % greater than 2 0 m m . T h e allowable
tolerance w a s 2 5 m m . T h e allowable tolerance Reinforcing bars available on the project Investigations revealed that the local ( Z i m -
for the difference between the position of consisted o f : b a b w e ) suppliers had neither the expertise
column corners at the top and bottom of the ( 7 ) Square twisted high yield 3 0 , 2 5 , 2 0 , 16, nor facilities to provide this type of equipment
same column w a s 20 mm. 5 % of the results 12 and 1 0 m m w i t h a characteristic strength on the scale necessary for the requirements of
were outside tolerance, 2 % were greater than fy=410N/mm 2
this project. Enquiries w e r e , therefore, directed
2 5 m m . T h e allowable tolerance for the at the more prominent external suppliers. T h e
( 2 ) Hot rolled round mild steel 3 0 , 2 5 , 2 0 , 1 6 ,
difference in position of c o l u m n corners analysis of these enquiries w a s then used to
1 2 . 1 0 , 8, 5.5mm with a characteristic strength
directly above and below a slab w a s 3 0 m m . firm up on a satisfactory solution to the
fy=250N/mm 2

1.5% of results were greater than 3 0 m m and control problem and to open negotiation with
M a x i m u m bar length 1 2 m .
4 . 0 % of results were greater than 2 5 m m . T h e prospective suppliers,
above percentages were obtained using (3) Pre-stressing wire. T h e only size available (a) C o m p u t e r - b a s e d e q u i p m e n t
between 1,000 and 2 , 0 0 0 results and it is felt locally w a s 4 m m diameter strand w i t h a (/') Programmable logic controllers
that this gives a reasonably accurate result characteristic strength fy 1700N/mm . 2

T h i s class of equipment is cost-effective only


for the entire building. It is interesting to note Steel sections available locally consisted of w h e r e a high degree of logic in terms of input
that the a c c u r a c y of positioning c o l u m n s the following maximum sizes : related to output is necessary. From prelimin-
appeared to increase up the building with ary enquiries it w a s evident that the cost of
(7) 152 76 1 8 k g / m c h a n n e l s
a considerable increase between the third this type of equipment w a s in order of 2 0 0 %
and fifth floors, w h i c h coincided w i t h the (2) 230 25 4 5 k g / m flats more than that of the other alternatives. For
arrival on site of a full-time surveyor. {3) 100 100 1 7 . 8 k g / m angles this reason P L C d e v i c e s were given little
T h e actual position of the centre of gravity (4) 65 140 1 4 . 3 k g / m I beams. consideration.
for the vertical structure w a s determined at (//') Micro-processing units
Larger sizes were available but required the T h i s equipment proved to be slightly more
each floor. T h e largest distance from its design expenditure of foreign currency.
position w a s 9.9mm at the top of the s e c o n d expensive that the remaining alternatives but
floor. Labour w a s available in the area, but in most w a s not disregarded for this reason. Personnel
c a s e s w i t h no previous experience. During the with adequate technical expertise are at a
The geometry of a building s u c h as the site levelling and basement excavation phases premium in Z i m b a b w e . Recruitment of the
S h a b a n i Mill is important from t w o points of the project, a training school w a s estab- requisite calibre of staff a l w a y s presents a
of v i e w . Firstly from the structural point, lished on the site. G a n g s were trained on each problem. Another consideration w e i g h i n g the
w h e r e eccentricities c a n c a u s e significant specific standard building element by the decision in favour of the simpler s y s t e m s w a s
secondary stresses and, secondly, for pieces civil contractors. Construction techniques the high obsolescence rate of computer
of equipment s u c h as conveyors, lifts, etc., devised by the civil contractor's senior site equipment and its associated spares.
it is important that the structure does not staff enabled a high standard of construction
move out of plumb by more than the specified to be achieved w i t h the minimum use of
tolerance. skilled labour. T h e majority of their manage-
Civil engineering building c o n t r a c t ment and supervisory staff had to be imported
especially for this project.
T h e civil engineering contract for all buildings
in the mill w a s negotiated w i t h Grinaker Electrical design --
( A f r i c a ) ( P r i v a t e ) Ltd. Briefly, the contract
T h e following statistics give the scope of the
w a s handled as f o l l o w s :
electrical installation w h i c h w a s completed
During the preliminary design phase of the for a cost of Z$14 m., between the period
treatment plant, a bill of quantities based on J a n u a r y 1 977 and J u n e 1 9 8 1 .
provisional quantities measured from sketches
w a s prepared. Using these quantities and their Number of drives 4 , 0 0 0 plus
make up, rates were agreed by A r u p s and
Grinaker. A s final d r a w i n g s became available Installed transformer
at each level, they were measured and the capacity 42 MVA
agreed rates were applied to these quantities.
Reactive power 16 M V A V
In a similar w a y , separate bills w e r e prepared F i g . 29
from sketch plans for all buildings in the feed Service voltages 11,000/3300/ Typical cable racking,
systems, and then remeasured from final 550/400/230 below main floor coffered slab
d r a w i n g s . T h e treatment plant rates w e r e used
throughout, except w h e r e a n e w skill w a s Light fittings 12,000 F i g . 30
involved in w h i c h case a new rate w a s agreed. Cable access to s u b - b a s e m e n t ( b e l o w M C C s )
Total length cable 7 0 0 km
T h e cost plan w h i c h w a s prepared before
( F i g s . 2 9 and 3 0 )
construction commenced was updated
monthly as information firmed up. T h e s e costs Equivalent 1 0 , 0 0 0 km
were fed to the client w h o kept an overall cost single core cable
plan for the project. Escalation w a s based on
actual c h a n g e s to the make up of the rates Number of control 500,000
and w a s applied as it occurred. connections

Local material and labour Electrical staff 26 Design


T h e availability of local materials and skills (at peak) office, 4 Site
w e r e significant factors in the choice of the
Contractor's staff 80
structural concrete solutions for the different
(at peak)
buildings w h i c h make up the mill. Concrete
aggregate used on the project consisted o f :
Control system selection
(1) Coarse aggregate
It w a s necessary for the efficient operation,
A medium grained granite of reasonably
the utilization of labour and effective m a n a g e -
satisfactory quality obtained from Siboza I \
ment, that the large number of drives present
Quarry approximately 1 0 k m from site. I n c o n -
in this plant were centrally controlled, super-
sistent gradings and poor shape of this
vised and monitored. T h e high cost implica-
aggregate required close on-site attention.
tions resulting from d o w n time of the plant
( 2 ) Fine aggregate make it essential that any control applied is as
River sand w o n from the S h a b i River approxi- effective and simple as possible, whilst
simultaneously offering the m a x i m u m in \
mately 1 0 k m from the site. T h e fineness
modulus varied from 2.3 to 3.6 w h i c h again terms of fault diagnostic aids and fast \
required strict on-site monitoring. component replacement type. \\%\ \
(b) S o l i d s t a t e s y s t e m s of the data logger is s u c h that no influence on grammes are carried out at the interlock
Solid state s w i t c h i n g c a n be considered control is exercised. Malfunction of this matrix. ( F i g s . 34 and 3 5 ) .
statistically superior to the electro-mechanical system does not therefore result in plant Both the inputs and outputs of the drive and
relay with its attendant moving parts. H o w - stoppages. auxiliary cards are represented at the inter-
ever, the disadvantage with this system is the D e s c r i p t i o n of c o n t r o l s y s t e m ( F i g s . 31 lock matrix in the form of sockets. Flying
l o w susceptibility to line-borne noise. Unfor- and 3 2 ) leads with corresponding plugs are then
tunately, disturbances of this nature cannot be To meet the criteria of the provision of fault employed to patch up the desired sequences.
analyzed at the design stage. diagnosis aids along with a quick component A mimic display w a s provided to indicate
Light current technicians necessary for the replacement time, special c a r d s were designed. the process flow and drive status, the status
maintenance of solid state systems have Each motor control circuit w a s then allocated being confirmed by a multi-state indicating
generally progressed to higher employment a standard drive card. T h e s e cards w e r e lamp. T h e lamp indicates the following
status and are not particularly interested in manufactured from printed circuit bases conditions:
maintenance positions. T h e residue of staff before being loaded w i t h the necessary Red-field isolator o p e n / s t o p button operated
available for maintenance is usually an relays and light emitting diodes ( L E D ) to
electrician w h o eludes or offers resistance to Amber (flashing) - alarm condition
provide both control and fault diagnostic
black box techniques. functions ( F i g . 3 3 ) . Green - drive running
(c) E l e c t r o - m e c h a n i c a l r e l a y l o g i c Supplementary cards ( a u x i l i a r y ) w e r e e m - Blue - item e x c l u d e d from operation.

T h i s equipment without doubt offers the ployed to provide s u c h functions as timing T h e mimic lights are driven from the respec-
greatest degree of operational stability. It is to interludes and contact amplification. tive drive cards, the signals being c o n v e y e d
a large extent insensitive to disturbances that The relays and components fitted to the above via 50 core cables. The digital signals driving
generally create havoc on the more sophistic- mentioned cards were selected for 4 8 volt the mimic display w e r e also employed as
ated systems. No special k n o w l e d g e is D C , this being the highest available operating status inputs to the event-recording data
required for application. Further advantages voltage for miniature framed relays. logger. A g a i n 5 0 core cables were utilized
are realised from the basic simplicity of this T h e drive control and auxiliary cards w e r e to transmit this information from the mimic
system. Maintenance staff usually possess a accommodated in card files w h i c h were then to the data logger ( F i g . 3 6 ) .
rudimentary understanding of these s y s t e m s rack-mounted. Control cabling
and are therefore reasonably confident of their
Integral to these relay racks are marshalling T h e extremely high density of incoming and
ability to analyze, and subsequently rectify, in
and interlocking matrices w h i c h allow c o n - outgoing information to and from the relay
an expedient manner, 9 9 % of most faults that
nection of field inputs to the drive cards and racks, mimics and field control stations made
occur.
the subsequent s e q u e n c i n g / i n t e r ' o c k i n g pro- it necessary to develop a special s c h e m e .
With an assessed m a x i m u m of six operations
per hour per relay a n d a quotient of 1 0 6
number of operations, the probable reliability F i g . 31
term of this class of equipment w o u l d be in Typical hook-up
Local control station

1
e x c e s s of 2 0 years. diagram

i
Conclusion F i g . 32
On the basis of the foregoing considerations, Illustration of
the c i r c u m s t a n c e s particular to the project, Power Motor control centre
typical drive Marshalling box
reference and liaison w i t h other end users, it interlock
w a s our opinion that the electro-mechanical
relay logic w o u l d best fulfill the requirements F i g . 33
of this project. T y p i c a l drive card
It w a s decided that, in addition to the mimic Control Control desk
display, a data logging system should be logic panel
provided to record faults and the time at w h i c h
these faults occurred. It w a s therefore
necessary to perform this function w i t h a
( 1 5 , 0 0 0 lamps) Microprocessor-
computer-based microprocessor unit ( M P U ) .
mimic display based data logger
It may be argued therefore that the use of the
M P U for data logging purposes lent viability
Process information Monitors plant status
to the economical use of a computer-based
and drive status logs in real time
control system. H o w e v e r , feasibility studies
stoppages and
indicated that the cost savings w e r e insig-
identifies cause
nificant. Furthermore, the mode of operation

Field connections
for marshalling matrix

Drive Outputto M C C
card Output to interlocking matrix o Green L E D - Overload healthy
Input from interlocking matrix o Green L E D - C o n t a c t o r closed
Coil Drive card points represented o Red - I n t e r l o c k failed
N / O contacts on interlocking matrix
N / O contacts o Red - Stop button activated
Timer and auxiliary
N / O contacts
relays identical o Red - Alarm relay activated
+ ve j _
Start
button
02
]Drive1
]Drive2
]Drive3


Resistors

Relay Relay

Start Card end


D1 D2 D3 button
connectors
rive 1
Capacitors
Relay Relay

A
O

T1
Drive 2 ,
Time
interval Drive 3
--''-I-Si

F i g . 34
Front v i e w of relay rack s h o w i n g
interlock matrix (note roof-mounted
s m o k e detectors)

F i g . 35
Rear v i e w of relay rack
s h o w i n g marshalling matrix

F i g . 36
Control room s h o w i n g
mimic panel and control desk

F i g . 37
Motor control centres (1 line)

W h e n it is considered that the average drive connections. Each p l u g / s o c k e t arrangement T h e 5 0 core plugs each required a p p r o x i -
has 11 incoming/outgoing c o n n e c t i o n s with a c c o m m o d a t e s 5 0 c o n n e c t i o n s in an area mately 15 minutes to terminate results in a
approximately 3,600 drives, the number of approximately 25 6 0 m m . T h e total area revised time of 2 0 0 hours. T h i s w a s obviously
terminating points at the relay racks are required w a s therefore approximately 1 , 2 m . 2
a significant s a v i n g , particularly in v i e w of
therefore in the order of 4 0 , 0 0 0 . T o terminate A further advantage gained from the use of the fact that the 4 0 , 0 0 0 terminations w e r e
this amount by conventional terminals, each these connection arrangements w a s the very nearly duplicated at the mimic a n d data
3 m m thick, w o u l d have meant that the total greatly reduced termination time, i.e. if 1 0 logger.
termination area w o u l d have been prohibitive. minutes are a l l o w e d per connection for T h e use of 5 0 core cables, w h e r e possible,
For this reason high density aircraft type conventional s c r e w type terminals, 4 0 , 0 0 0 obviously offered major savings in terms of
plugs and s o c k e t s w e r e employed for these terminals w o u l d require 6,666 hours. service space required and cable installation
37T time.
Conventional armoured cables w e r e e m -
ployed in the open areas of plant w h e r e the
probability of damage exists.
M o t o r control centre (Fig. 37)
Motor control centres w e r e designed and
manufactured in s u c h a manner as to facilitate
expedient component c h a n g e . To this e n d the
smaller motors ( u p to 3 7 k W ) being in the
majority, and subject to a greater number of
operations, w e r e equipped with completely
w i t h d r a w a b l e starters. With this facility it is
possible to c h a n g e the complete starter
module in less than t w o minutes.
Interfacing the motor control centres to the
relay racks w a s a c h i e v e d by the use of
encapsulated pluggable 4 8 volt D C relays
w h i c h s w i t c h the 1 1 0 volt A C via interposing
relays, 1 1 0 volt A C being the operating coil
voltage of the 5 5 0 volt A C motor starter
circuits.
Advantage w a s taken of the large quantities
of starters involved to m a s s - p r o d u c e from
jigs all metalwork, bus-bars and associated
support components.
Transformers
A load analysis on the basis of 0 . 5 5 a m p per
k W indicated that it w a s necessary that the
lines each required 1 . 6 M V A transformers.
However, this a l l o w e d a negligible amount

I for future g r o w t h . On this basis it w a s therefore


decided that 2 M V A units should be installed. 1 3
Credits
F i g . 38
Client:
Treatment plant
transformer yard
as S h a b a n i and M a s h a b a M i n e s ( P r i v a t e ) L t d .
are the o w n e r s and operators of S h a b a n i
Mine. A f r i c a n Associated M i n e s (Private)
Ltd, are Secretaries and Consultants to
S h a b a n i and M a s h a b a Mines ( P r i v a t e ) Ltd.
Project management:
M.G.Webber,

if
T e c h n i c a l director
Design leader:
H . J . C Shone,
M e c h a n i c a l engineering consultant

Electrical design:
J . M. Pattison,
Electrical engineering consultant
Mechanical and electrical installations:
M. L e w i s ,
F i g . 39 Chief construction engineer
Typical arrangement
Commissioning:
of connections
J . Scholz,
to 2 M V A transformers
Chief construction engineer
(HV&LV)
Consulting civil, electrical and structura
engineers:
Ove Arup & Partners
Project partners:
R. A . Heydenrych
E.S.Walker
Project structural engineer:
1
M. B . Noyce *
Project electrical engineer:
H. P. G i l l '
Project civil engineer:
J . P. C a s s o n "
Project co-ordinator:
A. R. Allester
Senior resident engineer:
T. E. H. F a w c e t t "
"Authors of this J o u r n a l assisted by J . E.

3
F i g . 40 Goddard and R. M. L a m b .
31 panel 11 kV
main switchboard Consultants to Ove Arup B Partners
Quantity surveyors:
J . M. C o o m ( P a r t n e r ) ,

1
J.Thrasher (Partner),
Walter S i m p s o n , C o o m and Morant
Architect:

ILT.
M. N. Clinton ( P a r t n e r ) ,
Clinton & E v a n s

Main contractors for civil and


structural works:
Grinaker Construction Africa ( P t y . ) Ltd.
General manager, construction:
T. N. v a n der Walt

Construction co-ordinator:
L. A . G l u c k m a n
Project site manager:
In the interests of interchangeability and the T h e 4 > 4 M V A banks are automatically H. de Bruyne
effective utilization of spares, these units were s w i t c h e d by reactive power relays. T h i s is Site manager, construction:
used throughout w i t h the exception of the necessary, particularly as the plant may be J . Armstrong
larger ( 3 M V A ) 1 1 , 0 0 0 / 3 , 3 0 0 volt units run in sections, w h i c h w o u l d lead to over Site agent, construction:
needed to operate the main fans and m i s c e l - correction and subsequent over voltage, in R.Allen
laneous other units for lighting and services the event of too much reactive power being
( F i g s . 38 and 3 9 ) . inserted ( F i g . 4 0 ) . Electrical contractor for treatment plant
power installation:
Lighting small power
Conclusion Electroreps ( P v t . ) Ltd.
T h e lighting system allowed for a basic level
T h e s u c c e s s of any project depends mainly Director:
of 3 0 0 lux, supplemented in areas considered
on teamwork. A A M leadership and design M. Guard
necessary. All fluorescent lights were fitted
skill formed the backbone of the entire Site agent:
with quick release gear trays and 5 amp plug
project team and the completed S h a b a n i Mill E. Gustafson
tops to a c h i e v e connection. T h i s a l l o w s
is a great credit to their organization.
removal/replacement by unskilled labour.
T h i s project is one of the biggest structures in Electrical contractors for treatment plant
Reactive power installation lighting and small power, plus complete
Z i m b a b w e and it s h o w s that even large
The Z i m b a b w e scale of tariffs for the supply of projects like this c a n be s u c c e s s f u l l y c o m - installation for feed system:
electricity is based upon an annual charge for pleted w i t h the minimum expenditure of H.W.S. Contractors ( P v t . ) L t d .
the m a x i m u m demand value reached at any foreign currency providing the right use is Manager:
instant during the financial year. made of local resources. There is no doubt J . Barker
With anticipated values in e x c e s s of 4 2 M V A , that, like the King Mill before it, it will benefit Site agent:
uncorrected and calculated m a x i m u m of not only the people in the area but also the P. B i n n s
+ 3 6 M W , the capital costs of the reactive entire country. For all those involved in the
power installation ( 1 6 M V A ) will be offset design the experience w a s challenging, Photos: Bob Davey,
1 4 in the first t w o years of operation. interesting and above all tremendous fun. (except w h e r e otherwise credited.)
ID
to
CI

You might also like