You are on page 1of 86

Guide to

CONCRETE
OVERLAYS
Sustainable Solutions for Resurfacing
and Rehabilitating Existing Pavements

Second Edition September 2008


On the Cover

Urban concrete overlay construction with Rural concrete overlay construction Interstate highway concrete overlay
limited paving clearance (Photo courtesy of with widening (Photo courtesy of Gordon construction (Photo courtesy of Dan DeGraaf,
Kevin Klein, Gomaco) Smith, P.E., Iowa Concrete Paving Association) P.E., Michigan Concrete Paving Association)

Urban concrete overlay construction (Photo Completed concrete overlay of rural roadway Completed concrete overlay on interstate
courtesy of Kerry Sutton, P.E., Michigan with paved shoulders (Photo courtesy of highway (Photo courtesy of Matt Zeller, P.E.,
Concrete Paving Association) Gordon Smith, P.E., Iowa Concrete Paving Concrete Paving Association of Minnesota)
Association)
Guide to Concrete Overlays
Sustainable Solutions for Resurfacing
and Rehabilitating Existing Pavements

Second Edition, September 2008

Author Technical Advisory Committee


Dale Harrington, P.E., Principal Senior Engineer, Andy Bennett, Michigan Department of Transportation
Snyder and Associates, Inc.
Jim Cable, P.E., Iowa State University (retired)

Contributing Technical Authors Dan DeGraaf, P.E., Michigan Concrete Paving Association
Dan DeGraaf, P.E., Michigan Concrete Paving Association Jim Duit, Duit Construction Co., Inc., Oklahoma
Robert Otto Rasmussen, Ph.D., P.E., Transtec Group Jim Grove, P.E., Senior Project Engineer, FHWA
Jerod Gross, P.E., Snyder and Associates, Inc. Todd Hanson, P.E., Iowa Department of Transportation
Jim Grove, P.E., CP Tech Center Kevin Maillard, P.E., OHM Advisors, Michigan
Jim Mack, P.E., Cement Council of Texas Randell Riley, P.E., Illinois Chapter ACPA
Randell Riley, P.E., Illinois Chapter ACPA Robert Rodden, ACPA National
Je Roesler, Ph.D., P.E., University of Illinois at Urbana-Champaign Matt Ross, P.E., Missouri/Kansas Chapter ACPA
Matt Ross, P.E., Missouri/Kansas Chapter ACPA Jim Shea, New York State Chapter ACPA
Kurt Smith, P.E., AP Tech Gordon Smith, P.E., Iowa Concrete Paving Association
Leif Wathne, P.E., American Concrete Pavement Association Shannon Sweitzer, P.E., North Carolina Turnpike Authority
Sam Tyson, P.E., Federal Highway Association
Editorial Staff
Marcia Brink, Managing Editor Je Uhlmeyer, P.E., Washington State Department of Transportation

Oksana Gieseman, Copyeditor Leif Wathne, P.E., American Concrete Pavement Association

Mina Shin, Graphic Designer and Illustrator Matt Zeller, P.E., Concrete Paving Association of Minnesota

Alison Weidemann, Graphic Designer


Bill Beach, Illustrator
concrete pavement professionals, public and private, who contributed to
About This Guide the development of this guide, both the original version in 2007 and this
expanded edition.
This Guide to Concrete Overlays (second edition) is a product of the
National Concrete Pavement Technology Center (CP Tech Center) at While the authors generated the overall content, it was the techni-
Iowa State University, with partial funding from the American Concrete cal advisory committees reviews of drafts, thoughtful discussions,
Pavement Association. It was developed to ll a knowledge gap iden- and suggestions for revisions and renements that make this guide a
tied in the National Concrete Pavement Road Map, a coordinated, comprehensive resource for practitioners. The members broad exper-
long-term research plan for improving concrete pavements. In September tise regarding the use of concrete overlays as pavement resurfacing and
2007, the Road Maps national executive committee designated overlays rehabilitation solutions is reected in every page. CP Tech Center sta
as a priority topic for research and technology transfer. appreciate the committees invaluable assistance. In particular, we thank
Dan DeGraaf and Randy Riley, representing the Michigan and Illinois
In addition to serving a general industry need, this publication will be concrete pavement industry associations, respectively, for their tireless
a major resource for a eld application program, led by the National attention to this project.
Concrete Pavement Technology Center. This program is intended to
advance overlays eective use by answering pavement owners ques-
tions and increasing their knowledge about and condence in concrete
overlays. Abbreviations
With the advice and support of national expert teams, six regionally AASHTO American Association of State Highway and Transportation
diverse states will design, construct, and demonstrate dierent types Ocials
of concrete overlay solutions. Through this process, the six states will
ACI American Concrete Institute
become regional hubs of concrete overlay expertise. They will share their
knowledge and experience with surrounding states by hosting visits to ACPA American Concrete Pavement Association
the demonstration sites and/or making presentations at various events. ASR alkali-silica reactivity/reaction/reactive
Innovations learned from the eld applications will be incorporated ASTM American Society for Testing and Materials
into annual updates of this guide.
CRCP continuously reinforced concrete pavement
CTE coecient of thermal expansion
FHWA Federal Highway Administration
FWD falling weight deectometer
IRI International Roughness Index
JPCP jointed plain concrete pavement
M-E PDG Mechanistic-Empirical Pavement Design Guide
MRD material-related distress
MUTCD Manual on Uniform Trac Control Devices
NCHRP National Cooperative Highway Research Program
Acknowledgments PCA Portland Cement Association
PCC portland cement concrete
This document is a testimony to the value of agency-industry-university
SCM supplementary cementitious material
partnerships in research and technology transfer activities. The National
Concrete Pavement Technology Center at Iowa State University is TRB Transportation Research Board
sincerely grateful to the knowledgeable, experienced, and dedicated TCP trac control plan

For More Information Disclaimers


Marcia Brink, Managing Editor Neither Iowa State University nor this documents authors,
National CP Tech Center editors, designers, illustrators, distributors, or technical
Iowa State University advisors make any representations or warranties, expressed or
2711 S. Loop Drive, Suite 4700 implied, as to the accuracy of information herein and disclaim liability
Ames, IA 50010-8664 for any inaccuracies.
515-294-8103, mbrink@iastate.edu, www.cptechcenter.org/ Iowa State University does not discriminate on the basis of race, color,
age, religion, national origin, sexual orientation, gender identity, sex,
For technical assistance regarding concrete overlays, contact your
marital status, disability, or status as a U.S. veteran. Inquiries can be
state or regional paving association, American Concrete Pavement
directed to the Director of Equal Opportunity and Diversity, Iowa State
Association (ACPA) chapter (find contact information with the My
University, 3680 Beardshear Hall, 515-294-7612.
Locator tool at www.pavement.com), ACPA National Office, or the
National CP Tech Center.
CP Tech Center Mission
For Additional Copies The mission of the National Concrete Pavement
The American Concrete Pavement Association is distributing this Technology Center is to unite key transportation
guide. For additional copies, contact your state paving association/ stakeholders around the goal of advancing
ACPA chapter (find contact information with the My Locator tool at concrete pavement technology through research,
www.pavement.com); ask for ACPA publication no. TB021.02P. technology transfer, and technology implementation.
Contents
List of Figures ....................................................................................vii Performance ................................................................................16
List of Tables ....................................................................................viii Overlay Process ............................................................................16
Step 1. Pavement Evaluation ...............................................16
Introduction ....................................................................................... 1
Step 2. Overlay Design ........................................................16
Versatile Solutions .............................................................................. 2
Step 3. Preoverlay Work ......................................................17
Benets of Concrete Overlays ........................................................2
Step 4. Construction ...........................................................17
Two Concrete Overlay Systems ......................................................2
Future Repairs .............................................................................17
Bonded Overlay Systems ........................................................2
Unbonded Overlay Systems (2-page overviews)
Unbonded Overlay Systems ...................................................2
Unbonded Concrete Overlays of Concrete Pavements ...................... 18
Maintenance and Rehabilitation Solutions ....................................3
Uses .............................................................................................18
Pavement Preservation ...........................................................3
Performance ................................................................................18
Routine Maintenance .....................................................3
Overlay Process ............................................................................18
Preventive Maintenance .................................................3
Step 1. Pavement Evaluation ...............................................18
Minor Rehabilitation .....................................................3
Step 2. Overlay Design ........................................................18
Major Rehabilitation .............................................................3
Step 3. Preoverlay Work ......................................................19
Uses and Key Elements of Each Concrete Overlay Type ..................... 4
Step 4. Construction ...........................................................19
Bonded Concrete Overlay System ..................................................4
Future Repairs ..............................................................................19
Unbonded Concrete Overlay System .............................................5
Unbonded Concrete Overlays of Asphalt Pavements ........................ 20
Evaluating Existing Pavement Conditions .......................................... 6
Uses .............................................................................................20
Historical Data and Future Projections ..........................................6
Performance ................................................................................20
Visual Examination ........................................................................6
Overlay Process ............................................................................20
Pavement Coring ...........................................................................6
Step 1. Pavement Evaluation ...............................................20
Optional Analyses ..........................................................................6
Step 2. Overlay Design ........................................................20
Material-Related Distress .......................................................7
Step 3. Preoverlay Work ......................................................21
Distress Surveys .....................................................................7
Step 4. Construction ...........................................................21
Drainage Surveys ...................................................................7
Future Repairs .............................................................................21
Roughness and Surface Friction Tests .....................................7
Unbonded Concrete Overlays of Composite Pavements ................... 22
Elevations and Grade Restrictions ..........................................7
Uses .............................................................................................22
Condition Assessment Prole ........................................................7
Performance ................................................................................22
Condition Evaluation Report ........................................................7
Overlay Process ............................................................................22
Summary of Pavement Evaluation Process .....................................9
Step 1. Pavement Evaluation ...............................................22
Selecting Appropriate Concrete Overlay Solution ............................. 10
Step 2. Overlay Design ........................................................22
Bonded Overlay Systems (2-page overviews) Step 3. Preoverlay Work ......................................................23
Bonded Concrete Overlays of Concrete Pavements .......................... 12 Step 4. Construction ...........................................................23
Uses .............................................................................................12 Future Repairs .............................................................................23
Performance ................................................................................12
Design of Concrete Overlays ............................................................ 24
Overlay Process ............................................................................12
Design Objectives ........................................................................24
Step 1. Pavement Evaluation ................................................12
Bonded Overlay Systems ......................................................24
Step 2. Overlay Design ........................................................12
Unbonded Overlay Systems .................................................24
Step 3. Preoverlay Work .......................................................13
Overlay System Design Inputs .....................................................24
Step 4. Construction ............................................................13
Existing Pavement Characterization .....................................24
Future Repairs .............................................................................13
Surface Considerations .................................................24
Bonded Concrete Overlays of Asphalt Pavements ............................. 14 Structural Considerations .............................................24
Uses .............................................................................................14 Trac Characterization ........................................................25
Performance ................................................................................14 Material Properties ...............................................................25
Overlay Process ............................................................................14 Climatic Factors ...................................................................25
Step 1. Pavement Evaluation ................................................14 Constraints ..........................................................................25
Step 2. Overlay Design ........................................................14 Distress Mode ......................................................................26
Step 3. Preoverlay Work .......................................................15 Design Selection ..........................................................................26
Step 4. Construction ............................................................15 Design of Bonded Overlay Systems ......................................28
Future Repairs .............................................................................15 Bonded Overlays of Concrete Pavements .....................28
Bonded Concrete Overlays of Composite Pavements ....................... 16 Bonded Overlays of Asphalt Pavements ........................28
Uses .............................................................................................16 Bonded Overlays of Composite Pavements ..................29
Design of Unbonded Overlay Systems .................................29 Early Opening of Overlays to Trac ............................................54
Unbonded Overlays of Concrete Pavements .................29 Quality of Bond for Bonded Overlays of Existing
Unbonded Overlays of Asphalt Pavements ...................30 Concrete Surfaces ................................................................54
Unbonded Overlays of Composite Pavements ..............30 Strength Conversions for Opening to Trac ........................56
Widening and Lane Addition Design ..........................................30 Conversions .........................................................................56
Miscellaneous Design Details ........................................................... 31 Strength Criteria for Opening Bonded Systems to Trac .....56
Curbs and Gutters .......................................................................31 Existing Concrete Pavement ........................................56
Manhole .....................................................................................31 Existing Asphalt Pavements .........................................56
Transitions ...................................................................................31 Strength Criteria for Opening Unbonded Systems
to Trac ...............................................................................56
Mill and Fill Transitions for Bonded Concrete Overlays .......31
Minimizing Early Loading Fatigue Damage .........................56
New Transitions for Bonded Concrete Overlays ...................32
New Transitions for Unbonded Concrete Overlays ..............32 Considerations for Developing Project and Supplemental
Specications ................................................................................... 64
Transition Details for Bonded Concrete Overlays ................33
General ........................................................................................64
Transition Details for Unbonded Concrete Overlays ............33
Contractor Submittal Considerations ...................................64
Lane Addition .............................................................................33
Scheduling and Conicts .....................................................64
Concrete Overlay Materials .............................................................. 34
Limitations of Operations ....................................................64
Type of Mixture ...........................................................................34
Method of Measurement and Basis of Payment ....................64
Conventional Mixtures ........................................................34
Materials ......................................................................................64
Expedited Mixtures ..............................................................34
Separation Layer for Unbonded Overlays .............................64
Concrete Materials ......................................................................34
Construction ...............................................................................64
Cementitious Materials ........................................................34
Preoverlay Repairs ................................................................64
Aggregates ............................................................................34
Bonded Overlays Over Concrete ..................................65
Water-Cementitious Materials Ratio ....................................34
Bonded Overlays Over Asphalt ....................................65
Admixtures ..........................................................................34
Unbonded Overlays Over Concrete .............................65
Fiber-Reinforced Concrete ...........................................................35
Unbonded Overlays Over Asphalt ................................65
Synthetic Fibers (Macro and Micro) .....................................35
Surface Cleaning ..................................................................65
Steel Fibers ...........................................................................35
Bonded Concrete Overlays Over Concrete
Blended Fibers .....................................................................35 or Asphalt ....................................................................65
Separation Layer Materials ...........................................................35 Unbonded Concrete Overlays Over Concrete
Incidental Materials .....................................................................36 or Asphalt ....................................................................65
Managing Concrete Overlay Work Zones under Trac .................... 37 Concrete Placement .............................................................65
Objectives of Work Zone Management .......................................37 Grade Control ..............................................................65
Safety ...................................................................................37 Overlay Placement .......................................................65
Trac Flow ..........................................................................38 Liquid Membrane Curing ....................................................65
Cost-Eectiveness ................................................................38 Joint Sawing ........................................................................65
Pavement Performance .........................................................38 General ........................................................................65
Work Zone Space Considerations ................................................38 Joint Width ..................................................................66
Paving Equipment Clearances .....................................................38 Joint Seal ......................................................................66
Reducing Clearance with Paver Modications .....................38 Timing .........................................................................66
Reducing Clearance with Alternative Control Options ........39 Bonded Overlays Over Concrete ..................................66
Other Clearances .........................................................................39 Bonded Overlays Over Asphalt ....................................66
Construction Trac Control .......................................................39 Unbonded Overlays .....................................................66
Concrete Overlay Staging ............................................................39 Repairs of Concrete Overlays ............................................................ 67
Two-Lane Highway under Trac .........................................39 Repairs of Bonded or Thin Unbonded Concrete Overlays ...........67
Fillets ...........................................................................40 Repairs of Full-Depth Unbonded Concrete Overlays ...................68
Continuous Production ...............................................40 Appendix A. Evaluation and Selection Tables ................................... 69
Two-Lane Highway Expanded to Three Lanes
Appendix B. Sample Geotextile Specications (Germany) ................ 70
Under Trac ........................................................................40
Four-Lane Divided Highway without Crossovers and Appendix C. Innovative Methods for Accelerated Concrete
under Trac ........................................................................41 Overlay Construction .................................................. 71
Key Points for Concrete Overlay Construction.................................. 52 Sources ..............................................................................................74
References ...................................................................................74
Accelerated Construction .................................................................. 54
Bibliography ................................................................................75
Approach and Considerations ......................................................54

vi Guide to Concrete Overlays


List of Figures
Figure 1. All concrete overlay systems can be categorized as Figure 29. Bonded overlay of concrete pavement with
either bonded or unbonded ................................................1 widening unit ..................................................................33
Figure 2. Typical bonded and unbonded concrete solutions for Figure 30. Bonded overlay of asphalt or composite pavement
maintenance, rehabilitation, and reconstruction needs .......3 with widening unit ...........................................................33
Figure 3. Bonded overlay on concrete pavement ...............................4 Figure 31. Unbonded overlay of concrete, asphalt, or composite
Figure 4. Bonded overlay on asphalt pavement .................................4 pavement with widening unit ...........................................33

Figure 5. Bonded overlay on composite pavement ............................4 Figure 32. Bonded or unbonded overlay of asphalt or composite
pavement (previously widened with asphalt or concrete;
Figure 6. Unbonded overlay on concrete pavement ...........................5 to be widened again with new concrete overlay) ...............33
Figure 7. Unbonded overlay on asphalt pavement .............................5 Figure 33. Unbonded overlay of concrete, asphalt, or composite
Figure 8. Unbonded overlay on composite pavement ........................5 pavement with full concrete lane addition ........................33

Figure 9. Examples of existing pavement conditions .........................8 Figure 34. Close-up of geotextile fabric .............................................36

Figure 10. Flowchart process for selecting concrete overlay type ........10 Figure 35. Roll of geotextile fabric being placed prior to overlay .......36

Figure 11. Bonded concrete overlay of good condition concrete Figure 36. Managing work zones eectively involves balancing
pavement with surface distresses .......................................12 several priorities ...............................................................37

Figure 12. Width of transverse joint in bonded concrete overlay on Figure 37. Typical clearance on a concrete overlay project .................38
concrete pavement should be equal to or greater than Figure 38. A three-track, zero-clearance paver placing concrete
width of crack in existing pavement .................................13 along a median barrier .....................................................38
Figure 13. Bonded concrete overlay of fair or better condition Figure 39. A typical, four-track paver modied to three tracks,
asphalt pavement with surface distresses ...........................14 providing zero clearance in a curb-and-gutter
Figure 14. Bonded concrete overlay of fair or better condition situation in Oklahoma . ....................................................38
composite pavement with asphalt surface diistresses .........16 Figure 40. Controlling paving prole using a moveable stringline
Figure 15. Unbonded concrete overlay of poor condition on the adjacent lane .........................................................39
concrete pavement ...........................................................18 Figure 41. Controlling paving prole using a paver ski on
Figure 16. Unbonded concrete overlay of poor-to-deteriorated the adjacent lane ..............................................................39
condition asphalt pavement .............................................20 Figure 42. Vertical trac control panels may be used to mark
Figure 17. Consider asphalt rut depth when determining pavement edge dropo .....................................................40
saw-cut depth ...................................................................21 Figure 43. Centerline llets for overlays 2 in. (50 mm)
Figure 18. Unbonded concrete overlay of poor-to-deteriorated or greater ..........................................................................40
composite pavement ........................................................22 Figure 44. Overlay of two-lane roadway with paved
Figure 19. Design factors that aect one another ..............................24 shoulders (conventional paver) .........................................42

Figure 20. Bonded concrete overlay in urban areas where Figure 45. Overlay of two-lane roadway with granular
the existing curbs can remain in place ..............................31 shoulders (conventional paver) .........................................44

Figure 21. Concrete overlay with standard manhole ..........................31 Figure 46. Overlay of two-lane roadway with minimum
granular shoulders (zero-clearance paver) .........................46
Figure 22. Mill and ll transition for concrete overlay
of concrete pavement ........................................................31 Figure 47. Overlay of two-lane pavement widening to three lanes
with paved shoulder (conventional paver) ........................48
Figure 23. Mill and ll transition for concrete overlay of
asphalt or composite pavement .........................................31 Figure 48. Overlay of four-lane roadway with paved shoulders
(conventional paver) ........................................................50
Figure 24. New transition tapers used to meet bridge approach
slabs or maintain clearance under bridges with Figure 49. Compare the surface texture of the non-shotblasted
bonded overlay of concrete pavement ...............................32 area (upper left half of image) to the roughened
surface texture on the shotblasted section of
Figure 25. New transition tapers used to meet bridge approach pavement (under the pen) ................................................55
slabs or maintain clearance under bridges with
bonded overlay of asphalt pavement .................................32 Figure 50. Shear test .........................................................................55

Figure 26. New transition tapers used to meet bridge approach Figure 51. Pull-o test ......................................................................55
slabs or maintain clearance under bridges with Figure 52. Removing overlay panels ..................................................67
unbonded overlay of concrete pavement ..........................32
Figure 53. Finish and cure of concrete overlay repair .........................67
Figure 27. New transition tapers used to meet bridge approach
slabs or maintain clearance under bridges with Figure 54. Typical concrete pavement milling operation ...................67
unbonded overlay of asphalt pavement .............................32 Figure 55. Typical concrete pavement milling operation ...................67
Figure 28. Joint detail in concrete overlay of existing Figure 56. Typical concrete pavement millings from milling
concrete pavement ...........................................................32 operation .........................................................................68
Guide to Concrete Overlays vii
List of Tables
Table 1. Possible preoverlay repairs on existing concrete Table 8. Summary of design considerations for dierent
pavement in preparation for bonded overlay ....................13 types of concrete overlay systems ......................................26
Table 2. Possible preoverlay repairs on existing asphalt Table 9. Concrete overlay work zone management considerations ..37
pavement in preparation for bonded overlay ....................15
Table 10. Concrete paving construction practices for overlays .........52
Table 3. Possible preoverlay repairs on existing composite
Table 11. Accelerated construction under trac for concrete
pavement in preparation for bonded overlay ....................17
overlays ............................................................................57
Table 4. Typical transverse joint spacing ........................................19
Table 12. Distress types and severity levels recommended for
Table 5. Possible preoverlay repairs on existing concrete assessing concrete pavement structural adequacy ..............69
pavement in preparation for unbonded overlay ................19
Table 13. Distress types and levels recommended for assessing
Table 6. Possible preoverlay repairs on existing asphalt asphalt pavement structural adequacy ..............................69
pavement in preparation for unbonded overlay ................21
Table 14. Applicability, pros, and cons of various accelerated
Table 7. Possible preoverlay repairs on existing composite construction methods ......................................................71
pavement in preparation for unbonded overlay ................23

viii Guide to Concrete Overlays


Introduction
The need has never been greater for engi- practices by preserving pavement service for Evaluating existing pavements to determine
neered strategies to preserve and maintain the several decades beyond the original design life. if they are good candidates for concrete
nations pavements. With shrinking budgets, overlays
The goal of the Guide to Concrete Overlays is
ever-increasing trac volumes and loads, and
to answer pavement owners questions and Selecting the appropriate overlay system for
the critical emerging focus on infrastructure
increase their knowledge about engineered specic pavement conditions
sustainability, highway agencies are being asked
concrete overlay maintenance and rehabilita-
to do more with less in managing their pave- Managing concrete overlay construction
tion strategies. With this information, owners
ment networks. work zones under trac
can condently include concrete overlays in
Agencies need proactive, sustainable pavement their toolbox of pavement solutions and make Accelerating construction of concrete over-
maintenance and rehabilitation strategies that more informed decisions about using concrete lays when appropriate
last longer at reasonable cost. overlays for specic pavement conditions.
This guide is not a complete step-by-step man-
In many situations, concrete overlays repre- The rst edition of this guide (2007) described ual, nor does it provide prescriptive formulae
sent such strategies. They oer cost-eective, concrete overlay types, applications, and gen- or specications for designing and construct-
versatile, short- and long-term solutions for the eral issues related to design and construction. ing concrete overlays. As the title suggests,
full range of concrete, asphalt, and composite This second, expanded edition enhances the this booklet provides expert guidance that can
pavement needs (gure 1). In addition, they original material and adds detailed guidelines supplement practitioners own professional
contribute to more sustainable construction for several new topics: experience and judgment.

Bonded Overlay Systems Unbonded Overlay Systems


(Resurfacing/Minor Rehabilitation) (Minor/Major Rehabilitation)
In general, bonded overlays are used to add structural capacity In general, unbonded overlays are used to rehabilitate pave-
and/or eliminate surface distress when the existing pavement ments with some structural deterioration.
is in good structural condition. They are basically new pavements constructed on an
Bonding is essential, so thorough surface preparation is existing, stable platform (the existing pavement).
necessary before resurfacing.

Bonded Concrete Overlays of Concrete Pavements Unbonded Concrete Overlays of Concrete Pavements
previously called bonded overlays previously called unbonded overlays

Bonded Concrete Overlays of Asphalt Pavements Unbonded Concrete Overlays of Asphalt Pavements
previously called ultra-thin whitetopping previously called conventional whitetopping

Bonded Concrete Overlays of Composite Pavements Unbonded Concrete Overlays of Composite Pavements

Figure 1. All concrete overlay systems can be categorized as either bonded or unbonded

Guide to Concrete Overlays 1


Versatile Solutions
Many concrete overlays have been in service 3. Concrete overlays are easy to repair. solution for nearly any pavement maintenance,
for decades, extending the life of the original Repairing concrete overlays, especially thin resurfacing, or rehabilitation need.
pavement structure for 30 years or more. overlays, is usually much easier than repair-
Because concrete distributes trac loads over ing a section of conventional pavement. If a Bonded Overlay Systems
a wide area, the underlying pavement does panel is distressed but the ride quality is not The purpose of bonded concrete overlays is to
not experience highly concentrated stresses. As compromised, the panel may be left in place. add structural capacity to and eliminate surface
long as the original pavement remains stable If a ride quality problem develops, the panel distresses on existing pavements that are in
and uniform, a concrete overlay can be placed, or an isolated area should be replaced before good to fair structural condition. Bonded over-
replaced, or recycled as needed for maintenance any pieces of concrete come loose from the lays generally provide resurfacing solutions for
and/or rehabilitation cycles. overlay. routine or preventive pavement maintenance or
for minor rehabilitation (gure 2).
In this way, concrete overlay pavement systems Thin overlays constructed without reinforce-
can be sustainable for 100 years or longer. ment can be easily and economically milled Bonded concrete overlays are relatively thin (2
Rather than removing and reconstructing the out and replaced with a new concrete sur- to 5 in. [50 to 125 mm]). Bonded together, the
original pavement, the owner maintains and face. Utility repair locations can be restored overlay and the existing pavement perform as
builds equity in it, realizing a return on its to original surface elevation and ride quality one monolithic pavement.
original investment as long as the original pave- with ease.
Bonding between the overlay and the existing
ment remains part of the system.
4. Concrete overlays are a durable reha- pavement is essential. The bond ensures that
Benefits of Concrete bilitation tool as well as a cost-eective the overlay and existing pavement perform
maintenance tool. Because of the wide as one structure, with the original pavement
Overlays range of overlay thicknesses that can be used, continuing to carry a signicant portion of the
Despite hundreds of successful concrete overlay combined with the minimal preoverlay work load. All bonded overlay projects, therefore, are
projects, some public agencies and contractors required, concrete overlays provide cost- carefully designed and constructed to achieve
hesitate to construct concrete overlays. This eective solutions for almost any pavement and maintain a bond between the overlay and
may be based on a misconception that concrete type and condition, desired service life, and the existing pavement.
overlays are expensive, dicult to build, or anticipated trac loading.
Most bonded overlay projects are more chal-
appropriate in only a few situations. However, 5. Concrete overlays can serve, in and of lenging than unbonded overlay projects.
agencies that regularly construct concrete over- themselves, as complete preventive main- Therefore, it is important to pay close attention
lays describe several benets. tenance or rehabilitation solutions, or to details in this guide.
1. Concrete overlays consistently provide they can be used in conjunction with spot
repairs of isolated distresses. Factors that aect the performance of the
cost-eective solutions. Dollar for dollar, resurfaced pavement include the strength and
they are one of the most eective long-term 6. Concrete overlays are an eective means integrity of the underlying pavement, the
maintenance and rehabilitation options for to enhance pavement sustainability by eectiveness of the bond, the ability of the
existing pavements. improving surface reectance (albedo), two layers to move monolithically to maintain
2. Concrete overlays can be constructed increasing structural longevity, and the bond, and overlay jointing and curing
quickly and conveniently. enhancing surface prole stability. techniques.

The existing pavement does not need to For these and other reasons, concrete overlays The key to maintaining desired performance
be removed. In fact, it is factored into the are cost-eective, sustainable solutions. They is to ensure the two structuresthe existing
overlay design to continue to help carry provide societal benets in the form of reliable pavement and the overlaymove as one struc-
some of the trac load, either as part of a load-carrying capacity and fewer and shorter ture. Therefore, it is important to understand
new monolithic pavement (bonded over- disruptions to trac for pavement resurfacing movement-related properties, such as expan-
lay) or as a base to the overlay (unbonded and rehabilitation. sion and contraction properties, of both the
overlay). existing pavement and the overlay. In a bonded
Two Concrete Overlay concrete overlay on a concrete pavement, for
Few or no preoverlay repairs are neces-
example, the CTE of aggregate in the overlay
sary or even desirable in most cases. If Systems should be similar to or less than that of the
an agency believes extensive preoverlay
Sometimes, various terms for concrete overlays existing concrete pavement.
repairs are required for a specic project,
it should probably rethink its choice of (e.g., ultrathin whitetopping and conven-
overlay design solutions. tional whitetopping) have led to confusion Unbonded Overlay Systems
because they were not used consistently. As The purpose of unbonded overlays is to restore
Concrete overlays are placed using nor- with all developing technologies, simple, structural capacity to existing pavements that
mal concrete pavement construction consistent terminology is essential. This guide are moderately to signicantly deteriorated.
practices. Attention should be paid to uses straightforward terms that categorize all Unbonded overlays are minor or major reha-
overlay-specic details in this guide. concrete overlays in one of two basic systems: bilitation strategies (gure 2).
Many concrete overlays can be opened bonded systems and unbonded systems.
Unbonded concrete overlays are typically
to trac within a day of placement. Both bonded and unbonded concrete overlays thicker than bonded (4 to 11 in. [100 to
Nondestructive strength indicators, like can be placed on existing concrete pavements, 275 mm]) on concrete and composite pave-
maturity testing, enable engineers to take asphalt pavements, or composite pavements ments; typically 6 in. (150 mm) minimum on
advantage of this benet. (original concrete pavements that have been asphalt pavements less than 6 in. (150 mm)
Accelerated construction practices can be previously resurfaced with asphalt). Thus, there thick after milling. The overlay performs as a
used throughout the normal construc- are a total of six concrete overlay types from new pavement, and the existing pavement pro-
tion season as described in this guide. which owner-agencies can select the proper vides a stable base.
2 Guide to Concrete Overlays
The term unbonded simply means that bond- or reconstruction, highway agencies are increas- programs. Thin unbonded concrete overlays
ing between the overlay and the underlying ingly relying on a proactive approach called also provide minor rehabilitation solutions and
pavement is not needed to achieve the desired pavement preservation. A pavement preserva- can be placed eciently and opened to trac
performance. tion approach involves investing in a carefully very quickly.
planned system of regular routine maintenance,
When the underlying pavement is asphalt or
preventive maintenance, and minor rehabilita- Major Rehabilitation
composite, partial or full bonding between the
tion activities. For pavements needing structural improve-
concrete overlay and the underlying asphalt
layer should not cause a problem. In fact, such ment, rehabilitation is the approach typically
Routine Maintenance
bonding generally adds some structural car- used. Rehabilitation involves structural
Routine maintenance activities, such as joint enhancements that extend the service life of
rying capacity to the system. So, unbonded
resealing and diamond grinding, are important an existing pavement and/or improve its load-
concrete overlays on existing asphalt or com-
preservation activities that do not involve a new carrying capability. In rehabilitation, a new
posite pavements are not vigorously designed
pavement surface. surface layer of 4 in. (100 mm) or greater is
and constructed to prevent bonding between
usually placed.
the layers. Preventive Maintenance
Preventive maintenance is a major component Unbonded concrete overlays are an excellent
However, when the underlying pavement
of pavement preservation. Basically, it consists and well-demonstrated major rehabilitation
is concrete, unbonded concrete overlays are
of extending the service life of structurally solution for pavement in need of signicant
carefully designed and constructed to prevent
sound pavements by applying cost-eective structural improvement. They are highly
bonding between the two concrete layers. That
treatments to the surface or near the surface. reliable, with longer design lives than rehabili-
is because any bonding between the two con-
Some preventive maintenance treatments, such tation with asphalt.
crete layers may stress the overlay and result in
reective cracking. as joint resealing and diamond grinding, do To show the signicance of concrete overlays
not necessarily involve resurfacing. Bonded as a rehabilitation strategy, AASHTO (2007)
Maintenance and concrete overlays of approximately 4 in. (100 recently stated that thin unbonded concrete
mm) provide excellent preventive maintenance
Rehabilitation Solutions strategies for all types of pavements. On con-
overlays, 4 to 5 in. in depth [100 to 125 mm],
have proven to be a rehabilitation option for
Pavement management and pavement crete and composite pavements, 4 in. (100 composite (asphalt over concrete) pavements
preservation activities have become extremely mm) unbonded concrete overlays have also that exhibit signicant deterioration. When
important in managing and accounting for been used for maintenance purposes. properly designed and constructed, unbonded
investments in highway pavements. concrete overlays have been shown to increase
Many highway agencies are familiar with Minor Rehabilitation load-carrying capacity and extend pavement
asphalt maintenance and resurfacing options Minor rehabilitation is used when some life.
but are not equally knowledgeable about con- structural capacity needs to be restored to
a pavement but major rehabilitation is not Figure 2 represents a typical pavement condi-
crete resurfacing solutions and their benets.
required. tion curve over the life of a pavement. The
Yet the variety, exibility, and cost-eectiveness
maintenance, rehabilitation, and reconstruction
of concrete overlay options make them excel- One of the major advantages of concrete zones are noted where bonded and unbonded
lent solutions for a full spectrum of pavement overlays as maintenance solutions is that they overlays can be used to restore pavement to
maintenance and rehabilitation needs. increase the pavement structures structural original or better condition.
capacity, even if that is not the primary objec-
Pavement Preservation tive of the maintenance activity. Bonded On the following pages, gures 3 to 8 and the
To extend the life of existing pavements and concrete overlays provide minor rehabilitation accompanying dialogs provide brief overviews
delay any future need for major rehabilitation solutions as part of their pavement preservation of each of the six concrete overlay types.
Existing pavement condition

Bonded Bonded
Preventive on on Asphalt
maintenance Concrete or
Composite
before treatment

Minor Unbonded
on
rehabilitation Concrete
Unbonded
on Asphalt
Major or
rehabilitation Composite

Reconstruction

Time
Figure 2. Typical bonded and unbonded concrete solutions for maintenance, rehabilitation, and reconstruction needs
Guide to Concrete Overlays 3
Uses and Key Issues for Each Concrete Overlay Type
Bonded Concrete Overlay System
Typically 2 to 5 in. (50 to 125 mm) thick, depending on desired life (15 to 25+ years), anticipated traffic loading, and condition of underlying pavement
Overlay and existing concrete pavement act as one monolithic pavement (figures 3 to 5).
Bonded Concrete Overlays of Concrete Pavements
previously called bonded overlays Existing pavement condition Working cracks in the existing pavement
Good structural condition; some surface should be repaired (or the overlay should be
distress OK sawed over the crack) to prevent the crack
from reflecting through the overlay
Applications Existing joints must be in fair condition or
To eliminate surface defects such as repaired
extensive scaling or surface cracking or Thinner overlays may shorten sawing
to improve surface characteristics like window
friction, noise, and rideability
Transverse joints in the overlay must
To enhance structural capacity to be sawed full depth plus .50 in. (12 mm);
accommodate increase in traffic loads longitudinal joints must be at least T/2
To meet vertical clearances Joints in the overlay must align with those
To mill and inlay sections of existing pavement because the structure
must move monolithically
Keys to success
Width of transverse joints in the overlay must
Existing pavement surface must be
be equal to or greater than the underlying
prepared to enhance bonding to the overlay
crack width at the bottom of the existing
Overlays aggregate thermal properties transverse joint
Figure 3. Bonded overlay on concrete pavement
(CTE) must be similar to (or lower than)
Application of curing compound or other
existing pavements to minimize shear
curing methods must be timely and thorough,
stress in bond
especially at edges
Bonded Concrete Overlays of Asphalt Pavements
previously called ultra-thin whitetopping Existing pavement condition good bond; minimal spot repairs may be
Fair or better structural condition with required
surface distress Minimum 3 to 4 in. (75 to 100 mm) of asphalt
should remain after milling
Applications
Asphalt surface temperature must be
To eliminate surface defects such as maintained below 120F (49C) when placing
rutting and shoving or to improve surface overlay
characteristics like friction, noise, and
rideability Joints in overlay should be sawed in small,
square panels
To increase structural capacity where
traffic loads have increased or will increase Transverse joints must be sawed T/3 (with
special attention to thickened overlay over
To meet vertical clearances asphalt ruts)
To reduce urban heat island effect by Joints in the overlay should not be placed in
increasing pavement surface albedo wheel paths, if possible
Keys to success Thinner overlays may shorten sawing window;
Milling of existing asphalt may be required additional saws are likely to be required
Figure 4. Bonded overlay on asphalt pavement to eliminate or reduce surface distortions Application of curing compound or other
of 2 in. (50 mm) or more and to help provide curing methods must be timely and thorough,
especially at edges
Bonded Concrete Overlays of Composite Pavements
Existing pavement condition Milling existing asphalt may be required to
Fair or better structural condition with up to eliminate surface distortions of 2 in. (50 mm)
severe surface distress or more and to help provide good bond;
minimal spot repairs may be required
Applications Minimum 3 to 4 in. (75 to 100 mm) of asphalt
To eliminate surface defects such as should remain after milling
rutting and shoving or to improve surface Existing asphalt pavement surface
characteristics like friction, noise, and temperature must be maintained below 120F
rideability (48.89C) when placing overlay
To increase structural capacity where Joints in overlay should be sawed in small,
traffic loads have increased or will increase square panels
To meet vertical clearances Transverse joints must be sawed T/3 (with
To reduce urban heat island effect by special attention to thickened overlay over
increasing pavement surface albedo asphalt ruts)
Joints in the overlay should not be placed in
Keys to success
wheel paths, if possible
Figure 5. Bonded overlay on composite pavement If existing pavement profile indicates Thinner overlays may shorten sawing window;
isolated vertical distortions in underlying additional saws are likely to be required
concrete that could signal movement from
drainage or material-related distresses, Application of curing compound or other
repairs may be necessary curing methods must be timely and thorough,
especially at edges
4 Guide to Concrete Overlays
Unbonded Concrete Overlay System
Typically 4 to 11 in. (100 to 280 mm) thick, depending on desired life (15 to 30+ years), anticipated traffic loading, and condition of underlying pavement
In general, an unbonded overlay less than 6 in. (150 mm) thick on an asphalt pavement (not composite) normally requires at least 6 in. (150 mm) of
existing asphalt pavement (after milling). If the remaining asphalt is less than 6 in. (150 mm) thick, a bonded overlay should be considered.
Overlay serves as a new pavement on a stable platform (figures 6 to 8).

Unbonded Concrete Overlays of Concrete Pavements


previously called unbonded overlays Existing pavement condition reflective cracking (to reduce pore pressure
Poor condition, including material-related and minimize stripping of this separation
distress, but stable and uniform layer under high truck traffic, provide
adequate drainage and a more porous
Applications asphalt)
To restore or enhance pavements Some states are experimenting with
structural capacity geotextile materials for the separation layer
To increase pavement life equivalent to Faulting of 0.38 in. (10 mm) or less in the
full-depth pavement existing concrete pavement is generally not
To improve surface friction, noise, and a concern when asphalt separation layer is
rideability 1 in. (25 mm) or more
Joints should be sawed in overlay as soon
Keys to success
as possible because the sawing window
Full-depth repairs should be considered may be shorter than it is typically
only at isolated spots where structural Shorter joint spacing than normal in the
integrity needs restoring overlay can help reduce curling and
A separation layer (typically 1 in. [25 mm] warping stress
Figure 6. Unbonded overlay on concrete pavement asphalt) is required to separate overlay It is not critical to match or mismatch
from the existing concrete and eliminate overlay joints to the underlying joints
Unbonded Concrete Overlays of Asphalt Pavements
previously called conventional whitetopping Existing pavement condition If less than 6 in. (150 mm) of asphalt remains
Deteriorated (severe rutting, potholes, after milling, a 6 in. (150 mm) or greater
alligator cracking, shoving, and pumping) but unbonded overlay (or a thinner bonded
stable and uniform overlay) should be considered
Full-depth repairs should be considered to
Applications restore structural integrity in isolated areas
To restore or enhance pavements Concrete patches in the existing pavement
structural capacity should be separated from the overlay with
To increase pavement life equivalent to a thin layer of fabric or other bond breaker,
full-depth pavement or joints should be sawed in the overlay
To eliminate deterioration problems around the concrete patch perimeter
To improve surface friction, noise, and Overlay joints should be sawed as soon as
rideability possible because the sawing window may
be shorter than it is typically
To reduce urban heat island effect by
increasing pavement surface albedo Surface temperature of existing asphalt
pavement should be maintained below
Keys to success 120F (49C) when placing overlay
Figure 7. Unbonded overlay on asphalt pavement Milling existing asphalt may be required Partial bonding between the overlay and the
to eliminate surface distortions of 2 in. (50 existing asphalt pavement is acceptable and
mm) or more may even improve load-carrying capacity
Unbonded Concrete Overlays of Composite Pavements
Existing pavement condition the underlying concrete that could signal
Deteriorated (severe rutting, potholes, movement from drainage or material-related
alligator cracking, shoving, pumping, and distresses, repairs may be necessary
past material-related distress) but stable and Full-depth repairs should be considered
uniform only at isolated spots where structural
integrity needs restoring
Applications
Concrete patches in the existing asphalt
To restore or enhance pavements
pavement surface should be separated
structural capacity
from the overlay with a thin layer of fabric
To increase pavement life equivalent to or other bond breaker; or joints should be
full-depth pavement sawed in the overlay around the concrete
To eliminate rutting and shoving problems patch perimeter
To improve surface friction, noise, and Joints should be sawed in overlay as soon
rideability as possible because the sawing window
may be shorter than it is typically
To reduce urban heat island effect by
increasing pavement surface albedo Surface temperature of the asphalt layer of
the existing composite pavement should be
Figure 8. Unbonded overlay on composite pavement Keys to success maintained below 120F (49C) when placing
Milling of existing asphalt may be required overlay
to eliminate surface distortions of 2 in. (50 Partial bonding between the overlay and
mm) or more the asphalt layer of the existing composite
If the existing pavement profile indicates pavement is acceptable and may even
isolated areas of vertical distortion in improve load-carrying capacity
Guide to Concrete Overlays 5
Evaluating Existing Pavement Conditions
Evaluating the existing pavement condi- sections with similar design and performance indicate the presence of a void under a concrete
tion is an important part of the pavement characteristics. panel in an existing concrete or composite
preservation and rehabilitation process. A pavement. Sections with signicant tenting can
This step also includes determining future
comprehensive evaluation provides valuable be repaired to relieve the pressure and provide
performance requirements, like expected trac
information about the pavements perfor- uniform support.
loadings and overlay design life.
mance capabilities and limitations, including
the following: Pavement Coring
Presence, type, and extent of distress
Visual Examination
The third step is to take cores from the existing
The second step is a visual site inspection to
Structural condition and load-carrying pavement. The cores help owners determine
gain initial information about the pavements
capacity layer thickness and identify the pavements
performance and distress issues. Discussions
Functional characteristics of the pavement, support value, the kind and condition of layer
with local design and maintenance engineers
such as roughness, friction, and noise materials, depth of distress(es), and, if the exist-
may also be benecial. Information should be
Characteristics and behavior of in-place ing pavement is composite, the condition of
gathered on pavement distress, road rough-
pavement materials the existing bond between layers. Cores that
ness, surface friction, shoulder conditions, and
penetrate into the subgrade may show evidence
Several activities can be performed as part of moisture/drainage problems, as well as trac
of unstable conditions, such as the beginning
the pavement evaluation process (see Hall et control constraints, obstructions, right-of-way
of ne soil migration into open-graded subbase
al. 2001; Hoerner et al. 2001; NCHRP 2007). zones, presence of bridges and other structures,
layers that can lead to plugging and instability.
Specics will vary from project to project, and general safety issues.
Cores also provide samples for possible labora-
depending on the project type and relative sig- The FHWA publication Distress Identication tory analyses.
nicance. Generally, the process can be divided Manual for the Long-Term Pavement
into the following steps (Hoerner et al. 2001;
NCHRP 2007) (gure 9; appendix A):
Performance Program (2003a) is useful when Optional Analyses
identifying pavement distresses and measuring Various factors aect the necessity for and
1. Historical data collection, records review, their severity. extent of additional pavement evaluation tests.
and future projections These factors include the existing pavement
Information obtained in this step will be used
2. Visual surface examination to determine the type and extent of eld testing condition and performance as determined
3. Core analysis required. For example, during the rst three steps of the evaluation
4. Possible additional tests, including analyses process; network-level performance data; road-
Distress observations may help the owner way classication; current and future trac
of material-related distresses, drainage,
determine the data collection interval, num- volumes, especially truck trac; current and
roughness and surface friction, and grade
ber of surveyors needed, and any additional future service life; budgetary constraints; and
restrictions
measurement equipment that might be type of overlay being considered. For example,
5. Condition assessment prole, summarized required.
in condition assessment evaluation report additional analysis may not be required for
Roughness data may dictate the need for lower road classications, such as local streets.
a more rigorous measurement program to
Historical Data and address any dierential sag/swell problems. An eective pavement condition evaluation
Future Projections is always necessary to conrm the validity of
One key to successful concrete overlays is either a bonded or unbonded overlay solution.
The rst step is to collect data from oce les ensuring that the underlying pavement and In general, however, more information about
and other historical records associated with the subgrade/subbase provide uniform support. the existing pavement condition is required
project. The goal is to collect as much infor- Consideration should be given to any dete- when bonded overlay systems are being con-
mation about the existing pavement as pos- rioration of an asphalt surface course (existing sidered or designed. There are several reasons
sible, such as original design data, construction asphalt or composite pavement), as asphalt is for this:
information, subgrade/subbase data, materials a good reector of underlying problem areas.
testing data, trac data, performance data, Examples include subbase/subgrade problems, The performance of bonded concrete over-
and so on. Possible data sources for this eort material-related distresses such as alkili-silica lays is more dependent on the condition of
include the following: reaction or D-cracking in a concrete layer, and the existing pavement.
other defects that result in isolated expansion Because bonded overlays are relatively
Design reports
or loss of support. thin, they are somewhat more susceptible
Construction plans/specications (new and to stresses, and the very nature of a bond
rehabilitation) A review of the existing prole grade line imposes stress.
Materials and soils properties from previous should be conducted; areas of signicant
The existing pavement will become part of a
laboratory test programs and/or published deviation will have to be investigated through
monolithic, overlaid pavement structure (not
reports analysis of core samples. Evidence of numer-
just a base for an unbonded overlay), so it
Past pavement condition surveys, non- ous active panel movements in a concrete or
needs to contribute a certain level of strength
destructive testing and/or destructive composite pavement may indicate potentially
and integrity and be capable of developing
sampling investigations unstable or nonuniform subgrade support or
and maintaining a bond with the overlay.
material-related distress. These, too, will require
Maintenance/repair histories
detailed pavement analyses to determine Therefore, when evaluating a pavements suit-
Trac measurements/forecasts the extent of distress and possible corrective ability for a bonded concrete overlay, it is
Environmental/climate studies action(s). For example, if movement is con- particularly important to characterize the exist-
Pavement management system reports ned to isolated areas, full-depth repairs in ing cross section and pavement characteristics
these areas may be considered. and the type, severity, and extent of distress(es).
The information gathered in this step can
be used to divide the pavement into discrete Panel tenting (early stages of blowups) may Laboratory testing may not be required on every

6 Guide to Concrete Overlays


project. Lab tests may be conducted to conrm Severity of distress represents the criticality drainability. DRIP (Drainage Requirements In
or clarify results from the visual examination, of the distress in terms of progression; more Pavements), an FHWA computer program, can
reveal distress mechanisms, and provide addi- severe distresses will require more extreme assist in such an analysis (Mallela et al. 2002).
tional information needed to identify feasible rehabilitation measures.
treatments. Examples of information deter- The extent of each distress type and severity Roughness and Surface Friction
mined from lab tests include the following: level must be measured. Tests
Concrete strength data Pavement deection testing is an eective way to Roughness and surface friction are two key
Stiness of existing concrete and asphalt and assess a pavements structural capabilities. Again, indicators of the functional performance of a
of composite layers pavement deection tests are not required for pavement: its smoothness for comfortable ride
all pavements, especially those in fair or better and its skid resistance for safety. Roughness
Petrographic testing and analysis of material-
condition and on lower volume roads. testing (expressed in terms of the International
related or other durability distress
Support values of the subgrade and subbase Several deection devices are available, but all Roughness Index) at the project level can
operate in basically the same manner. A known be useful to help identify localized areas of
Concrete permeability
load is applied to a pavement surface, and the roughness and to assess the eectiveness of
Asphalt stripping treatments (pre- and post-treatment roughness
resulting deection is measured. The FWD,
CTE of concrete comparisons). Friction (skid resistance) testing
or any device capable of applying loads similar
in magnitude and duration to that of a mov- is not commonly conducted for project-level
Material-Related Distress evaluations but may be meaningful on projects
ing wheel load, is commonly used. Deection
A detailed engineering evaluation of the type, test results are also used to develop pavement exhibiting a disproportionate number of wet-
degree, and state of MRD may be warranted to deection proles, back-calculate layer proper- weather crashes.
determine if an overlay is feasible. Unbonded ties, determine load transfer capabilities, and
overlays on concrete or composite pavements Elevations and Grade
evaluate the potential for voids at slab corners.
with material-related distress can be expected to Restrictions
have a long life, equal to a full-depth concrete Drainage Surveys Constructing concrete overlays will raise the
pavement, if the overlays are designed correctly, roadway prole grade unless it is lowered
Poor drainage conditions are a major cause
taking into account any nonuniformity in the through mechanical measures such as milling.
of distress in pavement structures. Unless
existing pavement. Consideration should be given to the eects of
moisture-related problems are identied and
Thicker unbonded overlays (6 in. [150 mm] corrected, the eectiveness of repairs and over- grade change, particularly at bridge underpasses
or greater) have been used successfully on ASR lays will be reduced. As part of a pavement and approaches, shoulder areas, and curb and
distressed concrete pavement (alone or as part distress survey, the overall drainage conditions gutter units. Design details for these situations
of an existing composite pavement) in a variety of the existing pavement should be assessed. are included on pages 38 to 39.
of climates and for a wide range of highway Observations of moisture/drainage problems
classes. These overlays perform extraordinarily (e.g., pumping, corner breaks, standing water, Condition Assessment
well when the reactive aggregate expansion and so on) may indicate the need for a more Profile
is near completion or is relatively uniformly intensive FWD test for the support value k or
spread throughout the existing pavement. a more thorough survey of subsurface drainage When all aspects of an existing pavement have
conditions. The purposes of a drainage survey been evaluated, the critical distresses and drain-
However, extreme variation in degree of ASR are to age conditions should be summarized. One
distress along the length of pavement (particu- useful way to summarize this information is
larly when distress is concentrated at the joints) detect and identify moisture-related distress,
to plot it on a condition assessment prole, or
can result in nonuniform support and conse- document prevailing drainage conditions strip chart (Smith 2008). In bar chart form,
quent performance challenges for the overlay. (e.g., cross slopes, cut/ll areas, depth and this prole visually indicates where various
condition of ditches), and distresses occur over the length of the project,
Since D-cracking normally occurs at or near assess edge drain conditions. as well as their extent and severity. Distresses
concrete joints, bonded concrete overlays on
If edge drains are present, their eectiveness such as slab cracking, corner breaks, faulting
concrete pavements with D-cracking (or com-
should be evaluated by observing their outow and spalling, continuous roughness, etc., can
posite pavements in which the concrete layer
after a rainfall or after water is released from be displayed. Areas of poor drainage or signi-
has D-cracking) have had mixed performance
a water truck over pavement discontinuities. cant changes in topography (cut/ll sections)
results. Localized joint movement and even
Another way to assess edge drain eectiveness can be overlaid on the strip charts. Such sum-
failure can occur in the underlying pavement.
This may cause cracking in the bonded overlay is through video inspections (Daleiden 1998; maries provide critical insight into a pavements
as a result of the nonuniform base support. Christopher 2000). A video camera attached structural and functional performance, helping
to a pushrod cable and inserted into the drain- roadway owners determine if and when pave-
Distress Surveys age system at outlets can locate blockages like ment preservation or rehabilitation activities
rodents nests or areas of crushed pipe. Several are appropriate.
Information gained from distress surveys will
states have adopted edge drain video inspec-
have the greatest impact on identifying neces-
sary spot repairs and selecting appropriate
tion in their pavement evaluation/construction Pavement Evaluation
process.
overlays. Pavement distress in the form of vis- Report
ible defect or deterioration of the pavement It is especially important to determine the
The nal evaluation step is summarizing the
is the most basic indication of an existing subgrade soils freeze-thaw and shrink-swell
results of data collection and analyses in an
pavements current performance and structural characteristics. Soil strength-related tests using
evaluation report. Any critical non-pavement
condition. To evaluate pavement condition the dynamic cone penetrometer or the standard
factors, such as shoulder condition, ditches,
more completely, the type, severity, and extent penetration test provide useful information
right-of-way, curves, bridges, ramps, and traf-
of distresses should be examined in detail: about subgrade stability.
c patterns should be identied in the report.
Types of distress are determined primarily by Possible drainage problems indicated by a Ultimately, this information will be used in the
occurrence and appearance and can indicate drainage survey may suggest the need for identication and selection of appropriate spot
the underlying causes of deterioration. in-depth analysis of the pavement structures repairs and overlays (gure 10; appendix A).
Guide to Concrete Overlays 7
Initial Evaluation (steps 14)
Pavement History and Performance Goals Core Analysis
Pavement material (including Remaining life Type of distress
aggregate CTE), design, age,
Desired traffic and performance level Depth of distress
thickness, layers
Desired design life Verification of thickness for pavement
Existing traffic and performance level base/subbase
Elevations and grade restrictions
Design life
Other historical information

Visual Examination 4 Optional Analyses

Concrete Asphalt / Composite (depending on extent of problems)

4-a. Material-Related Tests


(indicated by core analysis)
Conduct if (a) material or durability issues are
indicated or (b) roadway provides service for
high levels of traffic, especially if a bonded
overlay is being considered.

Petrography analysis
Concrete material-related distress (MRD)
Poor air-void system
Good Good Asphalt stripping
CTE

4-b. Subsurface Tests


Conduct if (a) pavement or subgrade support
issues are indicated or (b) roadway provides
service for high levels of traffic, especially if
a bonded overlay is being considered.

FWD tests
Subgrade/subbase support (k value)
Fair Fair
Subgrade/subbase variability
Pavement properties
Load transfer efficiency
Presence of voids
Asphalt stiffness
Concrete flexural strength
Subgrade tests
Freeze-thaw characteristics
Shrink-swell characteristics
Soil strength (dynamic cone penetration
Poor Poor or standard penetration test)

4-c. Surface Texture Tests

Conduct if (a) materials or durability issues


are indicated, or (b) roadway provides
service for high levels of traffic, especially if
a bonded overlay is being considered.

International roughness index (IRI)


Friction (skid resistance) tests

Deteriorated Deteriorated

Figure 9. Examples of existing pavement conditions (Photo courtesy of Snyder and Associates)

8 Guide to Concrete Overlays


Initial Evaluation (step 5)
5 Condition Assessment Profile
Concrete Asphalt / Composite
Surface Deficiencies Surface Deficiencies
Friction loss Bleeding/flushing
Joint deterioration (low to medium) Block cracking Pavement
Map cracking (non-ASR) Friction loss Evaluation
Popouts Noise Report
Noise Corrugation and
Scaling Joint reflective cracking Pavement
Roughness (not distress-related) Roughness (not distress-related) Condition
Plastic shrinkage cracks Rutting Rankings
Thermal shrinkage cracks Weathering/raveling
IRI Shoving
Other Slippage
Structural Deficiencies IRI
Corner breaks Other
Joint deterioration (severe) Structural Deficiencies
Tented panels Fatigue (alligator) cracking
Longitudinal cracking Depressions
Pumping/faulting Heaves
Punchout Longitudinal cracking
MRD (medium to severe) Potholes
Transverse cracking Transverse thermal cracking
Subgrade/subbase condition Rutting/shoving
Other Subgrade /subbase condition
Other

Figure 9. Examples of existing pavement conditions, continued

Summary of Pavement Evaluation Process


The purpose of evaluating the existing pave- formance requirements, like expected trac sible support problems, or surface conditions
ments condition is to collect details about any loadings and overlay design life. may be necessary. The following questions can
distresses and performance problems that cur- help the pavement owner determine if addi-
This step should include a determination of
rently exist and their causes. This information tional tests are advisable:
any elevation limits and/or grade restrictions
helps the owner-agency determine if a pave-
that signal potential clearance issues for over- What is the extent of pavement distresses,
ment is a good candidate for a concrete overlay
lay construction. based on the visual evaluation and core
and, if so, the extent of spot repairs required
analysis?
before an overlay is constructed. The extent of 2. The second step is a visual examination of
repairs needed is an important factor in deter- the pavements condition, noting visible sur- What is the pavements expected service
mining if/when either a bonded or unbonded face and structural distresses. level and life? Major highways with sig-
overlay will be a cost-eective solution. nicantly high truck volumes and/or long
3. The third step is a more thorough examina-
service life require more extensive and com-
Evaluating the existing pavements condition tion of the pavement structure through a
prehensive evaluations than lower volume
involves at least three steps: core analysis. This step will identify distresses
roadways.
or performance problems that cannot be
1. The rst step is to review the pavements determined by a visual exam alone. Core Is a bonded or unbonded concrete overlay
historical design and performance record: analyses verify pavement thickness, the being considered? Bonded overlays can rep-
pavement thickness and other design subgrade/subbase material and thickness, resent some additional challenges compared
attributes, mixture materials and design, and the depth and perhaps type or cause of to unbonded overlays.
construction date and method, trac load- distresses.
ings, design life, maintenance activities to Results from all initial evaluation steps should
date, etc. Based on information learned in steps 1 be recorded in a Condition Assessment Prole.
through 3, the necessity for additional evalua- This prole helps the agency determine the
Along with looking at the historical records, tion should be considered. For example, tests pavements overall condition and summarize it
this step should include recording future per- related to materials or durability distresses, pos- in a Pavement Evaluation Report.
Guide to Concrete Overlays 9
Selecting Appropriate Concrete Overlay Solution
Several factors should be considered when
selecting the type of concrete overlay solution.
Pavement Condition Rankings The condition of the existing pavement is the
(based on existing pavement conditions) paramount factor. Generally, existing pave-
ments in relatively good condition, or that can
Concrete Pavement Condition be cost-eectively brought to good condition,
are candidates for bonded concrete overlays.
Good or Better (Concrete) In these cases, bonded overlays can improve
functionality (e.g., reduce roughness or noise
Structurally and materially sound but in
need of increased structural capacity,
or enhance friction) and/or increase struc-
improved rideability or skid resistance, or
removal of surface defects

Asphalt/Composite
Pavements Condition

Good or Better (Asphalt/Composite)


Structurally and materially sound but need-
ing increased structural capacity, improved
rideability or skid resistance, removal of
surface defects, and/or improved albedo Can Can YES
spot milling
surface the
repairs and/ surface
Fair or Better (Concrete)
or remove surface
Structurally and materially sound but in spot structural
And/or deficiencies
need of surface repairs or enhancement repairs cost- cost-effectively,
effectively solve any bringing the pavement
deficiencies, bringing to Good Condition
Fair or Better (Asphalt/Composite) the pavement to and enhancing
Good Condition potential bonding
Structurally and materially sound but has before overlay is before overlay is
surface distress such as rutting, shoving, constructed? constructed?
slippage, or thermal cracking

Poor or Better (Concrete)


Has measurable surface distresses and
exhibits some structural, material, and/or No
other durability-related deterioration

Poor or Better (Asphalt/Composite)


Has measurable surface distresses such YES
as severe rutting, shoving, slippage, ther-
mal cracking, and exhibits some structural
deterioration
Can an unbonded
overlay design, with
Deteriorated or Better (Concrete) minor repairs and/or thin
milling, cost-effectively
Exhibits significant deterioration, includ- meet future traffic loads
ing structural, material, and/or other and design life
durability-related distresses requirements?
No
Deteriorated or Better (Asphalt/Comp)
Exhibits significant surface deterioration and
some structural distresses

Figure 10. Flowchart process for selecting concrete overlay type

10 Guide to Concrete Overlays


tural capacity (e.g., accommodate anticipated just as cost-eective to place a slightly thicker Concrete overlays can provide economical
increases in truck trac loadings). For example, unbonded overlay with less preoverlay repair short- to long-term solutions. It should be
a pavement in fair to poor functional condition work and not have to depend on the bond. noted, however, that the recommendations
due to rutting and shoving can be resurfaced provided in the owchart (gure 10) are gener-
Generally, existing pavements in poor con-
with a bonded overlay, after the pavement has ally long-term xes, on the order of 20 years or
dition and exhibiting signicant structural
been improved to good condition through more of expected life.
deterioration are candidates for unbonded
spot repairs or milling to remove decien-
overlays. Moreover, the presence of MRD, The next several pages provide overviews of
cies. The bond between the overlay and the
such as ASR or D-cracking, on an existing the important issues related to designing and
existing pavement inherently adds structural
concrete pavement also suggests the need for an constructing each type of concrete overlay, as
capacity. In this situation, however, it may be
unbonded overlay or even reconstruction. illustrated in gures 11 to 18.

Can If Design
a 25 existing
in. (50125 pavement Bonded Overlay
mm) bonded is concrete, (25 in. [50125 mm])
overlay design And can joints in
cost-effectively overlay be sawed
meet future traffic
loads and design life
to match joints in
the existing concrete
Or
requirements? pavement? YES
Or
Design
Can a 4 in. (100 mm) or greater unbonded Unbonded Overlay
overlay design cost-effectively
meet future traffic loads and (45 in. [50125 mm])
design
life requirements?
Note: If any potential future durability
problems exist (e.g., early-age MRD or
unstable base), do not use bonded overlay. If
No you use an unbonded overlay in this situation,
be aware that these potential problems may
aect design life.

Are there
any indications
of potential future
durability problems, such as
early-age MRD or unstable
conditions? No Design
Unbonded Overlay
(411 in. [100275 mm])
YES YES
If milling
is used for
rehabilitation, can
milling remove major
surface and structural
Can existing deficiencies and still maintain a
or potential un- minimum of 34 in. (75100 mm)
Consider on-site recycling and
stable conditions or YES of existing pavement to
reconstruction options:
major deficiencies (e.g., serve as base for a
wet subgrade, MRD, faulting, new unbonded 1. Mill or crush pavement as granular
asphalt stripping, etc.) be addressed overlay? No material; recycle as base or
cost-effectively with a combination of shoulder material. (Although not
rehabilitation techniques (e.g., milling, a mainstream approach, concrete
retrofit subdrains, spot repairs, pavements may be rubblized as
base stabilization, etc.) alone long as they are uniform and the
or with adequately thick subgrade is stable enough to
unbonded overlay? No support rubblization. See page 30.)
2. Place full-depth concrete.
Or
Construct full-depth pavement
replacement

Guide to Concrete Overlays 11


Bonded Concrete Overlays Monolithic pavement with
new concrete surface
of Concrete Pavements
previously called bonded overlays Prepared surface

Existing concrete pavement


with surface distresses

Figure 11. Bonded concrete overlay of good condition


concrete pavement with surface distresses

Uses resurfaced, it will be structurally sound enough The use of high-modulus structural bers in
to carry anticipated trac loads. For general the mixture can improve the toughness and
Bonded concrete overlays should be used on
information on pavement evaluation, see post-cracking behavior of the concrete and help
concrete pavements only if the existing pave-
pages 6 through 9. control plastic shrinkage cracking.
ment is in good or better condition. Concrete
pavements that are structurally sound but need If an existing concrete pavement exhibits crack- Regarding concrete aggregate, the following
increased structural capacity and/or correction ing from expansion caused by MRD, such as issues should be considered:
of surface defects, such as extensive scaling or ASR or D-cracking, it is not a good candidate
for a bonded concrete overlay. An unbonded A well-graded aggregate will reduce the water
surface cracking, can benet from a 2 to 5 in. and paste content of the mixture, thus reduc-
(50 to 125 mm) bonded concrete overlay. overlay may be considered.
ing potential shrinkage and curling, as well
Resulting enhancements include improved as the related risk of debonding. The maxi-
rideability, skid resistance, and reectivity OVERLAY DESIGN
mum aggregate size of the overlay concrete
characteristics. should be one-third of the overlay thickness.
Overlay Thickness
A bonded concrete overlay relies on the exist- The design thickness for bonded concrete Aggregate with CTE similar to or lower than
ing concrete pavement to carry some trac overlays is typically 2 to 5 in. (50 to 125 mm), that of the existing concrete pavement will
loading. The overlay is bonded to the existing depending on the desired load-carrying capac- help ensure the two layers move together,
concrete pavement to form a monolithic sec- ity and service life and the structural capacity thus reducing stresses at the interface.
tion, thereby reducing stresses and deections. provided by the underlying pavement. Some
Under certain conditions, a mill and inlay can Pore space in the aggregate should be fully
states, such as Colorado, use 6 in. (150 mm) saturated before batching (saturated surface,
be used if the existing pavement has signicant bonded overlays on high-trac roads.
surface issues but is structurally sound and the dry condition); otherwise, the aggregate will
subbase/subgrade is stable. tend to pull water from the mixture at early
Thickness is commonly determined using an
ages, increasing the possibility of shrinkage,
established design procedure such as AASHTO
which can lead to debonding.
Performance Guide for Design of Pavement Structures
(AASHTO Guide) (1993, 1998). However,
Bonded concrete overlays have been success- agencies are becoming increasingly familiar with
Joint Design
fully used for over 90 years as a means of the procedure in the M-E PDG as well. For The bonded overlay joint type, location, and
strengthening old concrete pavement, provid- more information, see table 8 on page 26. width must match those of the existing con-
ing a new smooth surface, repairing surfaces crete pavement in order to create a monolithic
with popouts, or repairing other surface defects Mixture Design structure. Matched joints eliminate reective
such as spalls, scaled areas, and areas with high cracking and ensure that the two layers of the
steel near the surface. Conventional concrete mixtures have been
pavement structure move together, helping
successfully used for bonded concrete overlays
maintain bonding. To minimize curling and
of concrete pavements. When used in conjunc-
Overlay Process tion with mixture additives and accelerated
warping stresses, some agencies have success-
fully created smaller overlay panels by sawing
construction techniques, conventional con-
PAVEMENT EVALUATION additional transverse and longitudinal joints in
crete mixtures can be proportioned for rapid
the overlay between the matched joints.
An evaluation of the existing concrete pave- strength gain with corresponding minimum
ment is necessary to ensure that it is a good expansion and contraction. For additional An important element in transverse joint
candidate for a bonded overlay and that, once information on expedited mixtures, see page 34. design is joint dimensions. The depth should

12 Guide to Concrete Overlays


be full depth plus 0.50 in. (13 mm). To prevent necessary. When cracks (particularly working should be used only as supplementary cleaning
debonding, the width of the transverse joint cracks) exist in the pavement to be resurfaced, procedures to remove loose material from the
should be equal to or greater than the width reective cracking will almost always occur. surface after shotblasting, milling, or sand-
of the underlying joint or crack in the existing Crack cages over existing cracks have been suc- blasting. In no case should standing water or
pavement (gure 12). The width of the exisitng cessfully used to prevent reective cracking. moisture remain on the pavement surface when
underlying pavement crack may be determined the overlay is placed. Paving should commence
When voids are detected under existing slabs,
by spot-excavating along the pavement edge. soon after cleaning to minimize the chance of
the slabs should be stabilized through grout
(If the pavement system experiences expansion contamination.
injection or other methods. Asphalt patches
and the overlay pushes against itself because the
should be removed and replaced with concrete Vehicles should be limited on the existing
width of the transverse overlay joint is less than
patches (or simply lled with concrete at the surface after it is prepared. If it is absolutely
the width of the underlying existing pavement
time of overlay placement) to ensure bonding necessary to have vehicles on the existing con-
crack, debonding may occur.)
of the concrete layers. crete, care should be taken that they do not
Some agencies believe that T/2 is sucient for drip oil or other contaminants that could com-
A consideration in performing repairs is
longitudinal joint depth. Others recommend promise the bond.
whether movement in the underlying pave-
sawing longitudinal joints full depth plus .50 in.
ment will cause movement in the overlay. Any CONSTRUCTION
(13 mm) to cut through the bond line.
movement in the overlay that does not occur at
Tiebars, dowel bars, or other embedded steel matched joints could contribute to debonding Concrete Placement
products are not used in bonded concrete over- and subsequent deterioration of the overlay.
Grade adjustments may be made to ensure
lays to minimize restraint forces in the bond.
Surface Preparation the required thickness of the concrete.
Except for joint design, bonded overlays on Conventional concrete paving practices and
Surface preparation of the existing concrete procedures are followed for bonded concrete
existing CRCP are designed, prepared, and
pavement is accomplished to produce a overlays.
constructed the same way as bonded concrete
roughened surface that will enhance bonding
overlays on plain jointed concrete pave-
between the two layers. A variety of surface Curing
ments. Transverse joints are not cut in bonded
preparation procedures may be used, includ-
concrete overlays over CRCP pavements. Curing is especially critical on a bonded
ing shotblasting, milling, and sandblasting.
Acceptable cracking will occur in the bonded concrete overlay because its high surface area-
A bonding grout or epoxy is not required.
overlay, typically (but perhaps not immedi- to-volume ratio makes the thin concrete overlay
The most commonly used and most eective
ately) over existing cracks in the CRCP. more susceptible to rapid moisture loss. Within
surface preparation procedure is shotblasting.
30 minutes of placing the overlay, curing com-
Although milling will roughen the concrete
Drainage Repair pavement surface, milling should not be used
pound should be applied at twice the standard
During evaluation and design of a bonded con- rate. The nished product should appear as a
solely for that purpose because of its potential
crete overlay project, existing subgrade drainage uniformly painted solid white surface, with the
for causing surface microcracking and fractur-
should be evaluated, as would be done with vertical faces along the edges of the overlay also
ing the exposed aggregate. If milling is used
asphalt resurfacing. If necessary, steps should thoroughly coated.
to lower the pavement elevation, any resulting
be taken to ensure adequate drainage in the microcracking should be removed by shotblast-
future.
Joint Sawing
ing or high water pressure blasting.
Timely joint sawing is necessary to prevent
PREOVERLAY WORK Surface Cleaning random cracking. Sawing should begin as soon
as the concrete is strong enough that joints can
Following surface preparation, the concrete
Preoverlay Repairs be cut without signicant raveling or chipping.
surface should be cleaned to ensure adequate Lightweight early-entry saws allow the sawing
Preoverlay repairs of certain distresses may be bonding between the existing concrete surface
necessary to achieve the desired load-carrying crew to get on the pavement as soon as possible.
and the new concrete overlay. Cleaning may be
capacity and long-term durability. The surface accomplished by sweeping the concrete surface, To help match transverse joint locations, place
should be inspected for isolated pockets of followed by cleaning in front of the paver with guide nails on each edge of the existing pave-
deterioration that require repairs (table 1). compressed air. Airblasting and waterblasting ment at the joints; after the overlay is placed,
mark the joint with a chalk line connecting the
For isolated areas that have wide random cracks
guide nails.
or working joints, full-depth repairs may be
Table 1. Possible preoverlay repairs on
existing concrete pavement in preparation
Future Repairs
for bonded overlay The recommended repair option for bonded
Width of new concrete overlays on concrete is full-panel
Overlay joint overlay Existing Spot Repairs replacement. Concrete panels are easily
Concrete transverse joint Pavement Distress to Consider
overlay removed and replaced. Another option is sim-
Random cracks Reflective cracking is likely ply to mill and ll with concrete. If a panel is
if no repairs are made; use cracked or otherwise distressed but the ride
Saw cut in crack cages or full-depth
existing slab
repairs for severe cracks quality of the pavement is not compromised,
Underlying crack the panel may be left in place.
in existing slab Faulting Slab stabilization
Pumping Slab stabilization
Asphalt patch Replace with concrete patch
Figure 12. Width of transverse joint in to ensure bonding Key Resources
bonded concrete overlay on concrete Joint spalling Partial-depth repair ACI Committee 325 (2006); Trevino et al.
pavement should be equal to or greater than (2004); ACPA (1990a)
Scaling Remove with cleaning
width of crack in existing pavement

Guide to Concrete Overlays 13


Bonded Concrete Overlays New 25 in. (50125 mm)
of Asphalt Pavements bonded concrete overlay
with square panels

previously called ultra-thin whitetopping

Milled and cleaned


surface

Existing asphalt pavement


with surface distresses

Figure 13. Bonded concrete overlay of fair or better


condition asphalt pavement with surface distresses

Uses asphalt pavement and the overlaymove as www.pavement.com/Concrete_Pavement/


one structure. Technical/UTW_Calculator/), which incor-
Asphalt roads, streets, and intersections that porates methods to address limitations of the
are in fair or better condition structurally can Overlay Process AASHTO procedures. Agencies are also becom-
be enhanced with a 2 to 5 in. (50 to 125 mm) ing increasingly familiar with the procedure in
bonded concrete overlay if they exhibit surface PAVEMENT EVALUATION the M-E PDG. For more information, see table
distresses such as rutting, shoving, slippage, 8 on page 26.
An evaluation of the existing asphalt pavement
and thermal cracking and/or they could ben-
is necessary to ensure it is structurally adequate
et from increased structural capacity. Mixture Design
to carry the anticipated trac loads, to deter-
The bonded concrete overlay relies on the mine required milling depths, and to establish Conventional concrete mixtures have been suc-
existing asphalt pavement to carry some trac the bonded overlay design thickness. For gen- cessfully used for bonded concrete overlays of
loading. The overlay is bonded to the existing eral information on pavement evaluation, see asphalt pavements.
asphalt pavement to form a monolithic sec- pages 6 through 9.
tion, thereby reducing stresses and deections. When used in conjunction with mix addi-
Asphalt pavements with signicant structural tives and accelerated construction techniques,
deterioration, inadequate or uneven base/ conventional concrete mixtures can be
Performance subbase support, poor drainage conditions, or proportioned for rapid strength gain with
Bonded concrete overlays have been success- stripping of asphalt layers are not good bonded corresponding minimum expansion and
fully used in many states to maintain and overlay candidates; in such cases, an unbonded contraction. For additional information on
rehabilitate asphalt pavements with surface concrete overlay should be considered. expedited mixtures, see page 34.
defects. Numerous studies have shown
bonded concrete overlays to provide a durable, The use of high-modulus structural bers
OVERLAY DESIGN can improve the toughness and post-cracking
reliable surface course as long as there is a suf-
cient bond between the asphalt surface and Overlay Thickness behavior of the concrete and help control plas-
the overlay and the existing asphalt pavement tic shrinkage cracking.
The design thickness for bonded concrete
is structurally adequate for a bonded concrete overlays is typically 2 to 5 in. (50 to125 mm),
overlay. Joint Design
depending on the desired load-carrying
The recommended joint pattern for bonded
Factors that aect the performance of the capacity and service life and the structural
overlays of asphalt is small square panels, typi-
resurfaced pavement system include the capacity provided by the underlying pavement.
cally in the range of 3 to 8 ft (0.9 to 2.4 m),
strength and integrity of the underlying pave- Additional overlay thickness may be required in
to reduce curling and warping stresses. It is
ment, the eectiveness of the bond, the ability transition sections to prevent movement of the
recommended that the length and width of
of the two layers to move monolithically to overlay panels adjacent to the existing asphalt
joint squares in feet be limited to 1.5 times the
maintain the bond, and the overlay jointing pavement and to reduce the potential for crack-
overlay thickness in inches. In addition, if pos-
and curing techniques. ing due to trac impact loadings.
sible, longitudinal joints should be arranged so
They key to maintaining the performance is Thickness may be determined using AASHTO that they are not in the wheel path. The use of
to ensure the two structuresthe existing Supplement (1998). The most common pro- tiebars or dowels is not necessary because of the
cedure is an ACPA spreadsheet (revised 2008; small panel spacings.

14 Guide to Concrete Overlays


PREOVERLAY WORK the types and severity of distresses and the cracking. No standing water should remain on
thickness of the asphalt. The objective of mill- the surface at the time the overlay is placed.
Preoverlay Repairs ing is not to obtain a perfect cross section or to Water trapped in the milled surface can be
completely remove ruts. blown o with compressed air.
Areas with potholes; localized, moderate-to-se-
vere alligator cracking; or loss of base/subgrade It is important to make sure that the milling Once the surface of the existing asphalt
support may require partial or full-depth spot depth does not compromise the bonding eec- pavement has been prepared, paving is accom-
repairs to achieve the desired load-carrying tiveness of asphalt tack lines between existing plished using either conventional xed-form or
capacity and long-term durability (table 2). asphalt lifts. Therefore, milling should remove slipform construction, depending on the size of
However, new asphalt patches do not bond asphalt to the nearest tack line. the project and any geometric constraints.
well with concrete overlays, so new concrete
patches are recommended. A minimum of 3 to 4 in. (75 to 100 mm) Because of the variation of the thickness of
of asphalt should remain after milling. An concrete, the concrete material is bid on a
Patching with concrete should be completed adequate layer of asphalt is required to prevent cubic-yard basis. Some states also include a bid
after milling. Whether a concrete patch is delamination, thus ensuring that the asphalt item for placement on a square-yard basis.
placed separately or poured at the same time will function as a load-carrying portion of the
as the overlay (i.e., in one paving operation), composite section (not as a separation layer or Curing
the result is a spot section of thicker concrete. shear plane, as in an unbonded overlay). Curing is especially critical on a bonded
This thicker section of concrete will move dif- concrete overlay because its high surface area-
ferently from the adjacent asphalt, so no single While the milling machine is on site, it is
important that the pavement surface be to-volume ratio makes the thin concrete overlay
overlay panel should be over both asphalt pave- more susceptible to rapid moisture loss. Within
ment and the concrete patch. This will require inspected to determine if additional milling is
required. 30 minutes of placing the overlay, curing com-
adjusting the normal jointing pattern of the pound should be applied at twice the standard
overlay so the section over the concrete patch Further Repairs rate. The nished product should appear as a
is isolated. uniformly painted solid white surface, with the
After milling, the surface should be inspected
vertical faces along the edges of the overlay also
Milling for isolated pockets of deterioration that
thoroughly coated.
In general, milling should be minimized require further repairs. For isolated areas that
because it results in loss of structural support. have a high number of wide transverse thermal Joint Sawing
There is no reason to mill o good asphalt that cracks, a decision needs to be made whether to
bridge the cracks with the bonded overlay or Timely joint sawing is necessary to prevent ran-
can contribute to composite action and con- dom cracking. Joint sawing should commence
tinue to help carry trac loads. to clean and ll the cracks. Concrete can span
normal asphalt longitudinal and transverse as soon as the concrete has developed sucient
The main objectives of milling prior to placing cracks. Filling old cracks with y ash slurry, strength so that joints can be cut without
a bonded overlay are (1) to remove signicant concrete grout, or other appropriate material is signicant raveling or chipping. Lightweight
surface distortions that contain soft asphaltic necessary only for cracks that have an opening early-entry saws 0.13 in. (3.0 mm) thick may
material, which would result in an inadequate greater than the maximum size aggregate used be used to allow the sawing crew to get on the
bonding surface; (2) to reduce high spots in the overlay. pavement as soon as possible. Extra saws will
to help ensure minimum overlay depth and likely be needed. Transverse joints can be sawed
reduce the quantity of concrete needed to ll Surface Cleaning with conventional saws set to a depth of T/4.
low spots; and (3) to match curb or adjacent Transverse joint saw-cut depths for early-entry
Following repairs, the asphalt surface needs sawing should not be less than 1.25 in. (31
structure elevations. Milling may also be to be cleaned to ensure adequate bonding
considered to roughen the surface, which will mm). Longitudinal joints should be sawed
between the existing asphalt surface and the to a depth of T/3. Joint sealing may not be
likely enhance bonding. new concrete overlay. Adequate bonding is required.
Most surface distresses can be removed through very important to the performance of this type
milling (table 2). Milling may be used where of overlay. Cleaning may be accomplished by
surface distortions are 2 in. (50 mm) or greater. rst sweeping the asphalt surface, then clean- Future Repairs
The amount of asphalt removed depends on ing with compressed air. Pressure washing Bonded concrete overlays on asphalt may be
should be considered only when dust control is easily repaired using full-panel replacement.
mandated or when mud has been tracked onto Another option is simply to mill and ll with
the milled surface. In no case should water or concrete. Do not patch with asphalt, because
Table 2. Possible preoverlay repairs on moisture be allowed to stand on the asphalt the adjacent concrete panels will move and
existing asphalt pavement in preparation for pavement prior to overlay placement. To pre- break the bond. If a panel is distressed but the
bonded overlay
vent contamination, it is important to avoid a ride quality of the pavement is not compro-
Existing Spot Repairs lengthy lag time between nal surface cleaning mised, the panel should be left in place. If a
Pavement Distress to Consider and paving. ride quality problem develops, the panel should
Deep rutting be replaced before any pieces of concrete
Milling
CONSTRUCTION become loose from the overlay.
Shoving, slippage Milling
Thermal cracking Fill crack when opening is Concrete Placement
greater than maximum size
aggregate in the overlay When the surface temperature of the asphalt Key Resources
Fatigue cracking Full-depth concrete patch is at or above 120F (48.89C), surface water- ACI Committee 325 (2006); Rasmussen
Pothole Full-depth concrete patch
ing can be used to reduce the temperature and Rozycki (2004); ACPA (1999)
and minimize the chance of fast-set shrinkage

Guide to Concrete Overlays 15


Bonded Concrete Overlays New 25 in. (50125 mm) thick bonded
of Composite Pavements overlay with square panels

Milled and cleaned


surface

Existing composite pavement


with asphalt surface distresses

Figure 14. Bonded concrete overlay of fair or


better condition composite pavement with
asphalt surface diistresses

Uses Overlay Process (revised 2008; www.pavement.com/Concrete_


Pavement/Technical/UTW_Calculator/),
Composite (asphalt on concrete) roads, streets,
PAVEMENT EVALUATION which incorporates methods to address limita-
and intersections that are in fair or better con-
tions of the AASHTO procedures. Agencies
dition structurally can be enhanced with a 2 to An evaluation of the existing asphalt pavement
are also becoming increasingly familiar with the
5 in. (50 to 125 mm) bonded concrete overlay is necessary to ensure it is structurally adequate
procedure in the M-E PDG. For more informa-
if they exhibit surface distresses such as rutting, to carry the anticipated trac loads, to deter-
tion, see table 8 on page 26.
shoving, slippage, and thermal cracking and/ mine required milling depths, and to establish
or they could benet from increased structural the bonded overlay design thickness. For gen-
Mixture Design
capacity. eral information on pavement evaluation, see
Conventional concrete mixtures have been
pages 6 through 9.
The bonded concrete overlay relies on the exist- successfully used for many bonded overlays of
ing composite pavement to carry some trac Composite pavements are not good candidates composite pavements.
loading. The overlay is bonded to the exist- for bonded overlays of less than 5 in. (125 mm)
When used in conjunction with mixture
ing pavement to form a monolithic section, if they display any of the following problems:
additives and accelerated construction tech-
thereby reducing stresses and deections.
Signicant structural deterioration, inad- niques, conventional concrete mixtures can
equate or uneven subgrade/subbase support, be proportioned for rapid strength gain with
Performance poor drainage conditions, or stripping of corresponding minimum expansion and
Bonded concrete overlays have been success- asphalt layers contraction. For additional information on
fully used in many states to maintain and expedited mixtures, see page 34.
rehabilitate composite pavements with surface Problems in the underlying concrete (pos-
defects. sibly reected in the asphalt layer) due to The use of high-modulus structural bers
MRD can improve the toughness and post-cracking
Factors that aect the performance of the resur- behavior of the concrete and help control plas-
faced pavement system include the strength Indications of possible future durability tic shrinkage cracking.
and integrity of the underlying pavement problems
layers, the quality of the bond between layers Joint Design
of the existing composite pavement, the eec- The recommended joint pattern for bonded
OVERLAY DESIGN
tiveness of the bond between the underlying overlays of composite pavements is small square
composite pavement and the new concrete Overlay Thickness panels, typically in the range of 3 to 8 ft
overlay, the ability of the new system to move (0.9 to 2.4 m), to reduce curling and warping
monolithically to maintain the bond, and the The design thickness for bonded concrete
overlays is typically 2 to 5 in. (50 to 125 mm), stresses. It is recommended that the length
jointing and curing techniques. and width of joint squares in feet be limited
depending on the desired load-carrying capac-
ity and service life and the structural capacity to 1.5 times the overlay thickness in inches. In
The key to maintaining performance is
provided by the underlying pavement. addition, if possible, longitudinal joints should
ensuring the two structuresthe existing
be designed outside the wheel path. The use of
pavement and the overlaymove as one Thickness may be determined using AASHTO tiebars or dowels is not necessary because of the
structure. Supplement (1998). The most commonly small spacings.
used prodecure is an ACPA spreadsheet

16 Guide to Concrete Overlays


PREOVERLAY WORK Most surface distresses can be removed through CONSTRUCTION
milling (table 3). Milling may be used where
Preoverlay Repairs surface distortions are 2 in. (50 mm) or greater. Concrete Placement
Areas with potholes; localized, moderate- The amount of asphalt removed depends on When the surface temperature of the asphalt
to-severe alligator cracking; or loss of base/ the types and severity of distresses and the is at or above 120F (49C), surface watering
subbase/subgrade support may require partial thickness of the asphalt. The objective of mill- can be used to reduce the temperature and
or full-depth spot repairs (table 3) to achieve ing is not to obtain a perfect cross section or to minimize the chance of early-age shrinkage
the desired load-carrying capacity and long- completely remove ruts. cracking. No standing water or moisture should
term durability. However, new asphalt patches It is important to make sure that the milling remain on the surface at the time the overlay is
do not bond well with concrete overlays, so depth does not compromise the bonding eec- placed.
new concrete patches are recommended. tiveness of asphalt tack lines between existing Once the surface of the existing asphalt
Patching with concrete should be completed asphalt lifts. Therefore, milling should remove pavement has been prepared, paving is accom-
after milling. Whether a concrete patch is asphalt to the nearest tack line. plished using either conventional xed-form or
placed separately or poured at the same time A minimum of 3 to 4 in. (75 to 100 mm) slipform construction, depending on the size
as the overlay (i.e., in one paving operation), of asphalt should remain after milling. An of the project and any geometric constraints.
the result is a spot section of thicker concrete. adequate layer of asphalt is required to prevent Because of the variation of the concrete
This thicker section of concrete will move dif- delamination, thus ensuring that the asphalt thickness, the concrete material is bid on a
ferently from the adjacent asphalt, so no single will function as a load-carrying portion of the cubic-yard basis. Some states also include a bid
overlay panel should be over both asphalt pave- composite section (not as a separation layer or item for placement on a square-yard basis.
ment and the concrete patch. This will require shear plane, as in an unbonded overlay).
adjusting the normal jointing pattern of the Curing
overlay so the section over the concrete patch Further Repairs Curing is especially critical on a bonded
is isolated. concrete overlay because its high surface
After milling, the surface should be inspected
Panel tenting (early stages of blowups) may be for isolated pockets of deterioration that area-to-volume ratio makes the thin concrete
an indication that a void exists under existing require further repairs. For isolated areas that overlay more susceptible to rapid moisture
panels. Sections with signicant tenting can be have a high number of wide transverse thermal loss. Within 30 minutes of placing the overlay,
repaired to relieve the pressure and provide uni- cracks, a decision needs to be made whether to curing compound should be applied at twice
form support before construction of a bonded bridge the cracks with the bonded overlay or the recommended rate. The nished product
overlay. to clean and ll the cracks. Concrete can span should appear as a uniformly painted solid
normal asphalt longitudinal and transverse white surface, with the vertical faces along the
Milling cracks. Filling old cracks with y ash slurry, edges of the overlay also thoroughly coated.
In general, milling should be minimized concrete grout, or other appropriate material is
necessary only for cracks that have an opening Joint Sawing
because it reduces structural support in the
greater than the maximum size aggregate used Timely joint sawing is necessary to prevent ran-
milled sections. There is no reason to mill o
in the bonded overlay. dom cracking. Joint sawing should commence
good asphalt that can contribute to composite
as soon as the concrete has developed sucient
action and continue to help carry trac loads. If there is vertical movement of the underlying strength so that joints can be cut without sig-
The main objectives of milling prior to placing concrete adjacent to a crack, the movement nicant raveling or chipping, typically within 3
a bonded overlay are (1) to remove signicant can be stopped by replacing or retrotting the to 6 hours of concrete placement. Lightweight
surface distortions that contain soft asphaltic joint. The crack can also be controlled without early-entry saws with 0.13 in. (3.0 mm) wide
material, which would result in an inadequate repairing the underlying pavement by adding blades may be used to allow the sawing crew to
bonding surface; (2) to reduce high spots bers to the mixture or, in some cases, by plac- get on the pavement as soon as possible. Extra
to help ensure minimum overlay depth and ing reinforcing steel rebar over the joint in the saws will likely be needed. Transverse joints can
reduce the quantity of concrete needed to ll overlay. Typically, 36 in. (900 mm) long no. 4 be sawed with conventional saws to a depth of
low spots; and (3) to match curb or adjacent bars are stapled to the existing pavement at 30 T/4. Transverse joint saw-cut depths for early-
structure elevations. Milling may also be in. (750 mm) spacings, perpendicular to the entry sawing should not be less than 1.25 in.
considered to roughen the surface, which will crack. (31 mm). Longitudinal joints should be sawed
likely enhance bonding. to a depth of T/3. Joint sealing is not required.
Surface Cleaning
Table 3. Possible preoverlay repairs on
Following repairs, the asphalt surface needs Future Repairs
to be cleaned to ensure adequate bonding
existing composite pavement in preparation Bonded concrete overlays on composite pave-
between the existing asphalt surface and the
for bonded overlay ments may be easily repaired using full-panel
new concrete overlay. Adequate bonding is
replacement. Another option is simply to
Existing Spot Repairs very important to the performance of this type
Pavement Distress to Consider mill and ll with concrete. Do not patch with
of overlay. Cleaning may be accomplished by
asphalt, because the adjacent concrete panels
Deep rutting Milling rst sweeping the asphalt surface, followed by
will move and break the bond. If a panel is
Shoving, slippage cleaning with compressed air. Pressure washing
Milling distressed but the ride quality of the pavement
should only be considered when dust control is
Thermal cracking Fill crack when opening is is not compromised, the panel should be left
greater than maximum size mandated or when mud has been tracked onto
in place. If a ride quality problem develops, the
aggregate in the overlay the milled surface. No standing water should
panel should be replaced before any pieces of
Fatigue cracking Full-depth concrete patch remain on the surface at the time the overlay is
concrete become loose from the overlay.
placed. To prevent contamination, it is impor-
Pothole Full-depth concrete patch
tant to avoid a lengthy lag time between nal Key Resources
Tenting (early Full-depth repair
stages of blowups)
surface cleaning and paving. ACI Committee 325 (2006); Rasmussen
and Rozycki (2004); ACPA (1999)

Guide to Concrete Overlays 17


Unbonded Concrete Overlays
of Concrete Pavements New unbonded overlay

previously called unbonded overlays


Possible preoverlay
repairs

Existing concrete pavement

Figure 15. Unbonded concrete overlay of


poor condition concrete pavement

Uses subgrades can cause looseness and shifting of OVERLAY DESIGN


fractured concrete, especially under saturated
Unbonded concrete overlays are an excellent Unbonded overlays are designed similarly to
conditions, resulting in surface failure.
rehabilitation option for concrete pavements new concrete pavements on a stabilized sub-
that exhibit some structural deterioration. An base, assuming a separated condition between
unbonded overlay of an existing concrete pave- Overlay Process the layers.
ment can reestablish the strength lost through
deterioration, provide a surface with desired
PAVEMENT EVALUATION
Overlay Thickness
rideability and other characteristics, and extend An evaluation of the existing concrete pave-
On primary roads, unbonded overlay thick-
the performance life capable to carry existing ment is necessary to determine whether the
nesses typically range from 6 to 11 in. (150
and future trac loads. existing concrete and its subbase can provide
to 280 mm); on lower volume roads they can
uniform support and, if not, what actions
This type of overlay is designed essentially as a be as thin as 4 in. (100 mm). The required
are necessary to obtain that uniformity if an
new concrete pavement on a stabilized subbase, overlay thickness is aected by the desired load-
unbonded overlay is to be used. The evaluation
assuming an unbonded condition between carrying capacity and service life, as well as the
also determines the existing pavements struc-
the layers. Unbonded overlay projects are condition of the concrete pavement.
tural contribution as a stable base. For general
typically 4 to 11 in. (100 to 275 mm) thick,
information on pavement evaluation, including Both AASHTO Guide (1993, 1998) and the
depending on the type and amount of trac
specic information about material-related dis- M-E PDG consider the eects of the separation
loads and the condition of the existing pave-
tresses, see pages 6 through 9. layer. See basic highlights of and dierences
ment. Unbonded overlays can be designed as
among the various procedures in table 8 on
JPCPs or CRCPs. A properly designed and For faulted pavements, the cause can usually
page 26.
functioning separation layer is critical to the be attributed to the combination of some loss
performance of this overlay type. of load transfer between slabs and some loss
of subgrade/subbase support. If the subgrade/ Separation Layer Design
Unbonded concrete overlays typically do not
subbase is stable, the increase in the carrying The separation layer design is one of the pri-
require extensive preoverlay repairs, though
capacity of the unbonded overlay has proven to mary factors inuencing the performance of
spot repairs of certain severely deteriorated
be adequate to overcome faulting. Faulting is unbonded overlays on concrete pavements.
areas may be necessary to minimize the risk of
generally not a concern when a separation layer The separation layer provides a shear plane that
localized failure in the overlay.
of 1 in. (25 mm) or greater is used. Retrotted helps prevent cracks from reecting up from
edge drains have been successfully used to the existing pavement into the new overlay. In
Performance reduce the progression of faulting. addition, the separation layer prevents bonding
Unbonded overlays of concrete pavements have of the new pavement with the existing pave-
Panel tenting (early stages of blowups) may
been successfully used in many states, with ment, so both are free to move independently.
be an indication that a void exists under the
over 30 years of good to excellent performance. slab. Sections with signicant tenting should The most common and successful separa-
Critical factors that aect the performance of be repaired to relieve the pressure and provide tion layer is a conventional 1 in. (25 mm),
unbonded overlays include separation layer uniform support before unbonded overlay well-drained asphalt surface mixture, which
design, overlay thickness, joint spacing layout, placement. provides adequate coverage over irregularities
and load transfer design. In addition, weak
18 Guide to Concrete Overlays
in the existing pavement. The thickness can be as unbonded overlays on plain jointed concrete Separation Layer
slightly increased when irregularities are large pavements. Texas has completed some CRCP Use of a sucient separation layer can help
enough to impact placement operations. The unbonded overlays over existing CRCP and ensure good performance of the unbonded
separation layer does not provide signicant plain jointed pavements, sometimes increasing overlay. Before separation layer placement,
structural enhancement; therefore, the place- the asphalt separation layer thickness to greater the existing pavement surface should be
ment of an excessively thick layer should be than one inch. swept clean of any loose material either
avoided. with a mechanical sweeper or an air blower.
Drainage Considerations
If scouring is a problem due to poor drainage Conventional placement practices and pro-
and high truck trac, some states use a modi- Without good drainage of the separation layer, cedures should be followed for placing the
ed, more porous asphalt mixture, reducing pore pressure builds up from heavy truck trac separation layer.
the sand content and increasing the volume of and can cause stripping of the asphalt separa-
0.38 in. (10 mm) chip aggregate. tion layer. Properly designed, constructed,
and maintained edge drains may help reduce CONSTRUCTION
Some states are experimenting with geotextile pumping, asphalt stripping, faulting, and
separation layer materials that are commonly cracking. Deeper edge drains (subdrains) are
Concrete Placement
being used in Germany. See discussion on page used to help stabilize subgrades/subbases. It When the surface temperature of the asphalt
35. is becoming more acceptable to daylight free- separation layer is at or above 120F (49C),
draining granular subbase material in lieu of surface watering can be used to reduce the tem-
Mixture Design placing edge drains. perature and minimize the chance of early-age
Conventional concrete mixtures are typically shrinkage cracking. No standing water should
used for unbonded overlays of poor condition Edge Support Design remain on the surface at the time of overlay
concrete pavements. These mixtures can be placement.
If shoulders are to be paved, tied shoulders may
used with accelerator admixtures to provide the be preferable to widened overlays in unbonded Conventional concrete paving procedures are
early strength required to place trac on the overlay construction because of the increase in followed for placing, spreading, consolidating,
unbonded overlay within a short time period. load transfer. Widened unbonded overlay slabs and nishing the unbonded overlay. Anchoring
Early opening can also be aided by use of have increased risk of longitudinal cracking dowel baskets to the underlying concrete
maturity measurements. because of the high curling stresses resulting pavement is important. Alternatively, pavers
from sti support conditions. Since some equipped with dowel bar inserters can be used.
Joint Design shoulder work is required for unbonded over- Because of the variation of the concrete thick-
Load transfer is better in unbonded overlays lays, tied concrete shoulders can be included as ness, the concrete material is bid on a volume
of concrete pavements than in new JPCPs part of the overlay project. (cubic-yard) basis. Some states include a bid
because of the load transfer provided by the item for placement, measured on a square-yard
underlying pavement. Doweled joints are used basis.
for unbonded overlays of pavements that will PREOVERLAY WORK
experience signicant truck trac, typically Curing
pavements 8 in. (200 mm) and thicker.
Preoverlay Repairs
Typically, only distresses that cause a major Good curing practices are especially critical
Shorter joint spacing should be used to reduce loss of structural integrity require repair. If to thin unbonded overlays because of their
the risk of early cracking due to enhanced curl- signicantly distressed areas are not shifting high surface area-to-volume ratio. This is
ing caused by the sti support provided by the or moving and the subgrade/subbase is stable, accomplished by applying a curing compound
underlying pavement (table 4). Many states costly repairs typically are not needed, particu- immediately after surface texturing; if the
do not intentionally mismatch joints and have larly with an adequately designed overlay (table unbonded overlay is 6 in. (150 mm) or thinner,
not experienced any adverse eects. However, 5). As an alternative to numerous repairs, some use twice the usual rate of curing compound.
some states still intentionally mismatch joints, states increase the unbonded overlay thickness The nished product should appear as a uni-
according to previous guidance, to maximize to provide additional strength and therefore formly painted solid white surface, with the
the benets of load transfer. increase the load-carrying capacity. vertical faces along the edges of the overlay also
thoroughly coated.
Using lane tiebars may be appropriate in
open-ditch (or shoulder) sections of unbonded Joint Sawing
overlays if the overlay is 5 in. (125 mm) or
Timely joint sawing is necessary to prevent ran-
greater. In this category, a no. 4 tiebar (0.50 in. Table 5. Possible preoverlay repairs on
dom cracking. Transverse joints can be sawed
[13 mm]) may be appropriate. The use of existing concrete pavement in preparation
for unbonded overlay with conventional saws to a depth of between
tiebars in conned curb-and-gutter sections
T/4 (minimum) and T/3 (maximum), but not
should be considered if the overlay is 6 in. (150
Existing Pavement Possible Repairs to less than 1.25 in. (31 mm). Transverse joint
mm) or greater. Condition Consider saw-cut depths for early-entry sawing should
Unbonded plain jointed concrete overlays over Faulting 0.250.38 in. None not be less than 1.25 in. (31 mm). Saw longitu-
CRCP are designed and constructed the same (610 mm) dinal joints to a depth of T/3.
Faulting > 0.38 in. Thicker separation layer
(10 mm) Future Repairs
Table 4. Typical transverse joint spacing
Significant tenting Full-depth repair The recommended repair options for unbonded
Unbonded Resurfacing Maximum Transverse Badly shattered slabs Full-depth repair overlays are the same as for standard concrete
Thickness Joint Spacing pavements.
Significant pumping Full-depth spot repair and
< 5 in. (125 mm) 6 x 6 ft (1.8 x 1.8 m) panels drainage improvements
Severe joint spalling Clean Key Resources
57 in. (125175 mm) Spacing in feet =
2 times thickness in inches CRCP with punchouts Full-depth repair
ACI Committee 325 (2006); FHWA
> 7 in. (175 mm) 15 ft (4.6 m) or other severe damage (2002b); ACPA (1990b)

Guide to Concrete Overlays 19


Unbonded Concrete Overlays
New unbonded overlay
of Asphalt Pavements
previously called conventional whitetopping

Need for milling determined based


on degree of surface distortions

Existing deteriorated
asphalt pavement

Figure 16. Unbonded concrete overlay of poor-to-


deteriorated condition asphalt pavement

Uses Overlay Process the design of unbonded overlays on asphalt


(not composite) pavements requires special
Unbonded concrete overlays are an excellent PAVEMENT EVALUATION attention, particularly if the unbonded overlay
rehabilitation option for asphalt pavements
An evaluation of the existing asphalt pavement needs to be less than 6 in. (150 mm) thick for
that exhibit signicant deterioration such as
is necessary to ensure it is a good candidate for clearance purposes or other requirements. In
severe rutting, potholes, alligator cracking,
an unbonded overlay, to determine what if any this situation, the existing asphalt pavement
subgrade/subbase issues, shoving, and pump-
preoverlay repairs are required, to determine should be at least 6 in. (150 mm) thick, or a
ing. When properly designed and constructed,
the existing pavements structural contribu- bonded overlay should be considered.
an unbonded overlay will increase the load-
carrying capacity and extend the pavement life tion as a stable platform, and to determine key AASHTO Guide (1993, 1998) and M-E PDG
signicantly. inputs to the overlay design. For example, the provide design procedures. See basic highlights
foundation support value should be determined of and dierences among the various proce-
This type of overlay is designed essentially as a to establish a thickness design that accounts dures in table 8 on page 26.
new concrete pavement on a stable base course, for the contribution of the asphalt layer(s). For
assuming an unbonded condition between the general information on pavement evaluation,
layers. Unbonded concrete overlay projects are Mixture Design
see pages 6 through 9.
typically 4 to 11 in. (100 to 280 mm). (On Conventional concrete mixtures are typically
thinner asphalt pavements [less than 6 in. [150 Asphalt pavements are good candidates for used in unbonded overlays of deteriorated
mm], an unbonded overlay should be at least 6 unbonded overlays if the existing asphalt asphalt. These mixtures can be used with accel-
in. [150 mm] thick, or a bonded overlay should layer(s) can provide, or can be repaired cost-ef- erator admixtures to provide the early strength
be considered; see pages 14 and 15.) Unbonded fectively to provide, a uniform, stable platform required to place trac on the overlay within
overlays can be designed as JPCPs or CRCPs. for the overlay. a short time period. Early opening can also be
aided by use of maturity measurements.
Unbonded concrete overlays typically do not OVERLAY DESIGN
require extensive preoverlay repairs, but spot Joint Design
repairs of certain severely deteriorated areas Existing Pavement as Base
may be necessary to minimize the risk of local- The load transfer design is the same as for new
In an unbonded overlay design, the existing concrete pavements. Doweled joints are used
ized failure in the overlay. asphalt pavement is considered as a stable base, for unbonded overlays of pavements that will
and the overlay is designed similarly to a new experience signicant truck trac, typically
Performance concrete pavement. The design assumes an pavements 8 in. (200 mm) and thicker.
Unbonded overlays of asphalt pavements have unbonded condition between the layers. There
are two approaches to assessing the potential For pavements 6 in. (150 mm) thick or greater,
been successfully used in many states, with over
structural contribution of the existing asphalt a maximum joint spacing in feet of 2 times the
30 years of good to excellent performance in
pavement to the new pavement system. The slab thickness in inches is often recommended
states such as California and Iowa. Uniform
approach in AASHTO Design Guide (1993, for unbonded overlays. A 6 in. (150 mm)
support is an important factor aecting
1998) considers the modulus of subgrade reac- overlay would thus receive a maximum 12 ft
performance.
tion (k-value). The M-E PDG considers both (3.7 m) joint spacing. The maximum recom-
Though this overlay type does not rely on friction and k-value. mended spacing is typically 15 ft (4.6 m). For
bonding, some partial bonding between the pavements less than 6 in. (150 mm) thick,
overlay and existing asphalt pavement may Overlay Thickness the maximum spacing in feet is 1.5 times the
occur and can contribute to better performance Unbonded overlay thicknesses typically range slab thickness in inches. The use of tiebars for
of the pavement. from 4 to 11 in. (100 to 280 mm). However, unbonded overlays should follow conventional
20 Guide to Concrete Overlays
use for pavements 5 in. (125 mm) thick or Milling CONSTRUCTION
more. If surface distortions in the existing pavement Concrete Placement
Using lane tiebars may be appropriate in are 2 in. (50 mm) or greater, milling may be
considered prior to placing an unbonded over- When the surface temperature of the asphalt
open-ditch (or shoulder) sections of unbonded is at or above 120F (49C), surface watering
overlays if the overlay is 5 in. (125 mm) or lay. Milling can (1) reduce high spots to help
ensure minimum overlay depth and (2) remove can help reduce the temperature and minimize
greater. In this category, a no. 4 tiebar (0.50 in. the chance of early-age cracking. No standing
[13 mm]) may be appropriate. The use of signicant surface distortions that contain frac-
tured asphalt material. water should remain on the surface at the time
tiebars in conned curb-and-gutter sections of overlay placement.
should be considered if the overlay is 6 in. (150 Spot milling only signicant distortions,
mm) or greater. Conventional concrete paving practices and
typically 1 to 2 in. (25 to 50 mm), is often ade-
procedures are followed for placing, spreading,
quate. The objective of milling is not to obtain
Drainage Considerations consolidating, and nishing the unbonded
a perfect cross section, and it is not necessary to
overlay. Because of the variation of the thick-
Properly designed, constructed, and maintained completely remove ruts. There is no reason to
ness of concrete, the concrete material is bid on
edge drains help reduce pumping, faulting, and mill o good asphalt that can help carry trac
a volume (cubic-yard) basis. Some states also
cracking. All drainage conduits must have an loads.
include a bid item for placement, measured on
adequate outlet. It is becoming more acceptable
An adequate layer of asphalt (3 to 4 in. [75 to a square-yard basis.
to daylight granular subbase material in lieu of
placing edge drains. 100 mm] minimum) must remain to ensure
that the asphalt will function as a load-carrying Curing
base for the unbonded overlay structure. In Good curing practices are especially critical
Designing Different Sections
general, an unbonded overlay less than 6 in. (150 to thin unbonded overlays because of their
Portions of a project with signicantly dierent mm) thick on an asphalt pavement (not compos- high surface area-to-volume ratio. This is
existing pavement and subbase conditions can ite) requires at least 6 in. (150 mm) of existing accomplished by applying a curing compound
be broken into separate sections and designed asphalt pavement (after milling); if the remain- immediately after surface texturing; if the
to specically address those given conditions. ing asphalt is less than 6 in. (150 mm) thick, a unbonded overlay is 6 in. (150 mm) or thinner,
bonded overlay should be considered. use twice the usual rate of curing compound.
PREOVERLAY WORK It is important to make sure that milling depth The nished product should appear as a uni-
does not compromise the bonding eectiveness formly painted solid white surface, with the
Preoverlay Repairs of asphalt tack lines between existing asphalt vertical faces along the edges of the overlay also
Unbonded overlays generally require only lifts. Therefore, milling should remove asphalt thoroughly coated.
minimal preoverlay repairs of the existing to the nearest tack line.
Joint Sawing
asphalt (table 6). If signicantly distressed areas
are not shifting or moving and the subgrade/ Patch Preparation Timely joint sawing is necessary to prevent
subbase is stable, costly repairs typically are When full-depth concrete patches exist in random cracking. Transverse joints can be
not needed, particularly with an adequately the underlying asphalt pavement, each con- sawed with conventional saws to a depth of
designed overlay. crete patch needs to be isolated to prevent between T/4 (minimum) and T/3 (maximum).
its bonding to the concrete overlay. (Where When there is evidence of some wheel rut-
Direct Placement bonding occurs, the overlay over the patch will ting on the existing asphalt pavement, saw-cut
be restrained dierently than the rest of the depth is of particular concern for unbonded
Direct placement without milling is recom-
overlay over asphalt, potentially resulting in overlays because the distortions in the underly-
mended when rutting in the existing asphalt
cracking.) To isolate the patch, a debonding ing asphalt pavement can eectively increase
pavement does not exceed 2 in. (50 mm). Any
agent, fabric, or other bond breaking material the slab thickness (gure 17). Longitudinal
ruts in the existing pavement are lled with con-
should be applied to its surface. If there are joints should be sawed to a depth of T/3. As
crete, resulting in a thicker overlay above the ruts.
only a few patches, an alternative is to saw the mentioned before, always match overlay joints
overlay around the concrete patch perimeter to the joints in any concrete patches in the
and, if appropriate, to match overlay joints to existing asphalt pavement and cut the joints
patch joints. full depth.
Table 6. Possible preoverlay repairs on
existing asphalt pavement in preparation for Future Repairs
Surface Cleaning
unbonded overlay The recommended repair option for unbonded
Before concrete placement, the asphalt surface
Existing Pavement Possible Repairs to should simply be swept. Remaining small par- overlays is the same as for standard concrete
Condition Consider ticles are not considered a problem. pavements.
Area of subgrade/subbase Remove and replace
failure with stable material; Key Resources
correct water problems ACI Committee 325 (2006); FHWA
Severe distress that results Remove and replace (2002a); ACPA (1998)
in variation in strength of with stable material;
asphalt correct water problems
Potholes Fill with asphalt
Shoving Mill
Rutting 2 in. (50 mm) Mill
Rutting < 2 in. (50 mm) None or mill

Crack width 4 in. (100 mm) Fill with asphalt


Crack width < 4 in. (100 mm) None
Figure 17. Consider asphalt rut depth when determining saw-cut depth (ACPA 1998)

Guide to Concrete Overlays 21


Unbonded Concrete Overlays
New unbonded overlay
of Composite Pavements

Need for milling determined based


on degree of surface distortions

Existing deteriorated
composite pavement

Figure 18. Unbonded concrete overlay


of poor-to-deteriorated condition composite pavement

Uses vide a uniform platform for the unbonded tem. The approach in AASHTO Guide (1993,
overlay and, if not, what actions are necessary 1998) considers the modulus of subgrade reac-
Unbonded concrete overlays are an excellent to obtain that uniformity. In addition, the tion (k-value). The M-E PDG considers both
rehabilitation option for composite (asphalt evaluation determines the existing pavements friction and k-value.
on concrete) pavements that exhibit signicant structural contribution as a stable platform and
deterioration such as severe rutting, potholes, key inputs to the overlay design. For general Overlay Thickness
alligator cracking, shoving, and pumping. information on pavement evaluation, includ-
When properly designed and constructed, Unbonded overlay thicknesses typically range
ing specic information about material-related
an unbonded overlay will increase the load- from 4 to 11 in. (100 to 280 mm). The
distresses, see pages 6 through 9.
carrying capacity and extend the pavement life required overlay thickness is aected by the
signicantly. Composite pavements are good candidates for desired load-carrying capacity and service
unbonded overlays if the existing composite life, as well as the condition of the underlying
This type of overlay is designed essentially section can provide, or can be repaired cost-ef- pavement.
as a new concrete pavement on a stable and fectively to provide, a uniform, stable platform
uniform base course, assuming an unbonded AASHTO Guide (1993, 1998) and M-E PDG
for the overlay. Special consideration should be
condition between the layers. provide design procedures. See basic highlights
given to the following:
of and dierences among the various proce-
Unbonded concrete overlay projects are typi- dures in table 8 on page 26.
The condition of both layers of the compos-
cally 4 to 11 in. (100 to 280 mm). Unbonded
ite pavement
overlays can be designed as JPCPs or CRCPs. Mixture Design
Deterioration of the asphalt surface course
Unbonded concrete overlays typically do not Conventional concrete mixtures are typically
(asphalt is a good reector of problems in
require extensive preoverlay repairs, but spot used in unbonded overlays of deteriorated
the underlying concrete)
repairs of certain severely deteriorated areas composite pavements. These mixtures can be
may be necessary to minimize the risk of local- Existing prole grade line (possible evidence used with accelerator admixtures to provide
ized failure in the resurfacing. of active panel movements) the early strength required to place trac on
the overlay within a short time period. Early
Panel tenting, which may indicate the exis-
Performance tence of a void under the panel
opening can also be aided by use of maturity
measurements.
Unbonded overlays have the potential to
Foundation support value
greatly extend the life of existing composite
Joint Design
pavements. Uniform base support is an impor-
tant factor aecting performance. Though this OVERLAY DESIGN The load transfer design is the same as for new
overlay type does not rely on bonding, some concrete pavements. Doweled joints are used
partial bonding between the resurfacing and
Existing Pavement as Base for unbonded overlays of pavements that will
existing asphalt pavement can contribute to In an unbonded overlay design, the existing experience signicant truck trac, typically
better performance of the pavement. composite pavement is considered as a stable pavements 8 in. (200 mm) and thicker.
base, and the overlay is designed similarly to a
For pavements 6 in. (150 mm) or greater, a
new concrete pavement. The design assumes an
Overlay Process unbonded condition between the layers.
maximum joint spacing in feet of 2 times the
slab thickness in inches is often recommended
PAVEMENT EVALUATION There are two approaches to assessing the for unbonded overlays. A 6 in. (150 mm)
An evaluation of the existing pavement is potential structural contribution of the existing overlay would thus receive 12 ft (3.7 m) joint
necessary to determine whether it can pro- composite pavement to the new pavement sys- spacing. The maximum recommended spac-
22 Guide to Concrete Overlays
ing is typically 15 ft. (4.6 m). For pavements Therefore, it is important to match the overlay CONSTRUCTION
less than 6 in. (150 mm) thick, the maximum joints to the patch joints and to cut the joints
spacing in feet is 1.5 times the slab thickness full depth. If there are many concrete patches, Concrete Placement
in inches. The use of tiebars for unbonded consideration might be given to placing a sepa-
When the surface temperature of the asphalt
overlays should follow conventional use for ration layer.
is at or above 120F (49C), surface watering
pavements 5 in. (125 mm) thick or more.
can help reduce the temperature and minimize
Direct Placement
Using lane tiebars may be appropriate in the chance of early-age shrinkage cracking. No
open-ditch (or shoulder) sections of unbonded Direct placement without milling is recom- standing water should remain on the surface at
overlays if the overlay is 5 in. (125 mm) or mended when rutting in the existing asphalt the time of overlay placement.
greater. In this category, a no. 4 tiebar (0.50 pavement does not exceed 2 in. (5.08 cm). Any
ruts in the existing pavement are lled with Conventional concrete paving practices and
in. [12 mm]) may be appropriate. The use of
concrete, resulting in a thicker overlay above procedures are followed for placing, spread-
tiebars in conned curb-and-gutter sections
the ruts. ing, consolidating, and nishing the concrete
should be considered if the overlay is 6 in. (150
overlay. Because of the variation of the thick-
mm) or greater.
Milling ness of concrete, the concrete material is bid on
a volume (cubic-yard) basis. Some states also
Drainage Considerations If surface distortions in the existing pavement
include a bid item for placement, measured on
Properly designed, constructed, and maintained are 2 in. (5.08 cm) or greater, milling may be
a square-yard basis.
edge drains help reduce pumping, faulting, considered prior to placing an unbonded over-
and cracking. It is becoming more acceptable lay. Milling can (1) reduce high spots to help
ensure minimum overlay depth and (2) remove
Curing
to daylight free-draining subbase material in
signicant surface distortions that contain frac- Good curing practices are especially critical
lieu of placing edge drains.
tured asphalt material. to thin unbonded overlays because of their
high surface area-to-volume ratio. This is
Designing Different Sections Spot milling only signicant distortions, accomplished by applying a curing compound
Portions of a project with signicantly dierent typically 1 to 2 in. (25 to 50 mm), is often ade- immediately after surface texturing; if the
existing pavement and subbase conditions may quate. The objective of milling is not to obtain unbonded overlay is 6 in. (150 mm) or thinner,
be broken into separate sections and designed a perfect cross section, and it is not necessary to use twice the usual rate of curing compound.
to specically address those given conditions. completely remove ruts. There is no reason to The nished product should appear as a uni-
mill o good asphalt that can help carry trac formly painted solid white surface, with the
loads. vertical faces along the edges of the overlay also
PREOVERLAY WORK
It is important to make sure that milling depth thoroughly coated.
Preoverlay Repairs does not compromise the bonding eective-
Unbonded overlays generally require only ness of asphalt tack lines between existing Joint Sawing
minimal preoverlay repairs of the existing asphalt lifts. Therefore, milling should remove Timely joint sawing is necessary to prevent ran-
composite pavement. If signicantly distressed asphalt to the nearest tack line. When milling dom cracking. Transverse joints can be sawed
areas are not shifting and the subgrade/subbase composite pavements, the condition of the with conventional saws to a depth of between
is stable, costly repairs typically are not needed, remaining asphalt surface should be examined T/4 (minimum) and T/3 (maximum). When
particularly with an adequately designed overlay for large fractured or separated layers. If the there is evidence of some wheel rutting on
(table 7). remaining old asphalt is too brittle or broken the existing asphalt pavement, saw-cut depth
up to provide adequate separation, a new sepa- is of particular concern for unbonded over-
Note that concrete overlays will bond with any ration layer should be constructed. Without an lays because the distortions in the underlying
concrete patches on the underlying pavement. adequate separation layer, working cracks from asphalt pavement can eectively increase the
the underlying concrete could cause reective slab thickness (gure 17). Transverse joint saw-
cracking of the unbonded overlay. cut depths for early-entry sawing should not be
Table 7. Possible preoverlay repairs on
existing composite pavement in preparation
less than 1.25 in. (31 mm). Longitudinal joints
for unbonded overlay Patch Preparation should be sawed to a depth of T/3.
When full-depth concrete patches exist in the As mentioned before, always match overlay
Existing Pavement Possible Repairs to
Condition Consider existing composite pavement, each concrete joints to the joints in any concrete patches in
patch needs to be isolated to prevent its bonding the existing pavement and cut the joints full
Area of subgrade/subbase Remove and replace
failure with stable material; to the concrete overlay. (Where bonding occurs, depth.
correct water problems the overlay over the patch will be restrained dif-
Severe distress that Remove and replace ferently than the overlay over asphalt, potentially Future Repairs
results in variation in with stable material; resulting in cracking.) To isolate the patch, a
strength of asphalt correct water problems debonding agent or material, such as asphalt The recommended repair option for unbonded
Reflective faulting or Full-depth repair emulsion coating, needs to be applied to its overlays is the same as for standard concrete
panel tenting surface. If there are only a few patches, an alter- pavements.
Potholes Fill with asphalt native is to saw the overlay around the concrete
Shoving Mill patch perimeter and, if appropriate, to match
overlay joints to patch joints.
Rutting 2 in. (50 mm) Mill
Rutting < 2 in. (50 mm) None or mill Surface Cleaning Key Resources
Crack width 4 in. (100 mm) Fill with asphalt Before concrete placement, the asphalt surface ACI Committee 325 (2006); FHWA
should simply be swept. Remaining small par- (2002a); ACPA (1998)
Crack width < 4 in. (100 mm) None
ticles are not typically considered a problem.

Guide to Concrete Overlays 23


Design of Concrete Overlays
With todays limited highway funding and Overlay System Design the existing pavement structure should be
aging highway network, and given the cost- evaluated for its overall current condition,
eectiveness of concrete overlays for pavement Inputs which will inuence both the selection of over-
maintenance and rehabilitation, it is likely that Regardless of the overlay system and design lay system (bonded or unbonded) and the type,
pavement engineers will be designing concrete procedure used, the analysis begins with location, and extent of any preoverlay repairs
overlays more often and for a greater variety of recognition of a number of common inputs needed, if any.
existing pavements and pavement conditions. to the design process. It is important to rst For a bonded overlay to be a practical solution
This section provides clear, reliable guidance for dene the scope of the intended project and on an existing asphalt surface, at least 3 to 4 in.
designing high-quality concrete overlays and an its intended structural performance require- (75 to 100 mm) of existing asphalt pavement
outline of strategies and resources necessary to ments. Deciding whether the overlay is to last structure should remain after any necessary
implement concrete overlay projects as part of 15 years or 30 years will aect both the extent preoverlay repairs and milling. If the asphalt
an overall pavement maintenance and rehabili- of repairs required on the existing pavement surface is milled, the engineer should imme-
tation program. and the design inputs. These in turn inu- diately inspect the condition of the remaining
ence the thickness, the amount of repair, and pavement. Areas showing spot distress after
The information in this section has been thus the cost of the overlay (gure 19). The
collected from several valuable resources pub- milling should be removed and the thickness
engineer is also required to characterize and of the overlay increased in these locations, but
lished by ACI, AASHTO, FHWA, World understand the existing pavement structure (see
Road Association (PIARC), NCHRP, ACPA, only if it is cost-eective to do so. If not cost-
pages 6 through 9), the anticipated trac load- eective, an unbonded overlay design should
PCA, the U.S. Army Corps of Engineers, ing, and the materials expected to be used. In
Federal Aviation Administration, and various be considered.
some cases, climatic inuences may play a role,
state departments of transportation. Existing particularly with a bonded concrete overlay If the initial evaluation nds the existing
procedures are based on a variety of underly- system. pavement is in poor condition with many
ing assumptions and design strategies. It is localized failures, signicant base failures may
important for concrete overlay designers to Existing Pavement be indicated. Depending on the potential costs
understand the interaction of design with of these repairs, a bonded overlay may not be
both the selection of mixture materials and the Characterization
advisable. An unbonded overlay that is less
construction process. Perhaps the most critical The design and performance of a concrete over- sensitive to the underlying pavement condition
design principle is that the concrete overlay and lay is aected by the condition of the existing may be more cost-eective.
the underlying pavement should be viewed as pavement structure. Although both bonded
a system. and unbonded overlay systems benet from Condition evaluation permits the pavement
the load-transfer capabilities of the existing engineer to determine the quantity and loca-
pavement, bonded overlays are inuenced to tion of preoverlay repair required.
Design Objectives a greater degree by the underlying pavement
condition. In addition, the relative thinness of Structural Considerations
Bonded Overlay Systems
bonded overlays plus the bonds stress on the For unbonded overlays of concrete pavements,
Bonded concrete overlay systems are intended
new overlay tend to make these projects more some agencies note the underlying pavement
primarily to improve pavements that are struc-
challenging than unbonded overlays. joint locations and intentionally place the
turally sound but need increased structural
joints in the new overlay away from those
capacity and/or correction of surface defects. Therefore, eective characterization of the joints such that they are mismatched. The
Functional performance, including tire existing pavement condition is important in rationale for this is that load transfer will be
pavement noise, friction or skid resistance, and selecting the proper type of concrete overlay to improved. Other agencies discount this idea in
albedo, can also be improved through the use build. favor of a more construction-friendly approach.
of bonded overlays.
In this case, joints are simply placed where they
Surface Considerations
would normally be according to the type of
Unbonded Overlay Systems The rst step in designing a bonded overlay design being built. Both strategies have resulted
Unbonded concrete overlay systems are usually project is a thorough characterization of the in good performance.
designed to provide a service life more typi- existing pavement. At the very least, the exist-
cally associated with new pavements. A key ing pavement section should be veried with For bonded and unbonded overlays of exist-
advantage to constructing an unbonded overlay cores or historical records. Sometimes, however, ing asphalt or composite pavements, the
versus reconstruction is the elimination of a the historical records or plans do not represent layer moduli should be determined through
signicant amount of excavation work; thus, a the actual in-place pavement, so eld verica- nondestructive FWD testing. Cores are recom-
greater portion of the available funds are spent tion of the records is important. In addition, mended for all overlay projects that involve
directly on the roadway surface. an existing asphalt surface. If possible, a mea-
sure of the eciency of the joints and other
Unbonded overlays not only provide structural discontinuities to load transfer should also be
enhancement, they have the added benet measured using an FWD.
of eliminating existing surface distresses.
Unbonded overlays are typically designed with When overlaying composite pavements, the
the intent of being able to tolerate excess joint condition of the asphalt layer is a good indica-
degradation, existing cracking, and localized tor of the existing base support. If the joints
failures in the underlying pavement structure. and other discontinuities of the underlying
Proper characterization of the underlying struc- concrete are visible and extremely distressed
ture will result in the best balance between cost or exhibiting evidence of severe faulting, these
and performance. should be characterized. Excessive or visibly
Figure 19. Design factors that affect one large deections under truck loading may
another require attention prior to resurfacing.
24 Guide to Concrete Overlays
It should be noted that random cracks in the departure from the AASHTO Guide (1993, systems should be designed to accommodate
underlying pavement do not necessarily lead 1998) is becoming increasingly common, par- the movements of the joints due to seasonal
to reduction in service life. Many miles of ticularly in overlays. For example, using the changes in pavement temperature. For exam-
unbonded concrete overlays have been built conventional AASHTO Guide (1993, 1998) ple, shorter joint spacing may be appropriate.
that have performed very well with little regard for new concrete pavements, an asphalt layer
or consideration to repairing the cracking in is considered a support layer. The property Curling and warping are also considerations for
the underlying platform. dening this support, the modulus of subgrade pavement designers. Controlling large varia-
reaction, or k-value, describes the response of tions in temperature and relative humidity
Given this basic information about the existing
the material immediately beneath the concrete during construction can help improve overlay
system and then accounting for the possible
pavement. When using the design procedures, performance.
costs of preoverlay repair, the engineer can
it is important to understand at what location
determine the required thickness of the overlay.
in the pavement structure the k-value is being Constraints
considered. In other approaches to design,
Traffic Characterization principally with concrete overlay of asphalt, Potential constraints such as surface drainage
To develop a proper pavement design, the the exural capacity of the asphalt layer is con- should be considered in the design.
anticipated future trac loading should be sidered as a structural component. The specic Curb and gutter (C&G) sections may pose
known as accurately as reasonably possible. contribution of the asphalt layer depends on challenges with respect to how to design a con-
Care must be taken not only to measure or pre- the degree of bond with the concrete. In this crete overlay. Projects might include removal
dict current trac characteristics, but also to case, the k-value would describe the support and replacement of the existing C&G, con-
assign reasonable growth characteristics. provided by the materials beneath the asphalt. struction of an inlay with the nal pavement
A prediction of the number of trucks should be Strength of the concrete is one of the key elevation matching the existing C&G, or even
made over the design life. Measures sometimes design inputs, but this too is often misunder- an encasement of the existing C&G with a new
include a prediction of the number of equiva- stood. The designer should use a strength that system. Barriers and ditches can lead to similar
lent single-axle loads based on the anticipated is consistent with the assumptions of the design design challenges.
trac distribution. This approach is taken method being used. For example, all AASHTO Overhead clearance is also another potential
in AASHTOs Guide for Design of Pavement methods require third-point exural strength in constraint. Depending on the location of the
Structures (1993) and is used by many state 28 days, yet it is not uncommon for designers design, various regulations for minimum over-
departments of transportation. In this case, the to erroneously use the strength found in the head clearance may apply. The nal pavement
designer should not approach trac estimates construction specications. Since this value elevation and thickness may need to be limited
with conservative estimates. It is better to make is often lower, it can result in an unnecessarily or measures taken to raise overhead obstacles.
a reasonable estimate and adjust for uncertainty thick overlay that drives up cost. Alternatively, it may be preferred to conduct
later. full-depth reconstruction or build an alterna-
Some methods require an estimate of the mod-
Alternative mechanistic-empirical pavement ulus of elasticity of the materials. This is often tive section at such locations.
design procedures use a distribution of trac of secondary importance in unbonded overlays Adding new lanes or shoulders can also pres-
loading. This loading describes the number, and has negligible impact in terms of thickness. ent issues unique to concrete pavement design,
weight, and geometries of the associated axle However, this property becomes more impor- especially if there is a change in the underlying
loads. Sometimes this is further distributed by tant in bonded overlay designs. support of the overlay, or if the overlay is to
the time of day and even the season. Highly join a full-depth concrete pavement. Joint load
sophisticated models include the distribution In some mechanistic-based procedures, the
CTE of the concrete is also used. Though the transfer systems are frequently used in these
by lane and the wander of the wheel within the cases. Tiebars are used to help ensure aggre-
lane. eect of this property is increasingly being
considered in thicker overlays and even new gate interlock. Additional measures should be
It is sometimes dicult to obtain information pavements, it can have a much more signi- taken in the design to minimize dierential
at this level of detail. Additional trac charac- cant eect on the thickness of bonded overlay settlement or water inltration at these loca-
terization information quickly crosses a point designs. tions. For the same reasons, intersections and
of diminishing returns where it no longer has blockouts for utilities need to be understood,
signicant impact on the design thickness but In designing bonded concrete overlays for exist- and joint patterns developed that will minimize
will take substantial eorts to characterize. A ing concrete pavements, it is critical that the uncontrolled cracking.
number of typical distributions available in the CTE of aggregates selected for the concrete
overlay mixture design be the same as, or lower When construction will be completed under
M-E PDG (NCHRP 2007) may be adequate trac and certain lanes need to carry additional
for most situations. than, the CTE of the underlying pavement.
This helps ensure that both layers experience trac, various options regarding preoverlay
similar thermal movements, thus reducing spot repairs should be considered. For example,
Material Properties if spot repairs can be made quickly (and, if
stress on the bond between the two layers.
Certain properties of the overlay concrete appropriate, a separation layer can be placed
should be known or estimated prior to the Climatic Factors immediately after the repairs), then it is nor-
design process. This provides the designer mally acceptable to put temporary additional
additional exibility to adjust the designs Overlay system performance depends on cli-
vehicle trac on the existing pavement until
to available material options that can be matic factors, both during construction and
the overlay is constructed.
used to reduce costs without compromising during the service life of the overlay. Relatively
performance. thin bonded overlay sections are more suscep- Another option is to wait and make nal spot
tible to adverse weather conditions that may repairs after the temporary additional traf-
Regardless of the design procedure used, the aect the ability of the concrete to retain mois- c is moved o the existing pavement. This
designer should also dene the degree of sup- ture, prevent excessive heat buildup, or prevent approach should be used only when the extent
port directly beneath the structural layers. In freezing. Materials should be selected that are of additional repairs needed, the additional
terms of what is dened as a structural layer compatible with the anticipated climate and thickness of overlay required, and related costs
(as opposed to part of the support system), freeze/thaw conditions. Joints and load transfer are clearly understood.

Guide to Concrete Overlays 25


Another option is to temporarily close the the thickness. Appropriate selection of these tion techniques that consider one or more of
roadway (preferably during o-peak hours), parameters can build in a predictable level of the parameters.
make the critical repairs and complete the over- risk.
lay at least on one lane, and open it to trac as Multimodal deterioration techniques carry a
soon as possible. number of advantages. They may aid in fore-
Distress Mode casting potential maintenance, and they may
When high superelevation corrections are An understanding of the modes of distress assist in developing more eective and cost-
required, adequate information on the depth of as dened by the design procedures is also ecient designs.
material to meet superelevation is required. The
important. Pavement engineering is currently
type of ll materials to use (concrete, asphalt,
owable ll, cement-treated base, etc.) should undergoing rapid changes in this area. Existing Design Selection
be decided based on the depth of ll, installa- methods in AASHTO Guide (1993, 1998) are
based on a serviceability model. This model In most cases, the designer will have an idea of
tion and construction issues, initial costs, and the likely feasible alternatives based on the ini-
future removal costs. Some projects combine predicts an index or designs for a change in
overlays with full-depth reconstruction to the index under a stated set of conditions. The tial survey of the project. However, in selecting
address extreme superelevations. index describes a general overall condition the nal design, it is important for the engineer
that encompasses many factors associated with to anticipate the condition of the existing sec-
Designers are sometimes charged with mak- tion at the time of actual construction of the
pavement deterioration. These typically include
ing decisions based on limited amounts of new concrete surface. In many cases, construc-
faulting, cracking, patching, and pavement
information. This is particularly true in rehabil- tion will not begin for at least two or three
roughness.
itation project designs. Decisions on the design years. Some degradation of the existing struc-
selection should be logical and defendable. Advancements in computing hardware and the ture should be anticipated and considered in
The designer should be aware of the impact desire to better understand what is occurring as the analysis. Allowing for this continued deg-
that selecting the reliability level can have on pavements fail has led to newer AASHTO and radation in the surface condition, the designer
the nal design thickness. In AASHTO Guide industry-developed methods that, in essence, can begin the process of considering feasible
(1993, 1998), the reliability level and the break apart the serviceability model into its design alternatives using the procedures recom-
overall standard deviation result in an increase individual components. Pavement designs mended in table 8.
in the design trac used in determining are evaluated for multimodal deteriora-

Table 8. Summary of design considerations for different types of concrete overlay systems

Current Includes Joint Spacing


Deficiencies, Shortcomings, k-value
Type Design Design Failure Mode Fiber is a Design
or Items to Note Location
Methods Models Consideration

Bonded Overlays System

AASHTO Design Serviceability The procedure assumes complete bond and does N N Top of
Guide 1993, 1998 (thickness of the new not assess stresses at bond plane. The effective subbase
overlay is equal to the thickness of the existing pavement is based
difference between the on either observed distress conditions or the
thickness of the entire amount of traffic carried to date, which are either
Bonded new pavement needed subjective or uncertain.
Overlays to carry traffic minus the
of Concrete effective thickness of the
Pavements existing pavement)

M-E PDG Mechanistically-based The procedure assumes complete bond. However, N Joint spacing is Top of
multimodal; fatigue driven in the procedure no assessment is made of bond assumed to match subbase
plane limiting stresses. existing structure

AASHTO Design Serviceability The 1993 version does not apply to concrete N N Top of
Guide 1998 overlays bonded to asphalt because it does not asphalt
account for the bond between concrete and
asphalt. However, the 1998 version can account for
bond between the concrete and asphalt, but it does
not account for the short joint spacing in overlays
less than 6 in. thick. In both versions, the composite
k-value is utilized and results in conservative
thickness design.

Bonded ACPA 2008 Mechanistically-based The procedure addresses both bond and the Y Y Top of non-
Overlays (master multimodal; corner crack influence of asphalt fatigure. However, further stabilized,
of Asphalt spreadsheet will bond plane failure and refinements are needed. unbonded
Pavements be incorporated asphalt fatigue base or
into ACPAs subgrade
StreetPave layers
software in the
future)
M-E PDG Mechanistically-based The procedure uses full friction values, which is N Y Top of
multimodal; fatigue driven considered equivalent to bond. User can set the asphalt
period of time of effective bond, but the default
value is only 10 years.

26 Guide to Concrete Overlays


Table 8. Summary of design considerations for different types of concrete overlay systems, continued

Current Includes Joint Spacing


Deficiencies, Shortcomings, k-value
Type Design Design Failure Mode Fiber is a Design
or Items to Note Location
Methods Models Consideration
AASHTO Design Serviceability The 1993 version does not apply to concrete overlays N 1993: N Top of
Guide 1998 bonded to asphalt because it does not account for the asphalt
bond between concrete and asphalt. However, the 1998 1998: Y
version can account for the bond between concrete and
asphalt, but it does not account for the short joint spacing
in overlays less than 6 in. thick. In both versions, the
composite k-value is utilized and results in conservative
thickness designs.
Bonded
Overlays of ACPA 2008 Mechanistically-based The procedure addresses bond, but further refinement Y Y Top of non-
Composite (master multimodal is needed. Influence of asphalt fatigue is addressed, stabilized,
Pavements spreadsheet will but further refinement is needed. The procedure is not unbonded
be incorporated theoretically correct, but has been demonstrated to base or
into ACPAs provide workable reasonable answers that have proven subgrade
StreetPave satisfactory in practice. layers
software in the
future)
M-E PDG Mechanistically-based In the procedure, bond is handled as all or nothing with N Y Top of
multimodal; fatigue allowance for loss of bond over time. Procedure implies asphalt
driven bond is short term. No assessment is made of bond plane
limiting stresses.

Unbonded Overlays System

AASHTO Design Serviceability The 1993 procedure assumes no friction between the N N Top of
Guide 1993, 1998 (thickness of the new overlay and the separation layer. Although the 1998 separation
overlay is equal to the version can account for a bond or partial bond because layer
difference between the it allows for a friction value, it does not allow for loss of
thickness of the entire bond over time. (To account for this limitation, the friction
new pavement needed value is typically set at zero.) Under both versions,
to carry traffic minus the the effective thickness of the existing pavement can
Unbonded effective thickness of be based on observed distress conditions, which are
Overlays of the existing pavement) subjective or uncertain. Unlike the bonded overlay
Concrete design, there are no adjustment factors for durability or
Pavements fatigue damage of the existing pavement because of the
minimum effect on the performance of the new unbonded
overlay. The effective thickness can also be based on the
amount of traffic carried to date.
M-E PDG Mechanistically-based Bond is handled as all or nothing with allowance for loss N Y Top of
multimodal; fatigue of bond over time. separation
driven layer

AASHTO Design Serviceability The 1993 procedure assumes no friction between the N N Top of
Guide 1993, 1998 asphalt pavement and the concrete overlay. In principle, asphalt
the 1998 version can account for friction by assigning layer
Unbonded the appropriate friction factor. In both versions, the
Overlays composite k-value is used and results in conservative
of Asphalt thickness designs.
Pavements
M-E PDG Mechanistically-based In the procedure, bond is typically handled using zero N Y Top of
multimodal; fatigue friction. asphalt
driven layer

AASHTO Design Serviceability The 1993 procedure assumes no friction between the N N Top of
Guide 1993, 1998 asphalt pavement and the concrete overlay. In principle, asphalt
(in addition, the 1998 version can account for friction by assigning layer
ACPA [1998] the appropriate friction factor. In both versions, the
has developed composite k-value is used and results in conservative
Unbonded simple design thickness designs.
Overlays of charts for
Composite selecting
Pavements thickness)

M-E PDG Mechanistically-based In the procedure, bond is typically handled using zero N Y Top of
multimodal; fatigue friction. asphalt
driven layer

Guide to Concrete Overlays 27


Design of Bonded Overlay and proper curing procedures are used, bond bond plane or from failure in the underlying
Systems strength is usually not a problem. However, asphalt layer. Therefore, the most recent revi-
extreme daytime to nighttime temperature sions of the design procedure for this type of
With bonded concrete overlays, the bond overlay reect a weakest link approach, apply-
swings can sometimes trigger premature
between the overlay and the underlying pave- ing probabilistic techniques to all three modes
delamination failures. If temperature dieren-
ment assists the horizontal shear transfer at of failure.
tials in excess of 20F (7C) are anticipated, the
the bond plain. This horizontal shear transfers
section should be protected or paving at night
stresses into the underlying layers, thereby First, design parameters are input into the
should be considered.
decreasing tensile stresses in the bonded over- design model. Then stresses are calculated using
lay. Somewhat dierent considerations are Maintaining the bond is especially critical the corner stress model. From that information,
required depending on if the overlay is bonded during the rst few days when the overlay is strains in the bottom and top of the asphalt
to existing concrete or to existing asphalt. susceptible to curling and warping stresses, layer, plus horizontal stresses inferred at the
However, all bonded concrete overlay systems especially at the pavement edges. Therefore, bond plane, are calculated based on the loca-
depend on the integrity of the underlying the bond must be protected through thorough tion of the composite neutral axis.
pavement. curing practices, minimizing relative humidity
and temperature dierentials between the two Concrete corner stresses are then compared
Bonded Overlays of Concrete against ACPAs 2004 fatigue model for con-
Pavements layers, and keeping early trac away from the
pavement edges until adequate bond strength crete. Strains in the asphalt are compared to
The AASHTO Guide (1993, 1998) procedure Asphalt Institute design fatigue models. Bond
has been achieved (usually when opening
for bonded overlays of concrete pavements plane stresses are evaluated using a horizontal
strength has been achieved).
uses a design deciency or remaining life shear data model based on data obtained from
approach. The mode of failure most commonly Joints in designs of this type are matched to Iowa, Florida, and Colorado studies.
used is serviceability. This is largely due to the existing section. Transverse joints should
the fact that most pavement engineers today be cut full depth of the overlay plus a 0.50 in. The calculated stresses and strains for each
are comfortable with the concept. The exist- (13 mm) and must be as wide as or greater than mode are then compared against the probabi-
ing pavements in these cases have not failed. the crack below the joint in the underlying listic models of each mode to determine which
However, it is assumed that some of the pave- pavement. Longitudinal joints should be cut at factor is the most likely mode of failure, or
ment life has been consumed in either fatigue least T/2. (See miscellaneous details, page 31.) the weakest link, driving failure in the overall
or serviceability, depending upon the design Designs for overlays of existing CRCPs are also system.
procedure being used. possible. In the case of CRCPs, however, there Bottom line: Understanding the interaction
is no need to match the transverse joints since between bond plane stresses and corner break
First, standard design methods are used to
none exist with the exception of terminal joints stresses helps designers optimize joint spacing
determine the required thickness of a new
or lugs. and several other factors in designs for bonded
pavement based on the anticipated trac,
planned materials to be used, and other param- The use of steel reinforcement or dowels is not concrete overlays on asphalt pavements.
eters typically considered in new pavement usually a consideration for bonded overlays on In addition to the probabilistic adaptation of
design. concrete pavements unless the overlay is thicker the mechanistic procedures, new advancements
Having determined the overall required than usual, new shoulders are being tied, or in materials were included, particularly with
pavement thickness, the pavement thickness there is also a desire to retrot load transfer. regard to the inclusion of bers. The eect of
equivalent after adjusting for the life consumed Properly built, bonded overlays can reasonably bers in the models is based on their ability to
of the existing section is estimated. This thick- be expected to provide a minimum service life enhance the fatigue resistance of the concrete.
ness corresponds to the thickness required of 15 years before maintenance is required. The The design procedure for bers is open ended
to carry the number of loadings to failure as rst indication of problems on these overlay in that as new bers are developed and proper-
dened by AASHTO. In the AASHTO Guide projects is usually delamination at the bond ties are established, these can be incorporated
(1993, 1998) and earlier terminology, this is plane, quickly followed by classic fatigue fail- accordingly.
simply the change in serviceability and cor- ure at isolated joint locations. These can be Probably one of the more challenging aspects
responds to the remaining life. Additional repaired using partial-depth repair techniques if in the design of bonded overlays of asphalt is
minor adjustments may also be made having to the underlying slab remains sound. the consideration of the supporting platform.
do with observations of existing pavement con-
For designs of this type, the classic modulus of
dition, but these are somewhat subjective. After Bonded Overlays of Asphalt subgrade reaction or k-value described earlier is
the adjustments, the resulting number repre- Pavements based on the value at the bottom of the asphalt
sents how much eective pavement thickness is A unique design consideration for bonded layer rather than at the bottom of the concrete
still actually available to be further consumed overlays on asphalt pavements is the joint spac- layer.
or used in the new pavement system in addi- ing to mitigate curling and warping stresses
tion to the new overlay. in the bonded overlay. ACPAs original 1998 The joint design of bonded overlays over
design procedure for this overlay type was asphalt pavement is a distinguishing character-
The dierence in the thickness calculated for a
based on a single mode of failurethe corner istic when these projects are placed in the eld.
new pavement and this eective section is the
break. ACPAs 2004 revised procedures incor- The transverse and longitudinal joint spacings
design deciency or the required thickness of
porated probabilistic methods into concrete are always 6 ft (1.8 m) or less in length as
the new section that should be bonded to the
fatigue models, but the procedure for this determined by the design analysis. It is impor-
existing pavement. For further information see
overlay type continued to be based only on the tant that joints in this type of overlay be cut
the AASHTO Guide (1993, 1998).
corner break mode of failure. as quickly as possible to minimize the likeli-
Critical to the performance of this type of hood of curling stresses developing, triggering
overlay is the development of a bond between The corner break model has worked adequately. delamination at the edge of the pavement.
the two layers. Existing design procedures for In recent years, however, it has been recognized Early-entry saws are usually used.
bonded overlays do not specically address that the two most common precursors to fail-
bond strength, treating it primarily as a con- ure for bonded concrete overlays on asphalt Since existing sections of bonded overlays of
struction issue. If the section is built correctly are delamination stemming from failure in the asphalt are fairly young, actual service life has

28 Guide to Concrete Overlays


yet to be determined, but based on 18 years of Existing guidance for the design of each of lays. Some agencies have even had success with
performance data, it appears quite likely that the unbonded overlay types can be found in inlling deteriorated joints with stable material
15 to 25 years of service can be expected from AASHTO Guide (1993, 1998). The selection such as owable mortar.
this type of overlay, provided it is constructed of the load transfer coecient in the AASHTO
properly. This technology continues to evolve procedure should be made with recognition of When an entire concrete pavement has deterio-
and is one of the most dynamic areas of interest the character of the underlying layer in addi- rated severely along the length of the pavement
in concrete paving research at this time. tion to the intended load transfer system for due to movement, it is probably time to recycle
the overlay. Consideration should be given to and reconstruct the entire base. A good option
The design procedure is available from ACPA is to crush the pavement in place and use it as
the underlying structure providing additional
and its chapter/state association network. The an unstabilized (granular) subbase for a new,
load transfer, which is not necessarily true of
procedure will be incorporated in a future ver- full-depth pavement if the existing subgrade is
new concrete pavements. The designer should
sion of ACPAs pavement design software for adequate.
not arbitrarily pick a conservative value, as
streets and roads, StreetPave.
this is not the intent of the design procedure.
Separation layer
Bonded Overlays of Composite ACPAs WinPAS software program (based on
AASHTO Guide 1993) includes an entire sec- All unbonded concrete overlays on concrete
Pavements must be separated from the existing concrete
tion for use in designing these types of systems.
Of all of the designs in the bonded system, the pavement by a stress-relief layer, or separation
design of bonded overlays of composite pave- Care must be exercised to ensure that the saw layer, to prevent bond development. The sepa-
ments is the most complex. However, it is also depth of the unbonded overlay is adequate, ration layer provides a shear plane that relieves
the one with the most potential applications, particularly when the overlay thickness varies, stress and helps prevent cracks from reecting
because many miles of existing concrete pave- such as in super transitions, dropos, etc., or up from the existing pavement into the new
ments have been resurfaced with asphalt. when there is embedded steel. overlay. In addition, the layer prevents bonding
of the new pavement with the existing pave-
Current generally accepted design procedures Unbonded Overlays of Concrete ment, so both are free to move independently.
(AASHTO Guide [1993, 1998]) assume a Pavements
serviceability mode of failure and have treated Over the years, many stress-relief methods
In many cases, an existing concrete pave-
the top of the asphalt layer as a high-strength have been used successfully. The most common
menteven one in poor conditioncan
platform from which the k-value is calculated. stress relief is a thin layer of asphalt material.
provide a cost-eective base for a new concrete
Enhancement from the bond is ignored. When Thickness is not critical, but 1 in. (25 mm)
overlay. This is one reason why rubblizing or
used, these procedures often result in overly is usually adequate to eliminate potential
crack and seat techniques are generally not rec-
conservative designs that far exceed design problems with keying of faulted slabs, local-
ommended; these techniques eectively result
expectations. ized repairs, etc. When constructing CRCP
in the loss of any structural carrying capacity of
the existing pavement. unbonded overlays over both CRCP and
Reexamination is ongoing at this time but
plain jointed pavements, Texas has sometimes
some promise has been shown on work in
Suitability of existing pavement as a base increased the asphalt separation layer thickness
Illinois using minor adaptations to the pro-
The existing pavement is suitable as a base for to greater than 1 in (25 mm).
cedures for bonded overlays over asphalt
pavement. In this approach, the same failure an unbonded overlay if it can meet the desired It is important not to use the asphalt separation
model is used, but the assumption is made design life requirements for the base. The exist- layer as a leveling course. All grade corrections,
that the asphalt layer has the maximum per- ing pavement must be stable and uniform; that including leveling, should be accomplished
mitted thickness of 6 in. (150 mm), which is, it must not experience signicant dierential with the concrete overlay itself.
corresponds to the limits of the current design movement and there should not be large areas
model. The elastic properties of the asphalt sur- lacking adequate structural support. Occasional problems have been noted with
face are used in the model. asphalt stripping within the separation layer
When an entire concrete pavement has begun under repeated loading. This can occur occa-
The advantage of this approach is that it to break up, it is a good indicator of serious sionally with high truck trac volumes in the
allows consideration of bond plane protec- subgrade/subbase problems that need to be presence of water. Usually, the stripping takes
tion and method of preparation, inclusion of addressed before other solutions are considered. several years to develop. The best preventive
bers, interaction between joint spacing and If the subgrade is unstable, it may be time to solutions are the following:
thickness, and considerations for curling and replace the pavement and correct the subgrade/
warping due to use of dierent aggregates. subbase. Using anti-strip additives in the asphalt

Isolated areas of full-depth structural distress Using materials other than asphalt that are
Design of Unbonded Overlay are generally not a problem if they can be not subject to stripping phenomena
Systems repaired cost-eectively before placing the Providing a clear path to allow moisture to
Unbonded overlay designs usually do not overlay. On the other hand, areas of MRD leave without the assistance of pore pressure
consider bond, though in fact some bonding that cause movement from expansion and/or
usually occurs. They are essentially designed as contraction in the existing pavement require Other materials for stress-relief layers are pos-
new concrete pavements, with the pavement careful evaluation. sible and have been used. Recent work in the
being overlaid acting as a base. Adaptation United States and Europe has included the
If MRD-related movement is limited primarily use of geotextiles as a stress-relief layer. If the
of existing design procedures is relatively to the joints (e.g., D-cracking movement), and
straightforward and construction relatively easy. separation layer is particularly thin, attention
if full-depth joint repairs can be justied from should be paid to the potential for keying of
Unbonded overlays are usually designed to a cost perspective, a pavement may still be a
serve 20 to 30 years. the overlay to the existing section, stemming
good candidate for an unbonded concrete over- from existing severe faulting. It is thought that
The newer mechanistic-empirical design pro- lay. Unbonded concrete overlays on concrete the keyed locations may have some potential to
cedures are far better and more theoretically pavements with full-depth structural and/or reect into the new weaker concrete layer early
sound for designs of this type, but these are joint repairs have proven performance records in the life of the section, though not much data
beyond the scope of this guide. as eective bases for unbonded concrete over- exist to conrm or refute this hypothesis.

Guide to Concrete Overlays 29


Joint design saves the costs and avoids the potential prob- from payment for placement. These so called
Due to the high stiness of the underlying lems associated with rubblization. square-yard cubic-yard provisions are some-
platform (the existing concrete pavement) in what out of the norm for concrete pavement
Rubblizing a concrete pavement can result in
unbonded overlays on concrete, it is necessary operations, but they are important in reducing
several problems. First, rubblizing techniques
to shorten joint spacing in the overlay com- the contractors risk and owner cost in bidding
can result in a broad range of sizes of con-
pared with normal designs. The shorter joint the projects.
crete pieces. To provide a uniform base for
spacings accommodate additive stress from
an unbonded concrete overlay, the size of the Unbonded Overlays of Composite
temperature curling combined with loading.
rubblized pieces needs to be a consistent 6 to Pavements
Note that existing AASHTO methods do not
12 in. (150 to 300 mm) in diameter. Second, Unbonded overlays of composite pavements
consider this in design. Rule-of-thumb guid-
the rubblization process can drive concrete follow the same design guidelines as concrete
ance for joint spacing for unbonded overlays
pieces into the subgrade, forcing water upward overlays of concrete pavements. The primary
using these methods is based largely on experi-
and reducing the subgrades stability. The dierence is that the stress-relief layer already
ence (see page 19, table 4, for maximum joint
ability of a particular pavement to withstand exists in the form of the existing asphalt layer
spacings).
rubblization and retain its drainage and sup- of the composite pavement.
Newer procedures, in particular the M-E port functions is typically not known until
PDG, do a much better job of considering the pavement is actually rubblized. Finally,
the relationship between load, joint spacing, rubblization results in the loss of the existing Widening and Lane
type of load transfer, temperature conditions, pavements structural carrying capacity, and Addition Design
and support of the underlying platform. For thus requires a thicker, more costly overlay. Concrete overlay projects provide a good
this reason, these are the procedures of choice opportunity for the widening of an old pave-
and will likely result in more cost-eective For these reasons, rubblizing deteriorated
concrete pavements is not a mainstream rec- ment with narrow trac lanes, the addition of
solutions. new travel lanes, or the extension of ramps.
ommendation for concrete overlays. If it is
Joints in the unbonded overlays can be dow- decided to rubblize, a relatively thick (mini- Adequately designed and constructed widening
eled, plain, or, in a continuous reinforced mum 2 to 4 in. [50 to 100 mm]) asphalt or can improve both faulting and cracking perfor-
concrete overlay, totally eliminated. A few thin granular layer should be constructed on the mance of the pavement.
unbonded concrete overlays (less than 5 in. rubblized pavement. This thick separation layer
[125 mm]) have been built under fairly heavy can help provide more uniform support for Widened slabs should be used with care with
trac situations using very short joint spac- the overlay and reduce the potential for seg- concrete overlays on sti foundations (such
ings, usually 6 ft (1.8 m) or less. The shorter ments of concrete rubble to protrude close to as on concrete pavements) because of the
joint spacings are necessary to reduce the risk or through the surface of the separation layer, increased risk of longitudinal cracking.
of early cracking due to curling and warping resulting in concentrated areas of stress. Some rules of thumb for 3 to 6 ft. (0.9 to
stresses.
Crack and seat has been tried in place of rub- 1.8 m) widening units (illustrated in design
Rubblization and Crack and Seat blization, but because it is very dicult to details, gures 29 to 32) are as follows:
Some agencies have experiemented with achieve uniformity, it is not recommended as Where possible, keep joints out of wheel
recycling severely deteriorated concrete pave- an in-place reconstruction method either. paths, especially for bonded overlays on
ments through rubblization. The practice of
asphalt or composite pavements.
rubblization was developed primarily to pre- Unbonded Overlays of Asphalt
pare concrete pavements for asphalt overlays. Pavements For concrete overlays 5 in. (125 mm) or
The concept was to minimize the potential Unbonded overlays of asphalt pavements can thicker at open-ditch (shoulder) sections,
for reective cracking through the asphalt by address existing sections that have existing tie longitudinal joints with no. 4 tiebars to
breaking the existing concrete pavement into crown or ruts in the surface. Placing the con- prevent pavement separation.
small, fairly uniform concrete pieces that, crete directly on the surface places the thickest
individually, experience little contraction or The width of widening rather than depth
concrete at the points of highest load in the
expansion. has more of a positive eect in reducing
pavement structure and is therefore one of the
stresses in the overlay section.
more ecient designs. If rutting is extreme
Instead of rubblizing, the concrete industry
(greater than 2 in. [50 mm]) or the change Not every detail shown will t a specic proj-
typically deals with deteriorated concrete pave-
in cross section due to crown is signicant, ect. Apply the principles illustrated in the
ments that are uniform and stable by repairing
care should be taken to ensure that the design details to address specic project issues.
isolated areas of full-depth structural distress
plans call for adjusting the sawed joint depth
and then placing an unbonded overlay. This Lane addition design details are illustrated in
accordingly.
process accomplishes the goal of minimiz- gure 33. To prevent cracking related to dif-
ing or eliminating reective cracking. Plus, Due to the variability in thickness across the ferential expansion and contraction between
the pavement owner makes use of the exist- section if placed directly on the asphalt, the a concrete overlay and a full-depth adjacent
ing pavements remaining structural capacity, contract documents should include provi- concrete lane addition, use a butt joint with no
which would be lost through rubblization, and sions for payment for materials separately tiebars.

30 Guide to Concrete Overlays


Miscellaneous Design Details
Various details are illustrated in gures 20 to 33. jointing. It is possible to include an integral
curb and gutter, but this should be balanced
Curbs and Gutters with the extent of this type of section and the
Curb and gutter sections require additional equipment that might be available to con-
details since a decision needs to be made about struct it.

(0.81.1 m)

1.5 in. (38 mm)

Figure 20. Bonded concrete overlay in urban areas where the existing curbs can remain in place (adapted from ACPA 1990b)

Manhole
Figure 21. Concrete overlay
with standard manhole
(0.81.1 m)

Transitions
A concrete overlay design often requires transi- to additional stress, a variety of alternatives
tion details that link the concrete overlay with have been used, including thicker concrete
the pavement structure adjacent to the project sections, conventional reinforcement or wire
length. Since these locations are often subject mesh, and structural steel bers.

Mill and Fill Transitions for Bonded Concrete Overlays


Figure 22. Mill and fill transition for concrete
overlay of concrete pavement (adapted from
ACPA 1998)

(50 mm) min.

Figure 23. Mill and fill transition for concrete


overlay of asphalt or composite pavement
(adapted from ACPA 1998)
(75 mm)

Guide to Concrete Overlays 31


Transition Details for Bonded Concrete Overlays
Figure 24. New transition
tapers used to meet bridge
approach slabs or maintain
clearance under bridges with
bonded overlay of concrete
pavement (adapted from
ACPA 1990b)

Figure 25. New transition


tapers used to meet bridge
approach slabs or maintain
clearance under bridges with
bonded overlay of asphalt
pavement (adapted from
ACPA 1991)
(75 mm)

8 in. (200 mm)

Transition Details for Unbonded Concrete Overlays


Figure 26. New transition
tapers used to meet bridge
approach slabs or maintain
clearance under bridges with
unbonded overlay of concrete
Separation pavement (adapted from
layer ACPA 1990b)

Figure 27. New transition


tapers used to meet bridge
approach slabs or maintain
clearance under bridges with
unbonded overlay of asphalt
pavement (adapted from
ACPA 1991)

Figure 28. Joint detail in


Width of new Note: Overlay joint width shall be equal to or concrete overlay of existing
Overlay joint overlay greater than crack in the existing slab. concrete pavement
Concrete transverse joint
overlay If X is 0.50 in. (13 mm) or greater, the underlying
crack width in the existing slab should be
measured. If crack is 0.25 in. (6.4 mm) or greater,
Saw cut in and existing pavement does not have dowel bars,
existing slab the joints should be evaluated to determine if load
transfer rehabilitation is required to eliminate
Underlying crack
in existing slab faulting. If numerous joints of this type exist, the
existing pavement may not be a good candidate
for a bonded overlay.

32 Guide to Concrete Overlays


Widening Unit for Bonded Concrete Overlays

Figure 29. Bonded overlay of concrete pavement with widening unit Figure 30. Bonded overlay of asphalt or composite pavement with
widening unit

Widening Unit for Unbonded Concrete Overlays

Tiebars stapled to asphalt, if overlay is


< 5 in. (125 mm)
If > 5 in. (125 m), then place tiebar
in the center of the overlay

Keep joint out of wheel path


where possible

Saw cut joint


only if joint is in
the wheel path

Extend tiebar
only if wheel
loads are to be
on concrete
widening

Previously widened with asphalt or concrete

Figure 31. Unbonded overlay of concrete, asphalt, or composite Figure 32. Bonded or unbonded overlay of asphalt or composite
pavement with widening unit pavement (previously widened with asphalt or concrete; to be
widened again with new concrete overlay)

Lane Addition
Figure 33. Unbonded overlay of concrete,
asphalt, or composite pavement with full
Cold joint or
full-depth
concrete lane addition
saw cut
-no tiebar

Guide to Concrete Overlays 33


Concrete Overlay Materials
Decisions about mixture materials are aected Although the use of expedited mixtures and is recommended that the largest practical maxi-
by the type of mixtureconventional or expedited paving practices has become more mum coarse aggregate size be used in order to
expediteddesired for a specic project. In common in bonded overlay projects, there has minimize paste requirements, reduce shrinkage,
addition to the mixture itself, other important been some concern regarding potential detri- minimize costs, and improve mechanical inter-
materials for concrete overlays are reinforcing mental eects of quicker setting cements and lock properties at joints and cracks.
bers, separation materials, dowel bars and tie- faster construction times on long-term durabil-
Although maximum coarse aggregate sizes of
bars, curing compound, and joint sealant. ity of concrete. Thus, it may be that both speed
.75 to 1 in. (19 to 25 mm) have been com-
of construction and long-term concrete dura-
In general, it is better to have a wet, sticky mon in the last two decades, smaller maximum
bility need to be considered during the mix
mixture than a dry one for a concrete overlay. coarse aggregate sizes may be required for con-
design phase of a project. In general, emphasis
The use of high-modulus structural bers can crete resurfacing. For nonreinforced pavement
should be given to using the simplest mixture
improve the fatigue resistance, toughness, and structures, a maximum aggregate size of one-
materials that will provide the desired opening
post-cracking behavior of the concrete and help third of the slab thickness is recommended.
times for a specic project.
control plastic shrinkage cracking.
The use of uniformly graded aggregates reduces
Expedited paving can be achieved not only
shrinkage. This is good practice for all overlays
Type of Mixture through the concrete mixture but also through
but is especially important for bonded overlays
good planning and coordination of all con-
Both conventional and expedited mixtures can of concrete pavements. For bonded concrete
struction activities to minimize downtime.
be used in concrete overlay projects. overlays, well-graded aggregate with proper
cement content will reduce shrinkage and
Conventional Mixtures Concrete Materials curling potential and thus reduce the risk of
Conventional concrete paving mixtures are Concrete materials include cement, supplemen- debonding.
typically used in the construction of concrete tary cementitious materials (SCMs), aggregates, When selecting aggregate for a bonded concrete
overlays. As with conventional concrete pave- water, and admixtures. overlay on an existing concrete pavement, the
ments, an eective mixture design is essential CTE becomes a particularly important param-
to the performance of a concrete overlay. Cementitious Materials eter. Because aggregate composes a majority of
Type I and type II cements are commonly used the concretes mass, its CTE is a good indicator
Each of the components used in a concrete
in concrete mixtures for concrete overlays. of concrete movement due to thermal expan-
mixture should be carefully selected so that the
When high early strength is desired, some sion and contraction. Using an aggregate in the
resulting mixture is dense, relatively imper-
agencies use type III cement, which is more overlay mixture with CTE similar to that of
meable, and resistant to both environmental
nely ground, to promote the development of the existing pavement helps ensure that the two
eects and deleterious chemical reactions over
high early strength. layers move together, thus minimizing stress at
the length of its service life.
the bond line due to dierential movement and
Since conventional type I and II cements are
Most agencies specify a minimum concrete helping to maintain the bond between the lay-
normally adequate, the use of type III cements
strength requirement for their pavements. ers. CTE can be determined using AASHTO
with overlays is normally limited to isolated
Typical values include a 28-day compressive provisional test TP-60 (Coecient of Thermal
areas that require special attention.
strength of 4,000 psi (27.6 MPa) or a 28-day Expansion of Hydraulic Cement Concrete).
third-point exural strength of 650 psi (4.5 As with conventional paving, SCMs normally
MPa). If not similar to the CTE of the underlying
improve durability and can enhance the ease of
concrete pavement, the CTE of the overlay
construction.
Expedited Mixtures should be less than that of the underlying pave-
ment. The overlay surface is exposed to greater
Some states use rapid-strength concrete mix- Aggregates
temperature swings than the underlying pave-
tures with a high cementitious material content Aggregates used in concrete mixtures range ment. Therefore, the lower the overlays CTE,
(though not to exceed 660 lb/yd [299 kg/ from crushed stones to river gravels and glacial the less the dierential movement between the
m]), low water-cementitious materials (w/cm) deposits. To help ensure the longevity of the overlay and underlying pavement.
ratio, and smaller top size aggregate (typically pavement, the aggregate should not only pos-
0.75 in. [19 mm]). sess adequate strength but should also be stable Water-Cementitious Materials
physically and chemically within the concrete
These mixtures can be used with accelerat-
mixture.
Ratio
ing admixtures to provide the early strength Guidance on the selection of the appropriate
required to place trac on the overlay within a Agencies generally require that aggregates w/cm ratio is provided by ACI and PCA. A
short time period. A water-reducing admixture conform to ASTM C 33. Extensive labora- maximum w/cm ratio value of 0.45 is common
is used to reduce the w/cm ratio. The slump tory testing or demonstrated eld performance for pavements in a moist environment that will
range is typically 2 to 3 in. (50 to 75 mm), is often required to ensure the selection of a be subjected to freeze-thaw cycles. However,
which provides good bonding grout. durable aggregate. lower w/cm ratio values are often used for con-
For bonded concrete overlay mixtures, the The maximum coarse aggregate size used in crete overlays to minimize drying shrinkage.
proper cement content, together with well- concrete mixtures for overlays is a function of
graded aggregate, will reduce shrinkage and the overlay thickness. Some thinner concrete Admixtures
curling potential and thus the related stresses overlays may require a reduction in size of the Various admixtures and additives are com-
that can cause debonding. standard aggregate used in concrete paving. It monly introduced into concrete mixtures.

34 Guide to Concrete Overlays


These include the following: Fibers are commonly classied into synthetic, fatigue resistance, greater exural toughness,
steel, and blended types. and improved durability. Additional benets
Air entrainment protects the hardened con-
include improved impact, abrasion, and shatter
crete from freeze-thaw damage and deicer
Synthetic Fibers (Micro and resistance.
scaling. However, air entrainment also helps
increase the workability of fresh concrete, Macro)
signicantly reducing segregation and bleed- Polypropylene microbers are produced either Separation Layer
ing. The typical entrained air content of as cylindrical monolaments or ne brils Materials
concrete for overlays is in the range of 5 to 7 with a rectangular cross section. Polypropylene A separation layer is an important feature of
percent. micro bers can be in monolament, multila- unbonded concrete overlays on existing con-
ment, or brillated form. At low dosage rates, crete pavements. The performance of these
Water reducers are added to concrete mix- microbers are eective in controlling plastic
tures in order to reduce the amount of overlays depends largely upon using a separa-
shrinkage and settlement cracking. The bril- tion layer to separate the two layers.
water required to produce concrete of a lation process greatly enhances the bonding
given consistency. This allows for a lower- between the concrete and the polypropylene The separation layer performs two functions. It
ing of the w/cm ratio while maintaining a bers and can provide increased load capacity provides a shear plane that helps prevent cracks
desired slump and thus has the benecial in pavements that have already cracked. from reecting up from the existing pavement
eect of increasing strength and reducing into the new overlay. It also prevents bonding
permeability. Polypropylene macrobers are coarse bers of the new concrete overlay with the existing
that allow greater surface area contact within concrete pavement, so both are free to move
SCMs such as y ash and ground, granulated the concrete, resulting in increased interfacial
blast-furnace slag (GGBFS) may be added independently.
bonding and exural toughness. Polypropylene
to concrete mixtures. These materials may macrobers can be used as secondary rein- The most common and successful separation
be added to the portland cement or partially forcement and can provide greater post-crack layer used in the United States is a conven-
substituted for a percentage of the portland strength and concrete slab capacity (Roesler tional asphalt surface mixture. On most
cement. 2004; 2007). Additional benets include projects, a nominal 1 in. (25 mm) thick layer
Since SCMs can retard set time in cold improved impact, abrasion, and shatter provides adequate coverage over irregularities
weather, some agencies restrict their use in resistance. in the existing pavement. The thickness can be
colder seasons of the year. However, SCMs slightly increased when irregularities are large
Polyester bers are available only in monola- enough to impact placement operations.
can aid construction during hot weather by ment form. They commonly have relatively low
extending the placement time. ber content and are used to control plastic The separation layer does not provide signi-
SCMs typically improve the workability of shrinkageinduced cracking. cant structural enhancement; therefore, the
the mix and also increase concrete durability; placement of an excessively thick layer should
they also can increase the long-term strength Steel Fibers be avoided.
of the concrete, although the short-term Steel bers are primarily made of carbon steel, When a pavement is poorly drained and experi-
strength may be lower. although stainless steel bers are also manu- ences heavy truck trac, scouring (stripping)
factured. Perhaps the biggest advantage of of the asphalt separation layer may occur. In
In addition, y ash and GGBFS are eective
steel bers is their high tensile strength and an eort to reduce the scour pore pressure
in reducing alkali-silica reactivity.
their ability to bridge joints and cracks to and increase stability, some states modify the
provide tighter aggregate interlock, resulting asphalt mixture to make it more porous. In
Fiber-Reinforced in increased load-carrying capacity. Steel FRC particular, the sand content is reduced and
Concrete pavements exhibit excellent toughness and pre- the volume of 0.38 in. (10 mm) chip aggre-
and post-crack capacity. gate is increased. This modied mixture has a
Fiber-reinforced concrete (FRC) mixtures have
been used in concrete overlays. The principal lower unit weight and lower asphalt content,
The aspect ratio is an important parameter
reason for incorporating bers is to create con- and is comparable in cost with typical surface
inuencing the bond between the concrete and
crete composites that are more durable than mixtures.
the ber, with longer bers providing greater
plain concrete. FRC can provide improved ex- bond strength and toughness. Steel bers may Some states have used a few other separation
ural ductility and toughness, fatigue capacity, also have certain geometric features to enhance layer materials, including bituminous material,
and abrasion and impact resistance. FRC inhib- pullout or anchorage within the concrete mix. polyethylene sheeting, wax-based curing com-
its crack development and slows crack growth, These features may include crimped or hooked pounds, liquid asphalts, and hot-mix asphalt,
while it provides increased load capacity in ends or surface deformations and irregularities. with mixed results:
pavements that have already cracked. Another
benet is reduced spalling at contraction joints Some concerns have been raised regarding the Less than 1 in. (25 mm) thick asphaltic
by keeping them tighter and more stable. FRC corrosion of steel bers, particularly in pave- separation layers, such as slurry seals, have
mixtures are used in both bonded and thin ments exhibiting cracks wider than 0.004 in. worked well in some cases, but are gener-
unbonded overlays. (0.10 mm). ally not recommended because they do not
eliminate mechanical interlock, they erode
A wide variety of ber materials has been used Blended Fibers near the joints, and they do not eectively
to reinforce concrete. In the United States, Blended ber systems combine macrobers or separate the two layers.
steel and synthetic bers (e.g., polypropyl- steel bers with microbers.
ene, polyester, or nylon) are commonly used. Polyethylene sheeting and curing com-
Fibers have been used on multiple U.S. paving The microbers in these systems provide pounds are also not recommended. They
projects over the last several years. For bonded resistance to plastic shrinkage and settlement do not prevent working cracks from reect-
overlays, polypropylene bers have been used cracking, while the macrobers or steel bers ing through the overlay (ACI Committee
most commonly in recent years, and their use is provide long-term secondary reinforcement. 325 [2006]), and they trap moisture in the
increasing steadily. Blended systems provide higher levels of concrete, which may accelerate freeze-thaw
damage.

Guide to Concrete Overlays 35


Some states, such as Missouri, are conducting Incidental Materials are typically spaced at 30 in. (76.20 cm)
research on the use of geotextile materials as apart, but greater spacing may be used in
a separation layer. For several years, Germany Other materials used in the construction of some cases. When small panel sizes are
has used a geotextile material between cement- concrete overlays are essentially the same as designed, tiebars are typically not used.
treated base courses and concrete pavement used in conventional concrete pavement con-
with very good results (gures 34 and 35). The struction, as summarized below: Joint sealant materials, if used, are either
thickness of the geotextile is typically about hot-poured rubberized materials conforming
Dowel bars are typically billet steel, grade to ASTM D6690, AASHTO M301, or per
0.25 in. (6.3 mm) (appendix B).
60 bars that conform to ASTM A615 or normal design; silicone materials conform-
According to Leykauf and Birmann (2006) of AASHTO M31. The dowel bar size, layout, ing to a governing state specication; or
Munich University of Technology, geotextiles and coatings should be selected for the spe- preformed compression seals conforming to
have provided uniform, elastic support of the cic project location and trac levels. ASTM D2628, AASHTO M220, or a gov-
concrete slab, hence reducing stresses due to erning state specication.
Dowels should be positioned in the middle
temperature and moisture gradient. They also
third of the slab. Target the average thickness When small panel sizes are constructed, seal-
reduce pumping processes and prevent origi-
and avoid multiple basket heights. ant is often not used.
nation of reected cracks from bonded base
courses without notching them. In some cases, because of the underlying Curing materials may include wet burlap,
support of the old pavement, dowels are not polyethylene, or liquid membrane-forming
Leykauf and Birmann (2006) also state,
used or their size is reduced. curing compounds that comply with ASTM
Concrete roads with a separation layer of
geotextiles are especially recommended for Tiebars are typically billet steel, grade 40 C309 or AASHTO M148.
concrete overlays on old concrete pavements, in bars that meet ASTM A615 or AASHTO
tunnels and on rigid base courses. M31 specications. No. 5 deformed tiebars Key Resources
Smith et al. (2002)

Figure 34. Close-up of geotextile fabric


(Photo courtesy of Prof. Gunther Leykauf,
Technische Universitat Munchen)

Figure 35. Roll of geotextile fabric being placed prior to overlay


(Photo courtesy of Prof. Gunther Leykauf, Technische Universitat Munchen)

36 Guide to Concrete Overlays


Managing Concrete Overlay Work Zones under Traffic
This section discusses several issues related to Table 9. Concrete overlay work zone management considerations
work zone management, including clearances,
trac control, and staging. Areas of Consideration Items to Consider

Traffic Management 1. Capacity analyseslanes required, length of queues anticipated


Objectives of Work Zone 2. Time restrictionspeak hours, seasonal peaks
Management 3. Limits to work areas
4. Capacity of detour routes
Managing work zones for concrete overlay 5. Work vehicle access and worker parking
projects is no more challenging than for any 6. Bicycle and pedestrian traffic
other paving project under trac, as long as
7. Warning sign locationsdetours, long queues, intersecting roads
certain straightforward practices are followed.
8. Railroad crossings and train schedule
Eective work zone management for all 9. Nighttime delineation and illumination
concrete pavement projects, including concrete 10. Signals, turning lanes, bus stops
overlays for maintenance and rehabilitation, 11. Traffic serviceresidential/business
involves designing a comprehensive plan of 12. Future rehabilitation
action that balances several equally important
priorities (gure 36): Concrete Pavement 1. Accelerated constructionplanning, concrete materials, construction
Construction requirements, curing, jointing
Ensure safety of workers and motorists
Requirements 2. Opening to trafficmaturity, pulse velocity, strength requirements,
Minimize inconvenience to the traveling cure time
public
3. Rehabilitation considerations
Maintain or enhance cost-eectiveness of the
4. Off-peak traffic hours for increased production
project
5. Phasing of worklength of work zone, project limits
Follow best construction practices to maxi-
6. Special conditions such as dropoffs, sign bridge installation, etc.
mize pavement performance
7. Pre-paving and paving restrictions
The basic elements of these priorities are dis- 8. Special contract provisions needed
cussed below. A checklist of considerations in 9. Short duration closures anticipated
overlay work zone management is provided in 10. Temporary drainage
table 9. 11. Lights for night work
12. Temporary roadway lighting
Safety
Safety 1. Work zone crash rates
Promoting worker and traveler safety should
2. Traffic management strategies
be an integral, high-priority element of every
3. Interstate system
project, from planning through construction.
4. Congestion
Roadway users (vehicles, bicycles, pedestrians,
etc.) must be clearly guided by trac control 5. Nighttime
devices and markings while approaching, pass- 6. Large trucks
ing through, and leaving temporary trac 7. Workers on foot
control zones. Trac control elements should 8. Pedestrians
be regularly inspected. All people involved 9. Local experience
in selecting, placing, and maintaining work Constructibility 1. Structural capacity of bridges, shoulders, and pavement
zones should be trained in safe trac control 2. Timing of phases versus probable starting date
practices.
3. Strategy to allow contractor to finish project
The exposure of highway workers and travelers 4. Status of existing traffic control devicessignals, signs, railroad
to safety risks can be minimized by reducing crossings, etc.
5. Wintertime restrictionssnow removal, etc.

Safety of the Emergency Planning 1. Incident management plans


traveling public and
highway workers 2. Emergency medical assistance
3. Accidents, breakdowns, tow trucks
4. Severe storms and storm water runoff
5. Emergency closures
6. Utility interruptions
Minimal Successful Cost-
Cost-
7. State police
disruption work zone effective
to traffic management solutions 8. Local law enforcement

Public Information 1. Public informationpublic hearings, media, motorist service agencies,


Coordination residents, local businesses, motor carriers
2. Local officialspolice, fire, hospitals, schools, environmental agencies,
Superior utilities, toll facilities, ferries, railroads, airports
pavement 3. Special events
performance
4. Intra-agency coordinationmaintenance crews, permits section,
adjacent project
Figure 36. Managing work zones effectively 5. Transit
involves balancing several priorities
Guide to Concrete Overlays Adapted from multiple sources 37
the frequency that work zones are established, When overlay projects are constructed under barrierspaving equipment clearances may
reducing the length of time work zones are in trac, space and trac capacity considerations need to be reduced. These situations are fairly
place, and where possible reducing the volume impact three primary elements of a work zone common with all maintenance and rehabilita-
of trac through the work zone. management strategy: construction clearances, tion projects. With adequate planning, zero
trac control, and project staging. paving equipment clearance can be achieved
A detailed emergency response plan should
to accommodate specic project needs, such
be in place to deal with any injury that might
Paving Equipment as paving next to a median barrier (gure 38).
occur in the work zone. The plan should include
(As with asphalt paving, zero paving equipment
protocols for emergency medical services. Clearances clearance in concrete paving does not include
When work zones are set up under trac, the 6 to 8 in. [150 to 200 mm] for the paving
Traffic Flow adequate clearance must be provided to accom- machine edge form.)
Minimizing disruption to trac in work zones modate the paving machines tracks and frame,
requires a proactive, partnership approach to as well as the paving stringline. For a standard Reducing Clearance with Paver
work zone management. By involving ocials concrete paver operation, the typical paving Modifications
and the public during early stages of project equipment clearance is 4 ft (1.2 m) on each
Paving machine manufacturers have developed
planning, the designer and contractor can gain side of the paving machine (3 ft [0.9 m] for
special paving machines designed to execute
a better understanding of trac issues related the paver track and 1 ft [0.3 m] for the paver
minimum clearance projects (gure 38). In
to the project. As a result, they can develop bet- control stringline) (gure 37). Paving equip-
addition, many contractors around the country
ter, more coordinated solutions. In addition, ment clearances do not include space for trac
control devices or workers or space for highway have made various modications to standard
broadly publicizing the work zone well before
users (vehicles, pedestrians, bicycles, etc.). pavers to achieve zero clearances (gure 39).
construction begins helps ensure that motorists
Additional clearances needed should be deter- Instead of specifying a certain manufacturers
have every opportunity to plan travel routes
mined on a project-by-project basis. machine, owner-agencies are advised to dene
and times accordingly.
the maximum allowable clearance zone and let
In some situationsnarrow roadways, the contractor select or modify the equipment
Cost-Effectiveness minimum or no shoulders, trac in adjacent and operation to meet project needs.
Strategies used to manage trac in work zones lanes, obstacles like retaining walls or safety
can signicantly aect project costs. Therefore,
it is important to carefully evaluate road use Figure 37. Typical clearance
demands and select the most cost-eective on a concrete overlay project
strategies to accommodate the demands. For (Photo courtesy of Matt Ross,
example, partly or completely closing a work P.E., Missouri/Kansas Chapter
zone to trac can help minimize trac man- ACPA)
agement costs, but when a roadway cannot be
closed, higher costs are probably justiable.
Possible ways to manage costs include, where
possible, reducing trac volume through work
zones, reducing the frequency and duration of
work zones, and minimizing detours and cross-
over construction elements.

Pavement Performance
Figure 38. A three-track,
To ensure that concrete overlays provide
zero-clearance paver placing
durable, long-lasting maintenance and reha-
concrete along a median barrier
bilitation solutions, basic good design and (Photo courtesy of Kevin Klein,
construction practices must be followed. These Gomaco)
include designing an overlay that is appropriate
for the situation, accomplishing appropriate
preoverlay repairs and preparation of the exist-
ing pavement, and using good construction
practices like proper jointing and curing. With
thorough planning, work zones can be man-
aged to accommodate these activities without
sacricing project safety, trac ow, or cost-
eectiveness.
Figure 39. A typical, four-track
paver modified to three tracks,
Work Zone Space providing zero clearance in a
Considerations curb-and-gutter situation in
Oklahoma (Photo courtesy of
Constructing any overlay requires occupy-
Jim Duit, Duit Construction
ing some part of the traveled portion of the Co., Inc.)
roadway to accommodate work activities and
provide trac control and other safety provi-
sions for workers and motorists. This will aect
trac capacity through the work zone for the
duration of the work activities. In some cases,
safety considerations may require partial or
even complete closure of the roadway.
38 Guide to Concrete Overlays
Reducing Clearance with overlays. See, in particular, chapter 4 on trac If deciencies will occur, the work zone man-
Alternative Control Options control strategies for concrete pavement. agement plan must address them to prevent
congestion and increased project costs. For
Alternative paving control options may be used ACPAs handbook explains that, as trac example, the plan might include variable work
to reduce clearance as long as smoothness crite- volumes increase, the window of time where times (e.g., o-peak hours, nighttime) or con-
ria are met. For example, an average proler, a the trac demand is below the capacity of the struction sequencing to meet production and
movable stringline, or a ski can be used in tight work zone will become smaller. When the time safety demands.
areas, each relying on the smoothness of an is too short to allow for daytime work, the
existing lane to ensure a smooth prole on the work is usually moved to nighttime. In some An increasingly popular alternative is to com-
new pavement (gures 40 and 41). Use caution cases even the nighttime hours are restricted. pletely close the facility briey to complete
when allowing heavy truck trac on part of the project or a critical phase of the project. In
the lane being overlaid because vibrations may For situations such as recreational routes, some cases, this alternative has reduced the over-
aect results, particularly of bonded overlays. the peak trac hours may be on Friday and all project duration signicantly.
Sunday afternoon. The allowable window of
Advanced technologies may eventually time for road construction in this case may be
eliminate the need for stringlines or other noon Monday to 6:00 p.m. Thursday. Concrete Overlay
physical control methods. Three-dimensional
The limitation of work hours and the number
Staging
equipment controls, for example, are already A common misconception is that construct-
available. Guidance technologies based on of lanes closed results in a piecemeal type of
project that can increase the duration of the ing a concrete overlay on a two-lane roadway
global positioning systems (GPS) are showing requires closing the roadway for the duration of
great promise, although more development is project as much as 100 percent or more. This
approach also requires planning exible trac the project. Many easy-to-use approaches exist
necessary before they are accurate enough to for staging concrete overlay projects in almost
allow contractors to consistently earn smooth- control strategies that can be adjusted for peak
hours or days when the roadway is entirely any situation.
ness incentives.
open to trac. For example, concrete overlays can be con-
Other Clearances For roadways under high trac demands, a structed on four-lane divided roadways
trac analysis should be conducted to identify without crossovers and head-to-head trac.
In addition to paving equipment clearances on Trac can be allowed on the new pavement
all construction operations, clearance must be which parts of the roadway can be occupied
by construction and public trac at any point within 24 hours of construction by protecting
allowed for trac control devices and construc- the concrete as described under Accelerated
tion workers. The width of this clearance zone during the construction time period. The goal
is to identify congestion points that could aect Construction beginning on page 54.
varies depending on adjacent trac volume,
trac speed, and agency requirements. In addi- trac capacity and safety as well as construc- A system approach that considers work zone
tion, the location of workers with long-handled tion production levels. safety, trac requirements, and key elements of
oats should be restricted to the non-trac Such an analysis answers specic questions: construction should be used in staging concrete
side of the pavement. overlay projects for fast, cost-eective construc-
Is the capacity of the existing roadway ade- tion projects. Some common scenarios are
Construction Traffic quate for existing trac levels? described below.
Control How will capacity be aected if some lanes
Two-Lane Highway under Traffic
All work zone trac control, including speed are shut down and other lanes kept open?
When staging a two-lane concrete overlay
restrictions, should follow jurisdictional Comparing existing trac levels to the project under trac, the widths of the vehicle
requirements and the latest MUTCD (FHWA under-construction capacity, are there any lane and of the construction lane must be
2003b). The fundamental principles of work capacity deciencies? considered.
zone trac control are given in Section 6B. In
addition, the Trac Management Handbook The analysis should consider both the lateral Typically, the minimum desirable width for the
for Concrete Pavements Reconstruction and clearance (availability and need) and the length vehicle lane is 11 ft (3.4 m). Some jurisdictions
Rehabilitation (ACPA 2000a) is a good refer- of roadway needed to provide ecient, cost- may allow as little as 10 ft (3.1 m) under cer-
ence on trac control strategies for common eective paving production. It must also factor tain circumstances, for example, in very short
roadway rehabilitation categories, including in peak and o-peak trac ows. segments (less than 100 ft [30.5 m]).

Figure 40. Controlling paving profile using a moveable stringline Figure 41. Controlling paving profile using a paver ski on the adjacent
on the adjacent lane (Photo courtesy of Kevin Klein, Gomaco) lane (Photo courtesy of Wouter Gulden, P.E., Southeast Chapter ACPA)
Guide to Concrete Overlays 39
The width of the construction lane depends on Continuous Production Leaving gaps in or staggering construction
several factors, including thickness of overlay, Pilot cars can be used to keep one lane of traf- areas (that is, leap-frogging over a section of
maximum allowable centerline or edge llet, c adjacent to the paving operation open at all pavement) can allow the contractor to stage
slope of llet, type of trac control device, times. To minimize traveler delays, many juris- work in ways that use crews and machinery
type of paving machine, and automobile and dictions limit the length of such work zones. more eciently. This may require two sepa-
truck trac. Contractors must balance those limitations rate trac control systems.
Concrete overlays can be successfully con- with their need for continuous production so Using multiple paving machines may make
structed under trac with conventional paving that crews do not stand idle at any time. This it possible to stagger work zones more
machines; in some cases where minimum clear- requires detailed planning and staging. eciently.
ances are required, minor adjustments may be Following are some considerations for staging a The direction of the initial pour is important
necessary. project using pilot cars cost-eectively: to make sure the paver ends each pour in the
The length of the temporary trac control Typically, a contractor can prepare and pave optimum position to begin the next.
zone is another important factor. Typically, the 4,000 to 5,000 ft (1,219 to 1,525 m) in one
length of trac control zones is limited to 0.25 lane per working day, roughly one short lane Two-Lane Highway Expanded to
mi (0.40 km), and a pilot car is not used. In mile. Three Lanes under Traffic
rural areas, however, it may be more feasible
Constructing an edge llet may make it pos- When constructing a concrete overlay and
to pave longer sections. In such situations, a
sible to open the lane to trac before the widening a pavement from two lanes to three
pilot car and aggers are often used and the
shoulder backll is completed. lanes, some states require that the remaining
maximum length of the trac control zone is
shoulder after pavement widening be at least
established by the jurisdiction. A new overlay can be opened in 24 hours or 4 ft (1.2 m) wide. Therefore, using both exist-
Other trac control measures, including less. ing shoulders for staging and widening has
aggers and trac control signals, may be war- distinct advantages.
ranted according to jurisdictional requirements.
When granular shoulders of adequate widths
are available to accommodate a conventional
paver, it is recommended that the shoulders be
treated with 3 ft (0.9 m) of calcium chloride
before opening the road to vehicular trac.
The calcium chloride treatment is a successful
way of stabilizing the shoulder in case errant
vehicles leave the pavement. Also, vertical traf-
c control panels may be used to designate the
pavement edge (gure 42).
If shoulder paving is part of the project, the
trenching of paved shoulder base widening
should be completed in the rst stage along Vertical traffic
with surface preparation of the initial lane to be control panel
overlaid. Once this is completed, this lane can
be opened to trac and the adjacent lane can
be prepared for paving. Calcium chloride treatment
During the second stage, the second lane is
paved. A thickened edge may be paved if pave-
ment widening is part of the project. Figure 42. Vertical traffic control panels may be used to mark pavement edge dropoff
(Photo courtesy of Dan DeGraaf, P.E., Michigan Concrete Paving Association)
The third stage includes opening the newly
placed overlay to trac and shifting trac
control for work on the opposite lane. The nal
stage includes placing pavement markings, Traffic control device
Traffic control device
rumble strips if shoulders are paved, and nal Full-depth saw cut
before stage 3
shouldering. (match existing
2 in. Saw cut between
centerline) stages 2 and 3
Some possible two-lane staging options are pre- (50 mm)
Overlay
sented in gures 44 through 46. 2 in.
(50 mm)
T/2 or greater
Fillet T
Fillets
Match existing centerline
If two-way trac is desired on the roadway for overlay on concrete
after the rst lane is cured, and the overlay Unbonded separation layer
thickness is greater than 2 in. (50 mm), con-
Bonded and unbonded overlay 24 in.
struction of centerline and outside edge llets Unbonded overlay greater than 4 in. (100 mm)
(50100 mm) thick
may be an option (gure 43). Outside edge
llet should be considered if shouldering will 1 Traffic control and slope of fillet depends on jurisdictional requirements.
not be completed before opening the roadway
to trac. Figure 43. Centerline fillets for overlays 2 in. (50 mm) or greater

40 Guide to Concrete Overlays


First, base shoulder widening on one half Four-Lane Divided Highway A possible staging sequence for this type of
of the road is accomplished. The overlay is without Crossovers and under construction is shown in gure 48. Because
constructed in halves similar to the two-lane each half of the four-lane divided highway is
staging example. The existing shoulder is Traffic treated like a two-lane section, any of the stag-
trimmed and properly compacted. The rst Staging a concrete overlay on a four-lane ing sequences from gures 44 through 46 may
concrete overlay section is then placed with a divided highway is similar to that on a two-lane be used on either half of the section.
thickened edge. The other half of the overlay highway. Both two-lane sides may be under
can be placed directly on top of the base shoul- construction at the same time, and crossovers
der constructed rst. are eliminated. By eliminating crossovers, proj-
ect costs are reduced and safety is increased.
A possible staging sequence for this type of The existing shoulders usually provide adequate Key Resources
construction management is shown in room for the paver track, stringline, and work-
gure 47. FHWA (2003b)
ers between the paver and trac.

Guide to Concrete Overlays 41


COMPLETED OVERLAY (Two-Lane Roadway with Paved Shoulders, Conventional Paver)

Applied to:

;Bonded concrete overlay of concrete pavements ;Unbonded concrete overlay of concrete pavements
;Bonded concrete overlay of asphalt pavements ;Unbonded concrete overlay of asphalt pavements
;Bonded concrete overlay of composite pavements ;Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface, prepare for overlay, and construct base shoulder
widening and separation layer
Install traffic control and close the left lane. Follow Prepare for shoulder widening by trenching the
jurisdictional requirements for traffic control. Check existing shoulder and trimming to the specified
with jurisdiction regarding allowable lane closure width. The trench should be rolled and compacted
length. If surface repair and preparation for the as necessary to obtain a firm and stable platform as Typically
specified in the contract documents. A continuous less than
overlay are minimal, then slow-moving traffic control 0.25 mi
may be appropriate. Closing the lane may require progression approach with the shoulder trencher (0.40 km)
additional traffic control (e.g., signals, flaggers, and/or and placement of the base shoulder widening without
pilot cars). material is encouraged. pilot car

Repair the surface as appropriate. Prepare the surface Construct separation layer (only for unbonded
for the overlay (or, in the case of concrete overlay on overlay on concrete).
concrete, the separation layer) as described in the
contract document.

STAGE 2. Construct right shoulder and concrete overlay

Shift the traffic control to the left lane and close the should be additionally restricted adjacent to paver
right lane to traffic. The length of the closure will when clearance between the paver and vehicle
depend on the jurisdictions maximum closure length traffic is tight.
with pilot car. Traffic controls and traffic control Construct concrete overlay on the existing
signals will be based on jurisdictional requirements. pavement. Complete right PCC shoulder widening
Repair and prepare the surface for the overlay or the with the overlay. Bull float work shall operate from
separation layer and subsequent overlay as described the outside shoulder only.
in the contract documents. Construct separation layer Early entry saws are encouraged and should follow
(for unbonded overlay). the depth as described in this manual.
Normal space for the paver stringline is 11.50 ft The X dimension between the roadway centerline
(0.300.46 m) and the paver track is a minimum and vertical panel is for the paving machine track
of 2.503 ft (0.760.91 m). 1 ft (0.3 m) incremental and stringline.
encroachment reduction (up to 2 ft (0.6 m) total) is
common through typical machine adjustment. Speeds

STAGE 3. Construct left lane concrete overlay

Close the opposite lane to traffic and place the If the outside edge dropoffs at the shoulder exceeds
concrete overlay according to contract documents, the jurisdictional allowance for a 1:1 fillet, then
using the same procedures as described in stage construct the granular shoulders in this stage.
2. Note that stringline may not be necessary for the Complete shouldering. Install (mill) rumble strips
right edge of the paving when the paved overlay in the paved shoulders and complete pavement
constructed in stage 2 is used as the paver control in marking and regulatory signing in accordance with
this stage. If the right stringline is not used, the X contract documents.
dimension could possibly be reduced to 3 ft (0.9 m).

Figure 44. Overlay of two-lane roadway with paved shoulders (conventional paver)

42 Guide to Concrete Overlays


LEGEND
Remaining Paved Paved Remaining
shoulder shoulder shoulder shoulder
12 ft (3.7 m) lane 12 ft (3.7 m) lane Stage work area
Pavement (Typical) (Typical)
marking Pavement Concrete
Rumble strip marking
Finished Base shoulder widening materials
shoulder (e.g., cement-treated base, porous
concrete, roller compacted con-
Saw joint crete (RCC), asphalt, or concrete)
12 ft (3.7 m) existing lane with tied steel Granular material
Existing pavement
Concrete overlay
Separation layer Existing subbase
(only for unbonded overlay on concrete)
COMPLETED OVERLAY

NOTES:

Traffic 1 Follow jurisdictional requirements


Construction area for traffic control devices.
control
device
Existing Existing 2 Treat 3 ft (0.9 m) area outside of
shoulder Vehicle traffic shoulder proposed paved shoulder with
11 ft (3.4 m) lane calcium chloride. If the existing
(Typical) shoulder outside the proposed
paved shoulder is less than 3 ft
(0.9 m), it may be necessary to
adjust the slipform paver and/or
paver control to accommodate the
Base shoulder Surface repair Existing pavement reduced space.
widening Varies and overlay surface
material
Existing subbase 3 Minimum lane width next to the
preparation
paver may be reduced for short-
Separation layer (only for term, stationary work on low-
unbonded overlay on concrete) volume, low-speed roadways when
STAGE 1 vehicular traffic does not include
longer and wider heavy commercial
vehicles.
4 If the overlay is opened to traffic
Vehicle traffic Construction area in this stage, and final shoulder
11 ft (3.4 m) lane backfill is delayed, place fillet as
(Typical) shown or (if overlay creates a
Shoulder Varies
dropoff greater than jurisdictional
allowance) place granular shoulder.
12 ft (3.7 m) lane Concrete
(Typical) fillet placed 5 See centerline fillet illustration and
Traffic Varies
control
with overlay subsequent removal on figure 43.
device 6 For X less than 4 ft (1.2 m),
adjustments to paver may be
necessary to accommodate paver
Concrete thickened control and paver track.
Concrete paved shoulder
Varies Varies
overlay placement 7 The X dimension can be reduced
Surface repair to 3 ft (0.9 m) minimum when the
Existing pavement right lane is used as paver control.
Separation layer 8 Mark edgelines and centerlines per
(only for unbonded overlay on concrete) MUTCD (FHWA 2003b) section 6F.71
STAGE 2
(mark both lanes).
9 Construct longitudinal joint.
Construction area Vehicle traffic
11 ft (3.4 m) lane
Remaining Paved 12 ft (3.7 m) lane (Typical) Remaining
Concrete shoulder shoulder shoulder
(Typical)
fillet placed
with overlay Concrete
9 overlay 8 9 8
placement

Overlay of
Two-Lane Roadway
Separation layer Existing pavement
(only for unbonded
overlay on concrete)
Varies Varies with Paved Shoulders
STAGE 3
(Conventional Paver)

Guide to Concrete Overlays 43


COMPLETED OVERLAY (Two-Lane Roadway with Granular Shoulders, Conventional Paver)

Applied to:

;Bonded concrete overlay of concrete pavements ;Unbonded concrete overlay of concrete pavements
;Bonded concrete overlay of asphalt pavements ;Unbonded concrete overlay of asphalt pavements
;Bonded concrete overlay of composite pavements ;Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface, prepare for overlay, and construct left shoulder
and separation layer
Install traffic control and close the left lane. Follow trench should be rolled and compacted as
jurisdictional requirements for traffic control. Check necessary to obtain a firm and stable platform.
with jurisdiction regarding allowable lane closure Compact shoulder material as specified in the
length. If surface repair and preparation for the overlay contract documents. A continuous progression Typically
are minimal, then slow-moving traffic control may be approach with the shoulder trencher and less than
appropriate. Closing the lane may require additional placement of the base shoulder widening is 0.25 mi
(0.40 km)
traffic control (e.g., signals, flaggers, and/or pilot cars). encouraged. without
pilot car
Repair the surface as appropriate. Prepare the surface Construct calcium chloride treated granular
for the overlay (or, in the case of concrete overlay on shoulder as outlined in contract documents. The
concrete, the separation layer) as described in the treated shoulder shall be firm and stable to support
contract document. vehicular traffic at low speeds.
Prepare shoulder widening by trenching the existing Construct separation layer (only for unbonded
shoulder and trimming to the specified width. The overlay on concrete).

STAGE 2. Construct right shoulder and concrete overlay


Shift the traffic control to the left lane and close the traffic is limited.
right lane to traffic. The length of the closure will Construct concrete overlay on the existing
depend on the jurisdictions maximum closure length pavement. Construct right shoulder base with 6 in.
with pilot car. Traffic controls and traffic control (150 mm) thick granular shoulder. Bull float work
signals will be based on jurisdictional requirements. shall operate from the outside shoulder only.
Repair and prepare the surface for the overlay or the Place 6 in. (150 mm) minimum thickness calcium
separation layer and subsequent overlay as described chloride treated granular shoulder to help stabilize
in the contract documents. Construct separation layer shoulder and minimize heavy dust that can impair
(for unbonded overlay on concrete). vision.
Normal space for the paver stringline is 11.5 ft (0.30.5 Early entry saws are encouraged and should follow
m) and the paver track is a minimum of 2.53 ft (0.80.9 the depth as described in this manual.
m). 1 ft (0.3 m) incremental encroachment reduction (up
to 2 ft [0.6 m] total) is common through typical machine The X dimension between the roadway centerline
adjustment. Speeds should be restricted adjacent to and vertical panel is for the paving machine track
paver when clearance between the paver and vehicle and stringline.

STAGE 3. Construct left lane concrete overlay

Close the opposite lane to traffic and place the If the outside edge dropoffs at the shoulder
concrete overlay according to contract documents, exceeds the jurisdictional allowance for a 1:1 fillet,
using the same procedures as described in stage 2. then construct the granular shoulders in this stage.
Stringline may not be necessary for the right edge of Complete shouldering. Complete pavement marking
the paving when the paved overlay constructed in and regulatory signing in accordance with contract
stage 2 is used as the paver control in this stage. If the documents.
right stringline is not used, the X dimension could
possibly be reduced to 3 ft (0.9 m).

Figure 45. Overlay of two-lane roadway with granular shoulders (conventional paver)

44 Guide to Concrete Overlays


LEGEND
Remaining Remaining
shoulder Granular Granular shoulder Stage work area
shoulder 12 ft (3.7 m) lane 12 ft (3.7 m) lane shoulder
Pavement (Typical) (Typical) Concrete
marking Pavement
marking
Granular material
Finished
shoulder

12 ft (3.7 m) existing lane


Existing pavement
Concrete overlay
Existing subbase
Separation layer
(only for unbonded overlay on concrete)
COMPLETED OVERLAY

NOTES:

1 Follow jurisdictional requirements


Traffic
Construction area control
for traffic control devices.
device 2 When the existing shoulder is less
Existing Existing
shoulder Vehicle traffic shoulder than 4 ft (1.2 m), adjustment to the
11 ft (3.4 m) lane slipform paver and/or paver control
(Typical) may be necessary to accommodate
(10 ft [3 m] min.) 10 the reduced space for paver control
and paver track.
3 Minimum lane width next to the
paver may be reduced for short-
Construct 6 in. (150 mm) Existing pavement term, stationary work on low-
thick granular shoulder Surface repair
treated with calcium and overlay surface Existing subbase volume, low-speed roadways when
Varies preparation vehicular traffic does not include
chloride 4 ft (1.2 m)
min. Separation layer longer and wider heavy commercial
(only for unbonded overlay on concrete) vehicles.
STAGE 1 4 If the completed overlay in this
stage opens to traffic and the final
shoulder backfill is delayed, place
fillet as shown. If overlay creates a
Vehicle traffic Construction area dropoff greater than jurisdictional
allowance, place granular shoulder
11 ft (3.4 m) lane
in lieu of concrete fillet.
10 (Typical) Remaining
Shoulder (10 ft [3 m] min.) Varies shoulder 5 See centerline fillet illustration and
subsequent removal on figure 43.
12 ft (3.7 m) lane
Traffic (Typical) Varies 6 For X less than 4 ft (1.2 m),
control
device adjustments to paver may be
necessary to accommodate paver
control and paver track.
7 The X dimension can be reduced
to 3 ft (0.9 m) minimum when the
Concrete Construct 6 in. (150 mm) right lane is used as paver control.
Varies Varies overlay placement thick granular shoulder
Base shoulder
widening Surface repair base if needed 8 Mark edgelines and centerlines per
Existing pavement MUTCD (FHWA 2003b) section 6F.71
Separation layer (mark both lanes).
(only for unbonded overlay on concrete)
9 Use calcium chloride for dust
STAGE 2 control.
10 For low-volume roads only
Construction area Vehicle traffic
11 ft (3.4 m) lane
Remaining 12 ft (3.7 m) lane (Typical)
Remaining
shoulder Shoulder (Typical) (10 ft [3 m] min.) shoulder
10
Concrete 8
overlay 8 9
Temporary
concrete fillet placement
placed with
overlay Overlay of Two-
Lane Roadway with
Separation layer Existing pavement Granular Shoulders
(only for unbonded overlay on concrete) Varies Varies
STAGE 3 (Conventional Paver)
Guide to Concrete Overlays 45
COMPLETED OVERLAY (Two-Lane Roadway with Minimum Granular Shoulders, Zero-Clearance Paver)

Applied to:

;Bonded concrete overlay of concrete pavements ;Unbonded concrete overlay of concrete pavements
;Bonded concrete overlay of asphalt pavements ;Unbonded concrete overlay of asphalt pavements
;Bonded concrete overlay of composite pavements ;Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface, prepare for overlay, and construct left shoulder
In order to construct an overlay on a roadway with with jurisdiction regarding allowable lane closure
a minimum of 2 ft (0.6 m) wide existing shoulders, length. If surface repair and preparation for the
adjustments to typical slipform pavers are necessary overlay are minimal, then slow-moving traffic
in order to meet existing clearances adjacent to the control may be appropriate. Closing the lane may
paver. The width of the clearance zone is dependent require additional traffic control (e.g., signals, Typically
on traffic control, paver track, and paver control flaggers, and/or pilot cars). less than
0.25 mi
(stringline). When there is not enough clearance for the
Repair the surface as appropriate. Prepare the (0.40 km)
paver track, paving molds may be installed on typical without
surface for the overlay (or, in the case of concrete
two-track pavers to provide zero clearances. The pilot car
overlay on concrete, the separation layer) as
outside edges of the mold are brought out behind the
described in the contract document.
rear tracks and then the material from the front of the
paver is moved to the back by an auger to be spread Construct calcium chloride treated granular
and paved. shoulder as outlined in contract documents. The
treated shoulder shall be firm and stable to support
Install traffic control and close the left lane. Follow
vehicular traffic at low speeds.
jurisdictional requirements for traffic control. Check
Construct separation layer (only for unbonded
overlay on concrete).

STAGE 2. Construct right shoulder and concrete overlay


Shift the traffic control to the left lane and close the be restricted adjacent to paver when clearance
right lane to traffic. The length of the closure will between the paver and vehicle traffic is limited.
depend on the jurisdictions maximum closure length
Construct concrete overlay on the existing
with pilot car. Traffic controls and traffic control signals
pavement. Bull float work shall operate from the
will be based on jurisdictional requirements.
outside shoulder only.
Repair and prepare the surface for the overlay or the
Place 6 in. (150 mm) minimum thickness calcium
separation layer and subsequent overlay as described
chloride treated granular shoulder to help stabilize
in the contract documents. Construct separation layer
shoulder and minimize heavy dust that can impair
(for unbonded overlay).
vision.
Normal space for the paver stringline is 11.5 ft (0.30.5
Early entry saws are encouraged and should follow
m) and the paver track is a minimum of 2.53 ft (0.80.9
the depth as described in this manual.
m). 1 ft (0.3 m)incremental encroachment reduction (up
to 2 ft [0.6 m] total) is common through typical machine The 1.5 ft (0.5 m) dimension between the roadway
adjustment. Modification to a conventional paver is centerline and vertical panel is for the stringline
necessary to achieve these dimensions. Speeds should and fillet.

STAGE 3. Construct left lane concrete overlay

Close the opposite lane to traffic and place the


concrete overlay according to contract documents,
using the same procedures as described in stage 2.
Complete shouldering. Complete pavement marking
and regulatory signing in accordance with contract
documents.

Figure 46. Overlay of two-lane roadway with minimum granular shoulders (zero-clearance paver)

46 Guide to Concrete Overlays


LEGEND
24 ft (7.3 m)
Granular
Granular shoulder Stage work area
shoulder
12 ft (3.7 m) lane 12 ft (3.7 m) lane Concrete
Pavement (Typical) (Typical)
Pavement
marking marking Granular material

Finished
shoulder

Existing pavement
Concrete overlay Existing subbase
Separation layer
(only for unbonded overlay on concrete)
COMPLETED OVERLAY

NOTES:

Traffic 1 Follow jurisdictional requirements


Construction area control Existing for traffic control devices. Outside
device shoulder shoulder traffic control may depend
Existing shoulder
Vehicle traffic on width of shoulder.
11 ft (3.4 m) lane 2 Existing shoulder should have
(Typical)
(10 ft [3 m] min.) 8
minimum 6 in. (150 mm) of granular
material and should be treated with
calcium chloride.
3 Minimum lane width next to the
paver may be reduced for short-
Existing pavement
Surface repair
term, stationary work on low-
and overlay surface preparation Existing volume, low-speed roadways when
Separation layer subbase vehicular traffic does not include
Varies (only for unbonded overlay on concrete) longer and wider heavy commercial
2 ft (0.6 m) min. vehicles.
4 Place granular shoulder with
STAGE 1 calcium chloride in two lifts. The
first lift is for the paver track. The
second lift is for final shoulder. If
Vehicle traffic Construction area the completed overlay in this stage
opens to traffic and the final lift
11 ft (3.4 m) lane is delayed, place concrete fillet
(Typical)
1.5 ft (0.46 m) min. as shown. If overlay creates a
(10 ft [3 m] min.) 8
Varies dropoff greater than jurisdictional
12 ft (3.7 m) lane allowance, place second lift before
Traffic Traffic (Typical) opening overlay to traffic.
control control Granular
device device shoulder 5 See centerline fillet illustration and
subsequent removal on figure 43.
6 Requires minimum to zero
clearance paver. 1.5 ft (0.5 m)
Concrete dimension is for the paver ski or
overlay placement stringline.
Surface repair 7 Mark edgelines and centerlines per
Existing pavement MUTCD (FHWA 2003b) section 6F.71
Separation layer (mark both lanes).
(only for unbonded overlay on concrete)
STAGE 2 8 For low-volume roads only

Construction area Vehicle traffic


Granular 11 ft (3.4 m) lane
(Typical) Traffic
shoulder 1.5 ft (0.46 m) min. control
12 ft (3.7 m) lane (10 ft [3 m] min.) device
(Typical) Concrete 8 6 in. (150 mm) plus
overlay 7 7
placement
overlay thickness
granular shoulder Overlay of Two-
treated with
calcium chloride Lane Roadway with
Minimum Granular
Separation layer
(only for unbonded
Existing
pavement
Shoulders (Zero-
overlay on concrete) STAGE 3
Clearance Paver)

Guide to Concrete Overlays 47


COMPLETED OVERLAY (Two-Lane Roadway Widened to Three Lanes with
Paved Shoulders, Conventional Paver)

Applied to:

;Bonded concrete overlay of concrete pavements ;Unbonded concrete overlay of concrete pavements
;Bonded concrete overlay of asphalt pavements ;Unbonded concrete overlay of asphalt pavements
;Bonded concrete overlay of composite pavements ;Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface, prepare for overlay, and construct base shoulder
widening and separation layer
Install traffic control and close the left lane. Follow to obtain a firm and stable platform. Compact
jurisdictional requirements for traffic control. Check shoulder material as specified in the contract
with jurisdiction regarding allowable lane closure documents. A continuous progression
length. If surface repair and preparation for the overlay approach with the shoulder trencher and
Typically
are minimal, then slow-moving traffic control may be placement of the base shoulder widening is less than
appropriate. Closing the lane may require additional encouraged. 0.25 mi
traffic control (e.g., signals, flaggers, and/or pilot cars). (0.40 km)
Pave the existing shoulder a minimum of 6 ft without
Repair the surface as appropriate. Prepare the surface (1.8 m) with concrete. pilot car
for the overlay (or, in the case of concrete overlay on
Use excavated granular material to widen
concrete, the separation layer) as described in the
existing shoulder. Treat 3 ft (0.9 m) area of
contract document.
shoulder with calcium chloride.
Prepare shoulder widening by trenching the existing
Construct separation layer (only for unbonded
shoulder and trimming to the specified width. The
overlay on concrete).
trench should be rolled and compacted as necessary

STAGE 2. Construct thickened shoulder and concrete overlay

Shift the traffic control to the left lane and close the Construct concrete overlay on the existing
right lane to traffic. The length of the closure will pavement. Complete right PCC shoulder
depend on the jurisdictions maximum closure length widening with the overlay.
with pilot car. Traffic controls and traffic control signals
Early entry saws are encouraged and should
will be based on jurisdictional requirements.
follow the depth as described in this manual.
Repair and prepare the surface for the overlay or the
The X dimension between the roadway
separation layer and subsequent overlay as described
centerline and vertical panel is for the paving
in the contract documents. Construct separation layer
machine track and stringline.
(for unbonded overlay).

STAGE 3. Construct left lane concrete overlay

Close the opposite lane to traffic and place the If the outside edge dropoffs at the shoulder
concrete overlay according to contract documents, exceeds the jurisdictional allowance for a 1:1
using the same procedures as described in stage 2. fillet, then construct the granular shoulders in
Stringline may not be necessary for the right edge of this stage.
the paving when the paved overlay constructed in
Complete shoulders. Install (mill) rumble strips
stage 2 is used as the paver control in this stage.
in the paved shoulders and complete pavement
marking and regulatory signing in accordance
with contract documents.

Figure 47. Overlay of two-lane roadway widening to three lanes with paved shoulder (conventional paver)

48 Guide to Concrete Overlays


LEGEND
Remaining
Remaining shoulder
shoulder 4 ft (1.2 m) 12 ft (3.7 m) 12 ft (3.7 m) 12 ft (3.7 m) 4 ft (1.2 m) Stage work area
(Typical) (Typical) (Typical) (Typical) (Typical)
Concrete
Pavement
marking Pavement Base shoulder widening
marking Rumble materials
Rumble strip
(e.g., cement-treated
strip base, porous concrete,
roller compacted con-
crete (RCC), asphalt, or
Tiebars optional concrete)
Finished shoulder
Overlay Granular material
6 ft (1.8 m) min. placement
Separation layer
(only for unbonded overlay on concrete) Surface repair
Existing pavement
Existing subbase COMPLETED OVERLAY

NOTES:

Traffic
1 Follow jurisdictional
Construction area control requirements for traffic
device control devices.
Existing shoulder Vehicle traffic Existing shoulder 2 Use excavated granular
10 ft (3 m) 11 ft (3.4 m) material to widen existing
(Typical) (Typical) shoulder. Treat 3 ft (0.9
m) area of shoulder with
calcium chloride.
3 Minimum lane width
next to the paver may
Surface repair Existing pavement be reduced for short-
Subbase 6 ft (1.8 m) min. and overlay surface Existing subbase term, stationary work on
widening preparation low-volume, low-speed
Separation layer roadways when vehicular
(only for unbonded overlay on concrete) traffic does not include
longer and wider heavy
STAGE 1 commercial vehicles.
4 If the completed overlay in
Construction area this stage opens to traffic
and the final shoulder
4 ft (1.2 m) back fill is delayed,
4 ft Vehicle traffic 4 ft shoulder
(1.2 m) 11 ft (3.4 m) (1.2 m) 11 ft (3.4 m) 6 ft (1.8 m)
place fillet as shown. If
(Typical)
overlay creates a dropoff
(Typical) (Typical) (Typical) (Typical) (Typical) greater than jurisdictional
Traffic
allowance, place second
control lift before opening overlay
device to traffic.
5 See centerline fillet
illustration and
Subbase subsequent removal on
Subbase Concrete widening
widening overlay placement figure 43.
Existing pavement Surface repair 6 Mark edgelines and
Separation layer centerlines per MUTCD
(only for unbonded overlay on concrete) (FHWA 2003b) section
STAGE 2
6F.71 (mark both lanes).

Construction area
Remaining Remaining
shoulder shoulder
4 ft 6 ft 4 ft Vehicle traffic Paved shoulder
(1.2 m) (1.8 m) 12 ft (3.7 m) (1.2 m) 11 ft (3.4 m) 4 ft (1.2 m)

(Typical) (Typical) (Typical) (Typical) (Typical)


Overlay of Two-
6
Traffic 6 Lane Roadway
control device
Widened to Three
Lanes with Paved
Separation layer
(only for unbonded
Concrete
overlay placement
Shoulders
Subbase
widening
overlay on concrete )
Existing pavement
Surface repair (Conventional
STAGE 3
Paver)

Guide to Concrete Overlays 49


COMPLETED OVERLAY (Four-Lane Roadway with Paved Shoulders, Conventional Paver)

Applied to:

;Bonded concrete overlay of concrete pavements


;Unbonded concrete overlay of concrete pavements
;Bonded concrete overlay of asphalt pavements
;Unbonded concrete overlay of asphalt pavements
;Bonded concrete overlay of composite pavements
;Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface and prepare for overlay

Install traffic control and close the Repair the surface as appropriate.
inside lanes. Follow jurisdictional Prepare the surface for the overlay
requirements for traffic control. Check (or, in the case of concrete overlay
with jurisdiction regarding allowable on concrete, the separation layer) as Typically Typically
lane closure length. If surface repair described in the contract document. less than less than
0.25 mi 0.25 mi
and preparation for the overlay are Evaluate the structural condition of (0.40 km) (0.40 km)
minimal, then slow-moving traffic the existing shoulder. Mill existing without without
control may be appropriate. Closing shoulder or reconstruct shoulder to
pilot car pilot car
the lanes may require additional carry traffic load if necessary.
traffic control (e.g., signals, flaggers,
and/or pilot cars). Construct separation layer (only for
unbonded overlay on concrete).

STAGE 2. Construct concrete overlay on outside lane

Shift the traffic control to the inside separation layer (for unbonded
lanes and close the outside lanes overlay).
to traffic. The length of the closures
Construct temporary shoulder for
will depend on the jurisdictions
paver track.
maximum closure length with pilot
car. Traffic controls and traffic control Construct concrete overlay on the
signals will be based on jurisdictional existing pavement. Bull float work
requirements. shall operate from the outside
shoulder only.
Repair and prepare the surface for
the overlay or the separation layer Early entry saws are encouraged and
and subsequent overlay as described should follow the depth as described
in the contract documents. Construct in this manual.

STAGE 3. Construct concrete overlay on inside lane

Shift the traffic control to the outside If the right stringline is not used,
lane and close the inside lane to the X dimension could possibly
traffic. Place the concrete overlay be reduced to 3 ft (0.9 m).
according to contract documents,
Complete shoulder finish
using the same procedures as
grading. Install (mill) rumble
described in stage 2. Stringline may
strips in the paved shoulders and
not be necessary for the right edge
complete pavement marking and
of the paving when the paved overlay
regulatory signing in accordance
constructed in stage 2 is used as the
with contract documents.
paver control in this stage.

Figure 48. Overlay of four-lane roadway with paved shoulders (conventional paver)

50 Guide to Concrete Overlays


LEGEND

10 ft (3 m) Stage work area


Paved 12 ft (3.7 m) lane 12 ft (3.7 m) lane paved shoulder
shoulder varies (Typical) (Typical) (Typical) Concrete

Pavement marking Pavement


marking Existing shoulder
Rumble strip (Reconstructed
Rumble
strip if necessary)

Concrete shoulder Concrete


Existing pavement shoulder
Concrete overlay NOTES:
12 ft (3.7 m) existing lane
Separation layer 1 Follow jurisdictional
(only for unbonded overlay on concrete) Existing subbase
requirements for traffic
COMPLETED OVERLAY control devices.
2 Evaluate the structural
condition of the existing
shoulder. If necessary,
12 ft (3.7 m) 10 ft (3 m) reconstruct shoulder with
vehicle traffic existing shoulder PCC or asphalt to carry
Construction area (Typical) (Typical) the traffic load.
6 ft (1.8 m) Separation layer Traffic
(Typical) control
3 See centerline fillet and
(for unbonded
overlay) device subsequent removal
illustration on figure 43.
4 When the existing
shoulder outside of the
Surface repair Existing pavement proposed paved shoulder
Existing and overlay surface Existing subbase is less than 3 ft (0.9 m),
shoulder preparation adjustment to the paver
may be necessary to
accommodate paver
STAGE 1 control and paver track.
5 If the completed overlay
Vehicle traffic Construction area in this stage opens to
traffic and the final
Remaining 11 ft (3.4 m)
shoulder (Typical)
shoulder backfill is
22 ft (6.7 m) delayed, place fillet as
(Typical) shown. If overlay creates
12 ft (3.7 m) 10 ft (3 m) a dropoff greater than
Traffic (Typical) (Typical) jurisdictional allowance,
control place second lift before
device
opening overlay to traffic.
6 For X less than 4 ft
Temporary
(1.2 m), adjustments to
concrete fillet paver may be necessary
Concrete placed with overlay to accommodate paver
Separation layer overlay Concrete shoulder control and paver track.
(only for unbonded overlay on concrete) placement
7 The X dimension can
Surface repair be reduced to 3 ft (0.9 m)
Existing pavement STAGE 2 minimum when the right
lane is used as paver
control.
Construction area Vehicle traffic 8 Mark edgelines and
11 ft (3.4 m) centerlines per MUTCD
12 ft (3.7 m) (Typical) Remaining (FHWA 2003b) section
Temporary Varies (Typical) shoulder 6F.71 (mark both lanes).
concrete fillet
placed with Concrete 8 8
overlay overlay placement
Overlay of Four-
Lane Roadway
Concrete shoulder
Temporary
concrete fillet
with Paved
Existing pavement Varies Varies placed with
overlay Shoulders
Separation layer
(only for unbonded
overlay on concrete)
(Conventional
STAGE 3
Paver)
Guide to Concrete Overlays 51
Key Points for Concrete Overlay Construction
Normal concrete paving construction practices can be used to complete desirable conditions, such as inclement weather conditions, when an
concrete overlay projects as quickly and eciently as any other paving overlay is particularly thin, or when a project does not have much ex-
method (table 10). Resurfaced streets and highways can be opened to ibility in scheduling.
trac within short periods of time with adequate planning, expedited
staging, and ecient operations. Payment is typically based on two items: square yards and cubic yards.
The surface is measured to account for the square-yard surface area, and
HIPERPAV is a software tool available to predict stresses in concrete. It is batch tickets are collected to account for the cubic-yard concrete vol-
especially useful when there is a need for more information in less-than- ume, including variable depths.
Bonded Overlays Unbonded Overlays
Table 10. Concrete paving construction practices for overlays

Bonded Bonded Unbonded Unbonded


Overlays Overlays of Overlays Overlays of
Construction Consideration of Asphalt or of Asphalt or
Concrete Composite Concrete Composite
1. Mixture Design
Aggregate:
Physically and chemically stable and durable X X X X
Well-graded mix X X X X
Match aggregate thermal properties with existing pavement X
Maximum aggregate size should be D/2.5 in relation to the new overlay thickness X X
Use conventional mixtures with type I or II cement. X X X X
If the project is to move forward as quickly as possible, all aspects of construction need to be treated with X X X X
an expedited approach and not just a few elements of the project. For example, do not only use accelerators
to expedite the set time and then not finish the shoulders in an efficient manner. Use fly ash and slag to
reduce permeability with w/cm ratio of 0.45. Use water reducer to help maintain w/cm ratio, desired slump,
and to increase strength.
To improve bonding and expedite opening, use higher cementitious content (an example would be 660 lb/yd3 X X
[299 kg/m3]).
Fibers may be used to increase the toughness of concrete (measure of its energy absorbing capacity), X X
improve resistance to deformation, hold concrete together in case of cracking, and serve as an insurance
policy that protects the surface from unseen base conditions.
Verification testing in the laboratory of nonstandard mixes (trial batches) and specifications of temperatures X X X X
representative of site conditions is encouraged to flag any mix problems.

2. Grade Control
Centerline profile only (as-built) with uniform finished cross section. X Mill and fill
Three-line profile (edges and centerline) when cross slope varies or surface distortions exist. X Little or no Inlays only Inlays only
milling
Measure off existing pavement or top of milled surface to set stringline or form. Adjust individual points up to X X X X
produce a smooth line.
Survey 100500 ft (30.5152 m) cross sections when shouldering, foreslopes, and backslopes need adjusting. If X X
the existing profile grade is irregular, additional centerline elevations may be necessary for grade corrections in
certain locations for smoothness.
Survey bridge tie-end or bridge clearance conditions and extreme superelevations. X X
To prevent thicker asphalt separation layer and thus compaction, stability, and grade control issues, use concrete X
to make up any 3 in. (75 mm) or greater variances in grade and a nominal 1 in. (25 mm) asphalt separation
layer.
3. Preoverlay Repairs for Uniform Support
Minimal minor repairs of surface defects. Remove deteriorated area and replace with overlay. X
An engineer should observe final condition of subbase pavement prior to overlay construction. For minimal X
isolated distress that causes some loss of structural integrity that cannot be overcome with milling, thicken
the overlay in this area.
Replace isolated areas of subbase pavement when there is evidence of active movement. X X
Joint deterioration with little or no faulting can be bridged with the overlay. X
To widen the roadway, excavate the shoulder to allow for the widened thicker section to be placed with the X X X X
overlay.
4. Surface Preparation
Surface roughness for bonding:
Shot- or sandblasting X
Minimal milling to remove significant distortions or reduce high spots X X
Surface cleaning:
Sweeping followed by high pressure air blasting X X
(waterblasting may be needed to remove dirt tracked onto surface)
Surface sweeping only X X
Maintain saturated surface dry (SSD) surface. X X
Place nominal 1 in. (25 mm) asphalt layer to separate concrete layers and prevent bonding. X
When heavy truck traffic is anticipated, it is advisable to consider a drainable asphalt layer and drainage system.
If the existing asphalt surface of a composite pavement section remains intact, it can serve as a separation layer. X

52 Guide to Concrete Overlays


Bonded Overlays Unbonded Overlays
Table 10. Concrete paving construction practices for overlays, continued

Bonded Bonded Unbonded Unbonded


Overlays Overlays of Overlays Overlays of
Construction Consideration of Asphalt or of Asphalt or
Concrete Composite Concrete Composite
5. Concrete Placement
When the surface temperature of the asphalt is at or above 120F (49C), surface watering can be used to X X X
reduce the temperature and minimize the potential for shrinkage cracking. No standing water should remain
at the time the overlay is placed.
The bonding of the overlay can be affected by the climatic conditions at the time of placement. Significant X X
stresses that develop due to rapid changes in temperature, humidity, and wind speed may cause debonding
under severe conditions. HIPERPAV can predict interface bond stress based on numerous factors.
Feeding concrete consistently into the paver requires an adequate number of batch delivery trucks. The X X X X
number of trucks will often dictate the slipform or placement speed. The entire cycle of mixing, discharging,
traveling, and depositing concrete must be coordinated for the mixing plan capacity, hauling distance, and
spreader and paving machine capabilities. Extra trucks may be needed as the haul time increases.
Do not track paste or dirt onto the existing surface ahead of the paver because it can cause debonding. X X
The manner in which the crew deposits concrete in front of the paving operation is an important factor for X X X X
creating a smooth pavement surface in overlay projects. Placement in front of slipform paver should be done
in small overlapping piles so as to minimize lateral movements.
Properly established, secure, and maintained stringline is very important to smoothness; constant and X X X X
continuous paving prevents interruptions that lead to bumps.
Tiebars may be appropriate in an open-ditch situation when constructing 36 ft (0.91.8 m) widening units X X
and overlay thickness is 5 in. (125 mm) or greater. Normally, tiebars are not used for lane widening to prevent
cracking from stresses due to differential expansion and contraction between lanes.
Dowel bar use should follow full-depth pavement requirements. When used, they should be located X X
approximately in the mid-third of the overlay. Isolated thicker sections should not dictate a change in basket
height or dowel bar insertion depth.
Texturing needs to be performed at the right time so as not to disturb setting of the concrete. Shallow X X X X
longitudinal tining or burlap/turf are two effective textures. Burlap/turf drag have shown adequate friction
with a quiet surface when hard sands are used in the mix.

6. Curing to Prevent Rapid Loss of Water from the Concrete


HIPERPAV is a useful tool for predicting the effect of various curing techniques. It can model the design, X X X X
materials, construction, and environmental conditions affecting the concrete during early age.
Proper curing of bonded and thin unbonded overlays is particularly important because they are thin with large 2 times normal 1.52 times 1.52 times 1.52 times
surface compared with the volume of concrete. The curing rate may be increased from the normal rate to normal normal normal
provide additional protection. Standard curing compound rates may be used for thicker unbonded overlays.
During hot weather, steps should be taken to reduce the evaporation rate from the concrete. For significant X X X X
evaporation, provide a more effective curing application, such as fog spraying, or apply an approved
evaporation reducer.
Adequate curing of overlays on a stiff support system (especially on underlying concrete pavement) is X X X X
important to minimize curling and warping stresses.
7. Joints
Joint spacing for concrete overlays requires special consideration for each type:
Joints are to be matched with underlying concrete to prevent reflective cracking. X
Joints are typically mismatched to maximize load transfer from the underlying pavement. However, some X
states that have not intentionally mismatched joints have not experienced any adverse effects.
Joint panel spacings are very short (1.5 times overlay thickness) to reduce shear stress and reduce X
curling and warping stress.
Because of the potential for higher curling and warping stress from a rigid underlying pavement, shorter X X
than normal spacing is typical (see pages 19, 20, and 22).
Joint sawing:
The timing of sawing is critical. Sawing joints too early can cause excess raveling. HIPERPAV may be X X X X
useful in helping to predict the appropriate time window for joint sawing, based on the concrete mix
design, construction times, and environmental conditions.
Sawing must be completed before curl stresses exceed the bond strength developed. X X
Sawing too late can cause excess stresses, leading to uncontrolled random cracking. X X X X
Transverse joint saw-cut depth for conventional saws. Full depth + 0.50 in. T/4 T/4 min.T/3 max.
(13 mm)
Transverse joint saw-cut depth for early-entry saws. Full depth + 0.50 in. Not < 1.25 in. Not < 1.25 in.
(13 mm) (31 mm) (32 mm)
Longitudinal joint saw-cut depth. T/2 (at least) T/4T/3 T/4T/3
Transverse joint width must be equal to or greater than the underlying crack width at the bottom of the X
existing transverse joint.
Sealing:
Seal joint using low-modulus hot-pour sealant with narrow joint. X ** * *

* Some states have experienced problems with asphalt stripping of the separation layer, particularly under heavy truck traffic and high speeds. Therefore, sealing is important in these
conditions. On lower speed roads without a heavy traffic loading, some states successfully do not seal.
**Joint between overlay and curb and gutter

Guide to Concrete Overlays 53


Accelerated Construction
Road improvements not only have direct Evaluation of existing pavement crete pavement. There are issues related to
construction costs, but they also have indirect the concrete mixture, surface preparation and
Staging
time-related costs. Construction delays and cleaning, curing, sawing, and strength mea-
road closings are generally not well accepted by Concrete mixture surement. While several of these factors are
the road users. (type III cement is not necessary) currently considered in conventional concrete
paving, specic emphasis should be placed
One of the signicant benets of acceler- Surface preparation
on certain key factors of these elements, since
ated concrete overlay construction (typically (depending on type of overlay)
bonded concrete overlays are particularly sensi-
unbonded overlays) is decreasing total con-
Grade control (too much or too little) tive to volumetric changes.
struction time which in turn reduces road
user costs and increases driver safety. In addi- Bonding where required Concrete mixtures used in bonded concrete
tion, concrete overlays oer condence that overlays should shrink as little as possible
the improvements will provide a long-life Separation layer where required and behave thermally as close to the existing
pavement. Jointing widths and depths concrete pavement as possible. This typically
means optimizing the cement content to mini-
One of the main goals during accelerated over- Maturity methods for early opening mize shrinkage while maintaining an adequate
lay construction is to maintain successful trac
Curing strength. Another mixture-related consider-
management throughout the duration of the
ation is aggregate gradation (which helps in
project. The techniques used for accelerated
reducing cement factors without sacricing
construction often have more benet when the Early Opening of strength), as well as aggregate type. To help
overlay operation is open to trac. Overlays to Traffic minimize the thermal strains and stresses expe-
A common question is, When can I open a rienced at the bond line of bonded overlays
Approach and bonded overlay to trac so that the loading over concrete, the overlay should have aggre-
Considerations will not compromise the bond? The answer gate thermal properties similar to the aggregate
is related to minimum concrete strength and in the underlying concrete pavement. If local
Accelerated construction often uses con-
not an arbitrarily selected time from place- aggregate sources make matching the thermal
ventional concrete pavement materials and
ment. Concrete opening strength (compressive coecient dicult, an eort should be made to
procedures, but key changes can signicantly
or exural) directly relates to concretes load- use only aggregates with a thermal coecient
expedite projects (appendix C). These changes
carrying capacity and provides an indication of lower than that of the aggregates in the existing
add exibility for the contractor. They often
the bond strength. pavement.
involve contract incentives, modifying pave-
ment equipment for minimum zero clearance, Surface preparation of the existing concrete
materials proportioning modications, acceler- Quality of Bond for Bonded pavement is accomplished to produce a
ated curing methods, construction staging, Overlays of Existing Concrete roughened surface that will promote bonding
changes to pavement joint construction, and Surfaces between the two layers (gure 49). A variety of
revisions to opening criteria. When bonding a concrete overlay to an exist- surface preparation procedures may be used,
ing concrete surface, the necessity for a sound including shotblasting, milling, and high water
Life-cycle user costs should be evaluated when
bond cannot be overstated. Both theory and pressure blasting. A bonding grout or epoxy is
determining the type of rehabilitation that is to
practice show that without this bond, the over- not required. The most commonly used and
be implemented. When determining if acceler-
lay will develop secondary distress quickly, thus most eective surface preparation procedure
ated construction is to be implemented, it is
signicantly compromising the life of the pave- is shotblasting. Although milling will roughen
important that there is a benet to be gained
ment system. the concrete pavement surface, milling should
such as reducing road user costs and delays.
not be used solely for that purpose because of
The implementation of accelerated construc- Research has attempted to measure and char- its potential for causing surface microcracking
tion techniques on concrete overlays is based acterize bond strength during early ages of the and fracturing the exposed aggregate. If milling
on project and user needs. The techniques may concrete overlay. However, to date no simple is used to lower the pavement elevation, any
be used on critical parts of a project, such as and reliable test has been developed. As a resulting microcracking should be removed by
intersections and crossovers, the nal segment, result, bond strength is typically characterized shotblasting or high water pressure blasting.
or for the entire project. using a surrogate test, namely strength (com-
pressive or exural) of the overlay. The strength In some cases, a surface roughness or mean
Typically, standard mixtures used in conjunc- of the bond between the overlay and the texture depth is specied. The sand patch
tion with mixture additives and accelerated existing concrete pavement can be correlated test (ASTM C 965) is often used to measure
construction techniques meet project acceler- with the exural/compressive strength of the and verify the mean texture depth. Typically,
ated opening requirements. In some critical overlay. If the early opening strength criteria a mean texture depth in the range of 0.04 to
areas, accelerated concrete mixtures are used has been met, then the bond strength should 0.08 in. (0.9 to 2.0 mm) is deemed adequate
for unbonded concrete overlays and at times on also be adequate to allow the pavement to be for proper bond development.
bonded overlays, particularly over asphalt. open without bond failure, provided that care
Following surface preparation, the surface
has been taken to prepare the existing pave-
Table 11, beginning on page 57, outlines a should be thoroughly cleaned to remove all
ment surface properly and the overlay has been
variety of details for planning, designing, and loose material to ensure adequate bonding.
adequately cured.
constructing concrete overlays in an acceler- Cleaning may be accomplished by sweeping the
ated process. Not all items listed are needed for Several elements (beyond those common to concrete surface, followed by cleaning in front
every accelerated overlay project. However, the a typical concrete pavement) are particularly of the paver with compressed air. Airblasting
following topics should be considered for most important in ensuring a good bond between and waterblasting should be used only as
projects: the concrete overlay and the underlying con- supplementary cleaning procedures to remove

54 Guide to Concrete Overlays


loose material from the surface after shotblast- overlay performance, states are relying on actual and the underlying pavement) behaves like a
ing or milling. In no case should standing bond measurement to increase their condence truly monolithic slab. The direct pull-o test
water or moisture remain on the pavement sur- level in the quality of the bond. Several bond (ASTM C 1583) (gure 51) has also been used
face when the overlay is placed. Paving should tests have been used for this purpose, most for this purpose, although most commonly
commence soon after cleaning to minimize the notably the Iowa Shear Test (Iowa Test Method with bridge deck overlays. As with most tests
chance of contamination. 406C) (gure 50) and the Pennsylvania Shear of this nature that are sensitive to core orien-
Test (PTM 610). These tests involve coring tation, asymmetry in testing, and specimen
Vehicles should be limited on the existing
the overlaid pavement and placing the core in handling, results tend to be variable. However,
surface after it is prepared. If it is absolutely
a shear testing jig, where a shear load is applied when these factors are carefully controlled and
necessary to have vehicles on the existing con-
along the bond interface on the core. Early tests are performed by experienced person-
crete, care should be taken that they do not
work (research and evaluation) with this kind nel, shear bond testing can be a useful way to
drip oil or other contaminants that could com-
of testing suggests that a shear bond strength of develop condence that the desired quality of
promise the bond.
200 psi is enough to ensure that the composite bond has been achieved.
When the surface temperature of the concrete pavement (i.e., the bonded concrete overlay
is at or above 120F (49C), surface watering
can be used to reduce the temperature and
minimize the chance of shrinkage cracking. Figure 49. Compare the
Water standing on the surface should be blown surface texture of the non-
shotblasted area (upper
o with compressed air.
left half of image) to the
Curing also can have a pronounced impact roughened surface texture
on concrete overlay bond. The diligent and on the shotblasted section
thorough application of curing compound of pavement (under the
pen) (Photo courtesy of
(sometimes at twice the normal application
Leif Wathne, P.E., American
rate) is an eective method to control moisture Concrete Pavement
loss and thus lower shrinkage and early-age Association)
cracking potentials. This is particularly true
for thin bonded overlays. More extreme
measures, such as wet or blanket curing, can
help to minimize the risks of poor performance
when proper curing compound application
is either dicult or doubtful. These types of
more extreme curing regimes are typically
only applicable for short paving sections such Figure 50. Shear test (Photo
as intersection rehabilitation. courtesy of Leif Wathne, P.E.,
American Concrete Pavement
Good construction sawing practices can also
Association)
greatly reduce early pavement stresses and help
accommodate early opening to trac. As men-
tioned elsewhere in this document, sawing the
transverse joints in the new overlay full depth
exactly over the joints in the existing pavement
is absolutely critical for proper bonding. There
have been examples of early bonded concrete
overlay failures due to debonding as a result of
not sawing the joints all the way through the
depth of the overlay. The width of the trans-
verse joints in the overlay should be equal to
or greater than the width of the cracks under
transverse joints in the existing pavement.
When all of these factors have been properly Figure 51. Pull-off test (Photo
considered and executed during construction, courtesy of Leif Wathne,
the overlay strength can be used to character- P.E., American Concrete
ize the bond with some condence. Strength Pavement Association)
monitoring of the overlay concrete can be done
in a fashion similar to that of conventional
concrete paving. Maturity methods for early-
age strength prediction (ASTM C 1074) can
be particularly helpful. Knowing that bond
strength correlates reasonably well with con-
crete strength under these conditions means
that early opening to trac decisions can be
made relatively reliably, in-place, and in a
timely fashion.
In some cases, given the critical importance
of proper bond development to good bonded

Guide to Concrete Overlays 55


Strength Conversions for ing should be adequate if 540 psi (3.7 MPa) that are commonly used for conventional pav-
Opening to Traffic exural or 3,600 psi (24.8 MPa) compressive ing. For example, a minimum exural strength
strength is achieved. As a rule of thumb for (3rd point) of approximately 340 psi (2.3 MPa)
Guidance on concrete strength requirements
bonded concrete overlays, the bond tensile or 1,800 psi (12.4 MPa) compressive strength
for opening concrete roadways to trac is
strength may be on the order of 2 to 10 percent can be used for non-interstate trac. The state
readily available. For example, the Flexural
of the compressive strength, and the bond shear of Georgia for example, uses a concrete open-
Strength Criteria for Opening Concrete Roadways
strength approximately 4 to 20 percent of the ing strength criteria of 1,400 psi (9.7 MPa)
to Trac, as published by TRB (Cole and
compressive strength. It is advisable to verify as long as the mixture reaches 2,500 psi (17.2
Okamoto 1995), bases its opening exural
the relationship between compressive, exural, MPa) in 24 hours and 3,500 psi (24.1 MPa) in
strengths on thickness, k-values, and estimated
and bond strength for the mixture intended 3 days. Georgia typically uses a special mixture
ESALs, whereas FHWA and ACPAs Trac
for use. for these accelerated construction projects.
Management Handbook (2000a) is based on
thickness, foundation support, and the number Existing Asphalt Pavements Minimizing Early Loading
of ESALs between the time of opening and the Bonded concrete overlays on asphalt have one
time concrete reaches strength. Other methods Fatigue Damage
distinct advantage over bonded concrete over-
are available (FHWA 1994) and depend on the The fatigue life of concrete pavements are
lays on concrete. The concrete panels can be
type of trac, early loading locations on the sensitive to early wheel loading. A fatigue-con-
cut into small squares or rectangles in order to
slab, pavement thickness, and subbase support. sumption approach (FHWA 1994) theorizes
reduce the curling and warping stresses and the
that concrete pavement has a nite life and
expansion and contraction of concrete at the
Conversions can withstand some maximum number of
bond interface because there are no joints that
The modulus of rupture, or exural strength, load repetitions, N, of a given trac loading
need to be matched in the underlying pave-
is an important parameter in the estimate before fracture. Every individual trac load-
ment. The result is a reduction in shear at the
of fatigue damage. Many states use exural ing applied decreases the life of pavement by
bond interface. This technique has been suc-
strength (modulus of rupture) for concrete an innitesimal amount. This damage value
cessfully used for a number of years. However,
opening strength criteria and others use com- provides the percentage of life that is con-
overlays over asphalt are typically relatively
pressive strength. The following equation sumed by the actual number of trac loads
thin and are therefore susceptible to excessive
is sometimes used to convert compressive up to a given point in time. During the early
temperature-related stresses, particularly when
strength to third-point exural strength, stages of strength development, it is important
the existing asphalt is hot from solar heating.
although it is widely recognized that this rela- that decreases in pavement fatigue life are
If accelerated methods are used, extreme care
tionship is mixture dependent: not caused by heavy early loadings, until the
must be taken to minimize shrinkage cracking
concrete strength has reached a certain point.
*fr = 2.3 fc
0.667
(psi) through diligent and thorough curing (some-
Certain techniques can be employed to control
times at double the ordinary rate of curing
early loading that reduces fatigue damage until
where compound, or, in short sections, wet curing
the concrete strength can accommodate normal
fr = exural strength (MR or modulus of and/or blankets may be necessary). Some states
trac loadings.
rupture, psi) have incorporated bers to increase the tough-
fc = concrete compressive strength, psi ness of the concrete as well as to improve its One of the most important techniques is
resistance to cracking. restricting wheel loads to within 3 to 4 ft
Note: This empirical equation was developed
(0.9 to 1.2 m) from the edge of the pavement
using data from four dierent studies, con- Determining a reasonable value for opening
(and ideally 6 ft [1.8 m]) to minimize stress.
ducted between 1928 and 1965 (Raphael bond strengths for these types of overlays may
Research has shown that allowing only inte-
1984). Also the equation is contained in prove dicult, as described above, since there
rior early slab loadings greatly reduces fatigue
reports from ACI Committee 330 (2008). is not a simple eld test available to measure
damage (FHWA 1994). Trac cones are an
the bond strength. Instead, a value for opening
Since early-age strength can change rapidly eective way of restricting construction trac
strength of the concrete of 420 psi (2.9 MPa)
in a short time and since some agencies use a along the pavement edges until the pavement
exural (2,500 psi [17.2 MPa] compressive)
variation of the above referenced equation, it is reaches the desired full opening strength. In
to 480 psi (3.3 MPa) exural (3,000 psi [20.7
recommended that each agency develop its own addition to restricting early edge loadings, the
MPa] compressive) seems to be reasonable. An
relationship between the compressive strength use of higher modulus of subgrade reaction,
additional consideration for accelerated con-
and exural strength (modulus of rupture) for k, can help minimize early-age stress. With
struction is to encourage bond via milling of
the mixture they intend to use. As described concrete unbonded overlays this is a particular
the existing asphalt surface. If shear failures do
earlier, non-destructive tests such as maturity plus, since the underlying pavement provides a
occur, they will likely occur in the asphalt since
can be used to determine opening strength high level of base support.
concrete shear strength is greater than asphalt
since it provides real-time results.
shear strength. Dierential temperature and moisture values
throughout the slab can result in early-age curl-
Strength Criteria for Opening Strength Criteria for Opening ing and warping stress. When these stresses are
Bonded Systems to Traffic Unbonded Systems to Traffic added under certain conditions to early-age
Existing Concrete Pavement loading stress, cracking can occur. This can be
It is common for unbonded overlays plus the
controlled through proper curing and sawing
If proper surface treatment, curing, and sawing existing pavement to have a total thickness in
techniques.
are employed in the construction of concrete excess of new full depth pavements. Therefore,
overlays, the bond strength at the time of open- it is appropriate to use opening strength criteria

56 Guide to Concrete Overlays


Table 11. Accelerated construction under traffic for concrete overlays

Factors to Consider Objectives / Expectations Considerations / Limitations

Incentives/Disincentives An effective way of managing successful accelerated Incentives and disincentives should be considered for the
construction is to offer its incentives for the contractor. If the project to encourage the contractor to perform within the given
schedule is very critical, the contractor may likely consider schedule when a competitive bidding environment is expected.
innovative pavement techniques to complete the project on Use of disincentives should not deter potential bidders when the
time or even ahead of schedule. The use of incentives also schedule is critical.
allows for a better competitive bidding environment for the
owner.

Grade Control Grade control for the project should be considered early. If payment is based on the plan area, then the contractor may
In the planning of the project, the type of overlay and want a more detailed survey and additional cross sections to
existing pavement conditions will often dictate the level of ensure proper thickness and yield. If the payment is based on
survey required for the design and stakeout of the project. the volume of concrete supplied and the area paved, less survey
Resurfacing projects historically have required little in is required.
the way of surveying. A vast number of them are even
When milling machines are used to remove existing pavement,
constructed without detailed construction plans; they are
it is advisable to have them either follow the same control as the
referred to in many states as log jobs. When concrete
concrete paver or wait to establish the paving control until the
is used as the resurfacing material, there is no need to
milling has been completed.
increase the level of surveying required on a project.
With all resurfacing projects, it is advisable to visit the One point of caution for multi-lane construction is that on many
project site during a rain event and verify that there is no pavements, the cross-slope of each existing lane may differ, and
drainage issue. A drive through the project at the posted the paver should have crowning adjustment capability located
speed limit will alert you to adverse cross-slope issues. For at the intermediate lane lines or actively remove any cross-slope
rural areas, surveying is only required when you determine differences between the lanes with the milling operation.
that there is some type of a drainage, cross-slope, or profile
issue that needs to be corrected.
The elevation of the concrete paver can be controlled by
either a traveling ski or by a stringline that is referenced
from the existing pavement. When stringline control is
used, establish grades at each stringline pin by projecting
the existing cross-slope, sight the string longitudinally, and
adjust individual grades up to produce a smooth profile.

Materials / Mixtures
Reliability of Material Supply All materials that are required on the project need to be Materials that are prone to delivery delays need to be stockpiled.
available or scheduled or properly stored for use prior to
constructing the overlay project.

Material Schedule Under an accelerated schedule, there is little time for Contingency plans need to be developed to address potential
deviation from the intended plan. As such, representative changes in critical material properties.
samples from all material supplies should be made with
proper certification.

Concrete Mixture Normal concrete paving mixtures are typically used for The mixture needs to match the opening requirements and
concrete overlay projects. Rapid strength gain to meet construction methods to obtain opening requirements. However,
accelerated construction schedules does not require special the mixture should not be accelerated to a point where there is a
blended cements or sophisticated material. It is possible high probability of early-age cracking from shrinkage and curling
to proportion a mixture using locally available aggregates, and warping. Each crew member will have to be accustomed to
type I and type II cements, SCMs, and certain admixtures. the accelerated duties that accompany expedited construction.
Some initial adjustments will probably be required by the
paving crew as they become accustomed to the mixture
characteristics.

Cementitious Materials Hydraulic cements include portland cement and blended High levels of Tricalcium Silicate C3S (Alite) and finely ground
cements which contain SCMs. Other types of hydraulic cement particles will usually generate strength quickly for
cements are rapid-setting calcium sulfo-alumina cements accelerated mixes. Tricalcuim Aluminate (C3A) can be a catalyst
used for repair materials or for pavements where fast to enhance the rate of hydration of Alite by releasing heat early
turnaround times are critical. Cements and SCMs play a during the cement hydration. The Integrated Materials and
major role in both heat and strength development, and Construction Practices for Concrete Pavement Manual (IMCP
these properties depend on the interaction of the individual Manual) is a very good reference in order to understand the
compounds that constitute the mixture. importance of the proper blend of cementitious materials.

Type I/II cements Type I/II cements can reach opening strength without More cement does not necessarily mean higher strength.
increasing the risk of shrinkage cracks.

Slag Cement Slag cement can effectively reduce ASR expansion, increase Slag cement may reduce rate of strength gain and hydration rate.
long-term strength, reduce permeability, reduce concrete
temperature, and slow hydration.

Guide to Concrete Overlays 57


Table 11. Accelerated construction under traffic for concrete overlays, continued

Factors to Consider Objectives / Expectations Considerations / Limitations

Fly ash Fly ash will increase long-term strength, reduce permeability, Some states impose restrictions on the use of fly ash in cold
and reduce set temperature. Some fly ash can slow weather and may restrict the use of fly ash to 10% on accelerated
hydration on accelerated construction projects. construction projects even in warm weather months.

Type C Type C fly ash will increase long-term strength and reduce Type C fly ash can affect strength gain. Mixtures must be tested
water demand and permeability. This may or may not slow to determine how much class C fly ash is required to reduce
hydration or reduce ASR expansion. ASR-related expansion. Too high a dosage may increase the risk
of rapid stiffening and/or damage due to salt scaling.

Type F Type F fly ash will increase long-term strength and reduce Type F fly ash delays setting and reduces rate of strength gain.
permeability. It will also slow hydration and help reduce ASR High loss-on-ignition affects air entrainment. Type F is generally
expansion. effective at reducing ASR-related expansion. Availability may be
a limitation.

Chemical Admixtures Chemical admixtures are added to the concrete mixtures to The effects of set-modifying admixtures on other properties of
modify certain concrete properties such as strength. Adding concrete, like shrinkage, may not be predictable. Therefore,
chemical admixtures can achieve these properties more acceptance tests of set modifiers should be made with job
efficiently than adjusting other mixture ingredients such materials under anticipated job conditions. Compatibility of the
as the type of cement. Admixtures that are combined and admixtures with other ingredients should be tested as it relates to
contain both water reducers and accelerators are available. potential constructibility problems.

Water reducers Water reducers reduce water demand in order to reduce Confirm that water reducers are compatible with other chemical
paste content (lowers w/cm) to help minimize shrinkage, admixtures and cements, particularly under harsh environmental
temperature, and cracking without sacrificing workability. conditions. Confirmed laboratory testing is essential to determine
Water reducing admixtures can also increase early strength if the admixtures will develop the desirable properties. Type F and
gain by lowering the quantity of water necessary for G water reducers (superplasticizers) are not normally used in
cement hydration (by as much as 10% in 28 days). The w/ pavements because of their high cost and because it is difficult
cm ratio typically are at or lower than 0.43 for accelerated to control the slump range required for slipform paving with their
construction. use. Overdoses of water reducers, particularly normal-range
products, may severely retard or prevent setting.
Accelerators Accelerating admixtures are used to increase the rate of Long-term strength may be lower. Excess acceleration may result
strength development of concrete at an early age, including in cracking before finishing and/or saw cutting can be completed.
in cold weather. It is important to test both fresh and Care must be exercised in using accelerators in thin overlays so
hardened concrete properties before using accelerators in as not to cause early shrinkage, cracking, and high curling and
overlays, particularly bonded overlays. warping.

Air entrainment Air entrainment will dramatically improve the durability of Need to check compatibility with other admixtures. For about
concrete exposed to moisture during cycles of freezing and every 1% of air entrained, about 5% of concrete compressive
thawing. It improves concrete resistance to surface scaling strength is lost. Loss of air through the paver is acceptable up to
caused by chemical deicers. It also tends to improve the 1.50% to 1.75%. However, when the loss of air through the paver
workability of concrete mixtures, reduce water demand, and approaches 3%, the air system (quantity and distribution) is not
decrease mixture segregation and bleeding. acceptable.

Retarders Retarders are useful in extending set times. They increase Retarders are sometimes used to try to decrease slump loss and
the bleeding rate and capacity and may be accompanied by extend workability. This application is incorrect because, under
some reduction in early-age strength gain (one to three days) certain conditions, the opposite results can occur.
but higher later strengths.

Aggregates It is critical that aggregate be well graded (that is, there An aggregates CTE is a measure of how much the material
should be a wide range of aggregate sizes). Well-graded changes in length (or volume) for a given change in temperature.
aggregate has less space between aggregate particles, For bonded overlays over concrete, use aggregates that match
therefore reducing paste demand without loss of workability. the underlying pavement CTE. The material is subject to varying
Reduced paste content reduces shrinkage and early- conditions in storage and handling. At the very least, these
age cracking, particularly with accelerated mixes. With changes should be anticipated, and accommodations made to
accelerated construction, aggregate moisture content needs adjust the water content in the mixture as necessary. Ideally,
to be constantly monitored since it can change significantly real-time monitoring of the aggregate moisture content would
during the course of construction. Physical properties of the allow for on the fly changes. In most circumstances, a well-
aggregate such as absorption may be one source of change. regulated sampling program using rapid evaluation equipment
will improve this component of the process considerably.

Separation Layer A separation layer provides a necessary separation plane A separation layer does not provide structural support. Heavy
between overlay and underlying pavement. For asphalt truck traffic may decrease stability and strip the asphalt due to
separation layer under heavy truck traffic, decrease sand pore pressure. Consider drainable asphalt layer and drainage
content and increase 0.13 in. (3.3 mm) aggregate in order to system under heavy truck traffic.
reduce stripping the asphalt due to pore pressure.

58 Guide to Concrete Overlays


Table 11. Accelerated construction under traffic for concrete overlays, continued

Factors to Consider Objectives / Expectations Considerations / Limitations

Fibers Although not typically required for concrete overlays, Placement of fibers in the mixture must be accomplished so as to
consideration needs to be given to the use of fibers under prevent balling of the fibers into clumps. In some cases, water-
accelerated conditions. Fibers improve the toughness of the soluble bags are added to the final batch. A staging area may be
concrete overlay and resistance to plastic and dry shrinkage needed with adequate capacity to avoid a queue. In other cases,
cracking, particularly with bonded overlays. Fibers also can individual (bulk) fibers may be introduced into the mixture, where a
increase the flexural strength of the concrete. blower appropriate to the application should then be considered.

Batching Batching of concrete used in concrete overlays is usually no Depending on the size of the job, a dedicated mobile batch plant
different from conventional concrete paving, or even other is a benefit to the project under accelerated construction. In fact,
ready-mix applications. this is recommended when at all possible due to the potential for
increased control of quality and reliability.
Capacity Having adequate batching capacity is a critical link in Contingency plans should include preparation for rapid responses
the process of constructing concrete overlays under an (repairs) of the more common equipment malfunctions.
expedited schedule. Both mixing time and the availability of
transport equipment should be balanced along with cost.
Consistency During batching, consistency and uniformity are critical. Overlays are particularly vulnerable to changes in material
Adequate mixing time should be balanced with the need for properties due to their commonly thin sections.
increased production rates. If possible, a continuous type or
high-speed twin-shaft mixer could be used to accommodate
both objectives.

Concrete Transportation
Traffic Separation In an ideal situation, a separation of the transit vehicles from In most situations, however, circumstances deviate from the ideal,
both the traveling public and other construction vehicles is which warrants appropriate measures to ensure an accelerated
helpful. schedule.

Transit Time Transit time is one variable that must be known. If a mobile Caution must be exercised if a retarder is used as it may also effect
batch plant is used, transport of the concrete from the batch the strength gain of the mixture, thus affecting the time of opening to
plant to the paver may be quick. As a result, deviations from traffic. Curing may also become more critical in these situations as
a conventional concrete mixture (including the admixtures fresh concrete will be exposed for longer.
that are used) may not be necessary. However, if there is
a potential for delay (e.g., due to traffic congestion), or if a
ready-mix plant is used for supply with a longer travel time,
a modified mixture may be necessary.

Protection Protection of the mixture from environmental factors may Dry and windy conditions can lead to rapid moisture loss from
also be a consideration, particularly in long transit times. any exposed concrete. Conditions that are marginal for the risk of
freezing or rain must also be addressed. In each case, protection of
the concrete in transit may be warranted, and can often be done by
use of tarps. If ready-mix trucks are used, protection is often less
critical as the concrete is provided by the drum.

Haul Roads The condition of the haul roads is another consideration Care must be taken to ensure that the repeated heavy axles of the
when constructing under expedited conditions. trucks will not excessively rut the haul road. Evaluation of a haul
road in questionable areas should be done prior to the first batching.

Preoverlay Repairs Prior to the construction of overlays, there may be a need If the preoverlay repairs dictate the accelerated overlay schedule,
for a variety of spot repairs on the existing pavement to be the repairs should be considered under a separate project or
overlaid. The timing of these repairs will effect the schedule completed in off-peak hours.
of the overlay construction.

Dowel Bar Retrofit Typically, dowel bar retrofit is not done in conjunction with Slots should be cut by special diamond slot cutters that are capable
unbonded overlays since both can serve many of the same of making multiple cuts at a time. Modified milling machines are
functions. Dowel bars have been used in conjunction with not recommended due to associated spalling and variable cut
thin bonded overlays when you want to significantly increase widths that effect chair width requirements. Slots should be cut
load-carrying capacity. Good candidate projects for dowel parallel with the direction of traffic. To properly prepare the slots,
bar retrofits have the following characteristics: pavements material should be removed with a lightweight jackhammer, and the
with adequate slab thickness, but showing significant loss slot should be sandblasted and cleaned. When choosing a repair
of load transfer due to lack of dowels, poor aggregate material, select a material with the following characteristics: little
interlock, or subbase/subgrade erosion. Relatively young or no shrinkage, good ultimate strength, thermal compatibility,
pavements, because of insufficient slab thickness, excessive freeze-thaw durability, and good bond to existing concrete.
joint spacing, inadequate steel reinforcement at transverse
cracks, and/or inadequate joint load transfer, are at risk
of developing faulting, working cracks, and corner cracks
unless the load transfer is improved. Typically, 3 to 5 smooth
round steel dowel bars are used in each wheel path.

Guide to Concrete Overlays 59


Table 11. Accelerated construction under traffic for concrete overlays, continued

Factors to Consider Objectives / Expectations Considerations / Limitations

Drainage Drainage improvements are sometimes warranted to Since the equipment used for drainage improvements often works
complement the construction of a concrete overlay. These on or near the pavement edge, their operation before the overlay is
improvements may include cleaning adjacent ditches, complete would decrease the likelihood of premature damage to the
increasing their capacity, or even retrofitting subdrains. young concrete. In addition, if retrofit subdrains are to stabilize the
subbase, they should ideally be installed prior to the overlay in order
to reduce movement of the existing pavement. However, be careful
not to damage the subdrains during overlay construction.

Utilities Utility work is also sometimes done prior to overlay New patches can be particularly troublesome as they may not have
construction. This may include relocation of utilities from adequate time to settle prior to the overlay construction. As with
beneath the pavement to off of the pavement edge. If drainage improvements, all utility work should be completed prior to
trenching or other disturbance of the existing pavement the overlay in order to minimize interference or early-age damage.
is required, care should be taken to ensure proper
construction of patches.

Spot Repairs Some concrete overlays will require spot preoverlay repair In all cases, quality of the spot repairs will often be critical to the
to the existing concrete or asphalt pavement structure. If success of the performance of the pavement.
there are extensive repairs, the roadway may not be a good
candidate for an overlay.
Partial-depth repairs Good candidates are sections where slab deterioration is Poor candidates for partial depth repairs are those with distress
contained to the upper one-third of the slab and where the caused by compressive stress buildup in long-jointed pavements,
existing load transfer devices (if any) are still effective. spalling caused by dowel bar misalignment or lockup, transverse
or longitudinal cracking caused by improper joint construction
techniques, working transverse or longitudinal cracks, and spalls
caused by D-cracking or reactive aggregate. It is important to verify
that all delaminated concrete is removed, and that no concrete
around the repair boundaries has been damaged during the
process.

Full-depth repairs Full-depth repairs of existing concrete or asphalt pavements The effectiveness of a repair is dependent on the proper sizing of
are effective at correcting many different types of localized the repair. Most agencies specify a repair with a minimum length
distress. However, there are a few cases that limit the of 4 to 6 ft (1.2 to 1.8 m). Salvaging the existing dowel system is not
effectiveness of a full-depth repair. recommended. It is also important to verify that all delaminated
concrete is removed, and that no concrete around the repair
boundaries has been damaged during the process.

Retrofitted edge drains A good candidate project for retrofitted edge drains is a Retrofitted edge drains are not recommended on pavements
pavement that is showing early signs of moisture damage, where base contains more than 15% to 20% fines. When placing
is relatively young (i.e., less than 10 years old), and is only corrugated polyethylene pipes, extra care is also required to prevent
exhibiting a minimal amount of cracking (less than 5% overstretching of the pipes during installation. To avoid damage to
cracked slabs) (Mathis 1990; FHWA 1992). Many studies the pipes during compaction, a minimum of 6 in. (150 mm) of cover
have concluded that retrofitted edge drains are not effective over the drainage pipe is recommended before compacting.
at prolonging the service life of pavements that have already
experienced significant moisture-related deterioration
(Wells and Wiley 1987; Young 1990; VDOT 1990).

Slab stabilization Slab stabilization restores support beneath concrete slabs, Watch the maximum pressure to make sure it does not exceed
thereby reducing progression of support-related distresses 100 psi (0.69 MPa). Monitor slab lift closely. Lift is typically limited
such as pumping, joint faulting, and corner breaks. Slab to <_ 0.13 in. (3.3 mm). Stop grout injection when the grout is seen
stabilization is not intended to raise depressed or settled flowing from holes, cracks, or joints. Stop injection if one minute has
slabs to the desired elevation. Cement grout mixtures and elapsed, regardless of pressure or lift changes.
polyurethane are the most commonly used materials.

Surface Preparation/Cleaning Surface preparation and cleaning are required to prepare The techniques used will vary depending on the surface type.
the existing surface for the concrete overlay. The equipment used for repair should be sized to provide not only
adequate production rates but also to minimize the disruption to the
traveling public and to assist with the accelerated schedule.

Traffic on Prepared Surface Phasing of the surface preparation operation can allow for If trafficking is allowed on the prepared surface prior to the paving
intermediate trafficking of the surface prior to the overlay of the overlay, subsequent cleaning of the surface, particularly
placement. for bonded overlays, is required in order to remove any potential
contamination.

60 Guide to Concrete Overlays


Table 11. Accelerated construction under traffic for concrete overlays, continued

Factors to Consider Objectives / Expectations Considerations / Limitations

Bond on Concrete Existing pavement surface preparation typically consists of Paving should commence soon after cleaning to minimize the
shotblasting followed by sweeping the concrete surface. chance of contamination of the surface. Milling is used to lower the
Cleaning consists of compressed air. concrete elevation where required and is not used as a concrete
surface preparation since it can cause surface microcracking and
fracturing of the exposed aggregate.

Bond on Asphalt Existing pavement milling may be used where surface Water or moisture cannot be allowed to stand on the asphalt
distortions are 2 in. (50 mm) or greater to remove soft surface prior to the bonding resurfacing. In order to prevent
asphaltic material that would result in inadequate bond contamination of the surface, it is important to avoid a large lag time
surface or to roughen the surface to enhance bond between the final surface cleaning and paving.
development. Cleaning consists of sweeping the asphalt
surface then cleaning with compressed air.

Unbonded on Concrete Only the distresses that cause a major loss of structural The existing pavement needs to be stable and not shifting or
capacity require repair. moving, particularly at the subbase level.

Unbonded on Asphalt Milling may be used where surface distortions are 2 in. (50 Spot milling of only parts of the projects with significant distortions
mm) or greater to remove distortions that contain soft or or structural problems is often adequate.
fractured asphalt. Before concrete placement, the asphalt
surface should be swept. Remaining small particles are not
considered a problem.

Traffic Considerations
Vehicle Access Meet needs of user. May want to open pavement to cars Opening strength of pavement is the typical limit and may be
earlier and open to trucks later. increased through mixture material, protective curing, and heating.

Pedestrian Access in Channel pedestrian movements around construction zone. In areas where heavy pedestrian traffic must be accommodated,
Intersections/Urban Areas looping the pedestrian path may be necessary.

Traffic Control Devices Traffic can be accommodated during construction. Fit traffic Too many times concrete overlays are eliminated as rehabilitation
control to user needs and follow the MUTCD (FHWA 2003b). options when the project is to be built under traffic. The limitation
of clearance requirements for paver tracks and stringline are no
longer valid since many options are now available.

Lighting Lighting allows night work. Lighting must be movable with Number of lights and control of light patterns within work zone must
construction. be considered.

Nighttime Construction Nighttime construction for accelerated projects is Nighttime visual limits must be utilized. They include shorter spacing
increasing. It provides an off-peak construction period that of channelizing devices, longer transitions, changing colors nearing
lessens disruption to the traffic. off-ramps, missing devices the same as no devices, widening
pavement markings, using glare screens, using more truck-mounted
attenuators, using real-time information on signs and changeable
message signs, and covering signs when work is not being done.

Lane Capacity Examine lane capacity of construction zone speed and not Must deal with existing traffic flows in a safe manner for the driver
design speed of roadway. and construction worker.

Large Trucks Limited data show that tractor-trailer crash involvement in Special attention should be given to accommodate tractor-trailer
work zones is higher than the national average for these combinations, both in work zones and their transitions, especially
vehicles, particularly on the interstate system. where there are large truck volumes. Items to consider are lane
widths in curves with runs of barrier on both sides and stopping
distance where congestion is expected.

Detours Must be conveniently located and have effective signage. May have negative impact on users. Always minimize the out-of-
distance travel where possible.

Events
School Coordinate schedule with bus routes and events. The schedule may be difficult to control because of limit changes.
Commuter Plan project to minimize disruption. Normally limits can be relied upon.
Holidays Normally work stops during holidays. Holidays present an uncontrollable increase of traffic.

Visibility Provide adequate stopping distance, which increases Equipment and traffic control must be considered in regard to
overall safety. visibility.

Guide to Concrete Overlays 61


Table 11. Accelerated construction under traffic for concrete overlays, continued

Factors to Consider Objectives / Expectations Considerations / Limitations

Construction Staging
Staging Area The project limits should be evaluated to determine A dedicated ready mixture plant or mobile batch plant located near
adequate staging areas. The staging areas are necessary the project site will also cut down on the haul times to the site, and
for ready mix truck washouts, storage of equipment and the quality of the mixture will be more easily controlled.
materials, construction trailers, and possibly a portable
concrete mixing plant.

Incremental Lane Closure Allows for continuous single lane paving in one direction, Requires multiple traffic control setups and pilot cars.
(Leap Frog) leaving opened areas for traffic recovery.

Mobilization It is important that the project is planned to minimize staging Remobilizing of the paving crew on the project site takes time, and
operations. Every time a stage comes to an end, there are time not paving increases costs. A paradigm approach to paving is
mobilizations necessary to regroup and prepare for the next recommended to minimize the staging operations and mobilizations.
step in the paving process.

Work Production To keep paving crews busy and provide cost-effective work, Length based on curing time and production rates and acceptable
it is important to keep construction crews effectively utilized traffic delays when under traffic.
in accelerated construction projects involving overlays. That
requires the crews to utilize effective work schedules that
provide continuous and uninterrupted results.

Number and Type of Lane Traffic control must meet acceptable standards. Methods Number and type of closures will depend on traffic demands, lane
Closure and materials used must meet project restriction. capacity, adjacent access requirements, and number of available
traffic lanes.

Paver Encroachment All encroachment restrictions can be met. Normal stringline and track paver widths per side is typically 4 ft
(1.2 m). One foot incremental encroachment reduction (up to 3 ft [0.9
m] reduction total) is common through typical machine adjustment.
These do not require specialized pavers, but may require
adjustment or modifications to an existing paver.

Construction Under Traffic The user costs of constructing the roadway under traffic Additional construction cost and delays to users when construction
Versus Lane Closure typically are less than the costs of closing the road. is under traffic must be compared to travel delay and out-of-
However, closing the roadway is less in construction costs distance travel for detours.
since it eliminates staging expense and improves the speed
of construction.

Construction

Thickness of Overlay Thinner overlays cure quicker, causing stresses to form Thin overlays are subject to higher risk of cracking (shrinkage,
earlier. Therefore, early sawing is important. curling, and warping stresses).

Weather

Cold weather (below 40F Consider covering pavement to help achieve opening Do not place overlays less than 4 in. (100 mm) thick; there is a higher
[4.4C]) strength. risk of debonding and overlays require insulation.

Normal weather 40F to Overlays have fast strength gain and high production rates There should only be project restrictions and not normal material or
85F (4.4C to 29C) with reduced early-age cracking potential. equipment limits.

Hot weather > 85F (29C) Faster strength gain exists during hot weather. There is a higher risk of surface cracking during hot weather.
Proper curing is important. Also, bottom up cracking needs to be
considered when the underlying pavement is too hot.

Construction Equipment One of the most important aspects of accelerated In the event of failure to the concrete paver, a plan should be
construction that is often overlooked is the availability and available to continue operations. The plan could be simple, such
performance of the equipment on the site. All equipment as keeping a mechanic on call, or it may be more complex, such as
should be in working condition and properly maintained. having a backup paver in the vicinity. A staging plan should be part
The contractor should present a back up plan in the event of the back up plan to properly rout traffic in the event of scheduling
of equipment failure during construction. Proper parts, disruptions. If the pavement is to be open in a matter of hours
hydraulic fluids, oil, and fuel should be readily available. after paving, the critical stage is often the sawing. It is important
Concrete saws should be abundant and readily available on to have the adequate manpower and saws on the job site when
the job site. constructing a concrete overlay on an accelerated schedule.

62 Guide to Concrete Overlays


Table 11. Accelerated construction under traffic for concrete overlays, continued

Factors to Consider Objectives / Expectations Considerations / Limitations

Curing Curing is arguably more critical for overlays than for most While cost should be a consideration, the incremental quality
other paving. The relatively thin nature of concrete overlays improvements, such as high production curing from an effective
increases their surface area with respect to the volume curing program, will often far outweigh the additional cost.
of concrete. The result is more susceptibility to excess
moisture loss and the distresses that can result from this.
To avoid problems including plastic shrinkage cracking,
full-depth shrinkage cracking, wide joints, and surface
distresses, a rapid and effective curing program should
be adopted that includes using twice the recommended
compound rate for bonded overlays and 1.50 to 2 times the
application rate for unbonded overlays.

Special curing For overlays that require a very short opening to traffic and Special curing is normally not required in summer months for
are relatively short in length, special curing in addition to accelerated construction, but it does have an effect on strength
curing compound is used. It normally consist of insulating gain when air temperatures are less than 65F (19C), and it has a
blankets that provide a uniform temperature environment for pronounced effect when temperatures are less than 55F (13C)
the concrete. in colder months.

Jointing Jointing concrete overlays is also typically a more critical The timing of the saw cutting should be done to balance the
operation as compared to more conventional concrete potential for uncontrolled cracking with the potential for
paving. The thin section will often gain stresses rapidly, excessive joint spalling during sawing. Bonded concrete overlays
and thus require accelerated sawing. Sometimes the need over concrete require the most effective sawing operations to
for accelerated sawing is underestimated and the sawing prevent overlay failures. Not only does the transverse joint require
operations fall too far behind the paver. To respond to this, full depth saw cut plus 0.50 in. (13 mm) over the existing joint, the
the contractor should be prepared with the proper type width of the cut should not be less than the existing transverse
and number of saws. In the case of jointing, redundancy in crack below the existing saw cut. This allows the two monolithic
equipment is also important. pavements (overlay and existing pavement) to contract the same
way. For overlays on asphalt, particularly when there is wheel
rutting in the asphalt, the depth of the saw should be increased to
account for the extra depth in the wheel rut areas.

Fillets Provide fillets a level of safety precaution at dropoffs. Placement of form fillets may require sawing.

Opening Pavement Considerations


Public Relations Where construction will affect adjacent homeowners and Construction needs to follow the schedule and, during
businesses along with the traveling public, an effective construction, signing to business access is very important,
public relations campaign should be implemented. Flyers, along with daily communication between the contractor and the
media coverage, and public meetings regarding the impacted business. Informed local drivers can avoid the area
project schedule and the reason for the schedule timeline when possible, thus reducing delays.
need to be developed and implemented. Preconstruction
meetings between the government and the citizens, with the
contractor in attendance, help keep the public well informed
and allow the contractor to understand any concerns.

Schedule The project schedule must be reachable and realistic. The Proper equipment and staffing, mixture, construction methods,
schedule affects public acceptance, contractors methods, curing, and sawing are all considerations. There is a need to
payment and incentives, quality of work, and safety. Most understand the impact of traffic controls and openings, staging,
accelerated construction projects are moving more to material requirements, and isolated restricted spot locations on
calendar days and days when work is not usually done in the construction schedule.
order to address critical completion dates where a large
volume of traffic is affected. It also allows for the counting
of weekends when necessary and eliminates working day
issues of whether a contractor could or could not work.

Maturity Method Utilizing maturity testing for accelerated construction Development of a maturity curve is an important element of
provides a reliable technique for estimating in-place maturity testing. As construction proceeds on a project, validation
strength and thus the time of opening. The temperatures of the maturity curve may be necessary when changes occur in
measured as part of maturity testing have shown to be mixture constituents, material sources, mixture operations, and
effective in identifying potential changes to the concrete the watercementitious materials ratios. Also some states set an
mixture. Maturity testing provides a reliable technique for automatic validation criterion based on a time period. Most states
continuous monitoring of concrete strength gain. Most that use a maturity curve have validation criteria established
importantly, maturity testing enables any pavement to be which allows some flexibility in mixture changes without the
opened to traffic as soon as it meets strength criteria. development of a new maturity curve.
Concrete maturity concepts are being applied by 32 states.
Opening Strength See Early Opening of Overlays to Traffic section. See Early Opening of Overlays to Traffic section.

Note: Adapted from multiple sources.

Guide to Concrete Overlays 63


Considerations for Developing Project
and Supplemental Specifications
Every jurisdiction has its own project devel- Limitations of Operations overlay placement can be determined from
opment process and concrete pavement In addition to the limitations of operations for the length and pavement width, including
specications. The following guidelines can the placement of standard concrete pavement, widening sections. Payment should be full
be used in overlay project development and the following limitations for concrete overlays compensation for labor and equipment nec-
in developing supplemental specications or apply: essary to place, nish, texture, protect and
special provisions. They apply to bonded and cure the pavement, including sawing and
unbonded concrete overlay projects on existing At air temperatures below 55F (13C), sealing (if required) joints, furnishing, and
concrete, asphalt, and composite pavements. the opening of the pavement should be installing reinforcement (if required).
established using in-place strength measure-
The guidelines are specic only to concrete ment devices, such as the maturity method Separation layer: Hot mix asphalt or other
overlay projects and do not represent every (ASTM C-1074). In order to place concrete approved separation layer material should be
item that needs to be considered in a concrete in cold weather, air temperature require- measured and paid by area or weight.
paving project. ments for the jurisdiction should apply. If the contract documents require accelerat-
ing curing, such as wet or blanket curing,
General The engineer may impose a restriction on
the curing area should be measured and the
edge loading of construction equipment on
contractor should be paid per square yard.
Contractor Submittal the nished slab until opening strength is
Considerations reached.
Materials
Maturity method for strength determination Bonded concrete overlays should be placed
The CTE of the bonded overlays over
prior to opening to trac. according to the local jurisdictions schedule,
concrete need to be similar to that of the
based on seasonal temperatures.
Paving mixture design for each source of existing concrete pavement. This is typically
aggregate to be used for review and approval Unbonded overlays should not be placed accomplished by using similar aggregates in
by the engineer. when the asphalt or concrete pavement the concrete mixture. If it is not possible, a
surface temperature exceeds the maximum coarse aggregate should be used in the over-
Provide material certications to the temperature allowed by the engineer. lay that has a lower CTE than in the existing
engineer. Typically, this temperature is around 120F pavement.
Where required, submit a plan for con- (49C). Water may be added to cool the
The largest particle size of the coarse aggre-
struction sequence and schedule prior to pavement ahead of the paver. The surface
gate should be less than or equal to one-third
commencing construction. If the plans show should be dry and free of standing water
of the overlay thickness.
a specic sequence/schedule, the contrac- prior to paving.
tor may need to verify compliance with Refer to contract requirements for concrete
the schedule or submit an alternate plan to Method of Measurement and mixture parameters.
the engineer for approval. A detailed stag- Basis of Payment
ing and sequencing plan is recommended The quantity of the various items of work
Separation Layer for Unbonded
for concrete overlay projects when using an involved in the construction of concrete overlay Overlays
expedited construction process and schedule will be measured by the engineer in accordance If asphalt is used as the separation layer
of opening. with the following provisions: material, it should be designed with the
intention of preventing asphalt stripping
Scheduling and Conflicts Surface preparation may include milling,
from the build up of pore pressure from
air, water, and sand- or shotblasting; these
Construction sequence: A preconstruction heavy trac. Special consideration should
should be measured and paid in square
meeting is recommended to discuss critical be given to pavements where high speeds
yards. Sweeping and cleaning with com-
items such as staging, opening strengths, and heavy trucks are expected. These vari-
pressed air is a surface preparation task but is
time of placement, and overall schedule. ables are known to contribute to stripping.
most often incidental to paving.
Typically, a concrete overlay schedule is Fabric: Technology is evolving rapidly on
Concrete overlay, furnish only: The quantity
much shorter than a standard concrete pav- the use of geotextile fabric for the separation
of concrete furnished will be measured in
ing project. layer. Care should be exercised in select-
cubic yards. This quantity should include
ing geotextile fabric, however, because not
Conict avoidance: Expose possible conicts concrete placed in widening sections and
all products perform equally well for this
in advance of construction. Verify elevations partial depth patches. The contractor can be
application.
and locations of each and verify clearance for paid the contract unit price per cubic yards.
proposed construction. This payment should be full compensation
for furnishing all raw materials, and for pro- Construction
Complete elements of the work that can portioning, mixing, and delivery of concrete
aect line and grade in advance of construc- Preoverlay Repairs
to the paving machine.
tion unless noted on plans. Preoverlay repairs include: slab stabilization
Concrete overlay, placement only: The and slab jacking, partial depth repairs, full-
Trac control plan: The contractor should quantity of concrete overlay, placement only, depth repairs, retrotted edge drains, load
develop a trac control plan where required should be measured and paid for in square transfer restoration, and milling. If milling
based on the MUTCD (FHWA 2003b) and yards. This will be the quantity shown in the is part of the repairs, it should be completed
approved by the engineer. contract documents. The area of concrete prior to other repairs.

64 Guide to Concrete Overlays


Materials removed in the preparation The concrete surface should be cleaned prior 120F (48.89C). The pavement surface
operation may be temporarily placed in to the placement of the separation layer. If should not be moist or wet prior to place-
the shoulder area unless otherwise specied a leveling course is required, it should be ment of the overlay.
in the contract documents. The removal completed with the concrete overlay and not
Conventional concrete paving procedures
of materials must take place prior to the with the asphalt separation layer.
should be followed for placing, spreading,
removal of approved construction signage.
Unbonded Concrete Overlays Over consolidating, and nishing the unbonded
Surface preparation equipment used Asphalt overlay when required. When dowels are
should be subject to approval of the engi- specied, anchoring dowel baskets to the
All partial and full-depth patching should be
neer. Milling, air, water, sandblasting, and underlying pavement must be done accord-
completed with asphalt. Existing concrete
shotblasting equipment should be power ing to the jurisdictions requirements.
patches in the existing asphalt pavement should
operated and capable of preparing and clean- Alternatively, paving machines equipped
be isolated to prevent bonding to the concrete
ing of the existing surface in accordance with with dowel bar inserters can be used.
overlay. A debonding agent, fabric, or other
the contract documents.
bond-breaking material should be applied to A quality control plan should dictate the
Bonded Concrete Overlays Over the patch before the overlay is placed (see page time of placement with consideration
Concrete 21). given to air and pavement temperatures.
For bonded overlays on concrete, it is not
The surface of the existing pavement should
Surface Cleaning desirable to have the overlay pavement
be prepared by shotblasting, sandblasting
contracting, due to shrinkage, at the same
and/or milling. Milling, if used, should Bonded Concrete Overlays Over time as the existing underlying concrete is
be followed by shotblasting or high pres- Concrete or Asphalt expanding due to the heat of the day. The
sure water blasting to remove concrete The surface of the existing pavement should best time to place a bonded overlay over
damaged during milling (evidenced by be cleaned by sweeping and followed by concrete is when the temperature dierential
microcracking). compressed air in front of the paver. Paving between the existing pavement and new
Preparation should be adequate to remove all should commence soon after cleaning to overlay is minimal.
dirt, oil, and other foreign materials, as well minimize contamination.
as any laitance or loose material from the Pressure washing should only be consid- Liquid Membrane Curing
surface and edges against which new con- ered when surface contaminants are hard Apply curing compound immediately
crete is to be placed. to remove or when mud or other debris is after surface moisture has disappeared but
Airblast surface to remove loose debris and tracked on the surface. If pressure washed, typically no later than 30 minutes after
prevent resettlement of debris into cleaned no standing water should be allowed prior to nishing/texturing. Apply liquid curing
area. The surface should be free of oil or paving. Paving should commence soon after compound in a ne spray to form a continu-
other automobile uids. The pavement sur- cleaning to minimize contamination. ous, uniform lm on the horizontal surface
face should not be moist or damp or have and vertical edges of pavement, curbs, and
standing water prior to placement of the Unbonded Concrete Overlays Over back of curbs.
overlay. Concrete or Asphalt
Use a white pigment liquid curing com-
Surface cleaning is provided by sweeping of
Bonded Concrete Overlays Over pound for concrete.
the existing asphalt surface with a mechani-
Asphalt cal sweeper or air blower. Paving should For overlays with a thickness of 6 in. (150
A guideline to determine whether milling is commence soon after cleaning to minimize mm) or less, apply curing compound at
required is if asphalt surface distortions are 2 contamination. 2 times the manufacturers recommended
in. (5.08 cm) or greater. If milling is speci- application rate for a standard concrete pave-
ed, it is important that there is at least 3 to Concrete Placement ment. Do not dilute the compound.
4 in. (7.62 to 10.16 cm) of asphalt remain-
Grade Control For overlays with a thickness greater than
ing prior to the overlay. Milling should
remove the asphalt to the nearest tack line. The engineer will review and approve the 6 in. (150 mm), curing compound should
control system. Information detailing the be applied at 1.5 times the manufacturers
After milling, the surface should be inspected pavement thickness at the various survey recommended rate for a standard concrete
for further preoverlay repairs. The milling points and material quantities should also be pavement.
operation may expose wide thermal cracks. provided.
If the cracks are wider than the maximum When white pigment curing compound is
overlay aggregate size, they may be lled Concrete paver should place in single lane employed correctly, the surface of the con-
with y ash slurry, sand, or other appropriate width or be capable of adjusting the crown crete pavement should be solid white with
material. at each plan lane line when placing multiple no visible grey.
lanes.
Following any milling, partial or full depth If forms are used, apply to pavement edges
repairs should be completed with concrete to When appropriate, grade control for the pav- and back of curbs within 30 minutes after
ensure bonding with the overlay. ing operation should be referenced o the forms are removed.
milled surface, unless the milling machine is
All concrete patches plus the overlay should controlled by a previously established paver Protect concrete pavement during cold
be isolated from the rest of the overlay using control line. weather for at least 5 days, or protect for
normal joint patterns (see page 15). a minimum of 24 hours and until exural
Overlay Placement strength of 340 psi (2.3 MPa) is achieved for
Unbonded Overlays Over Concrete Surface watering may be allowed by the engi- unbonded concrete overlays, 420 to 480 psi
For uniform support of the overlay, all neer to help cool the pavement in extremely (2.9 to 3.3 MPa) for bonded concrete over-
partial and full-depth repairs should be com- warm conditions and when the existing lays over asphalt, and 540 psi (3.7 MPa) for
pleted with concrete. pavement surface condition is at or exceeds bonded concrete overlays over concrete.

Guide to Concrete Overlays 65


Joint Sawing [3.3 mm]) saw cuts are used and sealing is Bonded Overlays Over Asphalt
required, follow jurisdictional requirements Saw transverse joints to a minimum depth of
General for low modules hot-pour sealant. T/4.
The contractor should provide a joint sawing
plan that demonstrates how all saw cuts will Timing Saw longitudinal joints to a depth of T/3.
be accomplished within a shortened sawing Timely sawing is necessary to prevent ran- Early entry saws may be required unless oth-
window. Details should include the number dom cracking due to shrinkage. This is erwise specied in contract documents.
of saws and anticipated sawing production particularly important for overlays less than
When 0.13 in. (3.3 mm) wide saw cuts
rates, as well as estimated starting and nish- 6 in. (150 mm).
are used and sealing is required, follow the
ing times. All sawing must be completed
jurisdictional requirement for low modulus
within the rst one-half of the sawing Bonded Overlays Over Concrete
hot-pour sealant.
window. Prior to construction of a concrete bonded
overlay, the exact location of each contrac- Unbonded Overlays
The contractor should exercise care in plac-
tion and expansion joint in the existing Saw transverse joints to a depth of T/4
ing, consolidating, and nishing the concrete
pavement, including joints created by full- (minimum) or T/3 (maximum). For early
at and around all joints.
depth patches, should be identied and entry, saw depth will be 1.25 in. (31 mm) or
Wet sawing should be used when required by marked on both sides of the pavement by a greater.
the contract documents for dust control. reliable method.
Saw all longitudinal joints to a depth of T/3.
Transverse joints should be placed in the
Joint Width overlay pavement directly over existing trans- Sealing will follow jurisdictional
All conventional sawing widths are normally verse joints. requirements.
0.19 in. (4.8 mm) +/- 0.06 in. (1.5 mm). For unbonded overlays over asphalt, the saw
Transverse joint width must be equal to or
All early entry sawing are normally 0.13 in. greater than the underlying crack width at cut depth may need adjustment over rutted
(3.3 mm) +/- 0.06 in. (1.5 mm) in width the bottom of the existing transverse joint to asphalt location in order to maintain a depth
and a minimum T/4 inches in depth. prevent debonding due to movement. of T/4 to T/3 requirements.
When 0.13 in. (3.3 mm) saw cuts are used
Joint Seal Saw all transverse joints to full depth of over-
and sealing is required, follow jurisdictional
lay plus 0.50 in. (13 mm).
Joint sealing should follow the jurisdic- requirement for low modulus hot-pour
tional requirements. When narrow (.13 in. Saw longitudinal joints to T/2. sealant.

66 Guide to Concrete Overlays


Repairs of Concrete Overlays
Concrete overlays can be expected to provide Figure 52. Removing
excellent performance and long life. Their per- overlay panels (Photo
formance is directly related to the uniformity courtesy of Randell
and quality of the existing pavement base. Riley, P.E., Illinois
Chapter ACPA)
Isolated weak or thin spots in the existing
pavement may not be uncovered during the
pavement evaluation, overlay design, or overlay
construction phases and, like all pavement
systems, some repairs may be necessary during
its service life. If a bonded or unbonded overlay
panel becomes distressed, overlay repairs are
relatively straightforward and, in many cases,
easier to perform than repairs of conventional
concrete pavements.

Repairs of Bonded
Figure 53. Finish
or Thin Unbonded and cure of concrete
Concrete Overlays overlay repair (Photo
courtesy of Dan
Full-depth panel replacement rather than DeGraaf, P.E., Michigan
partial-depth panel replacement is typical for Concrete Paving
bonded and thin unbonded overlays, because Association)
the panels are small and relatively thin. After
full-depth sawing of the panel perimeter, the
panel can be removed easily by jack hammers
or a backhoe (gure 52).
When the overlay has been removed, the exist-
ing base should be examined. If the old existing
pavement is determined to be decient, it
should be removed and replaced with concrete;
the pavement replacement may be placed in a
separate layer or poured monolithically with Figure 54. Typical
the overlay. Asphalt should not be used as a concrete pavement
patching material since concrete does not bond milling operation
well with new asphalt. Replacing an overlay (Photo courtesy of
panel(s) is easily accomplished using typical Randell Riley, P.E.,
overlay procedures and materials (gure 53). Illinois Chapter ACPA)

Thin concrete overlays at the end of their ser-


vice life can be milled and relled easily (gures
54 and 55). Removal by milling (also referred
to as carbide milling, cold planning, and roto-
milling) is a good option for concrete overlays,
because they rely on the existing pavement base
for load transfer and therefore do not typically
require steel reinforcement.
Generally, the productivity of milling concrete
Figure 55. Typical
is very good, depending on aggregate hard-
concrete pavement
ness, bit conguration, and removal depth.
milling operation
For example, removal of a concrete overlay at (Photo courtesy of Dan
2 in. (50 mm) depth has been reported as high DeGraaf, P.E., Michigan
as 8,000 ft2/hr (720 m2/hr) and for 4 in. (100 Concrete Paving
mm) depth as low as 2,700 ft2/hr (243m2/hr). Association)

The method of removal is similar to that used


for asphalt layers, particularly when there are
no steel tiebars in the overlay.
Milling can be performed under wet or dry
conditions.

Guide to Concrete Overlays 67


The milling depth can be feathered into adja-
cent pavements. Milling can be completed on
specic selected sections. The coarseness of the
surface after milling and the neness of the
millings can vary based on the type and spacing
of milling teeth on the drum (gure 56).

Repairs of Full-Depth
Unbonded Concrete
Overlays
Full-depth unbonded overlays typically are
constructed with dowel basket and lane ties, so
common concrete pavement repair techniques
are used. These include partial or full-depth
repairs, diamond grinding, and joint resealing.
With thicker overlays (8 in. [200 mm]) subject
to heavy trac, load transfer restoration can
also be applied to restore load transfer and
mitigate joint problems.
When a uniform separation course is used,
overlay thickness will likely vary, especially
where super-elevation changes are encountered;
repairs made in these areas may require provi-
Figure 56. Typical concrete pavement millings from milling operation (Photo courtesy of Dan
sions to account for additional saw-cut depth.
DeGraaf, P.E., Michigan Concrete Paving Association)
Standard full-depth concrete removal tech-
niques are used on thicker overlays. However,
8 to 9 in. (200 to 250 mm) concrete overlays
have been successfully removed by milling.

68 Guide to Concrete Overlays


Appendix A. Evaluation and Selection Tables

Table 12. Distress types and severity levels recommended for assessing concrete pavement structural adequacy

Current Distress Level


Load-Related Distress Highway Classification
Adequate Marginal Inadequate
Jointed plain concrete medium- and high- Interstate/Freeway <5 5 to 10 >10
severity transverse and longitudinal cracks
and corner breaks (% slabs) Primary <8 8 to 15 >15
Secondary <10 10 to 20 >20

Jointed reinforced concrete medium- and Interstate/Freeway <15 15 to 40 >40


high- severity transverse cracks and corner
Primary <20 20 to 50 >50
breaks (#/lane-miles)
Secondary <25 25 to 60 >60

Jointed plain concrete mean transverse Interstate/Freeway <0.10 (2.5 mm) 0.10 to 0.15 (2.5 to 3.8 mm) >0.15 (3.8 mm)
joint/crack faulting (in.)
Primary <0.125 (3.2 mm) 0.13 to 0.20 (3.3 to 5.1 mm) >0.20 (5.1 mm)

Secondary <0.15 (3.8 mm) 0.15 to 0.30 (3.8 to 7.6 mm) >0.30 (7.6 mm)

Jointed reinforced concrete mean transverse Interstate/Freeway <0.15 (3.8 mm) 0.15 to 0.30 (3.8 to 7.6 mm) >0.30 (7.6 mm)
joint/crack faulting (in.)
Primary <0.175 (4.5 mm) 0.18 to 0.35 (4.6 to 8.9 mm) >0.35 (8.9 mm)
Secondary <0.20 (5.1 mm) 0.20 to 0.40 (5.1 to 10.2 mm) >0.40 (10.2 mm)

Continuously reinforced concrete Interstate/Freeway <5 5 to 10 >10


medium- and high-severity punchouts
Primary <8 8 to 15 >15
(#/lane-miles)
Secondary <10 10 to 20 >20

Applicability of Bonded Concrete Overlays


Applicability of Unbonded Concrete Overlays

Table 13. Distress types and levels recommended for assessing asphalt and composite pavement structural adequacy

Distress Level
Distress Type Highway Classification
Adequate Marginal Inadequate
Fatigue cracking (% of wheel path area) Interstate/Freeway <5 5 to 20 >20

Primary <10 10 to 45 >45


Secondary <10 10 to 45 >45
Longitudinal cracking in wheel path (ft/mi) Interstate/Freeway <265 (50.2 m/km) 265 to 1060 (50.2 to 200.8 m/km) >1060 (200.8 m/km)
Primary <530 (100.4 m/km) 530 to 2650 (100.4 to 501.9 m/km) >2650 (501.9 m/km)
Secondary <530 (100.4 m/km) 530 to 2650 (100.4 to 501.9 m/km) >2650 (501.9 m/km)

Composite pavement reflection cracking crack Interstate/Freeway <0.50 (12.7 mm) 0.25 to 0.50 (6.4 to 12.7 mm) >0.50 (12.7 mm)
width (in.)
Primary <0.50 (12.7 mm) 0.50 to 0.75 (12.7 to 19.1 mm) >0.75 (19.1 mm)
Secondary <0.50 (12.7 mm) 0.50 to 0.75 (12.7 to 19.1 mm) >0.75 (19.1 mm)

Transverse crack spacing (ft) Interstate/Freeway >200 (61.0 m) 100 to 200 (30.5 to 61.0 m) <100 (30.5 m)
Primary >120 (36.6 m) 60 to 120 (18.3 to 36.6 m) <60 (18.3 m)
Secondary >120 (36.6 m) 60 to 120 (18.3 to 36.6 m) <60 (18.3 m)

Mean depth of rutting in both wheel paths (in.) Interstate/Freeway <0.25 (6.4 mm) 0.25 to 0.40 (6.4 to 10.2 mm) >0.40 (10.2 mm)
Primary <0.35 (8.9 mm) 0.35 to 0.60 (8.9 to 15.2 mm) >0.60 (15.2 mm)
Secondary <0.40 (10.2 mm) 0.40 to 0.80 (10.2 to 20.3 mm) >0.80 (20.3 mm)

Shoving (% of wheel path area) Interstate/Freeway None 1 to 10 >10


Primary <10 10 to 20 >20
Secondary <20 20 to 45 >45
Applicability of Bonded Concrete Overlays
Applicability of Unbonded Concrete Overlays

Guide to Concrete Overlays 69


Appendix B. Sample Geotextile Specifications
(Germany)
The following specications for geotextile interlayers in Germany are taken from Rasmussen (2008).

Design Specifications
Property Requirement*
Fabric Type Non-woven Geotextile
Uniform color

Mass per unit area 13.3 oz/yd2 (450 g/m)


16.2 oz/yd2 (550 g/m)

Thickness 0.29 psi (2 kN/m): 0.12 in. (3.0 mm)


under load (pressure) 2.9 psi (20 kN/m): 0.10 in. (2.5 mm)
29 psi (200 kN/m): 0.04 in. (1.0 mm)

Tensile strength 685 lb/ft (10 kN/m)

Maximum elongation 130%

Water permeability in normal direction 3.310-4 ft/s (110-4 m/s)


under load (pressure) [under pressure of 2.9 psi (20 kN/m)]

Water permeability in the plane direction of the fabric (transmittivity) 1.610-3 ft/s (510-4 m/s)
under load (pressure) [under pressure of 2.9 psi (20 kN/m)]
6.610-4 ft/s (210-4 m/s)
[under pressure of 29 psi (200 kN/m)]

Weather resistance Resistance 60% (per EN 12,224)

Alkali resistance 96% Polypropylene/Polyethylene

* Specifications must be met for 95% of samples.



60% maximum is recommended as a better practice.

Quality Control
The rst sample of fabric is taken after placement of 1,200 yd2 (1,000 m)
Second sample after 12,000 yd2 (10,000 m)
One sample every 12,000 yd2 (10,000 m) thereafter.
Samples are 1.20 yd2 (1 m) in size.
Testing of samples to meet requirements is on a dierent schedule for each requirement.

Cost
Material cost for the geotextile appears to be $1.50 to $2.00 per yd2 (circa 2008)
Installation cost is on the order of $0.50 per yd2 (circa 2008)

70 Guide to Concrete Overlays


Appendix C. Innovative Methods for Accelerated
Concrete Overlay Construction
The following table provides a summary of innovative accelerated construction methods (adapted from Simon et al. 2003).

Table 14. Applicability, pros, and cons of various accelerated construction methods

Method Applicability / Limitations Pros(+) / Cons(-)


Formal partnering with design This method has not been used + Provides a faster and cheaper construction process due to reduction of conflicts,
consultants, contractors, local very much with designers or other litigation, and claims (win-win situation)
authorities, and regulatory agencies agencies.
+ Brings about continuous improvement in the quality of services and products
Little training has been done and
+ Utilizes resources more effectively
much skepticism is in place regarding
this method. + Implements easily because is already being used on an informal basis
+ Improves communications
Limits completive market strategy
Creates strong dependency on the partners

Methods for expediting utility In highway construction, the need for + Encourages project managers to develop more economical means and methods
relocation work the relocation of utilities often arises,
+ Shortens project execution by using less formal documentation and improving
particularly in urban areas.
communication
Relocation is handled primarily by
+ Reduces executive personnel
utility companies.
+ Produces more continuity during the project
Currently, there is little recourse
that can be taken against utilities for Brings about need for independent engineers to check PMs work
delays.
Encourages overcoming the specialist mindset of the organization
Utilities have to pay for relocations.

Intelligent Transportation Systems Applicable areas include but are + Increases safety
(ITS) and work-zone traffic control not limited to traffic control, route
+ Reduces congestion
guidance, automated highway
systems, collision avoidance, + Enhances mobility
en-route driver information,
transportation demand management, + Minimizes environmental impact
etc. + Increases energy efficiency
+ Promotes economic productivity for healthier economy
Requires additional training of employees
Includes costs to implement

Public input on phasing of This method is applicable on + Allows for more expeditious construction methods to be employed
construction construction projects where there is
Requires more public relations effort earlier
a significant impact on the public.

Multiple approaches to Traffic TCP solutions for small simple + Reduces both construction costs and user costs through optimal TCPs
Control Plans (TCPs) jobs are often apparent, but
Requires larger consultant fees for development because of more thorough TCP
otherwise they should be thoroughly
analysis
investigated earlier in the process.

Descriptive catalog of construction Applicability of new technologies + Provides an online catalog that could easily be accessed and supported by FHWA
technologies could be widespread, but and other states
specifications may be affected.
Requires effort for maintenance and upkeep of the catalog

Contractor preparation of the TCP This approach will encourage + Reduces efforts
based on minimum requirements contractor innovation, but may be
+ Provides incentive for construction innovation
possible only on smaller, simpler
projects. Increases costs
Excludes impact on local businesses
Means that contractor compliance with safety standards may be challenging

Linear Scheduling Method (LSM) This method can be used for + Provides a better understanding of the project
and accurate productivity to rate repetitive projects in which there are
+ Enables the planner to determine when and where a change in resources must
data and establish project target no strict dependencies/constraints
take place to satisfy the goals set by the project
between project activities.
duration
+ Helps identify existing relationships and encourages the project team to try
Resurfacing overlays and shoulder
different alternatives
improvement are good types of
projects for the LSM. + Shortens schedule by overlapping activities instead of sequencing
Scheduling projects involving large cuts and fills might be more difficult to
schedule with LSM

Guide to Concrete Overlays 71


Table 14. Applicability, pros, and cons of various accelerated construction methods, continued

Method Applicability / Limitations Pros(+) / Cons()


A+B contracting (costs plus time) A+B bidding can be used to motivate + Includes consideration of the time component of a construction contract
the contractor to minimize the
+ Includes favorable treatment of contractors with the most available resources to
delivery time for high priority and
complete the project
highly trafficked roadways.
+ Involves incentives for contractors to compress the construction schedule
There must be a balance between the
benefits of early completion and any + Includes greater potential for early project completion
increased cost of construction.
Requires that incentives and disincentives are carefully managed
This approach requires incentives
and disincentives to be effective. Means that costs are defined whereas benefits are distributed to the public

Contractor milestone incentives Incentives must be relevant. + Encourages contractors to finish on time
Goals must be reachable. Causes impacts to contractors to be highly scrutinized
Incentives cannot be conflicting. Causes disagreements over compensable delays that may be problematic

Packaged multi-primes contracting This method can be used when a + Increases competition among construction bidders
specific highway project is composed
+ Reduces pyramiding of costs, particularly overhead and profit
of several major segments or is very
large. + Reduces project time through overlap of design and construction or from multiple
work forces
+ Requires more direct control by the project owner
Presents interface management challenges for the agency
Leads to physical interferences between contractors

Pre-qualified bidders based on past Bidders qualify based on several key + Provides a shorter and easier selection process
schedule performance items, including specific project type
+ Provides possibly better contractors
experience, individual experience,
past performance, capacity of the Reduces the competition
firm, and the primary firm location.
Requires that schedule performance data are well kept
Requires that agency and other noncontractual schedule impacts are recognized
and equitably settled

Incentives for TCP development To use this method, seek involvement + Leads to innovative ideas for successful TCPs
with a contractor who values an of local municipalities in funding the
Means that savings are difficult to estimate
engineering cost-savings sharing incentive (e.g., 5% of estimated user
cost savings).
provision
This method requires close scrutiny
to determine actual time savings.

Incentives for contractor work Incentives must be explicitly + Leads to innovative ideas for successful TCPs
progress with a lane-rental described in the bid package.
+ Minimizes contractor impact on the traffic
approach Rental rates have to be significant
Causes administration to be difficult
and should address high impact
lanes.

Increased amount of liquidated Just as important as the damages + Motivates better contractor performance
damages and routine enforcement happening in the contract are the
Requires rigorous documentation and quick request for information (RFI) response
claims made for damages. The time
to enforce
and effort involved in pursuing these
claims is, however, a limitation. This
should be weighed against potential
benefits.
Possibly provide incentives to finish
projects ahead of time.

No excuse incentives These incentives preclude delay + Results in considerable improvements in schedule performance
claims by contractors, give
Transfers risk to contractor and therefore may increase costs on the average over
contractors incentives to finish early,
time
and require a realistic schedule.

Tools and best practices for New technologies (such as intrusion + Increases safety for road users and workers
implementing multiple work shift alarms), modified traffic control plans,
+ Reduces user costs
and/or night work and new methods to monitor traffic
provide improvements in night work- + Provides faster completion time
zone safety.
Requires research and design costs
These improvements will lead to high
nighttime productivity.

72 Guide to Concrete Overlays


Table 14. Applicability, pros, and cons of various accelerated construction methods, continued

Method Applicability / Limitations Pros(+) / Cons()


Exploitation of web-based team To be efficient, access to information + Enhances project communication
collaboration system is needed quickly and without
+ Eases collaboration with project managers, designers, contractors, vendors, and
hassle. A web-based system can be
the public
used to track project deliverables,
track project tasks online, receive + Keeps everyone in the loop
email alerts as items become due,
share documents, and reduce + Allows tracking of project online which minimizes time taken and enhances
administrative document production performance
and delivery cost by uploading Requires high installation and learning costs
documents. This is handy for CAD
drawings or anything else that needs Lacks standards
to be shared with the project team.

Encouragement of the use Numerous research and + Results in possible savings


of automated construction implementation efforts are currently
+ Presents opportunity for significant schedule compression
technologies underway to automate conventional
infrastructure construction, condition Requires some training
assessment, and maintenance
actives such as earth moving, Requires contractor implementation
compaction, road construction, and
maintenance.
Commercial systems are available

Employment of methods for These methods can be used where + Decreases duration and unit costs
continuous work zones road geometry and weekend or night
+ Increases safety
scheduling permit.
Results in possible higher user costs and traffic congestion

Use of windowed milestone This method can be used where + Lowers project costs
milestone dates are not based on
+ Lowers user costs
hard constraints. Milestones should
be related to allow the contractor Reduces ability to hold contractors feet to the fire
maximum flexibility in efficiently
allocating project resources.

Schedule of calendar day projects Scheduling calendar day projects + Produces better weather management
is applicable to projects where the
+ Provides a direct method of expediting
completion is critical and a large
volume of traffic is affected. Requires strict adherence to the schedule for credibility with the public, even with
breakdowns or weather problems
Construction time shortened by full Full closure could be used in areas + Shortens construction time
closure of the roadway instead of where there is at least one alternative
Causes possible traffic congestion on alterative routes
partial closure route for drivers and where volume
is limited.

Duration and productivity effects Data collected can be very useful in + Produces quicker and more dependable exploitation of new technologies
tracked and associated with cost and time estimation for optimal
Requires personnel to devote time to properly monitor and record data
different technologies plans.
Can be perceived as costly
Technology choices may be limited,
however, by project conditions and
logical equipment spreads.

Optimal approaches to crew shifts The schedule can be shortened + Provides possible cost savings
and scheduling to eliminate long through use of additional crews on
+ Increases productivity
work hours regular shift, multiple shifting, or
selective overtime. + Reduces cycle time of tasks which improves the schedule
Scheduled overtime can be used Creates possible negative results if planning is done carelessly
where appropriate but effects should
be evaluated carefully. Creates a necessity for contractor to implement

Selected field personnel trained in Schedule flexibility may be minimal in + Creates a flexible and quick-to-adapt project team
scheduling methods and claims practice, but for complex jobs a broad
+ Leads to faster project completion
understanding of scheduling issues
should help expedite progress. Leads to possibly too many people trying to manage

Lessons learned database on ways This database would be broadly + Requires quick reference for implementation of expediting measures
to expediate schedules applicable but limited by legal and
Creates a need for the database to be maintained
policy constraints.

Guide to Concrete Overlays 73


Sources
References Christopher, B.R. 2000. Maintenance of 00-F-00199. Champaign, IL: ERES
Highway Edgedrains. NCHRP Synthesis of Consultants. http://isddc.dot.gov/OLPFiles/
AASHTO. 1993. Guide for Design of Highway Practice 285. Washington, DC: TRB. FHWA/010942.pdf.
Pavement Structures. Washington, DC: http://ntl.bts.gov/lib/17000/17600/17652/
PB2001102763.pdf. Mathis, D.M. 1990. Pavement Drainage
American Association of State Highway and Rehabilitation. Proceedings, Virginia Pavement
Transportation Ocials. Cole, L.W., and P.A. Okamoto. 1995. Flexural Drainage Workshop. Williamsburg, VA: Virginia
. 1998. Supplement to the AASHTO Strength Criteria for Opening Concrete Roadways Department of Transportation.
Guide for Design of Pavement Structures. to Trac. Transportation Research Record
. 2005. Versions 0.900 and 1.0
Washington, DC: American Association of 1478: 5361.
of the M-E Pavement Design Software.
State Highway and Transportation Ocials. Daleiden, J. 1998. Video Inspection of Highway NCHRP Project 1-40A. Washington, DC:
. 2002. Guide for Design of New and Edgedrain Systems. FHWA-SA-98-044. Transportation Research Board.
Established Pavement Structures. Washington, Washington, DC: FHWA.
. 2006. Technical Assistance to
DC: Transportation Research Board. FHWA. 1992. Drainable Pavement Systems, NCHRP and NCHRP Project 1-40a.
. 2007. A New Vision for the 21st Participant Notebook. FHWA-SA-92-008. NCHRP Project 1-40d. Washington, DC:
Century: Transportation Invest in Our Future. Washington, DC: FHWA. Transportation Research Board.
Washington, DC: AASHTO. http://www. . 1994. Guidelines for Timing . 2007. AASHTO Mechanistic-Empirical
transportation1.org/tif5report/TIF5.pdf Contraction Joint Sawing and Earliest Loading Design Guide. Version 1.0. NCHRP Project
ACI Committee 325. 2006. Concrete Overlays for Concrete Pavements, Volume 1. FHWA-RD- 1-37a. Washington, DC: Transportation
for Pavement Rehabilitation. Publication ACI 91-079. Washington, DC: FHWA. Research Board.
325.13R-06. Farmington Hills, MI: American . 2002a. Conventional Whitetopping Raphael, J.M. 1984. Tensile Strength of
Concrete Institute. Overlays. Technical Brief. FHWA-IF-03-008. Concrete. ACI Journal 163: 158165.
ACPA. 1990a. Guidelines for Bonded Concrete Washington, DC: FHWA.
Rasmussen, R.O., and D.K. Rozycki.
Overlays. Technical Bulletin TB-007P. Skokie, . 2002b. Unbonded Portland 2004. Thin and Ultra-Thin Whitetopping.
IL: American Concrete Pavement Association. Cement Concrete Overlays. Technical Brief. NCHRP Synthesis of Highway Practice 338.
. 1990b. Guidelines for Unbonded FHWA-IF-03-006. Washington, DC: FHWA. Washington, DC: Transportation Research
Concrete Overlays. Technical Bulletin TB-005P. Board.
. 2003a. Distress Identication
Skokie, IL: American Concrete Pavement Manual for the Long-Term Pavement Rasmussen, R.O. 2008. Geotextile Interlayers
Association. Performance Program. Fourth Revised Edition. for Separating Cementitious Pavement Layers:
. 1991. Guidelines for Concrete Overlays FHWA-RD-03-031. Washington, DC: Eurpoean Practice and U.S. Field Trials.
of Existing Asphalt Pavements (Whitetopping). FHWA. Washington, DC: FHWA and Transtec Group,
Technical Bulletin TB-009P. Skokie, IL: Inc.
. 2003b. Manual on Uniform Trac
American Concrete Pavement Association. Control Devices. 2003 Edition with revisions 1 Roesler, J.R. 2004. Fracture of Plain and Fiber-
. 1998. WhitetoppingState of the and 2 incorporated. Washington, DC: FHWA. Reinforced Concrete Slabs under Monotonic
Practice. Engineering Bulletin EB210.02P. Loading. Journal of Materials in Civil
Hall, K.T., C.E. Correa, S.H. Carpenter, and Engineering 16(5): 452460.
Skokie, IL: American Concrete Pavement R.P. Elliott. 2001. Rehabilitation Strategies for
Association. Highway Pavements. NCHRP Project C1-38. Roesler, J.R. 2007. Design and Specication
. 1999. Construction Specication Washington, DC: Transportation Research of Concrete Pavements with Structural Fibers.
Guideline for Ultra-Thin Whitetopping. Board. Paper presented at the International Workshop
Information Series IS120P. Skokie, IL: on Best Practices for Concrete Pavements,
Hoerner, T.E., K.D. Smith, H.T. Yu, D.G. Recife, Brazil.
American Concrete Pavement Association. Peshkin, and M J. Wade. 2001. PCC Pavement
. 2000a. Trac Management Handbook Evaluation and Rehabilitation: Reference Simon, E., G. E. Gibson, C. T. Haas, J. T.
for Concrete Pavement Reconstruction and Manual. NHI Course 131062. Arlington, VA: OConnor, B. Somali, and Z. Zhang. 2003.
Rehabilitation. Publication EB213P. Skokie, IL: National Highway Institute. Development of a Tool for Expediting Highway
ACPA. Construction While Retaining Quality. FHWA/
Leykauf, G., and D. Birmann. (2006). TX-03/4386-1. Austin, TX: Center for
. 2000b. Repair of Ultra-Thin Concrete Pavements with Geotextile Interlayer Transportation Research, University of Texas at
Whitetopping: Roadways and Airelds. in Germany: Measurements and Long-term Austin.
Publication PA397P. Skokie, IL: American Behavior. Proceedings, 10th International
Concrete Pavement Association. Symposium on Concrete Roads. Brussels, Smith, K.D., H.T. Yu, and D.G. Peshkin.
Belgium: European Cement Organisation 2002. Portland Cement Concrete Overlays:
. 2006. Concrete Pavement Field (CEMBUREAU), World Road Association State of the Technology Synthesis. Publication
Reference: Preservation and Repair. Publication (PIARC). CD-ROM. FHWA-IF-02-045. Washington, DC: Federal
EB 239 P. Skokie, IL: ACPA. Highway Administration.
Mallela, J., G. Larson, T. Wyatt, J. Hall,
. 2007. Subgrades and Subbases for and W. Barker. 2002. Users Guide for Smith, K.D., T.E. Hoerner, and D.G. Peshkin.
Concrete Pavements. EB204P. Skokie, IL: Drainage Requirements in Pavements: DRIP 2008 (draft). Concrete Pavement Preservation
American Concrete Pavement Association. 2.0 Microcomputer Program. DTFH61- Reference Manual. FHWA (no. to be assigned).
Ames, IA: National Concrete Pavement
Technology Center, Iowa State University.

74 Guide to Concrete Overlays


Trevino, M., B.F. McCullough, and D.W. Cable, J.K., L.E. Edgar, and D.R. Anderson. Riley, R.C., A. Gotlif, and J. Mallela.
Fowler. 2004. Techniques and Procedures for 2005. Ultra-Thin Portland Cement Concrete 2005a. Whitetopping: Atypical is Typical.
Bonded Concrete Overlays. FHWA/TX-05/0- Overlay Extended Evaluation. IHRB Project Proceedings of the International Conference
4398-2. Austin, TX: Center for Transportation TR-432. Ames, IA: Iowa State University. on Best Practices for Ultrathin and Thin
Research, University of Texas at Austin. Whitetoppings. Denver, CO, April 1215,
Cable, J.K., F.S. Fanous, H. Ceylan, D. Wood, 2005.
VDOT. 1990. Guidelines for Providing D. Frentress, T. Tabbert, S.-Y. Oh, and K.
Improved Drainage Systems for VDOT Gopalakrishnan. 2005. Design and Construction Riley, R.C., L. Titus-Glover, J. Mallela, S.
Pavement Structures. Charlottesville, VA: Procedures for Concrete Overlay and Widening Waalkes, and M. Darter. 2005b. Incorporation
Virginia Department of Transportation. of Existing Pavements. IHRB Project TR-511. of Probabilistic Concepts into Fatigue Analysis
Ames, IA: Iowa State University. of Ultrathin Whitetopping as Developed for
Wells, G.K., and S.M. Wiley. 1987. The the American Concrete Pavement Association.
Eectiveness of Portland Cement Concrete Cable, J.K., J.M. Hart, and T.J. Ciha. 2001. Proceedings of the International Conference
Pavement Rehabilitation Techniques. FHWA/ Thin Bonded Overlay Evaluation. IHRB Project on Best Practices for Ultrathin and Thin
CA/TL-87/10. Washington, DC: FHWA. HR-559. Ames, IA: Iowa State University. Whitetoppings. Denver, CO, April 1215,
Young, B. 1990. Evaluation of the Performance Delatte, N., S. Chen, J. Davidson, A. Sehdev, 2005.
of Fin Drains in Georgia. FHWA-GA-90-8709. N. Amer, and M. Endnger. 2001. Design and Sheehan, M.J., S.M. Tarr, and S.D. Tayabji.
Atlanta, GA: Georgia Department of Quality Control of Concrete Overlays. UTCA 2004. Instrumentation and Field Testing of
Transportation. Report 01220. Tuscaloosa, AL: University Thin Whitetopping Pavements in Colorado
Transportation Center for Alabama. and Revision of the Existing Colorado Thin
Bibliography ERES Consultants. 1999. Evaluation of Whitetopping Procedure. Report CDOT-
Unbonded Portland Cement Concrete Overlays. DTD-R-2004-12. Denver, CO: Colorado
AASHTO. 1993. Guide Specications for NCHRP Report 415. Washington, DC: Department of Transportation.
Highway Construction. Washington, DC: Transportation Research Board. Tarr, S.M., M.J. Sheehan, and P.A. Okamoto.
AASHTO.
FHWA. 1999. Pavement Preventive 1998. Guidelines for the Thickness Design of
ACPA. 1999. Ultra-Thin Whitetopping. Maintenance Reference Manual. Washington, Bonded Whitetopping Pavements in the State
Information Series IS100.02P. Skokie, IL: DC: FHWA. of Colorado. Report CDOT-DTD-R-98-10.
American Concrete Pavement Association. Denver, CO: Colorado Department of
. 2000. Insights into Pavement Transportation.
. 2007. Concrete Intersections: A Preservation: A Compendium. Washington, DC:
Guide for Design and Construction. TB019P. FHWA. Titus-Glover, L., J. Mallela, M.I. Darter,
Skokie, IL: American Concrete Pavement G. Voigt, and S. Waalkes. 2005. Enhanced
Association. . 2001. Pavement Preservation: Selecting Portland Cement Concrete Fatigue Model
Pavements for Preventive Maintenance. NHI for StreetPave: Rigid and Flexible Pavement
. 2008. Concrete Pavement Field Course 131058. Washington, DC: FHWA. Design 2005. Transportation Research Record
Reference: Pre-Paving. EB237P. Skokie, IL:
. 2001. PCC Pavement Evaluation 1919:2937.
American Concrete Pavement Association.
and Rehabilitation. NHI Course 131062. Vandenbossche, J.M., and A.J. Fagerness. 2002.
Altoubat, S.A., J.R. Roesler, D.A. Lange, K.-A. Washington, DC: FHWA. Performance, Analysis, and Repair of Ultrathin
Rieder. March 1, 2008. Simplied method
. 2004. Pavement Preservation: and Thin Whitetopping at Minnesota Road
for concrete pavement design with discrete
Integrating Pavement Preservation Practices Research Facility. Transportation Research Record
structural bers. Construction and Building
and Pavement Management. NHI Course 1809:191198.
Materials.
131104. Washington, DC: FHWA. Winkelman, T.J. 2002. Bonded Concrete
Anderson, S.D., G.L. Ullman, and B.C.
. 2007. Thin Whitetoppingthe Overlay Performance in Illinois. Report
Blaschke. 2002. A Process for Selecting
Colorado Experience. FHWA-HIF-07-025. FHWA/IL/PRR 143. Springeld, IL: Illinois
Strategies for Rehabilitation of Rigid Pavements.
Washington, DC: FHWA. Department of Transportation.
NCHRP Project 10-50A. Washington, DC:
Transportation Research Board. Mack, J.W., L.D. Hawbaker, and L.W. Cole. Wu, C.-L., S.M. Tarr, T.M. Refai, M.A.
1998. Ultrathin Whitetopping: State-of-the- Nagi, and M.J. Sheehan. 1999. Development
Cable, J.K., M.L. Anthony, F.S. Fanous, and
Practice for Thin Concrete Overlays of Asphalt. of Ultra-Thin Whitetopping Design Procedure.
B.M. Phares. 2006. Evaluation of Composite
Transportation Research Record 1610:3943. PCA R&D Serial 2124. Skokie, IL: Portland
Pavement Unbonded Overlays. IHRB Project
Cement Association.
TR-478. Ames, IA: Iowa State University. McGhee, K.H. 1994. Portland Cement Concrete
Resurfacing. NCHRP Synthesis of Highway
Practice 204. Washington, DC: Transportation
Research Board.

Guide to Concrete Overlays 75


2711 South Loop Drive, Suite 4700
Ames, IA 50010-8664
515-294-5798
www.cptechcenter.org

ACPA publication TB021.02P

You might also like