Evaluation of the track quality

11/09/201609/09/2016 | Constantin | alignment, cross-level, SD, TQI, track, track quality, Track Superstructure

Track measurement

The importance of knowing the track geometric quality arose in the middle of 20th century, when European infrastructure managers developed their own
track recording vehicles allowing a continuous measurement of track geometry and based on this, their own track geometry quality evaluation standards (EN 13848-6).

Periodic track measurement is required to evaluate the track quality and maintain an eective railway track system safe and with good vehicle ride quality.

The track quality output requires as a minimum the following (EN 13848-6):

Isolated defects that exceed a prescribed threshold and require intervention. This defect review is ensuring the safety of the railway track system.
A Track Quality Index (TQI). This is produced over a specic length of track and is the one that denes the riding quality.

Track defect

Any track parameter is dened by a nominal value which is the characteristic of an ideal track.

For example, the gauge nominal value is 1435 mm. Some railway networks dene for the normal gauge and some specic applications variations of this gure: 1432,
1433, 1438. All these are nominal gauge values for those track applications.

Example of track defect assessment the evaluation of gauge irregularities acc


to NR/L2/TRK/001/mod11

The installation, usage and maintenance of the railway track do not allow installing and maintaining the track parameters exactly to their nominal value. A real track
will be always characterised by variations of the nominal values for all the track parameters.

In the case of gauge we will nd the nominal value of 1435 mm only by chance. The measured gauge will be in a (narrow or wide) range around its nominal value.

All the variances from the nominal value dene the track irregularities.

In order to evaluate the track quality, these track irregularities are divided into two main categories:

tolerance accepted variance from the nominal value


defect (fault) nominal value variance that is not acceptable and require intervention to keep the track system safe.

The railway administrators dene, for each of the relevant track parameters and dependent on speed or other factors, three main levels of action:

Alert Limit (AL) the irregularity is still tolerated but requires a9ention.

1 of 3 13/09/2016 10:53
Evaluation of the track quality A Railway Track Blog https://pwayblog.wordpress.com/2016/09/11/evaluation-of-track-quality/

Intervention Limit (IL) the track irregularity has become a defect and correction needs to take place within a certain period of time.
Immediate Action Limit (IAL) the defect has reached a safety limit and requires immediate remedial actions.

Track Quality Index (TQI)

Some of the Track Quality Indexes used by the European Railway Networks are (EN 13848-6):

The number of insulated defects over a specic length (e.g. 1km). This is a very simple way of evaluating the track quality and is still used by several European
Railway Networks. Each defect and, sometimes, tolerated irregularity close to the defect limit, is scored and summed to produce the general defect scoring of that
length of track.
Parameters dened through the Vehicle Response Analysis (VRA). This is either a directly measured parameter or the product of a mathematical model that
quanties the vehicle response to the track irregularities.

Vehicle reactions calculated through vehicle response analysis VRA (Esveld 2001)

Power Spectral Density (PSD) this Track Quality Index evaluates the energy of the measured signal in relation to its frequency for a given track parameter.

Power spectral density (PSD) functions for track geometry measurements


carried out for ORE D 161 on dierent European railway networks (Esveld
2001)

Standard Deviation (SD). It is calculated for each specic wavelength range over a dened length, typically 200m. There is a direct relationship between Standard
Deviation (SD) and the Power Spectral Density (PSD).
Combination of various parameters. For example the TQI can be expressed as a combined standard deviation (CoSD) computed based on the dierent set of SD
considered in the measurement of track quality (for alignment, cant, gauge, cross level, longitudinal level).

(To be continued)

References

2 of 3 13/09/2016 10:53
Evaluation of the track quality A Railway Track Blog https://pwayblog.wordpress.com/2016/09/11/evaluation-of-track-quality/

Berawi, A. R. B. (2013). Improving Railway Track maintenance using Power Spectral Density (PSD) (h2ps://sigarra.up.pt/feup/pt/pub_geral.show_le?pi_gdoc_id=360013).
PhD Dissertation. Universidade do Porto.

BS EN 13848-1:2003 + A1:2008. Railway applications Track Track geometry quality Part 1: Characterisation of track geometry.

BS EN 13848-2:2006. Railway applications Track Track geometry quality Part 2: Measuring systems Track recording vehicles.

BS EN 13848-5:2008 + A1:2010. Railway applications Track Track geometry quality Part 5: Geometric quality levels Plain line.

BS EN 13848-6:2014. Railway applications Track Track geometry quality Part 6: Characterisation of track geometry quality.

Esveld, C. (2001). Modern Railway Track. (h9p://www.esveld.com/MRT.html) MRT Productions. (Chapter 6. Dynamic track design)

Karis, T (2009). Track Irregularities for High-Speed Trains. Evaluation of their correlation with vehicle response (h2ps://www.diva-portal.org/smash/get/diva2:840707
/FULLTEXT01.pdf). Master of Science Thesis. KTH Engineering Sciences.

Lewis, R. (2011). Track Geometry Recording and Usage (h2p://www.infrastructuremonitoring.co.uk/wp-content/uploads/2011/10/Track-Recording-And-Usage.pdf). Notes for a
lecture to Network Rail. (Read this one, is very good!)

NR/L2/TRK/001/mod11 (2013). Track geometry Inspections and minimum actions. Issue 6. Network Rail.

NR/L2/TRK/2102 (2015). Design and Construction of Track. Issue 7. Network Rail.

*** (2008). Improving Alignment Designs. I&I Track Programme. Network Rail.