You are on page 1of 53

New Tube for London

Feasibility Report
October 2014

New Tube for London - Feasibility Stage Summary 1


2 New Tube for London - Feasibility Report
New Tube for London - Feasibility Stage Summary 3
Contents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Context .....................................................7
Strategy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
System constraints ...........................................8
Asset renewal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9
NTfL programme . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Vision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Status . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Feasibility challenges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Summary of feasibility activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Capacity - rolling stock . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Capacity - signalling and control . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
Capacity infrastructure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Capacity modelling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Saloon air-cooling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Managing tunnel temperatures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Higher levels of automation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Project migration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
Feasibility outcomes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
Functional concept . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Design concept . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
Time savings and capacity improvements . . . . . . . . . . . . . . . . . . . . . . 46
Service patterns. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .47
The platform experience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
List of figures and images . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52

4 New Tube for London - Feasibility Report


Introduction
London is growing rapidly. By 2031, Our aim is to achieve a steady state
there will be an extra 1.8m people of renewal where modernisation is
living and working in the Capital a continual process, built into our
thats an extra Tube train of people everyday operations. This will
every three days. As a result, minimise disruption and will also
demand for Transport for London provide best value for London and
(TfL) services Underground, the UK, as well as creating certainty
Overground, Docklands Light for our supply chain and
Railway and Trams is growing too. consequently greater value for
In 2013-14, London Underground money.
alone carried over 1.25 billion In order to achieve this aim, we
customers. must first finish the network
Our vision is to be world class modernisation weve started.
despite the challenge of delivering Around two-thirds of our lines are
improved services to an ever- being or have already been
growing population. modernised. We are delivering
We have recently started to world class service frequencies on
experience the benefits of the the Victoria and Jubilee lines as a
renewal and modernisation of result of this investment, with work
many of our lines in the level of underway to achieve even higher
service and comfort we offer. frequencies.
Our approach is defined by four This year, the Northern line upgrade
priorities. These are: safety and will deliver a 20 per cent increase in
reliability, maximising capacity from capacity and works continue to
the existing network, growing the modernise the Circle, District,
network and meeting the growing Hammersmith & City and
expectations of our customers by Metropolitan lines.
providing excellent customer The introduction of Crossrail
service. services in 2018 will also contribute

New Tube for London - Feasibility Stage Summary 5


to the growth of our network, complete by 2025. The remaining
increasing rail-based capacity in lines will follow in a sequence
London by 10 per cent. which will maximise the benefit
By the 2020s, the Bakerloo, Central, from our investment.
Piccadilly and Waterloo & City lines This comprehensive modernisation
will be operating the oldest trains programme for the deep Tube lines
and signalling on the Tube. We are is referred to as the New Tube for
therefore developing a programme London (NTfL) programme.
for a comprehensive modernisation A feasibility study has been
of these deep Tube lines. For the conducted to examine the technical
first time, we are procuring a single challenges of delivering this
train fleet and signalling system. programme and this report
We expect the Piccadilly line to be documents the studys results.
first, with modern, air-cooled trains
entering service in the early 2020s
and the full modernisation

6 New Tube for London - Feasibility Report


Context
Strategy
TfLs major programme of investment to
upgrade its existing lines and stations, TfL Rail & Underground Priorities
and implement new or extended rail Improve reliability and safety
services aims to contribute to the
Mayors Transport Strategy by meeting Improve customer service
the goals of:
Increase capacity from current network
Supporting economic development
and population growth Increase capacity by growing the network
Enhancing the quality of life for
The NTfL programme provides the
Londoners
opportunity to advance three of these
Improving transport opportunities for
key TfL Rail & Underground priorities on
Londoners
the deep Tube lines: improving reliability
Improving the safety and security of
and safety; improving customer service;
Londoners
and increasing capacity from the current
In meeting these goals and ensuring the network.
transport needs of London are met, TfL
Rail & Underground has established four
key priorities for its business, as follows:

London Underground Peak Hour Crowding


in 2021 with committed upgrades

New Tube for London - Feasibility Stage Summary 7


Context
System Constraints
The Edwardian-era tunnel infrastrucure comprised the Baker St & Waterloo, the
presents a formidable challenge to the Piccadilly & Brompton and the
modernisation of the deep-level Tube Hampstead Tube line.
lines. Legacy Constraints - Todays fixed
As a system, these lines were not infrastructure constraints on the deep
designed to dissipate increasing levels of tube lines originate from their
heat from traction energy, leading to a construction, including: 3.5m diameter
steady rise in tunnel and station bored circular tunnels, cast iron tunnel
temperatures since the lines opened in linings and the line topography. The tight
the early 1900s. curvature of lines in the central London
area reflects the arrangement of the
Pioneering Technology - The advent of
street plan above ground.
the new tunnelling shield method and
electric traction enabled the construction
of the worlds first operational electric
railway in 1890 with the opening of the
City & South London Railway between
Stockwell and the City. This was followed
in 1898 by the Waterloo & City railway
and in 1900 the Central London Railway.

Additionally, the fixed platform lengths,


their depth below ground and sub-
optimal ventilation systems are all
legacies of the original design. The
insulated four-rail direct current traction
supply still in use today was first
introduced with the early deep tube lines.
Private Enterprise - By 1907 the network The deep-level tubes present physical
of the deep tube lines in central London constraints which severely limit the
had been firmly established by private potential for capacity enhancement.
entrepreneurs and financiers notably These require bespoke and unique
Charles Tyson Yerkes. The Underground applications for key assets such as rolling
Electric Railways of London group stock.

8 New Tube for London - Feasibility Report


Context
Asset Renewal
Rolling Stock: Legacy trains equipment. Although relatively modern
The Bakerloo line trains are now over 40 and well within their design life, work is
years old and although refurbished in the required in the medium term to ensure
1990s are beyond their design life and the continued reliability of the traction
require urgent replacement. Targeted control equipment and maintain fleet
investment is required to maintain the serviceability until renewal in the late
condition and performance of the 36- 2020s.
train 1972 Tube Stock fleet until its
renewal in the 2020s.

Legacy Signalling & Control Systems


The Bakerloo and Piccadilly lines are
The 86 Piccadilly line trains have equipped with electro-mechanical, fixed
benefitted from an extensive block signalling systems dating from the
refurbishment in the late 1990s. This 1970s and 1980s. With relay-based
1973 Tube Stock is beyond its design life interlockings, track circuits and line side
with reliability ever-more difficult to signals for manual driving, these legacy
maintain and in urgent need of systems limit the service frequencies to
22 trains per hour (tph) on the Bakerloo
and 24 tph on the Piccadilly line.
Obsolete line control systems and
control room facilities on both lines are a
priority for renewal.
The Central line was resignalled in the
replacement. 1990s with a Westinghouse automatic
train control and train protection system
The 90 trains of Central line and Waterloo
to enable Automatic Train Operation. At
& City line 1992 Tube Stock are equipped
present, a peak service of up to 34 tph is
with the first generation of solid state
achieved during the busiest half hour of
direct current thyristor control traction
each peak.

New Tube for London - Feasibility Stage Summary 9


10 New Tube for London - Feasibility Report
New Tube for London programme
Vision
The New Tube for London programme aims to provide extra capacity through the
renewal of ageing assets by delivering a coordinated series of line modernisations for the
Bakerloo, Central, Piccadilly and Waterloo & City lines. This programme supports the
priorities of improving reliability and safety; improving customer service; and increasing
capacity from the current network through the following:

Comprehensive line modernisation Capacity


strategy Catering for Londons growth by
Delivering asset renewals in a more significant increasing customer capacity
comprehensive, consistent and whilst improving energy efficiency to
systematic manner than previously achieve a sustainable line upgrade
achieved solution

Technology and asset renewal Customer experience


Transforming the operating and Introducing a new generation of energy
maintenance model through asset efficient, air-cooled, high capacity Tube
renewals and technology-enabled trains and adopting highly-reliable
change; adopting resilient models of management and control systems to
service delivery through higher levels of deliver an improved service experience
automation

New Tube for London - Feasibility Stage Summary 11


New Tube for London programme
Status
In 2011, TfL began to develop a studies, safety analysis, operational
coordinated series of modernisations for design and strategic option appraisal to
those lines not commenced under the assess the optimum scope, sequence and
London Underground (LU) Public Private business case for line upgrades delivery,
Partnership (PPP) - the Bakerloo, Central, based on:
Piccadilly and Waterloo & City lines.
An unconstrained view of future
Following the completion of extensive operations and systems design for the
preparatory work, the TfL Board next generation of upgrades
approved the commencement of the Research and benchmarking to capture
Feasibility Stage in July 2012. After global metro best practice (see blue
confirmation of the strategic priority and boxes in this report for key findings)
funding status of the programme in At the end of the feasibility stage, the
December 2012, the TfL Board approved NTfL concept reached a sufficient level of
the programmes continuation through to maturity for the TfL Board to authorise
a defined Gateway assurance stage (Gate the next stage of the programme, the
B). Design and Specification Stage.
The resulting feasibility studies, which are
now complete, comprised a
comprehensive programme of technical

12 New Tube for London - Feasibility Report


New Tube for London programme
Feasibility challenges

The Feasibility Stage was initiated to The challenge is therefore to ensure that
examine the key challenges in service provision on the deep Tube lines
modernising the remaining deep Tube is optimised within the limits of the
lines and to respond to the following infrastructure constraints to provide the
requirements: maximum capacity to meet future
demand levels.
Capacity
Saloon air cooling
The deep Tube lines have fundamental
system design constraints, especially in Customer expectations regarding public
the central area tunnelled sections. New- transport vehicle temperatures have been
build metros provide high levels of influenced by the introduction of cooling
capacity using long, larger-gauge trains, systems on new trains and buses,
which are not possible on our Tube including London Undergrounds new S-
infrastructure. Stock being introduced on the Sub-
Surface lines (Circle, District,
Significant increases in capacity can,
Hammersmith & City and Metropolitan
however, be realised through the
lines). The deep Tube tunnels present a
coordinated application of new trains and
constrained environment for such
control systems underpinned by changes
technology, with the need to consider
to the physical infrastructure. The
the installation of cooling equipment
potential for improvement on each line is
within the restricted Tube gauge, and
unique to the particular constraints of
dissipation of heat.
that line.
The challenge is to determine whether
saloon air-cooling technology can be
Benchmark Finding: The level of trains
deployed on new trains in the deep Tube
per hour (tph) chosen by metros is
environment.
the result of a myriad of system
design factors (e.g. train length, wheel Managing tunnel temperatures
type, signalling system), customer Saloon air-cooling and operation of fast,
service / operational factors (e.g.
high-frequency services will increase
dwell times, crowding levels, access / energy and heat in the tunnels.
egress), and business objectives.
There is an optimal level for each The challenge is to determine how tunnel
metro / line but this varies between temperatures can be managed, whilst
applications. enabling the benefits of air-cooling and
capacity enhancements.

New Tube for London - Feasibility Stage Summary 13


Higher Levels of Automation Project Migration
The NTfL rolling stock and signalling Approximately one third or 1.4m of the
systems will be designed for a service life 4.2m people who ride the Tube everyday
of around 40 years. The pace of use the Bakerloo, Central, Piccadilly and
technology development and the Waterloo & City lines each day. Careful
experiences of other world metros in consideration of the delivery method and
retro-fitting legacy lines with fully line modernisation sequence is therefore
automatic systems highlight the required to make the biggest strides in
opportunity to introduce higher levels of growing capacity.
automation on the deep Tube lines during The challenge is to develop an
the life of the upgraded system. implementation strategy for this work,
The challenge is to determine whether referred to as a Migration Strategy,
technology advancements now being comprising a pre-determined number of
introduced by other world metros could operational states through which the
be applied on the deep Tube lines to railway migrates to maximise the
enable safe and reliable fully-automatic efficiency of the project, whilst
train operation. minimising the impact on customers.

14 New Tube for London - Feasibility Report


Summary of feasibility activities

The NTfL feasibility study challenges are which discharges energy in the form of
closely inter-related. Therefore, their heat into the tunnels as a by-product.
analysis required a comprehensive, Consideration must therefore be given to
system-engineered design process. implementing infrastructure cooling
For example, delivering increased solutions to ensure the tunnel and
capacity is a key programme objective. platform environments remain
However, the effort to achieve this acceptable.
objective should not jeopardise achieving These can be complex in their own right,
others e.g. increasing reliability. so feasibility studies for implementation
Therefore, the intrinsic capability of the were carried out and iterated through the
existing infrastructure has to be overall system design.
understood, along with the impacts of
incremental changes that can be made to London Underground has many years of
improve this capability. experience of delivering large complex
engineering programmes. Lessons learned
The natural consequence of increasing from this experience have provided
capacity is an increase in energy demand. opportunities for continuous
Additional demand for energy is offset by
improvement in approaches and
optimising its use through the practices. NTfL has also drawn on
implementation of recognised strategies external best practice guidance (for
previously deployed on London example from The Royal Academy of
Underground. These include regenerative Engineering and other external expert
braking and new technologies to further guidance from BAe Systems) to define
increase system receptivity and energy the approach it would take to engineering
recovery. during the feasibility phase.
Deploying all of these strategies will not This approach was captured in a
fully mitigate the increase in energy framework called the Railway Level
demand due to the substantial increase in Design Management Framework (RLDMF).
capacity. Without mitigation measures,
there will be a consequential increase in The key feature of the framework was to
tunnel and platform temperatures due to coordinate the iterative development of
the increase in energy utilisation. This is many work streams of activities whilst
further reinforced by implementing maintaining an overall integrated systems
saloon cooling (a programme objective) approach. This was achieved by maturing
the understanding of key critical design

New Tube for London - Feasibility Stage Summary 15


features, such as capacity and energy The NTfL Integrated Programme Team
utilisation, of the overall system. Through (IPT) has managed a comprehensive
effective design review processes it was schedule of activities to determine the
possible to determine when sufficient right balance of outcomes to optimise
maturity had been achieved to derive a the business case benefits, including:
reliable outcome to the study (see
Surveys
diagram below). Supplier studies
The output of the work is an overall Internal design activities
concept design of the changes we intend Academic research
to make to the railway to achieve the Engineering simulation
required outcomes. This is reflected in an Strategic planning and modelling
operational concept with a physical Benchmarking with comparable metros
architecture, determining the changes The following sections present the key
alongside required assumptions made in findings against the study challenges.
achieving the changes. This forms the
basis of the requirements that will be
taken forward into further design
development and technical specifications
for procurement.

16 New Tube for London - Feasibility Report


Summary of feasibility activities
Capacity rolling stock

Modern rolling stock has a higher Customers can move through the train
performance capability than the existing so they are in the optimal section of
trains with better acceleration and the train at their destination station,
braking characteristics. These can reduce thus reducing the time spent exiting
journey times and enable a higher the system
frequency service to be operated from a The provision of a more continuous
given fleet size. Higher performance open space within the vehicle
capability is a core feature of a train improves security and reduces the
system upgrade, and one which has been opportunity for antisocial behaviour
achieved on several Underground lines Provision of through gangways on a Tube
over the past two decades. train with traditional configuration is very
The Feasibility Stage has investigated difficult, if not impossible, due to the
provision of more novel features for Tube dynamic behaviour of the vehicles. Tight
trains, such as open, wide gangways. curves, in particular, lead to large relative
These would offer a number of benefits movements between vehicles ends. This
to customers as follows: means an inter-car gangway would not be
possible without removing doors at the
Additional capacity is provided with
end of the carriages, due to the length of
improved configurations, including
the gangway which would be required.
walk-through rather than separate
carriages, creating more floor area as NTfL has identified that it is possible to
compared with traditional designs provide an inter-car gangway by altering
Customers can easily transfer between the Tube train design to incorporate an
carriages, meaning customers can articulated configuration with more,
distribute throughout the train, shorter carriages. By positioning the
avoiding busier carriages where vehicle bogies under the ends of two
possible. This in turn, will help to adjoining cars, the relative vertical and
reduce dwell times as a more evenly lateral movement of the carriage ends is
loaded train enables quicker boarding significantly reduced. This enables a
and alighting shorter, wide gangway to be fitted

New Tube for London - Feasibility Stage Summary 17


without loss of train capacity or a platforms and sidings to inform the
reduction in the number of doors. constraints on train dimensions for each
of the NTfL lines. Train length is a critical
The repositioning of the bogies allows all
design parameter. Increasing length
train doors to be double doors. Double
improves the capacity of the train,
doors allow for rapid access and egress,
generating customer benefits, but also
which reduces dwell times. Controlling
increases the modifications required to
dwell times becomes a dominant factor
existing infrastructure which can be
for achieving high frequency service
levels, due to reduced intervals between costly and disruptive.
trains. To ensure that the configuration is
future-proofed, provision for installation
Laboratory trials with University College
of Platform Edge Doors (PEDs) on
London at their PAMELA (Pedestrian
platforms is required. PEDs determine the
Accessibility and Movement Environment
position of the end doors of the train.
Laboratory) facility were used to gather
data which supported existing empirical This analysis confirmed the fixed
information on the impact of train and maximum dimensions for train length and
platform features (such as door size, door spacing for each of the deep Tube
stand backs, seat types and platform lines to inform the design and
edge doors) on dwell times. The outputs procurement of the new rolling stock.
of these trials were used to inform train
design options and evaluation of different
configurations.

Detailed surveys were made of the


existing infrastructure, including tunnels,

18 New Tube for London - Feasibility Report


Summary of feasibility activities
Capacity signalling and control
Modern, automated metros require a delivered on the Victoria, Jubilee and
higher level of control capability to Northern lines in recent years.
facilitate remote monitoring and NTfL will therefore replace the existing
management of the train service and its signalling and train control systems in
supporting assets and systems. For the order to achieve the increases in service
NTfL line modernisations, a fully- frequency necessary to deliver the
integrated Railway Control System (RCS) required capacity enhancements.
is envisaged comprising:
The Feasibility Stage looked in more
Signalling and train control - including detail at wider railway control elements.
vital signalling and communications Multiple independent systems are already
systems required for real time mature, but moving from disparate
movement control of train services systems to fully-integrated functionality -
Operational Control Systems (OCS) - in line with modern operational control
supporting functions for efficient philosophy - will represent an
operation and maintenance (e.g. enhancement to London Undergrounds
condition monitoring, maintenance current line management capability.
management, staff management,
Engagement with suppliers, other
degraded mode operation control,
operators and internal stakeholders has
traction and ventilation control,
indicated that at least two discrete
security and customer flow
communication networks should be
management)
deployed to deliver the NTfL
Independent communications - high
requirements. One will be a vital
bandwidth telecommunications to
signalling and train control network. The
support fully-automatic operation with
other will be a non-signalling
audio and visual links between the
(independent communications) network
train and the control centre
to support all other business and railway
Anticipated increases in customer information.
numbers drives a need for longer dwell
Based on the information available today,
times. Without intervention, a larger
provision of a network to satisfy the data
number of customers would reduce the
transfer needs is feasible but very high
number of trains per hour that could
bandwidth needs are a limitation. To
serve the line. Modern signalling and train
determine the feasibility of utilising an
control systems can help to offset this by
integrated railway control and
enabling trains to safely operate at closer
communications system, it was
intervals as has been successfully
necessary to examine communications

New Tube for London - Feasibility Stage Summary 19


connectivity, the most significant change Changes in tunnel geometry (e.g.
for which is the required increase in cross-over caverns) cause signal loss
quantity and quality of train-to-wayside 2.4GHz propagates up to 400m
communications. This required 5.8GHz propagates less than 200m
consideration of: The train in the tunnel creates a
Higher availability and higher blockage for signal propagation
bandwidth communications As part of the propagation trial, high
Data prioritisation: to maximise definition video was successfully
network capacity transmitted in the tunnel at distances of
Approach for main or backup signalling up to 200m.
and control data transmission The trial has confirmed London
Minimising trackside equipment to Undergrounds understanding of wireless
reduce whole life costs propagation in the deep Tube tunnel
Higher degrees of network and system environment. The resulting propagation
Reliability, Availability, Maintainability, model was then applied to the Bakerloo
Safety (RAMS) and Security line, to establish typical equipment
Early supplier engagement identified their requirements for line wide network
preference for the use of proprietary application.
radio operating at 2.4GHz or 5.8 GHz for This confirmed that should a higher
control communications. As this propagation frequency, such as 5.8GHz,
capability is not yet deployed within the be used there would be a potential need
Underground environment, a trial was for higher wayside equipment count in
commissioned to understand the physics the tightly curved deep Tube tunnel
of wireless propagation in the cast iron infrastructure.
deep Tube tunnel environment.
The studies considered current and
The trial tested single-path and multi- emerging communications technologies
path losses as well as ground reflection and concluded that given the rapid pace
effects in the disused tunnel between of evolution in this sector, London
Holborn and Aldwych, which was Underground will continue to keep an
identified as being representative of the ongoing technology watch on
NTfL lines target environment. developments. Future specifications,
The trial concluded that radio frequency prior to procurement, will be informed by
propagation within the tunnel follows a these developments.
predictable model, and that:

20 New Tube for London - Feasibility Report


Summary of feasibility activities
Capacity infrastructure

To support increases in capacity, a Managing Tunnel Temperatures


number of significant enhancements to section.
the infrastructure are required, as Track - The track infrastructure, quality
follows: and configuration will need to be
Power - London Underground has a enhanced to support the significant
comprehensive traction power increase in mileage expected such that
distribution network that needs to be it can be adequately maintained within
enhanced to deliver the increased the available access.
capacity demands. The power supply An important element of this is the
infrastructure feeding the NTfL lines Wheel- Rail Interface (WRI), which
was predominately installed in the considers the interaction of the train
1960s and 1970s. Therefore the plant and track in terms of performance and
items are generally reaching the end of adhesion, ride and wear and tear.
their economic lives. The NTfL study Bogie design studies have been carried
considered the necessary scale and out to consider the application of low
scope of a power infrastructure track force bogies on an articulated
upgrade required. A substantial train configuration. NTfL has engaged
upgrade is proposed, which will the University of Huddersfield to
address asset renewal (e.g. undertake academic research and
replacement of transformer rectifiers) specialist modelling support in this
and provide the additional capacity area.
needed for operation of faster, more
frequent and more reliable services.
Power enhancements will also be
needed to meet the requirements of a
modern railway control system.
The solution will also include
upgrading of cables, switchboards,
batteries and chargers, power system
control and auxiliary transformers.
The overall power solution includes
consideration of the most efficient
means of power transmission to and
between trains, which is covered in the

New Tube for London - Feasibility Stage Summary 21


The ultimate choice of bogie design Key lessons learnt from prior London
and vehicle articulation will be based Underground and other railway depot
on analysis of the conflicting projects are informing the detailed
requirements of underframe space, plans for the NTfL depots. Examples
gauging, gangway arrangement and include efficient utilisation of existing
acceptable levels of track wear. assets, consideration of all interfaces
and full system integration during the
Depots and stabling Existing depot
migration from existing trains and
facilities will require significant
modifications to support an increased facilities through to new trains and
new or amended facilities.
fleet size as well as the facilities
necessary to maintain a modern train. Additional stabling capacity will be
required on some of the lines to
NTfL has considered a range of depot
enable increased fleet size.
strategies, including combining depots
for multiple lines, building new depots Civils - Specific capacity pinch points
on green-field sites and developing have been identified through extensive
existing depots to be fit for the modelling to determine which, if any,
maintenance of the NTfL train fleet. have a case to be removed.
Amongst a number of measures
expected, will be localised tunnel
modifications to relieve the
constraints imposed by the historic
civil infrastructure, which act as a
limiting factor on performance.

Given limited availability of affordable


green-field sites in greater London, the
line specific requirements for depot
facilities and the need for efficient
access to the operational railway the
strategy is to redevelop existing line-
specific depot facilities, where
possible.

22 New Tube for London - Feasibility Report


Summary of feasibility activities
Capacity modelling
A multi-stage modelling process was each London Underground line.
undertaken to reach a combined view of 3) Railway Engineering Simulator (RES):
railway performance and post-upgrade this model assesses the system
demand levels, to determine the optimal performance of an Underground line
capacity to be delivered (see diagram based on the design parameters of the
below). Four main capacity modelling train, signalling and infrastructure. It
stages were completed: produces performance outputs such as
run times and available service
1) London Transport Studies (LTS): a TfL-
owned transport model that takes headways, which can also be used for
power, energy and cooling modelling.
forecast population and employment
4) Train Service Model (TSM): this model
data from the GLA together with
simulates the post-upgrade railway to
assumptions of land use and transport
understand the interactions between
network provision, and produces
the technical capability of the
estimates of public and private
modernised railway (fed from RES) and
transport usage by mode of transport.
forecasts of customer numbers on the
2) Railplan: this model takes the public
lines post-upgrade (fed from Railplan
transport demand forecast from LTS
and LTS). This has enabled the optimal
and allocates or assigns it between
capacity provision to be understood
the different possible routes and
and line-specific targets to be set.
modes, to optimise total customer
journey time. It produces assignments
of demand for given future years, for Train

different levels of planned service


across all modes of Public Transport, Railway Engineering
including estimates of the number of Signalling Simulator
(LU line performance)
customers using

Infrastructure
Line
Land Use Performance

Population
London Transport
Railplan
Studies Transport Train Service Model
(strategic public Line Demand
(strategic land use and Demand (LU line simulation)
transport)
transport)
Employment

Transport Network
New Tube for London - Feasibility Stage Summary 23
Summary of feasibility activities
Saloon air-cooling
Conventional Tube train design cannot Underground to conclude that a saloon
accommodate air cooling equipment cooling system could be fitted onto the
without taking up customer capacity in new train within the space, weight,
the vehicle interior since there is energy and capital cost assumptions
insufficient space available on the vehicle envisaged for the new train. The key
underframe for the air cooling modules. requirement to create space on the
The traditional rolling stock approach of vehicle underframe can be met by altering
placing this equipment in the roof space the train configuration to be articulated
is not viable on Tube trains given the which reduces the number of bogies
tunnel size and the need for sufficient required along the length of the train.
headroom for standing customers. The consequence of discharging waste
Detailed development studies have heat energy into the tunnels has been
determined the viability of configuring assessed and taken into consideration in
and reducing the size of the equipment the overall system design. This is covered
such that it can be both accommodated in more detail in the following section on
and maintained. A concept design study Managing Tunnel Temperatures.
was carried out and this has provided
sufficient information for London

24 New Tube for London - Feasibility Report


Comprehensive and ongoing dialogue less heat to be discharged into the
with train manufacturers has given tunnels and Underground stations, which
confidence that we can include would potentially reduce the need for
requirements for saloon cooling as part infrastructure cooling and/or reduce
of the train procurement. temperatures. Work continues to confirm
the viability of including this novel type
of cooling system in the specification for
Benchmark Finding: Air cooling is new train procurement.
common on modern trains with
systems typically located in roof
spaces. The challenge for NTfL is to
apply this standard industry
functionality in the constrained
environment using under-floor
modules, and managing dissipated
heat in the tunnels.

Studies completed to date have been


based on conventional cooling systems
which use refrigerants to cool air which is
then pumped into the saloon. As a
minimum, conventional cooling will be
specified in new train procurement.
NTfL is continuing studies into alternative
hybrid cooling systems as a potential
adaptation of conventional saloon
cooling. Hybrid systems allow generation
and storage of thermal energy whilst
trains are operating outside of tunnels.
This store is then used to cool the air for
circulation in the saloons when the trains
operate in the tunnels (the areas of the
line where customer comfort levels can
be most improved). This would enable

New Tube for London - Feasibility Stage Summary 25


Summary of feasibility activities
Managing tunnel temperatures

The original design of the Edwardian deep extra low loss rails. Adopting these
Tube tunnel infrastructure did not strategies has been shown to increase
address ventilation such that it could be energy efficiency by up to 30 per cent.
scaled for current demand. When NTfL has also instigated a trial of an
originally built, the ground around the inverting substation on the Victoria line
tunnels varied with seasonal changes in
to determine if this technology has a role
temperature. Over time the ground has to play in the NTfL power solution. The
become permanently heated. Any trial is ongoing and due to report during
increases in temperature are the current programme stage.
consequently difficult to mitigate; a
unique challenge for London Infrastructure - If unmitigated, there will
Underground. be consequential increases in tunnel and
platform temperatures caused by higher
The overriding principle is to avoid energy utilisation and fitment of saloon
generating waste heat as far as is cooling on the trains. The train air cooling
practical. London Underground has discharges energy in the form of heat into
successfully deployed strategies to the tunnels as a by-product of the
optimise energy use in an attempt to do cooling.
so. The following elements have been
considered in the overall design: Consideration must therefore be given to
implementing infrastructure cooling
Train - Maximising the use of regenerative solutions, such as the over-platform air
braking, thus avoiding the braking energy handling units shown below, to ensure
being dissipated as heat by either friction the tunnel and platform temperatures
or resistor grids. More sophisticated train remain acceptable for our customers.
regulation systems can exploit
opportunities for more energy efficient
run profiles.
Transmission - Increasing the traction
supply voltage to 750 Volts helps reduce
losses, along with increasing the
regenerative voltage and current. Re-
sectionalisation of the network increases
the probability of energy recovery by a
receiving train. The conductor rails can
also be replaced by modern composite

26 New Tube for London - Feasibility Report


The Railway Engineering Simulator (RES) The graph below illustrates the TVM
was used to provide a forecast of energy modelling process for the Piccadilly line. In
usage in tunnel sections. This was then summary, summer season platform
applied in comprehensive Tunnel temperatures can be managed to similar
Ventilation Model (TVM) simulations, to levels as pre-upgrade. Delivery of energy
predict the temperatures within the efficiency features in the train (such as
tunnels and stations and the consequential regenerative braking capability), and
environment in the train saloon given station and tunnel cooling schemes (such
energy and heat emitted by the train as new Platform Air Handling Units) will
service, tunnel temperatures and forecasts help to reduce platform temperatures,
of customer numbers and climate which would otherwise increase due to the
conditions. This analysis included provision of saloon air-cooling, and faster
Computational Fluid Dynamic (CFD) and more frequent services.
simulation to assess the mixing of air In addition, provision of saloon cooling will
between the track-way and platform which result in a step-change reduction in
is caused by the movement of the trains summer season train saloon temperatures.
through the Tube tunnels.

New train Faster and Station and


with more tunnel
Current regenerative Saloon frequent cooling
train braking cooling services schemes

New Tube for London - Feasibility Stage Summary 27


Summary of feasibility activities
Higher levels of automation
NTfL line upgrades will deliver new train to huge improvements in customer
systems for operation over at least the service and efficiency.
next 40 years, and consequently require London Underground now operates the
the system to be future-proofed with the Jubilee, Central, Victoria and Northern
capability for fully- automatic operation. Lines in automatic mode where the speed
The renewal of train systems provides of the trains, the distance between them,
the opportunity to build in the capability their acceleration and braking
for higher levels of automation. The new performance are under computer control.
assets and systems will provide detailed
information about their status which
combined with enhanced levels of Benchmark Finding: Fully Automatic
situational awareness of the railway will operation is proven, scalable and
allow more informed operational decision adaptable to a variety of metro
making and enhanced levels of predictive environments and is a growing reality
and preventative maintenance. in the industry. Globally, over 100
examples of existing or planned fully
automatic lines are known.
Benchmark Finding: Industry trends
and the plans of other metros support
increasing levels of predictive This enables a much higher level of
maintenance, and the programme service consistency to be achieved
plans to investigate further the compared to those lines with manually
maintenance techniques being driven trains.
adopted by other leading metros. Worldwide, Metro operators have
followed London Undergrounds early
lead and adopted automatic train control
London Underground has a long history systems to improve service capacity and
of technology-enabled change from the operating efficiency. With the advent of
worlds first Underground electric railway new technologies many new metros are
in 1890, the introduction of air-operated
now being built for fully-automatic train
doors in the 1920s (which allowed train operation where all train movements and
operation by just a driver and a guard) to door operation are under the control of
the Victoria line which opened in 1967 as the system. This improves reliability by
the worlds first automatically controlled the elimination of human variability and
railway (with one person operation). errors. It also allows much greater
These pioneering developments have led

28 New Tube for London - Feasibility Report


flexibility of operations since the Platform to Train Interface - The area of
scheduling of trains for service can be highest risk in London Undergrounds
decoupled from the planning and operation is the Platform-Train Interface
rostering of train operators duties. (PTI). Assessment has determined that
physical barriers (e.g. Platform-Edge Doors)
The NTfL programme can provide the
would be required to effectively and reliably
capability for this level of automation for
manage the PTI under fully-automated
use as required during the lifetime of the
operation.
upgraded system.
The key changes that would be required Benchmark Finding: PEDs are the
to enable this functionality are: dominant track protection system for
Train - The train design includes focus on modern fully automatic railways, with
significantly reducing the probability of very few operating without them
extended delays between stations by (those that do are predominantly
increasing the reliability of components older systems).
and increased automatic handling of
defects. Real time information about train Platform Edge Doors - the NTfL
health will be available with remote Feasibility Study evaluated both full
diagnostics, without the need for height Platform Edge Doors (PEDs) as
operator intervention. installed on parts of the Jubilee line, and
Open Section Security - Enhancements to half height Passenger Safety Gates (PSGs)
track or guide-way security in the open as installed on Paris Line 1, and
sections are required. Investigations have concluded that full-height PEDs offer the
found that the key areas which may best solution for NTfL.
require enhancement are as follows:
Upgrade of some boundary fencing
and provision of appropriate barriers
between NTfL and adjacent rail lines
Review of landscaping and vegetation
management
Review of bridge and tunnel parapets
and caging
Identification of site-specific measures
to prevent trespass or incursion

New Tube for London - Feasibility Stage Summary 29


Data confirmed that PEDs offer at least tested headers reduce the time
double the reliability of PSGs based on their requirements, but not to the point where a
simpler design which incorporates fewer doorway can be assembled and
components. The simplicity and robustness commissioned during engineering hours.
of the door guidance systems of PEDs is Over the last few years some manufacturers
also known to be a contributor to the
have developed and successfully installed
increased reliability compared to PSGs. modular PED systems specifically for fitment
PEDs provide much greater integrity of during a 3.5 hour night time closure. From the
separation of the platform and track door system perspective these are identical
environment. No track intrusions have been to traditional PEDs, but they incorporate a
recorded from platforms fitted with PEDs structural frame capable of resisting the
on the Jubilee line. 1.7m high PSGs have not stresses associated with transportation and
been proven to stop all track intrusion on installation. The doors are transported to site
other metros. The lower height also leads to on engineering trains and installed onto the
a greater number of false alarms where platforms utilising mechanical handling
secondary detection is deployed to mitigate equipment mounted on the engineers
the risk of entrapment on curved platforms. wagons.
In addition, it is comparatively easier for Investigations have confirmed that full-height
customers to drop rubbish over the top of a modular PEDs can be transported through the
PSG which can have a negative impact on structure gauge of London Undergrounds
service reliability. smallest Tube tunnel using specially designed
PED Installation - half height PSGs were wagons.
developed for ease of retrofitting to existing
platforms, and are supplied as factory
assembled and tested modular units. These
have successfully been retrofitted on other
metros at a rate of two to three doorways
per night within a typical three hour
window. Doors are generally installed and
commissioned in the same shift.
Full height PEDs, as installed on the Jubilee
line, have traditionally been built and tested
on the platform, making them more suitable
for new line construction. Preassembled and

30 New Tube for London - Feasibility Report


Obstacle detection trials - Extensive trials LIDAR scanner on trial at Bank
were undertaken to understand the
effectiveness of Obstacle Detection
systems which could be used on an
automated railway to ensure the safety of
customers, maintenance and operating staff.
Obstacle detection systems offer a
potential means of mitigating the risk of
incursion onto the track at stations, in
tunnels and in open section areas as a
possible alternative to PEDs. Such
systems are in use as part of integrated
control systems on other automated
metros including Nuremberg.
Four systems were trialled as follows: None of the detection systems trialled or
considered on other metros, prevent the
Light Detection And Ranging (LIDAR) or hazard occurring, they only mitigate the
laser scanners effects. By contrast, physical separation
RADAR radio frequency scanning units of the track would prevent accidental and
Video analytic systems deliberate track incursion so increasing
Ultrasonic transponders safety and reducing service affecting
All of the trialled systems detected incidents.
defined objects to varying degrees Although it is acknowledged that
although none to a level that would technologies are developing rapidly, the
support the reliability requirements of trial and industry/metro engagement
NTfL. The predominant finding was that indicate that current detection
whilst the technology is effective, a high technologies do not appear to offer a
number of false positives occurred (i.e. practical solution to PTI risk mitigation
system alarming when no object, trapping with its particular infrastructure
or dragging incident is replicated). When characteristics and demanding reliability
linked to the Railway Control System, requirement.
each occurrence would automatically
stop the train with unacceptable service
disruption impacts.

New Tube for London - Feasibility Stage Summary 31


The PED systems being considered by undertaken to better understand gap filler
NTfL will require secondary detection at deployment cycle/timings and its impact on
some curved platform locations to train service operation, as well as to identify
ensure the gap between the PED and any abnormal behaviour caused by
Train is clear prior to train dispatch. This prolonged intensive use, such as excessive
is a much simpler scenario than noise, wear and other potential technical
investigated during this trial. A scanning malfunctions.
laser would appear to offer the best Gap filler module built for NTfL trial
solution and is the system used on
overseas metros with good reliability.
Gap Fillers - Mechanical gap fillers were
identified as an integral part of the platform-
train interface (PTI) solution for the NTfL
programme, as they will be necessary at
various locations on the Piccadilly and
Central lines where curved platforms result
in large horizontal stepping distances.
Analysis of the Piccadilly line identifies 14
platforms which will require around 100
mechanical gap fillers, based on working
assumptions of the PTI concept design and
the candidate train design.
Platform-based mechanical gap fillers have Accelerated life tests have been running
so far been used in four metro systems without failure for approximately 3,000,000
worldwide, the most extensive use being in cycles to date, an equivalent of 15 years of
Tokyo, where over 200 units have been operational life. The current reliability rate is
installed in the last ten years. All four higher than the original target of five
metros have had mechanical gap fillers service-years between failures. Testing with
provided by different manufacturers. contaminants including railway dust, grit and
sugary drinks has revealed no detrimental
NTfL engaged a gap filler manufacturer to
performance impacts. Tests continue to
undertake a series of tests designed to
accurately represent continuous rainfall
prove the reliability and suitability of
conditions at the appropriate volumes for
mechanical gap fillers for use on the NTfL
the accelerated testing regime.
lines. In particular, these tests were

32 New Tube for London - Feasibility Report


Railway Control and Management -.The smoothly. With real time audio and visual
feasibility study was focussed on the communication links to the trains and
deployment of new technology to deliver stations, staff can take action in the
a higher capacity, more reliable train event of disruption or incidents to ensure
service. Best practice from benchmarking a swift response and recovery.
studies of other metros around the world
With staff duties no longer tied to the
also highlighted the opportunity for timetable, it is much easier to respond to
London Underground to consider new perturbations or sudden changes in
and more flexible operations, made demand. This flexibility allows the train
possible by the introduction of systems service to be increased at very short
for higher levels of automation. notice for special events where more
trains are required to deliver an enhanced
Benchmark Finding: Metros have
service. The automatic train control
reported that higher levels of
system needs to be extended to cover
automation have allowed them to
depot reception and stabling tracks to
significantly improve their
allow the automatic entry and exit of
response to changes in customer
trains to meet service requirements.
demand and are able to
introduce special service at hours Automated metro systems demand very
notice, rather than weeks. high levels of service reliability and asset
availability to maintain high service levels
Provision of the capability for fully- and meet capacity needs. This means that
automatic train operation would allow the railway system overall must be highly
train movement and normal operations reliable and resilient to failures which
to be brought fully under the control of lead to service suspension or delay, and
the train control system. It would also that the need for maintenance
allow traditional operational roles to interventions when failures occur must
become more flexible and customer- be reduced.
facing. With a new control system, the Feasibility studies have confirmed that
train service can be overseen and through the adoption of modern
managed remotely from the Service diagnostics and communications and
Control Centre where staff can monitor reporting systems, a predict and prevent
the state of the railway, the performance approach to system design and
of the assets and the deployment of staff maintenance can be introduced to
to keep the train service running support higher levels of reliability.

New Tube for London - Feasibility Stage Summary 33


Sub-systems can have the capability to A high level view of principles of a fully-
continuously report their condition and coordinated railway control system is
performance such that asset shown in the diagram below. This is
maintenance activities can be predicted intended to show the type of information
and scheduled just in time to eliminate and data flow which modern control
unnecessary periodic inspections and systems could provide for fully automatic
prevent failures in service. Benchmarking operation.
has highlighted the opportunities for
reduced asset down-time by increased
levels of modularity in design to enable
defective sub-systems to be easily
removed and replaced.

NTfL - RAILWAY CONTROL SYSTEM CONCEPT


RCS MANAGEMENT & CONTROL SYSTEMS DEPOT / Localised Control LEGACY EXTERNAL INTERFACES
Train Movement Depot External
Depot Interfaces
Control Interfaces Interfaces
Legacy Interfaces

s
Co U
mm
L
Da Non
ta
External Interfaces

Integrated
Command & LU Staff Customer
Control Member (outside NTfL)
Passenger &
Incident Monitoring
Information STATION
(inc CCTV)
Service and Fleet RCS
LU Mgnt Asset Performance
Comms
Manager Mgnt
LU LU SCADA Station Interfaces
Operations Maintenance Resource (including for PEDs)
Staff Member Staff Member Security Management

TRACKSIDE
NTfL RCS Encompasses

Signalling & Train Control;


Includes Automatic Train
Systems
Op

Interfaces Control (ATC)


era

AT
tio

CT
nal

Station Interfaces LU Staff


Trackside Trackside
rain

Members
Tra

Signalling Interfaces
/W
in

Systems
a ys
/W

Interfaces Operational Control Systems


ide
a ys

(OCS)
TRAIN
ide

ATC Communications

Supporting Communications

Note this is a concept diagram, the


precise scope and boundaries have yet to Trainborne
LU Mobile Staff Train Interfaces Train Interfaces
be determined. System
Including Live CCTV

34 New Tube for London - Feasibility Report


Summary of feasibility activities
Project migration

An overarching Generic Migration whilst minimising customer impacts


Strategy was developed which could be Replacement of existing service trains
applied to any of the NTfL lines, to form with new trains should be a gradual
the basis for Line Specific Migration process, to ensure service continuity,
Strategies. These documents will then resulting in a period when there are
form the basis for development of both existing and new trains operating
detailed requirements and plans for each in service at the same time
line implementation. The aim of the Increases in services levels (trains per
strategy is to align the high level hour) should occur after the line is
implementation phases of numerous operating a full fleet of new trains; i.e.
workstreams required to upgrade the once the constraints on performance
railway in such a way that interim states and efficient energy consumption
can be defined and validated. which existing trains impose (lower
voltage and no regenerative braking)
A number of key principles emerged from
have been removed
this exercise, either derived from specific
Platform Edge Doors cannot be
technical requirements / engineering
installed until all existing trains have
constraints, or application of lessons
been withdrawn due to differences in
learnt on similar projects implemented by
door spacing between new and
LU and other leading metros, as follows:
existing trains
If possible new trains should operate The line will not be capable of fully-
on new signalling from the outset to automated operation until Platform
minimise train configuration stages Edge Doors are installed
An initial phase of testing should occur
The resultant generic migration strategy,
on the railway, but outside of traffic
with seven stages of implementation is
hours to gain real railway interface
shown in the diagram below.
experience
6 7
NTfL Generic Railway Migration Strategy
Increases in
trains per
1 2 3 4 5 hour and
faster run
times
New trains in All new trains
1st new train 1st new train
New signalling service (old in service (all
(overnight (daytime
commissioned trains being old trains
testing) testing)
replaced) withdrawn)
Line capable
Platform Edge
of fully
Doors
automated
installation
operation

New Tube for London - Feasibility Stage Summary 35


Feasibility outcomes

The New Tube for London Feasibility Study Capacity - Greater capacity, up to 60 per
has determined that a world class cent on the Piccadilly line, will be
modernisation of the remaining deep Tube delivered to cater for Londons growth.
lines is possible and that all of the key Platforms - The platform experience will
challenges under consideration as part of be transformed at the majority of the
the programme can be overcome.
stations on these lines with full platform
A railway level system concept design has to train level access and Platform Edge
highlighted how a high capacity modern Doors, providing modern and safer
metro service can be achieved in spite of waiting environment.
the constraints imposed by the deep Temperature - Station cooling will also be
Tube Edwardian infrastructure. Line implemented at a number of sites
specific variations are expected to deal providing a cooler temperature for
with unique structural factors on some of customers waiting on platforms.
the lines but the core premise will remain
similar: Reliability - High levels of reliability are
being targeted based on benchmarking
New Tube for London - At the heart of with other world class metros. An NTfL
the design is the New Tube for London
upgrade target of 5 incidents per million
train concept which represents an car kilometres has been selected for the
evolution of traditional Tube train system design.
configuration such that walk-through, air-
cooled customer saloons can be The following sections step through
achieved. elements of the potential NTfL outcome
which customers could experience during
Quicker journeys - Customers will the coming decades.
experience significant improvements in
journey times due to faster and more
frequent services.

36 New Tube for London - Feasibility Report


Feasibility outcomes
Functional concept

The New Tube for London will build on


the success of the London Underground
S-Stock and Overground Class 378 trains,
which have enhanced the customer
experience through provision of through
gangways and saloon air-cooling.
Our extensive feasibility investigations
have demonstrated these features to be
viable in the deep Tube environment as
part of the NTfL train concept, which
would offer:
A 10 per cent capacity increase over an
equivalent length conventional train
design
Fewer bogies, thus reducing overall
train weight and energy consumption;
Under-frame space for fitment of
saloon air cooling systems
A fully walk-through saloon to reduce
crowding in the busiest carriages;
Key benefits of NTfL Conventional New Tube for
Accessibility concept Tube Train London *
All double doorways to improve
Number of cars 7 10
boarding and alighting times
Number of seats 238 Up to 248 (+4%)
Extensive engagement has taken place
with train manufacturers to confirm the Standing spaces (at
501 566 (+13%)
4/m2)
viability of these elements of Tube train
Estimated total
design. 739 814 (+10%)
capacity per train
This has been positively received and Space for air-cooling
No Yes
industry now has a high level of units
confidence in offering these features as in Walk through train No Yes
response to the NTfL train procurement.
All double-leaf doors No Yes

* Indicative design for Piccadilly line

New Tube for London - Feasibility Stage Summary 37


Feasibility outcomes
Design concept
The feasibility study included a design This stage verified the engineering data
exploration with industrial designers to and physical dimensions to ensure that
develop a concept or reference design to the requirements were established for
inform procurement specifications. reference trailer and driving cars. This
included:
A study was commissioned and awarded
to industrial designers PriestmanGoode The physical outer shell dimensions
to develop, with TfL, a concept of the The door dimensions and capacity
look and feel of the interior and exterior requirements
of a new deep Tube train. Human factors
Railway Vehicle Accessibility
This concept design was created within
Regulations (RVAR) requirements
the constraints of existing infrastructure
Customer information systems
and reviewed the best configuration and
including placement, sizes and number
design from customer and operational
of structure apertures
points of view.
Ventilation grilles for cooling and
The study was organised and delivered in heating
three distinct stages: research, concept
design and design development. These
elements culminated in a finalised
industrial design concept.
Stage 1: Research

38 New Tube for London - Feasibility Report


Stage 2: Concept The design ethos was aligned with work
taking place across TfL to deliver a more
In this stage three options emerged for
encompassing look and feel to aspects
the car interior and exterior. The design
of, for example, station, uniform and
discussions clarified the best layouts and
product design. The majority of Stage 3
elevations in order to deliver a functional,
was focussed on the interior of the train,
coherent interior.
including:
Consideration was given to the
Lighting, floor finish and colour palette
dimensions and layout of windows and
Seating moquette and arm rests
the integration of air cooling equipment.
Customer information displays
Stage 3: Design development Gangway
This stage captured the key design Grab pole
elements that are considered timeless The ultimate design for manufacture will
and highly-functional design features. be influenced by the engineering
These distinctive elements captured the elements of the selected suppliers train.
design DNA of London Underground
The following pages show exterior and
and enabled the design to develop
interior images resulting from the design
beyond the most recently acquired trains.
process to date.

New Tube for London - Feasibility Stage Summary 39


40 New Tube for London - Feasibility Stage Summary
New Tube for London - Feasibility Stage Summary 41
42 New Tube for London - Feasibility Stage Summary
New Tube for London - Feasibility Stage Summary 43
44 New Tube for London - Feasibility Stage Summary
New Tube for London - Feasibility Stage Summary 45
Feasibility outcomes
Time savings and capacity improvements

A high frequency fast service is possible Off-peak services - would also be


on all of these lines post-upgrade which increased, complementing the high peak
will generate a step-change improvement services, and, on the Piccadilly and
in the number of customer spaces and Central lines, 24 hour running on Friday
journey times. and Saturday nights.
Piccadilly and Central - peak period Forecast peak
services are expected to operate at Line
capacity increase
between 33 and 36 trains per hour in
central London (a train nearly every 90 Piccadilly 60%+
seconds, which would approach the most
frequent metro service operated globally, Bakerloo 25%+
in spite of our constrained infrastructure).
Central 25%+
Bakerloo - a peak service of around 27
trains per hour is expected. This is W&C Up to 50%
equivalent of a train nearly every 2
minutes, and although a lower service
than proposed on the other lines, will be Journey times - Waiting and travelling
a significant increase from today, times on the upgraded lines will reduce
commensurate with future demand and too. As an illustration, on the Piccadilly
crowding predictions on this line. line customers could experience
following approximate reductions in
Waterloo & City - A 30 trains per hour
typical journey times (including waiting
peak service could be offered on the
time):
Waterloo & City line with remodelling of
the track layout at Waterloo, although Heathrow - Leicester Square 7 mins
further investigations continue to confirm Hounslow - Kings Cross 6 mins
the operability of such a high frequency
Finsbury Park - Hammersmith 6 mins
of service on this constrained line.

46 New Tube for London - Feasibility Stage Summary


Feasibility outcomes
Service patterns

The feasibility study included a review of customers on those branches. In order


the strategic function of each line. to achieve this, Chiswick Park platforms
would need to be relocated to the
On the Piccadilly line, this involved
Richmond branch of the District line.
consideration of a number of
This would increase the number of trains
opportunities to ensure that the service
stopping at this station from the current
offering in west London is optimised for
6-7tph to 12-15tph.
the long-term. The feasibility study
concluded the following: Turnham Green - In conjunction with
this change, Piccadilly line trains will
Rayners Lane to Uxbridge - Both the
stop at Turnham Green throughout the
Piccadilly and Metropolitan lines should
traffic day post-upgrade, increasing the
continue to serve the section between
peak tph at this station from the current
Uxbridge and Rayners Lane. Curtailing
12-13tph to upwards of 40tph.
either line at Rayners Lane or more radical
options to extend the District line from
Acton Town to Uxbridge in place of the
Piccadilly cannot be justified.

Bakerloo - Similarly, the strategic role of


the Bakerloo line and London Overground
services in North West London were
Ealing Broadway - The Ealing Broadway considered as part of the feasibility
branch of the District line could in future study. The conclusions of this work were
be served by the Piccadilly line. The to retain the current service patterns on
Piccadilly line upgrade would provide both these services, as a case for change
sufficient train paths through central was not found.
London to enable this change, which
Whilst not directly delivering it, the
would allow a significant uplift in District
upgrade of the Bakerloo line will allow for
line services to Richmond and
a southern extension of the line should
Wimbledon, greatly benefiting
this be progressed in the future.

New Tube for London - Feasibility Stage Summary 47


Feasibility outcomes
The platform experience

NTfL can transform the platform


experience for customers.
Not only can waiting times be reduced
significantly but the waiting environment
can be improved too.
It is expected that ultimately Platform
Edge Doors (PEDs) will be implemented
on the majority of platforms served by
the New Tube for London. This will
provide a safer and more modern space
for customers who are waiting for their
trains, much like that provided on the trains with different door spacings and
underground stations on the Jubilee line floor heights.
extension.
At platforms to be fitted with PEDs,
PEDs cannot be implemented in the initial platform heights would be raised or
stages of the modernisation as they have lowered to create level access between
specific door spacing to match the trains the platform and the train at all
in service, and during the introduction of doorways.
the new trains, two different stock types
(existing and new) will be in operation on
the lines. Hence PEDs would be installed At platforms where curvature results in
after all of the existing trains have been an increased horizontal gap between the
withdrawn. train and the platform, mechanical gap
fillers are expected to be used. These
Platform Edge Doors are not suitable for
are metal extensions of the platform
the Bakerloo line between Kensal Green
which move out to fill the gap between
and Harrow & Wealdstone or the
the train and platform on curved
Piccadilly line between Rayners Lane and
platforms after the train arrives,
Uxbridge where Tube trains will continue
retracting before it then departs.
to share platforms with larger gauge

48 New Tube for London - Feasibility Stage Summary


New Tube for London - Feasibility Stage Summary 49
Conclusions

A comprehensive Feasibility Study has On the Piccadilly line, between Rayners


been carried out for the upgrade of the Lane and Uxbridge, and significant
remaining deep Tube lines. proportions of Bakerloo line (where
platforms are shared with larger gauge
Modernisation of the Piccadilly line will
trains) PEDs cannot be fitted; fully
deliver the greatest capacity uplift and
automatic operation is not considered
journey time savings. It therefore should
feasible on these parts of the network.
be the first major line for deployment of
the New Tube for London. Work continues apace to implement
these line upgrades at the earliest
Bakerloo and Central line modernisation
possible date, delivering significant
will follow, with the current expectation
benefits to customers of these deep
that the Bakerloo line will be second, to
Tube lines.
complete the replacement of London
Undergrounds oldest rolling stock. The next steps are currently as follows:
The Waterloo & City line will probably be 2015 New Tube for London rolling
modernised alongside the Central line, stock Invitation to Tender to be
however consideration is being given to issued
using this line as part of the trialling and 2016 New Tube for London rolling
testing plan for the NTfL concept. This stock contract to be awarded
would mean earlier modernisation
alongside the Piccadilly line. 2019 Railway Control System
installation on Piccadilly line
The programme expects to deliver saloon begins
air-cooling for customers in Londons
deep Tube tunnels for the first time. 2022 First new train delivered for pre-
production testing
High capacity, walk-through trains will be
procured and introduced. Additionally, 2023 First new train in service
the system can be designed with the 2025 Piccadilly line capacity
capability for fully-automatic operation, enhancements begin
should this mode of operation be needed
in the future.

50 New Tube for London - Feasibility Stage Summary


NTfL proposes to work towards the following outcomes when modernising
the Bakerloo, Central, Piccadilly and Waterloo & City lines:

Piccadilly line
A peak service level of 33-36tph, with air-cooled, walk-through
Tube trains, by 2025, over the current line geography, and
possibly the Ealing Broadway branch currently served by the
District line. The line will have PEDs and be capable of fully-
automatic operation (except between Rayners Lane and
Uxbridge).

Bakerloo line
A peak service level of 27tph with air-cooled, walk-through Tube
trains by 2027.

Central line
A peak service level of 33-36tph, with air-cooled, walk-through
Tube trains by 2032. The line will have PEDs and be capable of
fully automatic operation.

Waterloo & City line


A peak service level of up to 30tph, with air-cooled, walk-through
Tube trains by 2032. *The line will have PEDs and be capable of
fully-automatic operation.
* Subject to the role of W&C in the NTfL trialling and testing plan

New Tube for London - Feasibility Stage Summary 51


List of Figures and Images
Page Description
Cover Three of the proposed New Tube for London trains in depot
7 Network map showing forecast London Underground peak hour crowding in 2021,
with committed upgrades due to be in place by that date
8 Photograph of deep Tube tunnel shield construction method
Photograph of a typical deep Tube station soon after construction in the early 1900s
9 Bakerloo line 1972 Tube stock
Piccadilly line 1973 Tube stock
Central line 1992 Tube stock
11 Photograph of a Jubilee line platform
12 Network map highlighting the NTfL lines
14 Paris Line 1, fully automatic operation showing train and Platform Screen Gates
Paris Line 1, fully automatic operation showing Service Control Centre
16 NTfL Railway Level Design Process to be updated
17 Profile of New Tube for London concept train
18 Photograph of dwell time study being carried out at UCL PAMELA facility
21 Typical deep tube tunnel, showing track and curvature
22 Aerial view of London Road depot on the Bakerloo line
Northern line train demonstrating tight tunnel clearances
23 Flow chart of capacity modelling process
24 Plan and cut away of NTfL Tube car showing potential location of air cooling ducting
25 Potential installation of air cooling unit on vehicle under-frame
26 Existing Platform Air Handling Unit on the Victoria line
27 Chart showing net effect of upgrade elements on energy and temperature
29 Jubilee line platform with PEDs
30 Concept of overnight modular PED installation
31 Example obstacle detection LIDAR scanner on trial at Bank
32 Gap filler module built for NTfL accelerated life trials
34 Schematic of railway control system concept
35 Diagram of generic migration stages which could be applied to NTfL lines
36 Profile of New Tube for London concept train
37 Photograph of LU S Stock interior
Photograph of London Overground class 378
38 NTfL design mix
39 NTfL design palette
40-41 Exterior shot of NTfL train concept
42-43 Interior image of NTfL train concept, showing walk-though configuration
44-45 Interior image of NTfL train concept, showing cool air flow and removal of warm air

52 New Tube for London - Feasibility Stage Summary


47 LU map showing Rayners Lane area
LU map showing Chiswick area
48 Image of NTfL train at platform, showing level access
49 Image of NTfL platform with Platform Edge Doors and level access
51 Three of the proposed New Tube for London trains in depot

New Tube for London - Feasibility Stage Summary 53

You might also like