Professional Documents
Culture Documents
Feasibility Report
October 2014
The Feasibility Stage was initiated to The challenge is therefore to ensure that
examine the key challenges in service provision on the deep Tube lines
modernising the remaining deep Tube is optimised within the limits of the
lines and to respond to the following infrastructure constraints to provide the
requirements: maximum capacity to meet future
demand levels.
Capacity
Saloon air cooling
The deep Tube lines have fundamental
system design constraints, especially in Customer expectations regarding public
the central area tunnelled sections. New- transport vehicle temperatures have been
build metros provide high levels of influenced by the introduction of cooling
capacity using long, larger-gauge trains, systems on new trains and buses,
which are not possible on our Tube including London Undergrounds new S-
infrastructure. Stock being introduced on the Sub-
Surface lines (Circle, District,
Significant increases in capacity can,
Hammersmith & City and Metropolitan
however, be realised through the
lines). The deep Tube tunnels present a
coordinated application of new trains and
constrained environment for such
control systems underpinned by changes
technology, with the need to consider
to the physical infrastructure. The
the installation of cooling equipment
potential for improvement on each line is
within the restricted Tube gauge, and
unique to the particular constraints of
dissipation of heat.
that line.
The challenge is to determine whether
saloon air-cooling technology can be
Benchmark Finding: The level of trains
deployed on new trains in the deep Tube
per hour (tph) chosen by metros is
environment.
the result of a myriad of system
design factors (e.g. train length, wheel Managing tunnel temperatures
type, signalling system), customer Saloon air-cooling and operation of fast,
service / operational factors (e.g.
high-frequency services will increase
dwell times, crowding levels, access / energy and heat in the tunnels.
egress), and business objectives.
There is an optimal level for each The challenge is to determine how tunnel
metro / line but this varies between temperatures can be managed, whilst
applications. enabling the benefits of air-cooling and
capacity enhancements.
The NTfL feasibility study challenges are which discharges energy in the form of
closely inter-related. Therefore, their heat into the tunnels as a by-product.
analysis required a comprehensive, Consideration must therefore be given to
system-engineered design process. implementing infrastructure cooling
For example, delivering increased solutions to ensure the tunnel and
capacity is a key programme objective. platform environments remain
However, the effort to achieve this acceptable.
objective should not jeopardise achieving These can be complex in their own right,
others e.g. increasing reliability. so feasibility studies for implementation
Therefore, the intrinsic capability of the were carried out and iterated through the
existing infrastructure has to be overall system design.
understood, along with the impacts of
incremental changes that can be made to London Underground has many years of
improve this capability. experience of delivering large complex
engineering programmes. Lessons learned
The natural consequence of increasing from this experience have provided
capacity is an increase in energy demand. opportunities for continuous
Additional demand for energy is offset by
improvement in approaches and
optimising its use through the practices. NTfL has also drawn on
implementation of recognised strategies external best practice guidance (for
previously deployed on London example from The Royal Academy of
Underground. These include regenerative Engineering and other external expert
braking and new technologies to further guidance from BAe Systems) to define
increase system receptivity and energy the approach it would take to engineering
recovery. during the feasibility phase.
Deploying all of these strategies will not This approach was captured in a
fully mitigate the increase in energy framework called the Railway Level
demand due to the substantial increase in Design Management Framework (RLDMF).
capacity. Without mitigation measures,
there will be a consequential increase in The key feature of the framework was to
tunnel and platform temperatures due to coordinate the iterative development of
the increase in energy utilisation. This is many work streams of activities whilst
further reinforced by implementing maintaining an overall integrated systems
saloon cooling (a programme objective) approach. This was achieved by maturing
the understanding of key critical design
Modern rolling stock has a higher Customers can move through the train
performance capability than the existing so they are in the optimal section of
trains with better acceleration and the train at their destination station,
braking characteristics. These can reduce thus reducing the time spent exiting
journey times and enable a higher the system
frequency service to be operated from a The provision of a more continuous
given fleet size. Higher performance open space within the vehicle
capability is a core feature of a train improves security and reduces the
system upgrade, and one which has been opportunity for antisocial behaviour
achieved on several Underground lines Provision of through gangways on a Tube
over the past two decades. train with traditional configuration is very
The Feasibility Stage has investigated difficult, if not impossible, due to the
provision of more novel features for Tube dynamic behaviour of the vehicles. Tight
trains, such as open, wide gangways. curves, in particular, lead to large relative
These would offer a number of benefits movements between vehicles ends. This
to customers as follows: means an inter-car gangway would not be
possible without removing doors at the
Additional capacity is provided with
end of the carriages, due to the length of
improved configurations, including
the gangway which would be required.
walk-through rather than separate
carriages, creating more floor area as NTfL has identified that it is possible to
compared with traditional designs provide an inter-car gangway by altering
Customers can easily transfer between the Tube train design to incorporate an
carriages, meaning customers can articulated configuration with more,
distribute throughout the train, shorter carriages. By positioning the
avoiding busier carriages where vehicle bogies under the ends of two
possible. This in turn, will help to adjoining cars, the relative vertical and
reduce dwell times as a more evenly lateral movement of the carriage ends is
loaded train enables quicker boarding significantly reduced. This enables a
and alighting shorter, wide gangway to be fitted
Infrastructure
Line
Land Use Performance
Population
London Transport
Railplan
Studies Transport Train Service Model
(strategic public Line Demand
(strategic land use and Demand (LU line simulation)
transport)
transport)
Employment
Transport Network
New Tube for London - Feasibility Stage Summary 23
Summary of feasibility activities
Saloon air-cooling
Conventional Tube train design cannot Underground to conclude that a saloon
accommodate air cooling equipment cooling system could be fitted onto the
without taking up customer capacity in new train within the space, weight,
the vehicle interior since there is energy and capital cost assumptions
insufficient space available on the vehicle envisaged for the new train. The key
underframe for the air cooling modules. requirement to create space on the
The traditional rolling stock approach of vehicle underframe can be met by altering
placing this equipment in the roof space the train configuration to be articulated
is not viable on Tube trains given the which reduces the number of bogies
tunnel size and the need for sufficient required along the length of the train.
headroom for standing customers. The consequence of discharging waste
Detailed development studies have heat energy into the tunnels has been
determined the viability of configuring assessed and taken into consideration in
and reducing the size of the equipment the overall system design. This is covered
such that it can be both accommodated in more detail in the following section on
and maintained. A concept design study Managing Tunnel Temperatures.
was carried out and this has provided
sufficient information for London
The original design of the Edwardian deep extra low loss rails. Adopting these
Tube tunnel infrastructure did not strategies has been shown to increase
address ventilation such that it could be energy efficiency by up to 30 per cent.
scaled for current demand. When NTfL has also instigated a trial of an
originally built, the ground around the inverting substation on the Victoria line
tunnels varied with seasonal changes in
to determine if this technology has a role
temperature. Over time the ground has to play in the NTfL power solution. The
become permanently heated. Any trial is ongoing and due to report during
increases in temperature are the current programme stage.
consequently difficult to mitigate; a
unique challenge for London Infrastructure - If unmitigated, there will
Underground. be consequential increases in tunnel and
platform temperatures caused by higher
The overriding principle is to avoid energy utilisation and fitment of saloon
generating waste heat as far as is cooling on the trains. The train air cooling
practical. London Underground has discharges energy in the form of heat into
successfully deployed strategies to the tunnels as a by-product of the
optimise energy use in an attempt to do cooling.
so. The following elements have been
considered in the overall design: Consideration must therefore be given to
implementing infrastructure cooling
Train - Maximising the use of regenerative solutions, such as the over-platform air
braking, thus avoiding the braking energy handling units shown below, to ensure
being dissipated as heat by either friction the tunnel and platform temperatures
or resistor grids. More sophisticated train remain acceptable for our customers.
regulation systems can exploit
opportunities for more energy efficient
run profiles.
Transmission - Increasing the traction
supply voltage to 750 Volts helps reduce
losses, along with increasing the
regenerative voltage and current. Re-
sectionalisation of the network increases
the probability of energy recovery by a
receiving train. The conductor rails can
also be replaced by modern composite
s
Co U
mm
L
Da Non
ta
External Interfaces
Integrated
Command & LU Staff Customer
Control Member (outside NTfL)
Passenger &
Incident Monitoring
Information STATION
(inc CCTV)
Service and Fleet RCS
LU Mgnt Asset Performance
Comms
Manager Mgnt
LU LU SCADA Station Interfaces
Operations Maintenance Resource (including for PEDs)
Staff Member Staff Member Security Management
TRACKSIDE
NTfL RCS Encompasses
AT
tio
CT
nal
Members
Tra
Signalling Interfaces
/W
in
Systems
a ys
/W
(OCS)
TRAIN
ide
ATC Communications
Supporting Communications
The New Tube for London Feasibility Study Capacity - Greater capacity, up to 60 per
has determined that a world class cent on the Piccadilly line, will be
modernisation of the remaining deep Tube delivered to cater for Londons growth.
lines is possible and that all of the key Platforms - The platform experience will
challenges under consideration as part of be transformed at the majority of the
the programme can be overcome.
stations on these lines with full platform
A railway level system concept design has to train level access and Platform Edge
highlighted how a high capacity modern Doors, providing modern and safer
metro service can be achieved in spite of waiting environment.
the constraints imposed by the deep Temperature - Station cooling will also be
Tube Edwardian infrastructure. Line implemented at a number of sites
specific variations are expected to deal providing a cooler temperature for
with unique structural factors on some of customers waiting on platforms.
the lines but the core premise will remain
similar: Reliability - High levels of reliability are
being targeted based on benchmarking
New Tube for London - At the heart of with other world class metros. An NTfL
the design is the New Tube for London
upgrade target of 5 incidents per million
train concept which represents an car kilometres has been selected for the
evolution of traditional Tube train system design.
configuration such that walk-through, air-
cooled customer saloons can be The following sections step through
achieved. elements of the potential NTfL outcome
which customers could experience during
Quicker journeys - Customers will the coming decades.
experience significant improvements in
journey times due to faster and more
frequent services.
Piccadilly line
A peak service level of 33-36tph, with air-cooled, walk-through
Tube trains, by 2025, over the current line geography, and
possibly the Ealing Broadway branch currently served by the
District line. The line will have PEDs and be capable of fully-
automatic operation (except between Rayners Lane and
Uxbridge).
Bakerloo line
A peak service level of 27tph with air-cooled, walk-through Tube
trains by 2027.
Central line
A peak service level of 33-36tph, with air-cooled, walk-through
Tube trains by 2032. The line will have PEDs and be capable of
fully automatic operation.