STATUS OF SUPPLY OF FINISHING ITEMS - PHASE 2A

SL.
NO. DESCRIPTION TOWER AGENCY UOM SCOPE SUPPLIED BALANCE Schedule for Supply

1 NOS 128 128 - Delivery complete


PANNU INFRA
2 NOS 160 160 - Delivery complete

1 MAIN DOOR FRAME 3 NOS 159 159 - Delivery complete


MK TIMBER/KRISHNA
WOOD
4 NOS 160 160 - Delivery complete

20 ADSEL NOS 53 53 - Delivery complete

1 NOS 128 128 - Delivery complete


PANNU INFRA
2 NOS 160 160 - Delivery complete

2 MAIN DOOR SHUTTER 3 NOS 159 159 - Delivery complete


MK TIMBER/KRISHNA
WOOD
4 NOS 160 160 - Delivery complete

20 ADSEL NOS 53 53 - Delivery complete

1 NOS 792 792 - Delivery complete


PANNU INFRA
2 NOS 961 961 - Delivery complete

3 INTERNAL DOOR FRAME 3 NOS 1,035 1035 - Delivery complete


MK TIMBER/KRISHNA
WOOD
4 NOS 1,070 1,070 - Delivery complete

20 ADSEL NOS 610 610 - Delivery complete

1 NOS 792 319


PANNU INFRA 373
complete delivery by 10
Aug 16
2 NOS 961 461

4
INTERNAL DOOR 3 NOS 1,035 835 200
SHUTTER MK TIMBER/KRISHNA complete delivery by 10
WOOD Aug 16
4 NOS 1,070 571 499

20 ADSEL NOS 610 610 - Delivery complete

5
FIRE DOOR PHASE 2A SYNERGY NOS 653 653 0 Delivery complete
FRAME/SHUTTERS
1 NOS 640 640 - Delivery complete
KAENAT
2 NOS 716 716 - Delivery complete

6
ALUMINIUM DOOR 3 NOS 829 829 -
FRAMES
4 AXSYS NOS 866 866 - Delivery complete

20 NOS 430 430 -


1 NOS 292 292 -
KAENAT Delivery complete
2 NOS 266 266 -

7
ALUMINIUM 3 NOS 427 427 - Delivery complete
VENTILATOR FRAMES
4 AXSYS NOS 480 480 -
Delivery complete
20 NOS 266 266 -

1 NOS 640 640 -


KAENAT Delivery complete
2 NOS 716 716 -

8 ALUMINIUM SHUTTERS 3 NOS 1,790 1668 122 3-Aug-16

4 AXSYS NOS 1,861 1861 -


Delivery complete
20 NOS 390 390 -

1 NOS 640 450 190 Glass delivery to complete


KAENAT 20 Aug 16 with
2 NOS 716 400 316 installation

8 ALUMINIUM GLASS 3 NOS 795 490 305


Glass delivery to complete
4 AXSYS NOS 820 500 320 13 Aug 16 with
installation

20 NOS 424 350 74

1 Dreamz Infra/ Malani sqm 210 210 - Delivery complete


Marbles

2 Shiv Shanker Marble/ sqm 60 60 - Delivery complete


Malani Marbles

9
STONE WORKS(LIFT 3 Shiv Shanker Marble sqm 228 228 - Delivery complete
JAMB)
Shiv Shanker Marble/
4 Malani Marbles sqm 65 65 - Delivery complete

20 Shiv Shanker Marble/SJ sqm 254 254 - Delivery complete


Interior/malani

1 Dreamz/Malani sqm 510 510 - Delivery complete

2 Malani Marbles sqm 630 630 - Delivery complete

10
STONE WORKS(KITCHEN 3 Shiv Shanker Marble sqm 657 657 - Delivery complete
AND TOILET COUNTERS)
Shiv Shanker Marble/Malani
4 Marbles sqm 625 625 - Delivery complete

20 SJ Interior/Malani sqm 350 350 - Delivery complete

11
STONE WORKS(OMANI Phase 2A Deez Granite sqm 1,863 1863 - Delivery complete
WORKS)
STATUS OF SUPPLY OF FINISHING ITEMS - PHASE 2B
SL.
NO. DESCRIPTION TOWER AGENCY UOM SCOPE SUPPLIED BALANCE Schedule for Supply

15 NOS 164 125 39 6-Aug-16

16 PRADEEP GARG & SONS NOS 207 125 82 6-Aug-16

1
MAIN DOOR FRAME/ LV 17 NOS 180 100 80 6-Aug-16
SHAFT
18 DAY & NIGHT NOS 129 129 - Completed

19 DREAMZ INFRA NOS 75 75 - Completed

15 NOS 164 164 13-Aug-16

16 PRADEEP GARG & SONS NOS 207 207 13-Aug-16

2
MAIN DOOR SHUTTER/ 17 NOS 180 180 13-Aug-16
LV SHAFT
18 DAY & NIGHT NOS 129 50 79 6-Aug-16

19 DREAMZ INFRA NOS 75 75 6-Aug-16

5
FIRE DOOR PHASE 2A SYNERGY NOS 660 660 - Delivery complete
FRAME/SHUTTERS
15 Green Build Koncepts NOS 660 310 350 6-Aug-16

16 Al Sapphire NOS 864 413 451


13-Aug-16
6
ALUMINIUM DOOR 17 Al Sapphire NOS 716 310 406
FRAMES
18 Green Build Koncepts NOS 650 340 310 6-Aug-16

19 Kaenat NOS 424 52 372 13-Aug-16

15 Green Build Koncepts NOS 302 302

16 Al sapphire NOS 480 480


Formally revised
ALUMINIUM Schedule awaited
7 VENTILATOR FRAMES/ 17 Al sapphire NOS 266 266
SHUTTERS
18 Green Build Koncepts NOS 302 302

Formally revised
19 Kaenat NOS 266 266 Schedule awaited

15 Green Build Koncepts NOS 660 300 360 6-Aug-16

16 Al Sapphire NOS 864 864


Formally revised
Schedule awaited
8 ALUMINIUM SHUTTERS 17 Al Sapphire NOS 716 716

18 Green Build Koncepts NOS 650 150 500 6-Aug-16

19 Kaenat NOS 424 424 Formally revised


Schedule awaited
15 Green Build Koncepts NOS 660 660

16 Al Sapphire NOS 864 864

Formally revised
8 ALUMINIUM GLASS 17 Al Sapphire NOS 716 716 Schedule awaited

18 Green Build Koncepts NOS 650 650

19 Kaenat NOS 424 424

15 JJDJ/ Banke Bihari SQM 210 210 - Delivery Complete,


Installation complete
02 No Lift handed over,
16 JJDJ SQM 260 200 60 12 th floor

02 Nos lift handing over,


9
STONE WORKS(LIFT 17 Malani Marbles SQM 250 50 200 some issues of level dif
JAMB)
Three lifts handed over,
18 Malani Marbles SQM 210 120 90 two lifts complete 06 Aug
16
02 No Lift handed over
19 Malani Marbles SQM 254 150 104 25 July 2016
80 Kitchen angle
15 JJDJ/ Banke Bihari SQM 710 310 400 complete, 15 July 16
Till 10 Floor complete
16 JJDJ SQM 885 400 485 Toilet, Kitchen Ledge wall
pending
STONE 9 floor toilet and 6 floor
10 WORKS(KITCHEN AND 17 Malani Marbles SQM 650 200 450 kitchen complete, 20 Aug
TOILET COUNTERS) 15
9 floor toilet and 6 floor
18 Malani Marbles SQM 550 250 300 kitchen complete, 20 Aug
15

19 Malani Marbles SQM 340 340 25-Aug-16

STONE WORKS( GF No front avalaible in T-


10 Phase 2B Dees Granite SQM 600 155 445 15,16, 17, 18, due to
OMANI WORKS) floor conduiting

STONE WORKS(OMANI Phase 2B Malani Marbles SQM 650 200 450


No front avalaible in T-
WORKS - High end) 15,16, 17, 18, 19