Professional Documents
Culture Documents
Owner
Contractor
Location
Subject : BILL OF MATERIALS
Total Unit
Cost
A. GENERAL REQUIREMENTS
1.0 Mobilization / Demobilization lot 1.00
2.0 Permit and Licenses
2.1 Building Permit lot 1.00
2.2 Certificate of Occupancy lot 1.00
2.3 Miscellaneous Permit lot 1.00
3.0 Bonds & Insurances
3.1 Guarantee Repayment Bond lot 1.00
3.2 Performance Bond lot 1.00
3.3 CARI lot 1.00
3.4 Guarantee Bond lot 1.00
4.0 Temporary Facilities
4.1 Site Offices-CM, Architects, owner's rep" lot 1.00
(office table, fax machine, aircon, filing cabinet and computer set)
4.2 Conference Room lot 1.00
4.3 Warehouse lot 1.00
4.4 Staging Area lot 1.00
4.5 Quarters lot 1.00
5.0 Temporary Utilities
5.1 Temporary Power Supply & Fixtures lot 1.00
5.2 Lighting (All Areas) lot 1.00
5.3 Water lot 1.00
5.4 Toilets lot 1.00
5.5 Telephone/Communication lot 1.00
6.0 Security Services (24 hours) lot 1.00
7.0 As built plans & Shop Drawings lot 1.00
8.0 Scaffolding, shoring and support lot 1.00
9.0 Safety and housekeeping lot 1.00
10.0 Material Testing/FDT lot 1.00
11.0 Support Equipment lot 1.00
12.0 Site Supervision / Technical &Support Staff lot 1.00
13.0 Temporary Fence / Enclosure lot 1.00
14.0 Others (please specify) lot 1.00
B. CIVIL WORKS
1.0 Excavation cu.m. 2,617.84 250.00
2.0 Back Filling / Compaction cu.m. 711.69 175.00
3.0 Soil Poisoning sq.m. 1,433.83 250.00
4.0 Gravel Bedding cu.m. 597.57 1,290.00
5.0 Polyethelene Sheet sq.m. 5,051.97 55.00
6.0 PVC Waterstop l.m. 129.00 700.00
7.0 Cutting of Pile pcs. 225.00 650.00
8.0 Hauling / Disposal cu.m. 1,906.15 95.00
Sub-total Civil Works ###
C. STRUCTURAL WORKS
Note: RSB Gr. 60-12mm and up: Gr. 40-100mm and lower
1.0 Pile Cap
1.1 Concrete, 5000 psi cu.m. 355.52 5,500.00
1.2 Rebars, Grade 60 kgs 35,983.91 45.20
1.3 Formworks sq.m. 735.65 650.00
2.0 Footing Tie Beams
2.1 Concrete, 5000 psi cu.m. 298.90 5,500.00
2.2 Rebars
Grade 60 kgs 68,821.49 45.20
Grade 40 kgs 1,218.67 44.30
2.3 Formworks sq.m. 1,537.85 650.00
3 .0 Slab on Fill
3.1 Concrete, 3000 psi cu.m. 663.07 4,479.00
3.2 Rebars
3.2 Grade 40 kgs 21,145.77 44.30
Grade 60 kgs 53.78 45.20
4.0 Wall Footing
4.1 Concrete, 5000 psi cu.m. N/A
4.2 Rebars, Grade 40 kgs N/A
4.3 Formworks sq.m. N/A
5.0 Suspended Beams
5.1 Concrete, 5000 psi cu.m. 2,373.51 5,500.00
5.2 Rebars
Grade 60 kgs ### 45.20
Grade 40 kgs 19,549.00 44.30
5.3 Formworks sq.m. 11,315.73 670.00
6.0 Suspended Slab / Ledges
6.1 Concrete, 5000 psi cu.m. 1,767.37 5,500.00
6.2 Rebars
Grade 40 kgs 56,687.62 44.30
Grade 60 kgs ### 45.20
6.3 Formworks sq.m. 12,807.66 670.00
7.0 Column
7.1 Concrete, 5000 psi cu.m. 707.69 5,500.00
7.2 Rebars
Grade 40 kgs ### 45.20
Grade 60 kgs 113.19 44.30
7.3 Formworks sq.m. 3,648.31 670.00
8.0 R.C. Wall
8.1 Concrete, 5000 psi cu.m. 31.34 5,500.00
8.2 Rebars, Grade 40 kgs 1,365.82 44.30
8.3 Formworks sq.m. 491.93 670.00
9.0 Stairs
9.1 Concrete, 5000 psi cu.m. 52.43 4,479.00
9.2 Rebars
Grade 40 kgs 6,012.50 45.20
Grade 60 kgs 1,337.53 44.30
9.3 Formworks sq.m. 421.59 670.00
10.0 Walkalator Pit
10.1 Concrete, 5000 psi cu.m. 18.83 4,479.00
10.2 Rebars
Grade 40 kgs 1,593.60 45.20
Grade 60 kgs N/A
10.3 Formworks sq.m. 154.07 650.00
11.0 Concrete Gutter / Corbel / Parapet Wall / Lower wall for Ramp.
11.1 Concrete, 5000 psi cu.m. 97.72 4,479.00
11.2 Rebars, Grade 40 kgs 12,796.96 44.30
11.3 Formworks sq.m. 1,076.57 670.00
12.0 Equipment pad
12.1 Concrete, 5000 psi cu.m. 18.47 4,479.00
12.2 Rebars, Grade 40 kgs 794.87 45.20
Rebars, Grade 40 kgs 774.40 44.30
12.3 Formworks sq.m. 106.99 670.00
13.0 Cistern
13.1 Concrete, 5000 psi cu.m. 273.84 4,479.00
13.2 Rebars
Grade 40 kgs 32,052.80 45.20
Grade 60 kgs 1,302.62 44.30
13.3 Formworks sq.m. 171.80 670.00
14.0 Retaining Wall
14.1 Concrete, 5000 psi cu.m. 183.71 5,500.00
14.2 Rebars
Grade 40 kgs 45,681.54 45.20
Grade 60 kgs N/A
14.3 Formworks sq.m. 901.04 670.00
15.0 Concrete Pads
15.1 Concrete cu.m. same as e 4,479.00
15.2 Rebars
Grade 40 kgs same as e 45.20
Grade 60 kgs same as e 44.30
15.3 Formworks sq.m. same as e 670.00
16.0 Concrete Saddle
16.1 Concrete, 3000 psi cu.m. 1.42 4,479.00
16.2 Rebars
Grade 40 kgs 297.64 45.20
Grade 60 kgs
16.3 Formworks sq.m. 10.56 670.00
17.0 Structural Steel Works
17.1 Steel Truss, Purlins and all other accessories kgs 84,823.55 95.00
18.0 Seismic Gap
19.0 Others (Pls Specify)
Canopy Steel Frame lot 1.00
Sub-total Structural Works ###
C. ARCHITECTURAL WORKS
1.0 Msonry Works
a. 6'' CHB sq.m. 5,966.84 1450
b. 4'' CHB sq.m. 1,490.99 1100
c. Others (please speccify)
Sub Total ###
2.0 Tinsmithry
a. 0.6 mm (BMT) Corrugated G.I. Roofing Sheet Galvanum Long Span sq.m. 4,635.08 1115.5
Pre-painted Siver Grey
b. 32 kg Fiber Glass Insulation with double faced Aluminum Foil sq.m. 4,635.08 715
c. Spray applied insulation sq.m. N/A
d. Others (pls specify)
Sub Total ###
3.0 Waterproofing
a. Sanded Polybond (3.0 kg) Membrane Waterproffing (Gutter only) sq.m. 544.00 598
b. Others (pls specify)
Sub Total ###
Total ARCHITECTURAL WORKS ###
Plan Weekly
% Physical Accomplishment Accomplishment
Plan Cummulative Accom
Actual Weekly Accompli
% Actual Accomplishment
% Actual Accomplishment Actual Cummulative Acc
Variance
Prepared by:
Prepared By:
Prepared By:
A. GENERAL REQUIREMENTS
100,000.00 1.0 Mobilization / Demobilization lot
2.0 Permit and Licenses
585,000.00 2.1 Building Permit lot
200,000.00 2.2 Certificate of Occupancy lot
150,000.00 2.3 Miscellaneous Permit lot
3.0 Bonds & Insurances
235,094.80 3.1 Guarantee Repayment Bond lot
323,195.35 3.2 Performance Bond lot
380,587.63 3.3 CARI lot
55,000.00 3.4 Guarantee Bond lot
4.0 Temporary Facilities
150,000.00 4.1 Site Offices-CM, Architects, owner's rep" lot
(office table, fax machine, aircon, filing cabinet and computer set)
75,000.00 4.2 Conference Room lot
50,000.00 4.3 Warehouse lot
50,000.00 4.4 Staging Area lot
60,000.00 4.5 Quarters lot
5.0 Temporary Utilities
### 5.1 Temporary Power Supply & Fixtures lot
C. ARCHITECTURAL WORKS
1.0 Msonry Works
8,651,918.00 a. 6'' CHB sq.m.
1,640,089.00 b. 4'' CHB sq.m.
c. Others (please speccify)
Sub Total
2.0 Tinsmithry
5,170,431.76 a. 0.6 mm (BMT) Corrugated G.I. Roofing Sheet Galvanum Long Span sq.m.
Pre-painted Siver Grey
3,314,082.20 b. 32 kg Fiber Glass Insulation with double faced Aluminum Foil sq.m.
c. Spray applied insulation sq.m.
d. Others (pls specify)
Sub Total
3.0 Waterproofing
325,312.00 a. Sanded Polybond (3.0 kg) Membrane Waterproffing (Gutter only) sq.m.
b. Others (pls specify)
Sub Total
Total ARCHITECTURAL WORKS
###
an Weekly
complishment
an Cummulative Accom
% Physical Accomplishment
tual Weekly Accompli
% Actual Accomplishment
tual Cummulative Acc
% Actual Accomplishment
riance
Prepared by:
COST ESTIMATE
Amount
15,000.00
3,000.00
-
-
6,800.00
9,000.00
2,400.00
-
-
-
303.00
804.00
3,680.00
-
3,850.00
2,850.00
15.00
-
630.00
1,680.00
7,130.00
3,120.00
150.00
-
600.00
1,620.00
7,130.00
4,400.00
15,600.00
960.00
-
600.00
1,620.00
7,130.00
3,300.00
2,600.00
300.00
-
600.00
3,200.00
4,600.00
1,100.00
120.00
-
-
-
16,087.50
6,000.00
46,000.00
3,300.00
180.00
-
3,000.00
900.00
9,200.00
1,650.00
120.00
-
2,400.00
11,500.00
-
-
3,200.00
3,200.00
4,000.00
6,480.00
-
-
-
22,500.00
3,465.00
-
1,500.00
8,250.00
-
11,470.00
28,363.00
-
600.00
75,330.00
525.00
12,210.00
2,275.00
2,822.50
3,037.50
-
-
36,000.00
750.00
18,225.00
87,129.00
60,000.00
-
-
4,000.00
12,500.00
20,000.00
-
-
7,000.00
5,200.00
15,000.00
6,000.00
6,000.00
3,500.00
200.00
600.00
-
30,000.00
-
-
717,561.50
251,146.53
968,708.03
COST ESTIMATE
Amount
-
-
4,000.00
-
-
4,000.00
10,000.00
-
3,000.00
3,000.00
3,500.00
-
200.00
300.00
-
20,000.00
-
-
487,591.06
146,277.32
633,868.38
Total Unit
Cost
Qty. Amount
1.00 100,000.00
1.00 585,000.00
1.00 200,000.00
1.00 150,000.00
1.00 235,094.80
1.00 323,195.35
1.00 380,587.63
1.00 55,000.00
1.00 150,000.00
1.00 75,000.00
1.00 50,000.00
1.00 50,000.00
1.00 60,000.00
1.00 ###
1.00 100,000.00
1.00 275,000.00
1.00 100,000.00
1.00 80,000.00
1.00 300,000.00
1.00 100,000.00
1.00 150,000.00
1.00 457,800.00
1.00 50,000.00
1.00 ###
1.00 ###
1.00 150,000.00
1.00
N/A
N/A
N/A
same as 4,479.00
same as 45.20
same as 44.30
same as 670.00
1.00 462,623.05
###
###
###
###
###
###
Plan Weekly
Accomplishment
Plan Cummulative Acco
Actual Weekly Accompl
Actual Cummulative Ac
Variance
SPECIFICATION
Prepared By:
PRC # 0082018
PTR # 2155619
issued on : 02/07/2017
issued at : Bayambang, Pangasinan
ATION
O BED-ROOM BUNGALOW
MBANG, PANGASINAN
LA CRUZ JR.
CONFORME: