PRESUPUESTO DE TECHADO PARABOLICO DE LOSA DEPORTIVA - CASERIO LLUCHICATE

METRADO UND C.U TOTAL


1) TRABAJOS PRELIMINARES

LIMPIEZA DEL TERRENO MANUAL 240.00 M2 S/. 0.50 S/. 120.00

2) MOVIMIENTO DE TIERRAS

EXCAVACION PARA CIMIENTOS 12.00 M3 S/. 25.00 S/. 300.00


CONCRETO EN CIMIENTOS F`c = 175 kg/cm2 12.00 M3 S/. 300.00 S/. 3,600.00

3) VIGAS METALICAS DE 25 m
Angulos de 3"x3" 6 42 UND S/. 180.00 S/. 45,360.00
Soladadura 6 25 KG S/. 12.50 S/. 1,875.00
Pintura 6 6 GLN S/. 50.00 S/. 1,800.00
Thiner 6 6 GLN S/. 20.00 S/. 720.00
Mano de Obra 6 1 GLB S/. 1,500.00 S/. 9,000.00

4) VIGUETAS
Angulos de 1"x1/8" 220 UND S/. 60.00 S/. 13,200.00
Fierro Liso 1/2" 300 UND S/. 22.00 S/. 6,600.00
Soldadura 25 KG S/. 12.50 S/. 312.50
Zincromato 6 GLN S/. 50.00 S/. 300.00
Esmalte 6 GLN S/. 50.00 S/. 300.00
Thiner 12 GLN S/. 20.00 S/. 240.00
Disco de Corte 7" 20 UND S/. 7.00 S/. 140.00
Mano de Obra 578 ML S/. 8.00 S/. 4,624.00

5) COLUMNAS METALICAS DE 8 m de 25x25


Plancha 1/4 3.5 PLANCHA S/. 500.00 S/. 1,750.00
Doblado de Plancha 1 GLB S/. 1,800.00 S/. 1,800.00
Soldadura 25 KG S/. 12.50 S/. 312.50
Pintura 5 GLN S/. 50.00 S/. 250.00
Thiner 5 GLN S/. 20.00 S/. 100.00
Mano de Obra 12 UND S/. 1,500.00 S/. 18,000.00

6) CORREAS
Fierro Liso 3/8" 120 UND S/. 13.50 S/. 1,620.00
Soldadura 25 KG S/. 13.50 S/. 337.50
Pintura 4 GLN S/. 50.00 S/. 200.00
Thiner 4 GLN S/. 20.00 S/. 80.00
Mano de Obra 1 GLB S/. 2,500.00 S/. 2,500.00

7) CALAMINAS 0.80 X 1.80


CALAMINA 1.80 x 0.80 800 UND S/. 17.00 S/. 13,600.00
PERNO 3 " X 1/4 " 5000 UND S/. 0.80 S/. 4,000.00

8) MONTAJE DE ESTRUCTURAS
MONTAJE DE VIGAS PRINCIPALES 6 UND S/. 2,500.00 S/. 15,000.00
MONTAJE VIGUETAS 1 GLB S/. 7,800.00 S/. 7,800.00
MONTAJE COLUMNAS 1 GLB S/. 5,000.00 S/. 5,000.00
COLOCACION CALAMINAS 1 GLB S/. 8,000.00 S/. 8,000.00

TOTAL S/. 168,841.50