Testing&CommissioningOfFireSuppressionSystem
The scope of method statements covers the planning,
OracleGRC preparation, and conduct of fire suppression systems
cablelaying,Installationtestingandcommissioning.
Training
LearnHowtoImplementandUse Preparation&PreTesting&CommissioningWork
OracleGRCwithAccesstoGRC
apps.Gototheoicllc.com 1.Before start of testing & commissioning the completeness
ofthesystemshallbeensuredbyphysicalinspectionsand
interpreting the previously submitted and approved work
H2Smeasurement inspectionreports/records.
ATEXZone 2.All tools/equipment/instruments required are calibrated
MonitoringofH2SvaluesinATEX andhavingvalidcertificate.
zonesviaGSMorBLEGoto 3.Safe access to work areas shall be provided and shall be
microtronics.at/h2s
approvedbythesafetypersonpriortocommencementof
works.
4.Temporaryrequirementstobearrangedwhererequired.

Precableandinstallation:

Thefollowinginitialactivitiesmustbefollowedandtakenintoaccountasmandatorybytheauthorizedpersonalto
dothework.

Manpower:

Thecompetentpersonmustbeassignedtotheproject/worktobeundertaken.Thecompetentpersonmusthave
theauthoritytostoptheworkbeingundertaken,ifrequired,whenhazardisidentified.Thecompetentpersonwill
actasthesitesupervisor.

Workersshallbeskilledandsomeonewiththeskills,understandingandexperiencetobeabletocarryoutatask
correctlyandsafety.

Planningandpreparation:

Beforetheinitialcablelayingworkstarts,thecompetentperson,shallcarryoutthefollowingpreplanningworks.

Obtain all relevant information and drawings and then inspect the proposed work at site. Obtain all necessary
workpermitsandpassesfromtheauthoritieshavingjurisdiction.

Ensurethattheentireteammemberaretrainedproperly.
Ensure that the all team member have the appropriate personnel protective equipment (Safety shoe,
Helmet,Eyesafetyglass,Safetybeltandsafetyglovesandjackets.)

http://methodstatementhq.com/testingcommissioningoffiresuppressionsystem.html 1/5
11/8/2016 Testing&CommissioningOfFireSuppressionSystem

Demarcationofworkarea:

Workareashallbeidentified,barricadedaroundtheperipherywithtapesandconesalongwithsignboard.The
variouspointsmarkedforsmokedetectors,ontherooflevelforeachzone.

COMMISSIONINGOFFIRESUPPRESSIONSYSTEMS

PreCommissioning

RemoveSolenoidoutputcablecablefromcontrolpanel
ApplyACPowerandconnectBattery
CheckallLEDsstatus
CheckAuxiliaryvoltageitshouldbe24VoltDC
Checkzonescircuit.
CheckSoundercircuits(FirstStage&SecondStage)

ZoneTest

Applydetectortestliquidonthedetectorandcheckfollowingsequence.
FirstSounderstagealarmstarts.
Thedetectorgoesintofireconditionafterappliedtestliquid.
CheckthecommonfireLEDandrespectivezoneLEDshouldindicate
CheckthecommonfireLEDandrespectivezoneLEDshouldindicate
Checkcommonfirerelyoutput.
Presssilence/soundalarmbuttonandresetbuttons.
RepeatthesameaboveprocedureforZone2Test

CrosszoneTest

RemovesolenoidoutputterminalfromtheControlpanel
Applytestliquidonthezone1&Zone2(orwhateverapplicable)detectors.
Checkbothsounderstagealarmstatus.
Monitorthesevensegmentdisplayandcheckdelaycountertimerstart
Placethemultimeteracrossthesolenoidterminalandcheckthevoltageattheenddelaytimer.Itshouldbe
24
CheckVDCatfractionofsecondtooperatesolenoidvalve
Checkallcablepolarity+,etc.

http://methodstatementhq.com/testingcommissioningoffiresuppressionsystem.html 2/5
11/8/2016 Testing&CommissioningOfFireSuppressionSystem

PhysicalInspection

Checkallthedevicesinstalledaspertheapproveddrawings.
CheckthecontrolPanelmountedproperly
Checkalldetectorbasemountedproperly
ChecktheEOL18VTransorbfittedornotinthelastdetector.
CheckallnecessaryEOLmountedornot.
CheckinstallationofExtinguishingdevices(Piping,cylinder,LPS,Solenoid)etc.
Checkallthesupportsproperlyinstalled.
CheckpowerONLED&OperatingAccessLEDshouldbelitandallotherLEDsshouldnotbelit.
Checkallthecablesproperlylabelledornot.

SystemCheck:

ChecktheSolenoidscableisdisconnectedfromthepanel.
Checkthepanelstatuscontacts(Fault&Fire)toexternalbuildingfirealarmpanel.
Createanyfault,likebyremovingbatteryterminalorswitchoffACpowerorremovingdetectorsorremoving
soundersetc.andobservefaultLEDandstatuscontacts.
Stimulate fire to zone 1 detector by using spray liquid and observe, the detectors go into fire (LED) &
CorrespondingZoneLEDinthepanel.
Checkthefirestatuscontactstobuildingfirecontrolpanel
Checkthesounder1workingornotSilencethesounderandreset
Checkthepanelgoesintonormalconditionafterresetit
Repeataboveforprocedureforallthedetectors.

CrossZoneFunction:

Stimulatefireforbothzonesdetectorsimultaneouslyandmonitorbelowsequence.

1.Checkallsoundersshouldbeactivated
2.FireLEDshouldactivatedinthecontrolpanel
3.CheckDelaytimerstart(30Seconds)
4.Checkthevoltageatsolenoidend,24VoltDCshouldcomeafterendofthedelaytimer.
5.Thevoltageshouldkeepshows5Seconds
6.Resetthecontrolpanel.

AbortFunction:

Stimulatefireforbothzonesdetectorandobservetheabovesequences.
PressanyoneAbortswitchtostopextinguishing
AbortLEDshouldlitinthecontrolpanel
TheMultimetershouldnotshow24VDCatendofthedelaytimer.
Releasetheabortswitchandresetthepanel.
Checkthepanelshouldgointonormalmodeafterreset.

ManualRelease(ElectricallyRemoteoperation)

http://methodstatementhq.com/testingcommissioningoffiresuppressionsystem.html 3/5
11/8/2016 Testing&CommissioningOfFireSuppressionSystem

Checkthepanelisinnormal
SlidetheAeromarksymbolintheplatewhichisshowninthemanualgasrelease.
InserttheKer(Red)intothemanualreleaseandturnit.
Thetopcoverwillcomeoutandthenpressthebuttonandmonitorbelowsequence.
CheckManualreleaseandactuatorLEDsshouldlit
Checktwosounder(Flasher&Horn)Workingproperly
Checkthedelaytimer(30Seconds)
Measurethevoltage(24VoltDC)acrossthesolenoidatendofdelaytimer.

The testing and commissioning procedures shall be in compliance with Specification and applicable NFPA
standard.

PipePressureTestwillbedoneandresultsshallbeprovided.
RoomIntegrityTestwillbeprovided.
FunctionalityofMagneticdoorholderwillbeprovided&confirmed.
InterfacingwithFireAlarmPanelwillbeprovidedandconfirmed.
FunctionalityofAlarmBellwillbeprovidedandconfirmed.
AgentsDischargetimeandduration.
Loopandinsulationtestofthecableswillbeprovided
BatterytestshallbeasperSpecs&NFPA2001.
Visualverificationofsolenoidvalvefunctionalityshallbetestedanddemonstrated.

RoomIntegrityTest

WhendeployingaCleanAgentsystemitisvitaltotesttheintegrityofaroomistoensuretheprotectedareais
wellsealedandtheCleanAgentextinguishingmediawontescape.

CompliancewithNFPA2001(2008ED.)requires:

The enclosure protected by the clean agent shall be thoroughly inspected at least every 12 months to
determine if penetrations or other changes have occurred that could adversely affect agent leakage or
changevolumeofhazard,orboth.Wheretheinspectionindicatesconditionsthatcouldresultintheinability
tomaintainthecleanagentconcentration,theconditionsshallbecorrected.
Whereexternalvisualinspectionindicatesthecontainerhasbeendamaged,additionalstrengthtestsshall
berequired.
All persons who could be expected to inspect, test, maintain, or operate fire systems shall be thoroughly
trained
All total flooding systems shall have the enclosure examined and tested to locate and effectively seal any
significant air leaks that could result in a failure of the enclosure to hold the specified agent concentration
level for the specified holding period. The current preferred method is using a blower door fan unit and
smokepencil.

Room Integrity tests should be carried out at the design stage of a Clean Agent systems and annually
thereafterandevenmorefrequentlyifthespacemayhavechangedduetorenovations,orlayoutchanges.

Thistestingdeterminestheexactdesignofthecleanagentsystem,andmayalsoindicateaneedforotherwork
needingtotakeplaceinordertosealgapswithinthespacetobeprotected.
http://methodstatementhq.com/testingcommissioningoffiresuppressionsystem.html 4/5
11/8/2016 Testing&CommissioningOfFireSuppressionSystem

Inspection,
Commissioning
HMSWebHandover
ManagementSystemInspection,
Completions&Commiss.
hmsweb.com.br

RelatedMethodStatements:

MethodStatementFor MethodStatementFor MethodStatementFor


Testing&Commissioning Testing&Commissioning Testing&Commissioning FireAlarmSystem
Of OfFire OfFoamSystem Installation&

Testing&Commissioning
ReportForFireAlarm Testing&Commissioning