NOTES:

1This drawing shall be read in conjuction with all


relevant drawings.
2 Foundations shall generally be taken down below
existing ground level 1000mm and all excavations
to be confirmed by engineer.
3 Weak pockets of bearing strata to be dug out
and filled with 1:4:8 all in concrete mix
4 Concrete mixes
(a) Mass concrete to have a minimum works
cube strength of 15N/mm^2 at 28 days with
40mm maximum aggregate size
(b) Reinforced concrete to have works
cube strength of 25N/mm^2 at 28 days with
20mm maximum aggregate size
5 Reinforcement
(a) High yield bars to be square twisted cold
formed bars to B.S. 4461
(b) Mild steel to be round bars to B.S. 4449
(c) Mesh reinforcement to comply with
requirement of B.S. 4483
6 Minimum cover to all steel in foundations = 50mm
Stub column = 40mm
Beams = 25mm
Slab = 25mm
Columns = 40mm
unless otherwise specified
7 All dimensions must be verified on site
before cutting any reinforcement
8 All dimensions must be checked on site
before commencing any works.
9
MUJU CONSULTING ENGINEERS LIMITED
STRUCTURAL & CIVIL ENGINEERS
KIKUBA HOUSE P.O.BOX 11284 KAMPALA
PLOT 967 MBOGO ROAD KIBULI TEL 0772838691,0752693987,0312261050
PROJECT PROPOSED RESIDENTIAL BUILDINGS AT PLOT 7529, BLOCK 244,
KISUGU
CLIENT MR. KENNETH SEMAFUMU, P.O.BOX 16568, KAMPALA
TITLE ROOF BEAMS DETAILS
ARCHITECT JR CONSULTANTS P.O.BOX 33096 KAMPALA
DRAWN RONNIE LULE
CHECKED ENG. DR UMARU BAGAMPADDE
SCALE 1:10, 1:20 DATE NOVEMBER 2016
DRG NO. 0022016 SHEET NO. 09
NOTES:
1This drawing shall be read in conjuction with all
relevant drawings.
2 Foundations shall generally be taken down below
existing ground level 1000mm and all excavations
to be confirmed by engineer.
3 Weak pockets of bearing strata to be dug out
and filled with 1:4:8 all in concrete mix
4 Concrete mixes
(a) Mass concrete to have a minimum works
cube strength of 15N/mm^2 at 28 days with
40mm maximum aggregate size
(b) Reinforced concrete to have works
cube strength of 25N/mm^2 at 28 days with
20mm maximum aggregate size
5 Reinforcement
(a) High yield bars to be square twisted cold
formed bars to B.S. 4461
(b) Mild steel to be round bars to B.S. 4449
(c) Mesh reinforcement to comply with
requirement of B.S. 4483
6 Minimum cover to all steel in foundations = 50mm
Stub column = 40mm
Beams = 25mm
Slab = 25mm
Columns = 40mm
unless otherwise specified
7 All dimensions must be verified on site
before cutting any reinforcement
8 All dimensions must be checked on site
before commencing any works.
9
MUJU CONSULTING ENGINEERS LIMITED
STRUCTURAL & CIVIL ENGINEERS
KIKUBA HOUSE P.O.BOX 11284 KAMPALA
PLOT 967 MBOGO ROAD KIBULI TEL 0772838691,0752693987,0312261050
PROJECT PROPOSED RESIDENTIAL BUILDINGS AT PLOT 7529, BLOCK 244,
KISUGU
CLIENT MR. KENNETH SEMAFUMU, P.O.BOX 16568, KAMPALA
TITLE ROOF BEAMS DETAILS
ARCHITECT JR CONSULTANTS P.O.BOX 33096 KAMPALA
DRAWN RONNIE LULE
CHECKED ENG. DR UMARU BAGAMPADDE
SCALE 1:10, 1:20 DATE NOVEMBER 2016
DRG NO. 0022016 SHEET NO. 10

You might also like