Professional Documents
Culture Documents
www.elsevier.com/locate/epsr
Received 20 February 2001; received in revised form 15 May 2001; accepted 1 October 2001
Abstract
This paper presents an adaptive protection scheme for optimal coordination of overcurrent relays (OCR) in interconnected
power networks with an improved formulation. The scheme adapts to system changes; new relays settings are implemented as
load, generation-level or system-topology changes. The software developed for this application is described. The developed scheme
is applied to the IEEE 30-bus test system. Results showed the importance and necessity of this scheme in maintaining the optimal
performance of the relays under all conditions. 2002 Elsevier Science B.V. All rights reserved.
Keywords: Overcurrent relay coordination; Optimization; Adaptive protection; Interconnected power networks
0378-7796/02/$ - see front matter 2002 Elsevier Science B.V. All rights reserved.
PII: S 0 3 7 8 - 7 7 9 6 ( 0 1 ) 0 0 1 7 6 - 6
2 A.Y. Abdelaziz et al. / Electric Power Systems Research 61 (2002) 19
Table 1
Loads, fault currents and TDS for IEEE 30-bus system
Relay Operating condition Load current (A) Near-end fault current (A) CT ratio Ipu (A) Optimal TDS (0.051)
Table 1 (Continued)
Relay Operating condition Load current (A) Near-end fault current (A) CT ratio Ipu (A) Optimal TDS (0.051)
The problem formulation can be demonstrated with greater than the sum of the operating times of its
the help of Fig. 1 and by assuming a network consisting primary relay and the coordination margin. This can be
of n relays, the objective function J to be minimized can expressed as:
be expressed as:
Tji ] Tii + CTI (3)
n
J= % Tii (2) where: Tji is the operating time of the backup relay Rj
i=1
for the same near-end fault at i, and CTI is the coordi-
where Tii is the operating time of the primary relay Ri nation time interval.
for a near-end fault i. From Eq. (1) one can see that the relation between
The operating time of the backup relay must be the operating time T of the time overcurrent unit, and
A.Y. Abdelaziz et al. / Electric Power Systems Research 61 (2002) 19 5
Table 2
Samples of OCR operating times for IEEE 30-bus test system (MXLG-1)
Backup relay no. Time (s) Primary relay no. Time (s) Backup relay no. Time (s) Primary relay no Time (s)
Table 3
Samples of OCR operating times for IEEE 30-bus test system (MNLG-1)
Backup relay no. Time (s) Primary relay no. Time (s) Backup relay no. Time (s) Primary relay no Time (s)
Table 4
Samples of OCR operating times for IEEE 30-bus test system (MXLG-2)
Backup relay no. Time (s) Primary relay no. Time (s) Backup relay no. Time (s) Primary relay no Time (s)
Table 5
Samples of OCR operating times for IEEE-30 bus test system (MNLG-2)
Backup relay no. Time (s) Primary relay no. Time (s) Backup relay no. Time (s) Primary relay no Time (s)
Fig. 2 shows the functional block diagram of the 4.1. Topology processor
adaptive relaying scheme proposed for overcurrent pro-
tection of the power system. Similar configurations of The topology processor tracks the network topology
relays and computers are used at other substations. The over the time. The circuit breaker status information is
relays sample line currents via current transformers. the main input to this module. The topology processor
Each relay possesses quantized samples and calculates feeds the network information to the load flow program
voltage and current phasors. Under normal operating and the fault analysis program.
conditions, each relay provides the measurements to the
substation control computer at regular intervals. 4.2. Optimal coordination procedure
The SCADA system checks the status of local isola-
tors and circuit breakers and provides the information Just as described in Section 2 using a linear program-
to the substation computers. In addition to communi- ming technique (Active Set Strategy two-phase method)
cating with the relays, the station computer pass on the as follows:
collected information to the central computer at prespe- In phase I, a feasible solution is obtained and in
cified intervals (e.g. 1 h). phase II, the optimal solution is found.
The central computer estimates the system state and
decides whether or not the relay settings should be 4.3. Transfer settings to the relays
changed. If it decides to change the settings, it will
calculate the new settings and conveys them to the In adaptive coordination of overcurrent relays, it is
relays via the substation control computers. The relays assumed that all relays are of digital type and that there
A.Y. Abdelaziz et al. / Electric Power Systems Research 61 (2002) 19 7
is a communication channel between them and the distribution system of the IEEE-30 bus system. Full
substation control computers (optic-fiber cables) as results of the whole system are listed in Ref. [15].
shown in Fig. 2. Hence, once the relay settings are Two modes of operation are assumed for the relay-
calculated, these are communicated to the respective ing scheme: nonadaptive and adaptive modes. In the
relays. nonadaptive mode, the relay settings are optimized
based on the concepts discussed in Section 2 corre-
4.4. Monitoring sponding to the operating condition of state 1
(MXLG-1: maximum generation and load with line-2
The power system is continuously monitored, using is in service). Meanwhile, in the adaptive mode the
SCADA system, for any change operational or topo- relay settings will be updated according to the signifi-
logical. If the change detected is an operational cant changes detected under the operating conditions
change, the computer will restart the coordination discussed in this section.
process from the load flow program and if the change Tables 25 show samples of overcurrent relay op-
is due to a topological change, the procedure will be erating times for the four operating conditions in the
restarted from the topology processor. nonadaptive and adaptive modes.
From the previous four studied states, it is con-
cluded that:
5. Application of the proposed methodology to the In state-1, optimal solution is obtained without any
IEEE 30-bus system miscoordination case, because the optimal coordina-
tion is conformed with this state (maximum load and
Considering the IEEE 30-bus test system shown in generation and all lines are in service).
Appendix A, it consists of two subsystems (subtrans- In state-2, when the maximum loads and generations
mission system 132 kV and distribution system 33 are reduced to minimum (operational change), there
kV). The conjunction substations have 132/33 kV is 26-miscoordination case in the nonadaptive mode,
step-down transformers. Each line is equipped with a but in the adaptive mode this problem is removed.
circuit breaker at each end. Each breaker is equipped In state-3, when the system operates at the maximum
with a directional overcurrent relay (with inverse load and generation condition, but line-2 is removed
characteristics). Directional overcurrent relays are (topological change), there is 18-miscoordination case
used to protect the 33/132 kV transformers and load in the nonadaptive mode but in the adaptive mode
circuit emanating from the substations. The system this problem is also removed. It is worth mentioning
data (loads and line parameters) are given in Ref. that only a local sub-system has been affected by the
[15]. disturbance.
To investigate the adequacy of the developed al- In state-4, the system undergoes both topological and
gorithm and the necessity of adaptive scheme for operational changes (the maximum loads reduce to
changing system conditions operational and/or topo- minimum with line-2 outage). This case is the worst
logical, the following four operating states of the sys- because it resulted in 35-miscoordination case. These
tem were considered: miscoordination cases are removed by following the
State 1: Maximum system load and generation with adaptive protection scheme.
line L2 is in service (MXLG-1).
State 2: Minimum system load and generation with
line L2 is in service (MNLG-1). 6. Conclusions
State 3: Maximum system load and generation with
line L2 is open (MXLG-2). An adaptive protection scheme for optimal coordi-
State 4: Minimum system load and generation with nation of the directional overcurrent relays in inter-
line L2 is open (MNLG-2). connected power networks with an improved
Load flows under different operating conditions formulation has been introduced. This algorithm is
were conducted and relay currents for faults at differ- applied to the IEEE 30-bus test system with system
ent near-end locations in the system were calculated. condition changes, operational and/or topological.
A coordination time interval of 0.2 s was adopted, The results showed that the proposed adaptive
with a TDS in the range of 0.05 1. The current scheme has exhibited optimal performance in the
transformer (CT) selection was achieved based on the studied cases without any miscoordination case.
maximum load and fault currents in order to prevent
the miscoordination problem resulting from CTs sat-
uration. Table 1 shows the load and fault currents, Appendix A
CT values and Ipu selections and the optimal TDS for
the four mentioned operating states for the 33 kV Fig. 4
8 A.Y. Abdelaziz et al. / Electric Power Systems Research 61 (2002) 19
[6] N.A. Laway, H.O. Gupta, A method for coordination of overcur- Power Delivery 4 (1) (1989) 177 185.
rent relays in interconnected power systems, IE J. 74 (1993) 59 65. [11] A.G. Phadke, S.H. Horwitz, Adaptive relaying, IEEE Computer
[7] B. Chattopadhyay, M.S. Sachdev, T.S. Sidhu, An on-line relay Appl. Power (1990) 47 51.
coordination algorithm for adaptive protection using linear pro- [12] IEEE Working Group, Adaptive Protection and Control Commit-
gramming technique, IEEE Trans. Power Delivery 11 (1) (1996) tee, Feasibility of Adaptive Protection and Control, Paper No. 92
165 173. SM 384-8 PWRD.
[8] A.J. Urdenta, L.G. Perez, H. Resterbo, Optimal coordination of [13] Ammar Hajjar, A.Y. Abdelaziz, H.E.A.Talaat, A.I. Nosseir,
directional overcurrent relays considering dynamic changes in the Optimal coordination of overcurrent relays by linear program-
network topology, IEEE Trans. Power Delivery 12 (4) (1997) ming: an enhanced problem formulation, Proceedings of Third
1458 1464. CIGRE Regional Conference for Arab Countries, Douha, May
[9] S.H. Horwitz, A.G. Phadke, J.S. Thorp, Adaptive transmission 1999.
system relaying, IEEE Trans. Power Delivery 3 (4) (1988) 1436 [14] IEC Standard, Single Input Energizing Quantity Measuring Re-
1445. lays with Dependent Specified Time, Publication No. 255-4, 1976.
[10] A. Jampala, S. Venkata, M. Damborg, Adaptive transmission [15] Ammar Hajjar, MSc Thesis in Electrical Engineering, Ain Shams
protection: concepts and computational issues, IEEE Trans. University, June 1999.