You are on page 1of 48

--

-- --
XII

HSE
Health C Safety
Executive

l%e &es and e x p l m i at


BP Oil (Gm$emouuth)
Rehery Ltd
A report of the investigations by the
Health and Safety Executive into the fires and
explosion at Grangemouth and Dalmeny,
Scotland, 13 March, 22 March and 11.June
l987
@ Crown copyright 1989
First published 1989

Any enquiries regarding the content of


this publication should be addressed to:
HSE Area Office
Belford House
59 Belford Road
Edinburgh
EH4 3UE
tel031-225 1313
The fires and
explosion at BP Oil
(Grangemouth)
Refinery Ltd
A report of the investigations
by the Health and Safety
Executive into the fires and
explosion at Grangemouth and
Dalmeny, Scotland, 13 March,
22 March and 11 June 1987

Contents

Introduction 1
Action taken 1
Description of the sites 1

The refinery flare line incident: 13 March 1987 2


The flare line system 2
Events leading to incident 4
The permit to work 8
The incident 11
lnvestigation by HSE 12
Preventive measures to avoid the incident 13
The hydrocracker explosion and fire:
22 March 1987 15
The hydrocracker unit 15
Events leading to incident 17
The explosion and fire 17
lnvestigation by HSE 19
Causes 28
Conclusions 33
Preventive measures to avoid the incident 34
Fire in crude oil storage tank at Dalmeny:
11 June 1987 36
The site 36
Events leading to the incident 36
The incident 38
lnvestigation by HSE 38
Conclusions 42
Bibliography 44

London: Her Majesty's Stationery Office


Introduction Regulations 1984 (CIMAH). The process of
producing and periodically reviewing
1 This booklet describes the safety reports should lead to the
investigations made of three separate identification and elimination of
maintenance related incidents within a deficiencies in plant and systems of work
major British Company in 1987. The four such as are illustrated by these case
deaths caused were all of contractors' studies. HSE emphasise that safety
men. The second incident, which invites reports for existing plant must reflect
comparison with the Flixborough disaster, actual conditions and be based on
could have had serious consequences for appraisal of the plant as it is functioning
the public. The case studies here at the time. A management view of how it
presented illustrate further the lessons should ideally be will not suffice - HSE
drawn by the HSE publication Dangerous hope that study of these incidents will
Maintenance: A study of maintenance demonstrate to companies undertaking
accidents in the Chemical Industry and hazardous operations the need for
how to prevent them (Ref 1). continuing self appraisal and constant
vigilance.
2 Firstly, a fire of flammable liquids,
unexpectedly (although foreseeably) Action taken
present and released during maintenance
of a refinery flare system, killed two men 6 Following investigations into the
and seriously injured two more. Potential incidents at the refinery, the HSE
ignition sources had not rigorously been recommended to the Procurator Fiscal at
excluded, means of escape were Falkirk that two cases be taken against
inadequate, and permit-to-work procedures the operating company for breaches of
had been devised and were being Sections 2 and 3 of the Health and Safety
implemented without sufficient awareness at Work etc Act 1974. These were heard
of potential hazards. in the High Court in Edinburgh on 21
March 1988 when a fine of 250 000 was
3 Secondly, one man was killed and imposed for the charge relating to the
extensive damage was caused by a major circumstances of the flare line incident
explosion with consequent fire while the and E500 000 for the second charge
refinery hydrocracker plant was being arising out of the hydrocracker explosion.
recommissioned after repairs. Debris 7 The circumstances of the fire at
weighing several tonnes was propelled up Dalmeny were reported to the Procurator
to 1 km, in some instances off-site. Fiscal at Edinburgh and a Fatal Accident
Rupture of a vessel occurred following Inquiry was held from 10-16 March 1988.
breakthrough of high pressure hydrogen,
probably caused by less than perfect Description of the sites
operating practices and made possible by
the disconnection of safety devices. 8 BP Oil (Grangemouth) Refinery Ltd is
part of BP Oil International. Their refinery
4 Lastly, a fire within a storage tank at site, situated on the outskirts of
the refinery's crude oil terminal killed one Grangemouth close to the River Forth,
of a contractor's team removing sludge. has been there since the early 1920s.
Smoking caused ignition. There had been Eight million tons of crude oil are
persistent deliberate evasion of safety processed per annum. There are 1200 full
rules by some of that team - equally, time employees and up to 1000
those rules had not been effectively contractors may be employed on
enforced by either the site occupier or the maintenance. Crude oil is received by
contractor. pipeline from the ocean terminal at
Finnart and from the North Sea Forties
5 Both refinery and terminal are subject Field. End products, exported by road,
to the Control of Industrial Major Hazard rail, sea and pipeline, are kerosene, gas
oil, propane, butane, naphtha, motor spirit through the refinery is shown in Fig 1.
and fuel oil. The dotted lines represent pipework which
9 The oil storage terminal at Dalmeny should have been isolated to enable the
near Edinburgh has the capacity to store cross-over valve V17 (with which this
up to 490 000 tonnes of stabilised crude incident is concerned) to be removed
oil prior to export by ship. Forties crude safely. Vented hydrocarbon gases from
is piped 20 km to the terminal after being production units can be flared in three
degassed at the refinery's Kinneil plant. 91 m high flare stacks or recovered for fuel
gas. Much of the flare system pipework is
suspended on gantries about 4.6 m above
The Refinery Flare Line Incident: ground. Sections can be isolated for
maintenance by operating cross-over
13 March 1987 valves allowing vented gases from
operating units to be re-routed. As gases
The flare line system
pass through the extensive pipework
10 The flare line system comprising a system entrained liquids condense out on
complex of pipework which passes the unlagged cold surfaces.

isolated
- Live

--W-- Openvalve

++ Shutvalve

Kodrurn Knock~ouldrurn
Photograph l Cross-over
valve area on 14 March.
Flare No 1 and knock-out
drum No 1 in background.
Courtesy of British
Petroleum

Photograph 2 Cross-over
valve V17. Courtesy of
British Petroleum
11 Pipelines slope down to knock-out 15 About March 1986, senior refinery
drums which collect the condensate for operations and engineering staff held
transfer to the refinery slops system for discussions to preplan a scheme for the
reclamation. At certain locations pipelines isolation of the flare system at V17. They
slope down in both directions, one such concentrated on the operational and
being at point A on Fig 1 which is 25 m safety requirements of the refinery and
to the north of V17. The 760 mm diameter the flare system. It was very important for
lines slope down towards No 1 knock-out safety reasons that the flare lines from
drum and down towards No 2 knock-out operational units should not be
drum, via V17 and V6. The directions of inadvertently isolated. A system for flare
slope are not marked and at gradients of alignment was drawn up. The procedures
1 in 400 are not obvious. At V17 the and safety precautions necessary for the
direction of liquid flow could only be removal of V17 were not considered. The
established by knowledge of the flare detail was left to those who would
system or by survey. eventually be responsible for the work.
12 Fig 2a shows a knock-out drum. As 16 In late January 1987 crude oil
incoming gases and entrained liquids distillation unit 3 (COD3) was shut down
pass over the vertical loop into the upper for routine overhaul. In early February the
part of the drum, the consequent loss of operations department staff who were to
velocity causes liquids to separate out. oversee the removal of V17 held a
Liquids already in the line by-pass the meeting to discuss and agree the flare
loop by means of a liquid take off. Gas is alignment outlined in Fig 1. Again the
taken from the top of the drum to flare actual work methods were not considered,
possibly via further knock-out drums, and these being left to the two process
the liquid which collects is pumped to the supervisors responsible for general work
slops system. activities on the flare system. About
22 February the catalytic cracker and
13 Most of the flare system valves, alkylation units were shut down. The flare
including V17 consist simply of a movable lines from each of these units were
wedge gate which can pass across the 'spaded' to provide effective isolation.
valve bore. An external gear wheel causes Preparatory to its overhaul the No 1 flare
a threaded spindle to push the wedge was also isolated and 'spaded'. 'Spading'
gate into a guide to create a seal across is a common refinery practice by which a
the internal diameter. (Fig 3). section of pipe is positively isolated by
the insertion of a blank flange. (Fig 4). On
Events leading to the incident 9 March COD3 was ready to be started.
14 Some 15 months earlier losses had Its line to flare No 1 was isolated by
been noted on the flare gas recovery closing gate valve V10 and the operators
system and gas from the alkylation unit had great difficulty turning the
normally routed to No 1 flare was passing handwheel. Once they could turn it no
to No 2. Tests showed that (although it further even using valve wheel keys with
appeared closed) V17 was not providing extension levers, they assumed it was
effective isolation and would require closed and isolated although 75 mm to
eventual removal for overhaul. It was 100 mm of valve spindle protruded.
decided that the loss of recoverable gas 17 Two process supervisors were
could be tolerated until a scheduled responsible for organising the work. Each
shutdown of the catalytic cracker, had a team of process operators working
alkylation unit and No 1 flare. Gases from to them in a double shift pattern. It was
remaining operating units could be re- their job to isolate the appropriate part of
routed to No 2 and No 3 flares matching the flare line system so that removal and
the maximum venting rates to the flaring repair of V17 could be carried out safely.
capacity. This flare alignment would allow The job of valve removal was put out to
for the pipelines at V17 to be isolated. contractors.
Fig 2a Flare knock-out
drum

Llquid take-on line

Temporary raffold
acceu fa terf valve

Knock-out drum

monitors condition

not in scale-waled
flareline

Fig 2b Effects of blocked


liquid take-off line
Valve mounted horizontally with faces vertical

Scale settlesto bottom


and compactsasvalve
isclosed

Crescent shaped
opening

Screwed spindle
protruding

Valve spindle
\ ~calesettlestobottom
and compacts as valve

\ Valve body
\
isclosed
I

l
Notfully closed
d p e r e d guide

Fig 3 Flare line wedge gate valve

6
Wedge gatevalve

normal use

Valve in position
with spade in
place of spacer

two pipe endsfitted


with blank spades

Fig 4 Flare line valve removal and spading


The permit to work 20 The date for removal of V17 was
18 The refinery, following the general finally set for 13 March and the work was
practice of the petroleum industry,controls discussed at the regular morning meeting
potentially hazardous work by formal between refinery staff and the contractor.
written procedures included in a permit-to- The contractor's shift superintendent, the
work. The permit, signed by a competent 'performing authority', approached the
and 'authorised' person, usually a process supervisor on the early shift for a
member of the refinery staff, should list permit. Since the refinery compressed air
the safety precautions which must be distribution system did not extend to the
taken. Further guidance on permit-to-work work area, the supervisor made
procedures is contained in the Oil arrangements for a mobile diesel-et ~yine
Industry Advisory Coinrntttee publrcat~dn air-compressor to supply the airline
A g u ~ d eto the principles ano opeiat~oi-ro i breathing apparatus to be worn by c:
permit-to-work pi ocedl~res3s applied in men on the work platform. Respira. :I\/
the UK Petroleum lndustry (Ref 2). The protective equipment was necessarv to
'authorised' official with oversight of the protect them froin the potentially t~>.(rc
work in the course of issuing a permit and asphyxiating effects of flammable
intimates by his signature as the residual gases which would escape from
'operating authority' that necessary safety the flare-line when opened. Also, as a
checks have been properly done and that precaution against flammable gases being
it is safe for work to commence subject ignited, he arranged for two men from the
to any special instructions indicated. On refinery fire brigade to be present with a
receipt, the form is signed by the fire hose to form a water curtain between
'performing authority', ie the person in the work area and adjacent operating
charge of and responsible for those refinery units. These two precautions were
carrying out the work, who may be either subsequently written as special
a contractor or a BP employee. For instructions on the issued permit (Fig 5).
removal of V17 a 'cold work' permit was
21 Shift changeover occurred at
drawn up as the work did not involve the
1315 hours and the incoming process
application of burners or heat.
shift supervisor was told by his colleague
19 On the morning of 11 March, the of the arrangements made. He was aware
contractor's shift superintendent as of the flare system isolation as he had
'performing authority' sought a permit to supervised the work on earlier shifts. He
enable preparatory work on V17 to be was advised that the removal of V17
started. Alternate bolts on the flange could commence after checks on flare-
joints were removed and the remaining line isolation and line conditions and after
bolts lubricated. This was standard the issue of a permit. He went to the
practice to save time during the actual cross-over valve area and confirmed that
operation of valve removal. Sufficient a fire curtain was available, that there
bolts remained at all times to retain the was breathing apparatus and an air
flange seals. There was therefore at that compressor, and that a crane was on site
time no need to verify line conditions. A to lift V17 away. A slight wind was
permit was issued and the work blowing towards the refinery and he
cornpleted without incident. A tower requested a second fire curtain. He
scaffold had been erected at V17 some considered the compressor was too close
months previously, the means of access and instructed it to be moved further
to and egress from the working platform away. The site layout around the work
being a single ladder. The workmen, position was then as shown in Fig 6. He
having climbed the ladder to the platform then checked line conditions by visual
had to crawl under or over the valve body examination of the isolation valves. He
for work on the other side. This was to was aware that they had been closed for
have serious consequences in limiting many weeks and considered it necessary
their avenues of escape. just to confirm that their status had not
FORM W.P. 2. BP OIL GRANGEMOUTH REFINERY LIMITED

COLD WORK PERMIT serial .0.0.0.0.....


DATE AND TIMEOF FROM ( S O0 TO f'?"'OU WORK SITE - --
INITIAL 8 HOUR PERIOD
\>'\L\&? \:..,\3\?f " 3,c 0 c, \ ;:L I
14

EQUIPMENT NAMEINUMBER.. . . . . . .'-.


r--
!??-*?'!?.F.. ..b!~!>!-?. . ,yc"- .. c 'L-
. .!\'d"Ffi*
l. . . . . . . . :. . . . . . . . . . .
DESCRIPTION OF WORK.. . . . . . . . . . . . . . . . . . . . . . ..:?..!?!????;,.! :?l,.. ?'?'C:?, . . . .+-.. ?"!
. . , . . . . . . .:,..... . . . . . .1.. . . i. . . . . . . . . . . . . .
.h
.;> -2 '\~-k c,.+ L , :L
,.LJ ..
............................................................................. ............................................
b....

MARK - REQUIRED X CHECKED4 YES NO ch.~ MARK - REQUIRED X CHECKED J YES NO cwtd
A. Has the equipment to be: -
1.Depressured- - - C. Has the prime mover been:
- 7 vm
,
2. Drained -
1. lsolated from mechanical motive power
3. Isolated by - Blanking? Blank List No. - %
and steam valves locked off? - - . L
- Disconnecting? - - 7
- Valving? - - 10- 2. lsolated from other power sources? -
4.Steamed7
5.Waterflushed
- -
-
- -
- 3-
3. Electrically isolated, locked and tagged? - /
6. Purged with inert gas? - - . % D. 1. Has power cable been disconnected? ,
?
7. Ventilated by naturallmechanical means? 2. Has control cable been disconnected? -
8. Neutralised - - - - - X

B. 1. Has worksite been passed for Excavation1


stake driving to proceed? - U Authority granted to Isolate. . . . . . . . . . . . . . . . . . . . Time: ........hrs.
OPERATING AUTHORlTY
2. Has wind direction been considered? - V Date: . . . . . . . . . .
3. Is a gas test required? * Equipment Isolated . . . . . . . . . . . . . . . . . . . . . . . . . Time: .........hrs.
4. Neutralising Solution on site?
5. H F FlAid kit available
- -
- - - \
ELECTRICAL SECTION
Date: ......... .... .
ALKYUTION UNIT
PROTECTIVE CLOTHING TO BE WORN:
[Operating Authority)-(Indicate by 'X') H2S PRECAUTIONS [7 T.E.L. CLOTHING ACID AREA CLOTHING
:~b:LLPrECTlVE FACE SHIELD GOGGLES
P.V C. GLOVES [7 AIR FED HOOD

OUST MASK e., Q EAR PROTECTION [7 AIR FED SUIT

SPECIAL INSTRUCTIONS:-
+ - Li*>
4 - I' &tc 4 9',2
..
-%
?
&& -
i p, ,S,:

-- - c-. - .;~d.a,~...
- -. \
Lp.>i....r
J,i,J.l(\cc.n~Lr
'X- ,
'CO 'COMBUSTIBLEITOXICIOXYGEN
GAS TEST RESULTS - ~S~lBLEITOXIClOX~N ----P-

DatelTime Result Signature DatelTime Result Signature

Initial Check -
Re-check -
Re-check -
'DELETE when not ap~licable.
Site preparation is complete: - Permissionis granted for work to commence.
To be signed by Initial check I DateITime I Re-check I DatelTime I Re-check I Date=
OPERATING AUTHORITY I
I am aware that this work is in progress and that conditions are as above.
To be signed by Re-check DarelTime i Re-check I DatelTime

OPERATOR IN CHARGE 1 I
PERFORMING AUTHORITY INSTRUCTIONS:-

I understand the precautions to be taken and have Instructed the Person1Persons carrying our the work accordlnglv
I w ~ lnotlfv
l the Operat~ngAuthorl'y when work 1s complete
To be stgned by lntlal Check DateIT~me I Re check ( DatelT~me I Re-check I DateITlme
PERFORMING AUTHORITY I
Performing Authority
Work'completed at hrs on (Date) Signed
Electrical supply Electrical Sectlon
returned to equipment at hrs on
PERFORMING AUTHORITY
Fig 5 Cold work permit
Craneengine Crane

Operators
cab

Air compressor
Jib

Cross-over
valveV17

ToKOdrum1
andflare 1

To
alkylatim To V6
unit

m m p

6 - Flare line
b

Fig 6 Diagrammatic representation of site layout


changed. There was no physical access scaffold. They sought the advice of the
to V6 which was thus only checked 'authorised person', the process shift
visually from ground level. supervisor, who donned breathing
apparatus and climbed up to t h e platform
22 To check that there was no gas to check the situation. He saw gas
pressure in the line, the supervisor looked issuing from the top and liquid leaking
at the pressure gauge, scale 0-15 psig from the bottom of the flange. He
(0-1 bar) on No 1 knock-out drum. He concluded that neither was under
assumed from the zero reading there was pressure and that the quantity of liquid
no gas pressure. He then opened a small was small, being only that in the
valve on the 100 mm diameter drain line depression in the pipeline adjacent to
to the knock-out drum (Fig 2b) as both a V17. He carried out no further tests and
second check on gas pressure and assured the contractors that it was safe
verification that the line was free of for work to continue.
liquid. No liquid and onlv a small amount
of'gas passed out. He cbncluded that the 25 The fitters remained concerned and,
flare-lines at No 1 knock-out drum and because they did not wish to create any
V17 were empty of liquid and had an potential sources of ignition by
acceptably low pressure of residual gas. hammering at spanners or bolts, asked
The supervisor anticipated that valves on for and were given 'spark proof' (ie non-
the system would not be completely leak ferrous) hammers. Again wearing
tight when closed and that gas would breathing apparatus, they returned to the
pass into the isolated section. He scaffold. Liquid continued to drip as they
believed he could accept some residual removed more of the bolts. A refinery
gas pressure because passage of gas out operator gave an instruction to take care
of the flareline when V17 was removed when lifting the spacer and to lift it
would help prevent ingress of air which gently. The crane took the strain. At
could cause pyrophoric scale inside to about 1610 hours as the last bolt was
ignite (para 31). Consequently the permit undone, the crane increased its lift and
indicates that the equipment was not and the spacer suddenly sprang upwards. In
did not have to be depressurised. the words of a survivor "gallons and
23 At 1500 hours the permit was issued. gallons of liquid were coming from the
All concerned acknowledged [hat upon pipe under pressure" on to the platform
receipt the 'performing authority' was and to the ground below.
entitled to proceed on the basis that it
was safe to start and continue. 26 A cloud of flammable vapour formed
from the rapidly spreading pool of liquid
The incident on the ground. It ignited at the
compressor and flashed back around the
24 Two fitters wearing airline breathing working area. One fitter and the crane
apparatus started to undo the remaining driver managed to escape although they
bolts on the spacer on the west flange. suffered burns. The rigger and the second
They were joined by a rigger wearing self- fitter had been on the side of the valve
contained breathing apparatus, who remote from the ladder. Although they
secured a rope sling to a shackle on the succeeded in reaching the ladder side of
spacer. When almost all of the bolts were the scaffold they were engulfed in the
undone the joint opened slightly and fire. One body was subsequently
liquid dripped from the small gap between recovered near the foot of the ladder and
the flanges. Escaping gas and vapour the other from the scaffold platform.
could be seen passing out of the joint at Large quantities of liquid continued to
the top. Being concerned about their escape and fuel the fire. The refinery fire
safety in the presence of leaking brigade were quickly at the scene and
flammable liquids and gases, they were joined 10 minutes later by units of
stopped work and came down from the the Central Scotland Fire Brigade.
lnvestigation by HSE valves, taking rigorous safety precautions.
The valves were subjected to careful
27 The HSE was notified and inspectors examination by HSE. On many of them
responded immediately. When they arrived pyrophoric scale, which is spontaneously
on site the incident was still in progress combustible in air, was found to have
and the fire brigade were fighting the fire. compacted in the wedge guides. The
For the first two hours the fire effect of this is illustrated in Fig 3.
progressively diminished as the quantity Wedge gate valves can be closed through
of liquids in the flare-line decreased. minor accumulations of scale or sludge,
However at 1800 hours, it again increased but eventually build up will prevent them
in intensity. from closing fully. They then no longer
28 lnvestigation revealed that there had seal effectively and hence pipeline
been some process difficulty with the isolation may be prevented even though
stabiliser column condenser at COD3 the valves are apparently closed. This
resulting in gases venting to flare. As V10 problem is more likely to arise when
was supposed to be closed, the vented valves are mounted horizontally with their
gases should not have reached V17. It wedge gates in the vertical position. V6,
was thus apparent that V10 was passing V10, V12 and V17 were installed in this
gas and so probably were other isolation manner. Flare line valves had nothing
valves. Inspectors liaised with the fitted to indicate whether or not they were
emergency services and advised on the fully closed and operators therefore
precautions necessary to enable safe assumed that they were closed when they
recovery of the bodies. A major concern could turn the handwheels no further
was that flare gas produced by refinery even using wheel keys to give increased
operations was feeding the fire. torque. In some cases, the screwed valve
Inspectors met senior refinery spindles protruded at least 150 mm,
management and engineers, and agreed which was excessive. It is now
with them that a controlled shut-down of recognised that sludge build up in V17
much of the refinery was necessary, in was the probable reason it allowed gas to
order to ensure that no more gas could pass.
reach the incident point. 31 Pyrophoric scale results from the
29 As the refinery shut down the fire interaction of sulphur-based gases and
diminished. There was concern that if the the mild steel commonly used for the
flame had been extinguished any majority of refinery vessels and pipework.
subsequent gas escape could spread to The brittle scale builds up on internal
cause an explosion. Additionally if the surfaces of flare pipelines and breaks off
flame receded into the pipeline an as they thermally expand and contract in
internal explosion could result. Therefore normal use. When mixed with liquid it
refinery fuel gas was fed into the flare- forms sludge which can pass down lines
line to keep the flame alight. By the next and build up in valves. The danger of
day conditions were safe enough to allow pyrophoric scale was referred to in the
recovery of the body on the ground. The refinery operations department standing
refinery obtained bulk supplies of liquid instructions and the pipeline section of
nitrogen and the inert gas was used to their safety regulations.
purge the system in order to extinguish 32 The liquid drain line to No 1 knock-
the flame safely. This was successfully out drum was blocked, the effects of
concluded at about 1300 hours on which are illustrated in Fig 2b. A blocked
15 March, and the second body was line results in the accumulation of liquid
safely recovered from the scaffold sufficient to prevent gas in the drum from
platform. registering line pressure. Therefore the
30 A substantial amount of work was test carried out by opening the small
undertaken by refinery staff, who valve on the drain line to verify line
organised the removal of many large pressure was ineffective and misleading.
Equally the absence of liquid from the (b) Knowing the risk that sludge and
test valve would not establish that the scale can prevent gate valves from
flare line was empty. The danger of small- closing, checks should have been
diameter drain pipelines and valves required to ensure that all relevant
quickly becoming blocked with scale and isolation valves were fully closed. An
sludge, preventing the passage of gas internal 1983 engineering code of
and liquids, was well recognised and is practice which was concerned with
referred to in the company's Code of the safety of flare-line operations
Practice on piping systems. stated: "flare-line isolation valves
should also incorporate valve
33 Valve V6, to the south and slightly position indicators". The refinery did
below the level of V17, had been closed not consider this code to be
for many months and condensate retrospective nor did they consider it
collected in the line. Close by V6 on the related to work activities. Valve
side leading up to V17, there was a position indicators would have
100 mm valved stub pipe which was assisted the isolation and since the
installed as a test valve during flare-line accident they have been fitted.
construction and which could have been
used as a drain and test point. The (c) The drainage and line contents
supervisor saw no need to test the line at should have been checked at two
this valve. points at least. The possibility of
smal l-bore pipes being blocked
34 The quantity of liquid which was should have been considered and
present in the system and the amount checks made. The clearance of test
which escaped could not be determined and drain lines could have been
accurately. The line before the expansion verified by the passage of steam or
loop into No 1 knock-out drum was nitrogen.
probably full and at V17 half full. HSE (d) Means of access to V6 should have
has estimated that the liquid inventory been provided and the valve opened
was 50 000 litres, of which 20 000 litres so that liquid build up could drain
may have escaped. The severity and away. After closing the valve, checks
duration of the fire support these on line contents should have been
estimates. made using the conveniently located
valved stub connection, itself verified
35 The ignition source was almost as free of blockage as outlined in (c)
certainly the engine of the diesel air above.
compressor. Examination showed that the
exhaust gas spark arrester was missing. (e) When work on V17 stopped as liquid
came from the open flange, line
Preventive measures to avoid the incident contents should have been
established by further checks on
36 The following preventive measures isolation and drainage. Work should
should have been taken: not have restarted until there was
absolutely no doubt over line
(a) In order to ensure the effective conditions and the safety precautions
isolation of the working area from necessary.
other parts of the system, senior
management should have carried out (f) There should have been detailed
a more detailed analysis of the work safety instructions for the opening of
and associated hazards. The detailed any pipeline which could contain
procedures involved in isolation and residual quantities of flammable
effective drainage of hydrocarbon liquids or gases, including a
liquids from the flare-lines at V17 requirement for sufficient bolts to
should have been agreed at that level remain while a gradual opening is
before being delegated. made by the use of a flange spreader,
for example. Drip trays could collect
leakage in a controlled manner.
(g) Adequate means of escape in case
of an emergency should have been
provided from the elevated working
platform. In this instance a single
ladder was insufficient.
(h) Rigorous control should be exercised
over possible ignition sources in the
vicinity of such operations. There
should be a system for checking all
equipment used on maintenance.
(j) When it is necessary to open pipe
systems which may contain
pyrophoric scale, reliance should not
be placed on the presence of
residual flammable gas to exclude
air. Nitrogen purging should be
considered but this can cause
pyrophoric scale to dry out so
increasing danger from spontaneous
combustion, if it is subsequently
exposed to air. Because of the
complexity and hazards associated
with such operations there is no
single set of measures which will
ensure safety and this highlights the
need for each job to be pre-planned
at a senior level. After the incident
the refinery successfully removed
many large flare-line valves. Nitrogen
purging was used. In addition to the
above precautions the men working
on elevated platforms wore fire suits
and they were withdrawn to a safe
distance before opening lines. The
disconnected and supported spacers
and valves were lifted out by crane
during which the whole area was
drenched with water sprayed from
fire hoses, which both wetted any
pyrophoric scale and dissipated
escaping residual gas. The drenches
then remained until protected
employees had fitted spades to the
open pipe ends.
The Hydrocracker Explosion and
Fire: 22 March 1987

Photograph 3
Hydrocracker area looking
east

The hydrocracker unit temperatures of the reactor beds were


monitored and at 425O temperature cut
37 'Hydrocracking' describes an outs (TCOs) would operate to stop the
exothermic refinery process involving the input of wax feed and hydrogen.
break down of low grade waxy products Sequenced depressurisation of the
and thick viscous oils by subjecting them system would start through blow down
to hydrogen gas at high temperatures and valves into the flare system. Hydrogen
pressures in the presence of a catalyst to recycle would continue through the
form high grade light oils, petroleum reactors to assist cooling during
spirits and liquid petroleum gas (LPG). depressurisation. Hydrogen make up feed
Fig 7 shows a simplified representation of gas for the reactors came mainly from a
the hydrocracker process flow system. hydrogen production unit augmented by a
38 The hydrocracker unit at the refinery supply which was a by-product from the
consisted of a series of 4 fixed bed catalytic reformer. The gas composition
vertical reactors, operating in an was subject to minor variations according
atmosphere of hydrogen at 155 bar to its methane content.
(2250 psig) and 350C. Waxy distillates
were continuously fed through the 39 From the reactors the hydrogenated
reactors from a feed surge drum at a liquidlgas mixture passed forward through
maximum rate of approximately 32 000 a series of heat exchangers and a fin fan
barrelslday (blday) (3500 litrelmin). The cooler into a vertical high pressure
Wax and heavy feed products
from vacuum unit, distillation units and tankage

surge

I Recycle
waxy
residue
1 Light products (LPG, spirit, kerosene, oils)

Fig 7 Hydrocracker process flow system


separator (V305) at a temperature of Events leading to the incident
about 50C. In V305 the hydrogen and 42 On 13 March the hydrocracker unit
light gases were separated from the liquid was taken out of service to carry out
and passed to the inlet of centrifugal essential repairs. Late on Saturday 21
compressor C301 to be recycled to the March it was being recommissioned. At
reactors. This compressor vibrated at high
the start of the nightshift at 2200 hours,
differential pressures and although it gave
production was steady at 20 000 blday. At
reliable service, it was crucial to the
about 0130 hours on Sunday alarms
operation of the plant. Thus vibration was
sounded in the control room. The plant
closely monitored to prevent breakdown.
tripped and a number of pumps and
From V305 the liquor at 155 bar and 50C compressors shut down automatically;
was then passed via control valves to a feed to the reactors was interrupted and
horizontal low pressure separator (V306)
the system started to depressurise. It was
where more hydrogen and light
noted that one of the TCOs on V303 had
hydrocarbon gases separated from the
caused the plant trip.
liquor as the pressure dropped to about
9 bar (135psig). 43 The hydrocracker appeared
40 The de-gassed liquor from V306 then satisfactory and the TCO was thought to
passed through heat exchangers into the be spurious. No over temperature
fractionation unit where products such as condition was found and the TCO trip
kerosene, gasoline, naphtha and was overridden enabling hydrogen
petroleum gases were separated from the circulation to be re-established. The
uncracked residue. The conversion instrument section verified the reactor
efficiency of the hydrocracking process temperature control circuits confirming
was typically 60%. Unconverted liquor that they were working. At about 0200
was recycled for further hydrocracking. At hours the night shift operators started to
bring the plant up to working pressure
32 000 blday throughput and 60%
conversion, the maximum flow of liquid and to stabilise reactor bed temperatures
from V305 to V306 was about 5900 preparatory to start up. From then until
litrelmin, consisting of 3500 litrelmin feed the time of the incident, the plant was
and 2400 litrelmin recycled residue. Gases being held on standby with no feed
from V306 passed to the amine treatment coming through. There was nothing of
plant to remove sulphur. special note in the operation except for a
slightly higher than usual vibration from
Table 1 Typical HP and LP separator operating parameters ~301.
44 In accordance with instructions
HP separator LP separator
Parameters
(V305) (V306) operators delayed introducing feedstock
until the arrival on site of the
Length 15.6 metres 9.1 metres hydrocracker supervisor. At 0600 hours
Diameter 3.05 metres 3.05 metres the shift changed. The day shift was told
Liquid Volume 33 000 litres 33 000 litres the plant had shut down because of an
Vapour Volume 79 000 litres 33 000 litres unexplained TCO, that there was excess
Temperature 4I0C 43OC
Pressure 155 bar 9 bar vibration on C301 compressor and that
Liquid specific gravity 0.85 0.85 the plant was to be kept on standby
Vapour molecular weight 5 15 pending the arrival of the supervisor.
Weight of liquid 27.7 te 28 te Between 0645 and 0655 the majority of
Weight of vapour 2.1 te 0.2 te
Weight of hydrogen 0.8te 0.04 te
operators returned to have breakfast in
the mess-room within the control room
building.
41 The process was operated locally The explosion and fire
from a plant control room, situated some
37 m from V306. A plot plan of the area 45 At 0700 hours there was a violent
is shown in Fig 8. explosion followed by an intense fire. The
Fig 8 Plan of hydrocracker complex
explosion was heard and felt 30 km away mutual aid arrangement from other
and it caused ccnsiderable local concern. localities throughout Scotland under the
A contractor who had just left the mess- refinery's emergency plans. HSE
room was killed. The explosion centred on inspectors were in early attendance.
V306 which was constructed from 18 mm
48 Difficulties in fighting the fire arose
steel plate and weighed 20 tonnes.
because waxy material from ruptured
Photograph 4 shows the hydrocracker
pipework blocked drains causing fire
area with two T-shaped plinths on which
water to accumulate. Leaking petroleum
V306 stood to the left of centre. The
spirit spread over a large area of the
vertical HP separator (V305) is on the far
resultant water surface and five hours
left. V306 had disintegrated and large
after the explosion it ignited. A number of
fragments were projected considerable
other process units in the hydrocracker
distances. A piece weighing nearly
complex were enveloped in flames.
3 tonnes was found on the foreshore
Fortunately, the fire brigade were able to
1 km away. Another was projected over a
regain control and that evening the fire
main road into a factory where it severed
was finally extinguished.
a steam line. A third went through the
roof of a workshop on an adjacent site. 49 The potential consequences of the
During the investigation almost all of incident could have been much greater. It
V306 was recovered and the positions occurred on a Sunday morning when few
where the main fragments landed are people were on site. V306 ruptured at
shown in Fig 9. support saddles underneath the vessel
46 At the time of the explosion there and the blast force was directed
were nine operators within the downwards with fragments being
hydrocracker complex. Two were in the projected upwards. Had it been otherwise,
control room; six were in the adjacent the control and mess room building could
mess room having breakfast; the ninth have been destroyed, increasing the
was out on the plant. Although the likelihood of death and injury. Fortunately
control room and mess room building of none of the fragments hit vulnerable plant
conventional brick construction suffered nor did they strike anyone. The risk did
considerable damage, it remained not warrant evacuating local residents but
standing. Those inside were uninjured and non essential personnel left the site. As a
escaped by the rear exit. The operator precaution traffic on the adjacent road
outside was far enough away and was diverted.
escaped the worst effects of the blast. Investigation by HSE
The only other person in the vicinity was
the contractor. 50 Initial fire and explosion evidence
suggested there had been an explosive
47 The Grangemouth Major Incident
pressure vessel failure involving V306
Plan was put into operation and its
followed by release of the gas and liquid
Control Committee comprising
contents as a cloud or mist. This
representatives of the Police, Fire produced not only a fireball but also blast
Brigade, District and Regional Councils,
effects due to the semi-confined nature of
and experts from the refinery and from
the plant. There were a number of
major chemical and petroleum companies
possibilities which could have lead to
in the Grangemouth area, co-ordinated the
such a failure including:
provision of emergency services and the
response to off-site events. The incident (a) an external event, such as sabotage
on-site was dealt with by the Police and or an incident on adjacent plant.
Fire Brigade, assisted by refinery staff.
(b) internal explosion.
Twelve units of the Central Scotland Fire
Brigade and the refinery fire brigade (c) mechanical failure under normal
fought the fire. Supplies of foam were operating conditions arising out of a
provided by BP and brought in under a critical defect within the vessel or
Photograph 4 LP separator support plinths

through other effects such as 52 With respect to (c) and (d), HSE were
vibration. alerted by the refinery management that
there had been alteration of some
(d) accidental overpressurisation.
instrument settings before security was
51 The investigation involved: fully established around the accident
location. The accounts given by some
(a) Recovery and metallurgical operators did not and still do not tally
examination of vessel fragments on with the physical evidence. It was not
which ballistic calculations were possible to establish unequivocally from
based. the operators' evidence the sequence of
(b) Recovery and examination of fire events which resulted in the explosion.
damaged components. The investigation therefore attempted to
reconstruct the physical conditions
(c) Examination of control room necessary to account for the incident.
instruments and records.
(d) Interviewing operating and 53 The normal operating pressure for
management staff. V306 was 9 bar (135 psig), its design
Fig 9 Refinery plan showing location of hydrocracker explosion and debris, and location of flare line incident
Photograph 5 Fragment
from LP separator; distance
340 metres

Photograph 6 LP separator
end section projected
75 metres over control room
building
pressure 10.7 bar (160 psig) and its test had grown rapidly from the origin in two
pressure 21.6 bar (324 psig). It had a opposite directions, in a predominantly
single pressure relief valve with an orifice brittle manner, consistent with fracture
area of 18 cm2 and a relief capacity to under high strain rate conditions at a
flare of 12.25 tonnelhour, sufficient to temperature near the impact transition
cater for overpressure from fire temperature of the material in this
engulfment. There was no evidence to thickness. On a plant of this type it is
suggest that this relief valve was not foreseeable that fluid transfer could set
operating effectively at its set pressure of up vibration effects giving rise to high
10.7 bar (160 psig). transient strain rates. At operating
temperatures well below normal a vessel
54 The fragments of V306 were located, subjected to these vibration effects could
weighed and their positions logged. The have failed.
explosive forces were calculated using
ballistic techniques based on fragment 57 However the other evidence strongly
trajectories which confirmed that rupture suggested that there had been a
was caused by over-pressurisation. The breakthrough of high pressure gas from
results correlated well with the calculated V305 to V306 leading to
theoretical burst pressure of 50 bar overpressurisation of the vessel. The
(750 psig). Blast damage established that liquid in V305 had drained away through
the force of the explosion was equivalent an output flow control valve when the
to approximately 90 kg of TNT. hydrocracker was being held on standby
operation with no product passing,
55 The overwhelming weight of evidence thereby allowing high pressure gas to
from blast damage, ballistics and break through. Fig 10 shows a single
metallurgical examination pointed towards 300 mm diameter outlet pipe from the
internal overpressure of V306 applied in a bottom of V305 which split into two
single event. Nevertheless other parallel streams each with a separate
possibilities of vessel failure, as set out flow control valve. The valve nearest V305
in para 50, were also considered by was the right-angled, air-diaphragm-
detailed examination of the plant, plant operated valve LIC 3-22 which could be
records and eye witness accounts. There operated from the control room either in
was no indication of an external initiating automatic or manual mode. Some
event such as sabotage. An internal distance from V305 was the air-
explosion or ignition occurring within diaphragm-operated, straight-through flow
V306 was considered. This would have control valve HIC 3-22, which could only
required the presence in the vessel be operated via a manually applied
system of both oxygen and a source of control signal from the control room.
ignition, and the possibility was
eliminated not only by detailed 58 Fig 11 shows the LIC 3-22 and HIC
consideration of the process conditions 3-22 valve control system. A pneumatic
and controls, but also by evidence from diaphragm assembly opened each valve.
vessel fragments. On removal of air pressure the valve was
closed by a spring. Its position was
56 The possibility of mechanical failure selected by a control unit from which an
for reasons other than simple electrical signal passed to an IIP
overpressure was considered. The (electrical currentlair pressure) converter.
metallurgical evidence established that A pneumatic signal was then sent to a
the origin of the failure was in the heat positioner unit at the valve. By this means
affected zone of a saddle weld on the air pressure was applied to the
underside of the vessel at the east end diaphragm. Two hand-wheel-operated
near the support plinth. There was no valves (SP25) in series provided a manual
indication of pre-existing defects nor of a by-pass to the control valves. One was
progressive mode of failure on any part of found open but the other was shut and
the fracture surface examined. Cracks found to be gas tight. Gas breakthrough,
Recycle hydrogen
to C301 compressor
Gas

A -& Uc3-22
r------l
l
I
I
I
!l 1L I To Amtne plant
Bypass Pressure control l
Plc 3-73

Nucleon~c
SP25 SP25

!I rl Float
gauge
LP separator V306 -1
I
I
l

Ltqutd
II
1r 1r r---------- J
II la
4- FIC 3-21
h f,ct10nator

F--'
Sour water

Fig 10 HPlLP separator control system


Float gauge
Alr supply
on V305
Vent t o
atmosphere
1I
A
PI1 converter
l!
11

- d
'\

&
0 ,,c322
controller
lip
converter Pos~t~oner Dump
solenold
0
-

fi
d

Low alarm

for
W ~LIC
d~sconnected
r l n 3-22
g
t o s o valve
l e n o ~was
dd u m p

Audlble Vlsual

Relay unit

(Svstem simplified for clarity)

Extra low
alarm

Audible Visual

Fig 11 LIC 3-22 & HIC 3-22 v a l v e control system


therefore, did not occur through the by- which stopped the audible alarm and
pass route. made the flashing light steady until the
alarm condition was cleared on plant. The
59 HSE tested the HIC 3-22 and LIC 3-22 low level alarm was in working order. By
valves. Apart from fire damage to the 0620 hours the liquid level had fallen
diaphragm assembly and positioner on below the 20% set value and the
LIC 3-22, they were found to be in consequent alarm was accepted by the
working order and sealing reasonably operator. The low level alarm did not have
effectively when in their closed positions. a trip function.
When valves were removed, waxy material
was found in all except LIC 3-22 evidence 63 The nucleonic level sensing gauge
that gas had passed through it purging it had a range of 900 mm, and provided a
of wax. means to verify the float gauge reading
over the middle of its range. It had no
60 The possibility that a valve positioner direct control, alarm or trip function. The
fault could have caused a valve to open float gauge and the nucleonic mid points
was considered. The positioner on coincided and there gave equal readings
HIC 3-22 was working but that on LIC 3-22 of 50%. A 100% reading (nucleonic) was
was destroyed. Fault conditions were equivalent to 63% on the float gauge;
simulated on an identical positioner while at 0% (nucleonic) the float gauge
which showed that in the event of a registered 38%.
component failure a valve would close
rather than open. Positioner failure 64 There was an 'extra-low' level
leading to LIC 3-22 opening was thus detection system on V305 comprising two
discounted. float switches which were attached to the
bridle assembly beneath the float gauge.
61 The liquid level in V305 was Each consisted of a chamber with a
measured by a 3.6 m long tubular float pivoted float, movement of which was
gauge, and a nucleonic level sensing actuated when the liquid level inside it
gauge both attached to a pipework bridle. fell. This then broke a magnetic circuit,
Levels were shown in the control room on operated an electrical switch, and
indicators and chart recorders. V305 initiated audible and visual alarms. This
contained 11 500 litres or less when the system was also intended to close both
float gauge registered 0%. A 1OO/ variation flow control valves from V305 to V306
in the float gauge reading was equivalent stopping the outflow of liquid and thus
to 266 litres, and at a 50% reading V305 preventing gas breakthrough. Operation of
thus contained 24 800 litres. Signals from this trip also prevented the valves from
the float gauge also provided input to the being opened until a safe liquid level was
LIC 3-22 controller (shown in photo 8) to established in V305.
provide level indication and to control the
opening of LIC 3-22 to a level set by the 65 The liquid pressure from V305 was
operator with the controller set to reduced solely by the throttle action of
automatic. The LIC 3-22 and HIC 3-22 the flow control valves. However, in the
controllers were tested and found to be in original installation some pressure drop
working order and correctly calibrated. was effected by a power recovery turbine
located in the line between V305 and
62 If the level in V305 fell to 20/0 V306, which the extra-low level trip
(16 800 litres) on the float gauge, signals system was intended to protect against
triggered a 'low liquid level' audible alarm gas breakthrough. The turbine was never
and a warning light showed on the used and was removed in the mid 1970s.
control panel to alert the operator, so that A safety audit carried out in 1975
he could monitor it or take corrective nevertheless confirmed a need to retain
action. Operators could 'accept' the alarm the extra-low level trip, because it was
by pressing an 'acknowledge' button critical to prevent over-pressure in V306.
The audit also identified operational temporarily at the rear of the control
problems in controlling the level in V305 panel". There are three possible reasons
and recommended duplicate tappings on why the trip was disconnected.
it for level detection instruments. This
recommendation was not implemented. (a) It was considered part of the
The nucleonic gauge operating over a redundant turbine system and
restricted range was fitted instead. The thought unnecessary.
audit recognised that the pressure relief (b) Liquid in V305 vortexed and often
valve on V306 could not cope with gas caused the extra-low level trip to
breakthrough. operate spuriously. At high
throughput this caused production
66 In 1980 a study of the pressure difficulties.
reliefs to flare was carried out by a
specialist contractor. It assumed that the (c) Because it was cumbersome to use
extra low level trip system on V305 would the manual bypass valves (SP25) the
function correctly and concluded that operators wanted LIC 3-22 to open at
existing precautions precluded gas levels below the extra-low trip so
breakthrough. No recommendations were that, for example, V305 could be
made for further pressure relief. completely drained prior to shut
down.
67 As part of the extra-low level trip
system LIC 3-22 and HIC 3-22 valves each 70 Many operators knew this trip was
originally incorporated an electrically inoperative as they had taken the level of
operated 'dump' solenoid to interrupt and liquid in V305 below the notional trip
release the air pressure on the valve point and the valve remained open. No
diaphragm, thus causing the valve to assessment of the potential
close. The HIC 3-22 solenoid dumped consequences was carried out before the
when de-energised, but the LIC 3-22 trip was disconnected. Routine
solenoid dumped when energised. Thus if procedures for testing and defect
the electrical supply to the LIC3-22 reporting did not highlight its absence.
solenoid failed, the valve would not close This state of affairs was accepted by
and therefore in this respect it failed to those concerned with the hydrocracker, at
danger although the electrical supply was least up to the level of process
monitored by a 'trip-supply-fail alarm'. supervisor.
68 The electrical supply wiring to the 71 The trip solenoid on HIC 3-22 was
LIC 3-22 trip solenoid was found to have removed and bypassed in 1986 after being
been deliberately disconnected at the damaged in a fire. It too would not have
control room and on HIC 3-22 the trip closed on 'extra-low' liquid level and
solenoid had been removed and could be opened with a dangerously low
bypassed. In consequence neither of level. There was therefore the potential
these flow control valves could trip to for gas breakthrough as with LIC 3-22.
close on extra-low levels in V305. It was The investigation revealed that HIC 3-22
thus possible to open the valves with remained shut and played no part in the
little or no liquid in V305. Safety of this incident, but the absence of its solenoid
part of the plant had for many years thus is considered by HSE to have been of
depended solely on the vigilance of equally serious potential.
operators.
72 Operators stated that the extra-low
69 Disconnection of the LIC 3-22 trip level alarm visual indication had been in
solenoid was commented on in a 1985 continuous operation for many months
memo by the refinery senior instrument until the light bulbs failed some time
engineer. A manuscript amendment before the explosion. The alarm had been
probably made some years before on a regarded as spurious. The extra-low level
wiring plan showed it was "disconnected alarm circuit board was tested and found
to be in working order. The two float- boardman controlling the hydrogen,
switches were fire damaged but there vacuum and amine units. Operators were
was evidence to suggest that the first largely trained on-the-job by experienced
switch was incorrectly assembled, and colleagues.
that the small bore pipework to the
second switch was blocked. The Senior Technician
possibility thus existed that both extra-
low level switches were inoperative.
Control Room Plant
73 Trend chart recorders provided a
permanent record of aspects of the
hydrocracker operation. However they
were not synchronised and the
information they provided needed to be Grade A Operator Grade A Operator

interpreted with care and by reference to


(Senior Boardman) I
other evidence. Several of their pens were
not working. The float gauge chart did
register the falling liquid level in V305 in Junior Boardman
the 45 minutes prior to the explosion, as
shown in Fig 12(A), but does not show
the minutes before the incident when the Amine Hydrogen Vacuum Hydrocracker
liquid level fell, V305 emptied, and gas Unit Unit Unit Unit
breakthrough occurred. Four minutes Operator Operator Operator Operator
before the explosion the chart (Fig 12B2)
shows a rapid fall in V305 pressure. This Table 2 Shift operator
responsibilities
along with eye witness reports, which
suggested that the pressure relief valve Causes
on V306 was lifting immediately before
the explosion, confirmed that gas 76 Operators denied taking action or
breakthrough had occurred. The rate of making adjustments which could explain
pressure drop could not be explained by the incident. However all the evidence
other mechanisms such as emergency suggested that LIC 3-22 had been opened
depressurisation. and closed on manual control at least
three times after the shift changeover at
74 There was no chart indication to 0600 hours. Liquid level in V305 fell and
confirm the pressure conditions in V306. when LIC 3-22 was opened again just
The amine plant pressure registered no prior to the incident all remaining liquid
change which taken with other evidence drained away allowing high pressure gas
confirmed that the gas output valve from to break through. LIC 3-22 did not close
V306 was shut and consequently this automatically because its trip solenoid
outlet for gas escape was closed. There was disconnected.
was no alarm or trip on V306 for high
pressure or over-pressure conditions. 77 Despite the presence of steam trace
heating, wax inside the float gauge and
75 The hydrocracker operated the small bore pipework to the extra-low
continuously. Shift hours were from level switches had been known to solidify
0600-1400 hours (day), 1400-2200 hours when it was cold. The float gauge
(back) and 2200-0600 hours (night). Each sometimes gave false readings and a
shift of eight operators is shown in number of operators mistrusted it. They
Table 2. A ninth operator on shift that placed more trust in the nucleonic gauge
morning was a trainee. The senior readings because the bridle itself was
boardman had primary responsibility for less prone to blockage. On that cold
all control room operations, in particular March morning the boardman paid no
the hydrocracker, with the junior attention to the falling
40

HPSeparator (V3051liquid level

30

%
chart 20
indication

10

40

B,
30
V
LP Separator (V3061liquid level
%
Chart 20
indication

10
float gauge
1
f Zero offset

80

%
Chart O'
indication
HP Separator (V3051Pressure

60

-
,h I I I I
l a s breakthrough -O6OohrS -0500hrs -0400hrs -0300hrs
Explosion
t
Shift changeover
Time
Approx 1 hr

m
0 'h l
Fig 12 Diagrammatic representation of charts (traces enhanced and time corrected for clarity)
float gauge trace, assuming instead that had no previous experience of it.
the nucleonic chart reading which
appeared steady at 1O0/0 reflected the 80 The following factors may account
actual level in V305 Unknown to him the for LIC 3-22 being opened, and liquid level
pen had been offset so that a zero in V305 falling during standby operation:
reading was shown on the chart as 10%.
(a) In cold weather and on standby with
He was thus unaware of the actual level no flow, wax could solidify in the
in V305 and of the imminent danger. unlagged and unheated HIC 3-22 and
78 Liquid level in V306 was similarly LIC 3-22 lines. To prevent blockages
measured by float and nucleonic gauges. the valves were opened on manual to
The charts indicated that liquid flowed pass warm liquid through. Flow was
from V306 to the fractionator some hours verified by noting changes in V305
prior to the incident and the gauges went and V306 levels and in V306 pressure
off-scale. The evidence indicated that which rises as gas escapes from the
V306 then emptied requiring 17 000 litres liquid. Alternatively V305 was drained
to bring its float gauge on-scale. Fig 12B1 of liquid allowing gas to
shows liquid surges in V306 breakthrough and blow the lines
corresponding to falls in the level of V305. clear of wax. Gas entering V306 was
The level also appears to rise in the again verified by a pressure increase.
minutes before the explosion. HSE With the reactors under standby
calculated from this that V306 contained conditions liquid transferred from
about 20 000 litres confirmed by V305 was not replaced. The duty
calculating the amount of liquid boardman had not practised the
transferred from V305 following closure of above techniques nor had they been
the outlet valve from V306 to the explained to him. However, he had
fractionator (para 80(b) refers). been in the control room the previous
day when a senior technician had
79 That morning the hydrocracker was blown gas through the lines in
on standby following the TCO trip with preparation for start-up. Another
feedstock from V308 (Fig 7) stopped. operator remembered that 2 years
However, residual liquid from the reactors earlier there was an occasion when
(V301 - V304) continued to pass into V305 gas was heard surging into V306 and
by the action of the recycling gas, its pressure relief valve operated.
although diminishing over a period of Almost certainly this was gas
hours. V305 level was controlled during breakthrough. However an incident
routine steady operation by having a fixed was avoided by the boardman
flow through HIC 3-22 on manual and closing the flow control valve. This
with flow variations controlled by LIC 3-22 near miss was not reported to either
on automatic. On standby, however, flow supervisors or management and there
was erratic and LIC 3-22 on automatic was no investigation.
would be too slow to cope with sudden
increases. Because it responded more (b) The fractionator feed valve (FIC 3-21)
quickly on manual, this was the preferred passed liquid significantly when
method of operation, but in this mode the closed using its control room
maintenance of safe levels required strict controller, and V306 emptied.
operator control. After about 0600 hours However before start up V306
liquid flow had almost ceased and the required sufficient liquid in it to
boardman said he had HIC 3-22 and ensure that gas breakthrough to the
LIC 3-22 shut on manual. He was mainly fractionator would not occur. To
concerned with the unexplained TCO, the ensure sufficient liquid it was
vibration on C301 and conditions on the therefore necessary for FIC 3-21 to
amine and downstream plants rather than be tightened (hand jacked shut)
the level in V305. However because manually on plant and this was done.
prolonged standby operation was rare he To get sufficient liquid level into
V306 for its float gauge to register, 82 Tests were carried out by HSE to
LIC 3-22 would then be opened on establish the gas and liquid flow
manual control. characteristics of the flow control valves.
Water flow rates at comparatively low
(c) Although unlikely, the array of similar pressure were used to calculate the flow
controllers could have resulted in an of hydrocarbon liquid which would have
operator turning the LIC 3-22 thumb been expected in service at the 155 bar
wheel in error. He may then not have pressure drop between V305 and V306.
noticed the level drop in V305. The results for LIC 3-22, the valve which
(d) The operator believed the V305 was opened are shown in Table 3. The
nucleonic gauge chart recorder variation between the HSE figures and
reading with its zero offset. In the manufacturer's data at mid-range is
addition he was not aware of the attributable to the effects of in-service
extent to which the liquid level in conditions and valve seat wear. Despite
V306 was below that which would there being no means on plant for
show a reading on its float gauge. measuring flow between V305 and V306,
Thus if LIC 3-22 was opened in an operators estimated flow rates against
attempt to establish a level of liquid percentage valve openings. Their
in V306 and no instrument changes estimates correlated closely with the
resulted, it could be concluded that calculated figures.
LIC 3-22 had not opened. The valve
may then have been opened further Table 3 Liquid flow characteristics of LIC 3-22 valve
or for a longer period to get the
levels to respond, whilst in reality LIC 3-22
levels were falling rapidly.
81 Opening LIC 3-22 on manual control Manufacturers
HSE values
% Open data
to pass warm liquid or gas through the
lines was permitted by supervisors. This
litreslmin litreslmin
necessitated bypassing the safety trips.
Because the danger was recognised this
was only supposed to be done under
carefully controlled conditions and with
extreme care. Operators were required to
pay close attention to instruments! The
shift instructions log book entry on 17
October 1986 stated:
"once all wax appears to have been
removed, block in and leave for 2 hours, 83 Gas flow characteristics of LIC 3-22
then check by opening LIC 3-22 carefully were obtained from the manufacturer and
to avoid over-pressurising the confirmed by calculation based upon the
LP separator. Repeat every 2 hours" liquid flow test results (Table 3). A
computer programme was then used to
and again on 13 March, 1987 stated: predict the expected pressures in V306,
"with caution and care, sweep hydrogen assuming hydrogen passing into it at
from the HP through the LP and the 155 bar, as a function of percentage open
multilocks to the fractionator to try to of LIC 3-22. Flow through its pressure
remove as much wax from the lines as relief valve (PRV) and its estimated liquid
possible". content (para 78) were taken into account.
The results are shown in Table 4
This was clearly a dangerous practice the (columns 1 and 2). The time taken for
potential consequences of which were not V306 to reach its calculated burst
fully understood. pressure of 50 bar is shown in Table 4
(columns 1 and 3). The times shown time of 108 seconds to reach its burst
commence once V305 is drained of liquid. pressure (Table 4) this would give a total
It can be seen that if LIC 3-22 was time to the explosion of about 6 minutes.
opened less than 40% the maximum The precise timing of the opening of LIC
pressure in V306 would be less than 3-22 beyond the 40% position may never
50 bar and it would therefore not rupture be known but the calculations
but would vent via its PRV. With LIC 3-22 demonstrate clearly the potential to over-
open more than 40% the PRV was not of pressurise V306.
sufficient capacity to prevent rupture.
These calculations therefore established 85 An indication of events in the
that for V306 to explode LIC 3-22 must minutes before the explosion is provided
have been opened beyond 40%. by the chart (Fig 12B2) showing V305
pressure. It shows a drop in pressure of
Table 4 Relationship between position of LIC 3-22 18 bar (270 psig) over 4 minutes and then
and pressure rise in V306 and time taken to reach a rapid drop as V306 ruptured. Although
burst pressure of 50 bar the complexity of the high pressure
system precluded using pressure drop
information to determine LIC 3-22
'10 Opening of Pressure Time to 50 bar (based position, close examination of the chart
LIC 3-22 bar (psig) on the models used) shows the rate of pressure drop increased
within that 4 minute period confirming
14 (200) Will not reach 50 bar that LIC 3-22 opened further. The volume
21 (300) Will not reach 50 bar of gas represented by the pressure drop
28 (400) Will not reach 50 bar was calculated as being sufficient for
35 (500) Will not reach 50 bar V306 to reach its burst pressure.
41 (600) Will not reach 50 bar
48 (700) Will not reach 50 bar 86 When the control room was entered
53 (800) 108 seconds after the explosion, a supervisor reported
35 seconds that the LIC 3-22 controller was on
25 seconds manual and 100% open. Later, when seen
22 seconds by HSE Inspectors it was found fully shut
and other controls were also in different
positions from those first reported. The
84 The chart recording of V305 level supervisor's report was correct, two
(Fig 12A) ceased some time before the operators who altered the controls
incident (para 73). The time taken after confirmed it several months later.
this for the incident to occur is the sum However no explanation for LIC 3-22
of the time to empty V305 of liquid and being fully open has been given. The
the time to raise V306 to its rupture reasons described in para 80 could
pressure. The LIC 3-22 liquid flow account for it being opened on manual
characteristics (Table 3) were used to during standby. The hydrocracker controls
estimate its percentage open when levels were typical of the late 1960s and the
in V305 were dropping prior to the following features could have led to
explosion and to calculate the time for it operator error:
to empty. The downward steps in the
float gauge trace (Fig 12A) show that (a) Errors could be made when
LIC 3-22 was open less than 5%. The final assessing the volume or depth of
downward trend no more than 20 minutes liquid in V305 and V306 as their
before the explosion starts at 6% on the measuring devices related to different
float gauge trace when 13 200 litres of indicated lengths, not to each other
liquid remained in V305 and in order to nor to the content of the vessels.
empty this amount in that time LIC 3-22 (b) False assumptions could be made
must have been opened much more. If it about the time to discharge the
was for example 40% open V305 would liquid in V305 since there was no
empty in 4 mins and when added to the means of measuring flow other than
Photograph 7 LIC 3-22 and
HIC 3-22 controllers

by noting changes in liquid level. If experience could move a thumbwheel


that level was below the range of the and not monitor the consequence of
level measuring devices the operator his action.
was working 'blind' further increasing Errors could arise if a valve controller
the probability for error. (e)
was adjusted directly from automatic
(c) Errors could occur as controls of a to manual mode without going
similar appearance carried out through a balancing procedure and
different functions. If one controller without checking the manual
was adjusted when the intention was thumbwheel setting (Photo 7). The
to adjust another, a valve could move balancing procedure should ensure
to a ~ o s i t i o nnot anticipated. that the valve position on manual
corresponds to the position on
In situations of high stress an error automatic before the change to
could be made if the manual manual mode is made. Failure to
thumbwheel controller (photo 7) were follow this procedure could lead to
moved in the wrong direction. The the valve moving to a position not
valve could then be opened instead anticipated. The LIC 3-22 controller
of closed. The LIC 3-22 thumbwheel
operated in this manner.
action was to close the valve when
moved from right to left but this was Conclusions
not clearly indicated. On some other
controllers where the valve action 87 The investigation established the
was different, thumbwheels operated following:
in the opposite manner. It is possible (a) V306 was subjected to an internal
that an operator relying upon long pressure of about 50 bar, significantly
in excess of its normal working (n) The pressure relief valve on V306 was
pressure and sufficient to cause it to not of sufficient capacity to relieve
explode. the maximum potential flow of high
pressure gas to prevent overpressure.
V306 overpressurised when hydrogen
at 155 bar entered it from V305. (0) Too much reliance was placed on
operators for the safe control of flow
The high pressure gas was able to from high pressure plant into a low
pass from V305 because liquid in it pressure system.
had drained through an open valve.
(p) The refinery was aware of the
The open LIC 3-22 valve formed the potential for gas breakthrough
route for liquid and then gas to pass following audits in 1975 and 1980.
into V306. HIC 3-22 and one of the
by-pass valves were closed. 88 It was very dangerous not to have
accurate knowledge of liquid levels at all
LIC 3-22 was not on automatic times given that the safety trip
control. Hence the possibility that the mechanisms on the two control valves
incident was caused by failure of the were inoperative. Excessive reliance was
V305 float gauge, which provided being placed on operators with
level signals for automatic control, insufficient appreciation of the risks
and its associated control circuitry, associated with gas breakthrough.
can be discounted. Without 'extra-low level' protection in
LIC 3-22, its level indicator controller V305, V306 was at risk of being over-
and its pneumatic positioner did not pressurised at any time when the
fail and the valve did not open of its maintenance of a liquid level in V305
own accord. could not be assured andlor was not
under precise control. This was most
LIC 3-22 was selected on manual likely when LIC 3-22 was on manual
control, was more than 40% open control, during start up, interruption to
and was very probably 100% open. normal operation and standby.
Safety shut off in the event of extra- 89 The refinery had procedures for
low levels in V305 relied solely on the routine monitoring of interlocks, alarms,
process flow control valves LIC 3-22 and trips, but on the checklist for toe
and HIC 3-22. There was no hydrocracker some were omitted. The
independent shut-off valve in the line detection, trip and alarm systems for
from V305 to V306. extra-low liquid level in V305, had been
The LIC 3-22 dump solenoid wiring inoperative for a long time and
was disconnected about 5 years maintenance staff and operators
earlier and as a result it did not presumed that these were no longer
close on extra low level liquid level in required. Training of new operators,
V305. carried out by experienced operators
helped to perpetuate this misconception.
The HIC 3-22 trip solenoid was Although the refinery chief instrument
bypassed in 1986. engineer noted in 1985 that the LIC 3-22
The alarms on the extra-low level trip solenoid had been disconnected, this
detection system had failed and was not followed up.
operators were not alerted as a Preventive measures to avoid the incident
dangerous situation developed.
90 The following preventive measures if
Because the hydrocracker was on taken, could have avoided the incident.
standby the normal process routes
from V306 were valved off so that (a) V306 should have had a high integrity
gas entering could leave only via its automatic safety system to protect
pressure relief valve. against gas breakthrough and also
pressure relief provision to cater for
maximum anticipated gas flow rates.
The safety shut off system shculd
have included a secondary shut off
valve in the line from V305, in
addition to the control valves. Dual
extra-low level detection should also
have been fitted on V305 to provide
independent shut off trips.
(b) The trip systems and alarms as
installed should nevertheless have
been connected and in full
operational order. They should have
been included in comprehensive
testing schedules. Defects should
have been reported, recorded and
actioned.
(c) Changes to plant should only have
been made after full consideration of
the possible safety consequences.
(d) Control room practices should have
been monitored to detect possibilities
for malpractice or error. Ergonomic
factors in the design and layout of
controls should have been
periodically reassessed.
(e) The problem of wax blockages in the
level detection system on V305 and
the associated small bore pipework
should have been fully analysed.
Steps should have been taken to
reduce the likelihood of blockage by
for example the use of larger bore
pipework and monitored trace
heating. The identification of
blockages could have been assisted
by dual level detectors and more
sophisticated level instrumentation.
(f) Wax blockages in the HIC and LIC
3-22 lines could have been prevented
by the provision of lagging and trace
heating.
(g) Finally, a full analysis of the dangers
and potential consequences inherent
in the operation of the hydrocracker
should have been carried out, and
documented. Adequate safeguards
should have been provided and all
concerned should have been made
aware of the potential dangers and
necessary precautions.
Fire in a crude oil storage tank, Events leading to the incident
Dalmeny: 11 June 1987
92 BP had identified that T807 required
The site a routine inspection and overhaul. At a
meeting on 10 November, 1986, they
91 The Dalmeny Oil Storage Terminal scheduled its removal from service for
where about 30 persons are employed is June, 1987 aiming for completion by the
approximately 20 km east of end of October. Thick sludge collects on
Grangemouth and is connected to the the bottom of the tanks and a survey was
refinery's Kinneil gas separation plant by carried out in April 1987 by external
pipeline. Stabilised crude oil, destined for dipping through the support column ports
export by ship from the BP Hound Point on the roof, which established that
marine terminal on the River Forth, is approximately 1000 tonnes of sludge was
stored in seven floating roof tanks (T802 - present, situated in two banks, shown in
T808). There are three fixed roof tanks Fig 14. T807 was withdrawn from service
used for storage of ballast water from on 19 May and by 22 May had been
ships. The site layout is shown in Fig 13. emptied of crude leaving only residuai
The floating roof tanks are identical, each sludge. The floating roof of T807 was
being 78 m diameter, 18 m high with a resting on 219 support pillars, at a height
capacity of 81 000 m3(70000 te). There of 2.1 m. It was then isolated by spading
are three pairs of tanks and a single tank the inlet and outlet pipes. At regular
located within 4 earthwork bunds. Tanks intervals around the circumference of
are called 'floating roof' as during normal T807 near ground level there were four
service a roof will float on the surface of manways (600 mm diameter) and three
the oil so that it rises and falls with ports (740 mm diameter) for motor
changes in the level. operated agitators. The agitators, the

Fig 13 Dalmeny oil storage terminal


Scale (metres)

Fig 14 T807 sludge survey

manway covers and one of the three roof equipment were transferred to T807 where
manway covers were removed. The tank work commenced on 2 June. For this
was then allowed to ventilate naturally. there were eight contract employees
including a working supervisor on site, all
93 On 20 May the terminal engineer met but three of whom had worked on T809.
representatives of several specialist
cleaning companies to inform them of the 94 The contractor was well known in the
nature and extent of the proposed work. field of tank cleaning operations. They
On 28 May, a contract was awarded to had successfully completed contracts on
the company which was already on site this and other sites. BP were satisfied of
cleaning out ballast tank T809. After their competence when they awarded the
completing this work, the men and contract. Procedures for tank cleaning
and sludge removal were decided by the of fire surrounding the three men inside.
contractor, although they were discussed As they ran to escape the flames one
with site management. man fell but managed to struggle to his
feet and escaped with a second man. The
95 The tank and its bund area remained third who had been driving the vehicle ran
under site control and a permit to work in the opposite direction and did not
was required to be issued before work escape. He died from the effects of
could be started. T807 was not 'gas-free', asphyxiation and burns. The fire
ie not free from all flammable and other escalated rapidly with flames and smoke
vapours. The evolution of flammable coming out of the open manways.
vapour with the risk of forming an
explosive atmosphere was not considered 98 After a crew change the terminal fire
sufficient to merit either mechanical tender was arriving at T807 to take up
ventilation or rigorous monitoring of the station after a brief absence. The terminal
vapour concentrations inside the tank. safety services operator and others took
However, as a precaution against fire hoses from the tender and connected
potentially toxic effects, the contractor's them to a nearby hydrant. Fire hoses had
employees working inside T807 were not been laid in position because on
required to wear airline breathing previous occasions they had been
apparatus supplied from a compressor accidentally damaged. The fire was
located outside the bund. A hydraulically extinguished within about 10 minutes by
powered screw pump was located in the the terminal fire crew. Lothian & Borders
tank and the men used hand tools to Fire Brigade arrived on the site at
pass sludge to its inlet hose. Sludge was 1330 hours and for the remainder of the
then pumped through a 100 mm diameter day were deployed in pumping foam
flexible hose assembly, which passed through manways into the tank to keep
through a tank manway, into the supply the contents cool and to prevent re-
pipeline to T808 via a non-return valve. ignition. The tank was allowed to cool
The diesel engined hydraulic power units and the body of the deceased, still
were positioned immediately outside T807. wearing the remnants of breathing
The location of equipment was agreed apparatus, was recovered on 12 June at
with the terminal engineer. 2100 hours.
96 On 4 June a hydraulically powered
99 HSE Inspectors were quickly on site
tracked vehicle fitted with a rubber edged
and co-operated with the emergency
wooden scraper was introduced to speed
services throughout the recovery phase of
up the work. It was taken into T807 in the incident.
pieces and assembled. The contractors
continued working on the north bank of
sludge. There were two teams of four Investigation by HSE
which alternated every two hours. Three
men worked inside and on duty outside 100 Crude oil is a complex mixture of
was a fourth man and a BP safety hydrocarbons and a typical analysis of
services operator. the crude in T807 is shown in Table 5. A
sample of sludge from the outlet hose,
identical to that in the tank prior to the
The incident
fire, was tested to establish its flashpoint
97 On 11 June the contractors started (the temperature at which it gives off
work inside T807 at 0630 hours, after their vapour sufficient to cause a flammable
supervisor had checked on the re- issue concentration in air). It was found to be
of the permit to work with the terminal less than OC. The upper and lower
engineer. The team changeover which flammable limits in air (the flammable
preceded the incident took place at 1230 range) of hydrocarbon vapour are typically
hours. At 1320 hours the outside man 1.5% and 6%. The vapour is heavier than
looked in and shouted as he saw a ring air.
Photograph 8 T807 at
Dalmeny tank farm looking
north

Photograph 9 Diesel
engined unit near to T807
manway
Table 5 Typical analysis of stabilised crude oil some men brought smoking materials on
to site and into T807. It is not known
when smoking inside tanks first started,
% by but it appears that the practice was
Constituent commonplace amongst certain
weight
contractor's employees who had smoked
Stabilised gasoline in T809 and had been smoking in T807
Benzine since work started. The contractor's
Naphtha foreman, in charge of the job was
Kerosene
Gas Oils
satisfied his men knew that smoking was
Heavy Oils and Tars
allowed only in the designated safe areas.
He never saw them smoking other than in
these areas and had he done so he would
have taken disciplinary action.
101 Many possible sources of ignition
were considered including pyrophoric Undoubtedly, the men all knew that
smoking outside designated areas was
scale, static electricity, machinery
forbidden and that they would face
malfunction, stray currents from the
disciplinary action if they were caught.
cathodic corrosion protection system, the
location and maintenance of diesel 104 The men inside T807 were required
engined equipment nearby, matches and to wear respiratory protective equipment
smoking. Enquiries had commenced into (breathing apparatus or BA) to protect
these possibilities when a man admitted from the potentially toxic fumes. Vapour
to smoking, stating that the fire started concentrations inside such tanks may
when he dropped his lit cigarette end. typically approach 25% of the Lower
Explosive Limit (LEL) and Table 6
102 A BP booklet entitled A Guide to illustrates the extent to which this
the Refinery Safety Regulations, set out exceeds the recommended exposure
rules to be observed. Rule 5 stated that limits. Vapour concentration is not evenly
smoking was not permitted except in distributed and depends on ventilation,
specified areas, and Rule 6 that matches ambient temperature, and the extent to
and lighters were not allowed in the which sludge is disturbed. Mechanical
premises and must be deposited at ventilation was not provided and thus the
thegatehouse. This booklet was not natural ventilation rate depended on wind
issued to all the contractor's personnel speed and direction, and the passage of
involved in T807. The temporary site entry air through the open ports.
passes for visitors and contractors had a
condition that matches and other sources Table 6 Typical volatile constituents of crude oil
of ignition should be surrendered before
entering the site. Such passes were not
issued to the contractor's employees Lower
explosive Concentration Recommended
involved in cleaning T807.
constituent limit at 25% LEL exposure limit
@pm) (PP~)
103 Notices were posted at the main @EL)
entrance to the terminal stating "no
smoking within the installation" and "no Pentane 1.4 3 500 600
Hexane 1.2 3 000 500
smoking: all lighters and matches must n-Hexane 1.2 3 000 100
be surrendered to security personnel at Heptane 1.1 2 750 400
the gate". However, the entrance was
unmanned and the gate was operated
remotely from the control room using 105 Some men did not appreciate the
video camera surveillance and intercom. toxic hazards; neither did they realise the
Terminal staff carried out no checks to extent to which vapour concentrations
ensure that contractor's employees would increase towards the floor of the
complied with the rules. Unchallenged, tank. Some discovered that they could
see better in the dark, unlit conditions if becoming entangled on a support pillar.
they removed their BA face pieces or He may also have slipped or tripped over
visors and they quickly became hoses or other equipment. Means of
accustomed to the smell. As they felt no escape from the tank in case of an
apparent ill-effects they concluded it was emergency, particularly in the event of
safe both to leave off their BA and to fire, had not been considered and
smoke. The deceased was a non-smoker emergency escape exercises had not
and so far as is known, wore his BA at been practiced by the contractor. The
all times. Although experienced outside man had no clear instructions
employees had received formal training about the action to take in the event of
some men were new to tank cleaning an emergency.
work and had received no such training.
Basic training in the use of breathing 108 Although this incident resulted in a
apparatus was given by the contractor's surface fire, there was the potential for an
supervisor. For some this involved only a explosion had there been a sufficient
short demonstration of how to fit the volume of vapour at a concentration
facepiece, operate the air regulator and between the lower and upper flammable
deal with snagged air hoses or air supply limits. Precautions to prevent this include
failure. ventilation and routine monitoring of
vapour concentrations. Mechanical
106 The team involved mostly worked ventilation would not only have reduced
unsupervised and on the occasions when the overall concentration of vapours in
their supervisor, a member of the other the tank but also minimised the extent to
squad, came in, they could return to which local concentrations could have
wearing BA before he came close enough been in the flammable range. However
to see them. Although the supervisor was the senior site engineer considered that
not aware of smoking and would not have such ventilation and vapour concentration
condoned it, he had on occasions monitoring were not necessary. He
removed his breathing apparatus whilst thought that concentrations would be
inside the tank, in order to give verbal above the upper flammable limit and that
instructions to the men. From the outside workmen wearing breathing apparatus
of the tank it was impossible to see what were adequately protected. A terminal
was going on inside and the terminal safety services operator undertook some
safety services operator was unaware of monitoring on his own initiative although
these malpractices. The men ensured that not fully aware of the instrument
they were wearing the correct equipment limitations. On the day before the
when entering and leaving to give the accident he obtained a reading in T807 of
impression that it was worn at all times, 25% of the LEL. He did not know how to
and it thus appears that they deliberately assess the significance of this reading
deceived both their own supervisor and which is in fact the limit at which
the terminal staff. consideration should have been given to
stopping work. He took vapour level
107 The survivors could not remember readings external to T807 daily and
their exact position in the tank, other recorded these on the permit to work.
than they were working at the northern
bank of sludge, and so the distance they 109 There were no detailed written
were required to travel when the fire procedures specifying the precautions to
occurred is not known accurately. When be taken during the cleaning of T807. The
the fire started flame is estimated to have contract only made reference to general
moved across the surface at about 2 mls standards which were expected and
and the fire may have spread to cut off stated inter alia that the contractor
the means of escape for the deceased. should ensure that his work methods "are
He alone was wearing his BA the hose of as safe as is reasonably practicable and
which may have impeded his escape by that any danger to life and limb and the
environment is minimised". The contract ventilation. This should be sufficient to
also stated that "all work will require the reduce the overall flammable vapour
issue of permits by the employer (BP) but concentration, to avoid vapour pockets
the employer reserves the right to and to minimise the extent to which the
suspend the permit at any time should he vapour above the sludge surfaces may be
consider the area becomes unsafe." in the flammable range. The effective
control of ignition sources is of equal
110 Rigorous inspection of equipment importance but in view of the ever
used by the contractors was not carried present risk of fire, precautions for tank
out. Despite a BP requirement for internal cleaning must also include provision for
combustion engines to be fitted with safe means of escape. Tank designers
sparklflame arresters, a diesel engined should give due consideration to the
hydraulic power generator located about hazards of cleaning operations and the
two metres from an open T807 manway need for access and ventilation.
was found with a cracked exhaust Companies who carry out tank cleaning
manifold. There were no formal operations should produce a detailed
procedures for checking the equipment method statement setting out clearly the
being taken into the tank. safety precautions they intend to take.
111 In 1985 following similar tank 114 "The preparation and operation of
cleaning operations, the terminal had contracts in the Petroleum Industry:
received advice from HSE which Health and Safety Guidelines" a
recommended that consideration be given publication produced by the Oil Industry
to the means of escape from inside tanks Advisory Committee (Reference 3) refers
for persons wearing airline breathing to the care which should be taken in
apparatus because of the risk of air hose selecting and assessing contractors
entanglement around roof support pillars. referring to, inter alia, management
attitude, safety performance assessment,
Conclusions safety policy etc. Reference is made to
the need to control contractors on site.
112 The fire was started because an Although the legal duties of employers
employee of the cleaning contractor described in section 2 of the Health and
deliberately disregarded a basic safety Safety at Work etc Act 1974 cannot be
rule. He smoked in the tank which delegated, every employer is, as a general
contained highly flammable vapours. He principle, responsible for those areas over
was not alone in this; two other men had which he can exert control. Site occupiers
also smoked in the tank. In his written should recognise their special
judgement following the Fatal Accident responsibilities relating to the overall
Inquiry the Sheriff stated "They knew that control of their sites and should make
it was dangerous. They wilfully shut their provision for possible shortfalls on the
eyes to the fact that by doing so they part of any contractor (and his
risked causing a fire". While good site employees).
security and supervision may reduce the
likelihood of smoking the Sheriff doubted 115 Site occupiers are advised to make
whether such precautions would be it a condition of contract that they may:
adequate "against the perversity of (a) Inspect and approve where necessary
workmen who choose to break all the any materials, substances and
rules" However, companies undertaking equipment provided by the contractor
such potentially hazardous work must be and specify any necessary conditions
rigorous in their staff selection under which the materials or
procedures. equipment may be used;
113 An important safeguard during tank (b) require the contractor to provide
cleaning operations involving flammable information on the health and safety
residues is the provision of adequate aspects of the materials, substances
and equipment to ensure that they statute or, additionally, by the owner-
conform to national specified operator's own accepted practices;
standards;
(f) require the contractor to stop work or
(c) require evidence from the contractor prohibit a particular practice when he
that his personnel are trained and considers his activities may be
experienced enough to do the job prejudicial to health or safety.
competently and safely;
116 The circumstances of the accident
(d) require the contractor to demonstrate demonstrate clearly the need to follow
that his employees are at all times the advice set out in the HSE publication
adequately trained and instructed in Dangerous Maintenance - a study of
the potential hazards associated with maintenance accidents in the chemical
the owner-operator's operations or, industry and how to prevent them (Ref 1)
as necessary, review the adequacy of especially at paras 88 to 92. The report
the training, instruction and highlights key points on contractors.
information given to contractor's
employees to identify areas for (a) Is the competence of contractors
improvements; properly evaluated?

(e) at any time - when a contractor is (b) Are contractors on site instructed in
working within an area under the the possible risks?
control of the owner-operator - (c) Do contractors receive full
inspect and audit the contractor's information on the job to be done?
workplace and working methods and
examine any record required by (d) Are contractors properly supervised?
applied in the UK Petroleum Industry. The
Oil lndustry Advisory Committee of the
Bibliography Health and Safety Commission. HMSO
ISBN 0 11 883885 7.
1 Dangerous Maintenance: A study of
3 The preparation and operation of
maintenance accidents in the Chemical
contracts in the Petroleum lndustry
Industry and how prevent Health and Safety Guidelines. The Oil
ISBN 0 883957 8.
lndustrv Advisorv Committee of the
2 A guide to the principles and Health 'and safety Commission. HMSO
operation of permit-to-work procedures as ISBN 0 11 883903 9.

Printed in the UK for HMSO 3M 3189

44
HMSO publications are available from:
HMSO Publications Centre
(Mail and telephone orders only)
PO Box 276, London, SW8 5DT
Telephone orders 01-873 9090
General enquiries 01-873 OOli
(queuing system in operation for both numbers)
HMSO Bookshops
49 High Holborn, London, WClV 6HB 01-873 0011 (Counter service only)
258 Broad Street, Birmingham, B1 2HE 021-643 3740
Southey House, 33 Wine Street, Bristol, BS1 2BQ (0272) 264306
9-21 Princess Street, Manchester, M60 8AS 061-834 7201
80 Chichester Street, Belfast, BTI 4JY (0232) 238451
71 Lothian Road, Edinburgh, EH3 9AZ 031-228 4181
HMSO's Accredited Agents
(see Yellow Pages)
and through good booksellers

Price: f 7.50 net


ISBN 0 11 885493 3

You might also like