You are on page 1of 7

METHOD STATEMENT FOR CORING PIT OF ELEVATOR

METHOD STATEMENT FOR


CORING PIT OF ELEVATOR

1
METHOD STATEMENT FOR CORING PIT OF ELEVATOR

I. PROJECT INFORMATION

Project name : STARTPHNOM PENH HOTEL

Location : #62, 63, 64 Villages 1, SangkatChaktomok, Khan Doun Penh, Phnom Penh,

Cambodia.

Client : STARTS CAM (CAMBODIA) CORPORATION

Consultant : Archetype Group

Contractor : Techno Design & Construction (TDC)

Project Scale : The project is comprised of 19 stories Hotel and Apartment on the land area
of

2,420m2 with total 26,100m2 of GFA in high luxury standard

FIGURE-1: Project Location

2
METHOD STATEMENT FOR CORING PIT OF ELEVATOR

II. INTRODUCTION

The purpose of this document is to provide the framework and general of the equipment,
materials and arrangement to ensure that all activities performance are following technical of
construction standard, procedure, specification of approved material used, so they can be
carried out in timely and proper manner, to meet the qualities and specifications of the project
requirement.

III. METHOD STATEMENT


1. EQUIPMENT AND MATERIALS

1. Chipping machine

2. Coring machine

3. Sika grout 214-11

4. Sikadur 32

2. PROCEDURE
The pile cap to be cut should be clearly marked by surveyor and approved
by the consultant before any cutting /coring work Starts.
Using Coring Machine 100mm dia. to drill and conduct as below:
Marked out the Position to be cored.
Ensure that there is no service in front and behind the location to
be cored.
Move away or protect thing that is directly underneath the area to
be cored.
Mount coring machine stand.

3
METHOD STATEMENT FOR CORING PIT OF ELEVATOR

Fix the core bit to be the machine.


Adjust and center the core bit to the marked position.
Setup water protection system.
Starting the coring machine.

SEQUENCE OF CORING
Turn on the water system and start coring.
One coring through, stop the motor and water.
Remove drill motor.
Remove cored concrete core.
Chipping concrete that remaining
Clean up area.
Apply sikadur 32 on rebar
Install formwork and then casting grouting

4
METHOD STATEMENT FOR CORING PIT OF ELEVATOR

3. RISK ASSESSMENT

Risk Identification Risks control

Task/Work Responsible Person in


No Risks description Risks prevention Status
Activities entity charge
1 Work ing at 1. Falling from high position 1. Using safety scaffolding which inspected and
high position 2. Falling object approved by safety officer
2. secure the working area by put signage and
warning tap Site engineer
3. Secure hand tool by rob TDC and safety Going on
4. Not be allowed to throw up or down material or officer
tool.
5. Wearing safety harness properly using life line

2 Working with 1. Get injured due to chemical 1. Wearing PPE properly including safety glasses
chemical product contact with eyes 2. Using safety hand gloves which can protect the Site engineer
product 2. Get injured due to direct skin and available to work with chemical product TDC and safety Going on
body with chemical product 3. Install caution sign board information on site officer

3 Using power 1. Electric shock 1. Not allow to laying electric cable direct on
tool the ground or under water
2. Laying the cable first before plug it to the
power supply, and unplug it before remove Site engineer
the electric cable TDC and safety Going on
3. Not allow to use power tool working under officer
the rain

You might also like