METHOD STATEMENT FOR CORING PIT OF ELEVATOR
I. PROJECT INFORMATION
Location : #62, 63, 64 Villages 1, SangkatChaktomok, Khan Doun Penh, Phnom Penh,
Cambodia.
Project Scale : The project is comprised of 19 stories Hotel and Apartment on the land area
of
2
METHOD STATEMENT FOR CORING PIT OF ELEVATOR
II. INTRODUCTION
The purpose of this document is to provide the framework and general of the equipment,
materials and arrangement to ensure that all activities performance are following technical of
construction standard, procedure, specification of approved material used, so they can be
carried out in timely and proper manner, to meet the qualities and specifications of the project
requirement.
1. Chipping machine
2. Coring machine
4. Sikadur 32
2. PROCEDURE
The pile cap to be cut should be clearly marked by surveyor and approved
by the consultant before any cutting /coring work Starts.
Using Coring Machine 100mm dia. to drill and conduct as below:
Marked out the Position to be cored.
Ensure that there is no service in front and behind the location to
be cored.
Move away or protect thing that is directly underneath the area to
be cored.
Mount coring machine stand.
3
METHOD STATEMENT FOR CORING PIT OF ELEVATOR
SEQUENCE OF CORING
Turn on the water system and start coring.
One coring through, stop the motor and water.
Remove drill motor.
Remove cored concrete core.
Chipping concrete that remaining
Clean up area.
Apply sikadur 32 on rebar
Install formwork and then casting grouting
4
METHOD STATEMENT FOR CORING PIT OF ELEVATOR
3. RISK ASSESSMENT
2 Working with 1. Get injured due to chemical 1. Wearing PPE properly including safety glasses
chemical product contact with eyes 2. Using safety hand gloves which can protect the Site engineer
product 2. Get injured due to direct skin and available to work with chemical product TDC and safety Going on
body with chemical product 3. Install caution sign board information on site officer
3 Using power 1. Electric shock 1. Not allow to laying electric cable direct on
tool the ground or under water
2. Laying the cable first before plug it to the
power supply, and unplug it before remove Site engineer
the electric cable TDC and safety Going on
3. Not allow to use power tool working under officer
the rain