FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Precommissioning of UPS 8741 in Tank Substation Tank Farm 16-23 Aug.07

See attached vendor print & cable schedule Substation 2:30 PM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Precommissioning of UPS 8742 in Tank Substation Tank Farm 16-23 Aug.07

See attached vendor print & cable schedule Substation 3:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Precommissioning of BC 8751 in Tank Substation Tank Farm 16-23 Aug.07

See attached vendor print & cable schedule Substation 4:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable laying inspection of L.V & Control cable Main Substation 17.Aug.2007

in HVAC room HVAC 8:00 AM

See Attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

16.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity & Insulation Resistance test of L.V. Main Substation 17.Aug.2007

control cable in HVAC room HVAC 9:00 AM

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

16.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable Laying inspection of low voltage cable Main Substation 15.Aug.07

from UPS 8042 to inert gas LCP 8:30 AM

See attached connection diagram

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity & insulation resistance test of L.V Cable Main Substation 15.Aug.07

from UPS 8042 to inert gas LCP 8:30 AM

See attached connection diagram

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

1.Insulation Resistance Test 33 kV H.V. cable Main Substation 16.Aug.07

2.Outer Sheath test of 33 kV H.V cable to 19.Aug.07

3. AC HiPOT test of 33 kV Cable Karhamaa Substation 20.Aug.07

from Main S/S to Karhamaa S/S 21.Aug.07

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity & Insulation Resistance of L.V & Control Main Substation 12.Aug.2007

Cable from UPS 8041 to UPS 8042 building 8:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

11.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Lighting & Small Power Layout inspection Main Substation 07.July.2007

1. Conduit installation inspection building 9:00 AM

2. Power Outlet & Switch installation inspection

3. Lighting fixture installation inspection

4. Wiring installation inspection

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

06.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity & Insulation Resistance test of Low Voltage Main Substation 14-18.Aug.2007

& Control cable building 8:30 AM

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

13.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of OTB-1 & OTB-2 in Main Substation 14.Aug.2007

Main Substation Switchgear room 8:30 AM

See attached drawing: 150/80/41/EL/DR/PL/001

rev. 12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

13.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of ELSB-8031 panel in Main Substation

accordance with precom checklist Switchgear room

See attached vendor print & layout drawing

150/80/41/EL/DR/PL/001 rev.12

7S19-VP-80/00/EL/PO/003-202

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of LSB 8031 panel in Main Substation

accordance with precom checklist Switchgear room

See attached vendor print & layout drawing

150/80/41/EL/DR/PL/001 rev.12

7S19-VP-80/00/EL/PO/003-201

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. : EL-COM-149

PROJECT NAME : LAFFAN REFINERY DATE : March 18, 2008

AREA : MAIN SUBSTATION

INSPECTION ITEM LOCATION DATE/TIME REMARKS

LP-800231 Main S/S 20-Mar-08

Lighting & Small Power Circuit Function Test

(Commissioning) 5:00PM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

Lighting & Small Power Circuit Function Test for LP-800231

NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) ( CONTRACTOR )

DATE : ______________ DATE : ______________


COMMISSIONING FUNCTIONAL TEST NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. : CFT-TEL-002

PROJECT NAME : LAFFAN REFINERY DATE :

AREA : SUB-SYSTEM :

COMMISSIONING ACTIVITY LOCATION DATE/TIME REMARKS

Dear Sir (s),

NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) ( CONTRACTOR )

DATE : ______________ DATE : ______________


FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

H.V. Splicing work in EWC EWC 15 -31 Aug

PJB1, PJB2,PJB3,PJB4,PJB5,PJB6 8:30 AM

See attached drawing

150/80/00/00/EL/DR/PL/101 - 116 rev.14

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

14.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable Laying inspection 2nd layer in crossing no. EWC 17.Aug.2007

16,17,18 EWC 8:00 AM

See attached drawing

150/80/00/EL/DR/PL/111 -113 rev.14

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

16.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Insulation resistance test of H.V. Cable in crossing EWC 17.Aug.2007

16,17,18 EWC 9:00 AM

See attached drawing & Cable schedule

150/80/00/EL/DR/PL/111 -113 rev.14

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

16.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of earthing system in Tank S/S Tank Farm 20.Aug.2007

and earth resistance test Substation 9:00 AM

See attached drawing 150/87/41/EL/DR/PL/403 rev. 11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

19.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of Lightning system in Tank S/S Tank Farm

See attached drawing 150/87/41/EL/DR/PL/403 rev. 11 Substation

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of Lightning system in Main S/S Main S/S 20.Aug.2007

tin copper bar, holder,stike counter

See attached drawiing 150/88/41/EL/DR/PL/404 rev.11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

19.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of LP-870231 switch room Tank farm substation

Tank Farm substation

See attached drawing

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of ELP-870231 switch room Tank farm substation

Tank Farm substation

See attached drawing

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of 20 kV Switchgear Main Substation 19-25.Aug.2007

Bus bar protection test & Primary injection test Switchroom 8:30

Functional test

See attached drawing vendor print

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

18.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

ELP & LP Panel installation inspection Main Substation 09.Aug.07

See attached Drawing Switchgear room 8:30 AM

150/88/41/EL/DR/PL/303 rev.11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

08.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Conduit installation inspection Main Substation 09.Aug.07

(lighting & Small Power conduit) Switchgear room 9:00 AM

See attached Drawing

150/88/41/EL/DR/PL/303 rev.11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

08.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Lighting fixture installation inspection Main Substation 09.Aug.07

See attached Drawing Switchgear room 10:00 AM

150/88/41/EL/DR/PL/303 rev.11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

08.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

ELP & LP Panel installation inspection Main Substation 09.Aug.07

Conduit installation inspection Switchgear room 8:30 AM

Lighting fixture installation inspection

Wiring installation inspection

See attached Drawing

150/88/41/EL/DR/PL/303 rev.11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

08.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable laying inspection of low voltage cable Main Substation 30.Jul.2007

(BC - 8053) room 9:30 AM

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

29.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Insulation Resistance test of H.V Cable EWC 07.July.2007

Crossing no. 14, 15 Area 4 9:30 AM

See attached drawing

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

05.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Visual inspection of welding inspection EWC 09.July.2007

in crossing no. 7,8,14

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

07.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Insulation Resistance test of H.V Cable EWC 07.July.2007

Crossing no. 11 Area 3 8:30 AM

See attached drawing

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

05.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of TMMC Panel (CP-8011) Main Substation 01.Aug.2007

See attached vendor print drawing building 8:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

31.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
NSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE


FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of Metering Panel (CP-8011) Main Substation 12,Aug.07

See attached vendor print drawing building 9:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

11.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of TELECOM Panel (CP-8015) Main Substation 01,Aug.07

See attached vendor print drawing building 10:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

31.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity & Insulation Resistance test of Low Voltage Main Substation 30.June.2007

See attached cable schedule (TMMC CP-8013) building 2:30 PM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

27.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of 20 kV switchgear Main Substation 5 - 21 Aug.07

Main Substation building 9:00 AM

Insulation Resistance Test of Bus bar & Breaker

Bolt Torque

H. V Test of Bus Bar & Breaker

Ducter Resistance

V.T & CT, ratio, polarity & magnetizinf test

Protection relay test

Bus Bar Protection & Primary injection test

Functional Test

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

04.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

33 kV Cable Splicing work in NSC NSC 05 - 8 Aug

See attached drawing 9:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

04.Aug.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity &Insulation resistance of 33 kV cable from NSC 15.JUL.07

PJB2 to Kahramaa. 2:30 PM

See Attached Drawing

150/80/00/EL/DR/PL/117 Rev.15

150/80/00/EL/DR/PL/120 - 123 rev. 13

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

14.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable tray and support inspection in crossing # 15 EWC 04.Aug.2007

#16, #17,#18 8:30 AM

See attached dwg no.150/80/00/EL/DR/PL/111,112,113

rev.14

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

03.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable tray support welding inspection in crossing EWC 04.Aug.2007

#15,#16, #17,#18 9:30 AM

See attached dwg no.150/80/00/EL/DR/PL/111,112,113

rev.14

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

03.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity & Insulation Resistance test of L.V. and Main substation 06 - 11 Aug.2007

Control cables switchgear room 9:00 AM

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

05.Aug.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable tray welding support visual inspection EWC 12.Jul.2007

See attached dwg no.150/80/00/EL/DR/PL/112 rev 14 Crossing No.17 9:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

10.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Precommissioning of 33 kV Switchgear Main Substation

See attached drawing

Dwg no.7S19-VP-80/00/EL/PO/002-100

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

16.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Earth Resistance Test in Main S/S Main Substation 16.Jul.2007

See attached drawing 9:00 AM

Dwg no.150/88/41/EL/DR/PL/403 rev.10

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

14.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Insulation Resistance Test of Low Voltage & control Main Substation

cable

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

1.) Insulation resistance test & Hipot test for 33 kV Main Substation

switchgear Bus Bar

2.) Insulation resistance test & Hipot test for 33 kV

switchgear circuit breaker

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

1.) Insulation resistance test & Hipot test for 33 kV Main Substation

switchgear Bus Bar

2.) Insulation resistance test & Hipot test for 33 kV

switchgear circuit breaker

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Insulation Resistance, Hipot Test of H.V. Cable Main Substation

Primary & Secondary cable

See attached Cable Schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable tray support welding inspection in EWC 26.July.2007

crossing no. 1,2,3 4,5 9:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

25.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable Laying Inspection from PJB4 to PJB5 EWC 28.July.2007

Crossing 16,17,18 Area 5 Area 5

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

26.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Insulation resistance test of H.V Cable from EWC 28.July.2007

from PJB4 - PJB5 Crossing 16,17,18 Area 5 Area 5

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

26.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity & Insulation resistance test of Low voltage Main Substation 28-31 Jul.07

cable, control cable

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

26.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Outer sheath test in NSC from JB1 to Main S/S JB1 to Main S/S 26.Jul.07

See attached map of Fault location 8:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

25.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation inspection of Neutral Earth Resistor Main Substation 30.Jul.2007

A & B for TR- 8071A & B TR Yard 9:00 AM

See arrangement drawing

7S19-VP-80/00/EL/PO/001- 250 rev 10

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

29.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pin brazing connection for underground pipes LRB 19.Jul.2007

at AW (MH 1922,1923 ) 9:30 AM

See attached drawing

7S19-VP-EL/PO/009-038 rev. 10

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

17.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation & Alignment inspection of ELDB-8031 Main Substation 24.Jul.2007

400 V Switchgear HVAC room 8:30 AM

Dwg no.150/80/00/EL/LDR/PL/001 rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

22.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation & Alignment inspection of ELSB-8031 Main Substation 24.Jul.2007

400 V Switchgear

Dwg no.150/80/00/EL/LDR/PL/001 rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

22.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation & Alignment inspection of LDB-8031 Main Substation 24.Jul.2007

400 V Switchgear HVAC room 9:30 AM

Dwg no.150/80/00/EL/LDR/PL/001 rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

22.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Installation & Alignment inspection of LTR-8031 Main Substation 24.Jul.2007

Dwg no.150/80/00/EL/LDR/PL/001 rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

22.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Dielectric Strength sample from Main transformer Main Substation 23.Jul.2007

TR 8071 A & B 9:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

22.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Dielectric Strength sample from main transformer Tank Farm 23.Jul.2007

TR 8721 A & B Substation 8:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

22.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Inspection of conduit,JB,bushing installation Tank Farm 24.Jul.2007

to close the NCR no.166 Substation 10:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

22.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Inspection of conduit,JB,bushing installation Control Building 24.Jul.2007

to close the NCR no.158 10:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

22.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable tray & Support installation inspection in EWC 26.Jul.2007

crossing no. 1,2,3,.4,5,6 8:30 AM

Dwg no.150/80/00/EL/DR/PL/101, 102 rev.14

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

25.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable tray Support welding inspection in EWC 26.Jul.2007

crossing no. 1,2,3,.4,5,6 9:00 AM

Dwg no.150/80/00/EL/DR/PL/101, 102 rev.14

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

25.July.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of 33kV Switchgear in main S/S Main Substation

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Inspection of Anode installation in tank farm Tank Farm 10.Jul.2007

AN-UGP87-029, AN-UGP87-026,AN-UGP87-027 8:30 AM

AN-UGP87023, AN-UGP87-022,AN-UGP87-021

See Attached Drawing: 7S19-VP-EL/PO/009-043, 048

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

08.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Conduit,PB Boxes for Telecommunication Layout Tank Farm Substation 16.Jul.07

installation inspection details 3:00 PM

See attached drawing

Dwg no.150/87/41/TE/DR/PL/702 rev.11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Conduit,PB Boxes for Lighting & Small Power layout Tank Farm Substation 16.Jul.07

installation inspection details 2:30 PM

See attached drawing

Dwg no.150/87/41/EL/DR/PL/302 rev. 11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Conduit,PB Boxes for Fire Alarm wiring layout Tank Farm Substation 16.Jul.06

installation inspection details 3:30 PM

See attached drawing

Dwg no.150/87/41/EL/DR/PL/602 rev.11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Conduit,PB Boxes for Lighting & Small Power layout Main Substation 16.Jul.07

installation inspection details 8:30 AM

See attached drawing

Dwg no.150/88/41/EL/DR/PL/303 rev.10

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Conduit,PB Boxes for Telecommunication Layout Main Substation 16.Jul.07

installation inspection details 9:00 AM

See attached drawing

Dwg no.150/88/41/TE/DR/PL/702 rev. 11

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Conduit,PB Boxes for Fire Alarm Wiring Layout Main Substation 16.Jul.07

installation inspection details 9:30 AM

See attached drawing

Dwg no.150/88/41/EL/DR/PL/602 rev. 13

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

15.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of Transformer 8071 A & B Main Substation 21-22.Jul.07

See attached drawing Transformer yard 9:30 AM

Dwg no.7S19-VP-80/00EL/PO/001 -011 Rev.10

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

21.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of Transformer 8721 A & B Tank Farm 22-23.Jul.07

See attached drawing Substation 9:30 AM

Dwg no.7S19-VP-80/00/EL/PO/001-020 rev.10

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

21.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of Transformer 8031 A & B Main Substation 21-22.Jul.07

See attached drawing Transformer yard 10:30 AM

Dwg no.7S19-VP-80/00EL/PO/001 -001-140 Rev.10

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

21.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre-commissioning of Transformer 8731 A & B Tank Farm 22-23.Jul.07

See attached drawing Substation 10:30 AM

Dwg no.7S19-VP-80/00/EL/PO/001 -190 Rev.10

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

21.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable Laying Inspection of 0.6 kV low voltage cable Main Substation 03.Jul.2007

Visual Inspection Building 9:30 AM

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

01.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre commisssioning of 33 kV switchgear Main Substation 21.Jul.07

See attached vendor print drawing Building 8:30 AM

51310484BA

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

19.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre commisssioning of LDB 8731 MCC Main Substation

See attached drawing Building

150/87/41/EL/DR/PL/001 rev. 12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre commisssioning of ELDB 8731 MCC Main Substation

See attached drawing Building

150/87/41/EL/DR/PL/001 rev. 12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Pre commisssioning of 20 kV switchgear Main Substation 19.Jul.07

See attached vendor print drawing Building 8:30 AM

51310484BH

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

18.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity & Insulation resistance test of control cable Main Substation 17.Jul.07

1.) C-UPS-8041-EMCS-C3 Building 9:00 AM

2.) C-UPS-8042-EMCS-C3

(See attached cable schedule)

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

16.Jul.07

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable Laying inspection of L.V. Main Substation 04.Jul.2007

control cable SB-8031 to EMCS Building 10:00 AM

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

02.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity &Insulation Resistance test 0.6 kV Main Substation 04.Jul.2007

low voltage control cable ESB-8031 to EMCS Building 9:30 AM

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

02.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable Laying inspection of L.V. Main Substation 04.Jul.2007

control cable ESB-8031 to EMCS Building 9:00 AM

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

02.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Continuity &Insulation Resistance test 0.6 kV Main Substation 04.Jul.2007

low voltage control cable LSB & ELSB to EMCS Building

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

02.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Cable Laying inspection of L.V. Main Substation 04.Jul.2007

control cable LSB & ELSB to EMCS Building

See attached cable schedule

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

02.Jul.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

6.6 kV Switchgear Installation & alignment Tank Farm 25.June.2007

inspection Substation 8:30 AM

Dwg no.150/87/41/EL/DR/PL/001 rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

23.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

400 V Switchgear Installation & alignment (SB-8731) Tank Farm 25.June.2007

inspection Substation 9:00 AM

Dwg no.150/87/41/EL/DR/PL/001 rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

23.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

400 V Switchgear Installation & alignment (SB-8732) Tank Farm 25.June.2007

inspection Substation 9:30 AM

Dwg no.150/87/41/EL/DR/PL/001 rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

23.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

400 V Switchgear Installation & alignment Tank Farm 25.June.2007

(ESB 8732) inspection Substation 11:30 AM

Dwg no.150/87/41/EL/DR/PL/001 rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

23.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

Battery Charger Panel V installation Tank Farm 25.June.2007

alignment installation Substation 10:00 AM

Dwg no.150/87/41/EL/DR/PL/001 Rev.12

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

23.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

UPS - 8041 installation & alignment inspection Main Substation 28.June.2007

Dwg no.150/80/41/EL/DR/PL/001 Rev.12 9:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

26.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

UPS - 8742 installation & alignment inspection Tank Farm 25.June.2007

Dwg no.150/87/41/EL/DR/PL/001 Rev.12 Substation 11:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

23.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

BC - 8051 installation & alignment inspection Main Substation 21.June.2007

Dwg no.150/80/41/EL/DR/PL/001 Process area 10:00 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

19.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

ETR-8031 installation & alignment inspection Main Substation 21.June.2007

Dwg no.150/80/41/EL/DR/PL/001 Process area 10:30 AM

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

19.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
FIELD TEST / INSPECTION NOTICE

CONTRACTOR JOB NO. : 7S19 AFI NO. :

PROJECT NAME : LAFFAN REFINERY DATE :

AREA :

INSPECTION ITEM LOCATION DATE/TIME

EMCS, Metering panel,Teleprotection, Main Substation 21.June.2007

Telecommunication (RTU) installation & alignment Process area 11:00 AM

inspection.

Dwg no.150/80/41/EL/DR/PL/001

Dear Sir (s),

We would like to have your presence for the following test / inspection according to the following schedule

NAME & SIGNATURE : NAME & SIGNATURE : NAME & SIGNATURE :

( COMPANY ) (CONTRACTOR) ( SUB-CONTRACTOR )

DATE : ______________ DATE : ______________ DATE : ______________


CE

19.June.2007

REMARKS

the following schedule

& SIGNATURE :

CONTRACTOR )

______________
Contractor :
Name Signature

Supervisor :
Name Signature

Acceptance Sample Results


No. Description
Range No. (mm)
A1 - A2
A2 - A3
A3 - A4
A4 - A5
A5 - A6
A6 - A7
A7 - A8

1 Anode Spacing 2310 ~ 1890 mm

B1 - B2
B2 - B3
B3 - B4
B4 - B5
B5 - B6
B6 - B7

Power
Feeder No. 1 No. 2 Remarks
Cable

No. 1

No. 2

No. 3
Results:
Signature Date

Signature Date

Remarks

7S19-VP-EL.PO.009-014