You are on page 1of 7

The Effects of Intermittent Supply on Water Distribution Networks

Bambos Charalambous
Water Board of Lemesos, P.O. Box 50225, 3602, Lemesos. Cyprus
(email: bambos@wbl.com.cy)
Key Words: water shortage, intermittent supply, leakage

ABSTRACT starting when total rainfall is well below


average for several months. A balance
The worlds population is increasing at a must be maintained between the water
tremendous rate, the worlds renewable taken out for supply and that being
water resources are reducing rapidly, replaced by surface run-off. Normally
the gap between supply and demand is the surface run-off during the winter far
widening with urbanisation and climate exceeds demand for supply, so that the
change making it even wider. This paper excess water can be stored and used
reviews how the Water Board of when surface run-off is less than
Lemesos, Cyprus, a water utility with a demand from consumers.
proven history of managing extremely Intermittent water supply may be
well its distribution network, was forced defined as a piped water supply service
due to water shortage conditions to that delivers water to users for less than
have intermittent supply, providing water 24 hours in 1 day. It is a type of service
3 times a week for about 12 hours each that, although little found in developed
time. Although intermittent supply is countries, is very common in developing
perhaps the last measure to be taken in countries. In an intermittent supply
conditions of water shortage, it is situation the consumers secure their
however a situation worthwhile avoiding water supply through the use of ground
through proactive planning and timely or tanks, where water is stored during
response to critical conditions. The the time that the supply is provided.
adverse effects of intermittent supply on Intermittent water supply is enforced not
customer service and on the integrity of only in cases where there is water
the distribution network as well as the shortage but also where the hydraulic
financial repercussions to the utility are capacity of network is such that can not
also discussed based on the satisfy demand as well as in cases
experiences gained from the intermittent where the networks are badly
supply measures taken during the water deteriorated.
shortage periods faced by the Water
Board in the last twenty years. Usually water shortage is declared when
the water supplies fall short of meeting
Introduction water demands. This situation usually
prevails in arid and semi-arid areas of
A drought can be defined as a our planet where precipitation has been
prolonged period of unusually dry steadily declining or where management
weather in an area where some rain of limited water resources has been
might normally be expected. Droughts wasteful and unwise.
involve water shortages, crop damage, In many instances there is no indication
stream flow reduction and depletion of how long intermittent supply measures
groundwater and soil moisture. A will be in place. The hydrological
drought happens when a period of low conditions in each case could impact
rainfall leads to a shortage of water. It is adversely on water supply for years in
1
which case conserving as much as agriculture and over-fertilisation
possible the limited water resources increased nitrate content particularly in
may not be the long term solutions but it the coastal areas. To increase the water
may be necessary to add to the water resources of Cyprus the Government
balance new non conventional water embarked in an ambitious programme of
resources. In many countries water tapping the surface water, which was
shortage problems were overcome lost to the sea through surface runoff.
trough the desalination of brackish or To increase further the water resources
saline water. Of course exploring every and especially to relieve the domestic
potential water source available may be water supply from the vagaries of the
the only solution in many instances, but weather the Cyprus Government
conservation is always one of the least proceeded with the construction of
expensive and quickest solutions to desalination plants to produce potable
ensuring that water will be available water and with the construction of
when needed. sewage treatment plants to treat
domestic effluent for use mainly in
Water Resources at Great Risk agriculture.

The scarcity of water resources in the A Sustainable Approach


Mediterranean islands is one of the
most pervasive natural resource In Cyprus the growing imbalance
allocation problems facing water users between supply and demand in the last
and policy makers. This problem is few decades reached a critical stage
faced each day in the many conflicts with the most recent drought periods in
that surround the use of this limited 1989-1991, 1997-2000 and 2007-2009
resource and the provision of water to with concurrent dramatic decrease of
the many user groups is determined the supply and considerable increase in
based on the specific condition demand.
pertaining at any point in time.
During the above drought periods the
Cyprus is the largest island in the government imposed water restrictions
Eastern Mediterranean with hot dry to both domestic and agricultural
summers and rainy, rather changeable supplies. At the same time it has moved
winters. The mean annual precipitation forward with the construction of
is about 500mm with substantial treatment units to treat domestic
variation from 300mm in the plains to sewage water for agriculture and of
over 1000mm on the mountainous desalination plants to produce potable
regions. The precipitation records of the water for domestic needs thus adding to
last 100 years indicate an overall the water balance and reducing the
decrease of the mean annual deficit.
precipitation of about 15%, but annual
variation in precipitation varies Despite the fact that the management of
considerably from the mean with long water, for both domestic and irrigation
periods below average, affecting purposes, has improved tremendously
significantly the annual water resources in recent years by reducing losses from
of the island. supply networks and adding recycled
and desalinated water to the national
For the last fifty years the annual water water balance there is still an imbalance
demand in Cyprus was mostly satisfied between water use and renewable water
by groundwater. However, over- resources. The last drought period of
pumping caused depletion of the 2007-2009 left the town of Lemesos with
islands aquifers. Intensive irrigated very limited water quantities and in order
2
to get over the crisis the Government of analysed and action taken as necessary
Cyprus in cooperation with the Water to reduce the Apparent Loss component
and Sewerage Company of Athens thus increasing the utility revenues as
transported potable water with tankers well as applying the most cost effective
from Athens, Greece to Lemesos, leakage programme which reduces
Cyprus on a daily basis from August leakage to an economically,
2008 to April 2009 to cover the domestic environmentally and socially acceptable
needs of the town. level.

Improving the Situation Water Board of Lemesos

Reducing losses from distribution Distribution Network


networks is of the utmost importance
and water utilities must recognise this The Water Board of Lemesos is a non-
and respond positively. In addition water profit, semi-government organisation
must be used wisely and wastage charged with the responsibility of
avoided. Unfortunately, water is wasted supplying potable water to the town and
and as long as people are not facing environs of Lemesos. The main
water scarcity, they believe access to activities of the Water Board are:
water is an obvious and natural thing. planning and execution of technical
Efficient and effective water loss control projects, operation and maintenance of
should be recognised as a first priority the water production and water supply
for improving potable water supply. systems and all associated financial
Decision makers at all levels in water services including collection of water
utilities must understand that any water revenues and determination of water
loss control strategy in order to be tariffs.
effective must be a continuous activity
based on a long term strategy and The development of the distribution
should form an integral part of the network takes place in an organised
utilitys vision. The success of the fashion with new areas of supply being
strategy will inevitably depend on the incorporated into their respective
commitment and dedication at all levels pressure zones, strictly governed by the
within the utility and of course on the areas ground contours. Each pressure
adoption of appropriate strategies and zone is subdivided into DMAs, a total of
techniques. 60 are currently operating, which have a
single metered source with physical
Accounting for water is the first step that discontinuity of pipe work at boundaries.
must be made by any utility. It is
imperative that an accurate and In late 1980 the Water Board embarked
comprehensive metering system is in on a detailed programme of leakage
place for registering all water along the management. Since 2002 the Water
chain from production to the consumer, Board has adopted the practices and
including measurement of the water methodologies advocated by the IWA
produced and/or imported, water flow in Water Loss Task Force. The efforts
and out of treatment plants and storage made and importance placed by the
reservoirs and into the zones and district Water Board for proper leakage
metered areas. It is imperative to management is reflected in the
eliminate or minimise Authorised Un- reduction of the non-revenue water over
Metered Consumption thus achieving the years and in the improved
the highest possible accuracy in operational performance of its network.
accounting for all water produced. In 2007 the Board had an ILI below 2
Apparent and Real losses must be
3
and real losses under 100 These measures were in force until the
litres/connection/day. end of 2000. In 2008 and 2009 similar
restrictions were applied providing water
Water Supply Conditions 3 times a week for about 12 hours each
time. These actions resulted in an
The Water Board realised that water overall reduction in the use of domestic
conservation is not to be equated with water of approximately 15% per annum
temporary restrictions on customer which proved that the domestic demand
water use. Although water restrictions is near enough inelastic.
can be a useful emergency tool for
drought management or water shortage It was thought that after the above 4
situation, water conservation programs year period of intermittent supply,
concentrate on continuous measures would have been taken so
improvements in water use efficiency. that there will be sufficiency of water
To this end the Water Board embarked quantities for at least the domestic
on a promotional campaign through needs. However, this was not the case
television, radio and leaflets to increase and 8 years later, in 2008, water cuts for
public awareness for water domestic use were imposed once again.
conservation. Water was brought with tanker boats
from Athens, Greece. For many this dire
In 1991, the government legislated situation is blamed on the politicians for
against the use of hosepipe for washing not taking the right decision at the right
cars and pavements at all times, a law, time. For others there is the argument
which the Water Board enforces during that there has been mismanagement of
drought periods only. During the drought the water reserves prior to the drought
period of 1997-2000 the government period and not sufficient forethought has
was forced to announce in early 1997 a gone into the planning of such a severe
reduction of 20% for potable water and drought taking place so soon after the
40% for irrigation water supplies. In last one. In any case fact remains that
1998 the water situation became worse the Water Board of Lemesos even
and the restriction measures became though it has improved its network to
more stringent as the available such an extent that it is consider
quantities of water were diminishing and amongst the worlds best with losses
the government, much to the discontent from the network being extremely low, it
of the public, went ahead with further was faced with a situation beyond its
measures, enforcing greater restrictions control. Of course the situation would
to the water supplies with targeted have been a lot worse if the Board did
figures of 28% for potable water and not continuously improve its network in
56% for irrigation use. order to minimise losses thus saving
valuable quantities of water.
The Water Board of Lemesos always
responded promptly to the governments Intermittent supply therefore, may have
declared drought measures and seemed to be the short term answer to
imposed each time restrictions to the the water shortage situations faced in
continuous supply. In February 1997 the last 20 years, however in the
restricted supply to consumers to four following sections the adverse effects on
days a week. In 1998 due to limited the integrity of the distribution network
water reserves the Water Board was of such actions are discussed and
forced to decrease further the quantified based on the experiences
availability of water reducing the time of gained.
the water being available to the
consumers to 12 hours every 48 hours. Effects of Intermittent Supply
4
1.655.000 m3 which is slightly greater
It was evident that there was a large than the average annual volume of
increase in the number of reported pipe water saved (1.607.000 m3) due to the
breaks during the period of intermittent intermittent supply measures during the
supply. In order to quantify these a 2 year period of the intermittent supply.
comparison was made for a large
number of District Metered Areas, 20 in It is therefore evident that no matter how
total, between the breaks reported in good the distribution network is,
2007, before the intermittent supply was intermittent supply operation has
applied, and those reported in 2010, the definitely a detrimental effect on its
first year immediately after the integrity. In addition the amount of water
measures were lifted. This comparison saved is later lost again through
showed that the number of breaks on increased levels of leakage.
mains increased from an average of 1
per 7,14 km of mains to 1 per 2,38 km Figure 2 shows the Minimum Night Flow
of mains, an increase of 300%. for District Metered Area (DMA) 129
before and after intermittent supply.
Similarly, the number of reported service From the graph it is evident that leakage
connection breaks increased from an in this DMA increased from 10 m3/hr to
average 15,5 per 1000 connection in 20 m3/hr. This situation is typical of all
2007 to an average of 29,7 per 1000 DMAs with relatively old, about 40
connections in 2010, an increase of years, network. In order to reduce
approximately 200%. leakage the Water Board applied a
program of Active Leakage Control
Of course, in addition to the reported commencing with Districts with the
breaks, there were a significant number highest increase in the equivalent
of breaks, caused by the frequent number of pipe bursts.
emptying and refilling of the network,
which did not come to the surface since Furthermore numerous complaints were
the network was not pressurised for any received from disgruntled consumers
significant length of time to force the regarding quality problems and of
water to come to the surface or to have course lack of pressure during
the opportunity to locate these through intermittent supply. Needless to say that
active leakage control. intermittent supply caused serious
disruption and upheaval to the daily
Calculations have shown that the activities of people whether these were
increase in leakage due to the at home or at work.
intermittent supply measures was of the
order of 9%. This figure was Cost of Intermittent Supply
substantiated in an analysis using a top
down and bottom up approach for The implementation of intermittent
2007, before the intermittent supply was supply had a direct financial cost to the
applied, and for 2010, the first year Water Board. On the one hand the
immediately after the measures were Water Board suffered loss of revenue
lifted. This result is shown graphically in due to the decrease in the sales of
Figure 1 where it can clearly be seen water. On the other hand there were
that the difference in the Minimum Night additional expenses paid to staff in
Flow in 2010 and 2007 is the additional overtime for opening and closing the
volume of water being lost due to new sluice valves to implement water
breaks caused by the intermittent supply rationing and to repair breaks caused to
operation. It is calculated that this the pipe work due to the frequent
additional volume is approximately emptying and filling of the pipes.

5
The Board estimated that the average
loss of revenue per annum due to the
reduction in water sales was of the order
of 300.000 and the additional
expenses paid as overtime to staff and
the cost of pipe work repairs was of the
order of 100.000.

Conclusions

It is evident from the results presented


in this paper that although intermittent
water supply may seem to be a solution
to a water shortage situation in overall
terms the water balance is adversely
affected. Supplying less quantity in an
intermittent manner causes such
deterioration to the network that when
continuous supply is re-established
additional quantities are lost through
increased leakage.

It is therefore prudent to avoid such


operational conditions for the pipeline
networks especially for networks that
have been designed for continuous
supply.

Acknowledgment

The author wishes to thank the


management and executive board of the
Water Board of Lemesos for their
continuous help and support in applying
innovative technologies and strategies
in a continuous effort to reduce and
maintain Non Revenue Water at
acceptable levels.

References

Charalambous B., 2007. Effective Pressure


Management of District Metered Areas.
Water Loss 2007 Conference Proceedings,
23-26 September, Bucharest, Romania,
Volume I, pp 241-255.
Charalambous B., 2009. Water Crisis Bridging
the Gap. Water Loss 2009 Conference
Proceedings, 26-30 April, Cape Town,
South Africa, pp 241 246.

6
Figure1. Minimum Night Flow Graph for all reservoirs

Figure2. Minimum Night Flow Graph for DMA 129

You might also like