You are on page 1of 11

Labour Productivity in the building industry

Henry Alinaitwe, Research Student, Makerere University, Uganda & Lund University, Sweden

Jackson Mwakali, Associate Professor, Makerere University, Uganda

Bengt Hansson, Professor, Lund University, Sweden

Abstract

The cost of labour in the building industry is in the region of 25 - 40 % of the cost of building.
Hence the cost of labour is quite high and yet it is the main cause of variability in construction
costs. The time used by workers on daily basis on productive activities averages about 30% of
the total time available for construction work. The remainder of the time, i.e. about 70% is
wasted on non-productive activities, delays and added activities. For a company in the building
industry to remain competitive, it must try to improve the productivity of its labour. This paper
reviews the literature on labour productivity in the building industry. It looks at the definitions,
measurement, use, factors affecting and theories on improvement of labour productivity in the
building industry. It is noted in the industry lacks generally agreed strategies for improvement of
labour productivity. The paper further reviews the paradigms of innovation, benchmarking, and
industrialization among the theories aimed at improving the productivity of labour in the building
industry.

Key words: Labour Productivity, Building Industry.

1. Introduction

1.1 Background

The construction sector has a strategic role in all developing and developed countries. The
construction industry is the single largest industrial employer in Europe employing more than 7%
of the labor force (Proverbs, Holt and Olomolaiye[1]). According to Ugandas Ministry of
Finance in Uganda [2], the construction industry contributes 12% of the Gross Domestic Product
(GDP) and employs 5% of the registered workforce in Uganda.

210
In most developing countries, labor-intensive production is still in use in the construction sector
and this situation will remain for a couple of years to come.

According to Buchan, Fleming and Kelly [3], Zakeri, et al [4] and Kaming et al [5], Gilleard J.
[6] labor cost is somewhere between 20% and 50% of the total project cost. Hence the reduction
of labor and therefore construction costs can be best carried out by labor productivity
improvement. Productivity is the key to greater competitiveness, as it is critical to the
profitability of most construction projects.

The time used by workers on daily basis on productive work averages about 30% of the total
time available for construction work (Jenkins, [7]). At the same time, low productivity has led to
high labour costs in comparison to the construction costs.

As pointed out by Yates and Guhathakurta [8], labor productivity is becoming an increasingly
important topic to members of the construction industry. The problem of low and decreasing
labour productivity appears in many other countries. For example, Teicholz [9] found out that
labour productivity in the United States has continued to slowly decline (with a few exceptions)
over the past 25 30 years. The important topic addressed in the Emerson report (1962), the
Latham report [10] and the Egan report [11] is the issue of productivity in the construction
industry.

1.2 Definitions

Different people have been using the word productivity to mean different things. Productivity is
defined by Calvert el at [12] as the ratio of outputs to inputs. Labour productivity is one of the
partial factors of productivity. It has been defined as the ratio of the total output to the labor
input (Gilleard, [6]). Noor ([13]) defines it by the following equation

unit.output
Labour . productivity =
labour.manhours

The determination of output is a relatively simple task, as they can be physically measured. As
pointed out by Noor [13], the determination of labour workhours associated with measured
output is a more contentious issue because it can be a measure of different input times. Different
measurements of input times will give rise to different productivity measurements.

Labour productivity measured in terms of the paid time provides useful information to
contractors for scheduling and estimating purposes on future projects. On the other hand, labour
productivity measurements based on time available for work help to provide the basis for
analyzing the effects of adverse weather conditions on labour productivity. Labour productivity

211
measures that are based on productive time help in determining the effect of various factors on
productivity such as constructability and delays due to lack of materials and equipment.

The measurement of output suffers from the non-standardization of the construction industry.
For example, even concreting which can be measured in cubic meters has several factors
influencing its productive time. The quantification of quality and increased use of prefabrication
complicates the quantification of labor inputs also. There is need for the industry to agree on the
way to measure the inputs.

2. Use of labour productivity

Productivity is one of the key measures of construction performance. Latham [10] and Egan [11]
clearly addressed the importance of raising productivity in the construction industry in UK. The
studies and the recommendations made for the UK construction industry are relevant worldwide.
It was observed by Kaming and Olomolaiye [14] that poor productivity of construction
craftsmen is one of the most daunting human resource problems in developing countries.

As pointed out by Kaming et al [5], the success of a construction company in todays


competitive environment largely depends on accurate estimation of productivity.

Labour productivity rates are used as indicators of the construction time performance. They are
used in planning and scheduling of construction, controlling of the cost and worker performance,
estimating and accounting.

If a company wishes to reduce risk, increase profits, or gain market share, there is direct need
within the firm to have accuracy data on and use of labor productivity (Gilleard [6]).

Although studies have been made in a number of countries, most of the data available is not
directly relevant to all countries because of the differences in materials used, techniques
employed and working environment. Construction workers too have differences in the work
culture.

3. Methods of obtaining labour productivity

Before productivity can be increased, there is need to measure and quantify the existing situation.
Lord Kelvins dictum to know properly you must measure itis sound advice to anybody
interested in measuring productivity. The measure of construction productivity is thus a very
important issue.

212
There are two different methods of generating data on productivity accountancy based and
engineering based methods.

Accountancy based standards rely on the analysis of historical accounting data to establish work-
hour requirements for specific types of work. Engineering based standards involve breaking
down complex work processes into small manageable parts and analyzing these parts for the
length of time required to complete these processes. The accountancy-based data are relatively
easy to follow but they do not capture the varying working conditions.

The engineering methods of measuring labor productivity include work measurement, work
sampling, time and motion analysis, and modeling.

Work measurement is the determination of the time required for an average operative to carry out
a particular task in accordance with a specified method and standard of performance (Calvert,
[12]). Work sampling involves observing individual pieces of the work process and classifying
the results as either productive or non-productive. It is useful for recording productivity levels
for comparative purposes. Harris and McCaffer [15]) describe its use. Thomas [16] roundly
condemned activity sampling as being unsuitable for measuring productivity in construction
activities.

Time and motion studies are said to be the most accurate methods for generating productivity
standards. Factor based modeling is arguably the most applicable engineering-based technique to
the construction industry and has the potential to produce useful data. The factor model
technique has been recommended by a number of authors (Gilleard, [6]) although it is yet to be
accepted internationally.

4. Factors affecting labour productivity

Factors influencing productivity of construction workers in many countries have been explored
(Borcheding, [17]). Gilleard [6] acknowledges that labor productivity figures are highly variable,
affected by such factors as the mode of employment, overall task duration, and length of the
workday.

Identifying and evaluating the factors that influence productivity are critical issues faced by
construction managers (Motwani et al [18]).

Most of these factors have been arrived at my asking the workmen directly and the project
managers. Borcherding [19] recognized that the best means of acquiring information about
production problems is by asking the workmen themselves.

213
The common factors influencing construction productivity have been listed by Yates and
Guhathakurta [8], Keone [20].

According to Keohn [20], productivity is related in part to the following variables: management
(proper planning, realistic scheduling, adequate coordination, and suitable control); labour (union
agreements, restrictive work practices, absenteeism, turnover, delays, availability, level of skilled
artisans, and the use of equipment); government (regulations, social characteristics,
environmental rules, climate and political ramifications); contracts (fixed price, unit cost, and
cost plus fixed fee); owner characteristics; and financing.

The factors affecting labour productivity can be summarized under the categories of design,
manpower, management, environment, and others.

Design issues including: design complexity, design changes, and quality.

Manpower issues including: worker motivation, skills of the workers, recruitment of workers,
recruitment of supervisors, absenteeism, labour turnover, communication problems, labour
disruptions, alcoholism, stoppages because of work being rejected by consultants, stoppages
because of disputes with owners/consultants, stoppages because of insolvency, labor
composition, overcrowding.

Management issues including: material shortages, delays in materials delivered to site, disruption
of power/water services, stop-work orders because of accidents, site congestion, site
layout/access, construction method.

Environment including harsh working conditions and others including construction volume,
regulatory requirements, economic conditions, social factors

According to Burton [21], companies should only track the important activities. Rosefielde and
Mills [22] argued that any measure of construction productivity that does not account for the
changes in design and quality would lead to low, if not negative, measures of construction
productivity.

5. Current theories for improvement of labour


productivity

The current thinking that will improve construction productivity hinges on the theories of
innovation and knowledge transfer, benchmarking and industrialization. Motwani, Kumar and

214
Novakoski [18] however pointed out that theories of improving productivity vary from business
to business and because of the variety of uncontrollable productivity influence factors it is hard
to have one plan.

5.1 Innovation

The performance of the construction industry in terms of productivity, quality and product
functionality has been low in comparison to other industries, and a low rate of innovation has
been provided as the major explanation to this situation (Winch [23], Gann [24]). As stated by
Winch [25], construction is commonly characterized as a backward industry, one that fails to
innovate in comparison to other sectors. While the other sectors modernized through the
introduction of interchangeable parts, then assembly lines, and then automation, construction
retained its craft method of operation and fell further and further behind the rest of the
manufacturing industry in terms of productivity, quality and hence value for money.

Innovation is a process of gaining and using new and existing knowledge to enhance either a
product or process (Dodgson and Bessant [26]). Freeman [27] defines innovation as the actual
use of a nontrivial change and improvement in a process, product or system that is novel to the
institution developing the change. Innovation as defined by Barret and Sexton [28] is the
effective generation and implementation of a new idea which enhances overall organizational
performance. The main factors for innovation include: reward for innovation; opportunity for
innovators to communicate their knowledge directly by presentation of events; funding and
support the industry Research and Development (R&D). The adaptation of new procurement
methods and the new organizational structures are seen to improve the ability to provide more
integrated and innovative solutions.

The industry requires radical changes if improvements in quality, productivity and performance
are to be achieved. The construction industry is increasingly being challenged to successfully
innovate in order to satisfy better aspirations and needs of society and clients, and improve
competitiveness (Latham[10] and Egan [11]).

As pointed out by Motwani, Kumar and Novakoski [18], improving communication skills,
preplanning and stricter management could help to raise the individual productivity rate from an
average of 32 per cent productive time per hour to almost 60 per cent per hour.

It is important that the Construction Industry adopts TQM if it is to improve productivity since
TQM is about changing attitude and skills so that the culture of the organization becomes one of
preventing failure and doing things right first time all the time (ISO [29]).

215
A framework for improvement of productivity would address innovation of remedial measures
such as recruiting and training a younger generation to have necessary skills, process
improvement, standardization, and transfer of knowledge within the industry. The focus should
be on continuous upgrading the management and technical skills of supervisory staff.

Barret and Sexton [28] acknowledge that although construction firms have always demonstrated
an ability to innovate, construction practioners are now very much getting to grips with the need
for and management of innovation as an explicit endeavor.

5.2 Benchmarking

Before productivity can be increased, there is need to measure and quantify the existing situation.
The point made is that a construction company should have a measurement procedure in place
such that it can determine how it is doing relative to the benchmark. As pointed out by Adrian
[30], by measuring the companys performance relative to the benchmark and by implementing
improved processes and procedures, the construction industry can work towards improvement.

Benchmarking is the search for the best practices that will lead to superior performance of an
organization (Camp [31]). Houston in a document titled Planning, Organizing and Managing
Benchmarking: Users Guide, defines benchmarking as a systematic and continuous measurement
process of 1992; a process of continuously measuring and comparing an organizations business
process against business leaders any where in the world to gain information which will help the
organization to take action to improve its performance.

As early as in the 1800s, Fredrick Taylors work on the application of the scientific method of
business had encouraged the comparison of work processes. This was within the concept of
benchmarking.

As Lema and Price [32] point out, there is need to explore the potentials of benchmarking for
performance improvement in the construction industry. The construction industry can learn from
the wealth of experiences available throughout the manufacturing industry. A common
understanding of benchmarking has to be reached, and a conceptual framework that would cater
for the industrys primary objectives at various levels has to be developed.

Lema and Price [32] point out that benchmarking is seen as a perfect vehicle to ensure that the
customer gets the best quality under competitive conditions that ensure lowest prices. The three
key roles of benchmarking are: to widen the competition base by exposing internal organizational
processes to external market forces; accelerate the TQM process and therefore increase
efficiency by providing the opportunity to learn from others, adopt and improve; and act as a tool

216
for cooperation to improve overall industry performance. The preconditions for successful
applications include: the need for performance improvement; the recognition and acceptance that
there are lessons to be drawn from others that can lead to improved performance; the willingness
and capability to change for better performance; and the accessibility to the best practices. The
problem with the construction industry is the lack of initiative to make full use of benchmarking
to create change.

5.3 Industrialization of construction

Increasing heavy demands for the products of the building industry were made in the years
following the end of the Second World War during the reconstruction programmes. Since the
Second World War, the world population has more than doubled. Currently, the demand on
housing is very high and the number of homeless people has been growing. There is also a big
number of huge construction projects, which are being undertaken notably in Eastern Asia and
China. While the increase in demand of construction products is happening, there is growing
shortage of skilled manpower. Shortage of manpower is unlikely to improve to any significant
extent (Foster [33]).

Industrialization of construction is needed to increase the productivity of the industry generally


while at the same time reducing the amount of site labour involved. Industrialization involves the
rationalization of the whole process of building (which includes the process of design, the forms
of construction used and the methods of building adopted).

Foster [33] defines industrialization as essentially an organizational process continuity of


production implying a steady flow of demand; standardization; integration of the different stages
of the whole production process; a high degree of organization of work; mechanization to replace
human labour wherever possible; research and organized experimentation integrated with
production.

There is need to industrial all sectors of the construction industry if we are to satisfy the current
demands. Ideally housing would be easier to provide for using industrialization in construction
because most of the spaces and products can be standardized as exemplified by the precast
concrete box units (Hansson [34]). Variations would only cater for special cases. The industry
requires radical changes if improvements in quality, productivity and performance are to be
achieved (Latham[10] and Egan[11]). Currently the industry is fragmented and has many
stakeholders who are not well coordinated. Product and process industrialization would help to
improve the situation.

Since the second world war, the idea of industrialization has received much attention both in
Europe, North America and elsewhere. However, in spite of a great number of attempts, there
has been a relative lack of success of industrialized building methods (Warzawski [35]). The

217
share of prefabricated components has risen, and there are examples of advanced
industrialization, notably the Japanese house producers (Gann [24]) and the American metal
building providers (Ellifritt and LaBoude[36]) but a wider breakthrough for industrialized
construction has still not occurred. According to Warzawski, the main problem of prefabrication
of today in the lack of a system approach to its deployment on the part of the various parties
involved.

The building construction industry still lacks in being rational. This is manifested by poor labour
productivity due to lack of integration of design, poor supply chain management, on site
fabrication and assembly with many inefficient processes.

6. Conclusions

It is has been noted that the industry lacks generally agreed ways of measuring and strategies for
improvement of labour productivity.

It can be concluded that there are many factors that affect labour productivity and their
effects vary from one industry to another. There is need to quantify the effects that those
factors have on labour productivity so that remedial measures are sought. Although a
few have been explored in specific industries, there are still many gaps to be filled in this
area.

Although the literature indicates that the theories on innovation and knowledge transfer,
benchmarking, industrialization in construction can be used to improve on labour productivity,
there is still need to develop strategies on how they can be used. There are gaps on the relevance
and application of the theories to improve labour productivity.

Acknowledgement

The support given by Sida/SAREC in producing this paper is acknowledged with great pleasure.

References
1. Proverbs D. G., Holt G. D., Olomolaiye P. O., (1999). The management of labor on high
rise construction projects: an international investigation. International Journal of Project
Management.
2. Ministry of Finance, (2004). Background to the budget 2004 - 2005. Government of
Uganda.

218
3. Buchan R. D., Fleming F. W., Kelly J. R., (1993), Estimating for builders and quantity
surveyors, Oxford: Butter worth-Heinemann.
4. Zakeri M., Olomolaiye P.O., Holt G. D., Harris F. C., Factors affecting the motivation of
Iranian construction operatives. Building and Environment 1997; 32: 161-6.
5. Kaming P.F., Olomolaiye P. O., Holt G. D., Harris F. C., What motivates construction
craftsmen in developing countries? A case study of Indonesia. Building and Environment
1998; 33: 131 141.
6. Gilleard J. D. (1992), The creation and use of labor productivity standards among specialist
subcontractors in the construction industry, Cost Engineering, 34, 4 pp 11-16
7. Jenkins, J. L. (2003). Productivity improvement through work sampling. AACE
International Transactions, CSC.05.
8. Yates J. K. and Guhathakurta S. (1993), International labor productivity, Cost Engineering,
35, 1pp 15
9. Teicholz [5] Teicholz, P. (2001). Discussion: US construction labour productivity trends,
1970 1998. Journal of construction engineering and management ASCE, 113(4), 626
644.
10. Latham, M. (1994), Constructing the team. HMSO, London
11. Egan, J. Sir (1998). Rethinking construction, Construction Task Force report, Department
of the Environment, Transport and the Regions. London.
12. Calvert R. E., Coles D. C. H, and Bailey G. J. (1995), Introduction to Building
Management, 6th ed.
13. Noor I. (1998). Measuring construction labour productivity by daily visits. AACE
International Transactions. Pg 16.
14. Kaming P. F. and Olomolaiye P. O. (1997), Factors influencing craftsmen productivity in
IndonesiaInternational Journal of Project Management, 15, no. 1, pp 21-30
15. Frank H. and McCaffer R. (1983). Modern Construction Management. 2nd ed. Collins
16. Thomas, H. R., Labour productivity and work sampling: the bottom lineJournal of
Construction Engineering and Management ASCE 113 (1991) 623 639
17. Borcherding, J. D., (1975) Effective utilization of Manpower in Construction, National
Electrical ContractorsAssociation Inc., Washington, DC
18. Motwani J., Kumar A., Novakoski M. (1995). Measuring construction productivity: a
practical approach. Work Study, Vol. 44 No. 8, pp 18 20.
19. Borcherding J. D. (1977). What is the construction foreman really like? Journal of the ASCE
(Construction Division), USA.
20. Kheon, E. and Brown G., (1986). International labor productivity factors. Journal of
construction engineering and management, Vol. 112, No. 2, pp 299 302
21. Burton, F. A methodology for measuring construction productivity, American Association
of Cost Engineers Transactions, 1991, pp L3 (1) L4 (4).
22. Rosefielde, S., and Quinn Mills, D. (1979). Is construction technologically stagnant?The
Construction Industry: balance wheel of the economy, J. Lange and D. Mills, eds., Lexington
Books, Lexington, Mass.
23. Winch, G. (1998). Zephyrs of creative destruction: understanding the management of
innovation in construction. Building Research and Information, 26(4), 268-79
24. Gann, D. (2000). Building innovation: Complex Constructs in a changing world. Thomas
Telford, London.
25. Winch, G. M. (2003). How innovative is construction? Comparing aggregated data on
construction innovation and other sectors a case of apples and pears. Construction
Management and Economics, 21, 651 654.
26. Dodgson, M. and Bessant, J. (1996). Effective innovation policy: A new approach, London,
ITP London.

219
27. Freeman, C. (1989). The Economics of Industrial Innovation. MIT Press. Cambridge.
28. Barret, P and Sexton, M. (2003). Appropriate innovation in small construction firms.
Construction management and economics, 21, 623 633.
29. ISO 9000 International Standards Organization
30. Adrian J. J., Benchmarking and risk analysis: Keys to increasing construction productivity,
Construction accounting and Taxation; Jul/Aug 2003, 13, pp 4.
31. Camp, R. C. (1989). Benchmarking: The Search for the industry Best Practice that lead to
superior performance, Quality Press.
32. Lema, N. M. and Price, A. D. F. (1996). Benchmarking: Performance Improvement Concept
towards competitive advantage. Loughborough University, UK.
33. Foster (2000). Foster J. S. (2000). Structure and Fabric, part I. Pg. 10. Longman. 5th ed.
34. Hansson B. (1995). Precast concrete box units Production analysis. Department of
Construction Management, School of Civil Engineering, Lund University.
35. Warzawski, A. (1990). Industrialization and robotics in building: a managerial approach.
Haper and Row, New York.
36. Ellifritt, D. and LaBoude, R. (1993). Building systems. Thin walled structures, 16(1-4), 263
74.

220

You might also like