You are on page 1of 6

DRILLING

Drilling hazard management: Excellent


performance begins with planning
Part 1 of 3: Misalignment of well objectives can complicate mitigation
efforts and induce drilling hazards by limiting the ability to apply
adequate hydraulic horsepower and to manage ECD.
David Pritchard, Successful Energy Practices International;
Patrick L. York, Scott Beattie and Don Hannegan, Weatherford

A drilling hazard is defined as any mitigants successfully. Because hazards weight at the base of an intermediate
event off the critical path of drilling may include mechanical failure and hu- casing string before drilling out the
operations. Drilling hazard manage- man error in addition to geology, under- shoe, especially in high-pressure/high-
ment focuses on wellbore stability and standing the totality of drilling data is temperature operations, Fig. 1. Mud
consequential hazards such as stuck necessary to avoid inducing risks and to is usually weighted up because higher
pipe, fluids loss and equivalent circulat- enable implementation of the most ap- pressures are anticipated at greater
ing density (ECD) management. These plicable mitigation measures. depths, but this practice actually masks
events lead to non-productive drilling One such example of DHM is simply drilling conditions and negatively im-
time in the least case, or catastrophic to apply casing seat optimization to the pacts drilling performance by increas-
wellbore failure and loss of well control maximum uncertainties of the drilling ing the confining stress of the mud
in the worst cases. Drilling hazard man- margin predictions. Predictions are al- weight column. This increase also cre-
agement requires understanding the un- ways uncertain in the Earth model, but ates unnecessary bit wear, resulting in
certainty of the drilling margin: i.e., the a well can be planned accordingly. Plac- premature trips with associated swab
safe applied ECD between the in situ ing the seat at the maximum safe ECD and surge that further impact wellbore
pore pressure and/or stress equivalence point of the overburden fracture gradient stability. This practice is often defended
and the fracture gradient as a result of ensures that the next hole section can be as the safest approach, but in reality, a
the overburden. drilled to maximum depth and reduces safer and more effective action would
Complex wells require multidisci- the risk of issues such as ballooning in be to drill out the casing shoe with the
plinary alignment to ensure and sus- the next interval. same mud weight as was used to set the
tain performance. Aligning objectives Another example involves the prac- casing. This should be followed with
is necessary to manage drilling hazards tice of planning an increase in mud a full leak-off test to obtain the safest
and associated mechanical risk critical
to successful well execution. For exam-
ple, geological uncertainties may require 0
the ability to sidetrack a hole, yet a slim 2,000
monobore solution is required to reduce 1983 1985 2001 2007
drilling costs. These objectives usually 4,000
conflict. It is important to understand
6,000
disciplinary tradeoffs necessary to ensure
drilling performance. 8,000
TVD, ft

BASIC PRACTICES 10,000


Drilling hazard management (DHM) 12,000
is the practice of managing the me-
chanical and efficiency risk of all drill- 14,000
ing operations. (Within this article, we
16,000
will deal only with DHM related to the
risk of mechanical success, not risks as- 18,000
sociated with health, safety and the en-
vironment.) Managing these risks re- 20,000
0 8 10 12 14 16 18 20
quires applying the best practices and Mud weight, ppg
mitigating technologies to successfully
Fig. 1. Plotting mud weight versus vertical depth for four historical wells shows the
reduce the risk profile while improving evolution of mud weighting schemes from the 1980s to the present.
the risk-adjusted cost of applying such
World Oil AUGUST 2010 75
DRILLING

ECD that the next hole section can tol- This uncertainty can lead drillers to ex- MULTIDISCIPLINARY PLANNING
erate, and then drilling ahead, raising ceed the drilling margin, or the safe enve- Alignment of multidisciplinary ob-
mud weight as conditions dictate. lope that can be drilled without danger of jectives begins with a stage, gated well-
Another DHM example involves the well control events, fluid losses, balloon- planning process. The initial phase of
uncertainty of pore pressure prediction. ing or fracturing of the well. the process is where the well is formulat-

Table 1. Typical project objectives and alignment process where conflicts are obvious
Well objective Measure Key uncertainty Comments Conflicts Actions

HSE incident free Contractor and Rig availability Three rigs meet Timing for Investigate needed
toperator availability criteria, two best-metrics rig training and
HSE metrics have poor incident-free improvements
operations record on other rigs
Drill first quarter 2010 Lose concession Rig availability Must have at least Only Rig 2 has hhp Investigate needed
2,000 hydraulic hp requirements, no training and
(hhp) and backup zero-discharge improvements
pump for target section capabilities on other rigs
Authorization-for- Funding AFE Asset manager says Low-cost well Need to prioritize
expenditure (AFE) over $100 million is objectives
approval outside of budget
Low-cost well Top quartile in Well design Assets want simple, Completions engineers Need to prioritize
regional cost/well small-diameter monobore want gas lift and intelligent objectives
(metrics) to reduced cost completions
Ability to Dry hole Well design Small monobore will not Low-cost well Need to prioritize
sidetrack well at location accommodate sidetrack objectives
Production rates Production rate Well design Completion Small monobore will Will need to fracture
of 10,000 bopd production not accommodate well for max. rate,
rate targets minimum production rate small wellbore will not
accommodate hhp
Primary geological Intersect target Well pathfaults Tight well path requires Low-cost well Priorities drive
target: 12,000 ft TVD at optimum depth significant geosteering well cost
(cuttings beds and key
seats, high torque/drag)
Secondary geological Intersect target Well pathfaults Tight well path requires Low-cost well Priorities drive
target: 11,750 ft TVD at optimum depth significant geosteering well cost
Core secondary Successful core Target 2 depth Requires trips, Low-cost well Priority drives well
target for future impacts wellbore cost: What is the
evaluation stability, increases overall cost/benefits
success risk case for the well?
Run conventional Successful DP-conveyed logs Requires trips, Low-cost well Tradeoff is LWD: What
logs on drill pipe log evaluation impacts wellbore are the risk-adjusted
(DP) in extended stability, increases cost/benefits?
reach/horizontal success risk case
Time Requires trips, Low-cost well Tradeoff is LWD: What
impacts wellbore are the risk-adjusted
stability, increases cost/benefits?
success risk case
Wellbore Requires trips, Low-cost well Tradeoff is LWD: What
stability impacts wellbore are the risk-adjusted
stability, increases cost/benefits?
success risk case
Drill five additional Successful logs Production test Well path and Low-cost well Tradeoff is future
wells if successful on and production test footprint must and future development cost
same footprint consider future wells development
Ensure wellbore Achieving Drilling Could require Lost well Could require two
stability hole section margin/faults drilling with liner hole sections intermediate casing
strings (well cost)
Minimum unscheduled Drilling Could require Low-cost well and Requires real-time
events (hazards: margin/faults drilling with liner sidetrack capability monitoring and
ballooning, susceptible contingency plans
shales) and NPT
Ensure top-quartile Improved critical-path Rock Requires compiling Geologists wont Develop a plan for
rotating performance time (metrics) geomechanics geomechanics log release logs rock log that ensures
on prior well confidentiality
No formation Productivity index Formation Reservoir engineer requires Low-cost well, impedes Align fluids with
damage sensitivity oil-based mud logging evaluation, and no geoscientitists; under-
rigs have zero-discharge stand costs/benefits
capabilities of requirements
Overall well plan: appraisal well12,000 ft TVD, 20,000 ft MD; extended reach horizontal wellsurface, intermediate casing at 10,000 ft TVD for stability, productivity to TVD; section 1surface,
section 2intermediate, section 3production.

76 AUGUST 2010 World Oil


DRILLING

ed and objectives are determined. Well Misalignment of objectives can compli-


objectives should be specific, measur- cate mitigation efforts and often results
able, achievable, relevant and timely. in inducing drilling hazards by limiting
Often the root cause of failure lies with the ability to apply adequate hydraulic
objectives that are not initially aligned horsepower and to manage ECD.
and understood by the disciplines or
stakeholders. Well planners must guard ALIGNING OBJECTIVES
against developing objectives that are not Developing specific, measurable,
measurable, often conflict, and are not achievable, relevant and timely objectives
mutually achievable. The following ob- requires alignment from all stakeholder
jectives for a 12,000-ft TVD, 15,000-ft disciplines to determine which well design
MD directional well do not follow the alternatives can best be accomplished.
well objective criteria listed above: This multidisciplinary process requires
Right-size initial flow capabilities understanding the tradeoffs, conflicts and
Adequate hole size for evaluation, compromises that are necessary between
coring and completion the nice-to-haves, wants, needs and
Completions free of formation must haves. Prioritizing objectives is the
damage first step of a process to ensure initial dis-
Rigless intervention capabilities ciplinary alignment.
Minimal complexity Mapping a process to define ranges
Directional well with a target on- of measures for the objectives is the ini-
bottom radius of 200 ft tial step in the process. This process is
Multiple targets facilitated by capturing the ideas and
Design life committing to an auditable trail to en-
Good reservoir surveillance sure decision quality. Table 1 shows an
Provision for a future sidetrack objective alignment process where all
Minimal number of casing strings the objectives meet the above criteria.
Small, low-cost monobore Further qualification and quantifica-
Optimization of costs tion of the objectives are required, with
Ability to frac stimulate the well the desired outcome being a prioritized
ESP artificial lift system. list of objectives, after which the design
For example, a small wellbore does process begins. DHM cannot occur
not lend itself to fracture stimulation, until, at a minimum, objectives are pri-
has limited if any automated reservoir oritized, which leads to alternative well
surveillance capabilities, and has limited design considerations.
sidetrack capabilities. Furthermore, the Failure to align objectives at the onset
number of casings necessary to reach of well planning usually results in execu-
TD may prevent fracturing, high initial tion issues that are counterproductive to
production rates and optimum installa- good performance and sustained learn-
tion of artificial lift systems. Maintain- ing. As an example, excessive geosteering
ing a stable wellbore becomes especially can complicate the well path and actually
challenging in directional sections with create drilling hazards. Target boxes must
small hole size, which prevents the drill- be agreed on in the initial well planning
er from applying enough horsepower to stages and ensured during execution. A
clean the hole. A small hole also com- target box is a window around the en-
plicates the ability to slide and achieve a tire directional section that limits or pre-
smooth hole. scribes the limits of geosteering.
These design objectives induce Although a large amount of geosteer-
wellbore stability issues and can impact ing may be agreed to by the stakeholders,
the following issues: there is a tradeoff in the risk of successful
Poor drilling performance as a re- execution and, at the minimum, a nega-
sult of reduced hydraulic pumping rates tive impact on performance and well
Bit wear cost. Many things can change, such as
Bottomhole steering difficulties, the design of the bit and BHA. Multiple
with excessive geosteering creating a tor- BHA and bit combinations are necessary
tuous well path to achieve this objective, requiring trips
Inability to apply mud weight and and inducing wellbore instability. All
effectively manage ECD in a slimhole of these tradeoffs must be understood,
environment. quantified and risk-assessed to ensure
The objectives listed above for this multidisciplinary alignment and ulti-
well result in many conflicts too dif- mate decision quality.
ficult to manage, and thus cannot suc- Examples such as this are also where
cessfully be achieved in the same well. total well engineering comes into play,
World Oil AUGUST 2010 79
DRILLING

as opposed to widget engineering be eliminated by way of decisions, or ning phases, the key to narrowing the
engineering a single product or service if at least their range can be narrowed. drilling margins range of uncertainty is to
that does not consider the total well and Eliminating or narrowing uncertain- ensure that predictions are as reliable as
its objectives. A bit designed for a build- ties is a multidisciplinary process. De- possible and are adjusted with actual his-
and-hold angle does not work well when cisions to eliminate uncertainties can torical data, such as the mud weight that
geosteering is required, nor does a tight include the rig selection process, post- was applied in a well where fluid losses
or locked assembly to ensure holding ing a locked basis of design or deciding actually occurred. There are many other
angle, even with adjustable stabilization. bottomhole targets and locking them techniques that can be used, including
These individual widget engineering into the well path. improving predictions while drilling,
designs are in conflict. The uncertainties that create the most such as D exponents (drilling exponents
problems and ancillary risks relate to the normally compiled in mud logs).
IMPACT OF UNCERTAINTIES drilling margin. At the onset, establishing For the planning phase, once the pre-
Uncertainties drive risk in everything. the safe drilling margin is an unknown dictions are as accurate as possible, alter-
For example, the weather is an uncer- prediction of pore pressure and fracture native models can be developed that deal
tainty. If the objective is to play golf, the gradient. While predictions may come with the well objectives and uncertainties,
more that is known about the forecast, from many sources, they are never abso- and then manage the risk or hazard.
the more narrow the range of uncer- lute. If the plan is to nail predictions to The first step toward managing haz-
tainty. The same philosophy applies to ensure good drilling performance, then ards and risk, then, is to narrow the
managing hazards and risk for any drill- success will not be sustained. range of drilling uncertainties by devel-
ing and completion operation. Risk occurs at the boundaries of the oping a multidisciplinary uncertainty
It is first necessary to understand how margin. For example, if the ECD is too management plan. This plan should
uncertainties impact risk. Uncertainties high, fluid losses with varying conse- be developed in concert with specific,
represent the unknowns in any drilling quences can occur. If the mud weight measurable, achievable, relevant and
operation. An important aspect of un- is too low, well control can be lost, also timely objectives in the initial concept
certainties is to know whether they can with varying consequences. In the plan- phase of planning.

Table 2. Developing an uncertainty management plan for the well models in Fig. 2
Objective Uncertainty Model 1 Model 2 Model 3 Model 4 Conflicts, comments,
requirements

Low cost (less Requires Needs budgetary Least expensive; Moderately Most Further engineering to
than $5 million) budgetary cost estimates, this smaller casings expensive, but expensive determine casing sizes
estimates model being the most size of casing needed to meet cost goals,
for all models cost effective, but may prohibit lift hazards management
limits depth of artificial capabilities and lift requirements
lift (gas lift mandrels)

Target 2 pore Pore pressure This model does not This model does not Allows for Allows for This known hazard requires
pressure in open hole in allow for any casing allow for any casing isolation isolation further engineering; consider
Target 2 contingency of the contingency of the of Target 1 of Target 1 designing for maximum
margin, which margin and cannot while drilling while drilling casing sizes, but if the
will be very difficult be managed while Target 2 Target 2 Target 2 reservoir pressure
to manage while drilling deeper is not as depleted as
drilling deeper suspected, it could be
possible to drill without the
liner; design must
accommodate this hazard

Rig schedule Rig may not Evaluate all models for


have enough maximum hookload and
hp to execute optimum hole cleaning
this hole sec- rates for the given BHAs
tion (hole and fluid systems
cleaning and
hookload)

Target 1 Casing might Casing might not Casing might This model All models should be evaluated
production of not be large be large enough to not be large should provide for rate capabilities
05,000 bopd enough to provide provide production enough to pro- for rate criteria
production rate rate criteria vide production and hazard
criteria rate criteria management

Remaining in Geosteering; Slim hole will com- Hole cleaning capabilities


target box for hole cleaning plicate hole cleaning should be evaluated
Target 1 hydraulics and ability for all models to avoid
to geosteer inducing hazards

Gas lift at 8,000 Casing sizes Improves lift Improves lift Lift capacity should be
ft TVD (min.) need to be capabilities; capabilities; evaluated for each casing size
to 9,000 ft TVD evaluated deeper and deeper and and the deeper capabilities of
(max. for max. large casing large casing Models 3 and 4
drawdown)

80 AUGUST 2010 World Oil


DRILLING

Consider the objectives listed in


Table 2 for a hypothetical well, which Model 1
conform to the requirement of being Surface casing: 958-in. set at 3,000 ft TVD/MD
specific, measurable, achievable, relevant
and timely. For these objectives, the key Intermediate casing: 7-in. set at 9,000 ft TVD/MD
uncertainties are the cost of well to best Kickoff point (KOP): 9,500 ft TVD/MD
Buildup rate (BUR): 3/100 ft
accomplish them; the production rate Target 2: Est. 11,00011,250 ft TVD long radius
range and the productivity index of the
reservoir; drilling hazards such as fluids Target 1: Est. 11,75012,000 ft TVD Production string: 5-in.
losses and stuck pipe; the height and (17,000 ft MD) to surface
thickness of the Target 1 reservoir; and
the ability to geosteer within the tight Model 2
target box. The last two uncertainties Surface casing: 7-in. set at 3,000 ft TVD/MD
dictate alternative well models.
Table 2 illustrates how these uncer- Intermediate casing: 5-in. set at 8,500 ft TVD/MD
tainties can impact the models (Fig. 2) KOP: 8,550 ft TVD/MD
and the resolutions required to deter- Target 2: Est. 11,00011,250 ft TVD
mine the best-fit model for the final well Tangent section for
design. The design of any well alterna- gas lift beginning at Target 1: Est. 11,75012,000 ft TVD Production string: 4-in.
9,000 ft TVD (17,000 ft MD)
tive begins with the recognition that to surface
the uncertainties of the drilling mar- Model 3
gin must be honored. Each casing seat
Surface casing: 958-in. set at 3,000 ft TVD/MD
must address the maximum force it can
exert against the fracture gradient with Intermediate casing: 7-in. set at 8,500 ft TVD/MD
safe tolerance at its vertical depth of de- KOP: 8,550 ft TVD/MD
Target 2: Est. 11,00011,250 ft TVD
ployment. The summation of the forces Tangent section for
must balance; that is, the force of the ap- gas lift beginning at
9,000 ft TVD Target 1: Est. 11,75012,000 ft TVD Production string: 5-in.
plied ECD must equal the force exerted (17,000 ft MD) to surface
by the overburden fracture gradient of
the earth in the wellbore. Model 4
Ignoring force balance when setting Surface casing: 1358-in. set at 3,000 ft TVD/MD
casing will result in a casing seat that is
not at optimum depth and that, there- Intermediate casing: 11 in. set at 8,500 ft TVD/MD
fore, will not facilitate an optimum
KOP: 8,550 ft TVD/MD
depth for drilling the next hole section. 958-in. liner Target 2: Est. 11,00011,250 ft TVD
This deficit continues to compound
with each successive casing seat. This Tangent section for
gas lift beginning at Production string: 7-in.
is especially critical in narrow-margin 9,000 ft TVD
Target 1: Est. 11,75012,000 ft TVD
(17,000 ft MD) to surface
drilling operations, especially in HPHT
and deepwater environments. In the lat- Fig. 2. Example well models for the objectives listed in Table 2
ter, the loss of overburden due to water
depth plays a critical role in the top hole
sections of the well. Seafloor
Figure 3 depicts the optimum place- 3,500
ment of casing seats that are normally Fracture gradient
4,000 Leak-off for String 2 Pore pressure mid-supra salt
inserted to the top of salt in a subsalt
deepwater environment. Applying this
methodology enables the optimum 4,500
TVD (below kelly bushing), ft

depth of each casing string, minimizing


the number of casing strings required to 5,000 String 1 design
casing seat
complete the well. Managing the uncer-
tainty of the drilling margin minimizes 5,500
the occurrence of boundary risks and
6,000 String 2 design casing seat
should be an initial principle of well plan-
ning and drilling hazard management.
6,500 Top of salt ~ 6,700 ft
Figure 4 shows the stacking effect
created by the failure to optimize cas-
7,000
ing seats in the deepwater environment. Source: US patent
It also indicates where the casing seats 7,500
application 12635511
should be to optimize the uncertainties 8 9 10 11 12 13 14
of the drilling margin. Pressure/fluid densities, ppg
In narrow-drilling-margin opera- Fig. 3. Optimum casing seat placement in a subsalt deepwater environment.
tions, the challenge is to optimize casing
82 AUGUST 2010 World Oil
DRILLING

Seafloor
real-time data while drilling has in some
3,500 cases become a crutch for drillers, result-
Conventional String 1 Fracture gradient ing in misinterpretation of issues such as
4,000 Pore pressure mid-supra salt background gas, this technology can also
Optimum seat for String 1 assist in well listening and, thus, facilitate
4,500 correct decision making and application
TVD (below kelly bushing), ft

Conventional Shallow water of best practices. WO


5,000 String 2 flow predicted

Optimum seat for String 2


5,500 THE AUTHORS
David Pritchard is a pe-
Hydrocarbons predicted troleum engineer with 40
6,000 between String 3 and
Conventional String 3 years of industry experi-
top of salt
ence, including manage-
6,500 Top of salt ~ 6,700 ft ment and supervision of
worldwide drilling and
7,000 production operations.
Source: US patent He has consulted for an
Conventional String 4 application 12635511 array of national and in-
7,500
8 9 10 11 12 13 14 ternational independents,
Pressure/fluid densities, ppg major companies and service providers. He
has conducted technical audits and developed
Fig. 4. Stacking effect of non-optimized casing seat placement versus optimized well plans leading to improved well execution
placement in a subsalt deepwater environment. for complex and HPHT wells. As owner of Prit-
chard Engineering and Operating, Mr. Pritchard
developed, participated in and operated a num-
seats despite the fact that predictions of HPHT and deepwater environments. ber of oil and gas properties in the ArkLaTex re-
gion of the US, resulting in the successful dis-
the drilling margin boundaries (fracture One reliable predictor of stress is D covery of over 500 Bcf of natural gas reserves.
gradient on the high side, pore pressure exponent trends, which represent the He holds a BS degree in petroleum engineering
on the low side) are never accurate, due specific energy supplied to the drilling from the University of Tulsa.
to the complexity of the Earth model. string and to the bit as well as the total
Any particular casing string must be of dynamic drilling conditions. Pat York is the Director of Commercialization
and Marketing for Weatherfords Solid Expand-
designed for its depth as if predictions Casing optimization begins with the ables and Drilling Hazard Mitigation product/
are absolute, and casing specifications design and ends with understanding service lines. He has 38 years of oil and gas
must have a design tolerance to drill and and properly interpreting actual drilling industry experience. Before joining Weather-
set deeper if conditions dictate. This is conditions to arrive at the correct set- ford, Mr. York was Vice President of Commer-
cialization and Marketing for Enventure Global
why actual drilling conditions must be ting depth. In terms of drilling hazard Technology after tenures with Halliburton and
monitored and why it is important to management, a mistake often made is to Dresser Atlas. He earned a BS degree in elec-
understand well listening as a neces- set the casing at a predetermined depth trical engineering at Northwestern State Uni-
sary condition of casing seat optimiza- regardless of drilling conditions. Casing versity in 1972 and pursued his MBA degree
there in economics and management before
tion. Planned depth becomes the maxi- seat tolerance not high enough for the launching his oilfield career.
mum predicted depth, plus more if hole next hole section results in the prema-
conditions dictate. The contingency ture setting of another string of casing or Scott Beattie has 22 years of oilfield service ex-
becomes a shallower setting depth. It is drilling liner. This makes all risks more perience. After spells with Halliburton and Baker
critical to ensure that the applied ECD difficult to manage and routinely results Oil Tools, he has spent the past 14 years with
plus safe tolerance is optimized for the in expending unnecessary casings. The Weatherford in various technical and operational
roles, primarily supporting drilling technologies.
given vertical depth, as dictated by ac- typical mitigant is then to set the liner Mr. Beatties latest assignment is in Kuala Lum-
tual drilling conditions. or full string of casing and hope for bet- pur, Malaysia, as Global Business Unit Manager
A useful predictive tool is pressure ter results, shifting the uncertainties and for Drilling with Casing. Mr. Beattie is regarded
while drilling (PWD), coupled with risk yet deeper. The shallower the depth as a subject matter expert in casing-drilling appli-
cations and engineering and is a key member of
ahead-of-the-bit trend predictions such at which the hazard can be managed, the Weatherfords Drill Hazard Mitigation team. He
as D exponents and seismic data. How- better the risk profile, drilling perfor- is a co-inventor of several onshore and subsea
ever, even tools such as PWD and seis- mance and cost, and the safer the well. casing-drilling technologies.
mic data will not predict stress, and there
is a distinct difference between stress NEXT INSTALLMENT Don Hannegan is the Drilling Hazard Mitigation
Technology Development Manager for Weath-
and pore pressure. Stress is a vector and Part 2 of this series will address risk erford. He received World Oils 2004 Innovative
is imposed on the borehole by variables management and avoidance through Thinker Award for his role in conceiving and de-
such as tectonics, faults or creeping salt proactive interpretation of real-time data, veloping specialized equipment and concepts
diapers. These vectors can be quite dif- or well listening. Listening to the well applicable to managed pressure drilling of chal-
lenging and complex wells. He also was an
ferent from pore pressure both in mag- while drilling is fundamental, and is de- SPE Distinguished Lecturer for 2006/2007, and
nitude and in direction. fined simply as recognizing, integrating is a charter member of the IADC UBO/MPD
Pore pressure can be normal, yet and correctly interpreting all drilling dy- Committee and a founding officer of the Arkan-
stress can be much higher, but both re- namics, weight on bit, rotational speed, sas SPE section. He was recently appointed by
the University of Texas Petroleum Engineering
quire the same solution to stabilize the ECD and shale shaker cuttings to assist Extension Service (PETEX) to serve as lead au-
borehole: casing or mud weight. The in making the correct proactive decisions thor of a textbook to be titled Drilling Hazard
uncertainty of this dynamic is critical in during operations. Whereas the advent of Mitigation Tools & Technology.
Article copyright 2010 by Gulf Publishing Company. All rights reserved. Printed in the US.
84 AUGUST 2010 World Oil
Not to be distributed in electronic or printed form, or posted on a website, without express written permission of copyright holder.

You might also like