DISEO DE ZAPATA AISLADA

1. METRADOS DE LA EDIFICACION INGRESAR DATOS


M= 1.645 m RESULTADOS
Area Tributaria
N= 2.9 m
Nro de pisos 4
Carga Muerta 800 kg/m2
Carga Viva 200 kg/m2
PD= 72.875 ton
PL= 33.125 ton Col=

2. DATOS S/C (kg/m2)= 500


PD= 125 ton
PV= 35 ton
terre= 2 kg/cm2 0.1
fc= 210 kg/cm2
fy= 4200 kg/cm2
Df= 1.5 m
hf= 1.6 m
S/c= 500 kg/m2
s= 1.8 ton/m3 d= 0.5
c= 2.4 ton/m3
m 2.1 ton/m3
COLUMNA 0.6 m
0.4 m

3. CALCULO DEL ESFUERZO NETO DEL SUELO


=/

n= 16.14 ton/m2

4. AREA DE LA ZAPATA EN PLANTA =/


Pservicio= 160 ton
Az= 9.9132589839 m2 Requerida

Columna 0.6 0.4 m


Lv= 1.3 m
T= 3.25 m
S= 3.05 m
S Area Coloc= 9.9125 m2
Diferencia -0.00075898 >>0 VERIFICAR SXT
T

=/
5. REACCION NETA ULTIMA DEL SUELO
Pu
Pu= 234.5 ton/m2
Wnu= 23.656998739 ton/m2

Wnu

6.DIMENSIONAMIENTO EN ALTURA h
h= 0.6 m
d= 0.5 m

7. VERIFICACION POR CORTANTE
= 0.85 =0.53 , =
Vc= 99.5575696684 ton =()
Vu= 57.7230769231 ton

d d
57.7230769231 99.5575696684 S
CUMPLE!!!

T
8. VERIFICACION POR PUNZONAMIENTO
m

= d/2

n
1=0.27(2+4/))
d/2

2=1.06
ELEGIR
EL
MENOR = 2+2
3=0.27(2+()/)

= 0.85
m= 1.1 m
n= 0.9 m
bo= 4m
Bc= 1.5 1.5
Vc1= 310.405289903 ton
Vc2= 261.134608966 ton
Vc3= 465.607934855 ton
Vu= 211.079571248 ton

211.0795712484 261.134608966
CUMPLE!!!

9. DISEO POR FLEXION


Wnu= 23.656998739 ton/m2
Lv= 1.325 m
S= 3.05 m
= ^2/2
Mu= 63.3375480769 ton*m
fc= 210 kg/cm2
fy= 4200 kg/cm2
phi= 0.9
b= 3.05 m
d= 0.5 m
w= 0.0451879489
cuantia 0.0022593974 As requerido 34.4558110581 cm2
Cuantia minima 0.0018 As minimo 27.45 cm2
USAR= 34.4558110581 cm2

ACERO EN LA DIRECCION LONGITUDNAL


Rec 7.5 cm
S= 3.05 m
T= 3.25 m
S
*Supongamos Acero 5/8"
Diam 1.59 cm
Ab= 2 cm2
T =(2)/(1)
Nro Varillas= 17.227905529
14
ESP= 22.1853846154
20 COLOCAR 14

ACERO EN LA DIRECCION TRANSVERSAL


r= 7.5 cm =/
Ast= 36.7152085045 cm2
=/

S= 3.05
T= 3.25
S
*Supongamos Acero 5/8"
Diam 1.59 cm
Ab= 2 cm2 =(2)/(1)
T Nro Varillas= 18.3576042522
14
S= 23.7238461538
20 COLOCAR 14
INGRESAR DATOS
RESULTADOS

0.6 x 0.4

Df= 1.5 hf= 1.6

h= 0.6

VERIFICAR SXT
2+2 = 40 30 20
=/
BARRA db(cm) Ab(cm2)
8 mm 0.8 0.5
3/8" 0.95 0.71
1/2" 1.27 1.29
5/8" 1.59 2
3/4" 1.91 2.84
7/8" 2.22 3.87
1" 2.54 5.1
1 3/8" 3.58 10.06

5/8" @ 20
5/8" @ 20
DISEO DE ZAPATA CONECTADA EXCENTRICA
1. METRADOS DE LA EDIFICACION INGRESAR DATOS
M= 3.1 m RESULTADOS
Area Tributaria
N= 3.23 m
Nro de pisos 4
Carga Muerta 800 kg/m2 COLUMNA 1
Carga Viva 210 kg/m2 0.4 0.3
PD= 32.0416 ton PD1= 32.0416
PL= 8.41092 ton PV1= 8.41092

DATOS
L= 6.46
L1= 6.06 m
PD1= 32.0416 ton
PV1= 8.41092 ton
Hf
PD2= 32.0416 ton
PV2= 8.41092 ton
terre= 1.4 kg/cm2
Df
fc= 210 kg/cm2
fy= 4200 kg/cm2
d1
Df= 1.5 m
hf= 1.6 m
S/c= 400 kg/m2
Y
s= 1.8 ton/m3 0.4
c= 2.4 ton/m3
m 2.1 ton/m3 X
COLUMNA 1 COLUMNA 2
0.4 0.3 0.4 0.3 m
x y x y

1. PREDIMENSIONAMIENT DE LA VIGA DE CONEXXION


L1= 6.06 m
h 0.87 USAR h= 0.6 m =1/7 =1/
b= 0.22 USAR b= 0.3 m (311)

2. ESFUERZ NETO
=/
n= 10.24 ton/m2

3. DIMENSIONAMIENTO DE LA ZAPATA EXTERIOR


1.20*P1= 48.54 ton =(1.21)/

Az= 4.74 m2 requerida
X Y
COLUMNA 1 0.4 0.3
Lv= 1.27 m
T T1= 2.84 m
S1= 1.67 m
Area Coloc= 4.74 m2
Diferencia 0.00 >>0 CUMPLE!

S
3. DIMENCIONAMIENTO DEFINITVO DE LA ZAPATA EXTERIOR 2 P1=
VIGA CIMENTA 0.3 0.6 m
Wviga= 0.432 ton/m
Distancias
1= 6.46 P1= 40.45252 ton
2= 0.2 P2= 40.45252 ton
3= 5.425 RN1= 41.84788 ton
4= 0.635 RN2= 41.84788 ton
5= 0.2 n= 10.24
6= 2.8125
7= 0.835 =/
8= 0.4175
9= 4.79 RN1

Az1= 4.09 Requerida Az2=


X Y
COLUMNA 1 0.4 0.3 COLUMNA 2
Lv= 1.160 m USAR Lv=
T1= 2.62 m 2.6 m T2=
S1= 1.56 m 1.6 m S2=
Area Coloc= 4.09 m2 Area Coloc=
Diferencia 0.00 >>0 CUMPLE! Diferencia

4. DISEO DE LA VIGA DE CIMENTACION


Pu 1.4*PD+1.7*PL
PU1= 59.156804
PU2= 59.156804
Wvigau= 0.6048 ton/m
Rnu1= 61.11 ton
Rnu2= 61.11 ton

4. REACCION NETA DEL SUELO POR UNIDAD DE LONGITUD


S= 1.6
Wnu1= 38.19375 ton/m =/
S= 1.6
Wnu2= 38.19375 ton/m

5. CALCULO DEL MOMENTO MAXIMO (ANALISIS ESTRUCTURAL)

a) Cuando V=0 ===> Mma


=1/() =()^2/21(/2)
x= 1.57 m
M Max= -34.72 ton*m

M (tonm) 34.72 BARRA db(cm) Ab(cm2)


b (cm) 0.3 8 mm 0.8 0.5
d (cm) 0.51 3/8" 0.95 0.71
fc (kg/cm2) 210 1/2" 1.27 1.29
fy (kg/cm2) 4200 5/8" 1.59 2
w= 0.2826 3/4" 1.91 2.84
p= 0.0141 7/8" 2.22 3.87
As cm2 21.62 1" 2.54 5.1
p minima= 0.0033 1 3/8" 3.58 10.06
Asmin 5.1000
ESPECIFICACIONES
4 PISOS Y DEMAS
INGRESAR DATOS
RESULTADOS

COLUMNA 2
0.4 0.3
PD2= 32.0416
PV2= 8.41092
L1= 6.06

L= 6.46

VIGA DE CIMENTACION d1

m 0.4 m

=1/ /2
11)

/
1.20*P1= 48.54 ton
Az= 4.74 m2 requerida

COLUMNA 2
Lv=
T T2=
S2=
Area Coloc=
CUMPLE! Diferencia

1
S
3 4 5
P2=

VIGA DE CIMENTACION

7
8
9
RN1 RN2

4.09 Requerida
X Y
0.4 0.3
1.160 m USAR
2.62 m 2.6 m
1.56 m 1.6 m
4.09 m2
0.00 >>0 CUMPLE!
)^2/21(/2)

USAR:
0 1/2" 1.29
0 5/8" 2
2 3/4" 2.84
0 7/8" 3.87
3 1" 5.1
Area Colocada 20.98 cm2
As inferior= 7.21
97.1 % 3/4"
=(1.21)/

X Y
0.4 0.3
1.27 m
2.84 m
1.67 m
4.74 m2
0.00 >>0 CUMPLE!
DISEO DE ZAPATA CONECTADA EXCENTRICA
1. METRADOS DE LA EDIFICACION INGRESAR DATOS
M= 3.1 m RESULTADOS
Area Tributaria
N= 3.23 m
Nro de pisos 4
Carga Muerta 800 kg/m2 COLUMNA 1
Carga Viva 210 kg/m2 0.5 0.5
PD= 32.0416 ton PD1= 70
PL= 8.41092 ton PV1= 26

DATOS
L= 5.6
L1= 6.2 m
PD1= 70 ton
PV1= 26 ton
Hf
PD2= 120 ton
PV2= 45 ton
terre= 3.5 kg/cm2
Df
fc= 210 kg/cm2
fy= 4200 kg/cm2
d1
Df= 1.4 m
hf= 1.5 m
S/c= 400 kg/m2
Y
s= 1.8 ton/m3 0.5
c= 2.4 ton/m3
m 2 ton/m3 X
COLUMNA 1 COLUMNA 2
0.5 0.5 0.7 0.7 m
x y x y

1. PREDIMENSIONAMIENT DE LA VIGA DE CONEXXION


L1= 6.20 m
h 0.89 USAR h= 0.9 m =1/7 =1/
b= 0.50 USAR b= 0.5 m (311)

2. ESFUERZ NETO
=/
n= 31.6 ton/m2

3. DIMENSIONAMIENTO DE LA ZAPATA EXTERIOR


1.20*P1= 115.20 ton =(1.21)/

Az= 3.65 m2 requerida
X Y
COLUMNA 1 0.5 0.5
Lv= 0.95 m
T T1= 2.70 m T=
S1= 1.35 S=
Area Coloc= 3.65 m2
Diferencia 0.00 >>0 VERIFICAR Lv.!!!

S
3. DIMENCIONAMIENTO DEFINITVO DE LA ZAPATA EXTERIOR P1=
VIGA CIMENTA 0.5 0.9 m =(1(1)+((1+2)^2")/2" )/
Wviga= 1.08 ton/m 2
Distancias
1= 6.2 P1= 96 ton
2= 0.25 P2= 165 ton
3= 5.775 RN= 106.96 ton

n= 31.6

=/

RN

Az1= 3.38 Requerida Az2=


X Y
COLUMNA 1 0.5 0.5 COLUMNA 2
USAR Lv=
T1= 2.51 m 2.55 m T2=
S1= 1.35 m 1.35 m S2=
Area Coloc= 3.38 m2 Area Coloc=
Diferencia 0.00 >>0 CUMPLE! Diferencia

4. DISEO DE LA VIGA DE CIMENTACION


Pu 1.4*PD+1.7*PL
PU1= 142.2
=(1(1)+((1+2)^2")/2" )/((3))
Wvigau= 1.512 ton/m

Rnu1= 158.1110805 ton


4. REACCION NETA DEL SUELO POR UNIDAD DE LONGITUD
S= 1.35
Wnu1= 117.1193189 ton/m =/
S= 1.6
Wnu2= 0 ton/m

5. CALCULO DEL MOMENTO MAXIMO (ANALISIS ESTRUCTURAL)

a) Cuando V=0 ===> Mma =()^2/21(/2)


=1/()
x= 1.23 m
M Max= -51.90 ton*m

M (tonm) 51.9 BARRA db(cm) Ab(cm2)


b (cm) 0.5 8 mm 0.8 0.5
d (cm) 0.81 3/8" 0.95 0.71
fc (kg/cm2) 210 1/2" 1.27 1.29
fy (kg/cm2) 4200 5/8" 1.59 2
w= 0.0883 3/4" 1.91 2.84
p= 0.0044 7/8" 2.22 3.87
As cm2 17.89 1" 2.54 5.1
p minima= 0.0033 1 3/8" 3.58 10.06
Asmin 13.5000
ESPECIFICACIONES
4 PISOS Y DEMAS
INGRESAR DATOS
RESULTADOS

COLUMNA 2
0.7 0.7
PD2= 120
LUZ PV2= 45
L1= 6.2

L= 5.6

VIGA DE CIMENTACION d1

m 0.7 m

=1/ /2
11)

/
1.20*P1= 198.00 ton
Az= 6.27 m2 requerida

COLUMNA 2
Lv=
2S T T2=
S 2 S2=
Area Coloc=
VERIFICAR Lv.!!! Diferencia

1 S

=(1(1)+((1+2)^2")/2" )/((3))

VIGA DE CIMENTACION
O

RN

0.00 Requerida
X Y
0.7 0.7
1.160 m USAR
3.02 m 2.6 m
1.86 m 1.6 m
5.62 m2
5.62 >>0 CUMPLE!
)^2/21(/2)

USAR:
0 1/2" 1.29
0 5/8" 2
3 3/4" 2.84
0 7/8" 3.87
2 1" 5.1
Area Colocada 18.72 cm2
As inferior= 5.96
104.6 % 3/4"
=(1.21)/

X Y
0.7 0.7
1.27 m
3.24 m
1.97 m
6.38 m2
0.12 >>0 CUMPLE!
DISEO DE CIMENTACION CON MOMENTOS DE SISMO

DATOS x y
Columna 0.65 0.5
CARGAS
Pm= 181.17 tn
Pv= 37.32 tn

Mmx= 2.546 tn*m Mmy= 1.019 tn*m


Mvx= 0.528 tn*m Mvy= 0.425 tn*m
Msx= 11.207 tn*m Msy= 11.265 tn*m
Psx= 3.15 tn Psy= 4.64 tn

Resistencia del terren 2.47 kg/cm2

1. DIMENSIONAMIENTO
Ptotal= 218.49 ton
Area tentativa 10.32004 m2

Columna 0.65 0.5 m


Lv= 1.35 m
T= 3.35 m L 3.25
S= 3.2 m B 3.1
S Area Coloc= 10.72 m2
Diferencia 0.399959514 >>0 CUMPLE!!!

T
=/+/(^ )
2. Verificamos Momentos en x
= 21.914195 ton/m2

3. Incrementamos las dimensiones


S= 3.15
T= 3.3
Lv= 1.325
4. Verificamos Biaxiamente
= 22.871964
=/+/(^ )+/( ^ )
=/+/(^ )+/( ^ )

5. Segunda verificacion (Sismo en X)


Pm 181.17
Pv 37.32
Mmx 2.546 Mmy= 1.019
Mvx 0.528 Mvy= 0.425
Msx 11.207
Psx 3.15
=/+/(^ )+/( ^ )
= 25.150354
= 29.64 incremento 20%

6. Tercera verificacion (Sismo en y)


Pm 181.17
Pv 37.32
Mmx 2.546 Mmy 1.019
Mvx 0.528 Mvy 0.425
Msy 11.265
Psy 4.64

= 25.40483 Por tanto se considera estas dimensiones como correctas


= 29.64 incremento 20%

7. DISEO
No se considero sismo
= 22.871964 ton/m2
u= 36.595143 ton/m2
Se considero Sismo X
= 25.150354 ton/m2
u= 31.437943 ton/m2
Se considero Sismo Y
= 25.40483 ton/m2
u= 31.756038 ton/m2

Por lo Tanto o REACCION NETA DEL SUELO


u= 36.595143 ton/m2 lo cual no es excto pero aproximado

8.DIMENSIONAMIENTO EN ALTURA h
h= 0.7 m
d= 0.6 m

9. VERIFICACION POR PUNZONAMIENTO


m

= d/2

n
1=0.27(2+4/))
d/2
ELEGIR
EL
2=1.06 MENOR
= 2+2
3=0.27(2+()/)

fy= 4200
fc= 210
= 0.85 =()
m= 1.25 m
n= 1.1 m
bo= 4.7 m
Bc= 1.3 1.3
Vc1= 476.1480705 ton
Vc2= 368.1997986 ton
Vc3= 666.484501 ton
Vu= 330.0881863 ton

330.088186 368.1997986
CUMPLE!!!


10. VERIFICACION POR CORTANTE
= 0.85 =0.53 , =
Vc= 123.3861027 ton =()
Vu= 83.57415692 ton

d d
83.5741569 123.3861027 S
CUMPLE!!!

11. DISEO POR FLEXION


Wnu= 36.595142603 ton/m2
Lv= 1.325 m
S= 3.15 m
= ^2/2
Mu= 101.18957189 ton*m
fc= 210 kg/cm2
fy= 4200 kg/cm2
phi= 0.9
b= 3.15 m
d= 0.6 m
w= 0.0486420067
cuantia 0.0024321003 As requerido 45.966696305 cm2
Cuantia mini 0.0018 As minimo 34.02 cm2
USAR= 45.966696305 cm2

ACERO EN LA DIRECCION LONGITUDNAL


Rec 7.5 cm
S= 3.15 m
T= 3.3 m
S
*Supongamos Acero 3/4"
Diam 1.91 cm
Ab= 2.84 cm2
T =(2)/(1)
Nro Varillas= 16.185456445
16
ESP= 19.872666667
20 COLOCAR 16 3/4"

ACERO EN LA DIRECCION TRANSVERSAL


r= 7.5 cm =/
Ast= 48.155586605 cm2
S= 3.15
T= 3.3
S
*Supongamos Acero 3/4"
Diam 1.91 cm
Ab= 2.84 cm2 =(2)/(1)
T Nro Varillas= 16.956192467
16
S= 20.872666667
20 COLOCAR 16 3/4"
nes como correctas
= 40 30 20
=/
BARRA db(cm) Ab(cm2)
8 mm 0.8 0.5
3/8" 0.95 0.71
1/2" 1.27 1.29
5/8" 1.59 2
3/4" 1.91 2.84
7/8" 2.22 3.87
1" 2.54 5.1
1 3/8" 3.58 10.06

@ 20

@ 20