Professional Documents
Culture Documents
en-GB
Dokaflex
User Information
Instructions for assembly and use (Method statement)
by Doka GmbH, A-3300 Amstetten
9720-337-01
by Doka GmbH, A-3300 Amstetten
User Information Dokaflex
Contents
3 Introduction
3 Timber-beam floor formwork
4 Elementary safety warnings
7 Eurocodes at Doka
8 Doka Services
10
10 System description
12 Dokaflex 1-2-4 system logic
14 Optimised equipment usage Dokaflex 20
16 Instructions for assembly and use
23 Adaptability
24 Floor formwork around edges
26 Tie-back solutions
27 Secondary-beam stabilisers
28 Slab stop-ends
30 Fall-arrest systems on the structure
31 Beam forming support
32 Drop-beam not integrated into the floor-slab /
stop-end formwork
33 Drop-beam integrated into the floor-slab
35 Combining Doka table systems
36 Formwork planning with Tipos-Doka
37 Transporting, stacking and storing
42 Reshoring props, concrete technology and
stripping out
44 Component overview
2 999776002 - 04/2015
User Information Dokaflex Introduction
Dokaflex
|
Dokaflex 1-2-4
The easy-to-use floor-slab formwork with a
logical, built-in system for setting up the
formwork
Dokaflex 20
The tailor-made solution for your specific
project requirements
Dokaflex 30 tec
The fast floor-slab formwork for forming
large areas
The easy-to-use floor-slab formwork with a logical, The timber-beam floor formwork with particularly sturdy
built-in system for setting up the formwork components reduces the number of items needed and
marks on the beams show you the maximum spac- is fast to erect and dismantle, resulting in savings in
ings between secondary beams, props and primary labour costs.
beams, for floor-slabs up to a thickness of 30 cm The fast floor-slab formwork for forming large areas:
having only 2 different lengths of beam facilitates fast working, as less equipment is needed
logistics and reduces the time spent searching - 1/3 fewer floor props needed because of the
you can tell at a glance whether the formwork has higher load-bearing capacity of the I tec 20 beam
been set up correctly - smaller storage and transport volume
- wide access paths beneath the floor-slab form-
Dokaflex 20 work
- reduced follow-up costs
The tailor-made solution for your specific project suitable for shoring filigree slabs
requirements:
Follow the directions in the 'Dokaflex 30 tec'
very little equipment is needed thanks to statically User Information booklet!
optimised beam and prop spacings, which are in
accordance with the room geometry and the loads
that occur
drop beams and floor extensions can easily be man-
aged 'within the system'
significant reduction in commissioning quantities
thanks to the Doka Xtra head, which allows early
stripping
999776002 - 04/2015 3
Introduction User Information Dokaflex
4 999776002 - 04/2015
User Information Dokaflex Introduction
999776002 - 04/2015 5
Introduction User Information Dokaflex
Tip
Points out useful practical tips.
Reference
Refers to other documents and materials.
6 999776002 - 04/2015
User Information Dokaflex Introduction
Eurocodes at Doka
In Europe, a uniform series of Standards known as The widely used "Permissible stress design" (compar-
Eurocodes (EC) was developed for the construction ing the actual stresses with the permissible stresses)
field by the end of 2007. These are intended to provide has been superseded by a new safety concept in the
a uniform basis, valid throughout Europe, for product EC.
specifications, tenders and mathematical verification. The EC contrast the actions (loads) with the resistance
The EC are the world's most highly developed Stand- (capacity). The previous safety factor in the permissible
ards in the construction field. stresses is now divided into several partial factors. The
In the Doka Group, the EC are to be used as standard safety level remains the same!
from the end of 2008. They will thus supersede the DIN
norms as the "Doka standard" for product design.
Ed Rd
98013-102
Factual Fpermissible Ed Rd
A Utilisation factor
999776002 - 04/2015 7
Introduction User Information Dokaflex
Doka Services
Support in every stage of the project
Doka offers a broad spectrum of services, all with a sin-
gle aim: to help you succeed on the site.
Every project is unique. Nevertheless, there is one
thing that all construction projects have in common
and that is a basic structure with five stages. We at
Doka know our clients' varying requirements. With our
consulting, planning and other services, we help you
achieve effective implementation of your formwork
assignment using our formwork products in every one
of these stages.
1 2 3
Project Development Stage Bidding Stage Operations Scheduling Stage
Taking well-founded decisions Optimising the preliminary work Controlled, regular forming oper-
thanks to professional advice and with Doka as an experienced part- ations, for greater efficiency
consulting ner resulting from realistically calculated
formwork concepts
Find precisely the right formwork Draw up potentially winning bids, by Plan cost-effectively right from the
solutions, with the aid of basing them on realistically calcu- outset, thanks to
help with the bid invitation lated guideline prices detailed offers
in-depth analysis of the initial sit- making the right formwork determination of the commission-
uation choices ing quantities
objective evaluation of the plan- having an optimum time-calcula- co-ordination of lead-times and
ning, execution, and time-risks tion basis handover deadlines
8 999776002 - 04/2015
User Information Dokaflex Introduction
Transparency
Because our services and costs
Optimum resource utilisation Seeing things through to a posi- are completely transparent, there
with assistance from the Doka tive conclusion is no need for improvisation dur-
Formwork Experts with professional support ing the project and no unpleas-
ant surprises at the end of it.
999776002 - 04/2015 9
User Information Dokaflex
System description
Dokaflex Small number of system components
The versatile hand-set system for - all perfectly co-ordinated
floor-slabs
Dokaflex:
A
1 system 2 possible ways of using it
Dokaflex 1-2-4
The easy-to-use floor-slab formwork with a logical,
built-in system for setting up the formwork
marks on the beams show you the maximum spac-
ings between secondary beams, props and primary B
beams, for floor-slabs up to a thickness of 30 cm
having only 2 different lengths of beam facilitates
logistics and reduces the time spent searching D
C
you can tell at a glance whether the formwork has
been set up correctly
Dokaflex 20
The tailor-made solution for your specific project E
requirements:
very little equipment is needed thanks to statically
optimised beam and prop spacings, which are in
accordance with the room geometry and the loads
that occur
drop beams and floor extensions can easily be man-
aged 'within the system'
F
significant reduction in commissioning quantities
thanks to the Doka Xtra head, which allows early
stripping
General features
9720-202-01
The system is ideal for enclosed spaces where the
formwork superstructure can rest up against walls on
all sides.
Horizontal forces at exposed slab-edges, downturned
beams or steps in ceiling slabs must be restrained by
bracing or tie-backs.
General advantages of Dokaflex:
infill zones are managed within the system, making it
easy to adapt to walls and columns
for shoring heights of up to 5.50 m
any type of form-facing can be used
10 999776002 - 04/2015
User Information Dokaflex
special surface coating for superb-quality concrete DIB (German Institute of Construction Engineering)
faces approval n Z-8.311-905
can be used on both sides EN 1065-compliant prop
all-round edge protection for long lifespan - all extension lengths: Class D
improved workplace safety thanks to reduced risk of - up to 3.50 m: In addition, Class B
slippage - up to 4.00 m: In addition, Class C
easy to clean, with high-pressure spray cleaner (see the approval or type-test for in-depth infor-
space-saving storage and handling mation)
1) Alternatively, it is also possible to use Doka formwork high load-bearing capacity
sheets 3-SO. - permitted capacity of Eurex 20: 20 kN
numbered pegging holes, for easier height adjust-
Follow the directions in the "Formwork sheet- ment
ing" User Information booklet! special thread geometry, which makes the prop eas-
ier to release even when it is under high load
(B) Doka beam H20 elbowed fastening clamps, reducing the risk of injury
and making the props easier to operate
1-2-4 method: easy-to-distinguish primary beams Follow the directions in the "Floor props Eurex
(3.90 m) and secondary beams (2.65 m) are used
top / Eurex eco" User Information booklet!
Dokaflex 20: also other beam lengths can be used
when using H20 top:
Note:
- pre-defined positioning points as reference
marks for setting-up and checking the formwork The floor props can be lengthened with the Floor prop
- integrated shock absorber on the beam end extension 0.50m (allow for the reduced load-bearing
piece for reduced damage and long service life capacity).
Follow the directions in the "Timber formwork Follow the directions in the "Floor prop exten-
beams" User Information booklet! sion 0.50m" User Information!
9720-239-01
999776002 - 04/2015 11
User Information Dokaflex
9776-100
4 D
component parts
2 2
A Floor prop Eurex + Lowering head H20 + Removable folding tri-
No matter whether the beams are resting on, between pod
or next to the marks, the maximum spacing is always B Floor prop Eurex + Supporting head H20 DF
plain to see. C Doka beam H20 top 2.65 m (secondary beam)
You can tell at a glance whether the formwork has been D Doka beam H20 top 3.90 m primary beam)
erected correctly, and without having to measure up.
12 999776002 - 04/2015
User Information Dokaflex
999776002 - 04/2015 13
User Information Dokaflex
14 999776002 - 04/2015
User Information Dokaflex
cc d
e
b
B A
b
C
98060-200-01
a a
a ... Prop spacing (from table)
b ... Primary-beam spacing (from table)
c ... Secondary-beam spacing (from table)
d ... max. 50 cm or half the prop spacing
e ... max. 50 cm
f ... min. 30 cm
A Floor prop Eurex + Lowering head H20 + Removable folding tri-
pod
B Floor prop Eurex + Supporting head H20 DF
C Doka beam H20 top (secondary beam)
D Doka beam H20 top (primary beam)
C
f d
E
g
g
A D B A
9776-211-01
999776002 - 04/2015 15
User Information Dokaflex
Important note:
As well as the instructions given here, you
Roughly adjust the height of the floor props, using
the fastening clamp.
MUST follow the instructions in 'Reshoring
props, concrete technology and stripping out'.
9720-006
CAUTION
If the floor props are transported with the
collapsible wheelaround platform made of lowering heads still attached, you must
light alloy secure these with a Spring-locked connect-
variable working heights of up to 3.50 m ing pin 16 mm to prevent them dropping out.
(max. platform height 1.50 m) This is particularly important when they are
width of scaffold: 0.75 m transported in the horizontal.
For greater heights, the Working scaffold Insert a Lowering head H20 into the floor prop.
Modul is ideal. Leave the correct amount of lowering play (a)!
Windproofing
For increased stability, in larger rooms, the
full erection sequence of "primary beams +
secondary beams + formwork sheets"
should be carried out progressively for suc-
cessive sub-areas of the room.
When doing this, provide suitable bracing to
walls or columns. 9720-006
If there is any risk of the formwork being Clearance a between wedge and head-plate:
blown over, all free-standing, non-enclosed
6 cm
areas of slab formwork must be secured dur-
ing work-breaks and when work finishes for
the day. Put up each removable folding tripod.
Put the floor prop into the tripod and fix it in place with
Using the 1-2-4 method: Lay the primary beams and the clamping lever.
secondary beams down on the ground, along the Before stepping onto the formwork, check again to
walls. make sure that the props have been correctly fixed
The marks on the beams show you the maximum in the tripods.
spacings:
- 4 marks for primary beams Setting up tripods in corners or up against walls
- 6 marks for props with removable folding tripods
(final prop spacing after putting up the intermediate
props - 2 marks)
Using Dokaflex 20: Measure up the positions of the
floor props. 9720-241-01 9720-240-01
16 999776002 - 04/2015
User Information Dokaflex
9720-004
Adjust the primary beams to the correct floor-slab
height.
9720-204-01
9720-335-01 9720-205-01
WARNING
Loads that are applied non-centrally can cause
overloading of the system.
Ensure that all loads are applied centrally!
9776-201-01
9776-102-01
999776002 - 04/2015 17
User Information Dokaflex
Placing the secondary beams on the primary Mounting slab stop-ends and guardrail
beams systems
Use the beam forks to place the secondary beams
on the primary beams, with an overlap. Use personal fall arrest systems to protect
against fall hazards when working on unse-
cured slab-edges (e.g. Doka personal fall-
arrest set).
Mount the slab stop-ends
Mount guard rails around all exposed edges.
9720-005
9776-204-01
98039-216-01
18 999776002 - 04/2015
User Information Dokaflex
Putting up intermediate props Laying the ProFrame panels onto the beams
9767-233-01
Put up the intermediate props.
Using the 1-2-4 method: Maximum spacing of floor
props: 2 marks.
Using Dokaflex 20: Measure up the positions of the
floor props.
9776-210-01
9768-215-01
B Working from above
9776-208-01
999776002 - 04/2015 19
User Information Dokaflex
9776-209-01
Pouring
To protect the surface of the form-facing, we recom-
mend using a vibrator with a protective rubber cap.
20 999776002 - 04/2015
User Information Dokaflex
9720-008
Take out the ProFrame panels and put them in the
stacking pallet.
9720-006
9720-009
9720-007
999776002 - 04/2015 21
User Information Dokaflex
9720-006
Reshoring
Before pouring the next floor-slab (i.e. above the one
that has just been stripped), put up reshoring props.
22 999776002 - 04/2015
User Information Dokaflex
Adaptability
Closures and adjustments Grid and flexibility - in one system
Infill zones are solved within the system - with no spe- Dokaflex also adapts to difficult layouts.
cial accessories needed. The necessary adaptation is
made by overlapping the Doka beams and inserting
strips of formwork sheeting.
9720-336-01
9720-211-01
B
B
A
A
9776-200-01
9768-209-01
A ProFrame panel
B Fitting boards in the closure zone
B
9792-210-01
999776002 - 04/2015 23
User Information Dokaflex
9720-339-01
C
A Dokamatic table
B Dokaflex
B
A C Handrail post T 1.80m (with Toeboard holder T 1.80m), Edge
protection system XP, Handrail clamp S or Handrail post 1.50m
D E D Lashing strap 5.00m
E Doka express anchor 16x125mm and Doka coil 16mm
9720-338-01
Supported by load-bearing tower
A Dokamatic table
B Dokaflex For downstand beams, the load-bearing towers and
C Dokamatic table platform beam-forming supports can be combined very effec-
D Lashing strap 5.00m tively with Dokaflex.
E Doka express anchor 16x125mm and Doka coil 16mm
D
Supported by load-bearing tower
C
B A B
A
C E
F
98024-236-01
D
F
A Load-bearing tower
B Dokaflex
98039-215-01 C Beam forming support 20
D Handrail post T 1.80m (optionally with Toeboard holder T
A Load-bearing tower 1.80m), Edge protection system XP, Handrail clamp S or Hand-
B Dokaflex rail post 1.50m
C Staxo 40 bracket 90cm E Lashing strap 5.00m
D Edge protection system XP F Doka express anchor 16x125mm and Doka coil 16mm
E Plumbing strut 340 for pre-cast members
F Doka express anchor 16x125mm and Doka coil 16mm
WARNING
Where formwork beams cantilever out a long
way, secure them against accidental lift-out.
24 999776002 - 04/2015
User Information Dokaflex
WARNING
Secure cantilevering slab formwork to pre-
vent lift-out and tipover.
Secondary beams with stop-end formwork
must be secured against horizontal pull-out.
In addition, if necessary, put up a protection
platform on the structure (e.g. Folding
platform K).
999776002 - 04/2015 25
User Information Dokaflex
Tie-back solutions
For transferring low horizontal loads (stabilisation, To a beam-hole
V/100, windproofing etc.).
Tie-back attached to a diam. 20 mm tie-rod or rein-
forcement rod placed through a beam-hole
Tr784-200-01
A
V
B
Tr784-200-01
H Horizontal load
V Vertical load A
A Back-stay force
WARNING
A Lashing strap 5.00m
Never attach the tie-back directly to a head
B Diam. 20 mm tie-rod or reinforcement rod
unit or floor prop
Lifting-bracket
Pre-mounted to primary beam.
Tr784-208-01
Max. tie-back load: 5 kN
Tr784-200-01
26 999776002 - 04/2015
User Information Dokaflex
Secondary-beam stabilisers
Secondary-beam stabilisers are used to prevent form-
work beams tipping over while panels are being laid on
them.
98039-217-01 98039-217-02
Advantages:
Special claws to prevent slippage on the beam-
flange
No work-platform scaffold needed, as the stabilisers
can be mounted/dismounted from ground level using
an Alu beam fork H20
Needs only small commissioning quantities, as the
Secondary-beam stabilisers can be re-set in tandem
with the formwork erection cycle:
- approx. 20 Secondary-beam stabilisers 1
- approx. 10 Secondary-beam stabilisers 2
Note:
In certain special situations, (e.g. when forming inclined
floor-slabs), Secondary-beam stabilisers can also be
used for transferring horizontal loads.
For more information, please contact your Doka techni-
cian.
How to mount:
Hang the Secondary-beam stabilisers into place with
an Alu beam fork H20.
98039-212-01
999776002 - 04/2015 27
User Information Dokaflex
Slab stop-ends
Universal end-shutter support 30cm Structural design
d
A
9776-202-01
TR652-202-01
d ... slab thickness max.30 cm
A Universal end-shutter support 30cm
Max. influence width: a
B Nail 3.1x80 for slab thickness of [cm]
C Doka formwork sheet 3-SO How fastened: Configuration 20 25 30
4 nails 3.1x80 A 90 50 30
Tip for striking formwork: 4 Spax screws 4x40
B 220 190 160
(fully threaded)
Take out the nails on the stop-end side.
Put the claw of a hammer under the corner
(put a piece of wood under it to protect the
formwork sheeting)
Lever up the end-shutter support
Tr652-203-02
9776-203-01
28 999776002 - 04/2015
User Information Dokaflex
98023-200-04
Practical example
98023-233-01
Note:
The edge railings must be mounted before the form-
work sheets are laid out.
999776002 - 04/2015 29
User Information Dokaflex
a
Protective grating XP, guard-rail boards or scaffold
tubes can be used as the safety barrier
9755-205-01
geprfte
Sicherheit
a
Handrail clamp S
Attached with integral clamp
Guard-rail boards or scaffold tubes can be used as
a
geprfte
Sicherheit
geprfte
Sicherheit
30 999776002 - 04/2015
User Information Dokaflex
9720-324-01
9720-323-01
9720-232-01
Note:
As a basic rule, it is forbidden to use formwork beams
"horizontally" (i.e. with the load-direction perpendicular
9720-322-01
to the web). However, the specific applications shown
here, using the Beam forming support, are permitted.
9720-321-01
Formwork beams vertical
The large bearing surface of the Beam-forming sup- (up to a height of 90 cm)
port gives the sidewall formwork a high degree of
(90) angle accuracy.
9720-233-01
999776002 - 04/2015 31
User Information Dokaflex
h
h
9720-251-01
b
l
9720-249-01
b
b ... max. 100 cm
l
l ... max. 150 cm
Sidewall formwork:
b ... max. 100 cm 2 Doka beams H20 top
l ... max. 150 cm
Sidewall formwork: h
Spacing of Position of Beam
secondary beams forming support
Doka beam H20 top
Up to 60 cm 50.0 cm On every 2nd secondary beam
From 60 cm 33.3 cm On every 2nd secondary beam
Spacing of Position of Beam
secondary beams forming support
50.0 cm On every 3rd secondary beam Drop beams of between 70 and 90 cm
in height
Drop beams of between 30 and 47 cm
in height
A
h
h
9720-252-01
b
9720-250-01
b l
l
b ... max. 100 cm
l ... max. 150 cm
b ... max. 100 cm Where the dimensional requirements are espe-
l ... max. 150 cm
cially stringent, we recommend placing a form-
Sidewall formwork: tie (A) through the sidewall formwork as an
Doka beam H20 top additional precaution.
Squared timber 4/8 cm for drop beams of between
30 and 34 cm in height Sidewall formwork:
Squared timber 8/8 cm for drop beams of between Doka formwork beams H20 in the upright
34 and 47 cm in height
Spacing of Position of Beam
h
secondary beams forming support
Spacing of Position of Beam
secondary beams forming support Up to 85 cm 41.7 cm On every secondary beam
From 85 cm 36.0 cm On every secondary beam
50.0 cm On every 2nd secondary beam
h... Drop-beam height
b... Drop-beam width
l... Spacing of primary beams
32 999776002 - 04/2015
User Information Dokaflex
d
3-SO 27 mm formwork sheets are used.
h
height
9720-255-01
b
l
d
Sidewall formwork:
2 Doka beams H20 top
h
999776002 - 04/2015 33
User Information Dokaflex
d
3-SO 27 mm formwork sheets are used.
Floor influence zone on either side of the drop-beam
max. 1.0 m
h
Drop beams of between 10 and 30 cm in
height 9720-259-01
b
l
height l
34 999776002 - 04/2015
User Information Dokaflex
999776002 - 04/2015 35
User Information Dokaflex
36 999776002 - 04/2015
User Information Dokaflex
9234-203-01
999776002 - 04/2015 37
User Information Dokaflex
Tr755-200-04 Tr755-200-05
A
Tr755-200-02
9206-202-01
38 999776002 - 04/2015
User Information Dokaflex
Doka stacking pallet 1.55x0.85m and Using Doka stacking pallets as transport
1.20x0.80m devices
Lifting by crane
Storage and transport devices for long items:
durable Multi-trip packaging items may only be lifted
stackable one at a time.
Suitable transport appliances: Use a suitable lifting chain
crane (e.g. Doka 4-part chain 3.20m).
pallet stacking truck Do not exceed the permitted load-bearing
capacity.
forklift truck
Load the items centrically.
The Bolt-on caster set B turns the stacking pallet into a Fasten the load to the stacking pallet so that
fast and manoeuvrable transport trolley. it cannot slide or tip out.
Follow the directions in the "Bolt-on castor set When lifting stacking pallets to which Bolt-on
B" Operating Instructions! castor sets B have been attached, you must
also follow the directions in these Operating
Instructions!
Spread-angle max. 30!
= =
a
92815-224-01
Max. load: 1100 kg
Permitted imposed load: 5900 kg a
Doka stacking pallet 1.55x0.85m max. 4.0 m
999776002 - 04/2015 39
User Information Dokaflex
92816-206-01
40 999776002 - 04/2015
User Information Dokaflex
98039-214-01
9776-205-01
999776002 - 04/2015 41
User Information Dokaflex
DLconcrete + LLconstruction state Reshoring props have the job of spreading loads
between the new floor-slab and the floor beneath it.
= DLconcrete + DLfinishing + LLfinal This load distribution will depend on the relationship
state between the rigidities of these two floor-slabs.
90
Important note:
80
If the floor props are not stress-relieved, mean-
70
ing that the slab has not been activated, then A B C
the props will remain loaded with the dead 60
weight of the floor-slab. 50
When the floor above is concreted, this may 40
lead to a doubling of the load that is being 30
applied to the floor props.
20
The floor props are not designed to cope with
98059-100
42 999776002 - 04/2015
User Information Dokaflex
Deflection of the new concrete Removing the load from the formwork
from wide-spanned floor-slabs with
The modulus of elasticity of the concrete has already
reached more than 90 % of the 28-day value after only support centres of over 7.5m
3 days, regardless of the formulation of the concrete.
The increase in the elastic deformation taking place in In the case of thin, wide-spanned concrete floor-slabs
the new concrete is thus only negligible. (e.g. in multistorey car parks), the following points must
The creep deformation, which only finally ceases after be remembered:
several years, is several times more than the elastic When the load is taken off the floor props, the floor
deformation. props that are still in place are briefly subjected to
Early stripping e.g. after 3 days instead of 28 thus additional loads. This may lead to overloading, and
only leads to an increase in the total deformation of less to the floor props being damaged.
than 5 %. Please consult your Doka technician.
The part of this deformation accounted for by creep
deformation, however, may be anything between 50 %
and 100 % of the standard value, due to such variable
influences as the strength of the aggregates, and the
The basic rule is:
Stress-release should always be carried
out working from one side towards the
atmospheric humidity. This means that the total deflec- other, or from the middle of the floor slab
tion of the floor-slab is practically independent of the (mid-span) towards the slab-edges.
time at which the formwork was stripped out. For wide spans, this procedure MUST be fol-
lowed!
Cracks in new concrete Stress-relieve must NEVER be carried out
from both sides towards the middle!
999776002 - 04/2015 43
Component overview User Information Dokaflex
Doka floor prop Eurex 20 top 150 8.0 586096000 Doka floor prop Eurex 30 top 250 12.8 586092400
Length: 92 - 150 cm Length: 148 - 250 cm
Doka floor prop Eurex 20 top 250 12.7 586086400 Doka floor prop Eurex 30 top 300 16.4 586093400
Length: 148 - 250 cm Length: 173 - 300 cm
Doka floor prop Eurex 20 top 300 14.3 586087400 Doka floor prop Eurex 30 top 350 20.7 586094400
Length: 173 - 300 cm Length: 198 - 350 cm
Doka floor prop Eurex 20 top 350 17.4 586088400 Doka floor prop Eurex 30 top 400 24.6 586095400
Length: 198 - 350 cm Length: 223 - 400 cm
Doka floor prop Eurex 20 top 400 21.6 586089400 Doka floor prop Eurex 30 top 450 29.1 586119400
Length: 223 - 400 cm Length: 248 - 450 cm
Doka floor prop Eurex 20 top 550 32.3 586090400 Doka floor prop Eurex 30 top 550 38.6 586129000
Length: 298 - 550 cm Length: 303 - 550 cm
Doka-Deckensttze Eurex 20 top Doka-Deckensttze Eurex 30 top
Galvanised Galvanised
Doka floor prop Eurex 20 eco 250 11.5 586270000 Doka floor prop Eurex 30 250 14.8 586092000
Length: 148 - 250 cm Length: 152 - 250 cm
Doka floor prop Eurex 20 eco 300 14.0 586271000 Doka floor prop Eurex 30 300 16.7 586093000
Length: 173 - 300 cm Length: 172 - 300 cm
Doka floor prop Eurex 20 eco 350 16.9 586272000 Doka floor prop Eurex 30 350 20.5 586094000
Length: 198 - 350 cm Length: 197 - 350 cm
Doka floor prop Eurex 20 eco 400 20.5 586273000 Doka floor prop Eurex 30 400 24.9 586095000
Length: 223 - 400 cm Length: 227 - 400 cm
Doka floor prop Eurex 20 eco 450 24.1 586275000 Doka floor prop Eurex 30 450 29.2 586119000
Length: 248 - 450 cm Length: 248 - 450 cm
Doka-Deckensttze Eurex 20 eco Doka-Deckensttze Eurex 30
Galvanised Galvanised
Doka floor prop Eurex 20 250 12.9 586086000 Doka floor prop Eco 20 250 11.7 586134000
Length: 152 - 250 cm Length: 152 - 250 cm
Doka floor prop Eurex 20 300 15.3 586087000 Doka floor prop Eco 20 300 13.0 586135000
Length: 172 - 300 cm Length: 172 - 300 cm
Doka floor prop Eurex 20 350 17.8 586088000 Doka floor prop Eco 20 350 15.3 586136000
Length: 197 - 350 cm Length: 197 - 350 cm
Doka floor prop Eurex 20 400 22.2 586089000 Doka floor prop Eco 20 400 19.1 586137000
Length: 227 - 400 cm Length: 227 - 400 cm
Doka-Deckensttze Eco 20
Doka floor prop Eurex 20 550 34.6 586090000
Length: 297 - 550 cm Galvanised
Doka-Deckensttze Eurex 20
Galvanised
44 999776002 - 04/2015
User Information Dokaflex Component overview
Lowering head H20 6.1 586174000 Beam forming support 20 6.9 586148000
Absenkkopf H20 Balkenzwinge 20
Galvanised Galvanised
Length: 25 cm Length: 30 cm
Width: 20 cm Height: 35 cm
Height: 38 cm
Bracing clamp B 1.4 586195000 End-shutter tie rod 15.0 15-40cm 0.91 586258000
Verschwertungsklammer B
Abschalanker 15,0 15-40cm
Painted blue
Galvanised
Length: 36 cm
Length: 55 cm
999776002 - 04/2015 45
Component overview User Information Dokaflex
Wheel-around scaffold DF 44.0 586157000 ProFrame panel 21mm 200/50cm 10.3 186118000
Mobilgerst DF ProFrame panel 21mm 200/50cm BS 10.3 186118100
Aluminium ProFrame panel 21mm 250/50cm 12.9 186117000
Length: 185 cm ProFrame panel 21mm 250/50cm BS 12.9 186117100
ProFrame-Paneel 21
Width: 80 cm
Height: 255 cm
Delivery condition: folded closed ProFrame panel 27mm 200/50cm 13.5 187178000
ProFrame panel 27mm 200/50cm BS 13.5 187178100
ProFrame panel 27mm 250/50cm 16.9 187177000
ProFrame panel 27mm 250/50cm BS 16.9 187177100
ProFrame-Paneel 27
46 999776002 - 04/2015
User Information Dokaflex Component overview
Scaffold tube 48.3mm 0.50m 1.7 682026000 Bolt-on castor set B 33.6 586168000
Scaffold tube 48.3mm 1.00m 3.6 682014000 Anklemm-Radsatz B
Scaffold tube 48.3mm 1.50m 5.4 682015000 Painted blue
Scaffold tube 48.3mm 2.00m 7.2 682016000
Scaffold tube 48.3mm 2.50m 9.0 682017000
Scaffold tube 48.3mm 3.00m 10.8 682018000
Scaffold tube 48.3mm 3.50m 12.6 682019000
Scaffold tube 48.3mm 4.00m 14.4 682021000
Scaffold tube 48.3mm 4.50m 16.2 682022000
Scaffold tube 48.3mm 5.00m 18.0 682023000
Scaffold tube 48.3mm 5.50m 19.8 682024000
Scaffold tube 48.3mm 6.00m 21.6 682025000
Scaffold tube 48.3mm .....m 3.6 682001000 Doka skeleton transport box 1.70x0.80m 87.0 583012000
Doka-Gitterbox 1,70x0,80m
Gerstrohr 48,3mm
Galvanised
Galvanised
Height: 113 cm
999776002 - 04/2015 47
Near to you, worldwide
Doka is one of the world leaders in developing, manu- technical support are provided swiftly and profession-
facturing and distributing formwork technology for use in ally.
all fields of the construction sector. An enterprise forming part of the Umdasch Group, the
With more than 160 sales and logistics facilities in over Doka Group employs a worldwide workforce of more
70 countries, the Doka Group has a highly efficient dis- than 6000.
tribution network which ensures that equipment and
Doka GmbH | Josef Umdasch Platz 1 | 3300 Amstetten | Austria | T +43 7472 605-0 | F +43 7472 66430 | info@doka.com | www.doka.com 999776002 - 04/2015