FACULTAD DE INGENIERA, ARQUITECTURA Y URBANISMO

ESCUELA PROFESIONAL DE INGENIERA CIVIL

Momentos de las Vigas del Primer Nivel (Direccin X-X)

EJE 1-1
Viga 101 Viga 102 Viga 103

Ma + = 0.68 tn-m. Mc + = 0.78 tn-m. Me + = 0.08 tn-m.


Ma - = 5.73 tn-m. Mc - = 2.71 tn-m. Me - = 4.05 tn-m.
M(a-c) + = 3.58 tn-m. M(c-e) + = 0.08 tn-m. M(e-g) + = 2.65 tn-m.
M(a-c) - = 1.66 tn-m. M(c-e) - = 0.49 tn-m. M(e-g) - = 1.25 tn-m.
Mc + = 0.55 tn-m. Me + = 0.67 tn-m. Mg + = 0.10 tn-m.
Mc - = 4.54 tn-m. Me - = 2.39 tn-m. Mg - = 5.30 tn-m.

EJE 2-2
Viga 104 Viga 102 Viga 105

Ma + = 1.00 tn-m. Mc + = 1.00 tn-m. Mf + = 1.00 tn-m.


Ma - = 2.00 tn-m. Mc - = 2.00 tn-m. Mf - = 2.00 tn-m.
M(a-c) + = 3.00 tn-m. M(c-e) + = 3.00 tn-m. M(f-g) + = 3.00 tn-m.
M(a-c) - = 4.00 tn-m. M(c-e) - = 4.00 tn-m. M(f-g) - = 4.00 tn-m.
Mc + = 5.00 tn-m. Me + = 5.00 tn-m. Mg + = 5.00 tn-m.
Mc - = 6.00 tn-m. Me - = 6.00 tn-m. Mg - = 6.00 tn-m.

EJE 3-3
Viga 106 Viga 107 Viga 108

Ma + = 1.00 tn-m. Mc + = 1.00 tn-m. Mf + = 1.00 tn-m.


Ma - = 2.00 tn-m. Mc - = 2.00 tn-m. Mf - = 2.00 tn-m.
M(a-c) + = 3.00 tn-m. M(c-f) + = 3.00 tn-m. M(f-g) + = 3.00 tn-m.
M(a-c) - = 4.00 tn-m. M(c-f) - = 4.00 tn-m. M(f-g) - = 4.00 tn-m.
Mc + = 5.00 tn-m. Mf + = 5.00 tn-m. Mg + = 5.00 tn-m.
Mc - = 6.00 tn-m. Mf - = 6.00 tn-m. Mg - = 6.00 tn-m.

EJE 4-4
Viga 109 Viga 110 Viga 111

Ma + = 1.00 tn-m. Mb + = 1.00 tn-m. Mf + = 1.00 tn-m.


Ma - = 2.00 tn-m. Mb - = 2.00 tn-m. Mf - = 2.00 tn-m.
M(a-b) + = 3.00 tn-m. M(b-d) + = 3.00 tn-m. M(f-g) + = 3.00 tn-m.
M(a-b) - = 4.00 tn-m. M(b-d) - = 4.00 tn-m. M(f-g) - = 4.00 tn-m.
Mb + = 5.00 tn-m. Md + = 5.00 tn-m. Mg + = 5.00 tn-m.
Mb - = 6.00 tn-m. Md - = 6.00 tn-m. Mg - = 6.00 tn-m.
EJE 5-5
Viga 112 Viga 113 Viga 114

Ma + = 1.00 tn-m. Mc + = 1.00 tn-m. Md + = 1.00 tn-m.


Ma - = 2.00 tn-m. Mc - = 2.00 tn-m. Md - = 2.00 tn-m.
M(a-c) + = 3.00 tn-m. M(c-d) + = 3.00 tn-m. M(d-g) + = 3.00 tn-m.
M(a-c) - = 4.00 tn-m. M(c-d) - = 4.00 tn-m. M(d-g) - = 4.00 tn-m.
Mc + = 5.00 tn-m. Md + = 5.00 tn-m. Mg + = 5.00 tn-m.
Mc - = 6.00 tn-m. Md - = 6.00 tn-m. Mg - = 6.00 tn-m.

EJE 6-6
Viga 109 Viga 110 Viga 114

Ma + = 1.00 tn-m. Mc + = 1.00 tn-m. Md + = 1.00 tn-m.


Ma - = 2.00 tn-m. Mc - = 2.00 tn-m. Md - = 2.00 tn-m.
M(a-c) + = 3.00 tn-m. M(c-d) + = 3.00 tn-m. M(d-g) + = 3.00 tn-m.
M(a-c) - = 4.00 tn-m. M(c-d) - = 4.00 tn-m. M(d-g) - = 4.00 tn-m.
Mc + = 5.00 tn-m. Md + = 5.00 tn-m. Mg + = 5.00 tn-m.
Mc - = 6.00 tn-m. Md - = 6.00 tn-m. Mg - = 6.00 tn-m.

EJE 7-7
Viga 115 Viga 110 Viga 117

Ma + = 1.00 tn-m. Mc + = 1.00 tn-m. Md + = 1.00 tn-m.


Ma - = 2.00 tn-m. Mc - = 2.00 tn-m. Md - = 2.00 tn-m.
M(a-c) + = 3.00 tn-m. M(c-d) + = 3.00 tn-m. M(d-g) + = 3.00 tn-m.
M(a-c) - = 4.00 tn-m. M(c-d) - = 4.00 tn-m. M(d-g) - = 4.00 tn-m.
Mc + = 5.00 tn-m. Md + = 5.00 tn-m. Mg + = 5.00 tn-m.
Mc - = 6.00 tn-m. Md - = 6.00 tn-m. Mg - = 6.00 tn-m.
SMO

103

105

108
111
114

114

117
FACULTAD DE INGENIERA, ARQUITECTURA Y URBANISMO

ESCUELA PROFESIONAL DE INGENIERA CIVIL

Momentos de las Vigas del Primer Nivel (Direccin Y-Y)

EJE A-A
Viga 124 Viga 125 Viga 126

M1 + = M2 + = M3 + =
M1 - = M2 - = M3 - =
M(1-2) + = M(2-3) + = M(3-4) + =
M(1-2) - = M(2-3) - = M(3-4) - =
M2 + = M3 + = M4 + =
M2 - = M3 - = M4 - =

EJE A-A
Viga 127 Viga 128 Viga 129

M4 + = M5 + = M6 + =
M4 - = M5 - = M6 - =
M(4-5) + = M(5-6) + = M(6-7) + =
M(4-5) - = M(5-6) - = M(6-7) - =
M5 + = M6 + = M7 + =
M5 - = M6 - = M7 - =

EJE B-B
Viga 127 Viga 130 Viga 131

M4 + = M5 + = M6 + =
M4 - = M5 - = M6 - =
M(4-5) + = M(5-6) + = M(6-7) + =
M(4-5) - = M(5-6) - = M(6-7) - =
M5 + = M6 + = M7 + =
M5 - = M6 - = M7 - =

EJE C-C
Viga 132 Viga 125 Viga 126

M1 + = M2 + = M3 + =
M1 - = M2 - = M3 - =
M(1-2) + = M(2-3) + = M(3-4) + =
M(1-2) - = M(2-3) - = M(3-4) - =
M2 + = M3 + = M4 + =
M2 - = M3 - = M4 - =
EJE D-D
Viga 127 Viga 128 Viga 133

M4 + = M5 + = M6 + =
M4 - = M5 - = M6 - =
M(4-5) + = M(5-6) + = M(6-7) + =
M(4-5) - = M(5-6) - = M(6-7) - =
M5 + = M6 + = M7 + =
M5 - = M6 - = M7 - =

EJE E-E EJE F-F


Viga 134 Viga 125 Viga 126

M1 + = M2 + = M3 + =
M1 - = M2 - = M3 - =
M(1-2) + = M(2-3) + = M(3-4) + =
M(1-2) - = M(2-3) - = M(3-4) - =
M2 + = M3 + = M4 + =
M2 - = M3 - = M4 - =

EJE G-G
Viga 124 Viga 125 Viga 126

M1 + = M2 + = M3 + =
M1 - = M2 - = M3 - =
M(1-2) + = M(2-3) + = M(3-4) + =
M(1-2) - = M(2-3) - = M(3-4) - =
M2 + = M3 + = M4 + =
M2 - = M3 - = M4 - =

EJE G-G
Viga 127 Viga 128 Viga 129

M4 + = M5 + = M6 + =
M4 - = M5 - = M6 - =
M(4-5) + = M(5-6) + = M(6-7) + =
M(4-5) - = M(5-6) - = M(6-7) - =
M5 + = M6 + = M7 + =
M5 - = M6 - = M7 - =
SMO

126

129

131
126
133

126

126

129
Concreto Armado I

DISEO DE VIGAS POR FLEXIN

Direccin en X

EJE 1-1 : VIGA 101

Nudo a+ Nudo a- Claro (a-c)+


Mu = 0.68 tn - m Mu = 5.73 tn - m Mu = 3.58 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.54 cm2 As = 4.81 cm2 As = 2.92 cm2
a= 0.50 cm a= 4.53 cm a= 2.75 cm

USAR : (2N4) USAR : (2N6) USAR : (2N5)


As = 2.53 cm2 correcto As = 5.67 cm2 correcto As = 3.97 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.007 = 0.005
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 16.24 cm correcto bmn. = 15.62 cm correcto

Claro (a-c)- Nudo c+ Nudo c-


Mu = 1.66 tn - m Mu = 0.55 tn - m Mu = 4.54 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.32 cm2 1.25 cm 0.43 cm2 0.41 cm 3.75 cm2 3.53 cm
As = 1.32 cm2 As = 0.43 cm2 As = 3.75 cm2
a= 1.25 cm a= 0.41 cm a= 3.53 cm

USAR : (2N4) USAR : (2N4) USAR : (2N5)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 3.97 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


Diseo de Vigas por Flexin Pgina 15
Concreto Armado I

= 0.003 = 0.003 = 0.005


b = 0.022
b = 0.022
b = 0.022
mn. = 0.002 mn. = 0.002 mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto bmn. = 15.62 cm correcto

Diseo de Vigas por Flexin Pgina 16


Concreto Armado I

EJE 1-1 : VIGA 102

Nudo c+ Nudo c- Claro (c-e)+


Mu = 0.78 tn - m Mu = 2.71 tn - m Mu = 0.08 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.62 cm2 As = 2.19 cm2 As = 0.06 cm2
a= 0.58 cm a= 2.06 cm a= 0.06 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 2.53 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.003
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto

Claro (c-e)- Nudo e+ Nudo e-


Mu = 0.49 tn - m Mu = 0.67 tn - m Mu = 2.39 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
0.39 cm2 0.36 cm 0.53 cm2 0.50 cm 1.92 cm2 1.81 cm
As = 0.39 cm2 As = 0.53 cm2 As = 1.92 cm2
a= 0.36 cm a= 0.50 cm a= 1.81 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 2.53 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.003
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto
Diseo de Vigas por Flexin Pgina 17
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto

Diseo de Vigas por Flexin Pgina 18


Concreto Armado I

EJE 1-1 : VIGA 103

Nudo e+ Nudo e- Claro (e-g)+


Mu = 0.08 tn - m Mu = 4.05 tn - m Mu = 2.65 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.06 cm2 As = 3.33 cm2 As = 2.14 cm2
a= 0.06 cm a= 3.13 cm a= 2.01 cm

USAR : (2N4) USAR : (2N5) USAR : (2N4)


As = 2.53 cm2 correcto As = 3.97 cm2 correcto As = 2.53 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.005 = 0.003
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 15.62 cm correcto bmn. = 14.98 cm correcto

Claro (e-g)- Nudo g+ Nudo g-


Mu = 1.25 tn - m Mu = 0.10 tn - m Mu = 5.30 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
0.99 cm2 0.93 cm 0.08 cm2 0.07 cm 4.42 cm2 4.16 cm
As = 0.99 cm2 As = 0.08 cm2 As = 4.42 cm2
a= 0.93 cm a= 0.07 cm a= 4.16 cm

USAR : (2N4) USAR : (2N4) USAR : (2N6)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 5.67 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.007
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto
Diseo de Vigas por Flexin Pgina 19
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto bmn. = 16.24 cm correcto

Diseo de Vigas por Flexin Pgina 20


Concreto Armado I

EJE 2-2 : VIGA 104

Nudo a+ Nudo a- Claro (a-c)+


Mu = 1.00 tn - m Mu = 2.00 tn - m Mu = 3.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.79 cm2 As = 1.60 cm2 As = 2.43 cm2
a= 0.75 cm a= 1.51 cm a= 2.29 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 2.53 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.003
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto

Claro (a-c)- Nudo c+ Nudo c-


Mu = 4.00 tn - m Mu = 5.00 tn - m Mu = 6.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
3.28 cm2 3.09 cm 4.16 cm2 3.91 cm 5.06 cm2 4.76 cm
As = 3.28 cm2 As = 4.16 cm2 As = 5.06 cm2
a= 3.09 cm a= 3.91 cm a= 4.76 cm

USAR : (2N5) USAR : (2N6) USAR : (2N6)


As = 3.97 cm2 correcto As = 5.67 cm2 correcto As = 5.67 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.005 = 0.007 = 0.007
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto
Diseo de Vigas por Flexin Pgina 21
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 15.62 cm correcto bmn. = 16.24 cm correcto bmn. = 16.24 cm correcto

Diseo de Vigas por Flexin Pgina 22


Concreto Armado I

EJE 2-2 : VIGA 102

Nudo c+ Nudo c- Claro (c-e)+


Mu = 1.00 tn - m Mu = 2.00 tn - m Mu = 3.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.79 cm2 As = 1.60 cm2 As = 2.43 cm2
a= 0.75 cm a= 1.51 cm a= 2.29 cm

USAR : (2N5) USAR : (2N6) USAR : (2N6)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 2.53 cm2 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.003
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 correcto

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto bmn. = 14.98 cm correcto

Claro (c-e)- Nudo e+ Nudo e-


Mu = 4.00 tn - m Mu = 5.00 tn - m Mu = 6.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
3.28 cm2 3.09 cm 4.16 cm2 3.91 cm 5.06 cm2 4.76 cm
As = 3.28 cm2 As = 4.16 cm2 As = 5.06 cm2
a= 3.09 cm a= 3.91 cm a= 4.76 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 23
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 24


Concreto Armado I

EJE 2-2 : VIGA 105

Nudo f+ Nudo f- Claro (f-g)+


Mu = 1.00 tn - m Mu = 2.00 tn - m Mu = 3.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.79 cm2 As = 1.60 cm2 As = 2.43 cm2
a= 0.75 cm a= 1.51 cm a= 2.29 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (f-g)- Nudo g+ Nudo g-


Mu = 4.00 tn - m Mu = 5.00 tn - m Mu = 6.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
3.28 cm2 3.09 cm 4.16 cm2 3.91 cm 5.06 cm2 4.76 cm
As = 3.28 cm2 As = 4.16 cm2 As = 5.06 cm2
a= 3.09 cm a= 3.91 cm a= 4.76 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 25
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 26


Concreto Armado I

EJE 3-3 : VIGA 106

Nudo a+ Nudo a- Claro (a-c)+


Mu = 1.00 tn - m Mu = 2.00 tn - m Mu = 3.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.79 cm2 As = 1.60 cm2 As = 2.43 cm2
a= 0.75 cm a= 1.51 cm a= 2.29 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (a-c)- Nudo c+ Nudo c-


Mu = 4.00 tn - m Mu = 5.00 tn - m Mu = 6.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
3.28 cm2 3.09 cm 4.16 cm2 3.91 cm 5.06 cm2 4.76 cm
As = 3.28 cm2 As = 4.16 cm2 As = 5.06 cm2
a= 3.09 cm a= 3.91 cm a= 4.76 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 27
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 28


Concreto Armado I

EJE 3-3 : VIGA 107

Nudo c+ Nudo c- Claro (c-f)+


Mu = 1.00 tn - m Mu = 2.00 tn - m Mu = 3.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.79 cm2 As = 1.60 cm2 As = 2.43 cm2
a= 0.75 cm a= 1.51 cm a= 2.29 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (c-f)- Nudo f+ Nudo f-


Mu = 4.00 tn - m Mu = 5.00 tn - m Mu = 6.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
3.28 cm2 3.09 cm 4.16 cm2 3.91 cm 5.06 cm2 4.76 cm
As = 3.28 cm2 As = 4.16 cm2 As = 5.06 cm2
a= 3.09 cm a= 3.91 cm a= 4.76 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 29
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 30


Concreto Armado I

EJE 3-3 : VIGA 108

Nudo f+ Nudo f- Claro (f-g)+


Mu = 1.00 tn - m Mu = 2.00 tn - m Mu = 3.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.79 cm2 As = 1.60 cm2 As = 2.43 cm2
a= 0.75 cm a= 1.51 cm a= 2.29 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (f-g)- Nudo g+ Nudo g-


Mu = 4.00 tn - m Mu = 5.00 tn - m Mu = 6.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
3.28 cm2 3.09 cm 4.16 cm2 3.91 cm 5.06 cm2 4.76 cm
As = 3.28 cm2 As = 4.16 cm2 As = 5.06 cm2
a= 3.09 cm a= 3.91 cm a= 4.76 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 31
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 32


Concreto Armado I
EJE 4-4 : VIGA 109

Nudo a+ Nudo a- Claro (a-b)+


Mu = 1.00 tn - m Mu = 2.00 tn - m Mu = 3.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.79 cm2 As = 1.60 cm2 As = 2.43 cm2
a= 0.75 cm a= 1.51 cm a= 2.29 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (a-b)- Nudo b+ Nudo b-

Mu = 4.00 tn - m Mu = 5.00 tn - m Mu = 6.00 tn - m


b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
3.28 cm2 3.09 cm 4.16 cm2 3.91 cm 5.06 cm2 4.76 cm
As = 3.28 cm2 As = 4.16 cm2 As = 5.06 cm2
a= 3.09 cm a= 3.91 cm a= 4.76 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 33
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 34


Concreto Armado I

EJE 4-4 : VIGA 110

Nudo b+ Nudo b- Claro (b-d)+


Mu = 1.00 tn - m Mu = 2.00 tn - m Mu = 3.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.79 cm2 As = 1.60 cm2 As = 2.43 cm2
a= 0.75 cm a= 1.51 cm a= 2.29 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (b-d)- Nudo d+ Nudo d-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 35
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 36


Concreto Armado I

EJE 4-4 : VIGA 111

Nudo c+ Nudo c- Claro (c-d)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (c-d)- Nudo d+ Nudo d-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 37
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 38


Concreto Armado I

EJE 5-5 : VIGA 112

Nudo a+ Nudo a- Claro (a-c)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (a-c)- Nudo c+ Nudo c-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 39
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 40


Concreto Armado I

EJE 5-5 : VIGA 113

Nudo c+ Nudo c- Claro (c-d)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (c-d)- Nudo d+ Nudo d-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 41
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 42


Concreto Armado I

EJE 5-5 : VIGA 114

Nudo d+ Nudo d- Claro (d-g)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (d-g)- Nudo g+ Nudo g-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 43
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 44


Concreto Armado I

EJE 6-6 : VIGA 109

Nudo a+ Nudo a- Claro (a-c)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (a-c)- Nudo c+ Nudo c-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 45
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 46


Concreto Armado I

EJE 6-6 : VIGA 110

Nudo c+ Nudo c- Claro (c-d)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (c-d)- Nudo d+ Nudo d-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 47
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 48


Concreto Armado I

EJE 6-6 : VIGA 114

Nudo d+ Nudo d- Claro (d-g)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (d-g)- Nudo g+ Nudo g-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 49
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 50


Concreto Armado I

EJE 7-7 : VIGA 115

Nudo a+ Nudo a- Claro (a-c)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (a-c)- Nudo c+ Nudo c-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 51
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 52


Concreto Armado I

EJE 7-7 : VIGA 110

Nudo c+ Nudo c- Claro (c-d)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (c-d)- Nudo d+ Nudo d-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 53
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 54


Concreto Armado I

EJE 7-7 : VIGA 117

Nudo d+ Nudo d- Claro (d-g)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (d-g)- Nudo g+ Nudo g-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 55
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 56


Concreto Armado I

GAS POR FLEXIN

Diseo de Vigas por Flexin Pgina 57


Concreto Armado I

Diseo de Vigas por Flexin Pgina 58


Concreto Armado I

Diseo de Vigas por Flexin Pgina 59


Concreto Armado I

Diseo de Vigas por Flexin Pgina 60


Concreto Armado I

Diseo de Vigas por Flexin Pgina 61


Concreto Armado I

Diseo de Vigas por Flexin Pgina 62


Concreto Armado I

Diseo de Vigas por Flexin Pgina 63


Concreto Armado I

Diseo de Vigas por Flexin Pgina 64


Concreto Armado I

Diseo de Vigas por Flexin Pgina 65


Concreto Armado I

Diseo de Vigas por Flexin Pgina 66


Concreto Armado I

Diseo de Vigas por Flexin Pgina 67


Concreto Armado I

Diseo de Vigas por Flexin Pgina 68


Concreto Armado I

Diseo de Vigas por Flexin Pgina 69


Concreto Armado I

Diseo de Vigas por Flexin Pgina 70


Concreto Armado I

Diseo de Vigas por Flexin Pgina 71


Concreto Armado I

Diseo de Vigas por Flexin Pgina 72


Concreto Armado I

Diseo de Vigas por Flexin Pgina 73


Concreto Armado I

Diseo de Vigas por Flexin Pgina 74


Concreto Armado I

Diseo de Vigas por Flexin Pgina 75


Concreto Armado I

Diseo de Vigas por Flexin Pgina 76


Concreto Armado I

Diseo de Vigas por Flexin Pgina 77


Concreto Armado I

Diseo de Vigas por Flexin Pgina 78


Concreto Armado I

Diseo de Vigas por Flexin Pgina 79


Concreto Armado I

Diseo de Vigas por Flexin Pgina 80


Concreto Armado I

Diseo de Vigas por Flexin Pgina 81


Concreto Armado I

Diseo de Vigas por Flexin Pgina 82


Concreto Armado I

Diseo de Vigas por Flexin Pgina 83


Concreto Armado I

Diseo de Vigas por Flexin Pgina 84


Concreto Armado I

Diseo de Vigas por Flexin Pgina 85


Concreto Armado I

Diseo de Vigas por Flexin Pgina 86


Concreto Armado I

Diseo de Vigas por Flexin Pgina 87


Concreto Armado I

Diseo de Vigas por Flexin Pgina 88


Concreto Armado I

Diseo de Vigas por Flexin Pgina 89


Concreto Armado I

Diseo de Vigas por Flexin Pgina 90


Concreto Armado I

Diseo de Vigas por Flexin Pgina 91


Concreto Armado I

Diseo de Vigas por Flexin Pgina 92


Concreto Armado I

Diseo de Vigas por Flexin Pgina 93


Concreto Armado I

Diseo de Vigas por Flexin Pgina 94


Concreto Armado I

Diseo de Vigas por Flexin Pgina 95


Concreto Armado I

Diseo de Vigas por Flexin Pgina 96


Concreto Armado I

Diseo de Vigas por Flexin Pgina 97


Concreto Armado I

Diseo de Vigas por Flexin Pgina 98


Concreto Armado I

DISEO DE VIGAS POR FLEXIN

Direccin en Y

EJE A-A : VIGA 124

Nudo 1+ Nudo 1- Claro (1-2)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (1-2)- Nudo 2+ Nudo 2-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


Diseo de Vigas por Flexin Pgina 99
Concreto Armado I

= 0.000 = 0.000 = 0.000


b = 0.022
b = 0.022
b = 0.022
mn. = 0.002 mn. = 0.002 mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 100


Concreto Armado I

EJE A-A : VIGA 125

Nudo 2+ Nudo 2- Claro (2-3)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (2-3)- Nudo 3+ Nudo 3-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 101
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 102


Concreto Armado I

EJE A-A : VIGA 126

Nudo 3+ Nudo 3- Claro (3-4)+


Mu = 1.70 tn - m Mu = 5.00 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 1.36 cm2 As = 4.16 cm2 As = 0.70 cm2
a= 1.28 cm a= 3.91 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (3-4)- Nudo 4+ Nudo 4-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 103
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 104


Concreto Armado I

EJE A-A : VIGA 127

Nudo 4+ Nudo 4- Claro (4-5)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (4-5)- Nudo 5+ Nudo 5-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 105
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 106


Concreto Armado I

EJE A-A : VIGA 128

Nudo 5+ Nudo 5- Claro (5-6)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (5-6)- Nudo 6+ Nudo 6-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 107
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 108


Concreto Armado I

EJE A-A : VIGA 129

Nudo 6+ Nudo 6- Claro (6-7)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (6-7)- Nudo 7+ Nudo 7-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 109
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 110


Concreto Armado I

EJE B-B : VIGA 127

Nudo 4+ Nudo 4- Claro (4-5)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (4-5)- Nudo 5+ Nudo 5-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 111
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 112


Concreto Armado I

EJE B-B : VIGA 130

Nudo 5+ Nudo 5- Claro (5-6)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (5-6)- Nudo 6+ Nudo 6-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 113
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 114


Concreto Armado I

EJE B-B : VIGA 131

Nudo 6+ Nudo 6- Claro (6-7)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (6-7)- Nudo 7+ Nudo 7-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 115
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 116


Concreto Armado I

EJE C-C : VIGA 132

Nudo 1+ Nudo 1- Claro (1-2)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (1-2)- Nudo 2+ Nudo 2-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 117
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 118


Concreto Armado I

EJE C-C : VIGA 125

Nudo 2+ Nudo 2- Claro (2-3)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (2-3)- Nudo 3+ Nudo 3-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 119
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 120


Concreto Armado I

EJE C-C : VIGA 126

Nudo 3+ Nudo 3- Claro (3-4)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (3-4)- Nudo 4+ Nudo 4-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 121
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 122


Concreto Armado I

EJE D-D : VIGA 127

Nudo 4+ Nudo 4- Claro (4-5)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (4-5)- Nudo 5+ Nudo 5-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 123
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 124


Concreto Armado I

EJE D-D : VIGA 128

Nudo 5+ Nudo 5- Claro (5-6)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (5-6)- Nudo 6+ Nudo 6-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 125
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 126


Concreto Armado I

EJE D-D : VIGA 133

Nudo 6+ Nudo 6- Claro (6-7)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (6-7)- Nudo 7+ Nudo 7-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 127
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 128


Concreto Armado I

EJE E-E : VIGA 134

Nudo 1+ Nudo 1- Claro (1-2)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (1-2)- Nudo 2+ Nudo 2-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 129
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 130


Concreto Armado I

EJE F-F : VIGA 125

Nudo 2+ Nudo 2- Claro (2-3)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (2-3)- Nudo 3+ Nudo 3-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 131
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 132


Concreto Armado I

EJE F-F : VIGA 126

Nudo 3+ Nudo 3- Claro (3-4)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (3-4)- Nudo 4+ Nudo 4-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 133
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 134


Concreto Armado I

EJE G-G : VIGA 124

Nudo 1+ Nudo 1- Claro (1-2)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (1-2)- Nudo 2+ Nudo 2-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 135
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 136


Concreto Armado I

EJE G-G : VIGA 125

Nudo 2+ Nudo 2- Claro (2-3)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (2-3)- Nudo 3+ Nudo 3-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 137
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 138


Concreto Armado I

EJE G-G : VIGA 126

Nudo 3+ Nudo 3- Claro (3-4)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (3-4)- Nudo 4+ Nudo 4-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 139
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 140


Concreto Armado I

EJE G-G : VIGA 127

Nudo 4+ Nudo 4- Claro (4-5)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (4-5)- Nudo 5+ Nudo 5-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 141
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 142


Concreto Armado I

EJE G-G : VIGA 128

Nudo 5+ Nudo 5- Claro (5-6)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (5-6)- Nudo 6+ Nudo 6-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 143
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 144


Concreto Armado I

EJE G-G : VIGA 129

Nudo 6+ Nudo 6- Claro (6-7)+


Mu = 0.76 tn - m Mu = 1.98 tn - m Mu = 0.88 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
As = 0.60 cm2 As = 1.59 cm2 As = 0.70 cm2
a= 0.56 cm a= 1.49 cm a= 0.65 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 2.53 cm2 correcto As = 2.53 cm2 correcto As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.003 = 0.003 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 correcto mx. = 0.016 correcto mx. = 0.016 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 14.98 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Claro (6-7)- Nudo 7+ Nudo 7-


Mu = 2.00 tn - m Mu = 22.00 tn - m Mu = 12.00 tn - m
b= 25 cm b= 25 cm b= 25 cm
h= 40 cm h= 40 cm h= 40 cm
r= 4 cm r= 4 cm r= 4 cm
e= 0.95 cm e= 0.95 cm e= 0.95 cm
d= 33.78 cm d= 33.78 cm d= 33.78 cm
= 0.90 = 0.90 = 0.90
fy = 4200 kg/cm2 fy = 4200 kg/cm2 fy = 4200 kg/cm2
f'c = 210 kg/cm2 f'c = 210 kg/cm2 f'c = 210 kg/cm2
= 0.85 = 0.85 = 0.85
1.60 cm2 1.51 cm 25.61 cm2 24.11 cm 11.10 cm2 10.45 cm
As = 1.60 cm2 As = 25.61 cm2 As = 11.10 cm2
a= 1.51 cm a= 24.11 cm a= 10.45 cm

USAR : (2N4) USAR : (2N4) USAR : (2N4)


As = 0.00 cm2 corregir As = 0.00 cm2 corregir As = 0.00 cm2 corregir

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:


= 0.000 = 0.000 = 0.000
b = 0.022
b = 0.022
b = 0.022
mn. = 0.002
mn. = 0.002
mn. = 0.002
mx. = 0.016 corregir mx. = 0.016 corregir mx. = 0.016 corregir
Diseo de Vigas por Flexin Pgina 145
Concreto Armado I

Verficacin de la cuantia: Verficacin de la cuantia: Verficacin de la cuantia:

bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto bmn. = 12.44 cm correcto

Diseo de Vigas por Flexin Pgina 146


Concreto Armado I

GAS POR FLEXIN

Diseo de Vigas por Flexin Pgina 147


Concreto Armado I

Diseo de Vigas por Flexin Pgina 148


Concreto Armado I

Diseo de Vigas por Flexin Pgina 149


Concreto Armado I

Diseo de Vigas por Flexin Pgina 150


Concreto Armado I

Diseo de Vigas por Flexin Pgina 151


Concreto Armado I

Diseo de Vigas por Flexin Pgina 152


Concreto Armado I

Diseo de Vigas por Flexin Pgina 153


Concreto Armado I

Diseo de Vigas por Flexin Pgina 154


Concreto Armado I

Diseo de Vigas por Flexin Pgina 155


Concreto Armado I

Diseo de Vigas por Flexin Pgina 156


Concreto Armado I

Diseo de Vigas por Flexin Pgina 157


Concreto Armado I

Diseo de Vigas por Flexin Pgina 158


Concreto Armado I

Diseo de Vigas por Flexin Pgina 159


Concreto Armado I

Diseo de Vigas por Flexin Pgina 160


Concreto Armado I

Diseo de Vigas por Flexin Pgina 161


Concreto Armado I

Diseo de Vigas por Flexin Pgina 162


Concreto Armado I

Diseo de Vigas por Flexin Pgina 163


Concreto Armado I

Diseo de Vigas por Flexin Pgina 164


Concreto Armado I

Diseo de Vigas por Flexin Pgina 165


Concreto Armado I

Diseo de Vigas por Flexin Pgina 166


Concreto Armado I

Diseo de Vigas por Flexin Pgina 167


Concreto Armado I

Diseo de Vigas por Flexin Pgina 168


Concreto Armado I

Diseo de Vigas por Flexin Pgina 169


Concreto Armado I

Diseo de Vigas por Flexin Pgina 170


Concreto Armado I

Diseo de Vigas por Flexin Pgina 171


Concreto Armado I

Diseo de Vigas por Flexin Pgina 172


Concreto Armado I

Diseo de Vigas por Flexin Pgina 173


Concreto Armado I

Diseo de Vigas por Flexin Pgina 174


Concreto Armado I

Diseo de Vigas por Flexin Pgina 175


Concreto Armado I

Diseo de Vigas por Flexin Pgina 176


Concreto Armado I

Diseo de Vigas por Flexin Pgina 177


Concreto Armado I

Diseo de Vigas por Flexin Pgina 178


Concreto Armado I

Diseo de Vigas por Flexin Pgina 179


Concreto Armado I

Diseo de Vigas por Flexin Pgina 180


Concreto Armado I

Diseo de Vigas por Flexin Pgina 181


Concreto Armado I

Diseo de Vigas por Flexin Pgina 182


Concreto Armado I

Diseo de Vigas por Flexin Pgina 183


Concreto Armado I

Diseo de Vigas por Flexin Pgina 184


Concreto Armado I

Diseo de Vigas por Flexin Pgina 185


Concreto Armado I

Diseo de Vigas por Flexin Pgina 186


Concreto Armado I

Diseo de Vigas por Flexin Pgina 187


Concreto Armado I

Diseo de Vigas por Flexin Pgina 188


Concreto Armado I

Diseo de Vigas por Flexin Pgina 189


Concreto Armado I

Diseo de Vigas por Flexin Pgina 190


Concreto Armado I

Diseo de Vigas por Flexin Pgina 191


Concreto Armado I

Diseo de Vigas por Flexin Pgina 192


Concreto Armado I

Diseo de Vigas por Flexin Pgina 193


Concreto Armado I

Diseo de Vigas por Flexin Pgina 194