Professional Documents
Culture Documents
YANGONREGIONGOVERNMENT
JANUARY2015
JAPANINTERNATIONALCOOPERATIONAGENCY
ALMECCORPORATION
ORIENTALCONSULTANTSCO.,LTD. EI
NIPPONKOEICO.,LTD. JR
14-212
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Location Map
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(Current Condition)
Table of Contents
1 INTRODUCTION................................................................................................................. 1-1
i
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2.7.1 Type of Interchanges .......................................................................................... 2-18
4.1.5 Further Schedule for Environmental and Social Considerations ......................... 4-12
ii
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
5 PROJECT COST ESTIMATES AND ECONOMIC EVALUATION ....................................... 5-1
5.1.4 Traffic Control System and Toll Collection System (for reference) ...................... 5-12
iii
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
7.4 Suggestions for Appropriate and Efficient O/M of Expressways ................................ 7-15
7.4.3 Suggestions for Inspection and Maintenance Works of Expressways ................ 7-17
iv
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
List of Figures
Figure 1.1.2 Term-wise Road Network Development in YUTRA M/P ............................... 1-2
Figure 2.2.2 Typical Cross Sections of Ring Roads in YUTRA ......................................... 2-3
Figure 2.3.3 Concept of New Logistic Route with YUEX/YORR ....................................... 2-8
Figure 2.5.2 Typical Cross Section of Existing Road (Built-up Area) .............................. 2-13
Figure 2.5.3 Typical Cross Section of YUEX (Built-up Area) .......................................... 2-14
Figure 2.5.4 Typical Cross Section of YUEX (Non Built-up Area 1) ................................ 2-14
Figure 2.5.5 Typical Cross Section of YUEX (Non Built-up Area 2) ................................ 2-15
Figure 2.5.6 Typical Cross Section of YORR (Initial Stage) ............................................ 2-15
Figure 2.5.7 Typical Cross Section of YORR (Ultimate Stage: At-graded) ..................... 2-16
Figure 2.5.8 Typical Cross Section of YORR (Ultimate Stage: Elevated) ....................... 2-16
v
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Figure 2.8.3 Connection between YUEX and YORR (JCT-01) ....................................... 2-24
Figure 3.2.1 Typical Cross Section of the Urban Expressway Viaduct ............................. 3-2
Figure 3.2.8 Span Arrangement of Crossing Hlaing River on YUEX W Section ............. 3-12
Figure 3.2.9 Span Arrangement of Crossing Inya Lake on YUEX M Section ................. 3-13
Figure 3.3.1 Flow Chart for Overall Construction of Viaduct ........................................... 3-22
Figure 3.3.3 Sketch for Construction of Screw Steel Pile ............................................... 3-23
Figure 3.3.6 Outline of Lifting Erection Method of PC-U Composite Girder .................... 3-25
vi
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Figure 3.3.7 Sample of Erection of Steel Box Girder at Intersection .............................. 3-25
Figure 7.2.2 Typical Cross Section of the Yangon-Mandalay Expressway ....................... 7-4
Figure 7.2.8 Instalment of Lighting System and Guard Rails on the Expressway ............ 7-7
Figure 7.3.1 Organization Chart of expressway maintenance unit (EMU) ........................ 7-7
Figure 7.3.3 Annual and O/M budget for the Yangon-Mandalay Expressway................. 7-10
Figure 7.3.5 Toll Gate and ETC System on the Yangon-Mandalay Expressway ............ 7-14
Figure 7.4.3 Outline of procedures of inspection and maintenance works ..................... 7-19
Figure 7.4.4 Outline of procedures of inspection and maintenance works ..................... 7-19
Figure 7.4.5 Outline of image and photo of ETC System in Japan ................................. 7-20
Figure 7.4.6 Experiences of mitigation of traffic congestion at toll gate in Japan ........... 7-21
Figure 7.4.7 Images of road side facilities and traffic patrolling team ............................. 7-22
vii
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
List of Tables
Table 1.1.1 Major Road Projects proposed for Each Term ............................................... 1-2
Table 2.4.1 Estimated Traffic Volume of YUEX (and YORR) in 2035 ............................. 2-11
Table 2.4.2 Required Number of Lanes of YUEX (and YORR) in 2035 .......................... 2-11
Table 3.2.5 Span Arrangement of Special Sections on YUEX N, R1 & E Section ............ 3-8
Table 3.2.6 Span Arrangement of Special Sections on YUEX R2 Section ....................... 3-8
Table 3.2.7 Span Arrangement of Special Sections on YUEX S Section ......................... 3-9
Table 3.2.8 Span Arrangement of Special Sections on YUEX W & M Section ................. 3-9
Table 3.2.11 Applicability Criteria of Foundation Types for Main Bridge ......................... 3-19
viii
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Table 4.1.3 Number of Affected Premises/Persons in R1-2 Section ................................ 4-5
Table 4.1.11 Tentative Schedule for Environmental and Social Considerations ............. 4-12
Table 5.1.12 Unit Cost of Traffic Control System and Toll Collection System ................. 5-12
Table 5.1.13 Estimated Cost of Traffic Control System and Toll Collection System ....... 5-12
Table 7.2.4 Comparison of the Number of Deaths on the Expressway ............................ 7-5
ix
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Table 7.3.1 The Outline of Tasks of Departments in EMU ................................................ 7-8
Table 7.3.2 List of Regional Head Offices and Operation Offices of EMU ........................ 7-8
Table 7.3.3 Annual and O/M budget for the Yangon-Mandalay Expressway .................... 7-9
Table 7.3.6 List of Road Maintenance Equipment / Machineries owned by EMU .......... 7-12
Table 7.3.7 List of Asphalt Pavement Equipment / Machineries owned by EMU ............ 7-12
x
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
List of Abbreviations
dir. : direction
FS : Feasibility Study
IC : Interchange
JCT : Junction
xi
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
M/P : Master Plan
SUDP : The Project for Strategic Urban Development Plan of the Greater Yangon
YGN : Yangon
YUTRA : The Project for Comprehensive Urban Transport Plan of the Greater Yangon
SC : Sub-center
TB : Toll Barrier
xii
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
USD : United States Dollars
xiii
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
CHAPTER 1
INTRODUCTION
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
1 INTRODUCTION
Under these circumstances, Yangon Region Government and JICA agreed to launch a
project named The Greater Yangon Urban Development Programme in May 2012.
Under the framework of this Programme, The project for Strategic Urban Development
Plan of the Greater Yangon (SUDP) started in August 2012 focusing mainly on the urban
development and land use aspects of the Yangon City. As the next step following this
project, Yangon Region Government and JICA agreed in September 2012 to start The
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA) to
prepare a comprehensive urban transport master plan in line with the above-mentioned
strategic urban development plan, so as to provide efficient, safe, comfortable and
environmentally friendly transport services to the people in the Greater Yangon, in order to
contribute to its balanced, inclusive and sustainable growth.
In the transport master plan (YUTRA M/P), the Do-maximum road network was
proposed as shown in Figure 1.1.2. The backbone of the network marked in red consists
of an inner ring road, an outer ring road and radial roads for both arterial roads and
expressways.
Based on the results of the traffic demand forecast and the recommended implementation
1-1
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
programme including the funding, the term-wise development plan of the road network
was established in YUTRA M/P as presented below.
Table 1.1.1 shows the major projects proposed by YUTRA M/P by each term.
Table 1.1.1 Major Road Projects proposed for Each Term
Term
Major Road Projects
(Target Year)
1) Northern Radial Section of Yangon Urban Expressway (extension of the existing
Yangon-Mandalay Expressway)
Mid Term 2) Inner Half Ring Section of Yangon Urban Expressway (eastern half of the ring road)
(by 2025) 3) Eastern Radial Section of Yangon Urban Expressway along the Road No.2
4) Improvement of the arterial roads along the above Yangon Urban Expressways
5) Outer Ring Arterial Road along Road No.7
1) Inner Half Ring Section of Yangon Urban Expressway (western half of the ring
road)
Long Term 2) Western Radial Section of Yangon Urban Expressway along Road No.5
(by 2035) 3) Trans-connected Section of Yangon Urban Expressway along Parami Road
4) Improvement of the arterial roads along the above expressways
5) Outer Ring Arterial Road
after 2035 1) Outer Ring Expressway
(for reference) 2) Improvement of the arterial roads along the above expressways
To accelerate the implementation of the above proposed projects, the further detailed
1-2
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
study focussing for YUEX, Data Collection Survey on Yangon Urban Expressway
(YUEX), was commenced from the end of July 2014 to prepare the basic information for
the next step of the study such as Feasibility Study.
YNM Expressway
(6.7km)
MSection
1-3
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
1.4 Survey Schedule
The schedule of the data collection survey is shown in Figure 1.4.1.
This survey is conducted from the mid of July 2014 until the end of August 2014.
July August afterSep.2014
Work Preparatory
in Works Reporting
Japan
SiteReconnaissance
Road
Work Planning
in
Myanmar Structure O/M
Planning Planning
Environmental
PreSurvey
Report DFR FR
2) UMRT No.1
1-4
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
As shown in the figure, the Data Collection Surveys under YUTRA have been conducted
for the following projects proposed in YUTRA M/P.
This report has prepared for the YUEX on the above and the member of the survey team
is summarized in Table 1.5.1.
Table 1.5.1 Survey Team Members
1-5
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
1.6 Discussions with Concerned Authorities during Survey
Table 1.6.1 shows the summary of the discussions with the concerned authorities.
Table 1.6.1 Summary of Discussions (for reference only)
1-6
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
1-7
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
CHAPTER 2
ROAD PLANNING
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2 ROAD PLANNING
DHSHDs classification seems comparatively suitable for the urban expressway. The
typical class section introduced in the guideline is shown in Figure 2.1.1.
Table 2.1.2 Road Classification by DHSHD
2-1
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
As seen in the above figure, the expressway is still likely inter-city road with wider ROW.
The urban expressway proposed in this survey is located in the built-up area and the
current available design standard or regulation in Myanmar might not be suitable for the
urban expressway.
Accordingly, the AASHTO and Japanese Standard may be referred to wherever the
Myanmar standard might not be sufficient.
2-2
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
The proposed expressway route by SUDP was reviewed by YUTRA with the traffic
demand analysis and the available land space to construct the expressway especially in
the densely developed area. The development concept of the inner ring road and the
outer ring road is presented below.
Inner Ring Road
2-3
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
The route of the inner ring road is proposed along the existing arterial roads which has
basically 100ft (=30m) ROW according to the road classification of DHSHD (Major Roads
in Table 2.1.2). Figure 2.2.2 shows the term-wise development of the expressway
network proposed by YUTRA.
Expressway Expressway
Network Network
in 2025 in 2035
Expressway
Network
after 2035
2-4
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Figure 2.2.4 shows the outer ring roads (toll road network) in Asian cities. The estimated
population of Yangon City in 2035 is similar with Jakarta, Bangkok and Tokyo which have
outer and inner rind roads as shown in the figure below.
2-5
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
sub-centers/newtowns were proposed with the urban development section of YCDC.
The outer ring road is generally proposed along the proposed sub-centers/newtowns and
the inner ring road (YUEX) will strengthen the east-west corridors which have less road
network than the north-south corridors in the city, connecting the proposed sub-centers
(Hlaing Tharya, Mindama, Dagon Myothit) and the outer ring road. The inner ring road
and the outer ring road are expected to accelerate the decentralization concept.
Currently the development of the eastern area (north-east by the new sub-centers and
new townships and the south-east by Thilawa SEZ) is rapidly in progress. The proposed
inner road and the outer ring road toward 2025 (mid-term development target of YUTRA)
are expected to be a backbone of these developments formulating an circular road
network in the eastern area.
This circular network will connect with Thilawa SEZ, National Highways (No.1 and No.2)
and the future new airport via the existing expressway (Yangon-NayPyiTaw-Mandalay
Expressway) and will be expected to be a logistic artery.
Figure 2.3.2 presents the general development concept of the inner ring road (both
expressway and arterial roads) and the outer ring road (arterial road) toward 2025
(Mid-term development plan of YUTRA).
2-6
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Legend:
DagonBridge(existing6lanes)
Newtownunderconstruction (DagonSeikan)under DHSHD
ProposedNewtown(Thanlyin) under YCDC
The relevant development projects shown in the above figure are briefly introduced below.
According to City Planning and Land Administration Department of YCDC, the following
development will be launched before 2025 (mid-term target of YUTRA).
Table 2.3.1 Sub-centers and Newtowns around YUEX/YORR
2-7
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Team has considered that the Road No.7 shall be improved based on the concept of
YUTRA as shown in Figure 2.2.2 with the geometric standard of the expressway.
On 29 August 2014, YUEX Survey Team had a meeting with the Head of Roads and
Bridges, YCDC and suggested that the Road No.7 should be improved as mentioned
above (ROW including the future expressway space, proper geometric standard for future
expressway).
The Thilawa SEZ is one of the national level strategic industrial development projects,
which has been supported by the Government of Japan as well. The role of international
gateway will be shifted from the existing Yangon Main Ports to the Thilawa Port. In order
to make the Thilawa Port fully functioning as the countrys gateway, corresponding land
transport systems should also be improved in parallel.
The proposed concept of the new logistic route with YUEX and YORR is presented in
Figure 2.3.3.
Legend:
Truck shallbeallowedtousetheexistingexpressway.
RoadNo.7shallbeimproved asapartofYORR.
Newtruckterminalshallbelocatedalongthenew
logisticroute.
RoadNo.2shall beimproved.
Accessbetween DagonBridgeandRoadNo.2shallbe
improved.
DagonBridgewillbemaximallyutilized bytheabove
measures.
Truckshallbeallowedtousetheproposed YUEXbut
shall beprohibited tousethearterialroads
underneaththeYUEX.
2-8
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2.3.4 Airports (YIA and HIA)
Air traffic demand of domestic flights is increasing recently and it is expected to continue in
future due to growth of Myanmar economy and other traffic mode (roads, railways, sea
and inland water transports). Regarding number of international air passengers and cargo
also rapidly increase mainly Yangon International Airport (YIA), leading to saturation of the
airport capacity of YIA having one runway.
Based on the adequate airport development policy for Yangon Metropolitan area, the new
airport (HIA: Hanthawaddy International Airport) was under construction and will start
operated in 2018.
Figure 2.3.4 shows the proposed accesses for HIA. The inner ring expressway (YUEX)
is proposed to connect directly with the road access to HIA.
2-9
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2.4 Traffic Demand Forecast and Number of Lanes
Based on past trends, future land use planned by SUDP, national framework estimated by
MYT-Plan and a series of GIS analysis, the future socio-economic framework was
prepared by YUTRA. The base year travel demand analysis and the development of travel
demand forecast models have been developed and described in detail in Volume II,
Chapter 2 of the main report of YUTRA.
Figure 2.4.1 shows the volume/capacity ratio of the road network after the modal split with
the proposed public transportation such as MRT, etc., based on the traffic demand
forecast model by YUTRA.
Existing Do-nothing
Condition Case
(2013) (2035)
Do-YUTRA
Case
(2035)
2-10
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
The traffic assignment along the proposed route of YUEX on the demand forecast model
was distributed with the following conditions.
(1) It will be very hard to widen the existing arterial roads especially in densely developed
area. However, as shown in Figure 2.4.1, the volume/capacity ratio will exceed 1.0 in case
of Do-nothing. Therefore the elevated road was introduced in the model to expand the
capacity of the existing arterial roads.
(2) The number of lanes of the existing arterial roads underneath YUEX was unchanged from
the existing condition (basically 6 lanes) and the several patterns were studied to
determine the number of lanes for the elevated
road (YUEX) on the existing arterial roads.
3 4
as a feasibility study. 8
Typeof TrafficVolume(pcu/day/bothdir.)atYUEXsections
Roads 1 2 3 4 5 6 7 8 9 10 11
Expressway 60,584 43,559 34,418 24,057 0 0 11,912 40,910 31,177 27,362 39,046
Arterial 23,722 49,859 27,788 51,595 22,646 11,501 15,033 26,228 31,783 38,065 28,087
Note: Refer to Figure 2.4.2 for the location of each section.
Source: YUTRA Study Team
Typeof RequiredNumberofLanes(bothdir.)atYUEXsections
Roads 1 2 3 4 5 6 7 8 9 10 11
Expressway 4 4 2 2 0 0 2 3 2 2 3
Arterial 2 4 3 4 2 2 2 2 4 4 3
Note: Refer to Figure 2.4.2 for the location of each section.
Source: YUEX Survey Team
2-11
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
The major findings on the estimated number of lanes are listed below.
(1) The maximum number of lanes for the expressway is 4 lanes for both directions.
(2) The required number of lanes for the sections No. 3, 4, 9, 10 of the expressway is
calculated to be 2 lanes for both directions. However the minimum number of lanes of the
expressway shall be 4 (2+2) lanes for both directions concerning the slow lane and
passing lane. Necessity of 4 lanes for the expressway could be justified taking into
account the recent rapid development along the Road No.2, No.4 and No.5.
(3) The number of lanes for the section No.7 (CBD area on Bogyoke Aung San Road) is also
calculated to be 2 lanes. The characteristic of the traffic of this section is through traffic
because of no interchange is provided. In the YUTRA, new public transport systems
such as BRT or LRT were introduced for CBD area in order to reduce the traffic volume.
Therefore the section No.7 (S Section of YUEX) could be merged into the section No.11
(M Section of YUEX). This issue shall be further studied in detailed during the next study
such as the feasibility study.
YUEX YUEX
RdNo.5 RdNo.5
Public Transport
CBD CBD
YORR YORR
With the route passing on CBD Without the route passing on CBD
Source: YUEX Survey Team
Figure 2.4.3 Route Options for Further Detailed Study
(4) The maximum number of lanes for the arterial roads is 4 lanes for both directions even
though the current number of the lanes is 6 lanes. It means that the BRT lanes could be
able to be provided for arterial roads underneath the YUEX.
2-12
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2.5 Definitive Route and Typical Cross Sections
The typical cross section of YUEX in the built-up area is designed within the existing ROW
(100ft=30m) of the arterial roads as shown in Figure 2.5.1.
30m
Accordingly the representative cross section of the existing arterial roads is assumed as
presented in Figure 2.5.2 for further consideration of the typical cross sections of YUEX.
2-13
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
The elevated expressway is proposed on the existing arterial roads as shown in Figure
2.5.3.
2.5m width of the road shoulders on the expressway is provided along the alignment for
emergency parking and road operation and maintenance services. The road shoulder
could be omitted by the provision of the parking bay (lay-bay space) with certain intervals
(i.e. 200m) on the expressway.
The land acquisition for YUEX in the non built-up area will be relatively easier than that in
the built-up area and thus the elevated structure is not proposed in terms of construction
cost saving.
The access-controlled expressway by the above cross section will divide the surrounding
area along the road. Therefore the expressway is designed to be elevated by the flyovers
providing u-turn facility for the arterial road to enable the traffic across the
access-controlled expressway.
2-14
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
YCDC is now planning to improve the Road No.7 along YORR by 2017. It is highly
recommended to improve the road applying the cross section shown in Figure 2.5.6
above.
Figure 2.5.7 and 2.5.8 present the proposed ultimate stage of the outer ring road (YORR)
in future.
2-15
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2-16
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2.6 Toll Levy System
The proposed expressway is mainly constructed as elevated viaduct structure with large
amount of the investment cost. The toll collection is usually implemented to help recover
the cost of the road construction, land acquisition and maintenance. The toll collection
facilities are designed in this survey.
IN Booths
TB1 TB-1 - Flat (YUEX)
(YUEX)
IN Booths
TB-2 Distance/Area (YORR)
YUEX TB2 (YUEX)
IN Booths Flat (YUEX)
TB3 &
(YORR) (IN Booths of YUEX and
OUT Booths OUT Booths of YORR
TB-3 could be integrated.)
(YORR)
YORR
Ticketing Payment Distance/Area
Y-N-M Expressway
2-17
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Diamond Type
Trumpet Type Cloverleaf Type
(recommended)
The location of the interchanges for the other sections is also indicated in the plan
drawings as attached in Appendix 2.
Due to land constraint along the proposed expressway, the location of the interchanges is
selected by the following considerations.
to set the interval of each interchange more than 1km to minimize the traffic weaving
between ON/OFF ramps
The detail location and layout of the interchanges and toll barriers shall be further studied
in detail during the next study such as the feasibility study in accordance with the result of
the detailed traffic demand forecast.
2-18
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2-19
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2.8 Alignment Study
In accordance with the definitive route for this survey, the preliminary alignment study has
been conducted utilizing the satellite photo taken in 2012 during SUDP. Further detailed
alignment study shall be conducted during the next step such as the feasibility study.
2-20
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Section, JCT-03 for M Section) are not constructed by R1 Section. The design control
points considered in this section are;
Re-alignment of the expressway where the arterial roads does not satisfy the
geometric design criteria of the expressway
Navigation clearance
Re-alignment of the expressway for the section crossing the Pazondaung Creek
Re-alignment of the expressway where the arterial roads does not satisfy the
geometric design criteria of the expressway
Re-alignment of the expressway where the arterial roads does not satisfy the
geometric design criteria of the expressway
Connection with the logistic access-controlled road operated by Asian World will be
further studied in the next step of the study such as FS.
2-21
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Flyovers for U-turn facility
Re-alignment of the expressway for the section crossing the Hlaing River
Re-alignment of the expressway where the arterial roads does not satisfy the
geometric design criteria of the expressway
Parami Road has been selected for the construction of the M Section in this survey in
which there are relatively more non-developed areas than other roads.
There is undeveloped land and low-rise buildings/housings along the road adjacent to the airport and the proposed
sub-center (Mindama). The road can be an East-West Corridor. The road is located close to the airport and it
will be difficult to build the elevated road.
There are many low-rise buildings/housings along the road. However the width of the existing road is relatively wide.
Modal shifting to the public transport such as BRT is recommended to enlarge the capacity.
Parami Road
:NondevelopedSection
N :DevelopedSection
There is undeveloped land and low-rise buildings/housings along the road. The road is extended to Hlaintaryar and
Dagon areas through Bayint Naung Bridge (6 lanes in future) and Parami Bridge (4 lanes). The road will be most
preferable for an East-West Corridor.
2-22
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
There are many low-rise buildings/housings along the road adjacent to Inya Lake (recreational area). Land
rearrangement to high-rise buildings will not be practical.
Re-alignment of the expressway where the arterial roads does not satisfy the
geometric design criteria of the expressway
Re-alignment of the expressway where the arterial roads does not satisfy the
geometric design criteria of the expressway
Connection with the logistic access-controlled road operated by Asian World will be
further studied in the next step of the study such as FS.
Accordingly, in view of the alignment design, the sections of N, R1 and E will be easier to
implement by less land acquisition and resettlement than other sections. This concept of
the priority sections coincides with the YUTRA MP (Refer to Figure 2.2.3 in this report.).
2-23
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2-24
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2-25
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2-26
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
2-27
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
CHAPTER 3
VIADUCT PLANNING
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
3 VIADUCT PLANNING
ASSHTO standard also specifies the track as a single concentrated load and a uniformed
load as follows;
The proposed bridge site will be affected by earthquakes. Myanmar Geosciences Society
(MGS) has prepared the earthquake zoning map of the Yangon Area. Seismic design shall
be carried out in next stage for viaducts of Yangon Urban Expressway.
(3) Temperature
3-1
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(4) Wind
The biggest cyclone NARGIS with winds up to 54m/s swept through the neighbouring
bridge location on May 2nd, 2008. There is a wind record with 49m/s in maximum wind
speed at Yangon. Therefore wind load acting on the superstructure should be considered
carefully in next stage. If suspension bridge, cable stayed bridge and other flexible
bridges are applied for crossing Yangon River, detailed study such as wind tunnel test is
necessary to examine the stability due to wind in the outline design stage or detailed
design stage.
3.2.1 General
As already described in previous chapter, it is planned to construct expressway viaduct
above existing Street (arterial road). Typical cross section is shown in below Figure.
Existing streets are one of major urban arterial road in Yangon City, and is important route.
However, width of them is very limited. During construction of viaduct, it is necessary to
secure space for traffic and safety. Therefore, following principles need to be taken into
consideration in this Study.
To keep the space for detour during construction period as much as possible
3-2
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
3.2.2 Selection of Superstructure Type
(1) Introduction
As for the selection of the superstructure, the type is selected on the following conditions.
Viaduct section is mainly comprised standard section and special section such as
Crossing River and road intersection etc. Therefore, the selection of superstructure is
conducted in two sections respectively.
The following three alternatives are extracted for bridge type selection. Especially, as for
PC Bridge, Pre-casting PC Girder which is fabricated at factory and/or girder casting yard
under quality control are extracted since many number of girders has to be fabricated in
short time.
Table 3.2.1 shows the comparison of bridge types for Standard Section. As a result of the
comparison of Bridge type for Standard Section, PC-I Composite Girder and PC-U
Composite Girder is selected as the most suitable structure type for the Standard Section
of Urban Expressway Viaduct by following reason. Detailed comparison shall be carried
out in next stage.
Construction period will be longer than steel box girder. However, difference is not
much.
3-3
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Table 3.2.1 Comparison of alternatives for Standard Section
Type PC-I Composite Girder PC-U Composite Girder Steel Box Girder
Cross-section
Photo
Cost Ratio
(including
1.00 1.00 1.16
substructure per
200m)
It is necessary to replace EXP It is necessary to replace EXP It is necessary to repaint once
Maintenance joint an Bearing shoes joint an Bearing shoes 20-30 year according to the
once20-30 years. once20-30 years. traffic condition.
3-4
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
New Technology
PC Composite Girder
Characteristics of this bridge type are the followings. This is a very suitable bridge type for
the viaducts in the urban area.
High quality pre-casting girders can be fabricated at factory and/or casting yard in
a short term.
Fabrication girder and pre-casting slab at factory and/or casting yard enables
applying high-strength concrete, labour saving and cost reduction.
Since the PC plate plays a role as the formwork and the scaffolding at the time of
the slab construction, and the assembling and dismantling of hanging scaffolding
for slab construction is unnecessary
It can reduce the production of waste materials, noise and vibration at site since
the pre-casting girders are applied.
Pavement Pavement
RC slab (cast-in-place)
Pre-casting PC Plate
U-shape Pre-casting
Girder
Pavement
RC slab (cast-in-place)
3-5
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(3) Viaduct Structure for Special Section
Special Section of Viaduct includes flyovers of intersection, junctions, curve portions and
river crossing portions. Generally span length of the viaduct requires more than 50m at
flyover of intersections and junctions. As the common superstructure types at flyover of
intersections and junctions in urban city, Steel-I Girder, Steel Box Girder and PC Box
Girder is extracted. Maximum span length of Steel-I Girder is generally around 60m, and
Steel Box Girder becomes economical than Steel-I Girder since the width of
superstructure is relatively wide. Accordingly, two bridge types of below Table are
compared in several aspects.
Table 3.2.2 Applicable Span Length of Bridge Types
Table 3.2.3 show the comparison between Steel Box Girder with RC slab and PC- Box
Girder. Steel Box Girder with RC slab is selected for Special Section.
Table 3.2.3 Comparison of Alternatives for Special Section
Cross-section
3-6
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
same type. But it is still new type.
Due to smooth surface of girder, side view Girder depth is higher and the size of
Aestheticism looks clear. It is possible to improve substructure is larger than Steel Box
aesthetics by modifying girder shape. Girder.
Evaluation Recommended
Curve Section
Urban expressway runs through the dense Yangon city so that viaduct alignment has
many curve sections. Therefore, Steel Box Girder is applied to small curve section less
than R=350m in this study.
Detailed study of bridge type will be carried out in next stage. However, the following span
arrangement is applied to those crossing river/lake sections in consideration of ship
navigation and not to construct piers inside river/lake as much as possible.
Table 3.2.4 Span Arrangement of Crossing River/Lake Sections
In case of above span length (70 -120m), although Steel Box Girder with Steel Plate Deck,
Truss Bridge, Arch Bridge, Extradosed Bridge and Cable-stayed Bridge can be considered
to apply, Steel Box Girder with Steel Plate Deck is selected in this Survey in consideration
of economic aspect and consistency of bridge type.
Table 3.2.5 to Table 3.2.8 shows the span arrangement of Special Section on Yangon
Urban Expressway.
Besides, Figure 3.2.1 to Figure 3.2.8 shows the span arrangement of several important
portions (blue columns in Table 3.2.5 to Table 3.2.8).
3-7
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Table 3.2.5 Span Arrangement of Special Sections on YUEX N, R1 & E Section
3-8
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Table 3.2.7 Span Arrangement of Special Sections on YUEX S Section
Bridge Length Lengh of PC Length of Steel
Name Location Span Arrangement Remarks
(m) Girder (m) Girder (m)
1 Flyover Sta.0+000 - 0+200 200 4@50 - 200
2 Flyover Sta.0+440 - 0+590 150 3@50 - 150
Arrange by PC girder
3 Intersection Sta.0+680 - - - -
(general span @40m)
Arrange by PC girder
4 Intersection Sta.0+980 - - - -
(general span @40m)
5 Intersection Sta.1+190 - 1+340 140 - 140
Arrange by PC girder
6 Intersection Sta.1+560 - - - -
(general span @40m)
Arrange by PC girder
7 Intersection Sta.2+150 - - - -
(general span @40m)
8 Intersection Sta.2+670 - 2+840 170 50+70+50 - 170 Sakura Tower
Arrange by PC girder
9 Flyover Sta.3+070 - - - -
(general span @40m)
Arrange by PC girder
10 Intersection Sta.3+650 - - - -
(general span @40m)
11 Curve Sta.3+710- 4+060 350 7@50 350
Arrange by PC girder
12 Flyover Sta.5+060 - - - -
(general span @40m)
13 Curve Sta.5+400 - 5+550 150 3@50 - 150 R=350
14 Curve Sta.5+790 - 6+290 500 10@50 - 500 R=350
15 Curve Sta.7+010 - 7+310 300 6@50 - 300 R=350
16 Flyover Sta.7+710 - 8+110 400 8@50 - 400 R=350
17 Curve Sta.8+230 - 8+730 500 10@50 - 500 R=350
3-9
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
3-10
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
3-11
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
3-12
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
The Study of sub-structure is considered below points and carried out in Standard Section
and Special Section separately.
The medium width of the future frontage road will be secured 5m. Therefore, the shape of
sub-structure adopts 1-Column & T-shape Type. In this case, there are the following
advantages.
Fence is straight and fixed during construction period for Pier Column and
Foundation
3-13
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
There are some sections where many houses, buildings and shops locate both side of
frontage road. Therefore, foundation and pile cap need to be constructed under restricted
condition. Besides, the quick, safest and eco-friendly type should be selected.
Normally, it is required widest construction yard during construction of foundation and pile
cap. Size of pile cap is determined by type and number of foundation. Therefore, required
width for construction yard is one of important factor to decide foundation type.
It seems that the foundation depth of Urban Expressway will be around 40m deep. The
construction depth of each foundation types is shown in below Table.
Table 3.2.9 Construction depth of foundation types
3-14
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
As shown in Table 3.2.9, various type of foundation can be applied to the Project. However,
following foundation type is not suitable to apply this project in consideration with
properties of this project.
Diaphragm Wall
Normally this type of foundation is not applied to the Viaduct with normal condition.
Special digging machine is necessary so that construction cost will be more expensive
than other foundation types.
Therefore, Screw Steel Pile is worth to study as an alternative. Design and construction
method of Screw Steel Pile is referred Specification for Design of Pile Foundation and
Specification for Construction of Pile Foundation published by Japan Road Association
in January 2007.
In consideration with above mentioned comments, Bored Pile, Diaphragm Wal, PC Well,
and Screw Steel Pile are compared in Table 3.2.10.
Recommendation
As a result of this study, Rotation Steel Pile type is selected as the recommended
foundation type at area where is difficult to secure enough construction yard from the
following points of view.
However, as for PC Pile and PC Well foundation, those foundation type also can be
eco-friendly type and construction cost might be cheaper than other foundation types in
future when fabrication factory of PC pile is established in Yangon. Therefore, more
detailed comparison study shall be carried out in consideration of the possibility of
application of PC pile in next stage.
3-15
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Table 3.2.10 Comparison of Foundation Type at Standard Section
3-16
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Eco-friendly Method.
None-excavated method
No bentonite circulation
system
Site becomes very clean. And,
no dust is expected
Compact Shape
Skin friction becomes bigger by
compressing surrounding soil.
Sub-structure type at Special Section is also adopted the same type (1-Column & T-shape
Type) as Standard Section when the medium width (5m) of frontage road can be secured.
However, the steel piers shall be applied to the locations that become high pier,
three-layer structure and/or large cantilever since it is superior in constructability in urban
area and can be shorten the construction period.
Figure 3.2.10 to Figure 3.2.12 shows the sketch of cross-section where the steel piers are
applied to.
3-17
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Foundation and pile cap need to be constructed under restricted condition. Besides, the
quick, safest and eco-friendly type should be selected.
Therefore, the foundation type at special section is basically applied the same one as
standard section.
Inside River
As mentioned before, there are two large river crossing bridges (Pazundaung Creek and
Hlaing River) on YUEX.
Span length of superstructure is arranged with 100m so that the dead load of structure is
also relatively large. According to the selection table of foundation type in Table 3.2.11,
four foundation types (Cast-in-Place Concrete Pile, Steel Pipe Pile, Steel Pipe Sheet Pile,
Caisson) can be applied to the bridge inside river. However, when we look at Steel Pipe
Pile, it will be required temporary cofferdam so that it can be judged that Steel Pipe Sheet
3-18
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
pile will be cheaper and more reasonable than Steel Pipe Pile. Accordingly, three
foundation types (Cast-in-Place Concrete Pile, Steel Pipe Sheet Pile, Caisson) can be
considered to the foundation type of the bridge inside river.
Diaphragm wall
Steel Pipe Pile
PHC / SC Pile
Caisson
Applicable Condition
Depth < 5 m
Temporary Jetty
Construction
Condition of
Depth > 5 m
Vibration Noise
Environment
Impact on Adjacent Structure
Normal
Loading
Large
<5m
Ground Condition
5 ~ 15 m
15 ~ 25 m
Depth of Supporting Layer
25 ~ 40 m
40 ~ 60 m
>= 60 m
Clay (20 =< N)
Soil Condition
Sand/Gravel (30 =< N)
Note: : Suitable, : Possible, : Impossible Source: Japan Bridge Standard
When the foundation is to be constructed more than 10 m deep from the water surface, in
accordance with the above conditions, the size of the temporary cofferdam would be large.
Therefore, a foundation that allows the use of a temporary cofferdam also for the main
part of the bridge or that omits the temporary cofferdam is considered advantageous.
Table 3.2.12 shows the foundation type alternatives inside river. As a result of the
comparison, Steel Pipe Sheet Pile Foundation is considered the optimal solution for the
foundation type inside river in terms of its applicability to deep-water construction and
anti-scouring properties.
3-19
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Foundation Type
3-20
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
After study of Bridge Type Selection, structure type for foundation, sub-structure and
superstructure is decided respectively. Selected structure type is shown in below Table.
Table 3.3.1 Structure Type of Expressway Viaduct
Foundation Sub-structure Superstructure
Standard Section Screw Steel Pile RC Pier PC-U Composite Girder
Screw Steel Pile/Steel Pile
Special Section RC Pier Steel Box Girder
Sheet Pile (inside river)
3-21
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Overall flow chart for construction of viaduct is shown in below Figure.
Currently, there are 6 carriageways in Thudhamma Road and Wai Za Yan Tar Road. In
order to minimize traffic congestion and keep service level for residents living along this
road, it is required to maintain existing traffic even during construction of viaduct. However,
it is obvious that width utilize for detour road will be narrower than existing road width.
In consideration of construction method for each work item, work item for Construction of
Pile Cap is required widest construction yard. Therefore, study on detour plan and
necessary construction yard is carried out at construction stage for Pile Cap.
After study on necessary width for construction of Pile Cap, it is required approximately
9m width as construction yard, even if sheet pile is used to reduce width of necessary
construction yard. Based on this width for construction yard, detour plan is studied as
shown in below.
3-22
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(3) Foundation
Foundation type is selected as Screw Steel Pile type. After levelling of ground and pile
location survey, casing rotator machine will be set and installation of lower pile will be
commenced. Connection between lower pile and upper pile will be by welding at site.
Typical sketch for construction of Screw Steel Pile and arrangement of equipment at site
are shown in Figure 3.3.3 and Figure 3.3.4.
3-23
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(4) Sub-structure
After construction of pile cap, backfill work will be carried out up to top surface of pile cap.
Then, construction of pier column and pier head will proceed.
Below photo shows the sample of construction of pier head in Jakarta, Indonesia.
Temporary crossing beam is provided for construction of pier-head, and traffic is allowed
to pass under pier-head during the construction. Traffic safety control must be secured
strictly in this situation. This construction method for pier-head will be applied in YUEX.
(5) Superstructure
PC Composite Girder segment will be fabricated at factory and/or fabrication yard and be
transported by trailers to erection site. In order to avoid negative impact to detour traffic
as much as possible, erection work needs to be carried out at night time only.
3-24
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Below Figure shows outline of lifting erection method of PC-U Composite Girder.
PC-U Girder
Pre-casting Girder
Main girder of Steel Box Girder consists of several blocks for each span. Erection of each
block of main girder will be carried out with bent. After erection of each block onto bent,
blocks will be connected by bolt.
Due to light weight of each block, it is possible to place crane and track for mobilize girder
from manufacture within construction yard.
During construction of the substructure, all steel members will be fabricated at steel girder
fabrication factories.
Below photos shows the sample of erection of steel box girder in Shwegonedaing Flyover
Project.
3-25
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
CHAPTER 4
CONSIDERATION FOR
SOCIAL ENVIRONMENT
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
By the results of the above, the environmental category under the JICA Guidelines for
Environment and Social Considerations (April, 2010) can be classified temporarily.
More than 200 persons: Category A (likely to have significant adverse impact)
Less than 200 persons: Category B (some extent impact is expected)
Structures or premises exist fully or partly inside the planned ROW are surveyed.
Approximate numbers of structures/premises expected to be affected by the Project
(YUEX) and to be replaced are estimated based on the available satellite map.
Alignment design
Site Survey
to distinguish
type of structures
4-1
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Numbers of the project affected small shops of easy assembly type or mobile type were
not estimated.
The reason is that looking at the satellite photo, these small shops are often hided under
the trees and are difficult to be recognized individually.
It is assumed that most of shop owners of these small shops do not live in the shops.
4-2
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
4.1.3 Results of the Survey
The affected premises and the number persons to be resettled have been tentatively
estimated based on the plan drawings on the satellite photos.
(1) N Section
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two Including seven
1 storey usual 10 60 old
houses houses(Photo1)
Shops/ Usual building Including 8 shops
Restaurants/ type 11 Buildings in two
2 34
Offices/ (17 shops) Buildings
Workshops (Photo2)
Private /Public Large buildings
3 Organizations /factories - -
Facilities
Total 94
Source: YUEX Survey Team
(Photo 1) (Photo 2)
4-3
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(2) R1 Section
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two
storey usual 6 36
1 houses
4 storey 2 buildings(12 (photo 2 below)
72
apartments households)
Shops/ Usual building
Restaurants/ type
2 38 76
Offices/
Workshops
Private /Public Large buildings
3 Organizations /factories - -
Facilities
Total 184
Source: YUEX Survey Team
(1) A small Pagoda exists in contact with the road. (However, road alignment is possible
to make no impact on the Pagoda. (See photo 1 below.)
(2) Replacement of these two Buildings (apartment) may be avoidable by re-design of
alignment. (See photo 2 below.)
(Photo 1) (Photo 2)
4-4
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(2-2) Sub-Section R1 (2)
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two
1 storey usual 12 72
houses
Shops/ Usual building
Restaurants/ type
2 36 72
Offices/
Workshops
Private /Public Large buildings
3 Organizations /factories - -
Facilities
Total 144
Source: YUEX Survey Team
Some of the buildings will be affected by the Project. However the partial land acquisition
with set-back of the buildings could be expected due to the affected area of the land.
4-5
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(3) E Section
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two
1 storey usual 13 78
houses
Shops/ Usual building
Restaurants/ type
2 20 40
Offices/
Workshops
Private /Public Large buildings One fuel station
3 Organizations /factories 1 - will be affected.
Facilities
Total 118
Source: YUEX Survey Team
One gas station will be located within the proposed road width and might require to be
replaced.
4-6
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(4) R2 Section
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two
1 storey usual 19 114
houses
Shops/ Usual building
Restaurants/ type
2 61 122
Offices/
Workshops
Private /Public Large buildings
3 Organizations /factories 8 -
Facilities
Total 236
Source: YUEX Survey Team
There are a lot of business buildings and facilities including stock facilities relating port
logistic activities.
4-7
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two
1 storey usual 47 282
houses
Shops/ Usual building
Restaurants/ type
2 143 286
Offices/
Workshops
Private /Public Large buildings
3 Organizations /factories 10 -
Facilities
Total 568
Source: YUEX Survey Team
Estimated numbers of persons to be resettled are the greatest of the all the planning
sections.
4-8
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(5) S Section
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two
1 storey usual 21 126
houses
Shops/ Usual building
Restaurants/ type
2 88 176
Offices/
Workshops
Private /Public Large buildings
3 Organizations /factories 6 -
Facilities
Total 302
Source: YUEX Survey Team
(S Section along Bogyoke Aung San Rd.) (S Section along Upper Pazundaung Rd.)
The necessity of the S Section will be further studied in the next stage of the Project as
mentioned in Chapter 2. During the SUDP, DHSHD preferred YUEX passing along
Bogyoke Aung San Road than others because the south of the road is inside CBD and the
north of the road will close to Shwedagon Pagoda.
However there are cultural/historical premises in the area along Bogyoke Aung San Road
and it should be studied further in detail for the multifaceted impacts on the living,
business and cultural environment in this section.
4-9
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(6) W Section
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two
1 storey usual 7 42
houses
Shops/ Usual building
Restaurants/ type
2 17 34
Offices/
Workshops
Private /Public Large buildings
3 Organizations /factories 15 -
Facilities
Total 76
Source: YUEX Survey Team
4-10
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
(7) M Section
Number of Number of
Structures to
Type Buildings to be Persons to be Remarks
be replaced
replaced resettled
Residences One or two
1 storey usual 9 54
houses
Shops/ Usual building
Restaurants/ type
2 28 56
Offices/
Workshops
Private /Public Large buildings
3 Organizations /factories 18 -
Facilities
Total 110
Source: YUEX Survey Team
(Parami Rd.)
4-11
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Months
1 2 3 4 5 6 7 8 9 10 11 12
-Planning /Preparation
-Actual Environmental Survey
Study -Baseline study /Regal system study
Relating
EIA
-Implementation of EIA
-Finalization RAP by MR
Advisory Committee
Stakeholders Meeting
4-12
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
CHAPTER 5
PROJECT COST ESTIMATES
AND ECONOMIC EVALUATION
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Exchange rate is applied JPY102.5/USD (as of August 2014). Price escalation and
physical contingency does not consider in this survey.
The unit cost for the road works applied for the at-graded sections of the Project is shown
in Table 5.1.2. The unit cost has been prepared referring the similar size of the project in
other Asian country under JICA ODA project, cost estimation from pile suppliers and also
the recent basic cost estimate results in Myanmar (grant aided bridge).
Unit Price
Items
(USD/m2)
Piled Slab 410
Arterial Road (Improvement) 126
Arterial Road (New Construction) 284
Source: YUEX Survey Team
5-1
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
5.1.3 Estimated Project Cost
The following tables show the estimated project cost at present value.
Table 5.1.3 Estimated Project Cost (N Section)
5-2
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
5-3
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
5-4
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
5-5
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
5-6
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
5.1.4 Traffic Control System and Toll Collection System (for reference)
The estimate of unit costs for traffic control system and toll collection system of YUEX is
shown in Table 5.1.12. The unit costs are referred from similar Indias projects which are
conducted under JICA ODA Project. Appropriate O/M organization system and required
facilities will be developed in the following feasibility study of YUEX, therefore these costs
need to be re-calculated with accuracy at next stage.
Table 5.1.12 Unit Cost of Traffic Control System and Toll Collection System
Note *2 : Including VMSs, CCTVs, ATCCs, Emergency telephones, weather monitoring stations, optical fiber cables,
optical transmission devices, other back-up facilities etc.
Note *3 : Including ETC (non-stop, touch and go) system , manual toll collection system etc.
Source: YUEX Survey Team
Table 5.1.13 Estimated Cost of Traffic Control System and Toll Collection System
R12
R21
R22
R11
R12
R21
R22
Total
M
M
W
W
N
N
E
E
S
S
USD)
Roa dSi deFa ci l i ti es 15 perkm 16.5 10.3 4.2 6.9 9.4 14.9 7.9 6.7 9.5 248 155 63 104 141 224 119 101 143 1295
pertoll
Tol l Col l ecti onSys tem 8 8 4 4 2 6 9 5 4 2 64 32 32 16 48 72 40 32 16 352
booth
Total 1817
=18millionUSD
5-7
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
5.2 Economic and Financial Evaluation
Project evaluation for the YUEX projects was conducted. As traffic demand projection per
each Sub-project basis was not conducted, only overall project benefits of YUEX were
evaluated in YUTRA as a single project. Therefore, the YUEX Survey Team estimated the
traffic demand volume of each Sub-project consisting of the YUEX this time. The following
assumption and methodology was employed for calculation purpose.
The basic conditions set for the calculation of economic analysis of YUEX remain same as
those of YUTRA. The indicators of Economic Internal Rate of Return (EIRR), Net Present
Value (NPV), and Cost Benefit Ratio (B/C) were calculated to assess the economic
viability of each Sub-project.
05 Economic Cost Standard Conversion Factor was set at 0.85 (same as YUTRA)
09 Tariff Ks.35/ km for car/ Ks.105/ km for truck as of 2013 (same as YUTRA)
For the economic cost components, the difference of the construction costs for each
Sub-project between YUTRA and YUEX Survey was confirmed as shown hereunder.
5-8
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Table 5.2.2 Economic Costs Comparison between YUTRA and YUEX Survey
(USD Million)
No. Project Title Economic Cost for Economic Cost for Remarks
YUTRA YUEX
(USD Mil.) (USD Mil.)
Note: The above figure is direct project costs and engineering and other indirect costs are excluded.
The evaluation results for the economic analysis of each Sub-project were summarized as
following Table 5.2.3.
Table 5.2.3 Economic Evaluation Results
EIRR NPV
No. Project Title B/C
(%) (USD Mil.)
5-9
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
The calculated major economic indicators shown above mentioned that all of the YUEX
Sub-projects are economically viable. Especially, the Sub-projects RD-06, RD-10, RD-12
and RD-13 recorded quite high figures.
Regarding the overall YUEX Project, EIRR was 21.6%, USD 7,120 million for NPV, and
B/C was 3.8. These figures are slightly lower than the figures calculated in the preceding
YUTRA, which were 25%, USD 7,313 million and 4.6, respectively.
For the EIRR of the overall YUEX project, the sensitivity analysis results were i) 19.4%, ii)
18.6%, and iii) 16.5%, respectively. These figures also confirmed that implementation of
YUEX project is economically viable.
5-10
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
In YUTRA, only the Sub-project RD-06: North Section was selected for the financial
evaluation, as YUTRAs traffic assignment model assumed only this Sub-project was the
toll portion. However, the financial analysis for the remaining eight Sub-projects was also
conducted in this survey by conducting the preliminary traffic demand volume analysis per
each Sub-project basis.
The financial internal rate of return (FIRR) of the each Sub-project was shown in the
following Table. As YUTRA preliminary set the fare as Ks. 35 per km for car, and Ks. 105
per km for truck as of FY2013, the FIRR of each Sub-project were projected very low. The
overall YUEX projects FIRR was negative and five (5) of the total nine (9) Sub-projects
recorded negative FIRR, too. There is the room for discussions of the amendment of this
fare setting in the following feasibility study for this Sub-project.
The financial evaluation results indicated that the implementation of YUEX is financially
viable for several sections but for the remaining sections the Governments subsidiaries or
special financing will be required for the smooth operation. It is required to examine the
appropriate tariff setting and financing plan based upon in the following F/S stage.
5-11
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
CHAPTER 6
IMPLEMENTATION SCHEDULE
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
6 IMPLEMENTATION SCHEDULE
The executing agency will be responsible for all project works as described below:
The implementation milestone and I/P are shown in Figure 6.1.1 assuming that common
practice will be adopted.
6-1
FINAL REPORT
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Source: YUEX Survey Team
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Fi na nci a l Yea r
I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV
Figure 6.1.1
Fea s i bi li tyStudy
Prepa ra ti onofEIA,RAP
Pl edgea ndL/A
ProcurementofD/DCons ul ta nt
ProcurementofC/SCons ul ta nt
(NSecti on)
(R11Section)
6-2
(R12Section)
(ESecti on)
(NSecti on)
(R11Section)
(R12Section)
(ESecti on)
(NSecti on)
(R11Section)
(R12Section)
(ESecti on)
CHAPTER 7
SUGGESTIONS FOR APPROPRIATE
OPERATION AND MAINTENANCE
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
7.1 Introduction
The Yangon-Mandalay expressway is the sole expressway in Myanmar opened in March
2009 between Yangon and Naypyitaw, and in March 2010 extended to Mandalay. This
Yangon-Mandalay expressway is operated and maintained by Public Works (PW) of
Ministry of Construction (MOC) in present.
In order to confirm current situation of O/M of the existing roads and expressway, several
interviews with organizations mentioned below were conducted in this Study.
The Yangon-Mandalay Expressway has been developed to fulfil the following objectives:
To minimize the travel time between Yangon and Mandalay. (By using this
expressway, the travel time from Yangon to Mandalay is observed to shorten from
13 hours by train or 16 hours by former highway to 7 hours.)
7-1
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
To open up avenue for industrial and urban development of the region and provide
the base for convergence to tourism and other allied industries.
No of Traffic Lane 24 24
No of Interchange 2 4
No of Rest Area 3 2
No of Toll Gate 3 3
No of Bridge 124 99
No of Bridge (L<30m) 40 39
No of Bridge (30<L<60m) 64 41
No of Bridge (60m<L) 20 19
No of Under Pass 40 21
7-2
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Mandalay
Sagar inn 21.92 km
242.28 km
Naypyitaw
325.12 km
Yangon
7-3
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Source: EMU of PW
Figure 7.2.2 Typical Cross Section of the Yangon-Mandalay Expressway
Compared to the Japanese expressways, many fatal accidents have occurred on the
Yangon-Mandalay expressway. Safety countermeasures such as speed measurement
and enforcement for over speed vehicles (Figure 7.2.3) or placement of chatter bar
(Figure 7.2.4), bump pavement (Figure 7.2.5), have being conducted by PW and traffic
police, however number of accidents have not been decreased.
In addition, emergency phone service 1880 hot line (Figure 7.2.6) is started by PW from
July 2014. This call is directly connected to Yangon-Mandalay Express Call Centre, and
the call centre has taken necessary actions such as to inform the nearest agencies (police,
fire brigade, hospital, PW) etc.
7-4
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Table 7.2.3 Accidents on the Yangon-Mandalay Expressway
Unit: persons
Length Traffic Volume
Items 2011 2012 2013
(km) (Veh./day, 2012)
Yangon-Mandalay 589 Approx. 4,500 47 78 113
NEXCO-East* 3,746 Approx. 26,500 59 70 59
Source: YUEX Survey Team
*Source: NEXCO-East HP
7-5
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
To install lighting system on the bridges as well as curvy and hilly sections of the
expressway.
To change all the raised medians to depressed medians for improving drainage
system.
To place rough concrete surface shoulder between carriage way and medians.
To install guard rails from the start to the end of the expressway.
To install road signs and signals to make a complete set of road furniture.
To extend the 4 lane (both directions) carriage way to 6 lane carriage way system,
and there after 8 lane system.
To evaluate and re-construct the super elevation for the curve section according to
the design speed, centripetal forces and centrifugal forces.
To install necessary facilities for expressway, such as guard rails, fencings, CCTV
and traffic control stations etc.
The improvement works have been implemented by PW in accordance with the Master
Plan of the Yangon-Mandalay expressway step by step, especially widening of the
existing bridges (Figure 7.2.7), instalment of lighting system, guard rails (Figure 7.2.8) etc.
7-6
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
7.3.1 Organizations
(1) Expressway Management Unit (EMU) of PW
7-7
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
EMU has 2 regional head offices and 25 operation offices under regional head offices. The
list of regional head offices and operation offices are given in Table 7.3.2 and organization
chart of operation offices is shown in Figure 7.3.2. Operation offices manage construction
and maintenance works of Yangon-Mandalay expressway and assist road safety.
Basically operation office comprises 3 sections (construction, maintenance, draftsman)
and approximately 41 officers are working including 1 engineers per office.
Table 7.3.2 List of Regional Head Offices and Operation Offices of EMU
7-8
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
7.3.2 Budget
Annual budget and O/M budget allocated to EMU for works of the Yangon-Mandalay
expressway in the past 3 years (after opening) are shown in Table 7.3.3 and Figure 7.3.3.
Required budget for the Yangon-Mandalay expressway is calculated by EMU and
requested from EMU to MOC each and every year, therefore budget has varied quite a bit
through the years and budget for improvement of Yangon-Mandalay expressway is larger
than O/M budget in recent years.
Currently simple maintenance works have been conducted such as mowing, restoration
works of accidents etc., and also damaged pavement has been rehabilitated on the
expressway by PW, therefore it is considered that minimal budget for maintenance works
have been allocated, in addition enough budget for improvement works have also been
allocated because of prioritized issues for PW.
Table 7.3.3 Annual and O/M budget for the Yangon-Mandalay Expressway
Unit: Billion Kyat
O/M Budget
2.944 4.309 3.272
(within annual budget)
7-9
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
20.00 18.466
2.00
0.00
2011 2012 2013
Fiscal Year
Annual Budget O/M budget
7-10
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
7.3.4 Current Situation of Road Maintenance Works
(1) Standards / Manuals
And road maintenance and asphalt pavement equipment / machineries owned by EMU
are given in Table 7.3.6 and Table 7.3.7 and the examples of photos of these machineries
are given in Figure 7.3.4. Maintenance works of the Yangon-Mandalay expressway
mentioned in Table 7.3.5 are basically conducted by EMU directly by using these
equipment and machineries.
Table 7.3.5 Current Situation of Road Maintenance on the Expressway
7-11
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
7-12
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Current toll rate of the Yangon-Mandalay is given in Table 7.3.8. Vehicle type is
categorized into 5 types (Class 1 to 5) depending on the weight of vehicles and class 5
vehicle is not allowed to drive the Yangon-Mandalay expressway currently.
Table 7.3.8 Toll Rate of the Yangon-Mandalay Expressway
Unit: Kyat per one way
There are 6 toll gates on the Yangon-Mandalay expressway, and toll fares are collected by
manual base at every toll gate at present. Collected toll fares have been included in
national budget until now.
Some toll gates are equipped with Electric Toll Collection (ETC) system, however these
systems are not operated in proper way and toll fares are currently collected by manual
base directly by officers of EMU.
EMU is now trying to develop ETC system and automatic toll collecting with private
companies and banks. Photo of toll gate and ETC system on the expressway are shown in
Figure 7.3.5.
7-13
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Traffic information collection and provision have not been conducted until now. CCTV
cameras are equipped at all 6 toll gates, however these cameras are used for toll
collection only. EMU is now trying to develop traffic control centre and constructing
buildings, however details have not been decided yet. Photo of constructing traffic control
centre is shown in Figure 7.3.6.
In case of traffic speed and weigh control, there are some speed cameras on the
expressway (Figure 7.2.3) and some toll gates are equipped weigh station. There facilities
are operated and used for enforcement of violators by PW and traffic police. Weigh station
equipped at toll gate is shown in Figure 7.3.7.
In addition, even if it is heavy rain or strong wind etc., the expressway can be used
because there is no rule and manual of traffic regulation or restriction under severe
weather condition, and also weather monitoring along the expressway is not conducted by
PW. This situation is one reason for many traffic accidents on the expressway.
7-14
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
7.4 Suggestions for Appropriate and Efficient O/M of Expressways
7-15
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Above mentioned functions and works are required for effective and efficient O/M of
expressways and should be collaborated each other, therefore appropriate organization
system should be set up corresponding to above functions and works under management
of head organization or company.
7-16
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Suitable O/M organization should be established for O/M of YUEX before opening,
therefore detailed survey and proposal is required in next feasibility study.
Appropriate inspection and maintenance works are necessary to keep safe and extend life
time of road structures. For these purposes, more strategic and well-planned frameworks
should be established for YUEX considering currently conducted inspection and
maintenance works on the Yangon-Mandalay expressway.
Inspection is conducted to confirm and evaluate condition of road structures and decide
rehabilitation methods and measures of damaged structures.
7-17
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Inspection results are summarized and inputted into database such as BMS / PMS, and
deterioration grades are judged and evaluated depending on their condition, then future
condition of structures and deterioration speed are forecasted. Based on information
obtained by this procedure, priorities of maintenance works of damaged structures are
given, and finally long-/mid- term maintenance plans are developed in consideration with
life cycle cost (LCC).
7-18
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Currently minimum maintenance works have been conducted such as mowing, cleaning,
restoration works of accidents etc., and also damaged pavement has been rehabilitated
on the Yangon-Mandalay expressway. Structures on the Yangon-Mandalay expressway
are comparatively new, therefore many rehabilitation works may not be necessary today,
however deteriorations and damages are progressing with their ages, periodical
inspection and development and implementation of maintenance plan are highly
recommended before damages become severe condition.
For appropriate inspection and maintenance works for YUEX, development of framework,
standards and/or manuals for inspection and maintenance works and training and
education for engineers should be required.
To achieve more efficient and effective inspection and maintenance works, introduction of
non-destructive inspection can be considered. Examples of non-destructive inspections
are shown in Figure 7.4.4.
The left photo shows pavement inspection using road surface condition measuring vehicle,
7-19
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
and the right photo shows sample of screening survey results of deterioration of bridge
using infrared camera.
In general, non-destructive equipment / tools are used to get uniformed inspection results
and to extract damaged places and members of structures efficiently and effectively to
conduct detailed inspection, therefore these methods of inspection can be considered to
introduce as next step.
Traffic congestions at toll gates are rarely occurred on the Yangon-Mandalay expressway
because of not much traffic volume (Table 7.2.2) and fixed toll rate (Table 7.3.8), although
toll fares are collected by manual base on the expressway currently. However, in case of
YUEX, over 60,000 PCU/day of traffic volume are forecasted and also enough number of
toll gates is not installed because of limited land space, therefore installation of efficient
and effective toll collection system is highly recommended.
Electric Toll Collection (ETC) system is one of the solutions to mitigate traffic congestion at
toll gate. ETC system is the system which collects toll fares automatically without stopping
at gate by communicating road side antennas and on-board unit (OBU) of vehicles.
In case of Japanese expressway, ETC system have been installed since 2000, and almost
90% of road users are using ETC system today. The outline image and photo of ETC
system in Japan are given in Figure 7.4.5.
7-20
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
96% decreased
Fiscal Year
Source: NEXCO-East HP
Figure 7.4.6 Experiences of Mitigation of Traffic Congestion at Toll Gate in Japan
Appropriate traffic control works are required to ensure safe and smooth traffic on
expressways. Major tasks of traffic control works are;
To collect 1) traffic information such as traffic jam etc., 2) road information such as
obstructs on roads and 3) weather information through regular and ad hoc
patrolling and road side facilities such as CCTV, traffic counter, emergency
telephone etc., and to take necessary actions for emergency incident such as
accidents, disabled vehicles etc.
To enforce and warn violated vehicles (over speed vehicles, over weight vehicles)
with close communication with traffic police.
To collect traffic information through road side facilities (CCTV, traffic counter etc.),
then to accumulate and analyze collected information, and to provide this
information to road users
To ensure safe and reliable expressways, traffic control system should be established and
steadily implemented. For smooth implementation, road side facilities should be
introduced and O/M of these facilities are also required. Therefore it is necessary to
develop standards and manuals for traffic control works including O/M of road side
facilities.
In addition, training and education should be required, because traffic control works are
7-21
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
required to have special knowledge and experiences of traffic control, to communicate
other organizations such as traffic police etc., and also to conduct road works on
expressways sometimes.
YUEX is planed as expressway in Yangon metropolitan area, and consist of 2 ring roads
(Inner ring road, Outer ring road) and several radial roads. After completion of YUEX, road
users can take several routes through ring roads depending on traffic situation and road
condition. Therefore wide-range traffic information collection and provision are required.
In this case, establishment of Traffic Control Centre (TCC) should be considered, having
centralized traffic control system. All relevant information is gathered to TCC, then
accumulated and analyzed, and provided to road users through TCC. In addition,
necessary actions for emergency incidents are ordered to patrolling teams from TCC.
In addition to traffic information provision using road side facilities such as Variable
Message Sign (VMS), highway radio conducted by NEXCO-East, all traffic information of
expressways, national highways, arterial roads are collected by Japan Road Traffic
Information Centre (JATRAC) and provided through broadcasts and mobile phone etc.
7-22
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
It is necessary to develop and establish efficient and appropriate traffic information system
and implementation framework, because real time traffic information collection and
provision is necessary to ensure safe and smooth road traffic. Therefore, additional survey
and proposal is required for traffic control system and framework in next feasibility study in
consideration with phase-wise development of YUEX.
7-23
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
CHAPTER 8
CONCLUSIONS AND
RECOMMENDATIONS
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
The following are the main findings and way forward of this data collection survey:
8.1 Conclusions
The road network proposed by YUTRA has been prepared in line with the VISION
2040 of Government of Myanmar. The Project, YUEX (Yangon Urban Expressway),
is expected to become a backbone of the development of Yangon City. Due to rapid
increase of the traffic demand, the capacity of the road network inside the City shall
be increased. YUEX will serve to increase the road capacity to ease the traffic
congestion inside the City.
YUEX is proposed to link with Thilawa SEZ, National Highways, and Hanthawaddy
Airport via the existing expressway (Yangon-NayPyiTaw-Mandalay Expressway).
YUEX is also expected to become a logistic artery for the sustainable development of
the country. The alternative route indicated in this survey shall be further studied in
the next step of the study or design.
In the built-up area, the construction of the new alignment will be quite difficult. Thus
the alignment of YUEX is generally planned on and along the arterial roads which
have wider ROW (=100 ft).
The proposed number of lanes of YUEX is 4 lanes (2+2) for both directions based on
the traffic demand forecast of YUTRA. The arterial roads underneath the YUEX
could accommodate BRT network according to the results of the demand forecast.
The elevated viaduct structure is proposed for the built-up area. On the other hand,
the at-graded cross section is proposed for the non built-up area (N Section).
YUEX is planned to connect with the Outer Ring Road via double trumpet
interchange which will accommodate the different type of the toll levy system. The
diamond type interchange is proposed for the ON/OFF ramps of YUEX in the built-up
area.
PC (Pre-cast) Girder bridges are proposed for the type of the structure for the
standard sections of YUEX. PC Girder could be mass produced in the factory yard
with uniform quality control.
The proposed alignment of YUEX will require the long span bridges for the specific
sections where cross over the intersections, rivers/creaks or other existing structures.
Accordingly the steel bridges are proposed for these sections.
The tentative financial evaluation results indicated that the implementation of YUEX
would be financially viable for several sections but for the remaining sections the
8-1
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey for the Yangon Urban Expressway (YUEX) Project
FINAL REPORT
Governments subsidiaries or special financing might be required for the smooth
operation. The fare rate set based on YUTRA is low so that it is required to examine
the appropriate tariff setting and financial plan during the feasibility study.
The overall traffic demand forecast used in this survey was conducted in 2013 under
YUTRA Master Plan. The detailed demand forecast shall be conducted especially for
the Project (YUEX). The route option as indicated in this survey (i.e. necessity of S
Section, etc.) will be studied in the feasibility study.
In this survey, the economic and financial analysis was preliminary conducted based
on the available demand forecast and indicators such as tariff setting, etc. by YUTRA.
The detailed analysis shall be re-examined to justify the feasibility of the Project.
The further detailed environmental study shall be required to establish IEE/EIA and
RAPs prior to the implementation of the Project.
8-2
Project for Comprehensive Urban Transport Plan of the Greater Yangon (YUTRA)
Data Collection Survey on The Project for Construction of Yangon Urban Expressway (YUEX)
FINAL REPORT
APPENDIX 1-1
PRESENTATION MATERIAL(1)
AGGENDA OF DISCUSSION YUEX
YANGON URBAN EXPRESSWAY
W are here
We h now.
Supplemental
Study(1month)
FeasibilityStudy
((9months)) Selectionof
Consultant Detailed
(6months) Design
ALMEC
OrientalConsultants
Oriental Consultants
NIPPONKOEI
3 4
1. BACKGROUND OF THE PROPOSAL YUEX YUEX
YANGON URBAN EXPRESSWAY YANGON URBAN EXPRESSWAY
ElevatedRadiaalRoad
Road]
Constructionof
[Inner RingR
Improvement
ofEW Corriror2
Le ge n d: Le ge n d: Le ge n d:
: Road to be constructed : Road to be constructed : Road to be constructed
: Completed Road : Completed Road : Completed Road
: Existing Road : Existing Road : Existing Road
5 Source:TheProjectforComprehensiveUrbanTransportPlanoftheGreaterYangon,JICA,2014 6
Source:TheProjectfortheStrategicUrbanDevelopmentPlanoftheGreaterYangon,JICA,2013
toThilawaSEZ
:Proposed Expresswayby 2025
:Proposed ArterialRoadImprovementby 2025
:Proposed/OngoingNewSubCenters 7 8
:Proposed LogisticTerminal/Depot
3)TRAFFICDEMANDFORECASTBYYUTRA(2014)
Theresultsofthetrafficdemandforecastindicated;;
1) MostofthemajorarterialroadswillbesaturatedinDONOTHINGcase.
2) Thecapacityofthearterialroadsneedtobeextendedbutthewideningwillbeadifficult
measureduetolandacquisition.
d t l d i iti
3) InYUTRA/SUDP,viaductringroadwasproposedtoextendthecapacityofthearterialroads.
AlsothemodalsplittoMRTwasconsideredinthetrafficanalysis.
Seeperspective
movie
Preliminaryeconomical/financialevaluationwasconductedbyYUTRAMPin2014.
EIRR 18%
B/C 1.7
FIRR 13.1%
S
Seeappendixpls.
di l
11 12
YUEX 2) Application of Screwed Steel Pile
4. TECHNOLOGY CHALLENGING YANGON URBAN EXPRESSWAY A lot of buildings/houses along YUEX
1) Application of Precast Prestressed Concrete Beam It is important to minimize noises,
noises vibrations and deformations of
Construction of Viaduct Structure on the Existing Arterial Roads ground conditions caused by piling work.
Traffic flow on the arterial roads shall be maintained even during the
construction of YUEX (mainly viaduct structures. Against the abo
above iss es Apply
e issues Appl Screwed
Scre ed Steel Pile
Need Quick Girder Erection Apply Precast Concrete Beam [Characteristic]
[Characteristic] It is possible to make small footing and reduce noise
noise, vibration and
The precast prestressed concrete beams are manufactured at a deformation of ground conditions.
factory/fabrication yard outside the project site. This pile can be applied over 60m depth.
The precast beams can be produced during the construction of the
substructures at the site
at the same time.
A track crane or launching girders will be used for erection.
15