CRONOGRAMA VALORIZADO PROYECTO "UNMSM"

CURSO: COSTOS Y PRESUPUESTO


GRUPO: JUAN PEDRO GALVEZ VARGAS
GIANPOOL MACHUCA SOTELO
WILMER CCENCHO CONDORI
UBICACIN: UNMSM
INICIO: 30/06/2016
FIN: 28/02/2017
DURACIN: 8 Meses (240 DIAS CALENDARIOS)

Curva S
1,050,000.00
950,000.00 MES 7, 837,088.21
850,000.00 MES 8, 908,190.05
MES 5, 707,436.49
750,000.00 MES 4, 671,673.81
650,000.00 MES 6, 766,164.51
550,000.00 MES 3, 528,366.50
S/.

450,000.00 Curva S
350,000.00
250,000.00 MES 2, 243,004.55
150,000.00
50,000.00 MES 1, 80,845.62

-50,000.00
0 1 2 3 4 5 6 7 8 9
MES