You are on page 1of 1

BAR CHART & S-CURVE

Weighted No. of
Item No. DESCRIPTION % Days Amount 15 Days 30 Days 45 Days 52 Days
100 %
B.5 Project Billboard/ Signboard 0.23 1 6,920.00 0.23

B.7 Occupational Safety and Health Program 1.13 52 33,216.00 0.20 0.30 0.30 0.33

B.8 Traffic Management 2.44 52 71,968.00 0.70 0.70 0.70 0.34

B.9 Mobilization/ Demobilization 0.16 2 5,112.40 0.08 0.08 50 %


416 Carbon Fiber Reinforcement Sheets (3 Layers) 89.60 43 2,645,944.00 4.65 17.64 54.00 13.31

5-1 Epoxy Injection 3.90 3 114,000.00 3.90

505(5) Grouted Riprap (Class A) 2.54 7 73,600.00 2.54


0%
TOTAL 2,950,760.40
8.40 18.64 55.00 17.96
PROGRESSIVE
247,863.87 550,021.74 1,622,918.22 529,956.57
CASHFLOW 27.04
8.40 82.04 100.00
CUMULATIVE
247,863.87 797,885.61 2,420,803.83 2,950,760.40

FROM THE OFFICE OF: PROJECT TITLE: PREPARED BY: CHECKED BY: SUBMMITED: APPROVAL RECOMMENDED: APPROVED: SHEET NO.

01 of 01
RETROFITTING / STRENGTHENING OF LALAO BRIDGE (B00460CB) GAVINO T. UMALI BEETHOVEN XAVIER B. EGOS MARLON D. MAROLLANO RENULT G. RICARDO JAMES D. DELLOSA Lt. Col. PA Res
GEN. ENGINEERING & BUILDING CONTRACTOR
PROJECT ENGINEER ARCHITECT II CHIEF, PLANNING & DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER SET NO.
Pakigne, Minglanilla Cebu
Tel. No. (032) 272-0661 Telefax No. (032) 490-4323 LOCATION : MALABUYOC, CEBU ADDRESS: PAKIGNE, MINGLANILLA CEBU DATE: DATE: DATE: