You are on page 1of 24

USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 1 of 24

No. 17-5132

____________________

IN THE UNITED STATES COURT OF APPEALS


FOR THE DISTRICT OF COLUMBIA
____________________

STATE OF MARYLAND,

DEFENDANT-INTERVENOR-APPELLANT

v.

FRIENDS OF THE CAPITAL CRESCENT TRAIL, JOHN MCKNIGHT


FITZGERALD AND CHRISTINE REAL DE AZUA

PLAINTIFFS-APPELLEES

____________________

APPELLANTS MOTION TO EXPEDITE

136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 2 of 24

TABLE OF CONTENTS

Page

BACKGROUND FACTS .........................................................................................2

ARGUMENT ............................................................................................................4
1. Continued Delay is Causing Appellants Irreparable Injury ................. 5

2. The District Courts Opinions are Subject to Substantial


Challenge ..............................................................................................9

A. The District Court Abused Its Discretion in Failing to


Reconsider Its Order Vacating the Record of Decision............. 9

B. The FTA Properly Determined That an SEIS Is Not


Needed......................................................................................11

3. The Public and Persons Not Before the Court Have an Unusual
Interest in Prompt Disposition............................................................16
PROPOSED SCHEDULE ......................................................................................17
CONCLUSION .......................................................................................................17

CERTIFICATE OF COMPLIANCE
CERTIFICATE OF SERVICE

-i-
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 3 of 24

TABLE OF AUTHORITIES

Page
CASES
Allied Signal v. Nuclear Regulatory Commn,
988 F.2d 146 (D.C. Cir. 1993) ............................................................................10

Coalition on Sensible Transportation, Inc. v. Dole,


826 F.2d 60 (D.C. Cir. 1987) ..............................................................................12

Gerber v. Norton,
294 F.3d 173 (D.C. Cir. 2002) ............................................................................15
Getty v. Federal Savings and Loan Insurance Corp.,
805 F.2d 1050 (D.C. Cir. 1986) ..........................................................................15
Marsh v. ONRC,
490 U.S. 360 (1989) ............................................................................................11

Monsanto v. Geertson Seed Farms,


561 U.S. 139 (2010) ............................................................................................11
Montrose Parkway Alternatives Coal. v. U.S. Army Corps of
Engineers,
405 F. Supp. 2d 587 (D. Md. 2005) ...................................................................... 7
Natl Comm. for the New River, Inc. v. FERC,
373 F.3d 1323 (D.C. Cir. 2004) ..........................................................................11

Public Employees for Environmental Responsibility (PEER) v.


Hopper,
827 F.3d 1077 (D.C. Cir. 2016) ....................................................................14, 15

Sierra Club, Inc. v. Bostick,


539 F. Appx 885 (10th Cir. 2013) ....................................................................... 8

Sierra Club v. United States Army Corps of Engineers,


990 F. Supp. 2d 9 (D.D.C. 2013) .......................................................................... 7

St. Johns United Church of Christ v. FAA,


550 F.3d 1168 (D.C. Cir. 2008) ..........................................................................12

-ii-
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 4 of 24

TABLE OF AUTHORITIES
(continued)
Page

Winter v. NRDC,
555 U.S. 7 (2008) ..................................................................................................5

Wisc. Gas Co. v. FERC,


758 F.2d 669 (D.C. Cir. 1985) .............................................................................. 5

STATUTES
16 U.S.C. 703712 ................................................................................................3
16 U.S.C. 1531-1544 ............................................................................................3
23 U.S.C. 138 ..........................................................................................................3

28 U.S.C. 1657 ....................................................................................................1, 4


42 U.S.C. 4321-4370m .....................................................................................3, 6

49 U.S.C. 303 ..........................................................................................................3

REGULATIONS
23 C.F.R. 771.109(c)(5) ........................................................................................15
23 C.F.R. 771.130(c).......................................................................................15, 16

OTHER AUTHORITIES
D.C. Circuit, Handbook of Practice and Internal Procedures (Jan. 26,
2017) .....................................................................................................................4

-iii-
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 5 of 24

Pursuant to 28 U.S.C. 1657 and Local Rule 27, the Appellant, State of

Maryland, respectfully moves this Court for expedited briefing and oral argument

in the above-captioned appeal. Expediting this appeal is essential, because the

District Courts decision to reject the expert opinion of the Federal Transit

Administration (FTA) and to vacate FTAs Record of Decision (ROD)

threatens the continued viability of the Purple Line (or the Project), a planned

16-mile-long transit line between Bethesda, in Montgomery County, and New

Carrollton, in Prince Georges County. The Purple Line has been in the planning

and approval process for well over a decade. It has broad support. Congress has

appropriated $325 million of a $900 million commitment to the Project, and the

two Counties have committed approximately $335 million to the Project.

The district courts final judgment, long-delayed and issued only after the

State sought mandamus relief in this Court, has already caused financial harm to

the State, threatens further losses to the State and its taxpayers, and promises to

deprive the public of the many benefits that would result from the Project. With

the fate of the Project in the balance, this appeal requires immediate attention by

this Court. The State has previously moved this Court to stay the district courts

judgment pending appeal, and now seeks expedited consideration of the merits to

ensure that the delay inherent in following the standard briefing schedule for an

appeal does not determine the future of the project.

1
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 6 of 24

The harm to the State, exacerbated by the district courts delay in resolving

the cross-motions for summary judgment, arises from the district courts August 3,

2016 Order (August 3 Order) (Exhibit 1), which vacated FTAs ROD approving

the Purple Line for federal funding. In the absence of that ROD, federal funding

necessary for the Project remains unavailable. The district court vacated the ROD

based on its mistaken conclusion that more analysis was needed on the impact of

recent ridership declines and safety issues on the Washington Metrorail system.

Exhibit 2. Nine months later, on May 22, 2017, after further analysis of that issue

by the State and FTA, the district court rejected the FTAs expert conclusions and,

once again, ordered the preparation of a supplemental environmental impact

statement (SEIS). Exhibit 3.

With the ROD still vacated and federal funding unavailable, the State lacks

the ability to proceed with construction of the Project. With each passing day, the

continued delay costs the State millions of dollars and places the Project in greater

jeopardy. Prompt consideration of this matter is needed to avoid the continuing

and irreparable harm to the State and its residents.

BACKGROUND FACTS

The history of this case is set out in the States Motion for a Stay Pending

Appeal and will not be repeated at length here. Following a lengthy and thorough

2
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 7 of 24

analysis of environmental impacts required by the National Environmental Policy

Act (NEPA), 42 U.S.C. 4321-4370m, FTA issued its ROD approving the

Purple Line Project on March 19, 2014. On August 16, 2014, an organization and

two individual plaintiffs sued the FTA, the U.S. Department of Transportation, and

two other federal agencies under NEPA the Migratory Bird Treaty Act, 16 U.S.C.

703712, the Endangered Species Act, 16 U.S.C. 1531-1544, and Section

4(f) of the Department of Transportation Act, 23 U.S.C. 138 and 49 U.S.C.

303. The State intervened to protect its substantial interests in the Project. Exhibit

4.

On August 3, 2016, the district court (1) granted partial summary judgment

to Appellees, finding that FTA had failed to take a hard look at new information

about Washington Metropolitan Area Transit Authoritys (WMATA) Metrorail

safety issues and ridership decline; (2) directed FTA to prepare an SEIS addressing

that single issue; and (3) vacated the ROD, which is a predicate to receiving the

Federal funding for the Project. Exhibits 1 and 2. Subsequently, in November

2016, the district court modified its order to allow FTA to determine first if an

SEIS was required. (Nov. 22 Order). Exhibit 5.

In December 2016, FTA filed its Determination (FTA Determination)

with the district court that no SEIS was needed. Exhibit 6. On May 22, 2017, the

district court rejected FTAs Determination based solely on its finding that FTA

3
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 8 of 24

had failed to consider three declarations submitted by Appellees to FTA. Exhibit

3. On May 30, 2017, the court issued a final judgment granting summary

judgment to Defendants on all issues raised by Plaintiffs except the single NEPA

SEIS issue decided in the May 22 Opinion. Exhibit 7. 1 The State filed its notice

of appeal that same day. On June 21, 2017, the State moved this Court to stay that

portion of the judgment that vacated the ROD pending appeal.

ARGUMENT

The State meets the requirements for expedited consideration of this appeal

under both 28 U.S.C. 1657(a) (mandating expedited review where good cause is

shown) and this Courts Local Rule 27. Good cause exists to expedite and action

if the delay will cause irreparable injury and . . . the decision under review is

subject to substantial challenge, or if the public generally, or persons not before

the Court, have any unusual interest in prompt disposition. U.S. Court of Appeals

for the D.C. Circuit, Handbook of Practice and Internal Procedures at 33 (Jan. 26,

2017). Here, good cause exists for an expedited appeal schedule given the

irreparable harm from the continued delay in resolving this litigation, the

significant errors in the district courts decisions, and the strong public interest in

1
On June 9, 2017, the court issued an opinion explaining its rationale for disposing
of the remaining issues in the case. Exhibit 8.

4
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 9 of 24

rapidly resolving a case that jeopardizes an important transportation project

designed to benefit many thousands of individuals and businesses.

1. Continued Delay is Causing Appellants Irreparable Injury

The Courts August 3 Order vacating the ROD has significant, immediate,

and potentially devastating consequences for the Project and for other non-Project

related transportation capital and maintenance projects planned by the State.

Declaration of Pete Rahn (Rahn Decl.) 56-78 (Exhibit 9). These harms easily

satisfy the irreparable harm standard.

For an injury to be irreparable, it must be both certain and great; it must

be actual and not theoretical. Wisc. Gas Co. v. FERC, 758 F.2d 669, 674 (D.C.

Cir. 1985); see also Winter v. NRDC, 555 U.S. 7, 22 (2008) (injury must be likely

to occur). Applying these standards, the State has and will continue to suffer

irreparable harm from the August 3 Order vacating the ROD.

The States injuries are both certain and great. Because the ROD remains

vacated, the federal funds anticipated for the Project have been delayed more than

nine months, already causing significant financial harm to the State. Exhibit 9,

66-71. That delay greatly increases the probability that the Project will need to

be abandoned to prevent further financial harm to the State. Even now, the cost to

the State of cancellation of the Project has grown to more than $800 million. Id.

74. This amount includes (1) funds expended to date in development of the

5
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 10 of 24

Project of approximately $545 million; (2) delay costs, which could reach

approximately $150 million for an estimated 12-month delay; and (3) termination

costs, which could reach approximately $200 million. Id. 2 These harms are real,

certain and substantial.

The harm to the State is not limited to the potential loss of over $800

million. The irreparable harm includes the tremendous loss to the tens of

thousands of workers, students, and other residents of the State who would use a

transit line connecting Montgomery and Prince Georges Counties, as well as the

lost and deferred jobs associated with the Projects construction. See Declaration

of Charles E. Lattuca (Exhibit 10) 45-49; 56-57. Cf. 42 U.S.C. 4370m-6(b)

(directing courts to consider potential negative effects on jobs when considering

whether to issue preliminary injunctive relief in cases under the National

Environmental Policy Act).

Moreover, the Project includes the replacement of eight bridges in the

Counties several of which are currently structurally deficient. Major

maintenance or replacement work by the Counties on these bridges was put on

hold pending implementation of the Project. One bridge was recently closed to

2
In anticipation of receiving the $325 million that Congress has already
appropriated for this Project, the State has expended that amount using State
taxpayer dollars to carry out ongoing and long lead-time pre-construction
activities, such as real property acquisitions, engineering and design, soil and
geotechnical analysis, utility relocations and community and small business
outreach and involvement. Exhibit 9, 33.

6
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 11 of 24

vehicular traffic, causing school buses and emergency vehicles to take longer

routes to reach their destinations. Exhibit 9 77. As of June 1, 2017, the State no

longer has sufficient funds to continue funding pre-construction activities and

began an orderly process of suspending Purple Line activities. Third Declaration

of Charles E. Lattuca (Exhibit 11) at 2.

In addition to the direct implications for the Project, because of the

expenditure of State funds on pre-construction activities that were expected to be

reimbursed by appropriate federal funds, a delay in obtaining federal funding for

this Project will also require the State to begin delaying or eliminating other

transportation projects from the States transportation plans to make up the

shortfall. Exhibit 9 at 78.

Appellees have incorrectly argued, and the district court wrongly concluded,

that these injuries may be ignored because they allegedly are self-inflicted. First,

courts routinely consider the financial and other harms that a project sponsor

would suffer from a delay in construction when deciding what relief to provide for

a Federal agencys NEPA violation. See, e.g., Montrose Parkway Alternatives

Coal. v. U.S. Army Corps of Engineers, 405 F. Supp. 2d 587, 600 (D. Md. 2005)

(rejecting plaintiffs self-inflicted theory); Sierra Club v. United States Army

Corps of Engineers, 990 F. Supp. 2d 9, 42-43 (D.D.C. 2013) (considering harm to

a developer that had committed major resources to the project). Courts have

7
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 12 of 24

held that the harm to a developer caused by delaying a project is to be considered

self-inflicted only in the limited context in which there is evidence of

wrongdoing. See Sierra Club, Inc. v. Bostick, 539 F. Appx 885, 892-95 (10th Cir.

2013) (distinguishing prior cases in the 10th Circuit in which the court had

disregarded harm as self-inflicted). There is no evidence or claim of wrongdoing

here. The State entered into a public-private partnership agreement (P3

Agreement) with the private partner on April 7, 2016, well after the ROD was

issued on March 14, 2014, in the absence of any request for preliminary injunctive

relief by Appellees, and before the district court vacated the ROD in August 2016.

Appellees self-inflicted harm rationale makes no sense, because the only way

for a project sponsor to avoid self-inflicted harm would be to self-enjoin once

a lawsuit challenging its project is filed, regardless of the merits of such a lawsuit.

The reality is that the harms suffered by the State and its citizens are

substantial, certain, and irreparable and cannot be ignored. The financial losses to

the State are not recoverable, and the continued delays in receiving federal funds

for the Project threatens its viability. Immediate attention to the appeal is essential

to minimize these irreparable harms.

8
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 13 of 24

2. The District Courts Opinions are Subject to Substantial


Challenge

The district courts opinions are subject to substantial challenge in at least

two respects. First, the court abused its discretion in vacating the ROD having

found no flaws in the ROD itself or in the underlying Final Environmental Impact

Statement. Second, the court failed to give the FTA Determination the level of

deference it deserved and erred in finding it to be arbitrary and capricious.

A. The District Court Abused Its Discretion in Failing to


Reconsider Its Order Vacating the Record of Decision.

The district courts August 3 Order vacated the ROD based on the finding

that FTA erred in its initial determination not to prepare an SEIS on the Metrorail

ridership issue. The court stated that vacating the ROD would only result in a

temporary halt in the project and that proceeding while an SEIS was prepared

might ultimately lead to more disruption if a different preferred alternative were

identified. Exhibit 2 at 9. The district courts November 22 Order rejected the

States request to reinstate the ROD. See Exhibit 5.

The FTA Determination satisfied the requirements of the remand by

considering the effect of scenarios comprising all possible impacts of a decline of

Metrorail ridership on the Project. The courts failure to address the States request

to reinstate the ROD, once the requirements of its remand had been met,

9
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 14 of 24

constitutes an abuse of discretion under the test established in Allied Signal v.

Nuclear Regulatory Commn, 988 F.2d 146 (D.C. Cir. 1993).

When the State and FTA filed their renewed motions for summary judgment

in December 2016 along with FTAs Determination, both again requested that the

district court reinstate the ROD. Exhibits 12 (State) and 13 (FTA). The State

provided a declaration explaining that the passage of time from the August 3 Order

had caused a change in circumstances that would result in severe financial harm to

the State and threatened the continued viability of the Project. See Second

Declaration of Charles Lattuca (Exhibit 12 at attachment 2). The State

demonstrated that it could be liable for significant delay and termination damages,

and that the Project and its benefits to the citizens of the State would be delayed or

lost if the ROD were not reinstated. Id. 12-14.

In its May 22 Opinion, the court again ignored the requests to reinstate the

ROD and the disruptions that could result from failing to do so. Exhibit 3.

Moreover, with its finding in the May 30 Final Judgment that the underlying Final

Environmental Impact Statement and ROD are valid (Exhibit 7 at 2), it is now

clear that vacating the ROD was not, and cannot be, based on any flaw in the ROD

itself. The courts refusal to reinstate the ROD operates as a de facto injunction

preventing the State from moving forward with the Project, having been issued

without considering the four-factor test governing injunctive relief under NEPA.

10
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 15 of 24

Monsanto v. Geertson Seed Farms, 561 U.S. 139, 157-58 (2010). Appellees have

never requested such relief.

B. The FTA Properly Determined That an SEIS Is Not


Needed.

In Marsh v. ONRC, 490 U.S. 360, 374 (1989), the Supreme Court held that

to require an SEIS every time new information comes to light would render

agency decision-making intractable, always awaiting updated information only to

find the new information outdated by the time a decision is made. In this Court,

an agencys obligation to prepare an SEIS depends on whether new circumstances

or new information create a seriously different picture of the environmental

landscape. Natl Comm. for the New River, Inc. v. FERC, 373 F.3d 1323, 1330

(D.C. Cir. 2004) (citing City of Olmsted Falls, OH v. FAA, 292 F.3d 261, 274

(D.C. Cir. 2002)) (emphasis in original).

Here, FTA fulfilled its obligation to take a hard look at the Metrorail

ridership and related maintenance and safety issues and properly concluded that

those issues did not create a seriously different picture of the environmental

landscape. FTA, in issuing its Determination, relied heavily on a detailed expert

report submitted by the Maryland Transit Administration (MTA), which

analyzed the impact on the Project of five different Metrorail ridership scenarios.

Exhibit 14 (MTA Report).

11
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 16 of 24

The MTA Report and FTA Determination confirm that, even in the most

extreme and highly unlikely scenario in which the number of Purple Line trips

involving transfers via Metrorail falls to zero, the projected 50,000 passengers

riding the Purple Line every day still justify going forward with the Project.

Exhibit 14 at 35 (MTA Report); Exhibit 6 at 4 (FTA Determination). They also

found that any reduction in Metrorail ridership would not alter the physical impacts

of the Project, which would have the same footprint regardless of the number of

riders using it. See e.g., Exhibit. 14 at 32-34; Exhibit 6 at 4. And the agencies

found that even the most drastic reduction in Metrorail ridership would not alter

the operational impacts of the Project in any material way, because the frequency

of service would not be reduced. Exhibit 14 at 34; Exhibit 6 at 5. Further, even if

the frequency of service were reduced, the environmental impacts from the Project

would be lower, not greater. Id.

The MTA Report was prepared and reviewed by FTA and MTA experts

with substantial knowledge and experience in forecasting ridership for public

transportation projects. An agency is entitled to rely upon the informed opinions

of its own experts when addressing highly technical issues, such as forecasting

ridership levels for transit projects. See Coalition on Sensible Transportation, Inc.

v. Dole, 826 F.2d 60, 66, 67 (D.C. Cir. 1987) ([T]echnical disputes of [this] sort

[are] most fit for expert administrative resolution and judicial deference); St.

12
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 17 of 24

Johns United Church of Christ v. FAA, 550 F.3d 1168, 1172 (D.C. Cir. 2008) (an

extreme degree of deference is due to the agencys determination involving

forecasts of passenger demands).

The district court, however, failed to afford the agencies reasoned and

expert determinations the level of deference they deserved. Although the district

court criticized the FTA Determination based on what it characterized as a

curious conclusion that the Project will meet the purpose and need as established

by FTA and MTA no matter what happens to Metrorail, it ignored FTAs

rationale for reaching that conclusion. Exhibit 3 at 8 (emphasis in original). The

FTA Determination specifically addresses how the Projects overall Purpose and

Need would be met even with no passengers transferring from Metrorail to the

Purple Line. While one element of the Purpose and Need for the Project would not

be met with respect to connections to Metrorail, the FTA determined that the

Metrorail element of Purpose and Need was irrelevant in that case to a

consideration of alternatives because no alternative would be capable of meeting

that element of Purpose and Need under that extreme and highly unlikely

scenario. Exhibit 6 at 7. 3 Moreover, the corresponding increases in roadway

3
The Purpose and Need is centered on providing more reliable ride between all
Metrorail stations and other transit services within the project corridor. The
Preferred Alternative will also improve connectivity to communities in the corridor
to better link people to employment and activities in the corridor and beyond.
ROD at AR1_000003 (Exhibit 15).

13
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 18 of 24

congestion [from the decline in Metrorail ridership] would amplify the extent to

which the project meets the other elements of Purpose and Need for the Purple

Line, making the Project still the best able to meet the overall Purpose and Need,

even under this highly unlikely scenario. Id.

The courts sole reason for rejecting FTAs Determination that FTA failed

to discuss[] or analy[ze] the three declarations Appellees submitted to the FTA

regarding the impact of Metrorail ridership declines on the viability of the Purple

Line is also erroneous. Exhibit 3 at 10. In reaching this decision, the court relied

on Public Employees for Environmental Responsibility (PEER) v. Hopper, 827

F.3d 1077 (D.C. Cir. 2016), a case that is inapposite both factually and legally. In

PEER, this Court determined that the U.S. Fish and Wildlife Service erred in not

considering information submitted by plaintiffs when the agency reconsidered a

decision under the Endangered Species Act, but that determination was based on

the conclusion that the agency itself had reopened the record on remand by

basing its decision on information supplied by the project developer, a private

entity. 827 F.3d at 1090.

Unlike the agency in PEER, FTA here considered Appellees submittal and

MTAs response to it. Exhibit 6 at 1. Appellees declarations asserted that an

earlier MTA assessment of the impact of Metrorail ridership declines was flawed

because it assumed that Metrorail ridership would recover and failed to consider a

14
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 19 of 24

more severe decline in Metrorail ridership. Appellees declarations claimed that

FTA needed to consider the impact of a continued decline in Metrorail, to a point

at which Metrorail itself was no longer a viable part of the transportation system in

the Washington metropolitan area. See Exhibit 16 at AR6_00303-05, 309-13, 325-

28. The MTA Report presents a scenario that analyzes that precise situation, and

FTA appropriately relied upon MTAs Report to support its Determination. See 23

C.F.R. 771.109(c)(5), 771.130(c).

Also, unlike in PEER, FTA did not reopen the record by using the MTA

Report, nor did it have any obligation to do so. FTAs regulations require the

applicant in this case MTA to develop appropriate environmental studies to

assess the impacts of the new information. 23 C.F.R. 771.130(c); see Exhibit 6

at 1 (citing this regulation as basis for asking for input from MTA). Although FTA

analyzed the concerns raised by the three declarations, it was not required to seek

or accept comments or analysis from anyone other than the applicant when

preparing a reevaluation under 23 C.F.R. 771.130(c).

Nor do Gerber v. Norton, 294 F.3d 173 (D.C. Cir. 2002) or Getty v. Federal

Savings and Loan Insurance Corp., 805 F.2d 1050 (D.C. Cir. 1986), also relied

upon by the district court, support its May 22 Opinion. Both cases address an

agencys failure to consider a factor specifically mandated to be considered by

statute. Here, the court never found, nor does the record show, that FTA failed to

15
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 20 of 24

consider a relevant factor. In fact, the FTA Determination assesses each of the

required factors to be considered when determining whether an SEIS is needed.

See 23 C.F.R. 771.130 (identifying factors to consider in evaluating whether to

prepare an SEIS); Exhibit 6 at 4-7.

3. The Public and Persons Not Before the Court Have an Unusual
Interest in Prompt Disposition.

The public has an unusual and exceedingly strong interest in prompt review.

Without prompt consideration of this matter, the public is at risk of losing the

many significant benefits from the project, including reliable and rapid east-west

travel, support for community revitalization and transit-oriented development, and

connecting thousands of people to jobs. 4 The State has conducted numerous

studies showing the overwhelming need for additional transit in the corridor. Both

Prince Georges and Montgomery Counties, in their amicus briefs (Exhibits 17 and

18), outline the depth of the two Counties support and need for this Project.

Indeed, both Counties have committed to providing substantial financial support to

the Project, and both are relying on the economic development that will result from

the Project. Further Congress has reviewed the Project and determined that it is

eligible for funding. To that end, it has appropriated $325 million to implement

4
See, e.g., https://www.transit.dot.gov/sites/fta.dot.gov/files/docs/funding/grant-
programs/capital-investments/60926/md-bethesda-new-carrollton-national-capital-
purple-line-fy-18-profile.pdf (describing benefits from project).

16
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 21 of 24

the project, in three separate appropriations. 5 The support for the Project from the

local level to Congress is strong and supports the need for prompt resolution of this

matter.

PROPOSED SCHEDULE

In light of the need for expedition in this appeal, Appellants proposed the

following briefing schedule: 6

Appellants Opening Brief: July 20, 2017

Briefs of any Amici in Support of Appellant July 27, 2017

Appellees Brief August 10, 2017

Briefs of Any Amici in Support of Appellees August 17, 2017

Appellants Reply Brief August 24, 2017

CONCLUSION

For the foregoing reasons and good cause shown, the State respectfully

requests that consideration of this matter be expedited, that the Court issue an order

5
See Exhibit 9 30. Congress appropriated $100 million for the Purple Line in
fiscal year 2015; an additional $100 million in fiscal year 2016; and an additional
$125 million in fiscal year 2017.
6
As required by Local Rule 27, the State has consulted with Appellees and the
other defendants regarding this motion. Appellees have indicated that they will
oppose this motion and do not agree with the proposed briefing schedule. The
United States Defendants, including FTA, have indicated that they do not oppose
this motion.

17
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 22 of 24

setting the above briefing schedule, and that the Court direct the Clerk to schedule

oral argument on the earliest available date following the completion of the

briefing.

Dated: July 3, 2017 Respectfully submitted,

BRIAN E. FROSH
Attorney General of Maryland

JULIE SWEENEY
Assistant Attorney General
Maryland Transit Administration
6 St. Paul Street, Suite 1200
Baltimore, MD 21202-1614
Telephone: 410.767.3844
Email: JSweeney@mta.maryland.gov

Eric D. Miller
Perkins Coie LLP
1201 Third Avenue, Suite 4900
Seattle, WA 98101-3099
Telephone: 206.359.3773
Facsimile: 206.359.4773
Email: emiller@perkinscoie.com

/s/ Albert M. Ferlo


ALBERT M. FERLO
Perkins Coie LLP
700 Thirteenth Street, N.W., Suite 600
Washington, D.C. 20005-3960
Telephone: 202.654.6200
Facsimile: 202.654.6211
Email: aferlo@perkinscoie.com

Attorneys for Appellant

18
136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 23 of 24

CERTIFICATE OF COMPLIANCE

I hereby certify that this brief complies with the type-volume limitation of

Rule 21(d)(i) of the Federal Rules of Appellate Procedure. As measured by the

word-processing system used to prepare this brief, the brief contains 4,007 words,

excluding the parts of the brief exempted by Fed. R. App. P. 32(a)(7)(B)(iii), and

complies with the type style requirements of Fed. R. App. P. 32(a)(6), because it

has been prepared in a 14 point proportionally spaced roman-style typeface (Times

New Roman).

/s/ Albert M. Ferlo


Albert M. Ferlo

136072497.4
USCA Case #17-5132 Document #1682460 Filed: 07/03/2017 Page 24 of 24

CERTIFICATE OF SERVICE
I hereby certify that on July 3, 2017, a copy of the foregoing document was

served via the CM/ECF system on all counsel of record.

Date: July 3, 2017 /s/ Albert M. Ferlo


Albert M. Ferlo

136072497.4

You might also like